Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
July 31, 2017
VM HOLDING S.A.
TECHNICAL REPORT ON THEPRELIMINARY ECONOMIC ASSESSMENTOF THE ARIPUANÃ ZINC PROJECT,STATE OF MATO GROSSO, BRAZIL
NI 43-101 Report
Qualified Persons:Jason J. Cox, P.Eng.Sean D. Horan P.Geo.,Brenna J.Y. Scholey, P.Eng.Stephan Theben, Dipl.-Ing., SLR Consulting (Canada) Ltd.
RPA T55 University Ave. Suite 501 I Toronto, ON, Canada M5J 2H7 I + 1 (416) 947 0907 www.rpacan.com
Report Control Form
Document Title Technical Report on the Preliminary Economic Assessment of the Aripuanã Zinc Project, State of Mato Grosso, Brazil
Client Name & Address VM Holdings S.A. 43 ave John Fitzgerald Kennedy, 3rd floor Luxembourg L1855
Document Reference Project #2779
Status & Issue No.
FINAL Version
Issue Date July 31, 2017
Lead Author Jason J. Cox Sean Horan Brenna J.Y. Scholey Stephan Theben
(Signed) (Signed) (Signed) (Signed)
Peer Reviewer David J F Smith (Signed)
Project Manager Approval Jason J. Cox (Signed)
Project Director Approval Deborah A. McCombe (Signed)
Report Distribution Name No. of Copies
Client
RPA Filing 1 (project box)
Roscoe Postle Associates Inc. 55 University Avenue, Suite 501
Toronto, ON M5J 2H7 Canada
Tel: +1 416 947 0907 Fax: +1 416 947 0395
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page i
TABLE OF CONTENTS PAGE
1 SUMMARY ...................................................................................................................... 1-1 Executive Summary ....................................................................................................... 1-1 Economic Analysis ......................................................................................................... 1-5 Technical Summary ..................................................................................................... 1-11
2 INTRODUCTION ............................................................................................................. 2-1
3 RELIANCE ON OTHER EXPERTS ................................................................................. 3-1
4 PROPERTY DESCRIPTION AND LOCATION ................................................................ 4-1
5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY ............................................................................................................... 5-1
6 HISTORY ........................................................................................................................ 6-1
7 GEOLOGICAL SETTING AND MINERALIZATION .......................................................... 7-1 Regional Geology .......................................................................................................... 7-1 Local Geology ................................................................................................................ 7-4 Property Geology ........................................................................................................... 7-4 Mineralization ................................................................................................................ 7-7
8 DEPOSIT TYPES ............................................................................................................ 8-1
9 EXPLORATION ............................................................................................................... 9-1 1999-2002 Exploration ................................................................................................... 9-1 VMH Exploration ............................................................................................................ 9-2 Exploration Potential ...................................................................................................... 9-4
10 DRILLING .................................................................................................................... 10-1 Previous Drilling ........................................................................................................... 10-1 Recent Drilling ............................................................................................................. 10-2
11 SAMPLE PREPARATION, ANALYSES AND SECURITY ............................................ 11-1 Sampling Method and Approach .................................................................................. 11-1 Density Analysis .......................................................................................................... 11-1 Sample Preparation ..................................................................................................... 11-2 Sample Analysis .......................................................................................................... 11-2 Database Management ................................................................................................ 11-3 Sample Chain of Custody and Storage ........................................................................ 11-4 Quality Assurance/Quality Control ............................................................................... 11-4
12 DATA VERIFICATION ................................................................................................. 12-1 VMH ............................................................................................................................ 12-1 RPA Audit of Drill Hole Database ................................................................................. 12-2
13 MINERAL PROCESSING AND METALLURGICAL TESTING ..................................... 13-1 Introduction .................................................................................................................. 13-1
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page ii
Metallurgical Sampling ................................................................................................. 13-1 Metallurgical Testing .................................................................................................... 13-5 Summary ................................................................................................................... 13-30
14 MINERAL RESOURCE ESTIMATE ............................................................................. 14-1 Comparison with Previous Estimate ............................................................................. 14-3 Resource Database ..................................................................................................... 14-6 Topography ................................................................................................................. 14-6 Geological Interpretation .............................................................................................. 14-6 Capping of High Grades ............................................................................................ 14-12 Compositing ............................................................................................................... 14-16 Exploratory Data Analysis .......................................................................................... 14-18 Variography ............................................................................................................... 14-22 Block Model ............................................................................................................... 14-28 Interpolation STrategy ................................................................................................ 14-30 Net Smelter Return Cut-Off Value .............................................................................. 14-33 Classification ............................................................................................................. 14-37 Validation ................................................................................................................... 14-41
15 MINERAL RESERVE ESTIMATE ................................................................................ 15-1
16 MINING METHODS ..................................................................................................... 16-1 Introduction .................................................................................................................. 16-1 Mine Design ................................................................................................................. 16-1 Mining Method ............................................................................................................. 16-7 Geomechanics and Ground Support ............................................................................ 16-8 Mine Infrastructure ..................................................................................................... 16-10 Mine Equipment ......................................................................................................... 16-13 Life of Mine Plan ........................................................................................................ 16-14
17 RECOVERY METHODS .............................................................................................. 17-1 Process Description ..................................................................................................... 17-1
18 PROJECT INFRASTRUCTURE .................................................................................. 18-1 Waste Production ........................................................................................................ 18-1 Power Supply .............................................................................................................. 18-5 Water Supply ............................................................................................................... 18-5
19 MARKET STUDIES AND CONTRACTS ...................................................................... 19-1 Markets ........................................................................................................................ 19-1 Contracts ..................................................................................................................... 19-1
20 ENVIRONMENTAL STUDIES, PERMITTING, AND SOCIAL OR COMMUNITY IMPACT ......................................................................................................................................... 20-1
Environmental and Social Setting ................................................................................ 20-1 Environmental Studies ................................................................................................. 20-2 Project Permitting ........................................................................................................ 20-5 Social or Community Requirements ............................................................................. 20-5 Mine Closure Requirements ......................................................................................... 20-6 Key Issues and Recommendations for Future Work .................................................... 20-6
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page iii
21 CAPITAL AND OPERATING COSTS .......................................................................... 21-1 Capital Costs ............................................................................................................... 21-1 Operating Costs ........................................................................................................... 21-2
22 ECONOMIC ANALYSIS............................................................................................... 22-1
23 ADJACENT PROPERTIES .......................................................................................... 23-1
24 OTHER RELEVANT DATA AND INFORMATION ........................................................ 24-1
25 INTERPRETATION AND CONCLUSIONS .................................................................. 25-1
26 RECOMMENDATIONS................................................................................................ 26-1
27 REFERENCES ............................................................................................................ 27-1
28 DATE AND SIGNATURE PAGE .................................................................................. 28-1
29 CERTIFICATE OF QUALIFIED PERSON .................................................................... 29-1
LIST OF TABLES PAGE
Table 1-1 2018 Project Advancement Budget ................................................................... 1-5 Table 1-2 After-Tax Cash Flow Summary ......................................................................... 1-7 Table 1-3 Sensitivity AnalyseS ....................................................................................... 1-10 Table 1-4 Mineral Resource Statement, December 23, 2016 .......................................... 1-14 Table 1-5 Pre-Production Capital Cost Estimate ............................................................. 1-18 Table 1-6 Operating Cost Estimate ................................................................................. 1-19 Table 4-1 Exploration Authorization Permits ..................................................................... 4-2 Table 4-2 Royalty Data ..................................................................................................... 4-6 Table 9-1 Anglo American and Karmin Exploration – 1999-2002 ...................................... 9-1 Table 10-1 Drill Hole Database ....................................................................................... 10-1 Table 11-1 Expected Values and Ranges of Standards .................................................. 11-7 Table 11-2 Expected Values and Ranges of Standards ................................................ 11-11 Table 11-3 Expected Values and Ranges of Standards ................................................ 11-11 Table 11-4 List of Reference Standards Used .............................................................. 11-15 Table 12-1 Summary of Re-analysis ............................................................................... 12-1 Table 13-1 Phase 1 - LCT 2 Results ............................................................................... 13-6 Table 13-2 CWi Results .................................................................................................. 13-8 Table 13-3 SMC Results ................................................................................................. 13-8 Table 13-4 SPI Results ................................................................................................... 13-9 Table 13-5 BWi Results ................................................................................................ 13-10 Table 13-6 Ai Results ................................................................................................... 13-11 Table 13-7 RWi Results ................................................................................................ 13-11 Table 13-8 Summary of Key Optimization LCT Results ................................................ 13-14 Table 13-9 LCT 028 Conditions and Results– Arex Stratabound Master Composite..... 13-16 Table 13-10 LCT 011 Conditions and Results– Arex Stringer Master Composite ......... 13-17 Table 13-11 LCT 025 Conditions and Results– Arex Stringer Master Composite ......... 13-18 Table 13-12 LCT 030 Conditions and Results– Arex Mix (75% Stratabound, 25% Stringer) ....................................................................................................................................... 13-19
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page iv
Table 13-13 LCT 009 Conditions and Results– Ambrex Stratabound Master Composite ....... ....................................................................................................................................... 13-20 Table 13-14 LCT 029 Conditions and Results– Ambrex Stratabound Master Composite ....... ....................................................................................................................................... 13-21 Table 13-15 Comparison of Metallurgical Data ............................................................. 13-23 Table 13-16 Summary of Settling Tests Using Magnafloc 10 Flocculant (3 g/t) ............. 13-26 Table 13-17 Summary of Filtration Test Work Conducted by ANDRITZ ........................ 13-30 Table 14-1 Mineral Resource Statement, December 23, 2016 ........................................ 14-2 Table 14-2 Mineral Resources by Type and Area, December 23, 2016 .......................... 14-3 Table 14-3 Comparison Between Current and October 20, 2016 Estimates ................... 14-5 Table 14-4 Grade Capping Levels ................................................................................ 14-13 Table 14-5 Uncapped versus Capped Assay Statistics ................................................. 14-14 Table 14-6 Composite Statistics ................................................................................... 14-17 Table 14-7 Wireframe Grouping for Variography and Search Parameters .................... 14-19 Table 14-8 Block Model Setup ...................................................................................... 14-28 Table 14-9 Block Model Attribute Descriptions .............................................................. 14-29 Table 14-10 Sample Selection Strategy ........................................................................ 14-30 Table 14-11 NSR Factors ............................................................................................. 14-35 Table 14-12 Sensitivity to Cut-off Grade - Stratabound ................................................. 14-36 Table 14-13 Sensitivity to Cut-off Grade - Stringer ........................................................ 14-36 Table 14-14 VMH Search Ellipse Ranges for Classification Criteria .............................. 14-38 Table 14-15 Comparison Between OK, NN and Composite Means (Zn and Cu) .......... 14-41 Table 16-1 Development Dimensions ............................................................................. 16-6 Table 16-2 LOM Total Development ............................................................................... 16-6 Table 16-3 Equipment Fleet .......................................................................................... 16-13 Table 16-4 Advance Rates ........................................................................................... 16-14 Table 16-5 Summary Mine Schedule ............................................................................ 16-16 Table 21-1 Pre-Production Capital Cost Estimate ........................................................... 21-1 Table 21-2 Sustaining Capital Cost Estimate .................................................................. 21-2 Table 21-3 Operating Cost Estimate ............................................................................... 21-3 Table 22-1 After-Tax Cash Flow Summary ..................................................................... 22-3 Table 22-2 Sensitivity Analyses ...................................................................................... 22-6 Table 26-1 2018 Project Advancement Budget ............................................................... 26-2
LIST OF FIGURES PAGE
