66
WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project Manager: Trevor Jahn Assistant Project Manager: Michael Young

WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

Embed Size (px)

Citation preview

Page 1: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

WELCOME TO CRITICAL DESIGN REVIEW

PROJECT LEGACY Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 2: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

PROJECT OVERVIEW

Photo Credit: (NASA, 2016) https://www.nasa.gov/content/journey-to-mars-overview

Lunar Base • 8 astronauts • Missions spanning

2 years • Investigate the

effects of long term crew mission

• Science Objectives • Technology

Readiness Levels (TRL)

• 2035 Crew to Mars Cycler Rendezvous

Page 3: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

PROJECT LEGACY Solution

• 9 habs (Radiation Shielding)

• 2 autonomous/crewed rovers

• In-Situ Resource Utilization (ISRU)

• Fuel Depot

• 4 Science Probes

• 3 Science Rovers (Range of +1200 km)

• +3 Nuclear Reactors

• JPL’s ATHLETE and JVA

1

2 3

4 5

6

Page 4: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

PROJECT LEGACY Solution

• 1 Impact vehicle

• 1 Ferrying Lander for crew of 8

• XM2 Space Habitat

• 3 Com Sats (24/7 HD coverage)

Page 5: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

MISSION ARCHITECTURE Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 6: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

MISSION ARCHITECTURE

Washington Series (2021-2023, 4 missions)

Aka Testing and XM2 Phase

• Raising TRL of power/orbiters/science objectives

• XM2 Delivered to CLO

• Moon Impact Mission for habitat foundation

Adams Series (2023-2029, 12 missions)

Aka First Construction Phase

• Deliver crew to orbiter for shakedown

• Validate life-support systems, resources

• Landing first five habs, ISRU equipment, consumables, rovers

• Crew construction mission 1

Jefferson Series (2029-2031, 5 missions)

Aka Second Construction Phase

• Remaining four habs

• Crew construction mission 2

TIMELINE, MISSION COUNT

Madison Series (2032-2035, 11 missions)

Aka Crew and Resupply

• Personal items, consumables deliveries

• Crew delivery and rotation via Orion

capsule

Monroe Series (2035+)

• Crew to cycler rendezvous

• Crew rotation

Page 7: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

WASHINGTON SERIES

2018-2020, 4 MISSIONS

Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 8: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2018-2020 WASHINGTON 1-4

Washington (2018-2020, 4 missions)

• 2018 Mission 1: XM2

• 2019 Mission 2: Moon Impactor Mission Launch

• 2019 Mission 3: Orion Docking Mechanism, 3 Com Sats, Nuclear

Reactor Test 1 (TRL 7 – 8)

• 2020 Mission 4: Lander, 3 Science Rovers, Nuclear Reactor Test 2 (TRL

8 – 9), 4 Science Probes

Page 9: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2018 WASHINGTON 2: MOON IMPACTOR MISSION LAUNCH

Excavated Mass 5202 [Mg]

Excavated Volume

Mass of Impactors 2.925 [Mg]

Volume of Impactors

Dr. Aldrin’s habitat layout

Required Mass [Mg]

Required Volume

Crater Model

Page 10: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2019 WASHINGTON 3: XM2

10 Amit Soni

Purpose: A go between from Earth

and the Moon Base

Dimensions based on BA330

• Deployed Volume: ~338 m3

• Deployed Mass: TBD

• Power: TBD

Page 11: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

Requirement: 24-hour HD video communication with crew throughout mission

Communication Satellite Specifications:

• Number of satellites: 3

• Orbit altitude: 1,200 km

• Period: 4 hours

• Inclination: 88 degrees (polar orbit)

• Relays data from Earth to Moon or from Moon to Earth

Control Characteristics: - 3 axis stabilization - Using 3 reaction wheels - Desaturate about once every half year - Thrusters are used for small

maneuver changes

2019 WASHINGTON 3: COM SATS

Page 12: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2020 WASHINGTON 4: CARGO LANDER - For the 20 Mg lander, the total DeltaV to land from our 4500 km orbiting radius will be 2.5

km/s.

- Both landers are powered by 1 Aerojet Rocketdyne RL10B-2 Engine.

