Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
34Date Subject
18 January 2017 Open Session Infrastructure Services Report Omokoroa February 2017
$250,000 will also be directed to improving mobility crossings, local drainage and other local minor improvements in urban areas.
6.2 Omokoroa Road Construction - State Highway to Railway The offer of service for the full project works has been accepted by the Council. The project will be split and delivered in two phases; the first being Prole Road to the Railway required to accommodate development timings, the second phase from SH2 to the Prole Road will now likely be delivered in the following 2017/18 earthworks season. The telecommunications formal cost estimate has increased from $450,000 to $700,000 for the relocation of the existing services but this is still an estimate and may be reduced by cost sharing open trenches with other providers. The option to underground the existing power overhead lines has been accepted by the Council.
Site works have commenced with the removal of shelter trees, fencing and hedges. The bulk earthworks and the new watermain installation is being programmed. Surplus earthworks material is still providing challenges in minimising the cost to dispose it. The power service provider has advised a 12-week lead-time requirement based on their current workload and for materials supplies. Co-ordination between Westlink, Council, Council's designers, three sets of developers, their technical service providers, their utility providers and contractors is ongoing.
6.3 SH2 North - NZTA The Te Puna intersection construction has commenced with off-line water, drainage utility relocations and new access road alignment. The surfacing work is outstanding. The online roundabout earthworks and pavement works are expected to follow, after the main holiday period in early February and scheduled to be completed by June 2017.
6.4 Community Roading Omokoroa The construction of the walkway I cycleway route from Western Avenue to Hamurana Road is complete. The last item, a bridge over the stream is subject to a resource consent with the Regional Council, which is currently being processed.
6.5 Community Roading Account
Budget Funding Relevant Detail Information
Omokoroa Balance 30 June 2016 $129,256
Community Allocation for 2016/17 $92,700 Roading Balance Available for Allocation $221,956 Account
Approved Project Omokoroa to Tauranga Cycle Trail $100,000 Remaining Balance $121,956
A2821656
35ATTACHMENT A
Community Board Report OMOKOROA COMMUNITY BOARD 1/09/2015
Remit Title
Remit Number
Owner
Status
Complete Date
Confidential
Resolution
Actions
Walkway I Cycleway - Western Avenue Extension to Anderley Avenue
OM1515 4.3
TOM
COMPLETED
12 January 2016
It was brought to the Board's attention that the area at the end of Western Avenue Extension had been churned up by machinery and was now in a very boggy state. This would be reported to the Transport Operations Manager to ensure remediation was undertaken as soon as the area dried out and weather conditions allowed.
12 January 2017: Cycleway project complete with the exception of the bridge which has been delayed due to requirement for a BOPRC consent. The issue of the consent has been delayed due to resourcing issues at BOPRC.
11 November 2016: Cycleway project virtually complete with the exception of the bridge which has been delayed due to requirement for a BOPRC consent. The issue of the boggy area has therefore been addressed.
11 October 2016: Cycleway project virtually complete with the exception of the bridge which will be installed in October (delay in manufacturing).
36Date Subject
24 November 2016 Open Session Proposed Western Avenue Parking Bays
Western Bay of Plenty District Council
Omokoroa Community Board
Proposed Western Avenue Parking Bays
Purpose and Summary
For the Board to consider allocating community reading funds for the construction of parking bays on Western Avenue adjacent to the Skate Path.
Funding Implications for Omokoroa Community Board
Funding is available in the Omokoroa Community Reading account to cover the estimated $60,000 for this project.
Delegated Authority of Omokoroa Community Board or To Make Submissions/Recommendations to Co unci 1/ Committees
The Board has delegated authority to authorise expenditure from the Omokoroa Community Reading Account to fund this project.
Recommendation
1. THAT the Deputy Chief Executive's report dated 24 November 2016 and titled "Proposed Western Avenue Parking Bays" be received.
2. THAT the report relates to an issue that is considered to be of low significance in terms of Council's Significance and Engagement Policy.
3. THAT the installation of sealed parking bays on Western Avenue proceed at an estimated cost of $60,000 funded from the Omokoroa Community Roading account.
