Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
1
Wanda Marais
From: NokoyoD <[email protected]>Sent: 24 May 2019 10:53 AMTo: Wanda MaraisSubject: RE: NOTICE OF COMMENT PERIOD: Revised Draft Basic Assessment Report: Quest
Petroleum logistics park, filling station & depot
Good day Wanda Thank you for copying DAFF the invite on the email below. I notice you mention the possibility of clearing indigenous vegetation on the affected site. As Forestry we don’t know of any forest on that site, the vegetation cover may be indigenous but not covered under the NFA. I we happen to be not correct we would rely on you to afford us site inspection which we do not expect at this stage. Regards Thabo
From: Wanda Marais <[email protected]> Sent: 23 May 2019 03:53 PM Subject: NOTICE OF COMMENT PERIOD: Revised Draft Basic Assessment Report: Quest Petroleum logistics park, filling station & depot Importance: High Dear Authorities, Stakeholders & Interested and Affected Parties, NOTICE OF COMMENT PERIOD: Revised Draft Basic Assessment Report: Quest Petroleum logistics park, filling station & depot DEDEAT Ref. No: ECm1/C/LN1&3/M/04‐2019 The Draft Basic Assessment Report (BAR) for the proposed Quest Petroleum Logistics Park, filling station and depot was made available for a 30‐day comment period from 19 March to 18 April 2019. Subsequently, due to the inclusion of additional information, a Revised Draft BAR has been compiled and is being released for an additional 30‐day comment period. Please find attached the Executive Summary of the Revised Draft Basic Assessment Report (DBAR), which has been submitted to the Eastern Cape Department of Economic Development, Environmental Affairs & Tourism (DEDEAT) for consideration. The Executive Summary provides a summary of the key elements of the Revised DBAR, however, should you wish to access the complete report, it can be viewed in printed form at the Walmer Public Library, Port Elizabeth or downloaded from the SRK Consulting webpage by clicking on the link: https://www.srk.co.za/en/za‐quest‐petroleum‐ba‐nelson‐mandela‐bay The Revised DBAR will be available for public review and comment for a period of 30 days (24 May – 24 June 2019). It will thereafter be amended in response to the comments received and released as the Final Basic Assessment Report (FBAR) which will be submitted to DEDEAT for a decision on whether Environmental Authorisation should be granted or refused. Comments on the Revised DBAR will assist to ensure that all potential environmental impacts related to the listed activities have been assessed. You are therefore urged to submit comments, as these could ultimately influence the recommendations of the FBAR and the decision taken by DEDEAT. Should you wish to comment on the contents of the Revised DBAR, please submit such comment, in writing, by 17h00 on 24 June 2019 to:
From: Bloem MarisaTo: Wanda MaraisCc: Karissa Nel; Gareth AndrewsSubject: RE: REQUEST FOR DWS COMMENT: Proposed Quest Petroleum Logistics Park, Filling station & depotDate: 25 June 2019 01:34:43 PM
Good Morning Wanda Apologies for not responding sooner. Our office will respond to the documents that you will upload during the phases of theapplication. We will not be submitting comments at this stage.This is the usual practice as comments are provided during the proposal of the project and notwhen the WULA has been submitted. Once documents are uploaded, only then will wecomment. I hope this clarifies things for you. Kind regardsMarisa
From: Wanda Marais [mailto:[email protected]] Sent: 25 June 2019 10:08 AMTo: Bloem MarisaCc: Karissa Nel; Gareth AndrewsSubject: FW: REQUEST FOR DWS COMMENT: Proposed Quest Petroleum Logistics Park, Fillingstation & depotImportance: High Good morning Ms Bloem, DEDEAT has reiterated their request for comment from DWS as set out below. Can you kindlyprovide the comment as a matter of urgency or confirm that DWS is satisfied with providing theirinput during the WULA process currently underway and will not be submitting comments at thisstage. Kind Regards Wanda Marais
