Remediation Weekly Activity Summary Report
General Field Activities Completed: Week Ending January 24
General Field Activities Planned: Week Ending January 31
Air Monitoring Summary Week Ending January 24
Weekly Project Meeting Summary:
The project team met with Joe Hamilton and Doug Keene of Kaskaskia Engineering on Jan 22 to discuss the
finalization of the sewer replacement design and the schedule to submit plans to the City of Columbia. The site team
called-in with John Dometrorch of C.L.Richardson also present to discuss the sewer work; C.L.Richardson is likely to
be the sewer contractor. KEG is concerned that the double length culvert section necessary to eliminate the junction
structure as requested by the City will be very heavy. The junction structure is also important to CLRichardson's plans
to construct. KEG will finalize their reports and plans and submit to the City in the next week. KEG will also
communicate with the City about continuing to use the junction structure instead of the double length culvert section. C
L Richardson described their approach to construction which was consistent with our expactations. C L Richradson
provided the following estimates for project task completions: drawings 1 week; steel fabrication 2 weeks; culvert
section fabrication 2.5 weeks; installation 2 weeks. The team agreed that C L Richardson should start their efforts
ASAP after completing contract discussions with EOI; it is hoped that the sewer reconstruction can be completed
during March. It is expected that Phase I work will be completed by mid-February; the extent of Phase II excavations
will be tailored to fit the schedule of the sewer installation work and the current culvert removal. KEG agreed to
communicate with the City about our revisions and complete their package for the City in the next week. The City can
take two weeks to review, but their responses to date have been more rapid.
Ameren Columbia MGP - Remedial Action
Project Week No.:
Period:
Completed By: Dave Pluhar
1/20 - 1/24/2014
Two
January 22, 2014
PSC Project Number: 624-1302-0002
Excavation in the east end of the Phase I area continued. EOI used three haul trucks on Monday to transport soil to
the landfill. Based on the Monday experience and a commitment from Allied to keep the landfill available until 5PM,
EOI used 10 trucks on Tuesday Wednesday and Thursday to transport soil and managed four loads with most trucks
each day. EOI worked a shorter day on Friday but still moved soil from the excavation to the Jefferson City landfill.
Ameren, EOI, and PSC met with KEG on January 22 to review the design plans for the sewer replacement. EOI's
subcontractor for the sewer work, C.L.Richardson also participated in this meeting by conference call from the Site.
Chris Cady visited the Site on Janaury 22. Crockett Engineering collected samples of the stone aggregate backfill from
Boone Co. quarry that EOI will use during the project; samples were tested to determine maximum densities according
to both Standard and Modified Proctor.
Soil excavation will continue. Backfill with aggregate may begin.
Remediation phase real-time ambient air monitoring activities continued through Week 2 by Burns & McDonnell
Engineering Company (Burns & McDonnell) hourly with a PID, GC, and dust Monitor. No exceedances of the real-time
action levels were recorded. Real-time dust concentrations for Week 2 were below action levels at the perimeter of the
property. Average real-time concentration graphs are attached. Odors were present intermittently at the perimeter of
the site during Week 2.
In total, 5 time-averaged, 72-hour air sample events were collected, including baseline, as of January 24th from five
perimeter air stations. Time-averaged samples were shipped to Con-Test Analytical Laboratory for analysis.
PM10 time-averaged analytical data has been received for sampling events up to January 6, 2014. PAH time-
averaged analytical data has been received for sampling events up to January 6, 2014. VOC time-averaged analytical
data has been received for sampling events up to January 2, 2014. Time-averaged PM10, naphthalene and benzene
concentrations are below the acceptable concentrations of 150 µg/m3, 4.1 µg/m3 and 41.5 µg/m3, respectively.