~~ ......................... ···················-~·········· ·······"·~ ·············--······-···-···-··- ··········································-·····--··-··········-Gary Allis Deputy Chief Executive
A2798609 Page 1
37Date Subject
24 November 2016 Open Session Proposed Western Avenue Parking Bays
1. Background
The success of the Western Avenue Skate Path has increased the requirement for additional parking for the area.
Currently, some users are parking on the grass and consequently creating a boggy area during wet periods. There is also uncertainty amongst users as to whether they are allowed to park on the grass. Attachment A
There are also traffic safety concerns about parking on Omokoroa Road adjacent to the Skate Path.
Installation of formed parking bays on Western Avenue will formalise the parking, reduce the boggy areas and provide an alternative to parking on Omokoroa Road.
There are three surfacing options for the parking bays shown on the plan.
Option 1: Option 2: Option 3:
Chip Seal Surface $60,000 Gobi Blocks & grass $76,000 Turf Cell and grass $69,000
The staff recommendation is for a chip seal surface.
2. Statutory Compliance
The recommendation meets:
• Legislative requirements/legal requirements • Current council plans/policies/bylaws • Regional/national policies/plans.
3. Funding/ Budget Implications
Attachment B
Estimated $60,000 Proposed Western Avenue Parking Bays
Budget Funding Relevant Detail Information
Omokoroa Balance 30 June 2016 ~129,256
Community Allocation for 2016/17 $92,700
Roading Account Balance Available for Allocation $221,956
Approved Project Omokoroa to Tauranga Cycle Trail (~100£0002 Remaining Balance $121,956
A2798609 Page 2
38Date Subject
24 November 2016 Proposed Western Avenue Parking Bays
4. Consultation and Communication
Interested/ Affected Completed/Planned Parties Consultation/ Communication
Name of interested Adjacent property owners: letter drop parties (if req.)
Tangata Whenua In accordance with Council protocol.
A2798609
Open Session
Notes
Page 3
39ATTACHMENT A
A2828632
40
I
l
E~g• ol ~
[a,eo! Yo•c
EGlND
\.O<lQI flc,uoGO<y ---
~fSh<·•<'B<I~
Opt~ ~·0·0
o,.., c~e, c•
C"""eo<j<OI"D
5e o<< ... 0•' - ·• - ·· -5tO<m WOI,. - ·--
Cut\-ert 0 0
S..<""YII<"""'""'" RetO"'•'Iij WO
=
~ NEW CAR PARK ~ SEE OPTIONS SHT.2
~ SEAL WIDENING ~ 2 COATGRAOE 315CHI
NOTES
INSTALL MANHOLE WITH LID OVER EXISTING 4500 STORMWATER PIPE
15.0 PARKING BAY
1. The locatton of services IS indicative only. The Contractor shall verify the location of servtces on s~e pnor to construction and identify any services that may need to be relocated to enable works to proceed.
~~g :;l""b I ! I ! I ~~ I ~~ I k I }4 I m
0<1'1Ar7987861 Pl0109te 201&. 1 1-17al~ ~l5 p m PalhG\!vqoo;l\2-glWBOM WO$lelnAvePart"'giA<:.:Ac....-~WestlniA"tt c.I'8A·ORAfT 1 1 IXQl[MogCill
Wortem Bay of Plenty Dlrtr/ct Council
-~'~o~.s •&17~782089
ATTACHMENT B
BOUNDARY LINE
DRAWING IN PROGRESS PLOTTED ON 2016-11-17 AT 4 48 p m
PRELI MINA RY
WESTERN BAY OF PLENTY DISTRICT COUNCIL WESTERN AVENUE CAR PARKING BA YS
I ""''""" I PRELIMINARY DRAWINGS 1 j GENERAL LAYOUT PLAN -'..an O!Ir'>'l~
" vande"VIugl 2-9 1WB0-88 COl
41
~
1
I
I
ATTACHMENT B
300 t 125 1~· 150 t KERB FACE LINE (SEE DETAIL) 5.1 PARKING BAY
INSTALLNEWDISH CHANNEL A CENTERED AROUND EXISTI NG
~I I (SEEPAVEMENTOP.T IONSBELO:STRUCTKERB&FOO~""' L EX.-LISTINGGROUNOLEVEL
EXJSTINGROMJWAY \ 200mm SEAl 200mm ~ (SEE DETAIL) MAX.STOl --OVERLAP CUT IN ~ -"-f--r "'- - !%.(Milt) ID6%(MAX.)Sl0PE
4 j
"'
150mm TNZ M/4 BASECOURSE
150mm SUBBASE (GAP65 SPEC.)