From: Wanda Marais Sent: 17 May 2019 09:40 AMTo: '[email protected]' <[email protected]>Subject: FW: REQUEST FOR DWS COMMENT: Proposed Quest Petroleum Logistics Park, Fillingstation & depotImportance: High Good morning Ms Bloem,
I hope that you are well. Kindly revert urgently regarding our request for DWS comment as set out below. Kind Regards Wanda Marais
From: Wanda Marais Sent: 29 April 2019 01:28 PMTo: '[email protected]' <[email protected]>Cc: Karissa Nel <[email protected]>; Gareth Andrews <[email protected]>Subject: REQUEST FOR DWS COMMENT: Proposed Quest Petroleum Logistics Park, Filling station& depotImportance: High Good afternoon Ms Bloem, REQUEST FOR DWS COMMENT: Proposed Quest Petroleum Logistics Park, Fuel station &depot I hope that you are well. A copy of the Draft Basic Assessment Report (DBAR) for the proposed project was delivered toDWS and was open for comment for a 30-day period (19 March – 18 April 2019). DWS did notsubmit any comment during this time, however DEDEAT has specifically requested that weobtain comment from DWS ‘…with respect to the usage of water from the borehole on site, aswell as any requirements they may have to protect the natural resource of the ground water andaquifers.’ Can you kindly supply us with the requested comment, alternatively with written confirmationthat DWS does not intend to submit any comments on the proposed project? Please take notethat a Water Use Licence application is currently underway for the above-referenced boreholefor which Phase 1 documentation will be submitted shortly. Kind Regards, Wanda Marais B Proc
Public Participation Practitioner
SRK Consulting (South Africa) (Pty) Ltd
Ground Floor, Bay Suites, 1a Humewood Rd, Humerail, Port Elizabeth, 6001P O Box 21842, Port Elizabeth, 6000Tel: +27-(0)41-509-4809; Fax: +27-(0)41-509-4850Email: [email protected]
www.srk.co.za
This transmission is intended for the sole use of the addressee, and may contain information that by its privileged and confidentialnature is exempt from disclosure under applicable law. You are hereby notified that any dissemination, distribution or duplication ofthis transmission by someone other than the intended recipient or its designated agent is strictly prohibited. If you have receivedthis transmission in error, please notify the sender immediately by replying to this transmission, or by collect call to the above phonenumber.
DISCLAIMER: This message and any attachments are confidential and intended solely forthe addressee. If you have received this message in error, please notify the systemmanager/sender. Any unauthorized use, alteration or dissemination is prohibited. TheDepartment of Water and Sanitation further accepts no liability whatsoever for any loss,whether it be direct, indirect or consequential, arising from this e-mail, nor for anyconsequence of its use or storage.
Gideon (Kallie) Erasmus B.Proc, MA (cum laude) in Political Science (Unisa)
Attorney, Notary, Conveyancer Prokureur, Notaris, Aktevervaardiger
Kerkstraat 61 Church St, Prince Albert, 6930 ( (023) 5411 900 6 0866 855 979 * Box / Bus 50, Prince Albert, 6930 [email protected]
Our Reference: GE/PE Logistics Park Your Reference: Ms Wanda Marais
Date: 23 June 2019
Ms Wanda Marais SRK Consulting By E-Mail: [email protected] Dear Ms Marais,
INTRODUCTION.
1. We refer to the above and again confirm that we act for:
1.1. Infinite Prospects 142 CC trading as Caltex Greenbushes
1.2. Kouga Business Brokers trading as Caltex Colleen Glen Service
Station; and
1.3. Seven Bridges Trading 23 (Pty) Ltd trading as Caltex Eastern Cape
Marketer (CECM).
Erasmus Environmental and Development Law Attorneys
Omgewings- en Ontwikkelingsreg Prokureurs
COMMENTS ON REVISED DRAFT BASIC ASSESSMENT REPORT: QUEST PETROLE-UM LOGISTICS PARK, FILLING STATION & DEPOT: DEDEAT Ref. No: ECm1/C/LN1&3/M/04-2019
2
2. We acknowledge receipt of the Revised Draft Basic Assessment Report
herein and comment as set out below on behalf of our clients.
In Limine: The Revised BAR is fatally flawed as it is impossible to discern from
the contents thereof precisely which activities as listed in the
NEMA EIA Regulations are being proposed and/or require au-
thorisation.
