Catalogue
Major part of the device
1 General
2 Device components and its system
3 Working process
4 Handling and storage
5 Installation and adjustment
6 Application and operation
7 Maintenance
8 Frequent fault and troubleshooting
Electrical control
1 General
2 Function description
3 Installation, commissioning and operation
4 Maintenance and error processing
7/31/2019 Warora-Installation Operation and Maintenance Manual
2/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
1
Major part of the device
1 General
This chemical dosing device for water treatment consists of auto NH3 dosing device,
auto N2H4 dosing device and Na3PO4 dosing device which are used for two units. Three
devices are controlled by one control panel.
The main function of the chemical dosing device is that putting the prepared dilute
solution of chemicals(NH3, N2H4, Na3PO4) into the feedwater, condensation water ,boilerwater or closed-type cooling water system through the dosing pump to adjust the quality of
water vapor in the system to prevent metallic corrosion , to prevent calcium scale from
depositing in the boiler .
2 Device components and its system
No.
Description
Model/specification
Qty
Remarks
1
Ammonia dosing equipment H30-1 1
1.1Ammonia solution tank
1000L 1000mm 316SS 2
1.2Ammonia mixer
910rpm 1.1kw 2
1.3 Level guage
UHZ-10C00B
L=1300mm2
1.4 Ammonia metering pump for
feed water
RA060S024
58L/h 2.0Bar 316SS3 Milton Roy
1.5 Ammonia metering pump for
condensate water
RB090S067
88L/h 4.1Bar 316SS3 Milton Roy
1.6 Pulsation damper
NXQ-L/A 304SS 6
1.7 Relief valve
RV2-MF-6N-AS316
@1.6MPa3 HY-LOK
1.8 Relief valve
RV2-MF-6N-AS316
@3.2MPa3 HY-LOK
1.9 Y GLT-25 304SS 2
7/31/2019 Warora-Installation Operation and Maintenance Manual
3/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
2
No.
Description
Model/specification
Qty
Remarks
Y-type strainer
1.10 Ball valve DN15~DN25 1
1.11 Pressure guage
YA-100 0~2.5MPa 3
1.12 Pressure guage
YA-100 0~6MPa 3
1.13
Ammonia transfer pumpC786-36 92L/h 7Bar 1 Milton Roy
1.14Pipe & accessories
DN15~DN32 304SS 1
1.15 SkidCarbon steel 1
1.16ladder & platform
Carbon steel 1
2
Hydrazine dosing equipmentH30-1 1
2.1
Hydrazine solution tank1000L 1000mm 316SS 2
2.2
Hydrazine mixer
910 rpm 1.1 kw 2
2.3 Level guage
UHZ-10C00B
L=1300mm2
2.4 Hydrazine metering pump for
feed water
RA060S024
58L/h 2.0Bar 316SS3 Milton Roy
2.5 Hydrazine metering pump for
condensate water
RB090S067
88L/h 4.1Bar 316SS3 Milton Roy
2.6
Pulsation damper
NXQ-L/A 304SS 6
2.7 Relief valve
RV2-MF-6N-AS316
@1.6MPa3 HY-LOK
2.8 Relief valve
RV2-MF-6N-AS316
@3.2MPa3 HY-LOK
2.9Y Y-type strainer
GLT-25 304SS 2
2.10Ball valve
DN15~DN25 1
2.11 YA-100 0~2.5MPa 3
7/31/2019 Warora-Installation Operation and Maintenance Manual
4/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
3
No.