Figure 1-1 Sensitivity Analysis ........................................................................................ 1-10 Figure 4-1 Location Map ................................................................................................... 4-3 Figure 4-2 Property Map ................................................................................................... 4-4 Figure 4-3 Surface Rights Map ......................................................................................... 4-7 Figure 7-1 Regional Geology ............................................................................................ 7-2 Figure 7-2 Geological Map of the Amazonian Shield ........................................................ 7-3 Figure 7-3 Property Geology ............................................................................................. 7-6 Figure 8-1 Target Model ................................................................................................... 8-2 Figure 10-1 Drill Hole Collar Map .................................................................................... 10-4 Figure 11-1 Blank Results for Zinc, Lead and Copper ..................................................... 11-6 Figure 11-2 Control Chart for CRM AP0002: Lead .......................................................... 11-8 Figure 11-3 Control Chart for CRM AP0001: Zinc ........................................................... 11-8
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page v
Figure 11-4 Percent Relative Difference Plot: Zinc Duplicate Samples ........................... 11-9 Figure 11-5 Blank Results for Zinc, Lead and Copper ................................................... 11-10 Figure 11-6 Control Chart for CRM AP0002: Lead ........................................................ 11-12 Figure 11-7 Control Chart for CRM AP0001: Lead ........................................................ 11-13 Figure 11-8 Control Chart for CRM AP0001: Zinc ......................................................... 11-13 Figure 11-9 Percent Relative Difference Plot: Zinc Duplicate Samples ......................... 11-14 Figure 11-10 Control Chart for CRM G312-4: Gold ....................................................... 11-17 Figure 11-11 Control Chart for Internal Standard APPD0003: Zinc ............................... 11-17 Figure 11-12 Control Chart for Internal Standard APPD0004: Lead .............................. 11-18 Figure 11-13 Control Chart for Internal Standard APPD0003: Copper .......................... 11-18 Figure 11-14 Percent Relative Difference Plot: Zinc Duplicate Samples ....................... 11-19 Figure 12-1 Density Measurements at Ambrex by Rock Unit .......................................... 12-4 Figure 12-2 Density Measurements at Arex by Rock Unit ............................................... 12-5 Figure 13-1 Location of Arex Metallurgical Samples ....................................................... 13-3 Figure 13-2 Location of Ambrex Metallurgical Samples .................................................. 13-4 Figure 13-3 Simplified Sequential Flotation Circuit ........................................................ 13-13 Figure 13-4 Variation of Metal Assays in Flotation Products ......................................... 13-27 Figure 13-5 Variation of Metal Assays in Flotation Products ......................................... 13-28 Figure 13-6 Yield Stress vs. Solids Percentage ............................................................ 13-29 Figure 13-7 Viscosity vs. Solids Percentage ................................................................. 13-29 Figure 14-1 3D Isometric View of Geological Wireframes ............................................... 14-9 Figure 14-2 Ambrex Geological Model .......................................................................... 14-10 Figure 14-3 Arex Geological Model ............................................................................... 14-11 Figure 14-4 Capping Analysis for Body=4 (Ambrex StrataBound) ................................. 14-15 Figure 14-5 Cu Capping Analysis for Body=116 (Arex Stringer) ................................... 14-16 Figure 14-6 Histograms for Assay (left) and Composite (right) Lengths ........................ 14-18 Figure 14-7 Arex Stratabound Contact Analysis ........................................................... 14-20 Figure 14-8 Correlation Matrices for Ambrex and Arex (STB=Stratabound, STR=Stringer) ....................................................................................................................................... 14-21 Figure 14-9 Zn and Cu Statistics by Body and Group ................................................... 14-22 Figure 14-10 Arex Stratabound, Group 21 Zn Directional Variograms .......................... 14-23 Figure 14-11 Ambrex Link Zone Stratabound, Group 3 Zn Directional Variograms ....... 14-24 Figure 14-12 Arex Stringer, Group 36 Zn Directional Variograms ................................. 14-25 Figure 14-13 Relative Nugget Effect Stratabound ......................................................... 14-26 Figure 14-14 RElative Nugget Effect Stratabound ........................................................ 14-26 Figure 14-15 Variogram Ranges Stratabound ............................................................... 14-27 Figure 14-16 Variogram Ranges Stringer ..................................................................... 14-27 Figure 14-17 Search Ranges for Zn Stratabound ......................................................... 14-32 Figure 14-18 Search Ranges for Cu Stringer ................................................................ 14-33 Figure 14-19 Global Variograms Used for Classification Criteria................................... 14-39 Figure 14-20 Final Classification Designation ............................................................... 14-40 Figure 14-21 Comparison Between OK and NN Means (Zn Stratabound) .................... 14-42 Figure 14-22 Comparison Between OK and NN Means (Cu Stringer) ........................... 14-42 Figure 14-23 Arex Zn Swath Plot – Easting .................................................................. 14-43 Figure 14-24 Arex Cu Swath Plot – Easting .................................................................. 14-43 Figure 14-25 Ambrex Zn Swath Plot – Easting ............................................................. 14-44 Figure 14-26 Ambrex Cu Swath Plot – Easting ............................................................. 14-44 Figure 14-27 Arex Vertical Section Showing Zn Block Versus Composite Grades ....... 14-45 Figure 14-28 Arex Vertical Section Showing Cu Block Versus Composite Grades ...... 14-46 Figure 14-29 Ambrex Vertical Section Showing Zn Block Versus Composite Grades .. 14-47 Figure 14-30 Ambrex Vertical Section Showing Cu Block Versus Composite Grades .. 14-48 Figure 14-31 Global Change of Support Check for Bodies 53, 54 and 80 ..................... 14-50
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page vi
Figure 16-1 Mine Layout of Both Deposits ...................................................................... 16-3 Figure 16-2 Layout of Ambrex ........................................................................................ 16-4 Figure 16-3 Layout of Arex ............................................................................................. 16-5 Figure 17-1 Simplified Process Flow Sheet .................................................................... 17-2 Figure 18-1 General Site Plan and Proposed TMF Sites for Option 10A ......................... 18-3 Figure 18-2 TMF Conceptual Design .............................................................................. 18-4 Figure 22-1 Sensitivity Analysis ...................................................................................... 22-6
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-1
1 SUMMARY EXECUTIVE SUMMARY Roscoe Postle Associates Inc. (RPA) was retained by VM Holding S.A. (VMH) to prepare an
independent Technical Report on the Aripuanã Zinc Project (the Project), located in the state
of Mato Grosso, Brazil. The purpose of this report is to audit a Mineral Resource estimate and
to disclose the results of a Preliminary Economic Assessment (PEA) of the Project. This
Technical Report conforms to NI 43-101 Standards of Disclosure for Mineral Projects. RPA
visited the property on June 2 and 5, 2017 and January 30 to February 2, 2017.
The Aripuanã Zinc property is owned by Mineração Dardanelos Ltda. (Dardanelos), a joint
venture between Votorantim Metais Zinco SA (VMZ, a subsidiary of VMH, 62.3%), Compañía
Minera - Milpo S.A.A. (Milpo, 7.7%), and Mineração Rio Aripuanã (a subsidiary of Karmin
Exploration Inc. (Karmin, 30%)), with VMH acting as the operator through VMZ.
To date, the focus of exploration activities on the property has been the Ambrex and Arex
deposits, which are the only two deposits that contain current Mineral Resources. As a result
of drilling between 2014 and 2016, a zone connecting the two deposits, the Link Zone, was
delineated. The Link Zone is considered to be a westward extension of Ambrex and is
therefore included in the Mineral Resources of that deposit.
In March 2017, RPA completed a NI 43-101 Technical Report on the Project dated March 1,
2017 for VMH’s joint venture partner Karmin. Additional drilling and a resource model update
have been carried out since the effective date of the Mineral Resource summarized in that
report.
This report is considered by RPA to meet the requirements of a Preliminary Economic
Assessment as defined in Canadian NI 43-101 regulations. The economic analysis contained
in this report is based, in part, on Inferred Resources, and is preliminary in nature. Inferred
Resources are considered too geologically speculative to have mining and economic
considerations applied to them and to be categorized as Mineral Reserves. There is no
certainty that economic forecasts on which this PEA is based will be realized.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-2
CONCLUSIONS The Project merits further work to improve economic outcomes, including completion of an
advanced engineering study.
RPA offers the following conclusions for each area:
GEOLOGY AND MINERAL RESOURCES
• The Aripuanã Zinc deposits are located within the central-southern portion of the Amazonian Craton, in which Paleoproterozoic and Mesoproterozoic lithostratigraphic units of the Rio Negro-Juruena province (1.80 Ga to 1.55 Ga) predominate.
• The Aripuanã Zinc polymetallic deposits are typical Volcanogenic Massive Sulphide (VMS) deposits associated with felsic bimodal volcanism. Three main elongate mineralized zones, Arex, Link, and Ambrex, have been defined in the central portion of the Project. A smaller, deeper zone, Babaçú, lies to the south of Ambrex.
• The drilling, sampling, sample preparation, analysis, and data verification procedures are appropriate for the estimation of Mineral Resources.
• As prepared by VMH and adopted by RPA, the Aripuanã Measured and Indicated Mineral Resources comprise 21.8 million tonnes (Mt) at 4.8% Zn, 1.8% Pb, 0.3% Cu, 0.4 g/t Au, and 45 g/t Ag for 2.3 billion pounds of Zn, 852 million pounds of Pb, 158 million pounds of Cu, 279,000 ounces of Au, and 31 million ounces of Ag. The Aripuanã Inferred Mineral Resources comprise 24.6 Mt at 3.9% Zn, 1.5% Pb, 0.42% Cu, 0.93 g/t Au, and 38 g/t Ag for 2.1 billion pounds of Zn, 829 million pounds of Pb, 226 million pounds of Cu, 732,000 ounces of Au, and 30 million ounces of Ag.
• The Mineral Resource estimate is consistent with the Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserves dated May 10, 2014 (CIM definitions) as incorporated by reference into NI 43-101.
• Limited exploration has identified additional, possible mineralized bodies including Massaranduba, Boroca, and Mocoto to the south and Arpa to the north.
MINING
• The deposits support a production rate of 1.8 million tonnes per annum (Mtpa), however, several years are required to advance ramps and development sufficiently to access the required number of workplaces.
• The large resource base provides a long mine life (24 years). There may be opportunities to be more selective in the mining of high-grade areas in the early years of the Life of Mine (LOM), to improve capital payback.
• Deposit geometry and geomechanical properties are amenable to bulk longhole mining methods, with some cut and fill mining in narrower areas.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-3
• Dilution and extraction estimates appear reasonable, ranging from 5% to 12% (dilution) and 90% to 95% (extraction). There is a risk of poorer recovery and additional dilution in flat-dipping stopes (below 50°).
• Arex and Ambrex deposits are not connected until later in the mine life, making it difficult to share the mobile equipment fleet efficiently. More units may be required in the early years.
• The issues identified above can be addressed in the next stage of study. PROCESS
• The results from recent SGS GEOSOL metallurgical testing form the current basis for engineering design of the sequential Cu/Pb/Zn flotation circuit.
• Separation of material types is necessary to improve copper recovery and to reduce costs, particularly when processing Copper Stringer material. Since Copper Stringer mineralization does not have significant zinc and lead grades, copper processing should be separate for flotation and filtration and it is expected that the lead and zinc circuits will be bypassed.
• To process Arex and Ambrex Stratabound mineralization, talc removal by flotation is required prior to sequential flotation of Cu, Pb, and Zn.
• Data for the final concentrate grades and recoveries for Arex and Ambrex mineralization in the Aripuanã LOM financial model did not rely consistently on metallurgical test data. The assumptions for the concentrate grades and recoveries for Ambrex Stringer and Ambrex Mixed materials were based on identical LOM assumed data for Arex mineralization and not on any metallurgical test results.
• The presence or absence of any deleterious elements that could impact extraction have not yet been clearly identified through metallurgical testing.
ENVIRONMENTAL CONSIDERATIONS
• The Environmental Impact Assessment (EIA), currently being finalized by VMH, is compliant with Brazilian standards and regulation needs for the current stage of the Project. As the Project is advanced, more detailed EIA submissions will be required with regard to the following: o Establishing existing environmental and socio-economic conditions in the Project
area and the influence on the Project. o Predicting Project effects. o Specifying and detailing mitigation measures to prevent any significant impacts. o Detailing future monitoring and management activities of the Project. o Continuing baseline data collection. This will also include community and
stakeholder consultation and impact generated by the Project in each area. o Testing to determine geochemistry baseline data. o Confirming that there are no fauna or flora species of importance or any
endangered or threatened species affected by the Project. o An ecological and human health risk assessment should be carried out, with the
aim of identifying if water quality, air quality, and noise combined with local uses of
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-4
the areas have the potential of affecting the health of local wildlife, feedstock, and/or the local population.
o Completing plans for site closure and reclamation.
COSTS AND ECONOMICS
• Pre-production capital costs total US$355 million.
• In RPA’s opinion, the capital cost estimate can be classified as Class 4, per American Association of Cost Engineers (AACE) guidelines, which generally corresponds to pre-feasibility studies.
• Contingency comprises 7% of direct and indirect capital costs, which RPA considers to be low for the current stage of the Project.
• Operating costs average US$38.43 per tonne over the LOM, with higher unit costs at the start and end when full production is not achievable.
• Economic results are adversely affected by a relatively long ramp-up to full production. Optimization of the mine design and schedule will help to improve the Project economics.
RECOMMENDATIONS RPA offers the following recommendations for each area:
GEOLOGY AND MINERAL RESOURCES
• Increase the wireframe modelling cut-off grade to limit the amount of sub-economic material not related to massive or disseminated sulphides in the stratabound zone in the wireframes.
• Substitute zeroes for unsampled intervals.
• Model correlograms to avoid fitting long second and third variogram model structures when an apparent zonal anisotropy is observed.
• Perform a visual review of the classification of all blocks with a minimum distance to the closest drill hole greater than 25 m, and consider downgrading blocks where appropriate to Inferred.
MINING
• Use only Measured and Indicated Resources at the next stage of study.
• Optimizing the ramp-up to full production will help improve economic outcomes. PROCESS
• Reference the metallurgical test data for the final concentrate grades and recoveries and report the assays of any penalty elements for Arex and Ambrex mineralization.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-5
• Further examine any deleterious elements (e.g., potential tremolite material) that could have a significant effect on potential economic extraction.
• Carry out additional test work to develop and optimize Zn/Pb recovery circuits on Ambrex mineralization, to conduct additional mineralogical analysis, to extend the variability analysis to a full geometallurgical program using samples from different locations in the deposits, and to conduct pilot plant test work to confirm the performance of the circuit selected.
INFRASTRUCTURE
• Complete a review of the acid base accounting (ABA) program test results for both the tailings and waste rock and assess the conceptual design of the Tailings Management Facility (TMF) sites based on the ABA test results.
• The next stage of design of the TMF should assess slope stability and geotechnical parameters based on current laboratory test results on grind size and talc content.
ENVIRONMENTAL AND SOCIAL CONSIDERATIONS
• Update the EIA in parallel with the next stage of study on the Project.
• Continue collection of baseline data. RECOMMENDED BUDGET A 2018 budget for field work, testing, and a Feasibility Study is summarized in Table 1-1.
TABLE 1-1 2018 PROJECT ADVANCEMENT BUDGET VM Holding S.A. – Aripuanã Zinc Project
Item Units Cost
Exploration Drilling US$ millions 5.0 Metallurgical Testwork US$ millions 1.0 VMH Project Team US$ millions 3.0 Feasibility Study US$ millions 2.0 Total US$ millions 11.0
ECONOMIC ANALYSIS The economic analysis contained in this report is based, in part, on Inferred Resources, and
is preliminary in nature. Inferred Resources are considered too geologically speculative to
have mining and economic considerations applied to them and to be categorized as Mineral
Reserves. There is no certainty that economic forecasts on which this Preliminary Economic
Assessment is based will be realized.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-6
RPA has generated a Cash Flow Projection from the LOM production schedule and capital
and operating cost estimates, and this is summarized in Table 1-2. A summary of the key
criteria is provided below.
ECONOMIC CRITERIA REVENUE
• LOM processing of 37 Mt, grading 4.06% Zn, 1.59% Pb, 0.33% Cu, 39 g/t Ag, and 0.61 g/t Au.
• LOM average metallurgical recovery of 82% Zn, 82% Pb, 86% Cu, 66% Ag, and 82% Au.