- 20 Mg Lander is 10.5 meters tall 7 meters wide at the top and 14 meters wide at the struts

Variant LHy Vol. (m3)

LHy Mass (Mg)

LOx. Vol. (m3)

LOx. Mass (Mg)

5 Mg 8.31 0.589 3.03 3.465

20 Mg 33.29 2.357 12.15 13.860

Hab and Lander in SLS Fairing

Cargo Lander with Extended Struts

Page 13: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2020 WASHINGTON 4: SCIENCE TRACEABILITY MATRIX

Science Objective Justification Measurement Objective

Measurement Requirement

Instrument Selected

Constrain Bulk Composition of

the Moon

Constrain age of SPA and Late

Heavy Bombardment (LHB) theory

Sample return from SPA to

analyze mineralogy and

volatile distributions

Age SPA melt sheet within 20 My ppb level –

measure high FeO areas

Drill, Sample, NSS, SuperCam, hand

lens

Example of one row from the STM. Full STM encompasses 3 goals.

The South Pole-Aitken Basin (SPA) has high Iron Oxide levels (yellow) that we want to sample.

SPA Basin

Page 14: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2020 WASHINGTON 4: TRAVERSE MAP FOR SCIENCE ROVER

CABEUS CRATER TO SCHRÖDINGER BASIN = ~600 KM. TOTAL TRAVEL DISTANCE ~1200 KM

Page 15: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2020 WASHINGTON 4: SCIENCE PROBES

4 science probes sent to lunar surface for condition assessment

1 Launch from LEO to CLO using Falcon heavy

15

Science Instruments and Objectives: ● Determine inner structure of Moon ● Measure global heat flow ● Examine Moon’s magnetic field ● Seismic activity

Science Probe Overview:

Mass (kg) 149.6

Power (W) 157.6

Volume (m^3) 0.783

*Totals for one probe

Page 16: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2020 WASHINGTON 4: SCIENCE PROBES

16

ACS Requirements: • Accommodate Precision Landing • Efficient use of fuel

ACS: • Use variable thrust main engines • Use Control Moment Gyroscope

(CMG) system Overall Propulsion System: Aerojet Rocketdyne R-6D (x3)

Mass (kg) Volume (m^3)

Propulsion 89.54 0.069

Total 149.6 0.783

* for one probe

Page 17: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

ADAMS SERIES

2021-2024, 10 MISSIONS

Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 18: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2020-2025 ADAMS 1 – 12 Adams Series (2020-2025, 10 missions)

• 2020 Mission 1: Crew of 2 to XM2 (1 week duration), docking test, and return to Earth

• 2023 Mission 2: Modular Rover / Attachments, 3 reactors, and ATHLETE

• 2023 Mission 3: Hab 1L (Living, Hab 1)

• 2023 Mission 4: Hab 2L (Living, Hab 2)

• 2023 Mission 5: Hab 3R (Rec center, Hab 3)

• 2024 Mission 6: Hab 4R (Rec center, Hab 4)

• 2024 Mission 7: Hab 5W (Wast/Water, Hab 5)

• 2024 Mission 8: Ferrying Lander to Lunar Surface

• 2024 Mission 9: ISRU, 3 Reactors

• 2024 Mission 10: Fuel Depot

• 2024 Mission 11: Ferrying Lander to XM2

• 2025 Mission 12: Crew of 2 to XM2, and 2 Crew to Surface (1 week): test systems

Page 19: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

LUNAR SURFACE LOCATIONS

Objective: Determine locations for Power

Structure Components

Reasoning: Navigational understanding and

General distance of separation

14.3 Km

Page 20: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

ADAMS 2: NUCLEAR POWER SYSTEM

Reactor Electric Power (kWe) Thermal Power (kWt) Mass (Mg)

SAFE-400 100 400 0.541

Lifespan of 5-7 years Raising the TRL of the reactor • Washington-1 in 2018 will raise the TRL from

a 7 to an 8 • Washington-3 in 2019 will raise the TRL from

an 8 to a 9 Replacement missions every 5 years

SAFE 400 Nuclear Reactor

SAFE 400 Nuclear Reactor Interior

Page 21: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2023 ADAMS 2: UNIFIED ROVER SYSTEM Operation Parameter

Value

Max Speed 30 [kph]

Cross country Speed

20 [kph]

Range 200 [km]

Carrying Capacity

3.5 [Mg]

Science Bay: Volume: 17.08 [m3] Mass: 0.912 [Mg]

Fluid Storage Module: Volume: 3.80 [m3] Mass: 0.709 [Mg]

Rover Arms: Volume: 8.9x10-3 [m3] Mass: 0.021 [Mg/arm]

Page 22: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

Scoop: Volume: 0.66 [m3] Mass: 1.987 [Mg/arm] Volume: 0.66 [m3]

2023 ADAMS 2: UNIFIED ROVER SYSTEM

Universal Pallets

JVA Bed

Page 23: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

RADIATION SHIELDING

Fig.1: Habitat Radiation Mitigation Design. Cross section and top down views.

lower Inter-hab connector

Lunar ground

level Water Tank

Reg. bags

ground

storage

GCR SCR

Page 24: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

RADIATION

Radiation Type Unmitigated Dose Dose after Mitigation

Top Sides

Galactic Cosmic Rays 0.75-1.0 Sv 0.0255 Sv 0.031 Sv

Solar Cosmic Rays 80-300 Sv 0.330 mSv 0.271 mSv

Total 81 – 301 Sv 0.0565 Sv

Table 2: Habitat radiation dosage. Comparison of the unmitigated and mitigated dosage from the most harmful sources of radiation (over 2 years).