3. The fundamental purpose of an EIA process is to afford members of the
public and other interested parties an opportunity to engage with the
process with a proper understanding of what the proposal entails.
4. The BID for this project states that “The main activities (amongst others)
potentially associated with the proposed project calling for the BA pro-
cess to be followed are the following:” and then lists 4 listed activities.
5. It also claims that “… more detailed information regarding the proposed
project will be made available in the Draft Basic Assessment Report”.
6. The Revised DBAR describes the proposed activity as:
“The applicant, Quest Petroleum (Pty) Ltd., proposes to develop a logis-
tics park, filling station and depot on Portion 52 (of 9) of the Farm Little
Chelsea No. 10 in the Nelson Mandela Bay Municipal area. The site co-
vers an area of approximately 5.2 ha and is situated in Seaview Road,
approximately 400 m north of the N2 National Road and very close to
the Seaview Road off-ramp (refer to the Locality Plan in Appendix A).”
7. That description could cover a myriad of listed activities yet the DBAR
contains not a single reference to a listing in terms of the NEMA EIA
Regulations.
3
8. Neither appendix 6, a letter from the department dated 14 February
2019, nor the description of the 24G rectification process now included
in the Revised BAR are of any assistance:
8.1. The letter records that:
“The Section 24 G application was authorised on 23 November
2017. This authorisation was granted only for those activities
which were illegally commenced on the site, and did not author-
ise the full development proposal that was contained in the 2011
application”.
8.2. As neither the 24G application nor authorisation have been dis-
closed to I&APs, the letter is of no use.
8.3. The description of what was authorised in terms of section 24G
contained in the DBAR is similarly of no use as it seems to suggest
that the only part of the proposed project that still requires au-
thorisation is the filling station.
9. To confuse matters further, the BAR says the previously authorised fuel
tanks have been removed, but the site development plan shows existing
80m3 fuel tanks.
10. Unless I&APs know precisely what authorisations are being applied for
and what is or is not extant, no sensible engagement with the EIA pro-
cess is possible.
11. A more fundamental problem, however, is that the applicant now en-
visages a phased development:
“It is proposed to construct the above-mentioned activities in two phas-
es with Phase 1 comprising the Logistics Park and Phase 2 the filling sta-
tion and truck stop with ancillary convenience shop and fast- food res-
4
taurant facilities. Phase 1 will commence as soon as all the relevant au-
thorisations are in place with the construction of Phase 2 starting approx-
imately 1.5 to 2 years later”.
12. This proposed phasing merely confirms that there is no need for the pro-
posed filling station.
13. The omission of the previous application for authorisation in terms of the
ECA, the section 24G application for rectification, all documents related
to the above-listed omissions, and a proper explanation of what the dif-
ference is between expansion and a greenfield development, makes it
impossible, not only for lay persons, but for all I&APs to properly consider
this application and Draft BAR.
14. As such it constitutes a denial of the right of I&APs to administrative ac-
tion that is lawful, reasonable and procedurally fair as entrenched in the
Constitution and enabled by the Promotion of Administrative Justice
Act, 3 of 2000.
15. Furthermore, as is self-evident from the Revised Draft BAR and accom-
panying reports, there has been no assessment at all of:
15.1. Whether the terms of the 24G authorisation have been complied
with;
15.2. For what purpose the said tank has been used since authorisa-
tion;
15.3. Whether there has been contamination of the site from the exist-
ing fuel tank;
15.4. What impact the proposed expansion will have on the existing
authorisation.
5
16. The fact is that:
16.1. this is an application to expand what started out as a criminally
unlawful activity, a fact not initially drawn to the attention of
I&APs, and in respect of which, the likelihood of a proper public
participation process having been held is unlikely;
16.2. there is nothing in the Revised Draft BAR to even suggest that the
unlawfully constructed tanks and associated infrastructure have
been lawfully used since rectification was authorised; and
16.3. there is no evidence that it has not contaminated the site al-
ready.
17. On this ground alone, the Draft BAR ought to be rejected out of hand
and the applicant compelled, subject also to what is stated below, di-
rected to undertake a full scoping and EIA
NO NEED FOR THE PROPOSED FILLING STATION FACILITY HAS BEEN PROVEN.