Description
Model/specification
Qty
Remarks
Pressure guage
2.12 Pressure guage YA-100 0~6MPa 3
2.13Pipe & accessories
DN15~DN32 304SS 1
2.14 Hydrazine transfer pump
C786-36 92L/h 7Bar 1 Milton Roy
2.15
SkidCarbon steel 1
2.16ladder & platform
Carbon steel 1
3
Phosphate dosing equipmentH30-1 1
3.1 Phosphate solution tank
1000L 1000mm 316SS 2
3.2 Phosphate mixer
910 rpm 1.1 kw 2
3.3 Level guage
UHZ-10C00B
L=1300mm2
3.4
Phosphate metering pump
MBH101-8MPF
47L/h 240Bar 316SS
4 Milton Roy
3.5Pulsation damper
NXQ 304SS 4
3.6 Relief valve
RV2-MF-6N-AS316
@19.5MPa4
3.7Y Y-type strainer
GLT-25 316SS 2
3.8
Ball valveDN15~DN32 1
3.9
Globe Valve
DN15 8
3.10
Pipe & accessoriesDN15~DN32 304SS 1
3.11 Pressure guage
Y-150 0~40MPa 4
3.12
SkidCarbon steel 1
3.13ladder & platform
Carbon steel 1
7/31/2019 Warora-Installation Operation and Maintenance Manual
5/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
4
No.
Description
Model/specification
Qty
Remarks
4
Control system
H30-1 1
4.1 Control panel
(800+600)x600x2200mm 1
4.2EAdjustbale frequency AC
draive
ATV312 7
4.3 PLC
Modicon 1
4.3.1Master station
4.3.1.1
+RW VWDQG\ FRQWUROOHU
PRGXOH
140CPU67160 2
4.3.1.2
3RZHUVXSSO\PRGXOH140CPS12420 4
4.3.1.36
VORWUDFN;%3 1
4.3.1.45,2
5,2+($'&53 1
4.3.1.5
.
.PHPRU\FDUG 76;0)33. 1
4.3.1.6
(WKHUQHWPRGXOH140NOE77101 2
4.3.2
6ODYHVWDWLRQ
4.3.2.1
3RZHUVXSSO\PRGXOH140CPS12420 1
4.3.2.2RIO RIO DROP
140CRA93200
4.3.2.3 $,PRGXOH
$&, 2
4.3.2.4
$2PRGXOH$&2 1
4.3.2.5
',PRGXOH'', 3
4.3.2.6
'2PRGXOH''2 1
4.3.2.7 10 ;%3 1
7/31/2019 Warora-Installation Operation and Maintenance Manual
6/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
5
No.
Description
Model/specification
Qty
Remarks
VORWUDFN
3 Working process3.1 Chemical solution preparation and chemical dosing proces
3.1.1 Ammoniadosing unit3.1.1.1 Chemical solution preparation
First step: the chemical outlet valve of the standby solution tank should be opened and at
the same time the chemical outlet valve of the solution tank in which the chemicals are
already used up should be off; the second step: according to the dosing concentration
requirement, the prepared strong ammonia water is deliveried to the solution tank; the third
step: the demineralized water inlet valve of the solution tank is opened, at the same time
the level of the solution tank should be observed, when the level reaches the high level
point (or the required level), the water inlet valve should be off; the fourth step: the
agitator of the solution tank should startup, the demineralized water and ammonia in thesolution tank shall be sufficiently soluted and mixed, then the mixer should be off to finish
the chemical dosing work. The solution tank is under standby condition.
This system has two ammonia solution tanks, which are interchangeabl
3.1.1.2 Chemical dosing process
EE
E
When the chemical dosing is required, the chemical outlet valve of the solution tank, the
inlet valve and the outlet valve of the metering pump (make sure all the valves on the pipes
which the chemical solution flow through are open.)should be opened, the metering pump
shall start up. The flow adjusting rotation button on the metering pump shall be adjusted to
enable the outlet flow to reach the required one; also the output frequency of the frequency
converter shall be directly adjusted to change the output flow of the metering pump. The
ammonia solution shall enter the metering pump through the inlet pipe of its pump and be
transmitted to the dosing point through the outlet pipe. The chemical dosing work is
realized.