Mass: 11,200 Mg Regolith, 8 Mg bags, 22440 kg of water necessary Volume: 7,450 m3 Total Dose: 0.0565 Sv over 2 years

2 major sources of radiation on the moon:

• Galactic Cosmic Rays [1 Sv]

• Solar Proton Events [~150 Sv]

Page 25: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

Leveraging current technology of

JPL’s ATHLETE (All Terrain Hex-

Limbed Extra-Terrestrial Explorer)

and modifying to fit requirements.

Linking Points

Cargo Lifting Wheels

2023 ADAMS 2: NASA’S ATHLETE

Page 26: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2021 – 2023 ADAMS 3 – 7: HABS 1 – 5

Hab 3R (Rec Center, Hab 3) Wally ball/Multipurpose Court

Hab 4R (Rec Center, Hab 4) Exercise Equipment

Hab 1L (Living, Hab 1) Residential Areas

Hab 2L (Living, Hab 2) Residential Areas

Hab 5W (Waste/Water, Hab 5) Exercise Equipment

Page 27: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2024 ADAMS 8: ISRU SYSTEM

27

COMPONENT BOILING POINT 1 ATM [C]

H2O (Water) 100

CH3OH (Methanol) 66

OH (Hydroxide) 35

SO2 (Sulfur Dioxide) -10

NH3 (Amonia) -33.34

H2S (Hydrogen Sulfide) -60

CO2 (Carbon Dioxide) Boils at 5.2 atm and -78.5

C2H4 (Ethylene) -103.7

CH4 (Methane) -161.5

• Heats up regolith to sublimate out “ice material” • Cool gases to slowly separate components into

liquids • Expels waste regolith and “ice material” out of

the system • Holds important materials (CO2, CH4, H2O) to be

picked up by the fuel rover

Regolith tank

Mixture gas tank

CO2 tank H2O tank CH4 tank

Microwave

Vent lines

Vacuum pump

Solenoid valves

Page 28: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

LCH4 Tank

LOX Tank

Reactants Tank GCH4

Tank

GCO2

Tank

LH2O Tank

1

2

3

4 5

6

- Heat Exchanger MLI Outer Shield

2024 ADAMS 9: FUEL DEPOT

Tube # Service

1 Liquid Water to LOX Tank

2 Gaseous Hydrogen to RT

3 Liquid Water to LH20 Tank

4 Gaseous Carbon Dioxide to Reactants Tank

5 Gaseous Methane to GCH4 Tank

6 Gaseous Methane to LCH4 Tank

Austin Black

Fuel Depot • Location: Partially shadowed region • Function: generates fuel/ox for reusable lander • Mass: 18.4 Mg (dry) • Power: 176.86 watts • Volume: 258 m^3

Page 29: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

JEFFERSON SERIES

2024-2028, 5 MISSIONS

Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 30: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2024-2028 JEFFERSON 1-5

Jefferson Series (2025-2027, 5 missions)

• 2025 Mission 1: Hab 6LL (Laboratory, Hab 6), Spacesuits, Laboratory

Supplies

• 2026 Mission 2: Hab 7M (Medical, Hab 7), Medical Hab Supplies

• 2026 Mission 3: Hab 8A (Aeroponics, Hab 8), Aeroponics equipment

• 2027 Mission 4: Hab 9F (Food Prep/Storage, Hab 9)

• 2027 Mission 5: Crew of 2 to XM2, and 2 Crew to Surface (1 week): test

systems

Page 31: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2025 – 2027 JEFFERSON 1 – 4: HABS 6 – 9

Hab 8A (Aeroponics, Hab 8) Aeroponics Facility

Hab 6LL (Laboratory, Hab 6) Science Lab

Hab 9F (Food Prep/Storage, Hab 9) Food Storage and Preperation

Hab 7M (Medical, Hab 7) Medical Research

Page 32: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

MADISON SERIES

2028-2036, 7 MISSIONS

Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 33: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2028-2035 MADISON 1-13: FOOD/WATER/PERSONAL