• LOM average metal payable of 84% Zn, 95% Pb, 96% Cu, 77% Ag, and 87% Au.
• LOM payable metal of 1,028 kt Zn, 459 kt Pb, 101 kt Cu, 23,638 koz Ag, and 529 koz Au.
• LOM metal prices based on forward-looking independent forecasts, averaging US$1.06/lb Zn, US$0.88/lb Pb, US$2.74/lb Cu, US$18.95/oz Ag, and US$1,278/oz Au.
• All revenues are received in US$.
• Total gross revenue of US$5,024 million.
• Total offsite treatment, transportation, and refining charges of US$1,383 million.
• Total royalties of US$192 million.
• Net revenue of US$3,449 million.
• Average unit net revenue of US$93/t processed.
• Revenue is recognized at the time of production.
COSTS
• Pre-production period: 24 months.
• Mine life: 24 years.
• Life of Mine production plan as summarized in Section 16.
• Pre-production capital totals US$354.3 million.
• Sustaining capital over the LOM totals US$229.0 million.
• Average operating cost over the mine life is US$38.43 per tonne processed.
Date:INPUTS UNITS TOTAL 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044
MININGUnderground
Operating Days 350 days 8,400 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 Tonnes milled per day tonnes / day 765 1,639 2,581 3,912 5,090 5,139 5,132 5,162 5,199 5,187 5,206 5,070 5,147 5,126 5,182 5,161 5,187 5,177 5,191 5,206 4,437 4,664 3,738 1,451 598
Production '000 tonnes 36,953 574 903 1,369 1,781 1,798 1,796 1,807 1,819 1,815 1,822 1,774 1,802 1,794 1,814 1,806 1,815 1,812 1,817 1,822 1,553 1,632 1,308 508 209 Zn Grade % 4.06% 4.98% 3.73% 3.96% 4.03% 4.36% 3.97% 3.59% 2.31% 3.55% 2.87% 4.63% 3.95% 7.84% 6.59% 5.09% 3.61% 3.81% 3.85% 2.89% 3.34% 3.25% 3.49% 3.48% 3.24%Pb Grade % 1.59% 1.71% 1.24% 1.38% 1.70% 1.76% 1.76% 1.40% 0.81% 1.24% 1.02% 2.19% 1.69% 3.44% 3.13% 2.01% 1.36% 1.31% 1.35% 1.05% 1.14% 1.01% 1.03% 1.22% 1.12%Cu Grade % 0.33% 0.60% 0.71% 0.35% 0.26% 0.16% 0.19% 0.27% 0.49% 0.37% 0.61% 0.52% 0.35% 0.17% 0.23% 0.31% 0.27% 0.26% 0.41% 0.41% 0.27% 0.27% 0.10% 0.05% 0.02%Ag Grade g/t 39 53 44 38 46 50 47 39 23 32 29 50 39 76 66 53 36 33 29 27 26 20 22 25 27Au Grade g/t 0.61 0.42 0.52 0.38 0.35 0.22 0.25 0.36 0.60 0.55 0.69 0.62 0.75 0.79 0.89 0.64 1.73 0.74 0.62 0.72 0.53 0.62 0.20 0.22 0.21
PROCESSING
Mill Feed '000 tonnes 36,953 574 903 1,369 1,781 1,798 1,796 1,807 1,819 1,815 1,822 1,774 1,802 1,794 1,814 1,806 1,815 1,812 1,817 1,822 1,553 1,632 1,308 508 209Zn Grade % 4.06% 4.98% 3.73% 3.96% 4.03% 4.36% 3.97% 3.59% 2.31% 3.55% 2.87% 4.63% 3.95% 7.84% 6.59% 5.09% 3.61% 3.81% 3.85% 2.89% 3.34% 3.25% 3.49% 3.48% 3.24%Pb Grade % 1.59% 1.71% 1.24% 1.38% 1.70% 1.76% 1.76% 1.40% 0.81% 1.24% 1.02% 2.19% 1.69% 3.44% 3.13% 2.01% 1.36% 1.31% 1.35% 1.05% 1.14% 1.01% 1.03% 1.22% 1.12%Cu Grade % 0.33% 0.60% 0.71% 0.35% 0.26% 0.16% 0.19% 0.27% 0.49% 0.37% 0.61% 0.52% 0.35% 0.17% 0.23% 0.31% 0.27% 0.26% 0.41% 0.41% 0.27% 0.27% 0.10% 0.05% 0.02%Ag Grade g/t 39 53 44 38 46 50 47 39 23 32 29 50 39 76 66 53 36 33 29 27 26 20 22 25 27Au Grade g/t 0.61 0.42 0.52 0.38 0.35 0.22 0.25 0.36 0.60 0.55 0.69 0.62 0.75 0.79 0.89 0.64 1.73 0.74 0.62 0.72 0.53 0.62 0.20 0.22 0.21 Contained Zn '000 tonnes 1,500 29 34 54 72 78 71 65 42 64 52 82 71 141 120 92 66 69 70 53 52 53 46 18 7Contained Pb '000 tonnes 587 10 11 19 30 32 32 25 15 23 19 39 30 62 57 36 25 24 24 19 18 17 13 6 2Contained Cu '000 tonnes 120 3 6 5 5 3 3 5 9 7 11 9 6 3 4 6 5 5 8 7 4 4 1 0 0Contained Ag koz 46,852 971 1,285 1,685 2,628 2,865 2,727 2,243 1,328 1,840 1,723 2,847 2,273 4,386 3,836 3,060 2,077 1,924 1,691 1,601 1,294 1,060 917 406 183 Contained Au koz 725 8 15 17 20 13 14 21 35 32 41 35 44 46 52 37 101 43 36 42 27 33 9 4 1
Net RecoveryZn 82% 82% 81% 82% 82% 82% 82% 82% 81% 82% 81% 82% 82% 82% 82% 82% 82% 82% 81% 82% 82% 82% 82% 82% 82%Pb 82% 82% 82% 83% 83% 83% 82% 82% 80% 81% 82% 83% 82% 83% 83% 83% 82% 82% 82% 82% 82% 83% 83% 83% 83%Cu 86% 79% 83% 81% 86% 83% 86% 86% 92% 89% 93% 93% 90% 85% 90% 83% 80% 87% 83% 87% 85% 84% 81% 79% 68%Ag 66% 87% 81% 71% 62% 62% 62% 64% 66% 64% 66% 62% 64% 61% 61% 65% 68% 68% 79% 72% 67% 64% 60% 60% 60%Au 82% 78% 83% 81% 80% 73% 75% 81% 89% 83% 87% 82% 86% 79% 83% 81% 89% 86% 83% 87% 82% 83% 71% 69% 64%
Concentrate ProductionZn Concentrate '000 tonnes 2,499 47 55 90 120 131 119 108 69 107 87 138 119 236 201 153 109 115 115 87 87 89 77 30 11
Zn % 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49%Ag g/t 61 55 65 60 75 76 80 70 53 55 57 66 61 65 66 67 62 52 41 53 47 39 42 49 58
Pb Concentrate '000 tonnes 774 13 15 25 40 42 42 34 19 29 25 51 40 82 75 48 33 31 32 25 23 22 18 8 3Pb % 62% 62% 62% 62% 63% 63% 63% 62% 62% 63% 62% 63% 62% 63% 63% 62% 62% 63% 62% 62% 62% 62% 63% 63% 63%Ag g/t 723 1,137 1,235 888 784 826 774 803 702 711 739 595 641 639 595 781 797 744 708 769 660 552 610 585 705 Au g/t 2.75 1.99 3.12 2.71 2.15 2.05 2.03 2.68 2.29 3.45 3.42 2.35 2.32 2.44 2.10 3.12 3.63 2.70 3.29 3.06 3.74 5.35 3.52 3.35 4.31
Cu Concentrate '000 tonnes 379 10 19 13 14 9 11 15 30 22 38 31 21 10 14 17 14 15 22 23 13 13 4 1 0Cu % 27.6% 27.8% 28.4% 28.5% 27.6% 27.7% 27.6% 27.8% 27.4% 27.4% 27.4% 27.3% 27.5% 27.2% 27.2% 28.3% 28.3% 27.3% 27.7% 27.5% 27.4% 27.8% 27.2% 27.0% 26.8%Ag g/t 636 903 576 704 722 1,244 972 676 340 453 330 486 606 1,601 1,024 809 774 784 621 510 556 413 826 1,828 5,605 Au g/t 44.29 16.65 18.60 26.02 28.26 23.54 23.35 28.70 30.51 33.92 26.80 25.20 52.02 94.14 84.58 47.57 192.25 71.57 36.75 45.83 45.53 54.53 33.05 70.65 151.17
Concentrate Moisture 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%
Total RecoveredZn '000 tonnes 1,228 23 27 44 59 64 58 53 34 53 43 67 58 116 98 75 54 57 57 43 43 44 38 15 6Pb '000 tonnes 483 8 9 16 25 26 26 21 12 18 15 32 25 51 47 30 20 19 20 16 15 14 11 5 2Cu '000 tonnes 105 3 5 4 4 2 3 4 8 6 10 9 6 3 4 5 4 4 6 6 4 4 1 0 0Ag koz 30,643 840 1,044 1,197 1,631 1,780 1,679 1,434 879 1,171 1,144 1,760 1,462 2,677 2,322 1,975 1,402 1,313 1,335 1,156 864 675 552 243 109 Au koz 608 6 13 13 16 9 11 17 31 27 35 29 38 36 43 30 91 37 30 37 22 27 6 3 1
REVENUEMetal Prices
Zn 2,338 US$/lb 1.06$ 1.09$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ Pb 1,933 US$/lb 0.88$ 0.89$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ Cu 6,042 US$/lb 2.74$ 2.73$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ Ag 18.91 US$/oz 18.95$ 19.31$ 19.45$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ Au 1,276 US$/oz 1,278$ 1,294$ 1,297$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$
Exchange Rate $3.30 R$/US$ $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30
Concentrate Payable %Zn % 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84%Pb % 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%Cu % 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96%Ag % 77% 84% 82% 79% 76% 76% 76% 77% 78% 77% 78% 76% 77% 75% 74% 77% 78% 79% 81% 80% 77% 76% 74% 74% 74%Au % 87% 85% 87% 86% 84% 79% 80% 85% 88% 88% 89% 86% 87% 85% 86% 86% 89% 88% 88% 88% 88% 89% 84% 83% 84%
Payable MetalZn '000 tonnes 1,028 19.5 22.9 37.2 49.3 53.9 48.8 44.5 28.4 44.0 35.7 56.4 48.8 96.9 82.3 63.1 45.0 47.3 47.7 36.0 35.7 36.5 31.5 12.2 4.7Pb '000 tonnes 459 7.6 8.7 14.9 23.7 24.9 24.8 19.8 11.3 17.4 14.6 30.4 23.7 48.6 44.5 28.5 19.2 18.5 18.9 14.9 13.9 12.9 10.6 4.9 1.8Cu '000 tonnes 101 2.6 5.1 3.7 3.8 2.3 2.8 4.0 8.0 5.7 9.9 8.2 5.5 2.6 3.7 4.5 3.8 3.9 6.0 6.2 3.4 3.6 1.0 0.2 0.0Ag koz 23,638 702 859 947 1,237 1,356 1,272 1,102 689 897 892 1,330 1,125 1,999 1,724 1,518 1,098 1,033 1,085 925 669 510 409 179 81Au koz 529 5.1 11.0 11.5 13.3 7.3 8.6 14.3 27.5 23.5 31.2 25.1 33.0 30.6 37.1 26.2 80.8 32.8 26.3 32.7 19.3 24.1 5.1 2.1 0.8
Gross RevenueZn US$ '000 $2,405,464 $47,047 $53,536 $87,085 $115,179 $126,085 $114,170 $103,971 $66,376 $102,791 $83,403 $131,926 $114,129 $226,655 $192,528 $147,436 $105,153 $110,618 $111,510 $84,245 $83,394 $85,259 $73,559 $28,499 $10,911Pb US$ '000 $887,469 $14,962 $16,738 $28,731 $45,839 $48,042 $47,988 $38,346 $21,757 $33,572 $28,126 $58,838 $45,861 $93,858 $86,104 $55,020 $37,119 $35,792 $36,583 $28,860 $26,878 $25,017 $20,431 $9,440 $3,569Cu US$ '000 $607,550 $15,729 $30,642 $22,237 $23,222 $14,004 $17,213 $24,208 $48,119 $34,401 $60,013 $49,592 $33,170 $15,531 $22,249 $27,385 $23,040 $23,729 $36,131 $37,345 $20,778 $21,565 $5,972 $1,121 $153Ag US$ '000 $447,746 $13,561 $16,706 $17,917 $23,390 $25,642 $24,055 $20,838 $13,027 $16,953 $16,875 $25,159 $21,270 $37,794 $32,604 $28,714 $20,763 $19,531 $20,516 $17,492 $12,651 $9,651 $7,725 $3,378 $1,534Au US$ '000 $675,626 $6,629 $14,281 $14,676 $16,991 $9,360 $11,026 $18,200 $35,112 $29,991 $39,802 $31,980 $42,068 $38,995 $47,369 $33,446 $103,134 $41,835 $33,500 $41,732 $24,623 $30,796 $6,451 $2,655 $971
Total Gross Revenue US$ '000 $5,023,854 $97,928 $131,903 $170,646 $224,622 $223,132 $214,452 $205,562 $184,391 $217,708 $228,219 $297,495 $256,498 $412,831 $380,854 $292,002 $289,211 $231,504 $238,241 $209,674 $168,325 $172,289 $114,137 $45,094 $17,138
Concentrate ChargesTotal Charges US$ '000 $1,382,981 $26,799 $33,614 $48,931 $66,251 $69,362 $65,276 $59,350 $44,008 $59,427 $55,467 $82,698 $67,780 $124,719 $110,004 $82,892 $59,547 $61,189 $64,183 $51,219 $46,493 $46,503 $37,081 $14,639 $5,551
