Unit: Sewagram Cement Works 1

UltraTech Cement Limited

(Unit: Sewagram Cement Works-Power Plant)

Welcomes all On 18th National Award for Excellence in Energy Management 2017

Welcome to All 19th National Award for Excellence in Energy Management 2018

Page 2: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 2

We are going to share…

Company Profile

Unit Profile

Plant Configuration and Flow diagram

List of ENCON Projects

Plant Performance over the years

Innovative Projects

Sustainability Initiatives

Methodology of Energy monitoring

Best practices/ Involvement of Employees

CSR initiatives

Awards & Accolades

Way forward

2

Page 3: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 3

Selected as Superbrand 2011-12 by the Super brands council along

with Powerbrand awarded by the institute Power Brands India.

Company Profile

Star Brand India

Page 4: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 4

One stop shop

for all

construction

needs of

Customer

Page 5: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 5

Sewagram Cement Works (Acquired from Jaypee in June-14)

Clinker Capacity :3.6 mtpa(2X5500 TPD) & Cement Capacity – 2.4 mtpa

Captive power plants (CPP) CPP-I 35 MW & CPP-II 22.5 MW capacity.

Mines with reserve of 246.45 MT,

Captive Jetty, a Desalination plant that can filter 2200 Kl of water every day

Unit At Glance

Page 6: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 6

Broad Specification of TPP Equipment

Package Make Type Capacity &Feature

Boiler-1 TKIL CFBC 170TPH, Pr.-87 Kg/cm2, Temp.-515 +/-50C

Boiler-2 IJT AFBC 110TPH,Pr.-87 Kg/cm2,

Temp.-515 +/-50C

Turbine-1 Siemens Condensing 35 MW, Pr.-84 Kg/cm2

Temp.-515 +/-30C, Steam Flow -143.5TPH

Turbine-2 Siemens Condensing 22.5 MW, Pr.-84 Kg/cm2

Temp.-515 +/-30C, Steam Flow -93.5TPH

Generator-1 &2 TDPS+Andritze

Hydro

Brushless

Excitation 11KV,43.75 & 28.125 MVA, PF-0.8

Coal &Lime stone

Handling Masyc

Blow bar

crusher

Coal-180TPH & Lime-60TPH, Flip flow screen

for High Moisture coal

DG (03 Nos.) Man B&W 12.5MW +12.5MW +10.8MW

Desal Plant ION Exchange PTP + RO 6700 KLD

Page 7: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 7

List Of ENCON Projects

Page 8: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 8

Without Investment

Rs. 489.8 Lacs

With Investment

Rs. 1508.6 Lacs (ROI- 1.8 Yrs)

Total Saving

Rs. 1998.4 Lacs

Savings in last Three year through EnCON Projects

Page 9: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 9

SN Energy Saving Projects (06 Nos.)

Saving Achieved

Electrical Energy

(Rs. Lacs)

Saving Achieved

Thermal Energy (Rs. Lacs)

1 Boiler -1 ID draft optimized at -15mmWC against -25mmWC 2.3 -

2 Running of one BFP in place of 02 BFP up to 80 % load for

Both Plant (Design is 2*50%) 191.1 -

3 Reduction of LOI from 10.5 to 4.5% 45.2

4 Further optimization of Instrument air pressure from 6.5

kg/sq.cm to 6.0 kg/sq.cm 3.5 -

5 Operation of Boiler at Lower Bed Height i.e. Reduction by

50MMWC. 87.1 -

6 Start Using of Pet Coke as alternate fuel to improve Boiler

Efficiency of Both TPP - 12.9

Sub Total 284.0 58.1

Grand Total 342.1

Energy Savings Projects with No Investment FY’15-16

Page 10: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 10

Energy Savings Projects with No Investment FY’16-17

SN Energy Saving Projects (14 Nos.)