7/31/2019 Warora-Installation Operation and Maintenance Manual
7/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
6
3.1.2 N2H4 dosing unit3.1.2.1 Chemical solution preparation
*
The first step: the chemical outlet valve of the standby solution tank should be opened at
the same the chemical outlet valve of the solution tank in which the chemicals are used up
should be off; the second step: according to the dosing concentration requirement, the
prepared strong N2H4 solution should be deliveried to the metering box which is on the top
of the solution tank; the third step: the chemical outlet valve of the metering box should be
opened to enable the N2H4 solution to enter the solution tank; the forth step: the
demineralized water inlet valve of the solution tank should be opened, at the same time the
level gauge of the solution tank should be observed, when the water level reaches high (or
the required level), the water inlet valve should be off; the fifth step: the agitator of the
solution tank should start up, the demineralized water and N2H4 in the solution tank shall
be sufficiently soluted and mixed, then the agitator should be off to finish the chemical
dosing work. The solution tank is under standby condition.
This system has two N2H4 solution tanks, which are interchangeable.
3.1.2.2 Chemical dosing process
EE
E
When the chemical dosing is required, the chemical outlet valve of the solution tank, the
inlet valve and the outlet valve of the metering pump (make sure all the valves on the pipes
which the chemical solution flow through are open.) should be opened, the metering pump
shall start up. The flow adjusting rotation button on the metering pump shall be adjusted to
enable the outlet flow to reach the required one; also the output frequency of the frequency
converter shall be directly adjusted to change the output flow of the metering pump. The
hydrazine solution shall enter the metering pump through the inlet pipe of its pump and be
transmitted to the dosing point through the outlet pipe. The chemical dosing work is
realized.
3.1.3 Na3PO4 dosing unit3.1.3.1 Chemical solution preparation
7/31/2019 Warora-Installation Operation and Maintenance Manual
8/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
7
The first step: the chemical outlet valve of the standby solution tank should be opened
at the same the chemical outlet valve of the solution tank in which the chemicals are used
up should be off; the second step:the prepared Na3PO4 cystal shall be put into the solution
basket from the material opening of the upper part of the solution tank; the third step: the
demineralized water inlet valve of the solution tank should be opened, at the same time the
level gauge of the solution tank should be observed, when the water level reaches high (or
the required level), the water inlet valve should be off; the fourth step: the agitator of the
solution tank should start up to enable the solid chemical to be soluted sufficiently then the
agitator should be off to finish the chemical dosing work. The solution tank is under
standby condition.
This system has two Na3PO4 solution tanks, which are interchangeable.
3.1.3.2 Chemical dosing process
EE
E
When the chemical dosing is required, the chemical outlet valve of the solution tank,
the inlet valve and the outlet valve of the metering pump (make sure all the valves on the
pipes which the chemical solution flow through are open.)should be opened, the metering
pump shall start up. The flow adjusting rotation button on the metering pump shall be
adjusted to enable the outlet flow to reach the required one; also the output frequency of
the frequency converter shall be directly adjusted to change the output flow of the
metering pump. The phosphate solution shall enter the metering pump through the inlet
pipe of its pump and be transmitted to the dosing point through the outlet pipe. The
chemical dosing work is realized.
3.2 Operation3.2.1 Each metering pump shall feed the correspondent chemical dosing point.
4~20mAEE
For the metering pump with automatic adjusting flow device, the processed water quality
measuring signal 4~20mA shall be transmitted to the frequency converter, which shall
be used to adjust the motor frequency of the metering pump and its piston stroke so as to
7/31/2019 Warora-Installation Operation and Maintenance Manual
9/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
8
realize the adjustment of the output flow of the metering pump.
+
For the metering pump with manual adjusting flow, the manual adjusting screw of themetering pump shall be performed to adjust the output flow of the metering pump as per
the instruction manual of metering pump.
When a pump operates abnormally, the auxiliary pump shall be put into operation
manually. The system is equipped with the automatic adjusting device which can adjust the
output flow of the metering pump, so the control signal shall be switched to the control
device of the auxiliary pump at that time.
3.2.2
During the operation, normally only one solution tank provides chemical solution while
the other is under standby condition. When the level of the operating solution tank reduces
to the low level, the auxiliary tank shall be put into use manually.