Net Smelter Return US$ '000 $3,640,873 $71,130 $98,289 $121,715 $158,370 $153,770 $149,175 $146,212 $140,383 $158,282 $172,752 $214,796 $188,719 $288,113 $270,850 $209,110 $229,664 $170,316 $174,058 $158,455 $121,831 $125,786 $77,057 $30,455 $11,586
Royalty NSRArex Royalties 4.90% US$ '000 $48,154 $3,476 $4,257 $3,292 $1,610 $839 $712 $676 $840 $1,063 $1,071 $655 $1,115 $1,125 $395 $3,040 $7,168 $4,196 $5,871 $4,043 $1,821 $888 $0 $0 $0Ambrex Royalties 5.40% US$ '000 $143,540 $10 $616 $2,945 $6,778 $7,379 $7,271 $7,150 $6,654 $7,376 $8,148 $10,877 $8,962 $14,318 $14,190 $7,942 $4,503 $4,573 $2,929 $4,101 $4,572 $5,814 $4,161 $1,645 $626Total Royalties US$ '000 $191,693 $3,486 $4,873 $6,237 $8,388 $8,218 $7,983 $7,826 $7,495 $8,439 $9,219 $11,532 $10,077 $15,443 $14,586 $10,982 $11,670 $8,769 $8,800 $8,144 $6,393 $6,702 $4,161 $1,645 $626
Net Revenue US$ '000 $3,449,179 $67,643 $93,416 $115,478 $149,983 $145,552 $141,192 $138,385 $132,888 $149,843 $163,533 $203,264 $178,642 $272,669 $256,265 $198,128 $217,994 $161,547 $165,258 $150,311 $115,438 $119,084 $72,896 $28,810 $10,961Unit NSR US$ / t proc $93 $118 $103 $84 $84 $81 $79 $77 $73 $83 $90 $115 $99 $152 $141 $110 $120 $89 $91 $82 $74 $73 $56 $57 $52
Net Revenue by MetalZn % 41% 42% 34% 44% 45% 51% 47% 44% 29% 40% 30% 38% 37% 49% 44% 44% 28% 40% 40% 33% 42% 42% 59% 58% 58%Pb % 17% 14% 12% 16% 20% 21% 22% 18% 11% 14% 11% 19% 16% 22% 22% 18% 11% 14% 14% 12% 15% 13% 18% 21% 21%Cu % 13% 17% 25% 15% 12% 7% 9% 13% 27% 17% 27% 18% 14% 4% 6% 10% 8% 11% 16% 19% 13% 14% 6% 3% 1%Ag % 11% 18% 16% 14% 14% 15% 15% 13% 9% 10% 9% 11% 10% 12% 11% 13% 8% 11% 11% 10% 10% 7% 9% 10% 12%Au % 18% 9% 14% 12% 11% 6% 7% 12% 25% 19% 23% 15% 22% 13% 17% 16% 45% 24% 19% 26% 20% 24% 8% 9% 8%
OPERATING COST
Mining (Underground) US$ / t proc $20.65 $35.41 $24.23 $20.77 $18.70 $18.16 $18.28 $18.18 $18.41 $18.88 $18.83 $19.00 $19.33 $19.52 $19.06 $19.22 $19.23 $19.96 $21.21 $23.50 $23.66 $19.29 $23.26 $42.44 $62.43Processing+Tailings US$ / t proc $15.47 $17.21 $16.83 $15.07 $14.99 $15.64 $14.92 $15.06 $14.28 $14.46 $13.80 $14.05 $14.08 $15.09 $14.51 $15.00 $14.93 $14.94 $14.50 $14.13 $15.27 $16.07 $23.27 $26.73 $40.96G&A US$ / t proc $2.31 $5.16 $3.97 $2.62 $2.01 $2.00 $2.00 $1.99 $1.97 $1.98 $1.97 $2.02 $1.99 $2.00 $1.98 $1.99 $1.98 $1.98 $1.98 $1.97 $2.31 $2.20 $2.74 $7.07 $17.15Total Operating Cost US$ / t proc $38.43 $57.78 $45.03 $38.46 $35.70 $35.79 $35.20 $35.23 $34.66 $35.31 $34.60 $35.07 $35.40 $36.61 $35.55 $36.21 $36.14 $36.88 $37.69 $39.60 $41.25 $37.57 $49.27 $76.24 $120.55
Mining (Underground) US$ '000 $762,941 $20,313 $21,892 $28,436 $33,315 $32,661 $32,829 $32,838 $33,491 $34,265 $34,311 $33,722 $34,833 $35,021 $34,575 $34,718 $34,919 $36,160 $38,537 $42,824 $36,750 $31,497 $30,428 $21,545 $13,059Processing US$ '000 $571,541 $9,870 $15,202 $20,635 $26,695 $28,121 $26,808 $27,218 $25,984 $26,249 $25,149 $24,927 $25,358 $27,076 $26,312 $27,102 $27,108 $27,079 $26,346 $25,750 $23,719 $26,241 $30,451 $13,572 $8,568G&A US$ '000 $85,494 $2,961 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588Total Operating Cost US$ '000 $1,419,976 $33,144 $40,682 $52,659 $63,599 $64,370 $63,225 $63,645 $63,063 $64,102 $63,049 $62,237 $63,780 $65,685 $64,475 $65,409 $65,615 $66,828 $68,471 $72,162 $64,058 $61,327 $64,468 $38,705 $25,216
Operating Cashflow US$ '000 $2,029,204 $34,499 $52,733 $62,819 $86,384 $81,182 $77,967 $74,740 $69,824 $85,741 $100,485 $141,027 $114,862 $206,985 $191,789 $132,719 $152,378 $94,719 $96,786 $78,148 $51,381 $57,757 $8,428 -$9,895 -$14,255
TABLE 1-2 CASH FLOW SUMMARY VM Holding S.A. - Aripuana Zinc Project
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 1-7
Date:INPUTS UNITS TOTAL 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044
CAPITAL COSTDirect Cost
Mining US$ '000 55,325$ 14,204$ 24,523$ 16,597$ Plant & Infrastructure US$ '000 197,715$ 29,336$ 83,164$ 85,215$
Total Direct Cost US$ '000 253,040$ 43,541$ 107,687$ 101,812$
EPCM / Owners / Indirect Cost US$ '000 77,803$ 11,544$ 32,726$ 33,533$ Subtotal Costs US$ '000 330,843$ 55,085$ 140,413$ 135,345$
Contingency US$ '000 23,609$ 3,503$ 9,930$ 10,175$ Initial Capital Cost US$ '000 354,452$ 58,588$ 150,344$ 145,521$
Sustaining Capital US$ '000 219,037$ $5,534 $12,715 $11,975 $17,210 $8,784 $17,486 $8,446 $14,947 $9,155 $18,247 $7,004 $12,105 $7,868 $9,329 $9,506 $15,948 $6,703 $14,756 $4,803 $2,606 $1,303 $1,303 $1,303 Reclamation and closure US$ '000 10,000$ $5,000 $5,000
Total Capital Cost US$ '000 583,489$ 58,588$ 150,344$ 145,521$ 5,534$ 12,715$ 11,975$ 17,210$ 8,784$ 17,486$ 8,446$ 14,947$ 9,155$ 18,247$ 7,004$ 12,105$ 7,868$ 9,329$ 9,506$ 15,948$ 6,703$ 14,756$ 4,803$ 2,606$ 1,303$ 1,303$ 6,303$ 5,000$
CASH FLOWNet Pre-Tax Cashflow US$ '000 1,445,715$ (58,588)$ (150,344)$ (111,021)$ 47,199$ 50,104$ 74,408$ 63,972$ 69,183$ 57,254$ 61,379$ 70,794$ 91,329$ 122,780$ 107,858$ 194,879$ 183,921$ 123,391$ 142,872$ 78,771$ 90,083$ 63,393$ 46,577$ 55,151$ 7,124$ (11,198)$ (20,558)$ (5,000)$ Cumulative Pre-Tax Cashflow US$ '000 (58,588)$ (208,931)$ (319,953)$ (272,753)$ (222,649)$ (148,241)$ (84,269)$ (15,086)$ 42,168$ 103,547$ 174,341$ 265,670$ 388,450$ 496,308$ 691,188$ 875,109$ 998,499$ 1,141,371$ 1,220,143$ 1,310,226$ 1,373,619$ 1,420,196$ 1,475,346$ 1,482,471$ 1,471,273$ 1,450,715$ 1,445,715$
Taxes (net of Working Capital credit) US$ '000 389,827$ 961$ (2,096)$ (976)$ 3,380$ 6,303$ 5,376$ 4,633$ 3,273$ 8,616$ 9,774$ 23,377$ 32,118$ 76,610$ 59,411$ 35,549$ 48,969$ 23,673$ 29,699$ 20,995$ (7,334)$ 16,993$ 86$ (2,830)$ (6,733)$
After-Tax Cashflow US$ '000 1,055,888$ (58,588)$ (150,344)$ (111,983)$ 49,295$ 51,080$ 71,028$ 57,669$ 63,807$ 52,621$ 58,106$ 62,178$ 81,556$ 99,403$ 75,740$ 118,269$ 124,510$ 87,841$ 93,903$ 55,098$ 60,384$ 42,397$ 53,912$ 38,158$ 7,039$ (8,368)$ (13,825)$ (5,000)$ Cumulative After-Tax Cashflow US$ '000 (58,588)$ (208,931)$ (320,914)$ (271,619)$ (220,539)$ (149,510)$ (91,842)$ (28,034)$ 24,587$ 82,692$ 144,870$ 226,426$ 325,829$ 401,569$ 519,839$ 644,348$ 732,189$ 826,092$ 881,191$ 941,575$ 983,972$ 1,037,884$ 1,076,042$ 1,083,081$ 1,074,713$ 1,060,888$ 1,055,888$
PROJECT ECONOMICS 0.5 1.5 2.5 3.5 4.5 5.5 6.5 7.5 8.5 9.5 10.5 11.5 12.5 13.5 14.5 15.5 16.5 17.5 18.5 19.5 20.5 21.5 22.5 23.5 24.5 25.5 26.5Pre-Tax IRR % 18.98%Pre-tax NPV at 7.0% discounting 7.0% US$ '000 $461,147 (56,639)$ (135,834)$ (93,745)$ 37,247$ 36,953$ 51,287$ 41,210$ 41,651$ 32,214$ 32,275$ 34,791$ 41,947$ 52,703$ 43,268$ 73,064$ 64,444$ 40,406$ 43,725$ 22,530$ 24,080$ 15,837$ 10,875$ 12,034$ 1,453$ (2,134)$ (3,662)$ (832)$ Pre-tax NPV at 9% discounting 9.0% US$ '000 $324,172 (56,117)$ (132,113)$ (89,504)$ 34,909$ 33,998$ 46,321$ 36,536$ 36,249$ 27,522$ 27,069$ 28,643$ 33,900$ 41,812$ 33,697$ 55,857$ 48,364$ 29,768$ 31,622$ 15,995$ 16,781$ 10,834$ 7,303$ 7,933$ 940$ (1,356)$ (2,284)$ (510)$ Pre-tax NPV at 11.0% discounting 11.0% US$ '000 $220,912 (55,609)$ (128,558)$ (85,526)$ 32,757$ 31,327$ 41,913$ 32,463$ 31,628$ 23,581$ 22,775$ 23,665$ 27,504$ 33,311$ 26,363$ 42,912$ 36,486$ 22,052$ 23,004$ 11,426$ 11,772$ 7,463$ 4,940$ 5,270$ 613$ (868)$ (1,436)$ (315)$
After-Tax IRR % 16.79%After-Tax NPV at 7.0% discounting 7.0% US$ '000 $320,716 (56,639)$ (135,834)$ (94,557)$ 38,901$ 37,673$ 48,958$ 37,149$ 38,414$ 29,607$ 30,554$ 30,557$ 37,458$ 42,668$ 30,384$ 44,341$ 43,627$ 28,765$ 28,738$ 15,759$ 16,141$ 10,592$ 12,587$ 8,326$ 1,435$ (1,595)$ (2,463)$ (832)$ After-Tax NPV at 9% discounting 9.0% US$ '000 $217,170 (56,117)$ (132,113)$ (90,279)$ 36,460$ 34,660$ 44,217$ 32,936$ 33,433$ 25,295$ 25,625$ 25,157$ 30,273$ 33,851$ 23,663$ 33,899$ 32,741$ 21,191$ 20,783$ 11,188$ 11,249$ 7,246$ 8,453$ 5,489$ 929$ (1,013)$ (1,536)$ (510)$ After-tax NPV at 11.0% discounting 11.0% US$ '000 $138,694 (55,609)$ (128,558)$ (86,267)$ 34,212$ 31,937$ 40,009$ 29,265$ 29,171$ 21,673$ 21,560$ 20,785$ 24,561$ 26,969$ 18,513$ 26,043$ 24,700$ 15,699$ 15,119$ 7,992$ 7,891$ 4,991$ 5,718$ 3,646$ 606$ (649)$ (966)$ (315)$
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 1-8
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-9
TAXATION AND ROYALTIES RPA has relied on a VMH taxation model for calculation of income taxes applicable to the cash
flow.
As discussed in Section 4, the Project is subject to royalties which differ for the two deposits.
In addition, a corporate income tax rate of 34% was applied to taxable income. The calculation
of taxable income takes into consideration the depreciation schedule, assuming a 10 year fixed
rate method. Over the LOM, the Project will pay US$390 million in corporate income taxes
(net of credits for working capital).
CASH FLOW ANALYSIS Considering the Project on a stand-alone basis, the undiscounted after-tax cash flow totals
US$1,055 million over the mine life, and simple payback occurs six years from start of
production.
The after-tax Net Present Value (NPV) at a 9% discount rate is $217 million (based on mid-
period discounting), and the Internal Rate of Return (IRR) is 16.8%.