18. It is a mandatory requirement of NEMA EIA regulation 2(c) that an appli-
cant must “describe the need and desirability of the proposed alterna-
tives”, which includes the proposed activity and the so-called no-go al-
ternative.
19. There has still been no consideration of alternatives with the applicant
merely stating that if the proposed activity is not authorised, no jobs will
be created.
20. In Fuel Retailers Association of Southern Africa v Director-General: Envi-
ronmental Management, Department of Agriculture, Conservation and
6
Environment, Mpumalanga Province and Others1, the Constitutional
Court held unequivocally that the socio-economic impacts of a pro-
posed filling station must be substantively considered by the competent
environmental authority in any EIA for a proposed filling station.
21. It is, furthermore, a mandatory requirement of NEMA that “sustainable
development requires the integration of social, economic and environ-
mental factors in the planning, implementation and evaluation of deci-
sions”
22. In response to our clients’ concerns regarding the need for another filling
station/truck stop in an already overtraded area, the response from the
EAPs (in the comments response report) is limited to the following:
“The location of the site is suitable in terms of supplying the traffic from
the N2 National Road, the Seaview Road and the surrounding areas
(such as Greenbushes) with fuel and associated facilities. The proposed
depot and logistics park will provide storage space and offices to ten-
ants”.
23. In response to our query regarding socio-economic impacts, the vacu-
ous response was as follows:
“Your concerns are noted, there are both positive and negative socio-
economic impacts. Kindly refer to Section D(2) of the Draft Basic Assess-
ment Report that described all potential impacted identified for the pro-
ject. The resultant sales of fuel and other business on the property will
contribute to the local economy as well as creating additional employ-
ment opportunities in the local area. Furthermore the filling station will
1 2007 (6) SA 4 (CC).
7
improve the levels of convenience to residents of areas that are in close
proximity to the site”.
24. Those vacuous responses reveal an alarming disregard for the mandato-
ry requirements of NEMA and the NEMA regulations:
24.1. “Suitability” is not synonymous with need – it is not even an ele-
ment of “need”;
24.2. The economic impacts of the proposed filling station, by defini-
tion, includes the impact on existing filling stations, including loss
of sales and presently sustainable jobs – neither of which is even
mentioned;
24.3. The need for another filling station, consequently, stands to be
determined by the extent to which existing filling stations meet
current and could meet foreseeable fuel retailing needs. That is
the sole measure.
25. In the present instance, there has been no identification of filling stations
to be affected, no assessment of how many jobs will be lost, and no as-
sessment of economic impacts at all.
26. The fact is that there are already the following extant filling stations with-
in a 10km radius of the proposed site serving precisely the same market
as is targeted by the proposed filling station:
26.1. Shell Highway and Truck stop site Geduldsrivier 9.5 kms away – li-
censed and under construction
26.2. Engen Baywest – licensed not under construction as yet
26.3. Colleen Glen Service Station (3.5kms)
26.4. Caltex Greenbushes (2 kms)
8
26.5. Shell Sherwood (7.5 kms)
26.6. Engen Rowallen Park
26.7. Caltex Hunters Retreat
26.8. BP Kabega Park
26.9. Shell Kabega Park
26.10. Engen Linton Grange
26.11. Caltex Westering
26.12. Sasol Cape Road
27. As a proposed Highway Site and Truck Stop, the following facilities exist
within a 60 km radius from the proposed site:
27.1. Caltex Mentorskraal
27.2. Caltex PE Convenience Centre
27.3. BP Colchestor
27.4. Engen Dealparty
27.5. Andy’s Deal Party
28. The Draft BAR is also silent on the objective facts that:
28.1. The fuel retailing market in the area has been stagnant for some
time;
28.2. The increasing economic pressure on motorists is likely to impact
negatively on fuel sales everywhere for the foreseeable future;
28.3. Between them the existing filling stations:
9
28.3.1. Fully and properly serve the local market;
28.3.2. Have sufficient residual capacity to properly serve that
market for the foreseeable future.