3.2.3
x
4~20mA
Every solution tank is equipped with a magnetic floater level gauge so that the tank levelcan be site observed. And the solution tank is also provided with the level sensor which
function is that the operation panel can automatically alarm when the tank level reduces to
the low level or increases to the high level, or the metering pump shall automatically stop
operation when the level reduces to the low-low level. These alarm signal shall be transmit
to other system as per the requirement. The solution tank with the level transmitter shall
send 4~20mA anolog signal to the control system so that the present level of the tank can
be remote monitored.
4 Handling and storage4.1
The device and control cubicle shall be packaged and handled separately. Handling shall
be smooth and horizontal without rotation and the device shall not be damaged during the
handling.
4.2 /The device shall be storaged suitably and shall not be placed with exposure and be free of
rain and moisture
4.3
7/31/2019 Warora-Installation Operation and Maintenance Manual
10/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
9
During the storage, the connection shall be sealed well, and all the flange surface shall be
blocked by the blind plate and be free from foreign matter so as to prevent the affect on the
operation of the chemical dosing device.
5 Installation and adjustment5.1
8
The components of the whole device shall be put into place as per the arrangement
drawing, and the base shall be adjusted horizontally. After the adjustment, the anchor bolt
shall be tightened or the base and pre-embedded parts shall be welded, and the operation
platform and the base shall be tack welded.
5.2
Before the installation, the temporary blind plate of the pipe opening shall be dismounted
first and the foreign matters in the solution tank and the pipe shall be removed, then the
demineralized water pipe, the dirt discharge pipe, the inlet pipe and outlet pipe for
connection of the chemical solution for every device shall be connected.
5.3 The electrical device installation refers to Section 2 electrical system
6 Application and operation6.1 Preparation and check before the application6.1.1 Check the instrument such as the pressure guage, level guage.
6.1.2 Check the sealing of the pipe connection and tighten the bolt and nut.6.1.3 Check the cleanness of the solution tank, metering tank, valve and pipe.
6.1.4 Preparation and checking before the operation of the metering pump (please refer to the
operation and maintanence manual of the metering pump)
1 2mm
Check the oil level which shall be in around 2mm of the oil level guage center line.
2
Regulate the piston stroke of the metering pump to zero.
3
Manually turn the rotating section of the pump and check whether exists jamming or
unbalance.
4
Check whether the rotation direction of the motor accords with the indication.
5
Check whether the valves on the intake and outlet pipe of the pump is opened.
6
7/31/2019 Warora-Installation Operation and Maintenance Manual
11/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
10
Check whether the foundation bolt of the pump is loose or not.
6.1.5 Checking before the operation of the mixer
1
Check whether the lubricant on the transmission part of the mixer is suitable.2
Manually turn the rotation shaft, check whether exists jamming or unbalance.
3
Check whether the rotation direction of the motor accords with the indication.
4
Check whether the foundation bolt and louver bolt is loose.
6.1.6
Checking of the control cubicle and electrical section refers to Section 2 electrical control
system.
6.2 Operation6.2.1 Preparation of various chemical solution
6.2.2 Open the relevant inlet or outlet pipe valve of the pump.
6.2.3 Press the sta button to start up the operating pump.
6.2.4 The operation of electrical section for the whole device refer to Section 2 electrical control
system.6.2.5 The abnormal condition during the operation of the whole device shall be timely checked
and eliminated.
6.3 Shut down
/
When the chemical dosing device stops operation, the relevant pipe valve and pressure
guage valve shall be off. During the long time shut down of the unit, the chemical solution
in the pump and pipe shall be discharged and shall be rushed by water. If it is cold, the
necessary anti-frozen measures must be taken.
7 Maintanence7.1 The whole device shall be kept clean and dry.
7.2 The oil level shall be suitable for the transmission part of the chemical dosing pump, and
the lubricant shall be replaced regularly as per the instruction manual of the pump.
7.3 Installation, dismounting and assembly of the pump shall be in accordance with the
7/31/2019 Warora-Installation Operation and Maintenance Manual
12/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
11
instruction manual of the pump.