SENSITIVITY ANALYSIS Project risks can be identified in both economic and non-economic terms. Key economic risks
were examined by running cash flow sensitivities:
• Metal price
• Head grade
• Metallurgical recovery
• Operating costs
• Capital costs
IRR sensitivity over the base case has been calculated for a variety of ranges depending on
the variable. The sensitivities are shown in Figure 1-1 and Table 1-3.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-10
FIGURE 1-1 SENSITIVITY ANALYSIS
TABLE 1-3 SENSITIVITY ANALYSES VM Holding S.A. – Aripuanã Zinc Project
Description Units Low Case
Mid-Low Case
Base Case
Mid-High Case
High Case
Head Grade (Zn) % Zn 3.25 3.65 4.06 4.46 4.87 Overall Recovery (Zn) % 79 80 82 83 85 Metal Prices (Zn) US$/lb Zn 0.85 0.96 1.06 1.17 1.27 Operating Costs US$/t 31 35 38 42 46 Capital Cost US$ millions 284 319 355 390 426
Adjustment Factor
Head Grade (ZnEq) % 80 90 100 110 120 Overall Recovery % 96 98 100 102 104 Metal Prices (Zn) % 80 90 100 110 120 Operating Costs % 80 90 100 110 120 Capital Cost % 80 90 100 110 120
Post-Tax NPV @ 9%
Head Grade (ZnEq) US$ millions -114 51 217 382 547 Overall Recovery US$ millions 151 184 217 250 283 Metal Prices (Zn) US$ millions -114 51 217 382 547 Operating Costs US$ millions 315 266 217 168 119 Capital Cost US$ millions 278 247 217 186 155
($200)
($100)
$0
$100
$200
$300
$400
$500
$600
0.7 0.8 0.9 1 1.1 1.2 1.3
Afte
r-Ta
x N
PV a
t 9%
Dis
coun
t Rat
e (U
S$
mill
ions
)
Percent Change From Base Case
Head Grade
Recovery
Metal Price
Operating Cost
Capital Cost
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-11
Factors were applied to all metals in the various categories, however, in the table, zinc is shown
because it provides the most revenue.
The Project is most sensitive to changes in metal prices and head grade, and least sensitive
to capital costs.
TECHNICAL SUMMARY
PROPERTY DESCRIPTION AND LOCATION The Project is located in Mato Grosso State, western Brazil, 1,200 km northwest of Brasilia,
the capital city. The property is located at approximately 226,000 mE and 8,888,000 mN UTM
21L zone (South American 1969 datum).
LAND TENURE The Aripuanã Zinc property contains 23 contiguous Exploration Authorization permits (EP),
mining concessions and EPs in application, covering an area approximately 871 km2. The EPs
are owned by Dardanelos, a joint venture between VMZ 62.3%), Milpo, (7.7%), and Mineração
Rio Aripuanã (a subsidiary of Karmin (30%)), with VMH acting as the operator through VMZ.
Karmin is not required to contribute financially to the Project until the completion of a bankable
feasibility study, and meanwhile VMH is fully funding the Project development. One year after
the completion of a bankable feasibility study, Karmin will contribute on a pro-rata basis
towards bringing Aripuanã Zinc into production.
EXISTING INFRASTRUCTURE The only permanent infrastructure on the Project is a series of exploration drill roads used to
access drill sites.
HISTORY Gold mineralization was discovered in the area during the 1700s by prospectors. Although no
formal records exist, the area was likely prospected sporadically over the years.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-12
Anglo American Brasil Ltda (Anglo American) began exploration over the property in 1995. At
the time, a small area including Expedito’s Pit, now part of the Project, was held by Madison
do Brasil (now Thistle Mining Inc.) and optioned to Ambrex Mining Corporation (now Karmin).
Dardanelos was created in 2000 to represent a joint venture, or “contract of association”,
between Karmin and Anglo American, with the intent of exploring for base and precious metals
in areas adjacent to the town of Aripuanã. Anglo American and Karmin held 70% and 28.5%
of Dardanelos, respectively, with remaining interest (1.5%) owned by SGV Merchant Bank.
In 2004, the initial agreement between Karmin and Anglo American was amended to allow
VMH’s participation. VMH subsequently acquired 100% of Anglo American’s interest in the
Project. In 2007, Karmin purchased SGV Merchant Bank’s interests, raising its participation to
30%.
GEOLOGY AND MINERALIZATION The Aripuanã Zinc deposits are located within the central-southern portion of the Amazonian
Craton, in which Paleoproterozoic and Mesoproterozoic lithostratigraphic units of the Rio
Negro-Juruena province (1.80 Ga to 1.55 Ga) predominate.
The lithological assemblage strikes northwest-southeast and dips between 35° and near
vertical to the northeast.
The Aripuanã Zinc polymetallic deposits are typical VMS deposits associated with felsic
bimodal volcanism. Three main elongate mineralized zones, Arex, Link, and Ambrex, have
been defined in the central portion of the Aripuanã Project. A smaller, deeper zone, Babaçú,
lies to the south of Ambrex. Limited exploration has identified additional, possible mineralized
bodies including Massaranduba, Boroca, and Mocoto to the south and Arpa to the north.
The individual mineralized bodies have complex shapes due to intense tectonic activity.
Stratabound mineralized bodies tend to follow the local folds, however, local-scale, tight
isoclinal folds are frequently observed, usually with axes parallel to major reverse faults,
causing rapid variations in the dips.
Massive, stratabound sulphide mineralization as well as vein and stockwork-type discordant
mineralization have been described on the property. The stratabound bodies, consisting of
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-13
disseminated to massive pyrite and pyrrhotite, with well-developed sphalerite and galena
mineralization, are commonly associated with the contact between the middle volcanic and the
upper sedimentary units. Discordant stringer bodies of pyrrhotite-pyrite-chalcopyrite
mineralization are usually located in the underlying volcanic units or intersect the massive
sulphide lenses, and have been interpreted as representing feeder zones.
EXPLORATION Between 2004 and 2007, VMH carried out geological, geochemical, and geophysical surveys
over the Project area to allow a more complete interpretation of the regional and local geology
and identification of local exploration targets.
Drilling on the property was carried out from 2004 to 2008, in 2012, and from 2014 to present.
The purpose of the drill program in 2004 to 2008 was to explore and delineate mineralization
on the property, and in 2012, to improve confidence and classification of the Mineral Resources
of the Arex and Ambrex deposits. The Link Zone, a zone of mineralization connecting the Arex
and Ambrex deposits, and included in the Mineral Resource summary for Ambrex, was
discovered in 2014 and delineated in 2015.
A total of 497 diamond drill holes totalling approximately 145,000 m have been completed at
the Project since 2004.
MINERAL RESOURCES The Mineral Resource estimate, dated December 23, 2016 was completed by VMH personnel
using Datamine Studio 3, Leapfrog Geo, and Isatis softwares. Wireframes for geology and
mineralization were constructed in Leapfrog Geo based on geology sections, assay results,
lithological information, and structural data. Assays were capped to various levels based on
exploratory data analysis and then composited to one metre lengths. Wireframes were filled
with blocks measuring 5 m by 10 m by 5 m with sub-celling at wireframe boundaries. Blocks
were interpolated with grade using Ordinary Kriging (OK) and Inverse Distance Squared (ID2).
Blocks estimates were validated using industry standard validation techniques. Classification
of blocks was based on distance based criteria.
A summary of the Mineral Resources is provided in Table 1-4.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-14
TABLE 1-4 MINERAL RESOURCE STATEMENT, DECEMBER 23, 2016 VM Holding S.A. – Aripuanã Zinc Project
Grade Contained Metal
Stratabound Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 8.6 5.88 2.16 0.19 0.23 52.65 1,109.0 407.1 36.0 64.2 14.5
Indicated 9.8 5.38 2.03 0.09 0.25 47.83 1,160.8 437.2 18.7 79.5 15.0 Measured and Indicated 18.3 5.61 2.09 0.14 0.24 50.08 2,269.9 844.3 54.7 143.7 29.5
Inferred 13.2 7.20 2.80 0.10 0.38 62.50 2,099.7 815.4 29.4 162.7 26.6
Stringer Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 2.3 0.28 0.12 1.54 1.18 17.61 14.4 6.3 78.5 87.8 1.3
Indicated 1.2 0.11 0.05 0.97 1.28 11.21 2.7 1.4 24.5 47.5 0.4 Measured and Indicated 3.5 0.22 0.10 1.35 1.21 15.49 17.2 7.7 103.1 135.3 1.7
Inferred 11.4 0.08 0.05 0.78 1.55 9.31 19.3 13.5 197.0 569.7 3.4
Total Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 10.9 4.68 1.72 0.48 0.43 45.18 1,123.5 413.5 114.6 152.0 15.8
Indicated 10.9 4.83 1.82 0.18 0.36 43.97 1,163.6 438.6 43.2 127.0 15.5 Measured and Indicated 21.8 4.76 1.77 0.33 0.40 44.58 2,287.0 852.0 157.8 279.0 31.3
Inferred 24.6 3.90 1.53 0.42 0.93 37.88 2,119.0 829.0 226.4 732.4 30.0 Notes:
1. CIM definitions were followed for Mineral Resources. 2. Mineral Resources are reported using a US$46/t Net Smelter Return (NSR) block cut-off value for
stratabound material and a US$42/t NSR block cut-off value for stringer material. 3. The NSR is calculated based on metal prices of US$1.26 per lb Zn, US$1.01 per lb Pb, US$3.08 per lb
Cu, US$1,471 per troy ounce Au, and US$21.8 per troy ounce Ag. 4. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. 5. Numbers may not add due to rounding.
RPA is not aware of any environmental, permitting, legal, title, taxation, socio-economic,
marketing, political, or other relevant factors that could materially affect the Mineral Resource
estimate.
MINERAL RESERVES No Mineral Reserves have been estimated for the Project.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-15
MINING METHOD The current Project targets three main elongated mineralized zones, Arex, Link, and Ambrex
that have been defined in the central portion of the Aripuanã Project.
The Arex and Ambrex deposits are separate VMS deposits with differing mineralized
compositions in stratabound and stringer forms and complex geometric shapes.
The Arex deposit extends over a strike length of approximately 1,400 m. Upper portions of the
deposit are near-vertical, reducing at depth to a dip of approximately 60° to the northeast.
Mineralization occurs in discrete stratabound and stringer lenses of stratabound, ranging from
less than one metre to 15 m thick in width interspersed with some zones between 100 m to
150 m wide. Mineralization extends from close to surface to about 500 m below surface (mbs).
The Ambrex deposit is located approximately 1,300 m southeast of Arex and represents the
largest of the known mineralized zones on the Project. The deposit has a strike extent of
approximately 1,050 m, based on current drilling. The dip varies from near vertical to 70° to
the northeast. Mineralization thicknesses typically range between 10 m and 50 m, with a
maximum of 150 m. The deposit extends vertically from 60 mbs to approximately 700 mbs.
Mining will be undertaken using conventional mechanized underground mobile mining
equipment via a network of declines, access drifts and ore drives. Access to the Arex and
Ambrex deposits will be from separate portals, which will access the deposits from the most
favorable topographic locations.
The deposit geometry is amenable to a number of underground mechanized mining techniques
including cut-and-fill and bulk stoping methods. A nominal production target of 5,000 tpd has
been used as the basis for the mine production schedule.
The two deposits will be accessed from two independent surface cut and cover portals and the
ramps are designed at a gradient of 14% to be driven with an arched profile and a cross-
sectional area (CSA) of 27 m2 to accommodate the selected major equipment. The main
loading and hauling equipment will be 12.5 t class load haul dump (LHD) combined with 35.5 t
class haul trucks.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-16
The selected method for the conceptual mine design and mine plan, is a combination of
longitudinal longhole retreat stoping (bench stoping) for the narrower zones of the deposits
with Vertical Retreat Mining (VRM) applied for the thicker zones. To increase the extraction
ratio, a primary and secondary stoping sequence will be used in the VRM areas with cemented
paste and rock fill used to backfill primary stopes and uncemented rock fill placed in the
secondary stopes. Finished longhole retreat stopes will also be backfilled with rock fill.
The majority of the production from the Arex deposit is based on longitudinal longhole retreat
mining, however, in areas where the deposit is wider (greater than 15 m), Vertical Retreat
Mining (VRM) longhole mining with primary and secondary stopes will be used. The method
applied in the Ambrex deposit will be predominantly the VRM method.
Main mining sublevels are spaced 75 m apart, with stope sublevels currently placed at 25 m
spacing.
Stope sizes are nominally 15 m long x 25 m high with varying widths from hanging wall (HW)
to footwall (FW). A minimum mining width of 4 m is applied.
For the narrow vein stopes 10% dilution was added, which RPA considers to be acceptable
for the steeper dipping stopes. However, for stopes flatter than 50° to 55°, RPA’s opinion is
that dilution could be between 15% and 20%.
A mining recovery of 95% has been applied to primary and vein stopes with 90% applied to
the secondary stopes.
MINERAL PROCESSING Concentrate grades and recoveries for the Stringer and Stratabound mineralization from the
Arex and Ambrex deposits were obtained based on metallurgical tests. The process circuit
proposed consists of comminution through a traditional SAB circuit (Semi-Autogenous
Grinding, or SAG) with Ball mill) and sulphide flotation by sequential methods in the following
order: talc (when required), copper, lead, and zinc.
Separation of material types is necessary to improve copper recovery and to reduce costs,
particularly when processing Copper Stringer material.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-17
The final copper and zinc concentrates produced will be filtered and trucked to customers,
while the lead concentrate will be bagged after filtration.
Tailings generated in the process will be used as mine backfill and will also be filtered and
disposed of in a lined surface dump.
INFRASTRUCTURE Electrical power will be provided by means of a short connection to the national grid.
Water supply will be obtained by constructing a water dam and filling a valley adjacent to the
Project site.
MARKET STUDIES The principal commodities at the Project are freely traded, at prices and terms that are widely
known, so that prospects for sale of any production are virtually assured. RPA reviewed the
concentrate terms provided by VMH and found them to be consistent with current industry
norms.
Metal prices are based on long-term consensus forecasts by independent banks and financial
institutions. A year-by-year price curve was used to cash flow modelling.