29. The fact is also that the EAP’s claim that “truck drivers in this area would
have a convenient facility to rest, wash and make repairs to trucks if re-
quired” is entirely spurious. There is already a similar facility under con-
struction approximately 10kms from the proposed site and several similar
facilities within a 30 km radius from the proposed facility.
30. Finally, on this issue, the applicant relies on projected growth in the area
while failing to inform the department that:
30.1. Much of that “growth” has been on the proverbial books for
years without becoming manifest – and is likely to remain so; and
30.2. Most of that “growth” is of a nature unlikely to increase the de-
mand for fuel in the area.
31. It is respectfully submitted that the failure of the applicant to undertake
a substantive socio-economic impact study is a fatal flaw in the process,
especially when it is borne in mind just how many existing filling stations
with facilities for long-distance drivers there already are serving traffic
along the N2, including those owned by our clients – the Draft BAR has
not even attempted to identify stations that will be affected.
32. A further problem is that the transformation of the industry in the area will
be fatally undermined because the existing filling stations will no longer
be attractive to BEE entrants due to non-profitability or low-profitability.
10
The proposed facility will cost more jobs than it will create.
33. The applicant’s claim that the proposed activity will create 200 new jobs
is completely unsubstantiated and appears to be nonsensical.
34. Filling stations are traffic interceptors. As such, they do not generate
“new” traffic and every litre of fuel sold at a new to market filling station
is effectively “taken” from an existing one.
35. Employment at filling stations, in turn, is directly related to sales volumes.
For every job created at a new to industry site, one is, consequently, lost
at an existing site. This situation becomes exponentially worse if any ex-
isting site were to become non-viable because of an over-proliferation
of filling stations.
The proposed filling station poses a potential danger to the public.
36. As any decent traffic flow audit would have shown, the location of the
site close to the N2 on a busy intersection on Seaview Road will, by defi-
nition, create a dangerous traffic situation and pose a potential danger
to motorists.
THE APPLICANT’S OWN HYDROGEOLOGICAL INVESTIGATION SHOWS THAT THE
PROPOSED SITE IS VULNERABLE TO GROUNDWATER CONTAMINATION.
37. On page 15 of the report under the heading “Aquifer Vulnerability”, the
applicant’s own consultants reach the following conclusions (own em-
phasis):
“For the Site, there may be a temporary shallow water table in the grav-
el layer. This water table may dry up during droughts, but will be present
during rainfall events and the rainy season. This water table is less than 2
m bgl, therefore the vulnerability of the aquifer will be very high.
11
The deeper, and more permanent groundwater level is expected
deeper than 10 m bgl; therefore the aquifer vulnerability is regarded to
be medium.
The permeability of the soils and unconsolidated material beneath the
Site will affect the flow rate at which potential pollutants can reach the
water table”.
38. To authorise an expanded facility or filling station for which no need has
been proven on an admittedly vulnerable site is entirely irreconcilable
with the peremptory constraint to caution prescribed by NEMA.
Conclusion.
39. The Revised Draft BAR as submitted remains an aberration which does
not remotely serve the purpose envisaged for the assessment process in
NEMA:
39.1. The activity is incorrectly described in a manner likely to mislead
members of the public;
39.2. The application is incomplete in that it omits and/or does not
deal with or provide adequate details regarding:
39.2.1. The previous unsuccessful application in terms of the
ECA;
39.2.2. The application for rectification in terms of section 24G;
39.2.3. The authorisation issued pursuant to that application;
39.2.4. Whether the terms and conditions of that authorisation
have been complied with;
12
39.2.5. Socio-economic impacts including impacts on existing
filling stations;
39.2.6. Consequential job-losses;
39.2.7. Negative impacts on transformation of the industry;
and/or
39.2.8. Whether there is a need for the proposed activity and
why is would be desirable.
40. In these circumstances it is submitted:
40.1. That the Revised Draft BAR does not contain sufficient information
for the department to make an informed decision other than to
finally deny the application;
40.2. That the application ought to be finally denied; alternatively
40.3. That the Draft BAR ought to be rejected and the applicant di-
rected to undertake a full Scoping and EIA process before the
application is considered for approval.
41. Kindly acknowledge receipt hereof.
Yours faithfully
G (Kallie) Erasmus
Erasmus
13