8706 LOCKWAY, SAN ANTONIO, TX 78217 (210) 655-1031 WWW.BARTLETTCOCKE.COM PAC MULTIPURPOSE BUILDING (201243) WEEKLY PROGRESS REPORT, MAY 27TH, 2022 /…; Completed acoustical ceilings on both floors E. Completed 1st paint on all E and N areas. This Week: Poured walkway/drive @ NW corner of N area. Continue MP @ East Elevation of East area and completed MP @ Penthouse. Completed OH punch list for level 2 East and level 1 North. Completed removal of floor protection on level 1 and 2 West in prep for start up of air handlers. Completed installing controls @ west penthouse. Now working on North. Installing bases for RR countertops. Poured drive to NW corner, continuing on. 2 Week Look-Ahead: Complete MP @ East and north area. Complete stone @ building exterior. Complete excavation for remainder of south drive/parking lot. Start re grading concession rd. Complete OAC OH punch lists @ level 1 & 2 East and West area. Start up of West area ahu’s. Tie in MPB to campus power loop.

WEEKLY PROGRESS REPORT NOVEMBER

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: WEEKLY PROGRESS REPORT NOVEMBER

8706 LOCKWAY, SAN ANTONIO, TX 78217 (210) 655-1031

WWW.BARTLETTCOCKE.COM

PAC MULTIPURPOSE BUILDING (201243)

WEEKLY PROGRESS REPORT, MAY 27TH, 2022

/…;

Completed acoustical ceilings on both floors E.

Completed 1st paint on all E and N areas.

This Week:

• Poured walkway/drive @ NW corner of N area.

• Continue MP @ East Elevation of East area and

completed MP @ Penthouse.

• Completed OH punch list for level 2 East and

level 1 North.

• Completed removal of floor protection on level

1 and 2 West in prep for start up of air handlers.

• Completed installing controls @ west

penthouse. Now working on North.

Installing bases for RR countertops.

Poured drive to NW corner, continuing on.

2 Week Look-Ahead:

• Complete MP @ East and north area.

• Complete stone @ building exterior.

• Complete excavation for remainder of south

drive/parking lot. Start re grading concession rd.

• Complete OAC OH punch lists @ level 1 & 2 East

and West area.

• Start up of West area ahu’s.

• Tie in MPB to campus power loop.