Madison Series (2028-2034, 19 missions) • 2028 Mission 1: Food and Water

• 2028 Mission 2: Personal Items, 4 humans, Orion Capsule, and Service Module

• 2029 Mission 3: Food and Water

• 2029 Mission 4: Personal Items, 4 humans, Orion Capsule, and Service Module

• 2030 Mission 5: Food and Water

• 2030 Mission 6: Madison 2 Crew Return to Earth

• 2030 Mission 7: Personal Items, 4 humans, Orion Capsule, and Service Module

• 2031 Mission 8: Food and Water

• 2031 Mission 9: Madison 4 Crew Return to Earth

• 2031 Mission 10: Personal Items, 4 humans, Orion Capsule, and Service Module

• 2032 Mission 11: Food and Water

• 2032 Mission 12: Madison 7 Crew Return to Earth

• 2032 Mission 13: Personal Items, 4 humans, Orion Capsule, and Service Module

• 2033 Mission 14: Food and Water

• 2033 Mission 15: Madison 11 Crew Return to Earth

• 2033 Mission 16: Personal Items, 4 humans, Orion Capsule, and Service Module

• 2034 Mission 17: Food and Water

• 2034 Mission 18: Madison 13 Crew Return to Earth

• 2034 Mission 19: Personal Items, 4 humans, Orion Capsule, and Service Module

Page 34: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

MONROE SERIES

2035+

Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 35: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2035 MONROE 1: FERRY TO CYCLER Objective: Design ferry to mars cycler to carry payload of 20Mg with safety option Reasoning: To make the hyperbolic rendezvous as safe as possible.

EUS, Exploration Upper Stage • Provide delta-v required to make

Hohmann transfer & initial stage of hyperbolic transfer

Booster • Provide delta-v required after EUS burn • Continue and finish hyperbolic transfer and perform approach maneuver

Service Module • Capable of doing same maneuver as

the Booster stage • Only used in Booster failure

Service Module • 20Mg, carries 4 crews • Has docking thruster and heat shield

FEMAC(Ferry to Mars Cycler) stage configuration:

Page 36: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

2035 MONROE 1: FERRY TO CYCLER Maneuver breakdown:

1. EUS burn: Hohmann transfer to 1000 km altitude – 0.32 km/s

2. EUS burn: Transfer to high energy ellipse – 2.09km/s

3. EUS jettison

4. Booster Burn: Inject into hyperbolic departure orbit – 1.69 km/s

5. Booster Burn: Trajectory correction maneuver – 0.066 km/s

6. Booster and Service Module jettison

7. Ferry RCS burn: Rendezvous/dock with cycler – 0.0300 km/s

*Booster burn can be also done by service module in emergency case

Launch Vehicle SLS Block 2

IMLEO 175.34 Mg

IVLEO 1040 m^3

Total Delta-V from LEO

4.1941 km/s

Time of Flight 46.11 hr

Basic specification of the FEMAC Configuration allows us to achieve; • Crew Survival rate: 96.96% • Mission Success rate: 93.96% Abort Options • Safe return 0.7 hr (2039) to 2.4 hr (2035)

after insertion • Prevent escape 2.6 hr (2039) to 84 hr

(2035) after insertion

Page 37: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX

Project Manager: Trevor Jahn

Assistant Project Manager: Michael Young

Page 38: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

METHOD COMPARISON What is needed?

• Need to find the most efficient method to move regolith for hab construction

• Need a construction schedule to reflect the recommended method

Assumptions:

• Time numbers are assuming rover is constantly moving regolith or charging

• Full list of assumptions is located on slide 47

Rectangle Dig Only

Rectangle Impact

Aldrin Dig Only

Aldrin Impact

Mass (Mg) 3676.8 3468.4 3542.6 3634.3

Power Required (kW) 1857.0 1542.6 1789.2 1101.3

Volume (m^3) 2451.2 2312.3 2361.8 2422.9

Excavation Time (days) 291.36 222.20 283.91 176.46

Fill in Time (days) 117.18 117.18 109.72 65.833

Recommendation: We use the impactors with Dr. Aldrin’s layout

Page 39: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

CONSTRUCTION SCHEDULE The Procedure

1. The impactors hit

2. Rovers fill in the craters to create pits

3. The first hab lands and is positioned in the pit closest to landing site

4. Rover fills in regolith around hab

5. First connector is positioned and attached

6. Regolith bag wall is built between pit and landing site

7. Repeat steps 3 – 5 for other two habs and connectors in cluster

8. Repeat steps 3 - 7 for the other 2 hab clusters

9. Position and attach the intermediate connectors

10.Create the remainder of the regolith bag wall

Figure 1: First Hab Cluster

Figure 2: Full Layout

Page 40: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

BACKUP SLIDE

The rover:

• The ramps giving access to the pits all have an incline of 16°

• Volume of rover scoop: 0.66 m^3

• Power for a low work trip: 300 W

• Power for a high work trip: 500 W

• Battery charge time: 28.8 hrs

• Battery Life: 10000 W and 24 hrs

The habs:

• 7.4 m diameter

• Short connectors are 0.5 m long

• Habs are buried 2.7m

The Moon

• Regolith density: 1500 kg/m^3

• Rectangle crater is 32 x 32 x 3.11 m initially with 4 m long sloping walls

• Aldrin crater has diameter of 20 m that slopes into a diameter of 5 m over a depth of 4.17 m

LIST OF ASSUMPTIONS/GATHERED VALUES

Figure 4: One of Three Pits for Dr. Aldrin’s Hab Layout

Figure 3: Pit for Rectangular Hab Layout

Page 41: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: VEHICLE CONTROLS AFFECTING FORCES AND CONTROL METHODS

Vehicle Control Method Mass [Mg] Power [W] Volume [m3 ]

Ferrying Lander

CMG/Reaction Wheels

0.292 356 1.627

Ferry to Cycler

CMG 0.544 552 3.240

XM CMG/Thrusters 0.010 200 1.000

Environmental forces:

• Gravitational forces

• Reflected solar radiation

• Solar radiation

• Gravity gradient

• Particle collision forces

• Magnetic field force

Nonenvironmental forces

• Nonpropulsive mass expulsion force

• Damping and structural flexing

• Propulsive maneuvers

• Fuel sloshing

• Other non-environmental movement

Page 42: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: TRAJECTORY OVERVIEW

James Millane High Altitude Retrograde Orbit

Trans-Lunar Injection Orbit

Impactor Vehicle Separation and Trajectories

Moon’s Velocity

Page 43: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: VEHICLE MASS/VOLUME BREAKDOWN

IMPACTOR VEHICLE Quantity: 6

Payload Mass 0.65 Mg

Fuel Mass 0.7 Mg

Inert Mass 0.238 Mg

ISP 320 s

2.0 km/s

Unloaded Mass 0.938 Mg

Loaded Mass 1.588 Mg

Volume

TLI STAGE Quantity: 1

Payload Mass 9.53 Mg

Fuel Mass 3.67 Mg

Inert Mass 2.33 Mg

ISP 320 s

0.9688 km/s

Unloaded Mass 6.01 Mg

Loaded Mass 15.536 Mg

Volume

IMLEO: 15.6 Mg

Page 44: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: IMPACT TRAJECTORY

FINDER PROGRAM OUTPUT

James Millane

Page 45: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: IMPACTING MINING SITE

Jake Elliott

Recommendation: Mine/dig the mining site

Area under the impact site will heat to > 373 K

Assuming the first 2 meters is removed: • 9.424 m2 of floor is exposed • Next ~0.75 m is heated to > 373 K • Rocks are not melted, but volatiles will evaporate

Objective: Determine whether it is possible to excavate material from mining site Reasoning: We want to minimize digging by rovers

Page 46: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: IMPACTOR AND CRATER PARAMETERS