150mm. GAP40 BASECOURSE 150mm GAP65 SUBBASE
SUBSOIL DRAIN (SEE DETAIL)
2COAT315CHIPSEAL
NOTE. STRIP TOPSOIL TO 150mm SUPPLY SUITABLE FILL TO BE APPROVED BY ENGINEER SUBGRADE MIN. CBR 4
OPTION 1: PAVEMENT DETAIL- TWO COAT CHIP SEAL
NOTE
BC)nm GRASS PAVER (FIRTH) ON TOP OF A 20mm BEDDING SAND ON TOP OF GEOTEXTILE FILTER CLOTH (ClASS D)
i i j i If II tJ I I I I I If I I I I I I I I I I I I I I I I I I I I I !I I JJ I
STRIP TOPSOIL TO 150mm SUPPLY SUITABLE FILL TO BE APPROVED BY ENGINEER SUBGRADE MIN CBR 4
~m. WAP12 DRAINAGE BASECOURSE
Subgrade MIN CBR 4
OPTION 2: PAVEMENT DETAIL- GOBI BLOCKS (GRASS PAVERS
25mm AP7 OR SAND
250mm. GAP40 SUBBASE
BACKFILL JACKMAT GEOCELL V'JITH GRAVEL
GEOTEXTILE FABRIC NOTE STRIP TOPSOIL TO 150mm SUPPLY SUITABLE FILL TO BE APPROVED BY ENGINEER SUBGRADE MIN. CBR 4
OPTION 3: PAVEMENT DETAIL- TURF CELL (JACKMAT GEOCELL OR SIMILAR)
~~: :;1'1"6 I ~ I ~ 112 I 1~ I .Jo I 214 )m
TYPICAL CROSS SECTION SCALE 1 :500(A3)
-~rlll$1m!S<leA118ol1>5941 f'1o1Dil ll! 20 TS-11-17&1 ~ca 39pm I'II~ G\~~112-!IIWSO &e WeslemA~~ngV.:~~WestErn.Ave C.Pa-lc -DRAFT 110099dlogC02
r EXISTING 4500 d ,_,, __
1-Kerbh 't 300 .:,00 r
~ =t
DISH CHANNEL DETAIL
W•rtern Bay of Plenty D/rlrfcl Council
.... ,
-~"~!;!,S •&17578al89
·~ 50mm nomlMI-.'-~'-~'-~ com......, le'tollhgoou:rse
KERB & FOOTING DETAIL
SUBSOIL DETAIL
t<!
~ 50rNn nominal- · ,_.., ~ Mlrngoourw
==~~n l.t~·: .. · , :~·-~,~;n drilwfog rordetalls
la!.fll"9131ol0
KERB & CHANNEL DETAIL
DRAWING IN PROGRESS PLOTTED ON 2016-11-17 AT 448 p m
PRELIMINARY
WESTERN BAY OF PLENTY DISTRICT COUNCIL WESTERN AVENUE CAR PARKING BAYS
~ , - ... ,,._ ~ PRELIMINARY DRAWINGS ;;o TYPICAL CROSS SECTION & DETAILS Allllnllef~ll!ll
A.Yan <WIJI~! 2-91W80-88 C02
A2798786
42ATTACHMENT B
Western Bay of Plenty District Council Western Ave, Car Park Omokoroa
Option 1: 2 Coat Chip seal
Item Description Unit Quantity Rate Amount
1.0 General
1.1 Establish LS 1 $ 1,956.00 $ 1,956.00
1.2 Disestablish LS 1 $ 1,848.00 $ 1,848.00
1.3 QA, H&S, TM , PM LS 1 $ 6,139.32 $ 6,139.32
1.4 Survey Set out LS 1 $ 720.00 $ 720.00
2.0 Earthworks
2.1 Strip Topsoil to Waste (up to 150mm depth) m2 240 $ 16.97 $ 4,072.32
2.2 Strip topsoil to stockpile, respread and grass (edge of kerb) m3 10 $ 32.40 $ 324.00
2.3 Cut to waste m3 40 $ 65.64 $ 2,625.60
2.4 Cut to Fill suitable material m3 5 $ 33.18 $ 165.90
3.0 Pavement
3.1 Supply and Install GAP65 Subbase (150mm) (incl. for beneath kerb) m3 45 $ 121 .27 $ 5,457.24
3.2 Supply and Install GAP40 Basecourse (150mm) m3 40 $ 125.1 0 $ 5,004.00
4.0 Drainage
4.1 Supply and construct kerb and channel m 14 $ 108.54 $ 1,519.56
4.2 Supply and construct kerb & footing m 68 $ 92.12 $ 6,264.43