Saving Achieved

Electrical Energy

(Rs. Lacs)

Saving Achieved

Thermal Energy

(Rs. Lacs)

1 Boiler-1&2 efficiency increase by optimize excess O2 in flue gas at

3.9 % against 4.5 % - 31

2 DM plant operation running hour optimized at 5 hrs./5 days

against 2 hrs./day 1.4 -

3 For Boiler -1 &2, Lime screw feeder stop due to pre mixing of

lime in Coal conveyor belt 1.6 -

4 For Boiler -1 & 2, 10 Nos. Lime stone belt conveyor stop due to

pre mixing of lime in Coal conveyor belt 1 -

5 TG-1 Deaerator O/L temp. increased upto 155 Deg C from 150 Deg

C - 2

6 Boiler -1 Bed ash cooler optimized running hrs. to reduce PA fans

power consumption 5.5 -

7 TG-1&2 Vacuum controlling through PID controller 11.3 -

Page 11: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 11

SN Energy Saving Projects (14 Nos.)

Saving Achieved

Electrical Energy

(Rs. Lacs)

Saving Achieved

Thermal Energy

(Rs. Lacs)

8 Cooling tower fan power consumption optimized by PID

controller of CW outlet temperature to start of CT fan 3.1 -

9 Ash conveying air cons optimized by reducing nos. of hole of

orifice 0.1 -

10 All lights are stopped at CHP area in night shift 2.1 -

11 Flue gas temp. of ESP I/L reduced from 135 to 130 Deg C looking

to the sulphur due point - 4.0

12

Service air compressor running Hrs. optimized at 18 Hrs./day

against 24 Hrs./day by optimized operation of ash conveying

system

8.6 -

13 Optimization of CHP running hours 4.7 -

14 Improvement of Boiler-2 Efficiency by increasing Petcoke

percentage by weight in fuel mix from 7.3 to 40.2% -

43

Sub Total 39.4 80

Grand Total 119.4

Energy Savings Projects with No Investment FY’16-17

Page 12: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 12

SN Energy Saving Projects

Saving Achieved

Electrical Energy

(Rs. Lacs)

Saving Achieved

Thermal Energy

(Rs. Lacs)

1 Boile-2 APH line diverted to Boiler-1 to reduction in LOI of fly

ash 6.50 -

2 P & V system stopped by proper ventilation through efficient

exhaust fan in TG building 15.30 -

3 Service air comp. running Hrs. reduced by use of Instrument

air as service by optimizing ash handling operation. 4.60 -

4 Both Boiler ESP Power reduced by adjusting optimized field

voltage as per fuel selection in boiler 1.30 -

5 Coal impactor VFD RPM set point varies with respect to fuel

selection to reduce APC 0.60 -

Grand Total 28.30

Energy Savings Projects with No Investment FY’17-18

Page 13: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 13

SN Energy saving Projects (04 Nos.)

Saving Achieved

(Rs. Lacs)

Investment (Rs.

Lacs)

1 Wet steam washing of TG-2 to improve efficiency 34.8 5

2 Overhauling of TG-1 for Heat Rate improvement 599.8 85

3 Installation of VFD in TPP-2 CEP 10 4.3

4 Installation of VFD in TPP-1 CEP & PID controller 19.3 4.3

Grand Total 663.9 98.6

Energy Savings Projects with Investment FY’15-16

Page 14: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 14

Energy Savings Projects with Investment FY’16-17

SN Energy saving Projects (08 Nos.) Saving Achieved

(Rs. Lacs)

Investment (Rs.