Jake Elliott

Individual Impactor Parameters

Number of impactors: 4

Mass: 975 kg

Density: 2700 kg m-3

Volume: 0.36 m-3

Velocity: 4600 m s-1

Impact angle: 40°

Individual Crater Properties

Diameter: 20.67m

Depth: 4.17 m

Volume: 1,156 m3

Total IMLEO: 12.104 Mg See Jay Millane’s slides from 2/25/16

Page 47: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: ISALE MATERIAL FILE #ISMAT ---------------------------------------------------------------- MATNAME Material name : crust__ : aluminu EOSNAME EOS name : miesand : aluminu EOSTYPE EOS type : tillo : tillo STRMOD Strength model : DRPR : ROCK DILMOD Dilatancy model : ALPHAPT : ALPHAPT DAMMOD Damage model : IVANOV : IVANOV ACFL Acoustic fluidisation : BLOCK : BLOCK PORMOD Porosity model : WUNNEMA : NONE THSOFT Thermal softening : OHNAKA : OHNAKA LDWEAK Low density weakening : POLY : POLY ------------------------------------------------------------------------------ POIS pois : 2.5000D-01 : 3.000D-01 ------------------------------------------------------------------------------ TMELT0 tmelt0 : 1.5130D+03 : 1.673D+03 CHEAT C_heat : 5.9000D+02 : 1.D+03 TFRAC tfrac : 1.2000D+00 : 1.2D+00 ASIMON a_simon : 1.8400D+09 : 6.D+09 CSIMON c_simon : 7.2700D+00 : 3.D+00 ------------------------------------------------------------------------------ YDAM0 ydam0 (ycoh) : 1.0000D+05 : 1.D+04 FRICDAM fricdam : 7.1000D-01 : 8.D-01 YLIMDAM ylimdam : 2.4700D+09 : 2.D+09 ---------------------------------------------------------------------------- YINT0 yint0 : 3.1900D+07 : 1.D+07 FRICINT fricint : 1.1000D+00 : 1.1D+00 YLIMINT ylimint : 2.4700D+09 : 2.5D+09 ------------------------------------------------------------------------------ IVANOV_A Damage parameter : 1.0000D-04 : 1.0000D-04 IVANOV_B Damage parameter : 1.0000D-11 : 1.0000D-11 IVANOV_C Damage parameter : 3.0000D+08 : 3.0000D+08 ------------------------------------------------------------------------------ GAMETA gam_eta : 2.0000D-02 : 8.D-03 GAMBETA gam_beta : 3.0000D+02 : 1.15D+02 ------------------------------------------------------------------------------ ALPHACRIT Zero dil angle distension : 1.2D0 : 1.2D0 DILATCOEF Max. dil angle : 0.0450 : 0.045D0 DILATPLIM Zero dil angle pressure : 2.0D8 : 2.0D8 DILATFRIC dam dist fric : 0.4D0 : 0.4D0 ------------------------------------------------------------------------------ ALPHA0 Initial porosity : 1.0730D+0 : 0.0000D+0 EPSE0 Elastic threshold : -1.0000D-2 : 0.0000D+0 ALPHAX Transition : 1.0898D+0 : 0.0000D+0 KAPPA Exp coefficient : 0.9800D+0 : 0.0000D+0 CHI Sound speed ratio : 1.0000D+0 : 0.0000D+0 ------------------------------------------------------------------------------- <<END

Page 48: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

METHOD COMPARISON What is needed?

• Need to find the most efficient method to move regolith for hab construction

• Need a construction schedule to reflect the recommended method

Assumptions:

• Time numbers are assuming rover is constantly moving regolith or charging

• More assumptions are located in backup slide

Rectangle Dig Only

Rectangle Impact

Aldrin Dig Only

Aldrin Impact

Mass (Mg) 4638.8 4476.4 4347.3 4845.8

Power Required (kW) 2342.8 1960.4 2195.6 1468.4

Volume (m^3) 3092.6 2984.3 2898.2 3230.5

Excavation Time (days) 373.84 289.69 357.64 247.82

Fill in Time (days) 141.59 141.59 125.39 75.235

Recommendation: We use the impactors with Dr. Aldrin’s layout

Kyle Bush

Table 1: Comparison of Mass, Power, Volume and Time for Regolith Moving

Page 49: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

CONSTRUCTION SCHEDULE The Procedure

1. The impactors hit

2. Rovers fill in the craters to create pits

3. The first hab lands and is positioned in

the pit closest to landing site

4. Rover fills in regolith around hab

5. First connector is positioned and

attached

6. Regolith bag wall is built between pit

and landing site

7. Repeat steps 3 – 5 for other two habs

and connectors in cluster

8. Repeat steps 3 - 7 for the other three

hab clusters

9. Position and attach the 3 long

connectors

10. Create the remainder of the regolith

bag wall

Kyle Bush

Figure 2: Full Layout

Figure 1: First Hab Cluster

Page 50: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

BACKUP SLIDE

The rover:

• The ramps giving access to the pits all have an incline of 16°

• Volume of rover scoop: 0.66 m^3

• Power for a low work trip: 300 W

• Power for a high work trip: 500 W

• Battery charge time: 28.8 hrs

• Battery Life: 10000 W and 24 hrs

The habs:

• 7.4 m diameter

• Short connectors are 0.5 m long

• Habs are buried 2.7m

The Moon

• Regolith density: 1500 kg/m^3

• Rectangle crater is 40 x 32 x 3.11 m initially with 4 m long sloping walls

• Aldrin crater has diameter of 20 m that slopes into a diameter of 5 m over a depth of 4.17 m

LIST OF ASSUMPTIONS/GATHERED VALUES AND PIT DIMENSIONS

Kyle Bush

Dimensions of Excavated Pits

Figure 3: Pit for Rectangular Hab Layout

Figure 4: One of Four Pits for Dr. Aldrin’s Hab Layout

Page 51: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: NUCLEAR POWER ESTIMATES CHARGED SPHERES AS A POTENTIAL METHOD OF RADIATION SHIELDING