7.4 The instrument, valve shall be checked periodically and be regulated, repaired or replaced
under abnormal conditions.7.5 The bearing of the mixer shall be oiled periodically, the louver shall be checked regularly
to avoid being loose.
7.6 The filter shall be cleaned periodically to prevent block.
8 Frequent failure and troubleshooting8.1 Inadequate or no output flow
Causes Methods
Broken of the pump intake pipe
Replace with the new intake pipe to ensure
the tightness of the pipe
Block of the pipe
Clean the pipe or replace with the new one,
check the filter and dismount the filter net to
clean
Unfreely operation of the pump valve
Check, clean or replace
Solid cystal appearance or the solidimpurities
Increase the output flow or restrain theconcentration or clean
The safety valve not reaching the setting
pressure to unload.
Check, adjust, clean or replace the safety
valve
Leakage of the connection of the outlet
pipe
Check to ensure the tightness
Jamming of the check valve
Slightly knock the check valve to make the
valve core looseE E
Low output frequency of the frequency
converter
E E
Increase the output frequency of the
frequency converter
Inadequate liquid pressure oil
Increase the liquid pressure oil
Broken of the diaphragm of the metering
pump
Replace the diaphragm of the metering pump
+
7/31/2019 Warora-Installation Operation and Maintenance Manual
13/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
12
Leakage of the relief valve of the
metering pump
As per the instruction of the metering pump,
regulate the relief valve of the metering pump
8.2
Overheat of the pump body (the motor) Causes Methods
1. The pump body exceeding the max.
allowed pressure results in overload
Reduce the output pressure
2. Low oil level
Fill the oil to the required level
3. ELong term operation in the low frequency
condition
E
Manual adjust to reduce the stroke of the
metering pump or to reduce the concentrationof the chemical solution to improve the
operation frequency
8.3 Overwhirling of the indicator of the pressure guage under normal working pressure
Causes Methods
1. 8 Unsuitable pre-charge pressure or the gas
leakage of the accumulator
,
Check the charge pressure and charge to the
required value
2. Broken of the accumulator peltry
Replace the accumulator3. The chemical solution entering the
accumulator
Dismount the valve of the accumulator and
pour out its inner solution
Electrical control system
1 General
4~20mA
The electrical control system of the automatic chemical dosing device for water treatment
consists of electrical control and thermal control. The electrical control is used to perform
the start-up and stop control of the electrical device and various protection inside the
device. The thermal control is used to receive 4~20mA to control the stroke of metering
pump or the motor rotation of the metering pump so as to change the dosing and to satisfy
the dosing requirement of different water quality, and to alarm for the fault of the metering
pump, the mixer or the level. The main technical parameters are as follows:
7/31/2019 Warora-Installation Operation and Maintenance Manual
14/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
13
1.1 50HZ415V
35KA
0~99minElectrical control
Working source: AC 50HZ415V
Limited breaking capacity of the main switch35KA
Timing range of the mixer0~99min
1.2 50HZ230V
4~20mADC
Thermal control
Working source:AC 50HZ230V
Input signal :4~20mADC
1.3 IP55
5~40
10~75%
Others
Motor protection degree of the metering pump: IP55
Working condition: ambient temperature: 5~40Relative humidity: 10~75%
No polluted or corrosive gas
No violent vibration
1.4P
Color meaning
The green light indicates stop, the red light indicates operation
The green button indicates stop, the red button indicates start up
2 Function introduction2.1 Control method and type
Three dosing devices are equipped with one set of control panel to distribute the
electricity, and the chemical dosing control system is independent. The inner unit does
not need re-wiring upon the device at on site.