Lacs)

1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5

2 TG-1&2 ACC internal Fins cleaning carried out through HP pump

water pressure to reduce ACC fan power cons. 41 2.2

3 APH tube change to improve APH efficiency & reduces PA fans

Auxiliary power 2.6 5

4 Instt Air used as service air 6.2 0.2

5 Replacement of Start-up vent 14.1 4.6

6 VFD in Inst. Comp & PID Logic Operation 12 7.2

7 Use of efficient LED lighting in place of conventional lamps. 1.8 9.3

8 Improvement of Boiler-1 Efficiency by increasing Petcoke

percentage by weight in fuel mix from 11.3 to 46.1% 223 0.5

Grand Total 512.4 34

Page 15: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 15

Energy Savings Projects with Investment FY’17-18

SN Energy saving Projects Saving Achieved

(Rs. Lacs)

Investment (Rs.

Lacs)

1 Installation of VFD in Boiler-1 BFP 40.0 32.9

2 Installation of VFD in Boiler-2 BFP 25.1 30.9

3 Installation of VFD in Instrument compressor-01 4.8 7.7

4 Installation of VFD in Service compressor-05 8.1 7.7

5 TPP-1 ACC fan 1&5 Tube bundle replaced 24.9 225.0

6 ACC APC reduce by its Fin Cleaning of TPP-1 16.2 1.8

7 ACC APC reduce by its Fin Cleaning of TPP-2 8.2 1.3

8 Boiler-1 APH tubes (1340 Nos.) replaced 93.3 17.6

9 Boiler -2 ESP outlet expansion bellow replacement 1.5 0.9

10 08 Nos. 150 Watt LED installation in place of 32 Nos. 250 Watt

HPSV lights in TG Building 17.3 1.0

Page 16: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 16

Energy Savings Projects with Investment FY’17-18

SN Energy saving Projects Saving Achieved

(Rs. Lacs)

Investment (Rs.

Lacs)

11 08 Nos. 150 Watt LED installation in place of 32 Nos. 250 Watt

HPSV lights in TG Building 17.3 1.0

12 LED Installation work and Circuit separated in TPP areas 3.8 6.6

13 RO Reject line modification work 3.2 6.7

14 Intake Pipe Line modification Work 2.4 4.7

15 PSF PUMP VFD installation. 3.7 4.7

16 Stilling Pump VFD installation. 10.9 4.7

17 Turbocharger Based HP Pump for RO Plant 48.3 184

18 Startup vent valve replacement done for TPP-1 1.7 4.5

19 Startup vent valve maintenance of TPP-2 1.6 4.5

Grand Total 332.3 548.2

Page 17: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 17

Plant Performance

Over The Year

Page 18: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 18

Sustainable Plant Performance

77.69 73.37 66.28

2015-16 2016-17 2017-18

10.80 10.20 8.92

2015-16 2016-17 2017-18

Aux. Power Cons.(%)

G

O

O

D

3172

3040 3018

2015-16 2016-17 2017-18

Heat Rate (Kcal/Kwh)

G

O

O

D

4.85% Reduction

4.00 3.68 3.79

2015-16 2016-17 2017-18

G

O

O

D

Power Cost (Rs./Kwh)

17.41% Reduction

PLF (%)

Page 19: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 19

Comparison with Group Units

8.4% 8.9% 9.0% 9.4% 9.6% 9.6% 9.7% 9.8% 9.8% 10.1% 11.9%

81%

66%

88% 78% 74% 70%

84% 79% 80% 80% 62%

0%

100%

0.00%

20.00%

KCW SCW RDCW RC VC RWCW GCW ACW AC APCW HCW

APC Vs PLF

3004 3018 3075 3102 3113 3127 3128 3129 3137

3320 3387 81%

66% 74% 79% 80% 80% 84%

78% 70%

62%

88%

0%

100%

2700

3500

KCW SCW VC ACW AC APCW GCW RC RWCW HCW RDCW

PHR Vs PLF

Page 20: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 20

Comparison with Benchmark & Cluster Units

7.5% 8.9% 9.7%

11.9%

100%

66%

84%

62%

0%

100%

0.00%

20.00%

National Benchmark SCW GCW Sanghi Cement

APC Vs PLF

2980 3018 3128

3147

100%

66% 84% 62%

0%

100%

2700

3500

National Benchmark SCW GCW Sanghi Cement

PHR Vs PLF

Page 21: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 21

Innovative Projects in FY’17-18

1.New Turbo

System Installation in Desal

2.Reduction of LOI

% in Boiler

3. Lignite firing in Boiler

4. MV Drive

installation in TPP

BFP

Page 22: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 22

1.New Turbo System installation in Desal

Objective

Reduction in specific Power Consumption of Desalination RO Plant . (Reduction from 7.99 Kwh/KL to 4.50 Kwh/KL)

