Upload
cassandra-douglas
View
215
Download
0
Embed Size (px)
Citation preview
Walter WuenschCLIC project meeting, 31 March 2015
Accelerating structure program: design and testing
Walter WuenschCLIC project meeting, 31 March 2015
Our current prototype structure designs date back to 2007/2008. There have been many important developments since then, with a cumulative effect which motivates launching a new set of prototypes.• Highlight the developments and the logic for designing new CLIC
baseline structures.• Review other new structures in the pipeline; baseline
alternatives, other applications and structures built by collaborators.
• Update the high-gradient testing program
Introduction
Walter WuenschCLIC project meeting, 31 March 2015
High-gradient data and analysis
Walter WuenschCLIC project meeting, 31 March 2015
Progress in understanding and feedback on rf design
Walter WuenschCLIC project meeting, 31 March 2015
LHC results, energy staging and rebaselining
Most efficient structure is very similar to CLIC_G
Walter WuenschCLIC project meeting, 31 March 2015
ConsequencesWe are now launching a new series of prototype baseline CLIC accelerating structures for high-gradient testing:
CLIC-G* - Optimized 3 TeV structure, new cell shape, constant ΔT, optimized damping features. Higher performance.
CLIC-G*-with-SiC – Smaller overall transverse size, revised mechanical design of vacuum manifolds, new loads. Simpler, cheaper design.
Two more are being defined but we don’t yet have final decisions:
CLIC-380 – Features as above but for entry energy, lower gradient but same rf constraints. Understanding, publicity, first structure needed.
CLIC-ST – Strongly tapered design. Depends on results of beam-loading experiment. Complex to understand but significant potential performance increase.
Walter WuenschCLIC project meeting, 31 March 2015
Timescale
• CLIC-G* and CLIC-G*-with-SiC – 2nd half 2016• CLIC- 380 - End 2016, early 2017• CLIC-ST - Hmmm
Quantities need to be decided before procurement.
Parametersfixed rf design
mechanical design procurement assembly
12-18 months
Walter WuenschCLIC project meeting, 31 March 2015
• Structure in halves by SLAC. Potentially cheaper, hard materials, preconditioned surfaces possible.
• Choke-mode damping by Tsinghua. Potentially cheaper
• Four XFEL structures by SINAP. New application with large potential.
• High-gradient proton funded by KT. New application.
Additional new accelerating structures
Walter WuenschCLIC project meeting, 31 March 2015
• Two TD26CC built and tested by KEK. Still unbeaten production!• One TD26CC built by CIEMAT. Next step after PETS.• Two T24s built by PSI in their production run. Vacuum brazing alternative,
benchmark for their production line.• One T24 built by SINAP. Potentially leads to large X-band installation.• Whole structure in industry – Technical specifications are under preparation.
Industrialization, cost estimate.
New accelerating structures in the pipeline built by collaborators
Walter WuenschCLIC project meeting, 31 March 2015
A now a look at our testing program
• XBox-1 and 2 clear since they run. • Delivery, installation, commissioning and testing for XBox-3 is work in progress. Big
job.• Steadily increasing testing capacity should more or less coincide with the arrival of
all the new structures.
NCL. 27.03.2015A M J J A S O N D J F M A M J J A S O N D
NEXTEF
ASTA
TBTS Slot 1
Slot 2
Xbox1 Dogleg
CTF2
Xbox2 Slot 1
Xbox3_a Slot 1
Slot 2
Xbox3_b Slot 3
Slot 4
2015 2016
TD26_CC_SiC_3 TD26_CC_SiC_5
Crab cavityKl. Repair and
full power testTD26_CC_2
CFT3 winter shutdown
TD26_CC_SiC_3 TD26_CC_SiC_5
TD26_CC_SiC_4 TD26_CC_SiC_6 TD26_CC_SiC_4 TD26_CC_SiC_6
TD26_CC_1
T24_1
CLICG'
RF comp. T24_2
Commissioning
TD26_CC_3
Half_SLAC_1
TD24_R05_SiC_1
RF components PS1#1
TD24_R05_SiC_2
FEL SINAP
T24_3
New
bas
elin
e str
uctu
res
Walter WuenschCLIC project meeting, 31 March 2015
Shorter Term Priorities
• Repeat TD26CC - Consolidate (finish) CLIC baseline point. Validate compact coupler design.
• First TD24-SiC in low-breakdown rate regime. Complements SiC structures in module.
• Repeat T24 – We have not been able to reproduce KEK T24 result with CERN (beam-loading) or Tsinghua (first try) fabrication. • Questions our fabrication quality• Means relative performance of damped/undamped still an open
question• Reference for XFEL
• Waveguide components; rf valve, 3D printed components, controlled fabrication. For once test before installing… Will use Toshiba klystrons during installation/commissioning of XBox-3.
Walter WuenschCLIC project meeting, 31 March 2015
Test stands status overview
• XBox-1 – T24, beam loading experiment ongoing and will continue.
• XBox-2 – Finish crab cavity, TD26CC next.• XBox-3 – Under preparation. • NEXTEF – Finish Tsinghua-built T24. KEK-built TD24R05
next.• ASTA – Commissioning clone of our NI-based control
system. KEK/SLAC-built TD24R05 installed and ready to go.
Walter WuenschCLIC project meeting, 31 March 2015
Conclusions
• New CLIC baseline structures are being designed and should begin to be ready for test late next year.
• New structures are also in the pipeline• baseline alternatives• built by collaborators• other applications
• XBox-1, XBox-2 and NEXTEF running and producing important results. XBox-3 coming on line during this year. Even ASTA is about to start up.
• Fabrication developments, pulsed dc, single cells, fundamental high-gradient studies, alternative materials another day.
Walter WuenschCLIC project meeting, 31 March 2015
Upcoming events