2.2 Dynamic control loop
7/31/2019 Warora-Installation Operation and Maintenance Manual
15/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
14
E
E
The dynamic control loop (motor control) consists of the high breaking capacity air circuit
breaker, AC contactor, thermal relay and the on or stop button and indicating light on the
control panel etc.(the auto control system also includes the frequency converter etc.). The
button and the light can realize the start-up or stop and the status of the motor. The thermal
relay or the frequency convertor can realize such functions as the overload, shortcircuit
and phase loss protection of the metering pump and the mixter and the alarm control. The
detailed on and stop operation see the sketch panel nameplate. The following are the
introduction of the thermal control function and instruction for the dynamic loop of the
metering pump etc.
2.2.1 Control loop of the metering pump
The motor operation of the metering pump shall be locked by the low-low level signal of
the solution tank (the switch chosen from the panel), i.e. when the liquid level of the
selected solution tank is lower than the low-low level setting value, the motor shall not be
able to start or automatically stop operation.
2.2.2 Automatic control function E
This function is realized by the frequency converter.
The chemical dosing control of the metering pump uses manual adjustment, which is to
directly manual adjust the screw (the stroke)of the metering pump to change the dosing
amount
2.2.2 Control loop of the mixer
0~99
5
The motor control loop of the mixer is equipped with the timer which can be adjusted
continuously for 0~99 min. When the operation time equals to the setting time, the mixer
shall automatically stop. The ex-factory setting time of the timer is 5 min.
3 Installation, commissioning and operation3.1 Installation of the device
The chemical dosing device adopts the unit assembly method, and three devices are
7/31/2019 Warora-Installation Operation and Maintenance Manual
16/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
15
equipped one control pannel. The cable (via the cable tray)from the control cubicle to the
electrical component of the device is installed by the manufacturer without the site
construction, so the workload reduces greatly. The site main installtion work is as follows:
3.1.1 Check the component and material list of the chemical dosing sytem.3.1.2 c Identify the inlet and outlet wiring of the control panel and the wiring of the terminal
blocks.
3.1.3 The connection of the outside power source, the cable of the control system and the
earthing wire.
The construction unit shall install and wiring as per the component arrangement drawing
and the electrical arrangement drawing and the wiring diagram of the terminal blocks for
the chemical dosing room.
3.2 Commissioning3.2.1 Preparation before the commissioning1
Check whether the wiring inside the cubicle is right, or the terminal is virtual connected
or is lost, or the unit component is loose or not.
2
Check the cable connection between the electrical cubicle and the powered device, and the
earthing conditions.
3
Check the wiring from the outside power cable, the outside signal cable to the control
cubicle is correct, and check the polar of the signal cable leads.
4+
Check the spec., the model, quantity of the components in the cubicle complies with the
information provided by the manufacturer.
5
Under the off state of the disconnector, check the mechanical part of the air circuit breaker,
contactor, relay, timer, button and rotation button have turned well, and have no jam.
6 500V 0.5
Measure the terminal connection of the motor to ground insulation resistor by means of
7/31/2019 Warora-Installation Operation and Maintenance Manual
17/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
16
500V M meter, and the resistance shall not be less than 0.5 MThe control cable
shall not be measured.
7
After the checking, the jobsite shall be timely cleaned and the measuring wire shall be
removed to restore previous condition of the device. Close the front and back cubicle door
and the cover of the cable tray. The main switch shall be in off status
3.2.2 Site commissioning1 c
Carefully read the operation instructions of the metering pump, the operating machine
and adjustor of the motor etc. and understand the working principle of the electrical system
and meaning of the nameplate on the cubicle control panel.
2 5 x 10%
The relevant device in the cubicle shall be set as per the operation requirement: the acting
value of the timer (5 min), the flow of the metering pump (10%), the adjustment of the low
level, low-low level probe location. (Notes:the setting value set by the manufacturer before
ex-factory of the device is indicated in the bracket.)
3
E
Notify the electrician to energize the chemical dosing device and to turn on the mainswitch. The volage in the front of the cubicle has the correct indication. Then turn on the
air circuit breaker one by one, and the red light on the panel for stop condition is on. When
no fault is found, turn on the control power switch in the thermal control cubicle, the
power source light of the frequency converter etc. is on.
4.