Background of Project

Water production cost is high due to high Sp. Power consumption (7.99Kwh/Kl) in

Desalination RO plant.

Less reliable of existing pump due to pump life was distorted by Sea water operation.

Approach

Page 23: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 23

23

Old design energy recovery system Installation of high efficient turbocharger with new design single pump

Efficiency of Energy recovery system is less Low efficient turbocharger

02 Nos. High pressure pumps installed in place of single and operating on DOL mode with high pressure against design Membrane efficiency, Re-handling of reject water

Desal RO Power consumption is very high (50% cost contribution)

Root Cause

Analysis

Pump power consumption is high Power consumption is 430 KW and operating at DOL mode

High RO Power Consumption

High Power consumption at RO

[VALUE] 6.50 4.90 4.50 4.80

SCW ABG Cement IR Veraval Tata Power Adani Power

Sp. Power Consumption (Kwh/KL)- Cluster

Power Consumption – WHY-WHY Analysis

1.New Turbo System installation in Desal

Page 24: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 24

UOM A B C D E F G H

CF Inlet HPP_1 HPP-2 HPP Common ERT RO inlet RO Product RO Reject ERT Reject

M3/Hr. 238 119 119 238 238 76 162 162

Kg/Cm2 1.6 38 38 38 61.5 1.5 60 1

KWH 0 225 225 0 0 0 0 0

KWH/KL 5.95

Code UOM A B E F G H

Desc. CF Inlet HPP _1 ERT RO inlet RO ProductRO Reject ERT Reject

Flow M3/Hr. 268 264 264 85.15 178.85 178.85

Pressure Kg/Cm2 2.92 30.88 57.92 0.5 57.22 0.6

Power KWH 0 352 0 0 0 0

Sp.Power KWH/KL 3.87

Before After

1.New Turbo System installation in Desal Performance Parameters

4.50 7.99

Page 25: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 25

1.New Turbo System installation in Desal Benefits

Performance parameter Before After Saving

Specific Power consumption

7.99 Kwh/KL 4.39 Kwh/KL 3.60 Kwh/KL

Power Cost for water Gen.

170.39Lac/Annum 109.21Lac/annum 61.18

Lacs/Annum

Reliability

Breakdown frequency of pump/its

Motor was increasing trend

( 2-3 time per month)

Breakdown frequency of pump

and its Motor eliminated

OEE was less OEE increased

Uniqueness Water Lubricated Bearing

Reduction in Power - 44%

Page 26: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 26

2. Reduction of LOI % in Boiler

Objective

To reduce power cost ,by increasing Boiler Efficiency through reduction in Boiler ash LOI from 4.5% to 2.0%

Background of the Project

LOI of Boiler was on higher side i.e.4.5%. Lower Boiler efficiency due to Higher LOI % Power cost was increasing due lower Boiler efficiency.

Page 27: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 27

Method/Process

Analysis of crushed Coal Size

Material

High Fly Ash LOI

Coal Quality

High Fines in Coal

Man

Skill

Knowledge

Training

Machine

Screen Size of Coal

Gap of crusher

2. Reduction of LOI % in Boiler Causes & Effect Diagram

Coal Crushing

Operation

Improper Air Flow/ Turbulence

Page 28: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 28

Key Initiatives Adjust the impactor Gap for proper Fuel fines on fortnightly basis.