ENVIRONMENTAL, PERMITTING AND SOCIAL CONSIDERATIONS The environmental licensing process for the Aripuanã Zinc Project started in 2008 following
the Terms of Reference (ToR) issued by Mato Grosso environmental agency (SEMA/MT). For
strategic reasons, the process was put on hold and the field activities performed in 2008 were
consolidated into a document in the format of a “Diagnosis of an EIA – Environmental Impact
Assessment of the Project” (EIA). In 2012, a new ToR was requested, and many of the studies
performed as a result were consolidated into a comprehensive EIA. The EIA was completed
in 2012, however, was not filed with the authorities, due to low commodity prices at that time.
In 2014, with zinc prices increasing, the EIA was filed. Taking into account further exploration
on the property, increased production levels were presented in 2015 with productions
increasing from 1.2 Mtpa to 1.8 Mtpa. SEMA performed many inspections and the Public
Hearing was held on August 26, 2015. During 2015 and 2016, the permitting process was
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-18
analyzed by SEMA/MT, however, due to changes in the engineering process, the analyses
were put on hold until all changes were performed.
At the time of report writing, VMH was in the process of finalizing an updated EIA for submittal,
covering the current design for the Project.
CAPITAL AND OPERATING COST ESTIMATES VMH has completed engineering studies on the Project, involving detailed cost estimates built
up from first principles. Costs were estimated as of Q2 2017, in Brazilian currency. RPA
reviewed the estimates and converted to US$ using an exchange rate of US$1.00 = R$3.30.
Capital costs are estimated at a +/- 20% confidence level.
Pre-production capital costs totalling US$354 million are summarized in Table 1-5.
TABLE 1-5 PRE-PRODUCTION CAPITAL COST ESTIMATE VM Holding S.A. – Aripuanã Zinc Project
Area Category Units Initial Costs
Mine Development US$ millions 23.9 Mobile Equipment US$ millions 31.4 Plant & Infrastructure Site Prep & Earthworks US$ millions 22.8 Civil & Roadwork US$ millions 24.2 Steelwork US$ millions 16.7 Electrical US$ millions 36.1 Instrumentation US$ millions 9.6 Mechanical Equipment US$ millions 75.3 Piping US$ millions 14.8 Communications US$ millions 6.0 Subtotal Direct Costs US$ millions 260.9 Indirect Costs EPCM US$ millions 18.9 Temporary Services US$ millions 10.4 Owner’s Team US$ millions 19.2 Other US$ millions 13.4 Subtotal Indirects US$ millions 69.7 Contingency US$ millions 23.6 Total Capital Cost US$ millions 354.3
Sustaining capital costs total US$229 million over the operating life of the mine, consisting of
mine equipment replacement, capital development, plant equipment, and tailings facility
expansions.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 1-19
RPA added an allowance of US$10 million for Closure and Reclamation to the estimate
provided by VMH.
OPERATING COSTS Operating costs, averaging US$64 million per year at full production, were estimated for
mining, processing, and general and administration (G&A). Operating cost inputs such as
labour rates, consumables, and supplies were based on VMH operating data. A summary of
operating costs is shown in Table 1-6.
TABLE 1-6 OPERATING COST ESTIMATE VM Holding S.A. – Aripuanã Zinc Project
Parameter Total LOM
(US$ millions) Average Year
(US$ millions / yr) LOM Unit Cost
(US$ / t) Mining 763 35.0 20.65
Processing 572 26.4 15.47
G&A 85 3.6 2.31
Total 1,420 64.0 38.43
LOM average unit costs are influenced by three higher-cost years during ramp-up to full
production and by five years of lower production at the end of the mine life.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 2-1
2 INTRODUCTION Roscoe Postle Associates Inc. (RPA) was retained by VM Holdings S.A. (VMH) to prepare an
independent Technical Report on the Aripuanã Zinc Project (the Project), located in the state
of Mato Grosso, Brazil. The purpose of this report is to audit a Mineral Resource estimate and
to disclose the results of a Preliminary Economic Assessment (PEA) of the Project. This
Technical Report conforms to NI 43-101 Standards of Disclosure for Mineral Projects.
VMH is one of the largest producers of zinc in the world. It has a diversified portfolio of
polymetallic mines (zinc, lead, copper, silver, and gold) and also greenfield projects at various
stages of development in Brazil and Peru. In Brazil, VMH owns and operates two underground
mines, Vazante (Zn and Pb) and Morro Agudo (Zn and Pb) and two development projects,
Aripuanã and Caçapava do Sul. It also operates two zinc smelters in Brazil (Três Marias and
Juiz de Fora). In Peru, VMH owns a controlling interest in Lima Stock Exchange-listed
Compañía Minera - Milpo S.A.A. (Milpo). Milpo currently operates the El Porvenir (Zn-Pb-Cu-
Ag-Au), Cerro Lindo (Zn-Cu-Pb-Ag), and Atacocha (Zn-Cu-Pb-Au-Ag) underground mines in
Peru. The development projects in Peru include Magistral, Shalipayco, Florida Canyon (JV
with Solitario), Hilarión, and Pukaqaqa. It also operates one zinc smelter in Peru
(Cajamarquilla).
In 2000, a joint venture between Anglo American Brasil Ltda. (Anglo American) and Karmin
Exploration Inc. (Karmin) was formed to explore for base and precious metals in the area
adjacent to the town of Aripuanã. Initially, Anglo American and Karmin held interests of 70%
and 28.5% in the joint venture, respectively, with the remaining 1.5% held by SGV Merchant
Bank (SGV). In 2004, the joint venture agreement was amended to allow VMH’s participation.
VMH subsequently acquired 100% of Anglo American’s interest in the Project. In 2007, Karmin
purchased SGV’s interests, raising its participation to 30%.
The exploration permits are owned by Mineração Dardanelos Ltda. (Dardanelos), a joint
venture between Votorantim Metais Zinco SA (VMZ, a subsidiary of VMH, 62.3%), Milpo
(7.7%), and Mineração Rio Aripuanã (a subsidiary of Karmin, 30%), with VMH acting as the
operator through VMZ.
This report is considered by RPA to meet the requirements of a Preliminary Economic
Assessment as defined in Canadian NI 43-101 regulations. The economic analysis contained
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 2-2
in this report is based, in part, on Inferred Resources, and is preliminary in nature. Inferred
Resources are considered too geologically speculative to have mining and economic
considerations applied to them and to be categorized as Mineral Reserves. There is no
certainty that economic forecasts on which this PEA is based will be realized.
SOURCES OF INFORMATION Mr. Jason Cox, P.Eng., RPA Principal Mining Engineer, visited the property between June 2
and 5, 2017.
Mr. Horan visited the Project site on January 30 to February 3, 2017. During the site visit, Mr.
Horan reviewed logging and sampling methods, inspected core from drill holes, and held
discussions with VMH personnel.
Technical documents and reports on the deposit were reviewed and obtained from project
personnel while at the site. The updated Mineral Resource files were transferred via a File
Transfer Protocol (FTP) or by email. The principal technical documents related to RPA’s
review are listed in the Sources of Information. Discussions were held with the following
technical personnel:
• Mr. Alex Jose Mattos Fortunato, Mining Engineer and Aripuanã Zinc Project Manager, VMH
• Mr. Julio Souza Santos, Senior Geologist and Aripuanã Zinc Field Manager, VMH
• Mr. Jose Antonio Lopes, Resource Manager, VMH
• Ms. Talita Cristina De Oliveira Ferreira, Senior Resource Geologist, VMH
This report was prepared by Jason Cox, P. Eng., Sean Horan, P. Geo., Brenna Scholey,
P.Eng., and Stephen Theben, Dipl-Ing. Mr. Cox prepared Sections 15, 16, 19, 21, and 22 and
contributed to Sections 1, 2, 3, 18, 25, and 26. Mr. Horan prepared Sections 4 to 12 and14
and contributed to Sections 1, 2, 3, 25, and 26. Ms. Scholey prepared Sections 13 and 17 and
contributed to Sections 1, 2, 3, 18, 25, and 26. Mr. Theben prepared Sections 20, and
contributed to Sections 1, 2, 3, 25, and 26.
RPA would like to acknowledge the excellent cooperation in the transmittal of data and
information by Messrs. Souza Santos, Fortunato, and Lopes, and Ms. Ferreira of VMH.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 2-3
The documentation reviewed, and other sources of information, are listed at the end of this
report in Section 27 References.
LIST OF ABBREVIATIONS Units of measurement used in this report conform to the metric system. All currency in this
report is US dollars (US$) unless otherwise noted.
a annum kWh kilowatt-hour A ampere L litre bbl barrels lb pound btu British thermal units L/s litres per second °C degree Celsius m metre C$ Canadian dollars M mega (million); molar cal calorie m2 square metre cfm cubic feet per minute m3 cubic metre cm centimetre µ micron cm2 square centimetre MASL metres above sea level d day µg microgram dia diameter m3/h cubic metres per hour dmt dry metric tonne mi mile dwt dead-weight ton min minute °F degree Fahrenheit µm micrometre ft foot mm millimetre ft2 square foot mph miles per hour ft3 cubic foot MVA megavolt-amperes ft/s foot per second MW megawatt g gram MWh megawatt-hour G giga (billion) oz Troy ounce (31.1035g) Gal Imperial gallon oz/st, opt ounce per short ton g/L gram per litre ppb part per billion Gpm Imperial gallons per minute ppm part per million g/t gram per tonne psia pound per square inch absolute gr/ft3 grain per cubic foot psig pound per square inch gauge gr/m3 grain per cubic metre RL relative elevation ha hectare s second hp horsepower st short ton hr hour stpa short ton per year Hz hertz stpd short ton per day in. inch t metric tonne in2 square inch tpa metric tonne per year J joule tpd metric tonne per day k kilo (thousand) US$ United States dollar kcal kilocalorie USg United States gallon kg kilogram USgpm US gallon per minute km kilometre V volt km2 square kilometre W watt km/h kilometre per hour wmt wet metric tonne kPa kilopascal wt% weight percent kVA kilovolt-amperes yd3 cubic yard kW kilowatt yr year
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 3-1
3 RELIANCE ON OTHER EXPERTS This report has been prepared by RPA for VMH. The information, conclusions, opinions, and
estimates contained herein are based on:
• Information available to RPA at the time of preparation of this report, • Assumptions, conditions, and qualifications as set forth in this report, and • Data, reports, and other information supplied by VMH and other third party sources.
For the purpose of this report, RPA has relied on ownership information provided by VMH.
The client has relied on an opinion by Azevedo Sette Advogados dated June 14, 2017 entitled
Title Opinion – Projects Aripuanã and Caçapava Do Sul, and this opinion is relied on in Section
4 and the Summary of this report. RPA has not researched property title or mineral rights for
the Aripuanã Zinc Project and expresses no opinion as to the ownership status of the property.
RPA has relied on VMH for guidance on applicable taxes, royalties, and other government
levies or interests, applicable to revenue or income from the Aripuanã Zinc Project.
Except for the purposes legislated under provincial securities laws, any use of this report by
any third party is at that party’s sole risk.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 4-1
4 PROPERTY DESCRIPTION AND LOCATION The Project is located in west-central Brazil, in the state of Mato Grosso, approximately 700
km northwest of Cuiabá and approximately 1,200 km northwest of Brasilia. The centre of the
property is located at approximately 10°05’00”S Latitude and 59°25’00”W Longitude (Figure 4-
1). The approximate Universal Transverse Mercator (UTM) co-ordinates of the centre of the
currently defined mineralization are 226,000 mE and 8,888,000 mN, UTM zone 21L (South
American 1969 datum), within the Aripuanã 1:250,000 topographic sheet (SC.21-Y-A).
LAND TENURE The property consists of a contiguous block comprising six mining applications, ten exploration
permits, and seven exploration claims covering a total area of 87,063 ha (Figure 4-2).
Table 4-1 lists all the subject concessions and relevant tenure information including concession
names, tenement numbers, areas, titleholders, and expiry dates.
In 2000, a joint venture between Anglo American Brasil Ltda. (Anglo American) and Karmin
Exploration Inc. (Karmin) was formed to explore for base and precious metals in the area
adjacent to the town of Aripuanã. Initially, Anglo American and Karmin held interests of 70%
and 28.5% in the joint venture, respectively, with the remaining 1.5% held by SGV Merchant
Bank (SGV). In 2004, the joint venture agreement was amended to allow VMH’s participation.
VMH subsequently acquired 100% of Anglo American’s interest in the Project. In 2007, Karmin
purchased SGV’s interests, raising its participation to 30%.
The exploration permits are owned by Mineração Dardanelos Ltda. (Dardanelos), a joint
venture between VMZ (a subsidiary of VMH, 62.3%), Milpo (7.7%), and Mineração Rio
Aripuanã (a subsidiary of Karmin, 30%), with VMH acting as the operator through VMZ. Karmin
is not required to contribute financially to the Project until the completion of a bankable
feasibility study. In the meanwhile, VMH is fully funding the Project development. One year
after the completion of a bankable feasibility study, Karmin will contribute on a pro-rata basis
towards bringing Aripuanã into production.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 4-2
TABLE 4-1 EXPLORATION AUTHORIZATION PERMITS VM Holding S.A. – Aripuanã Zinc Project
Map Ref. Tenement Area
(ha) Owner Status Expiry Date
1 866570/1992 1,000.00 MDL1 Mining Application2 *
2 866569/1992 639.91 MDL1 Mining Application2 *
3 866173/1992 1,000.00 MDL1 Mining Application2 *
4 866174/1992 1,000.00 MDL1 Mining Application2 *
5 866817/2016 4,647.58 MDL1 Claim/Application *
6 866208/2013 415.61 MDL1 Claim/Application *
7 866236/2007 7,448.24 MDL1 Exploration Permit - Replaced by 866230/2017 March 17, 2017
8 866050/2015 331.51 MDL1 Claim/Application *
9 866727/2015 4,814.68 MDL1 Claim/Application *
10 866941/2015 682.38 MDL1 Claim/Application *
11 866148/2017 9,388.80 MDL1 Claim/Application *
12 866728/2015 6,757.93 MDL1 Claim/Application *
13 866292/2015 839.18 MDL1 Exploration Permit - 1st Period August 21, 2018
14 866293/2015 930.38 MDL1 Exploration Permit - 1st Period August 21, 2018
15 866565/1992 975.00 MDL1 Mining Application2 *
16 866386/2003 412.20 MDL1 Mining Application2 *
17 867381/1991 1,000.00 MDL1 Mining Application Postponed *
18 866051/2015 978.88 MDL1 Exploration Permit - 1st Period August 21, 2018
19 866812/2008 5,462.30 VMZ1 Exploration Permit - 1st Period Assignment of rights to MDL Submitted November 29, 2019
20 866235/2007 9,829.78 MDL1 Exploration Permit - Replaced by 866229/2017 March 17, 2017
21 866729/2015 9,186.52 MDL1 Exploration Permit - 1st Period July 19, 2019
22 866730/2015 9,445.85 MDL1 Exploration Permit - 1st Period July 19, 2019
23 866342/2016 9,876.04 MDL1 Exploration Permit - 1st Period October 21, 2019 Notes:
1. MDL: Mineração Dardanelos Ltda; VMZ: Votorantim Metais Zinco SA. 2. Mining application submitted September 16, 2011. Awaiting decision.