Power Estimates for Charged Spheres

• Chose a sphere radius of 1 m

• To charge 35 spheres we need 0.0131 kWh of energy

• 35 spheres would then take up a volume of 146.6077 m3

• Spheres must be 50 MV each

Page 52: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

COMMUNICATIONS MAP EARTH – MOON SYSTEM

Objective: To create a communications map

Reasoning: To visually understand how the communication system will be positioned and operated

Chad Oetting

Page 53: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

COMMUNICATIONS MAP MOON SYSTEM

Chad Oetting

Page 54: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

BACKUP

Vehicle / Location Mass [kg] Power [W] Diameter [m]

Ferrying Lander 2.5 3 0.2019 0.0097

Cargo Lander 2.5 25 0.0875 0.1311

Ferry-Cycler 3 65 1.22 0.3897

ComSats (x3) 0.047 55 1.3125 0.0024

Pressurized Rover (UHF) 1 2 0.7698 0.6206

Pressurized Rover (HGA) 1 1 1.3125 1.804

Moon Base 4.7 Mg 100,000 9.4 110

Earth Base 4.7 (x2) Mg 100,000 9.4 110

Chad Oetting

Page 55: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: XM 2 DESIGN

• Dimensions based on BA330

• Deployed Volume: ~338 m3

• Deployed Mass: TBD

• Power: TBD

• Items Left to Determine

• Need material definition.

• Need to finalize XM shell.

• Need to work with

Power/Thermal and Human

Factors to define power

requirements.

BASED ON BIGELOW 330

55 Amit Soni

Page 56: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: XM SHELL STRESS ANALYSIS

• Major structural concern is the multi-layer inflatable shell.

• Loading conditions

• Interior pressurization

• Launch load

• Orbital Maneuvers

• Docking/undocking

• Solar radiation, etc.

• Need to determine shell layer composition.

• Systems Request: Payload Fairing Envelope

• 7.5m dia

• 14.03m length

• Usable volume : 620m3

* SolidWorks models by Amit Soni

56 Amit Soni

Page 57: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: XM-2 DIMENSIONS

57 Amit Soni

* SolidWorks drawing by Amit Soni. All dimensions in meters.

Page 58: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: STRESS ANALYSIS SETUP PROOF OF CONCEPT

• Internal Pressure Model: 101.325 kPa

• Gravity Load: 6 G’s

• Proof of concept modeled with 30 plys of Kevlar 29, oriented at 0°, 45°, 90°, -45° for isotropic properties.

• Only outer shell analyzed.

58 Amit Soni

* SolidWorks FEA model by Amit Soni

Page 59: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: CARGO LANDER

-10 and 20 Mg cargo landers are both powered by RL10B-2 Hydrolox Engines

-20 Mg lander and payload has a total mass of 45 Mg: 3.3 Mg inert mass, 20 Mg payload,

and 21.7 Mg of propellant. The volume of the fuel tank is 44.55 cubic meters while the

volume of the oxidizer tank is 16.25 cubic meters.

-The 10 Mg lander and payload has a total mass of 25 Mg: 2.9 Mg inert mass, 10 Mg

payload, and 12.1 Mg of propellant. The volume of the fuel tank is 24.84 cubic meters

while the volume of the oxidizer tank is 9.06 cubic meters.

- For the 20 Mg lander, the landing struts require an outer radius of 0.15m, an inner radius

of 0.13m, a total strut mass of 112.6 kg, and a volume of 1.2 m^3

- For the 10 Mg lander, the landing struts require an outer radius of 0.15m, an inner radius

of 0.145m, a total strut mass of 29.6 kg, and a volume of 1.2 m^3

- For the 20 Mg lander, the total DeltaV to land from our 4500 km orbiting radius will be

2.8031 km/s. This will include a 0.2761 km/s Descent Orbit Insertion, a 2.183 km/s

Braking and Rotation phase, and a .344 km/s Vertical Descent phase.

Page 60: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: UNIFIED ROVER SYSTEM FOR ASTRONAUTS

Operation Paramete

r

Value

Max Speed

30 [kph]

Cross country Speed

20 [kph]

Range 200 [km]

Height 2.765 [m]

Length 6.9 [m]

Width 2.6 [m]

Carrying Capacity

3.5 [Mg]

Ariel Dimston

Page 61: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: SCIENCE ROVER ARM DESIGN • Powered by geared motors motors for movement.

• 6 degrees of freedom

• 1.8 m fully extended

• Attachment barrel for multiple science tools

• Camera, drill, scoop, claw, etc.