Inject 1/2 solution of the whole volume to the tank according to the mechanical operation
sequency (the concrete solution preparation shall be as per the operation requirement of the
power plant). The red float column level inside the level gauge is the level of the solution
tank.
5
Short-time start up the motor and check the rotation direction of the motor. Before the
trial-runing of the motor, check the rotation of the motor shall be in accordance with the
symbol on the shell. If not correct, change the power phase sequence timely.
6Static commissioning
a. Manual metering pump
7/31/2019 Warora-Installation Operation and Maintenance Manual
18/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
17
Open the inlet and outlet valve of the pump, start the chemical dosing metering pump, usehand wheel to regulate the dosing of metering pump, then the change of the pump piston
stroke that is the dosing shall be observed. Close the inlet valve on the top and bottom of
the level gauge, open the dirt discharge valve at the bottom, when the level of the tank
reduces to the low-low level probe location, the alarming light is on. When the level of the
tank reduces below the low-low level probe location, each pump shall automatically stop.
The alarm test for the high level refers to that of the low level.
b. Automatic metering pumpE E E
E E E 50HZ15HZ
EEE
The rotation of the metering pump shall be controlled by the frequency convertor, and the
panel of frequency convertor shall be set on output status. The output frequency shall be
regulated by the frequency to control the rotation of the pump motor. The upper and lower
limit of the output frequency of the frequency converter shall be 50HZ and 15HZ. The
frequency converter shall not be allowed to work long time under low frequency. The
detailed operation of the frequency converter refer to the operation instruction.
c. The mixer
Start up the mixer of the solution tank one by one, when the setting time is over, the mixer
shall automatically stop, meanwhile the setting value of the time relay shall be checked.
3.2.3 Dynamic commissioning
Dynamic commissioning means the trial running of the complete chemical dosingdevice
before put into operation. This shall be done coordinated with the electrical and boiler
professions so as to prevent the happening of the accident.
1.
Open the inlet and outlet valve of the pump and relevant valve as per the mechanical
operation sequence.
2
4-20mA
Measure the input signal (i.e.the signal of electric conductivity) between the input
terminals of the adjuster by means of the universal meter set on the DC voltage level, the
input signal should be 4-20mA which proves the outside commissioning signal has been
transmitted.
3
7/31/2019 Warora-Installation Operation and Maintenance Manual
19/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
18
Start up the metering pump, observe the pump rotation.
4
After the adjustment, the device shall be put into operation.
3.3 Trial-operation of the device3.3.1 Necessary inspection shall be done before the trial-operation of the device. When no fault
has been found, the operator shall start up the chemical dosing device.
3.3.2 When the metering pump automatically regulate the dosing amount, it is on the remote
control status.
3.3.3 After the start-up, the cubicle door shall be closed timely and the required operating
records shall be filled.
3.3.4 - Observation of the following items during the operation
1
Control cubicle (panel indicating light, voltage meter etc.)
2
Operation condition of the pump motor
3E
Indication condition of the frequency converter
4
Check of the components (temperature rise of the cable, heating of the terminal,wearing of the contactor)
3.3.5 Check of the following items during the interval of the continous operation
1
Switchover test of the metering pump
2
Switchover test of the solution tank
3
Close-loop disturbance test of the adjusting loop
-
The finish of the above items means the site commissioning work of this device has been
made.
3.3.6 - Attention during the operation1
Be sure the level of the chemical solution shall be at least at 1/2 of the effective level
of the level guage before the start-up of the mixer.
2E
If there is any fault for the frequency converter, it shall be checked. If necessary
7/31/2019 Warora-Installation Operation and Maintenance Manual
20/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
19
inform the manufacturer to handle.
3
If the auxiliary metering pump is required to put into operation, attention shall bepaid to switch the start and stop signal, the outside control signal from the operating
pump to the auxiliary one.
4
The cubicle door shall be timely closed to prevent the entering of the dust and dirty water.
4 Maintenance and fault processing4.1 Maintenance4.1.1 Periocally clean the dust deposited in the cubicle, keep the cleanness of the electrical
device and its nearby.