Optimized the air flow ratios i.e. Primary air Vs secondary air Vs tertiary air .

Analysis of coal started on shift basis and maintained the coal size within range.

Results Reduction in Fly ash LOI by 1.8%

Increment in Boiler Efficiency by

1.20%

Saving of Rs. 92 Lacs/annum

2.Reduction of LOI % in Boiler Benefits

5.9 6.1 5.4 5.2

5.8 6.2 6.1

5.4 4.8

4.2 4.8

4.3 4.1 4.6

1.9 2.1 1.7 1.5

2.2 1.8 1.5

1 5 10 15 20 25 30

% LOI TREND

Oct-17 Nov-17 Dec-17

Page 29: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 29

3. Lignite firing in Boiler

Reduction in Power Generation cost by utilization of available low cost fuel- Lignite

Objective

Problem /Background

Boiler is not design for 100% lignite firing.

Available Imported coal cost Rs/MCV is higher compare to Lignite.

Volatile matters is very high in lignite which increasing high temperature in convection zone of boiler during firing of Lignite .

Lignite have high VM & due to same it get self ignite & create fire risk in fuel handling system

Page 30: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 30

Erected one new discharge chute (size 20’’) with manual isolation gate from Lime screen discharge chute which divert lime stone in coal feeding conveyor belt.

Provision for Raw meal extraction from Raw meal silo

Raw Meal feeding system at Boiler Lime bunker.

Looking to VM Boiler furnace draft reduced from -25mmWc to -10 mmWc which resulted saving of Aux. power

Action Initiated

3. Lignite firing in Boiler

Page 31: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 31

3. Lignite firing in Boiler

By this modification, Up to 80 % Lignite fired in boiler . For 100% Lignite firing Boiler FGD proposal in under process.

Better reaction between Lime Powder & SOx.

Fire risk minimized near belt conveyors by blending of lime stone with lignite at belt conveyor.

Saving of Aux. Power at ID fan – 33.24 Lacs/annum

Saving of amount 687 Lac/Annum by selection of Lignite fuel.

Results

Page 32: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 32

4. MV Drive Installation in BFP

Objective

Background of Project

TPP Power generation is directly depend upon power demand by Cement plant.

TPP PLF varying between 40 to 85 % as per load requirement & due to same DOL- BFP taking high power at low MW Generation & that was increasing the aux. power consumption.

Analysis & Implementation required to reduce APC of BFP at low MW Generation of TPP.

Reduction in Auxiliary power consumption by Installation of MV drive in Boiler Feed Pumps

Page 33: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 33

0.00

Aux. Power (13.2 cr.)

10.20%

MOP/AOP

(0.15%)

Boiler Fans (3.5%)

Boiler (6.5%) SA Fan (0.5%)

Turbine (0.15%)

CEP (0.5%)

PA Fan(1.8%)

ACC (2.5%)

BOP (0.70%)

BFP (2.5%)

ESP (0.5%)

ID Fan (2.2%)

Material handling

(0.20%)

ACC Fans (2.0%)

DM Plant (0.10%)

ACW &CT (0.30%)

CHP (0.15%)

LIme Stone

(0.05%)

Compressors(0.40

%)

Causes & Effect Diagram Value Driver mapping

4. MV Drive Installation in BFP - Analysis

Page 34: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 34

4. MV Drive Installation in BFP - Analysis

Analysis

To reduce power cost ,it is very important to optimize the BFP power consumption . By cause

& effect analysis following causes has been identified

Plant Running on Low capacity

Losses due to Recirculation

Losses due to Feed control valve throttle at low feed water demand to boiler drum

DOL Operated BFP

Implementation

Team TPP adopted Engineering & technological change in BFPs by installing of MV Drive in BFP with proper PID & Logic implementation as follows-

Feed water discharge pressure set point = Boiler Drum pressure + 7 Kg/Cm2( Head loss+ Bend Loss + Piping/tube friction loss)

Page 35: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 35

4. MV Drive installation in TPP BFP

Results

Throttling losses minimised by opening Feed control to maximum

BFP recirculation become zero at low load.