4.3 Supply and construct concrete dish channel m 38 $ 128.53 $ 4,884.22
4.4 Supply and install subsoil drain beneath dish channel m 50 $ 61.45 $ 3,072.60
4.5 Supply and install Class 4, 225mm dia lead pipe with HS2 beddinq m 6 $ 275.60 $ 1,653.62
4.6 Supply and install Manhole 1 050Dia. LS 1 $ 2,672.78 $ 2,672.78
4.7 Supply and install new catchpit LS 1 $ 1,455.00 $ 1,455.00
5.0 Surfacing
5.1 Supply and construct two coat coat chip seal m2 250 $ 8.70 $ 2,1 75.00
6.0 Miscellaneous
6.2 Relocate existing sign ea 1 $ 300.00 $ 300.00
MEASURE AND VALUE SCHEDULE OF QUANTITIES PHYSICAL WORKS TOTAL $ 52,309.60
Physical Works $ 52,309.60
Westlink Proffessinal Services
Design including , Arch checks. LS 1 $ 4,830.00 $ 4,830.00
Westlink Supervision and Management % 5.0% $ 52,309.60 $ 2,615.48
TOTAL $ 59,755.08
A2798786
43ATTACHMENT B
Western Bay of Plenty District Council Western Ave , Car Park Omokoroa
Option 2: Grass Pavers
Item Description Unit Quantity Rate Amount
1.0 General
1.1 Establish LS 1 $ 1,956.00 $ 1,956.00
1.2 Disestablish LS 1 $ 1,848.00 $ 1,848.00
1.3 QA, H&S, TM, PM LS 1 $ 6,139.32 $ 6, 139.32
1.4 Survey Set out LS 1 $ 720.00 $ 720.00
2.0 Earthworks
2.1 Strip Topsoil to Waste (up to 150mm depth) m2 240 $ 16.97 $ 4,072.32
2.2 Strip topsoil to stockpile, respread and grass (edge of kerb) m' 10 $ 32.40 $ 324.00
2.3 Cut to waste m' 40 $ 65.64 $ 2,625.60
2.4 Cut to Fill suitable material m' 5 $ 33.18 $ 165.90
3.0 Pavement
3.1 Supply and Install GAP65 Subbase (150mm) (seal widening area+kerbs) m3 15 $ 122.03 $ 1,830.42 Supply and Install GAP40 Basecourse (seal widening area + car
10 $ 125.78 $ 1,257.84 3.2 park+kerbs) m3 Supply and install Grass Pavers (includes bedding , geotextile ,
190 $ 127.90 $ 24,300.24 3.3 basecourse, topsoil respread and grass) m2
4.0 Drainage
4.1 Supply and construct kerb and channel m 14 $ 108.54 $ 1,519.56
4.2 Supply and construct kerb & footing m 68 $ 92.12 $ 6,264.43
4.3 Supply and construct concrete dish channe l m 38 $ 128.53 $ 4,884.22
4.4 Supply and install subsoil drain beneath dish channel m 50 $ 61.45 $ 3,072.60
4.5 Supply and install Class 4, 225mm dia lead pipe with HS2 bedding m 6 $ 275.60 $ 1,653.62
4.6 Supply and install Manhole 1 050Dia. LS 1 $ 2,672.78 $ 2,672.78
4.7 Supply and install new catchpit LS 1 $ 1,455.00 $ 1,455.00
5.0 Surfacing
5.1 Supply and construct two coat coat chip seal m2 60 $ 8.70 $ 522.00
6.0 Miscellaneous
6.2 Relocate existing sign ea 1 $ 300.00 $ 300.00
MEASURE AND VALUE SCHEDULE OF QUANTITIES PHYSICAL WORKS TOTAL $ 67,583.86
Physical Works $ 67,583.86
Westlink Proffessinal Services
Design including , Arch checks. LS 1 $ 4,830.00 $ 4,830.00