Page 2
Remediation Weekly Activity Summary Report
Actual Quantities Project Estimates
175.37 3432.01 3607.38 30000.00 - - -
37.38 0.00 37.38 2500.00 - - -
0.00 0.00 0.00 1000.00 - - -
212.75 3432.01 3644.76 33500.00 0.00
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
0.00 0.00 0.00 - - - - - -
Monday Tuesday Wednesday Thursday Friday
3 10 10 10 8
0 0 0 0 0
Completed By: Dave Pluhar
Ameren Columbia MGP - Remedial Action
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
Type 5 Aggregate (tons)
TwoProject Week No.:
Soil Waste to Allied Waste, Jefferson City, MO (tons)
C & D Waste to Allied Waste, Jefferson City, MO (tons)
MGP Remediation Waste to PDC (tons)
Total All Disposal (tons)
Material Log
Solid Waste Material:
Clean Material:
Prior Total: This Period:Total To
Date:Original: Revised:
Material Type:
Soil Backfill (tons)
1/4-inch Stone (tons)
Sand (tons)
Rip-rap (tons)
Type 1 Aggregate (tons)
Treated Wastewater:
Trucks Transporting:
Disposed (other)
Disposal
Backfill
Discharged to Columbia Regional WWTP
Page 3
Actual Quantities Project Estimates
Prior
Total:
This
Period:
Total To
Date:Original: Revised:
0 17 17 180 - - -
0 17 17 180 - - -
0 17 17 180 - - -
0 17 17 180 - - -
0 17 17 180 - - -
0 17 17 180 - - -
0 17 17 180 - - -
0 17 17 180 - - -
0 0 0 10 - - -
0 0 0 10 - - -
0 0 0 10 - - -
0 0 0 10 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
0 0 0 25 - - -
624-1302-0002
Metals (arsenic, lead, selenium)(6010)
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number:
Completed By: Dave Pluhar
VOCs (5035/8260)
SVOCs (8270)
Sample Collection Summary:
Soil Samples:
Total barium (EPA 200.8)
Cyanide, total/amenable (9012)
Per-cent moisture (D-2974)
pH (9045)
TPH GRO (8260)
TPH DRO (8270)
Reactice Cyanide
Reactive Sulfide
TCLP Benzene
TCLP RCRA Metals
Ammonia as Nitrogen (EPA 350.1)
Total arsenic (EPA 200.8)
Wastewater Samples:
BOD5 (5210)
Total boron (EPA 200.7)
Total cadmium (EPA 200.8)
Total hexavalent chromium (EPA 218.6)
Total chromium (EPA 200.8)
Total zinc (EPA 200.8)
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Oil & Grease (1664)
pH (4500-HB)
Phenols (420.2)
Total silver (EPA 200.8)
Total Suspended Solids ((2540-D)
Total toxic organics (EPA 624 & 625)
Cyanide (SM4500 CN-1)
Total copper (EPA 200.8)
Total iron (EPA 200.9)
Total lead (EPA 200.8)
Total mercury (EPA 200.8)
Total nickel (EPA 200.8)
Benzene (EPA 624)
Start Complete Start Complete
12/9/2013 1/10/2014 1/7/2014 1/13/2014
12/9/2013 12/13/2013 12/12/2013 12/13/2013
12/19/2013 12/20/2013 12/19/2013 12/20/2013
12/30/2013 1/4/2014 12/30/2013 1/4/2014
1/8/2014 1/10/2014
1/13/2014 1/17/2014 1/15 2014 1/17/2014
1/6/2014 1/6/2014 1/7/2014 1/7/2014
Ameren Office Building Demolition
11/12/2013 11/15/2013 11/12/2013 11/15/2013
12/17/2013 12/17/2013 12/17/2013 12/17/2013
1/8/2014 1/10/2014 1/13/2014 1/15/2014
1/9/2014 1/10/2014 1/15/2014 1/16/2014
1/17/2014 2/24/2014 1/17/2014
1/27/2014 2/24/2014 1/30/2014
2/25/2014 3/10/2014
3/11/2014 3/18/2014
3/19/2014 3/24/2014
3/11/2014 3/24/2014
3/25/2014 4/14/2014
2/25/2014 3/24/2014
3/25/2014 4/14/2014
3/3/2014 4/14/2014
Temporary Structure Assembled - 10 days 4/15/2014 4/24/2014
4/21/2014 4/25/2014
4/28/2014 4/28/2014
4/30/2014 6/13/2014
5/12/2014 7/3/2014
7/7/2014 7/17/2014
7/7/2014 7/19/2014
7/14/2014 7/19/2014
7/21/2014 7/23/2014
7/21/2014 7/31/2014