RioOrinoco
Amazon
Amazon
Rio
Mam
ore
Rio Negro
Rio
Pur
us
Rio
Beni
Rio
Uca
yali
Rio
Tap
ajos
Rio
Xin
gu
Rio
Ara
guaia
Rio Paranaiba
Rio
Para
guay
Par
ana
Rio
Para
na
Rio Grande
Rio
Sao
Fra
nci
sco
Rio
Tocanti
ns
RioM
adeira
Rio
TelesP
ires
Rio
Juru
ena
Rio
SOUTH
PACIFIC
OCEAN
SOUTH
ATLANTIC
OCEAN
NORTH
ATLANTIC
OCEAN
Equator
Lago
Titacaca
SantaMarta Maracaibo
San Cristobal
Bucaramango
ValenciaBarcelona
Maturin
New Amsterdam
Oiapoque
Careiro
Itaituba
Santarem
Altamira
Cachimbo
Humaita
Boca doAcre
Iquitos
Cruzeiro do Sul
QuillabambaCusco
Guajara-Mirim
Cochabamba
Santa Cruz
CaceresRondonopolis
Barreiras
Vitoria daConquista
Ilheus
Juazeiro
Uberlandia
Santos
Sao Francisco do Sul
Foz do Iguacu
PontaPora
Corumba
Potosi
San Miguelde Tucuman
Mendoza
Colonia
Rio Grande
Mar del Plata
Bahia Bianca
Concepcion
Valparaiso
CordobaSanta Fe
Rosario
La Plata
Resistencia
Ciudaddel Este
Pedro Juan Caballero
Salta
Antofagasta
IquiquePanorama
Santa Fedo Sul
Puerto SuarezSucreOruro
Matarani
Arequipa
IloTacna
Arica
Inapari Guayaramerin
Salgueiro
Picos
Leticia
Puerto Carreno
CucutaCiudad Bolivar
Santa Elenade Uairen
Barquisimeto
BenjaminConstant
Assis Brasil
SantaMaria
Sao Luis
Teresina
Palmas
Goiania
BeloHorizonte
Vitoria
Rio de Janeiro
Curitiba
Florianopolis
Porto Alegre
SaoPaulo
Cuiaba
CampoGrande
Fortaleza
Natal
Recife
Maceio
Aracaju
Salvador
JoaoPessoa
Belem
Macapa
Manaus
PortoVelhoRio Branco
Boa Vista
Parnaiba
Maraba
Carajas
Araguaina
Bogota
CaracasPort-of-Spain
Paramaribo
Georgetown
Cayenne
Brasilia
La Paz
Asuncion
Santiago Buenos Aires
Montevideo
COLOMBIA
VENEZUELAGUYANA
SURINAMEFrenchGuiana(FRANCE)
PERU
BOLIVIA
PARAGUAY
ARGENTINACHILE
URUGUAY
TRINIDAD AND
TOBAGO
B R A Z I L
AMAZONAS
ACRE
RONDONIA
AMAPA
PARA
MARANHAO
CEARARIO GRANDE
DO NORTE
PARAIBA
ALAGOAS
PERNAMBUCO
SERGIPEBAHIA
ESPIRITO
SANTO
RIO DE
JANEIRO
PIAUI
TOCANTINS
MATOGROSSO
MATO
GROSSO
DO SUL
SANTA
CATARINA
RIO GRANDE
DO SUL
MINAS
GERAIS
SAO
PAULO
GOIAS
DISTRITO
FEDERAL
PARANA
The islands of Trinidade, Martin Vaz,
Arquipelago de Fernando de Noronha,
Atol das Rocas, and Penedos de Sao
Pedro a Sao Paulo are not shown.
Trinidade and Martin Vaz are administered by
Espirito Santo; Arquipelago de Fernando de
Noronha by Pernambuco.
70° 60° 50° 40°
10°
0°
10°
20°
30°
30°40°50°60°70°
30°
20°
10°
10°
0°
ARIPUANÃ ZINC PROJECT
International Boundary
Legend:
National Capital
State Boundary
Road
Railway
State Capital
0
0
200
200
400 Kilometres
400 Miles
N
July 2017
Location Map
Aripuanã Zinc Project
VM Holding S.A.
State of Mato Grosso, Brazil
Figure 4-1
4-3
www.rpacan.com
Municipalities
Mining Application
Deposit
Legend
216,000 220,000 224,000 228,000
8,88
0,00
08,
884,
000
8,88
8,00
08,
832,
000
8,83
6,00
0 216,000 220,000 224,000 228,000 232,000 236,000 8,896,0008,892,000
8,888,0008,884,000
0 4
Kilometres
321
N
July 2017 Source: Votorantim Metais, 2017.
Property Map
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 4-2
4-4
ww
w.rp
acan
.co
m
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 4-5
MINERAL RIGHTS Exploration and exploitation of mineral deposits in Brazil are defined and regulated in the 1967
Mining Code and overseen by the National Department of Mineral Production (DNPM). There
are two main legal regimes under the Mining Code regulating Exploration and Mining in Brazil:
Exploration Permit (“Autorização de Pesquisa”) and Mining Concession (“Concessão de
Lavra”).
Applications for an Exploration Permit (EP) are made to the DNPM and are available to any
company incorporated under Brazilian law and maintaining a main office and administration in
Brazil. EPs are granted following submission of required documentation by a legally qualified
Geologist or Mining Engineer, including an exploration plan and evidence of funds or financing
for the investment forecast in the exploration plan. An annual fee per hectare ranging from
US$0.35 to US$0.70, is paid by the holder of the EP to the DNPM, and reports of exploration
work performed must be submitted. During the period where a formal EP application has been
submitted by a company for an area, but not yet granted, with the exception of drilling,
exploration works are permitted. In this document, these areas are referred to as Exploration
Claims.
EPs are valid for a maximum of three years, with a maximum extension equal to the initial
period, issued at the discretion of the DNPM. The annual fee per hectare increases by 50%
during the extension period. After submission of a Final Exploration Report, the EP holder
may request a mining concession. Mining concessions are granted by the Brazilian Ministry of
Mines and Energy, are renewable annually, and have no set expiry date. The concessions
remain in good standing subject to submission of annual production reports and payments of
royalties to the federal government.
Areas where the maximum extension of an EP has been reached, and a positive Final
Exploration Report and mining concession request have not been submitted by the company,
are designated with a status of “Available”. Following expiry, the DNPM will receive EP
applications from the public, including the first owner, for a period of 60 days. If any valid,
external EP applications are submitted during this period in addition to the first owner’s
application, the DNPM will review, with consideration of the work completed, and decide to
whom it will issue the permit. Before a decision is reached, claim status is set to “In Dispute”.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 4-6
SURFACE RIGHTS Surface rights can be applied for if the land is not owned by a third party. The owner of an EP
is guaranteed, by law, access to perform exploration field work, provided adequate
compensation is paid to third party landowners and the owner accepts all environmental
liabilities resulting from the exploration work.
VMH has purchased additional surface rights directly overlying the Arex, Ambrex, and Babaçú
deposits since 2012. Surface rights adjacent to the properties and necessary for mine
development are currently being negotiated by VMH. Figure 4-3 displays a map of surface
rights currently held by VMH in relation to the mineral deposits.
ROYALTIES AND OTHER ENCUMBRANCES Royalties applicable to the Project are detailed in Table 4-2.
TABLE 4-2 ROYALTY DATA VM Holding S.A. – Aripuanã Zinc Project
Receiver of Royalty Arex Ambrex Other Deposits
Gar
impe
iros
Expedito 42.5%
2% NSR from the start of the first sale of concentrate
Divino 21.25% Joaquim 21.25% Neder 5% Zadir 5% Max 5%
Luiz de Almeida 1.5% of net sales from the first sale of the mineral product
Anglo American1 2% NSR of 70% mining product of Zn, Pb, Cu, Au and Ag from the first of the beginning of the marketing of concentrates or June 13, 2013.
1.5% NSR of 70% of the mining product of Zn, Pb, Cu, Au and Ag
Notes:
1. Anglo American royalty is owed by VMH only.
PERMITTING RPA is not aware of any environmental liabilities on the property. VMH has all required permits
to conduct the proposed work on the property. RPA is not aware of any other significant factors
and risks that may affect access, title, or the right or ability to perform the proposed work
program on the property.
225,000
8,8
88
,00
0
228,000227,000224,000 226,000
8,8
89
,00
08
,88
7,0
00
8,8
86
,00
0
8,8
88
,00
08
,88
9,0
00
8,8
87
,00
08
,88
6,0
00
225,000 228,000227,000224,000 226,000
AMBREX
BABAÇU
AREX
LINK
8,8
8,0
00
5
8,8
8,0
00
5
Mineralization Projected to Surface
Legend:
Outline of Surface Rights
Transmission Line
0 500
Metres
1000 1500 2000
N
July 2017 Source: Karmin Exploration Inc., 2012.
Surface Rights Map
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 4-3
4-7
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 5-1
5 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE AND PHYSIOGRAPHY ACCESSIBILITY The Aripuanã Zinc property is located in the northwest corner of the state of Mato Grosso,
western Brazil. It can be accessed from the town of Aripuanã by a 25 km unpaved road, which
is well maintained in the dry season. Aripuanã can be accessed from the Mato Grosso capital
of Cuiabá by a 16 hour drive (935 km) on paved and unpaved roads BR-163/BR364, MT-160,
MT-220, MT-170, MT-208, MT-418, and MT-206. The final 250 km between Cuiabá and
Aripuanã are on unpaved roads, which are in poor condition and require substantial upgrades
to ensure road access to site. Aripuanã is also serviced by an unpaved airstrip suitable for
light aircraft. At the time of both site visits, no commercial flights were travelling between
Cuiabá and Aripuanã and access to site was accomplished via a three-hour chartered flight.
On the property, temporary roads link drill hole site locations, with the main access gravel road
from Aripuanã.
CLIMATE The climate in the area is hot and humid, with distinct dry (April to September) and wet (October
to March) seasons. It is classified as a “Tropical Savanna Climate” in the Koppen Climate
Classification due to its high mean temperature and marked wet and dry seasons. The mean
annual temperature is 24°C, with monthly average temperatures ranging between 20°C and
30°C. Average annual rainfall is 2,750 mm and annual average evaporation is 1,216 mm.
LOCAL RESOURCES The economic base in Aripuanã is rooted in the extractive industries, predominantly timber,
agriculture, and tourism. Although located in the Amazon district, deforestation has occurred
and the area is defined mostly by plantations of rubber and soy beans, as well as artisanal
mining operations. No skilled mining workforce exists in the district. Aripuanã has a hospital
and related medical facilities as well as primary and secondary schools.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 5-2
INFRASTRUCTURE Infrastructure is limited at, and adjacent to, the property. Infrastructure includes a core handling
facility located in the town of Aripuanã. Multi-purpose storage sheds are located at the facility
and a nursery for drill site and road reclamation is located on site. There are 270 km of
unpaved roads on site, which are difficult to traverse during the rainy season (November to
April). The gas price is very elevated in the region and there is a very high cost associated
with maintenance of the roads.
Services to the property are provided by the town of Aripuanã, which includes accommodation,
restaurants, and stores.
The Dardanelos Hydropower dam (261 MW) was completed at Aripuanã in 2011,
approximately 20 km from the Project. A thermal power plant next to the Aripuanã airport
(Guaçu Power Plant), which uses woodchips and waste as fuel, has a generation capacity of
30 MW.
Numerous rivers occur close to the Project and water supply is not expected to be an issue.
PHYSIOGRAPHY The Project lies between 250 MASL and 350 MASL, and comprises seven occurrences of
mineralization: Arex, Ambrex, Babaçú, Massaranduba, Boroca, Arpa, and Mocoto, over a 25
km strike length. The Arex, Ambrex, and Babaçú deposits are visible as three tree covered
mounds on a steep ridge surrounded by flat ground. Vegetation is dense on the ridge but has
been largely cleared in surrounding areas which are used primarily for agricultural purposes.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 6-1
6 HISTORY PRIOR OWNERSHIP The following information is summarized from AMEC International (Chile) S.A. (AMEC, 2007).
Gold mineralization was discovered in the area during the 1700s by prospectors and a small
fort was constructed to protect the portage at Aripuanã’s Cachoeira de Andorinhas (Swallow
Falls). No details of the extent of extraction of gold on the property during this time are
available. Between 1979 and 1990, artisanal gold miners extracted gold from the Aripuanã
area, mostly through gold panning and small excavations. It is thought that at one time up to
2,000 artisanal gold miners were active in the district. One large pit, named Expedito’s pit, was
excavated during this time and is approximately 200 m deep.
Western Mining Corporation (WMC) held an exploration licence on the property between 1992
and 1994. No details of exploration work completed during this time are available.
Anglo American began exploration over the property in 1995. At the time, a small area
including Expedito’s Pit, now part of the Project, was held by Madison do Brasil (now Thistle
Mining Inc.). This claim was optioned to Ambrex Mining Corporation (now Karmin). Between
1997 and 1999, Karmin optioned its property to Noranda, which withdrew from the option
without earning an interest after completing 24 drill holes on the property.