Westlink Supervision and Management % 5.0% $ 67,583.86 $ 3,379.19
TOTAL $ 75,793.05
A2798786
44ATTACHMENT B
Western Bay of Plenty District Council Western Ave, Car Park Omokoroa
Option 3: Turf Ce ll (Jackmat Geocell or similar)
Item Description Unit Quantity Rate Amount
1.0 General
1.1 Establish LS 1 $ 1,956.00 $ 1,956.00 1.2 Disestablish LS 1 $ 1,848.00 $ 1,848.00
1.3 QA, H&S, TM , PM LS 1 $ 6,139.32 $ 6,139.32
1.4 Survey Set out LS 1 $ 720.00 $ 720.00
2.0 Earthworks
2.1 Strip Topsoil to Waste (up to 300mm depth) m2 240 $ 16.97 $ 4,072.32
2.2 Strip topsoil to stockpile, respread and grass (edge of kerb) mJ 10 $ 32.40 $ 324.00
2.3 Cut to waste mJ 40 $ 65.64 $ 2,625.60
2.4 Cut to Fill suitable material mJ 5 $ 33 .18 $ 165.90
3.0 Pavement
3.1 Supply and Install GAP65 Subbase (150mm) (seal widening area) m3 15 $ 122.03 $ 1,830.42
3.2 Supply and Install GAP40 Basecourse (150mm) (seal widening area) m3 10 $ 125.78 $ 1,257.84 Supply and install Turf Cell (includes bedding , geotextile , subbase , (7·
190 $ 91 .80 $ 17,442.00 3.3 1 Omm) pea aggregate to fill the cells) m2
4.0 Drainage
4.1 Supply and construct kerb and channel m 14 $ 108.54 $ 1,519.56
4.2 Supply and construct kerb & looting m 68 $ 92.12 $ 6,264.43
4.3 Supply and construct concrete dish channel m 38 $ 128.53 $ 4,884.22
4.4 Supply and install subsoil drain beneath dish channel , kerb & channel m 50 $ 61.45 $ 3,072.60
4.5 Supply and install Class 4, 225mm dia lead pipe with HS2 bedding m 6 $ 275.60 $ 1,653.62
4.6 Supply and install Manhole 1 050Dia. LS 1 $ 2,672.78 $ 2,672.78
4.7 Supply and install new catch pit LS 1 $ 1,455.00 $ 1,455.00
5.0 Surfacing
5.1 Supply and construct two coat coat chip seal m2 60 $ 8.70 $ 522.00
6.0 Miscellaneous
6.2 Relocate existing sign ea 1 $ 300.00 $ 300.00
MEASURE AND VALUE SCHEDULE OF QUANTITIES PHYSICAL WORKS TOTAL $ 60,725.62
Physical Works $ 60,725.62
Westlink Proffessinal Services
Design including , Arch checks. LS 1 $ 4,830.00 $ 4,830.00
Westlink Supervision and Management % 5.0% $ 60,725.62 $ 3,036.28
TOTAL $ 68,591.90
A2798786
45Date Subject
16 January 2017 Open Session Financial Report Omokoroa - December 2016
Western Bay of Plenty District Council
Omokoroa Community Board
Financial Report Omokoroa - December 2016
Purpose and Summary
This report provides the Community Board with a six-weekly monitoring of its operational budget.
Attached are the financial statements for the period up to 31 December 2016 (Attachment A) .
Total operational costs are lower than budget and include conference expenses, contingency, grants, mileage allowances, salaries and inter-department charges.
