GREEN FLAG
QA/QC WEEKLY REPORT FOR WEEK ENDING 29-04-2015
GREEN FLAG
Final Paint Inspection was carried out for Base Frames of Novec System Skids. It was inspected and accepted by ZADCO PMC.RED FLAG
QHSE
Near missWork Injuries Vehicle Incidents Training by QA/QC EngineersNonconformanceSite QHSE Inspection Report for the week QHSE Management Walkthrough Report for the week Monthly QHSE Meeting
OTHERS
HSE Action Tracking Register was prepared for Halon Rep. Project of ZADCO. Document review was carried out of Material Handling Procedure for ADMA OPCO Project and comments from client mended. Document review was carried out of Project Overall Execution Philosophy and comments from client mended. REPORT ENDWeekly QA/QC Report for week ending29-04-2015 Page 1 of 1