4.1.2
Periocally check the contactor condition of the air circuit breaker, the AC contactor, the
relay and the level guage probe.If not contact well, check it timely.
4.1.3 Check the wiring of the motor terminal box, the terminal box of the chemical dosing unit
and the terminal blocks inside the cubicle.
4.1.4 The following repair shall be made during the overhaul of the device.
1Dismantle of the mixer motor
2+
Inspection of the pump motor (see the attached document)
3E+E
Inspection the frequency converter performance (refer to the operation instruction of
the frequency converter)
4.1.5
Periodically check the marking tube of the wire and the marking plate of the cubicle panel
etc.. The damaged and lost one shall be added or replaced.
4.1.6 Adjust necessarily the parameter as per the operation requirement of the power plant.
4.2
Fault phenomenon
Causes
Processing method
7/31/2019 Warora-Installation Operation and Maintenance Manual
21/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
20
Unable to startup
of the motor
1. Not energizing of the
power source
Check the air circuit breaker, the AC
contactor in the control circuit have beenturned on
2. Action of the thermal
relay
Check the overload, shortcircuit, phase
lose conditions, after eliminating the fault
reset the relay and start up, if still acts, the
overload current setting value shall be
adjusted again.
3. Fault of the control
loop
X
XCheck the wiring and fuse, if the fuse is
broken, replace with the same spec. fuse.
4. Inner fault of the motor
Dismantle and repair the motor
5. Much lower level of
the tank
Add some chemical solution to be higher
than the low low level
6. E Action of the frequency
converter
Disconnect the air circuit breaker to
re-energize
Unable to adjust
the dosing amount
1. No outside control
signal
4~20mA
Measure 4~20mA DC power between the
terminals of the signal blocks. If not
detected, check whether the control
system has the output signal and whether
the power source wiring is correct
2. E
The frequency
converter not receive
the outside signal
+E E Refer to the operation instruction of the
frequency converter, set the relevant
parameter of the frequency converter to
enable it to receive the outside signal
7/31/2019 Warora-Installation Operation and Maintenance Manual
22/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
21
Not alarm in the
low level
1. Not energizing of the
power source
XCheck the alarm power works well,
including the switch of the power , thewiring and the fusec
2. Fault of the liquid level
sensor
Replace after confirm, if the float column
of the level guage has no magnet, replace
the level guage
Not stop operation
of the pump in
low-low level
1.
The level of the
chemical not reduce to
the low low level probe
location
Not processing
2. Damage of the liquid
guage
Check the probe of the level guage, the
magnetic floater etc.
3. Control loop
Check the operation loop of the pump
motero inside the control cubicle
Big vibration after
the startup of the
mixer
1. Uncorrect rotation of
the motor
Adjust the power phase sequence
2. Distortion of the mixer
shaft
Align or replace the mixer shaft
E
Fault code occurs
in the frequency
converter
+E
Check the fault as per
the operation
instruction of the
frequency converter
E
Check the existence of the fault,
re-enegenize the frequency converter after
disconnect it
E E
Under long time
low frequency
operation of the
frequency
converter
Long stroke or more
concentration of the
chemical solution
Reduce the stroke or reduce the
concentration of the solution
7/31/2019 Warora-Installation Operation and Maintenance Manual
23/23
SHANGHAI ELECTRIC GROUP
CO. LTD.Zhenjiang East China Electric Power
Equipment Factory
:qilidian zenjiang jiagsu :212017 :86-511-85614193
:0511-85623761 :[email protected] :http://www.suyuan.com
22
E
EUnder the full
frequencyoperation of the
frequencyconverter
Short stroke or lowerconcentration
Increase the stroke or the concentration ofthe solution
E E
The frequency of
the converter not
vary with the
change of the
current signal
E
Uncorrect wiring or
uncorrect parameter
setting of the frequency
converter
+E
Check the wiring, set the parameter as per
the operation instruction of the frequency
converter