WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016
Page 1 of 4
Prepared For: Atlanta Public Schools
Prepared By: Austin Nichols
Aerial View Aerial View
Aerial View Auditorium Terrazzo
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016
Page 2 of 4
Admin Entrance Canopy Lighting
LED Sign Auditorium Sidewalk
Last Week’s Activities:
• Classroom Addition
o Finished installing tack boards and whiteboards
o Continued punch
• Auditorium
o Continued installing terrazzo
• Administration Addition
o Finished Installing terrazzo
o Finished painting
o Finished installing carpet
o Finished installing casework
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016
Page 3 of 4
• Administration Renovation
o Finished painting
o finished installing VCT
o Finished installing carpet
o Finished installing casework
• Gym Renovation
o Continued installing waste and vent
o Continued MEP overhead rough in new classrooms
o Began installing new doors in lower level
This Week’s Activities:
• Classroom Addition
o Completed punch
• Auditorium
o Finished installing terrazzo
• Administration Addition
o Began punch
o Installed tack boards
o Installed corner guard
• Administration Renovation
o Began punch
o Installed corner guard
o Waxed VCT
• Gym Renovation
o Finished painting lower level
o Finished hanging doors in lower level
Next Week’s Activities:
• Classroom Addition
o Final coats of wax
• Auditorium
o Finish installing coiling door
o Finish installing lights
• Administration Addition
o Finish punch
o Finish installing security system
o Finish pouring sidewalk
• Administration Renovation
WEEKLY CONSTRUCTION PROGRESS REPORT Crawford Long Middle School July 29th, 2016
Page 4 of 4
o Finish punch
• Gym Renovation
o Wax lower level
o Continue MEP rough in
Schedule:
• Status: Weather dependent
• Substantial Completion Dates:
o Classroom Addition: July 15, 2016
o Renovations: July 20, 2016
o Administration Addition: August 1, 2016
o Track and Field: September 1, 2016
o Auditorium Addition: September 7, 2016
o Gym Renovation: October 7, 2016
• Final Completion: December 31, 2016
Budget:
• Construction Budget: $15,920,000
• Budget Status: On Budget
• Gross Billed To Date: $10,118,024