Page 4
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
General Site Set-up
Asbestos Abatement - 3 days
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Completed By: Dave Pluhar
Actual DatesProjected Dates
Field Offices Established - 15 days
Perimeter Fence & Gates Revised - 3 days
Air Monitoring Stations Established - 2 days
Baseline Air Sampling Completed - 6 days
Storm Water Controls Installed - 3 days
WWPT System Assembled - 5 days
Traffic Control Plan Signs Installed - 1 day
Phase One Excavation
Sewer Replacement
Phase Two Excavation
Phase Three Excavation
Culvert Demolition
Excavations
Pre-cast Culvert Assembly
Cast-Inplace Structures Construction
Sewer Completion
Divert Flow & Remove Existing Culvert
Contents Disposal - 1 day
Structure Demolition - 3 days
Debris Disposal - 2 days
Phase One Excavation -
Phase One Backfilling
Phase One Excavation
Phase Two Backfilling
Ventilation System Assembled - 5 days
Temporary Structure Permit Received - 1 day
Phase Three Excavation -
Phase Three Backfilling
Structure Disaasembled - 10 days
Site Restoration
Pavement Repairs Completed
Top Soil & Seeding
Site Fence Revisions Completed
Site Surface Restorations Completed
Projected Dates Actual Dates
Projected Dates Actual Dates
Projected Dates Actual Dates
Projected Dates Actual Dates
Projected Dates Actual Dates
Projected Dates Actual Dates
Start Complete Start Complete
7/7/2014 7/8/2014
7/7/2014 7/8/2014
7/18/2014 7/22/2014
7/21/2014 7/22/2014
7/25/2014 7/25/2014
7/28/2014 7/28/2014
7/28/2014 7/28/2014
7/23/2014 7/24/2014
5/5/2014 5/5/2014
7/24/2014 7/25/2014
Page 5
Remediation Weekly Activity Summary Report
Ameren Decatur MGP - Remedial Action
Project Week No.: One
Period: 1/13 - 1/17/2014 PSC Project Number: 624-1302-0002
Actual DatesProjected Dates
Temporary Structure Shipped - 3 days
Ventilation Components Shipped - 2 days
Pac-Van Office Demobilized - 1 day
Traffic Control Signage Removed - 1 day
Sidewalk Reopened - 1 day
Utilities Disconnected - 2 days
WWPT System Removed - 2 days
Site Demobilization
Completed By: Dave Pluhar
Excavation Equipment Demobilized - 2 days
LP Tank Removed - 1 day
Facilities Removed - 2 days
Completed By: Dave Pluhar
Page 6
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
AS OF JANUARY 24, 2014 WEEK 2
Completed By: Dave Pluhar
Page 7
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
Subcontractor begins the removal of the former Ameren communication tower by removing the antennae
The pole was then cut in sections and lowered to the ground using a second crane
Completed By: Dave Pluhar
Page 8
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
The bottom two-thirds of the communication pole is lowered to the ground
Final cut at the base of the former radio communication pole
Completed By: Dave Pluhar
Page 9
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
Phase I excavation progress on January 22
Mid-week progress along the stormwater culvert, the first of two surface inlets has been removed
Completed By: Dave Pluhar
Page 10
Remediation Weekly Activity Summary Report
Ameren Columbia MGP - Remedial Action
Project Week No.: Two
Period: 1/20 - 1/24/2014 PSC Project Number: 624-1302-0002
Excavation progress as of Janury 24
Soil conditions below the culvert are shown well in the photo with the coal layer at the base of the excavation