Power Saving Rs. 1173 Mwh/Annum

Saving of Rs. 46.92 Lacs /Annum on fuel Cost

Page 36: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 36

Sustainability Initiatives

Page 37: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 37

GtG energy consumption status (Cement & Power Plant)

1223 1104 1149 1064 1032

2014-15(Baseline Year)

Target SEC for PAT-2 cycle(04/16 to 03/19)

2015-16 2016-17 2017-18

Gate to Gate Sp. Energy Cons. (Kcal/Kg PPC)

Unit registered as Designated Consumers (DC) under PAT-2 scheme

Target given for 7.57 % reduction in GtG Specific Energy Consumption at the end of PAT-2 cycle

(2016-19)

Implementation of Encon projects in the unit reflects 15.61 % reduction in SEC upto 2017-18

without normalization.

Page 38: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 38

GHG Emissions in MT/Yr (Cement & Power Plant)

221480

267746 251163

219191

2014-15 2015-16 2016-17 2017-18

GHG Emission TPP

Page 39: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 39

Green Belt development

Green cover of about 144.6 Ha in Plant, Mines and Colony premises

Total tree planted – 49629 Nos. in Plant, Mines & Colony area till date Survival Rate of plants are 79% Extensive Plantation undertaken at Colony, Plant and Mines.

Page 40: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 40

Green Belt development

Page 41: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 41

Utilization of Renewable Energy/ Alternate fuel/ Wastes

Page 42: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 42

5 MW Solar Plant Installation

Details of Solar Plant

Capacity is 5.0 MWp (DC) / 4.0 MWp (AC)

Approximate Land Requirement: 25 Acres

Type of System: Fix-Tilt

Expected Life Of Solar Plant: 22 Years

Proposed Power Gen. & Efficiency

Expected Generation- 22287 kWh/Day

First Year Power Generation - 85.0 (Lacs Units)

First Contract year adjusted - 2.5% degradation

Each subsequent Year degradation - 0.7%

Efficiency- 19.4%

Plant Commissioned on 14th August-18

Page 43: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 43

Solar Power Plant

Page 44: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 44

Use of Alternate Fuel/Wastes

Used 784 MT of Coal Dust i.e. reject of steel plant as alternate fuel.

Used 45 MT of Carbon black powder as alternate fuel

Used 334 MT Soya husk/Cow dung/Wooden Chips as a alternate fuel

Used PPF for boiler Light up – Usage of Petro Polymer fuel in place HSD.

Used 8196 MT AFBC Fly ash in CFBC as a fuel

Used 8105 M3 N-Pit water in dust suppression (zero water discharge).

Page 45: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 45

Energy Cell

Page 46: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 46

Energy Policy

We Committed to demonstrate excellence

in reduction in Energy Consumption &

Carbon emission in all our activities of

manufacturing of cement & Clinker on

continual basis so as to make our unit & its

surrounding environment sustainable for

future

Page 47: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 47

Methodology adopted for Energy Monitoring

Energy management cell headed by FH-TPP.

Daily monitoring of PLF, Heat rate and Aux. power deviation.

Analysis of equipment performance for deviation.

Identification of energy conservation scope through - Loss Cost Matrix, Brain

Storming and Theme base suggestions/Kaizens scheme under “Energy Saving ”.

Feasibility study of suggestions & submit proposal for sanction.

Preparation of detail action plan.

Monthly review to monitor project progress.

Benefits analysis after project implementation.

Sustainability of the project

Page 48: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 48

Energy Monitoring

Energy Monitoring System

Page 49: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 49

Implementation of corrective /

Preventive action

Page 50: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 50

ISO 9001:2015

ISO 14001:2015

OHSAS 18001:2007

ISO 50001:2011

Under Implementation

System Accreditation in 2016-18…..