Grant payments made to date:
$ Night Owls Cinema [OM22.7.1] $(1,150) CYBER Link Omokoroa [OM21.3.2] $( 423) Total grants to date $(1,573)
Committed - Operational expenditure
$ Total committed - o erational ex enditure Nil
2016/ 17 reserve analysis:
2016/17 Opening Balance $330,353 No postings to date. Nil 2016/17 Closing Balance $330,353
A2825590 Page 1
46Date Subject
16 January 2017 Financial Report Omokoroa - December 2016
Committed - Reserve expenditure
Funding for the proposed Tinopai Reserve to Lynley Park Walkway [OM1.9]. Contribution towards the cost of the new sports pavilion on the Western Avenue sports ground [OM9.4.2]. Contribute towards the skate path facility within the Western Avenue Sports Ground [OM8.6.2]. 2016/17 Closing Balance after committed expenditure
Recommendation
Open Session
$(60,000)
$(100,000)
Up to $(10,000)
$160,353
THAT the Financial Accountant's report dated 16 January 2017 and titled "Financial Report Omokoroa -December 2016" be received.
-~ ---Dion McCall Financial Accountant
Approved Matt Potton Chief Financial Officer
A2825590 Page 2
47 ATTACHMENT[] Western Bay of Plenty District Council Income and Expenditure Statement
For the period ended 31 December 2016
Omokoroa Communtty Board Year to Date Full Year Last Year
Variance Actual Budget (Unfav)/Fav Budget Actual
$ $ $ $ $ Direct Costs
Conference Expenses 0 0 0 0 1,000 0
Contingency - [see breakdown below] 80 500 420 0 5,000 1,675
Grants 1,573 2,000 427 0 5,000 2,565
Mileage Allowance 498 706 208 0 2,000 751
Salaries 10,207 12,435 2,228 0 24,694 18,002
Inter Department Charges 16,242 16,242 0 0 32,480 32,484
Total Operating Costs 28,599 31,883 3,284 0 70,174 55,477
Interest Expense 0 0 0 0 (6,000) (17,006)
Total Direct Costs 28,599 31,883 3,284 0 64,174 38,472
Costs Allocated 0 0 0 0 0 0
Total Costs 28,599 31,883 3,284 0 64,174 38,472
Income Rate I ncome 37,319 35,088 2,231 0 70,174 59,626
Total Direct Income 37,319 35,088 2,231 0 70,174 59,626
Net Cost of Service 8,719 3,205 5,514 0 6,000 21,154
Contingency - breakdown
Omokoroa Settlers Hall - Meeting 80
Year to date contingency costs 80
Communitv Board Reserves Opening Balance - Surplus (Deficit) 330,353
(Decrease) Increase in year 0
Closing Balance- Surplus (Deficit) 330,353
48
Meeting
Western Bay of Plenty District Council Formal Meeting Schedule 2017
FEBRUARY 2017
Date Time
Community Committee 2 February 9.30am
Venue
Chambers
Waitangi Day- Monday 6 February 2017
Policy Committee 9 February 9.30am Chambers
Operations and Monitoring 14 February 9.30am Chambers Committee
Rural Committee 14 February TBC TBC
Te Maru o Kaituna River Authority 16 February 10.30 am BOPRC Tauranga
Public Transport Subcommittee 17 February 9.30 am BOPRC Whakatane
Joint Road Safety Committee 21 February 10.00 am Chambers
Council 23 February 9.30am Chambers
Bay of Plenty Mayors I Civil 24 February 12.30 pm Rotorua Lakes Council Defence Emergency Management Group Joint Committee (CDEMG)
Regulatory Hearings Committee 28 February 9.30am Chambers
MARCH 2017
Regulatory Hearings Committee 1 March 9.30 am Chambers
(If required)
Waihi Beach Community Board 13 March 6.30 pm Waihi Beach Community Centre
Omokoroa Community Board 14 March 7.00 pm Omokoroa Community Church Hall
Katikati Community Board 15 March 7.00 pm Katikati Library and Service Centre
Community Committee 16 March 10.00 am TBC
Maketu Community Board 21 March 7.00 pm Maketu Community Centre
Te Puke Community Board 23 March 7.00 pm Te Puke Library and Service Centre
Operations and Monitoring 28 March 9.30 am Chambers Committee
2017 Meeting Schedule
49
MARCH 2017 continued
Meeting Date Time Venue
Rural Committee 28 March TBC TBC
District Plan Committee 29 March 9.30am Chambers
District Plan Committee 30 March 9.30 am Chambers
(If required)
Regional Transport Committee 30 March 9.30 am Waikato Regional Council, Hamilton East