• Can attach to multiple attachment points on rover with electrical access.

*Science Arms CAD designs by Amit Soni

Amit Soni

Shoulder

Attachment Barrel

Arm

Wrist

Geared motor

(x4)

Part Material Qty. Mass (kg) Volume (m3)

Shoulder Al 2090 1 6.72 2.59*10-3

Arm Zoltek™ PX 35 2 7.25 4.01*10-3

Wrist Zoltek™ PX 35 1 0.45 2.46*10-4

Barrel Al 2090 1 2.64 1.02*10-3

Geared Motor ---- 4 2 7.32*10-4

Holder Al 2090 1 0.4 1.59*10-4

Holder Motor ---- 1 1 1.12*10-4

Bolts A286 Steel 4 0.72 1.0*10-4

Mass: 0.021 Mg/arm

Volume: 8.9x10-3 m3

Power: 10W

Recommendation: Scale up science arm design for industrial applications.

Page 62: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

ROVER ATTACHMENTS

OTHER ATTACHMENTS PLANNED: SCOOP SHOVEL, MINING IMPLEMENT, BULLDOZER BLADE

Benjamin Mishler

Fluid Storage Module: Tank Volume: 3.80 [m3] Tank Mass: 0.709 [Mg]

Science Bay: Volume: 17.08 [m3] Mass: 0.912 [Mg]

Page 63: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

APPENDIX: FERRYING LANDER MISSION PARAMETERS

Maneuver ΔV (km/s) Number Required

Takeoff 1.962 1

Circularizing Burn to Enter CLO

0.231 1

15o Plane Change 0.271 2

Descent Hohmann and Landing

2.459 1

Total 5.194

Component TOF

Takeoff 6.7 min

Hohmann to CLO 2 hours, 19 min

Hohmann from CLO 2 hours, 19 min

Landing 13 min

Total 4 hours, 58 min

Purpose: To carry crew members between the Lunar Surface and the XM-2 module orbiting in CLO. To fulfill its mission it must be able to perform the following maneuvers.

Page 64: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

RISK TOP MISSION RISKS

Risk Risk Ranks

Launch Failure 1

Radiation 2

Hyperbolic Rendezvous

3

Communications Failure

4

Pressurized Rover Failure

5

ISRU Failure 6

Fuel Depot Failure 7

XM Failure 8

Crewed Lander Failure

9

1 2 3

4 5 6 7 8 9

Page 65: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

LUNAR VEHICLE SUMMARY 5 Mg Lander

20 Mg Lander

5 Mg Ferry

Vehicle 5 Mg Lander Descent

20 Mg Lander Descent

5 Mg Ferry Ascent Phase

5 Mg Ferry Descent Phase

Payload 5 Mg 20 Mg 5 Mg 5 Mg

Delta-V 2.5 km/s 2.5 km/s 2.5 km/s 2.5 km/s

Prop Mass 3833 – 4054 kg

15335 – 16218 kg

7161 – 8527 kg 4122 – 4908 kg

Initial Mass

9035 – 9555 kg

36142 – 38222 kg

16878 – 20097 kg

9717 – 11570 kg

Launch Vehicle

Falcon Heavy

SLS Block 1B SLS Block 1B SLS Block 1B

Surface

XM-2 Orbit r=4500 km

• Mass Ranges are for Inert Mass Fraction from .05 to .11 • All Lunar Vehicles powered by Aerojet Rocketdyne RL10B-2 Engine

Page 66: WELCOME TO CRITICAL DESIGN REVIEW PROJECT LEGACY TO CRITICAL DESIGN REVIEW PROJECT LEGACY Project ... • 2029 Mission 4: Personal Items, 4 humans, Orion ... • Has docking thruster

20 MG CARGO LANDER • 20 Mg Cargo Lander launched atop the SLS Block

1B within the 8 meter Payload Fairing

• Used primarily to land the habs on the surface of the moon

• Powered by RL10B-2 Engine, ISP of 464 sec

• Even designed at the historically largest Inert Mass Fraction the Cargo Lander is able to land 20 Mg on the surface while still fitting within the 41 Mg to CLO limit of the SLS Block 1B EUS

• The images on the right are of the Cargo Lander designed at an Inert Mass Fraction of .11

Habs and Lander in SLS Fairing

Cargo Lander with Extended Struts

Inert Mass Fraction .05 .11

Payload [Mg] 20 20

Inert Mass [Mg] 0.807 2.004

Initial Mass [Mg] 36.142 38.222

Prop Mass [Mg] 15.335 16.218

LHy [Mg] 2.228 2.357

LOX [Mg] 13.106 13.860