Page 51: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 51

IMS (ISO:9001,14001 and OHSAS:18001)

SCW has got Certification from International organization for standardization for Integrated Management systems for

Quality Management System (ISO 9001:2015), Environment Management System (ISO 14001:2015) and Occupational

Health & Safety Management Systems (OHASA18001:2007) from certification agency DNV.

Page 52: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 52

S.No. Non-conformity Description Corrective Action Taken

1 EMP is not evident to consistently meet compliance to new Stack emission norms of 30 micrograms/Nm3 in Clinker cooler Unit1 and in different stacks Unit Though improvement is observed in Unit stacks after replacement of

Bag filters, Clinker Cooler emission was found to be 29 micrograms/Nm3 in Feb 2018.

All Management programs identified.

2 As per the consent condition AWH-60839 clause 4.4, of limestone mines, ambient noise monitoring to be carried out. Organization shall take necessary authorization for the generation

and disposal of the hazardous waste.

Ambient Noise monitoring started

3 Failure - compliance to above condition is not evident. Evidence various hazardous waste such as Oily cotton waste, oil filters, used

Oil drums etc. are generated, however consent shows authorization for Used oil only.

Hazardous waste - such as Oily cotton waste, oil filters, used Oil drums etc., generation and disposal mechanism made for putting in Kiln.

Implementation of Corrective & Preventive Actions

52

Page 53: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 53

Best practices

Team Work

Knowledge Sharing

Page 54: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 54

Best Practices

• Examples are as under –

Analysis of area wise Aux. Power consumption on daily basis

Impact analysis in bearing by vibration spectrum analysis technique for lubrication of equipment

Energy efficient Motors & Illumination System

AFBC boiler converted into CFBC boiler without any technological upgradation

100% ash of boiler, utilized for Cement Manufacturing .

All new procurement is on the basis of energy efficiency.

Page 55: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 55

Team Work in EnCon

SN EnCon idea * Idea originated

in FY ** Extent of man-power involved

*** Progress of

implementation

1 Installation of MV Drive at Boiler Feed Pump 2017-18 O&M ,E&I & M/s Toshiba Team Completed

2 Closed Loop operation ACW pump operation with discharge pressure

2017-18 O&M and E&I Team Completed

3 New Turbo System installation in Desal 2017-18 O&M ,E&I and M/s Fedco Team Completed

4 Reduction of LOI in Fly Ash from 4.5 to 1.8% 2017-18 O&M Team Completed

5 Solar Power Generation 2017-18

E&I Team and M/s ABRL Team Completed

6 Closed loop operation of Lignite fuel feed in boiler

2017-18 O & M and E&I Team Completed

Page 56: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 56

Knowledge Sharing with Group Units / Vendors

Kaizen Souvenir shared to all Group Units. Achieved 15 KPE (Kaizen Per Employee) in Fy’18

Conversion of AFBC Boiler to CFBC horizontally replicated to other Group Units and same has implemented at Balaji and Aditya Cement.

Shared Erosion protection Plate modification to M/s ThyssenKrupp

Bed ash handling of AFBC Boiler through Primary Air fan in place of Compressed air shared with M/s ISGEC

Provision of MCB before signal isolator in VFD shared with M/s ABB

Page 57: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 57

Green Supply Management

Two way transportation for Raw meal and fly ash with bulker.

Two way Transportation for Fuel receipt and Clinker Export to Port.

Two way transportation of Clinker and receipt of Pond ash (Wanakbori Unit

& Gandhi Nagar Plant).

Operational of Captive Jetty for Coal.

Page 58: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 58

Corporate Social Responsibility

Corporate CSR

CSR Vision

CSR Policy

Focus Area

58

Infrastructure Development

Education

Health care Sustainable Livelihood

Page 59: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 59

Glimpses

Shala Praveshotsav and Kanya Kelvani Program

230 School Kit Distribution to surrounding Government 20 school and 55% Girls Involved .

Page 60: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 60

Awareness campaign for

Personal hygiene, Family

planning, Immunization

camps.

Awards to best students

nearby Villages.

Corporate Social Responsibility

60

Page 61: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 61

“ Women Empowerment ”

Installed of 7 Automatic Sanitary Pads vending Machine and Automatic Electrical

Incinerator in 7 Block in Model Girls Hostel. Total 839 Girls Model Hostel benefited by

activity

Page 62: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 62 62

Award & Accolades

Page 63: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 63

CII National Kaizen Award-2017 (Env. Category)

SCW (Only Cement Plant) have won National Kaizen Award (Top -18) for Utilization of Alkali-Chloride Bypass dust in

Cement under Environment Category.

The Award was presented by Dr.Baldev Raj (Indian scientist and former director of the Indira Gandhi Centre for Atomic

Research) on 10th CII National Competitiveness and Cluster Summit which was held at India Habitat Centre, New Delhi on 6th December 2017.

Page 64: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 64

CII-National Award for Excellent Energy Management

Sewagram Cement Works awarded as Energy Efficient Unit at CII 18th National Award for “Excellence in Energy Management” (Category: Captive Power Plant)

Page 65: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 65

Sewagram Cement Works Best practices recognized at IMC, Mumbai on 9th Mar’18 :

1.A giant step towards Green & Clean clinker production.

2.Utilization of ABC boiler Flyash as fuel in CFBC Boiler(TPP).

MQH Best Practices Recognition at IMC Mumbai

The same Best Practices were also published in their Annual Magazine with a Introduction of SCW Plant.

Page 66: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 66

Harudi-Kharai Limestone Mines

AWARDED 5 STAR rating mines

Amongst Top 5 best performing mines in INDIA

Kharai-Harudi Limestone Mines

Also AWARDED

5 STAR rating MINES

Receiving award from Hon’ble Union Minister of Mines & Panchayat Raj Shri Narendra Singh Tomar for Harudi

–Kharai Limestone Mine

Receiving award from Shri Haribhai Parthibhai Chaudhary Hon’ble Union Minister of State for

Mines for Kharai –Harudi Limestone Mine

Limestone/Raw Material

Page 67: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 67

We have received the official

Invitation letter for 2nd Intl’ Global

Cem Process Conference 2018 as

Keynote speaker For the presentation

on “A giant step towards ‘green and

clean’ production by replacing

conventional fuel for Cement Plant

(petcock and coal) with nearby

available lignite”.

Global Cem Process Conference

Page 68: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 68

Way Forward

Page 69: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 69

Energy Saving Projects

SN Energy Saving projects Proposed Saving

Per Annum (Rs. Lac) Target date

1 Energy Efficient Boiler Feed Pump Installation 25.5 Jan’19

2 Energy Efficient PA & ID fan Installation in CFBC

Boiler 27.6 Feb’19

3 Energy Efficient FD & ID fan Installation in AFBC Boiler 22.3 Feb’19

4 Optimization of CHP running hours 3.6 Oct’18

5 Installation Heat Exchanger at CBD tank 15.5 Nov’18

6 Installation of Energy Efficient fans in ACC 45.5 Oct’18

7 Installation of Energy efficient Boiler feed pump 14.5 Mar’19

Page 70: Welcome to All 19 th National Award for Excellence in ... Sector_72... · 1 AFBC high LOI ash used in CFBC to increase boiler efficiency 211.7 5 2 TG -1&2 ACC internal Fins cleaning

Unit: Sewagram Cement Works 70

Team Sewagram Cement Works

JOURNEY CONTINUES TOWARDS ACHIEVING

HEAT RATE 2950 KCAL/KWH AND AUX. POWER

7.5%.........