Dardanelos was created in 2000 to represent a joint venture, or “contract of association”,
between Karmin and Anglo American, with the intent of exploring for base and precious metals
in areas adjacent to the town of Aripuanã. Anglo American and Karmin held 70% and 28.5%
of Dardanelos, respectively, with the remaining interest (1.5%) owned by SGV.
In 2004, the initial agreement between Karmin and Anglo American was amended to allow
VMH’s participation. Through exploration expenditures of US$1.6 million between May 2004
and December 2005, VMH acquired 70% of Anglo American’s interest in the Project (70%).
The remaining 30% of the interest was acquired over the following year. In 2007, Karmin
purchased SGV’s interests, raising its interest to 30%.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 6-2
Currently, Aripuanã is a jointly held property by VMH (70%) and Karmin (30%). Karmin is not
required to contribute financially to the Project until the completion of a bankable feasibility
study. In the meantime, VMH is fully funding the Project development. Upon completion of a
bankable feasibility study, Karmin will contribute on a pro-rata basis towards bringing Aripuanã
into production.
EXPLORATION AND DEVELOPMENT HISTORY Excluding drilling, the following exploration activities have been undertaken on the Aripuanã
Zinc Project:
1. A SPECTREM airborne geophysical survey
2. Geological mapping
3. Ground geophysics
4. LiDAR airborne survey
5. Soil geochemistry
This work was carried out by Anglo American and Karmin in 1999-2002. Since 2004,
exploration has been conducted by VMH, and is described in more detail in Section 9
Exploration.
HISTORICAL RESOURCE ESTIMATES Previous Mineral Resource estimates have been completed on the property by AMEC in 2007
and by RPA in 2012 and 2017 for Karmin, which are superseded by the Mineral Resource
estimate presented in Section 14 of this report.
PAST PRODUCTION Approximately 350,000 ounces of gold are thought to have been extracted by artisanal miners
during the 1979 and 1990 gold rush. There has not been any formal production to date on the
property.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 7-1
7 GEOLOGICAL SETTING AND MINERALIZATION REGIONAL GEOLOGY The South American Platform is mainly composed of metamorphic and igneous complexes of
Archean/Proterozoic age and makes up the continental interior of South America. The
Platform consolidated during Late Proterozoic to Early Paleozoic times in the course of the
Brasiliano/Pan-African orogenic cycle during which the amalgamation of different continents
and micro continents with closure of several ocean basins led to the formation of the
Supercontinent Gondwana. Archean and Proterozoic rocks are exposed in three major shield
areas within the framework of Neoproterozoic fold belts (Guiana, Central Brazil, and Atlantic
shields). The western continental margin of the South American Plate developed from at least
Neoproterozoic to Early Paleozoic times and constitutes a convergent margin, along which
eastward subduction of Pacific oceanic plates beneath the South American Plate takes place.
Through this process, the Andean Chain, the highest non-collisional mountain range in the
world, developed. The eastern margin of the South American Plate forms a more than 10,000
km long divergent margin, which has developed as a result of the separation of the South
American Plate and the African Plate since the Mesozoic through the opening of the South
Atlantic and the break-up of Gondwana. The northern and southern margins of the South
American Plate developed along transform faults in transcurrent tectonic regimes due to the
collision of the South American Plate with the Caribbean and the Scotia plates. The South
American Plate reveals a long and complex geologic history (Engler, 2009). Figure 7-1 is a
simplified geological map of Brazil.
The Project is underlain by Paleoproterozoic and Mesoproterozoic-aged (1.80 Ga to 1.55 Ga)
lithologies belonging to the Río Negro-Juruena Province, one of six major geochronological
provinces comprising the Amazonian Craton. The Río Negro-Juruena Province occupies a
large portion of the western part of the Amazonian Craton (Figure 7-2) and includes volcano-
sedimentary sequences, felsic plutonic-gneiss, and granitoids. Rift basins within the province
are filled with continental platform molasse and marine sediments of Mesoproterozoic,
Paleozoic, and Mesozoic age (Engler, 2009). It is a zone of complex granitization and
migmatization. Regional metamorphism, in general, occurred in the upper amphibolite facies
(Tassinari et al., 2010).
ARIPUANÃ ZINC PROJECT
Sedimentary Rocks
Igneous and Metamorphic Rocks
Quaternary
Cretaceous-Tertiary Volcanics
Mesozoic Volcanics
Paleozoic-Mesozoic Intrusives
Precambrian Undifferentiated
Tertiary
Cretaceous
Jurassic-Cretaceous
Triassic
Permian
Carboniferous-Permian
Carboniferous
Devonian
Silurian
Cambrian-Ordovician
Paleozoic
66° 60° 5 °4 4 °8
28°
20°
1 °2
0°
7 °2 40° 36°
8°
4°
1 °6
2 °4
4°
28°
20°
1 °2
0°
8°
4°
1 °6
2 °4
66° 60° 5 °4 4 °87 °2 40° 36°
July 2017 Source: Votorantim Metais, 2017.
Regional Geology
Aripuanã Zinc Project
VM Holding S.A.
State of Mato Grosso, Brazil
Figure 7-1
7-2
www.rpacan.com
0°0'0
"
!(
60°0'0"W 50°0'0"W
10°0'0
"S
Bacia doAmazonas
Iquitos
Purus
Manaus Monte Alegre
Iricoume
Serra dosCarajás
Porto Velho
Bele
mGupupá
Xingu
Romaima
Imataca
Aripuanã
Legend:
Neoproterozoic Faults
Basement Structure
Strutures
Amazônia Central Province
( > 2.5 Ga )
Maroni-Itacaiúnas Province
Geocronological Provinces
Venturi-Tajapós Province
( 1,99 – 1,8 Ga)
Rio Negro-Juruena Province
(1,8 – 1,5 Ga)
Rondoniana-San Ignácio Province
( 1,55 – 1,3 Ga )
Sunsás Province
( 1,25 – 1,0 Ga)
Geological Units
Phanerozoic Cover
Granitoid
Precambrian Sedimentary Cover
Intermediate Acid Volcanic
Mafic Volcanics
Greenstone Belt
Granulitic Complex
Neoproterozoic Period
( 2,2 – 1,9 Ga)
0 2 00 1000
Kilometres
400 600 800
N
Source: Karmin Exploration Inc., 2012.July 2017
Geological Map of theAmazonian Shield
Aripuanã Zinc Project
VM Holding S.A.
State of Mato Grosso, Brazil
Figure 27-
7-3
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 7-4
LOCAL GEOLOGY The following is taken from Simon, Marinho and Lacroix (2007).
The Project area is underlain by a meta-volcano-sedimentary sequence known as the
Aripuanã Sequence or the Roosevelt Group (RG), which is interpreted as a back-arc setting
of the Tapajós arc. The sequence exhibits greenschist facies grade regional metamorphism,
and has been intruded by late-stage A-Type Granites. The sequence is associated with a
major intracontinental suture, which defines the margin of the Caiabís graben in the south. The
Aripuanã Sequence is bounded by granites and gneisses of the Xingu Complex in the north
through interrupted tectonic contacts.
The Aripuanã Sequence comprises three major meta-volcano-sedimentary units:
• a basal unit, represented by felsic and intermediate flows with tuffaceous layers
• an intermediate, transitional felsic volcanic unit
• an upper sequence, represented by inter-layered meta-argillites, meta-tuffs and meta-cherts
These units form a broad semicircular shape surrounding the Rio Branco granite. The
mineralized zones are located in the northeastern portion of the arc (Figure 7-3). Post-
mineralization aged overthrust faults, dipping to the north and northeast, form complex
imbricated sheets, which represent the most characteristic structural feature of the area.
Typically, these sheets include portions of the volcanic units, and the upper meta-sedimentary
unit, although often the contact relationships are obscured by extreme deformation.
The lithological assemblage generally strikes northwest-southeast and dips between 35° and
70° to the northeast. Stratigraphic features have been offset by younger sinistral, east-west
wrench faults that are traced by mapping and magnetic interpretation.
PROPERTY GEOLOGY The following has been summarized from VMH (2016).
Stratigraphy over the property consists of meta-sediments; meta-volcanic and meta-
pyroclastic rocks; and hydrothermally altered rocks at the interface between the meta-
sediments and meta-volcanics. The meta-sediments comprise meta-mudstones, meta-
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 7-5
siltstones, and carbonaceous meta-siltstone, while the meta-volcanics and meta-pyroclastics
grade from rhyolite to dacite in composition. The hydrothermal zone occurs as stratabound
when related to exhalative rocks or pipe like when related to the feeder zone. The stratabound
portion of the hydrothermal zone has three main types of alteration; carbonate, tremolite, and
sericitic. The feeder or stringer zone has three types of alteration; sericitic, phyllic (sericite +
chlorite), and chloritic (+silicification). On surface, the hydrothermal alteration zone is strongly
masked by tropical weathering, usually associated with gossans. Portions of the property have
Phanerozoic alluvial cover.
Figure 7-3 shows the property geology.
BASELINE
AREX
AMBREX
AR
PA
BA
SE
LIN
E
55
85
35
70
60
65
70
8080
75
6565
65
45
55
50
EXRP01
EX RP02
EXRP03 EXRP04
EXR
P05EXR
P06
EXRP07EXRP08
EXRP09E XRP10
EXRP11
EXRP12
EX RP13
EXRP14EXRP15
EXRP16
EXRP17
E XRP18EX RP19
FD056
FD057
FD057A
FD059
FD060
FD061
FD062
FEX01
FEX02
FEX03
FEX04
FEX05
FEX06
FEX07
FEX08
FEX09
FEX10
FEX11
FEX 12
FEX13
FEX14
FEX15
FEX16
FEX17
FEX18
FEX19
FEX20
FEX21
FEX22
FEX23FEX24
FEX25
FEX26
FEX27
FEX28
FEX29
FEX30
FEX31
FEX32
FEX33
FEX34
FEX35
FEX36
FEX37
FEX38
FEX39
FEX40
FEX41
FEX42
FEX43
FEX44
FEX45
FEX 46
FEX47
FEX48
FEX49
FEX50
FEX51
FEX 52
FEX53
FEX54
FEX55
FEX56
FEX57
F001
F002
F003
F004
F005
F006
F007
F008
F009
F010
F011
F012
F013
F014
F015F016
F017
F018
F019
F020
F021
F022
F023
F024
F025F026
F027
F028
F029
F0 30
F031
F032
F033
F034
F035
F036
F037
F038
F039
F040
F041
F042
F043
F044
F045
F046
F047
F048
F049
F050F051
F052
F053
F054
F054A
F055
FPAR001
FPAR002
FPAR003
FPAR003A
FPAR004
FPAR004A
FPAR005
FPAR005A
FPAR006
FPAR006A
FPAR008
FPAR009
FPAR010
FPAR011
FPAR012
FPAR013
FPA R014
FPAR015FPAR016
FPA R017
FPAR018
FPAR019
FPAR020FPA R021
FPAR022
FPAR023
FPA R024
FPAR025
FPAR026
FPA R027
FPAR028FPAR029
FPAR032
FPAR036
FPAR037
FPAR038
FPAR
039
FPAR042
FPA R044
FPAR047
FPAR048
FPAR049
FPAR050
FPA R051
FPA R052
FPAR053
FPAR054
FPAR055
FPAR056
FPAR058
FPAR059
FPAR060
FPAR061
FPAR062
FPAR063
FPAR065
FPAR066
FPAR068
FPAR069
FPAR070
FPAR071
FPAR072
FPAR073
F PAR074
FPAR076
BA
SE
LIN
E
888
4000
,,
88
86
00
0,
,8
885
00
0,
,
BASELINE
MASSARANDUBA
3300SSE
2.90
0NW
500NNW
1000
SE
3.90
0NW
00
888
7000
,,
889
0000
,,
230 000,229 000,228 000,227 000,226 000,225 000,224 000,
88
88
000
,,
88
89
000
,,
BABACU
888
4000
,,
88
86
00
0,
,8
885
00
0,
,8
88
7000
,,
889
0000
,,
88
88
000
,,
88
89
000
,,
888
000
,3
,
888
000
,3
,
230 000,229 000,228 000,227 000,226 000,225 000,224 000,
Alluvial
Lithology:
Siltites, Argilites, Carbonatic Philytes
Quartz Veins
Hydrothermal Zone
Volcanics
SA
GS
AS
QV
ZH
FV
Gossan
Falha Transcorrente Dextral
Falha Transcorrente Sinistral
Thrust Fault
Banding S1/S0 with dip
Foliation S2 with dip
Fault
0 0.5
Kilometres
1 1.5 2
N
Source: Amec, 2007 (Edited from Petrus, 2006).July 2017
Property Geology
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 7-3
7-6
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 7-7
MINERALIZATION Three main elongate mineralized zones, Arex, Link, and Ambrex, have been defined in the
central portion of the Aripuanã Project. A smaller, deeper zone, Babaçú, lies to the south
(stratigraphic footwall) of Ambrex. Limited exploration has identified additional, possible
mineralized bodies including Massaranduba, Boroca, and Mocoto to the south and Arpa to the
north.
Where outcropping, sulphide mineralization has been oxidized forming gossanous bodies
which frequently mark the position of overthrust faults. These gossans are generally small,
and contain low levels of gold. They do not appear to be economic at this time.
The individual mineralized bodies have complex shapes due to intense tectonic activity.
Stratabound mineralized bodies tend to follow the local folds, however, local-scale, tight
isoclinal folds are frequently observed, usually with fold axes that are parallel to major reverse
faults, causing rapid variations in the dips. The Ambrex, Arex, Link, and, to a limited extent,
Babaçú deposits, represent the best understood zones and are described below.
Hydrothermal alteration is commonly directly adjacent to the Arex, Ambrex, and Babaçú zones,
and according to Leite et al. (2005, as cited in AMEC, 2007) presents a zonal and symmetrical
standard:
• External zone: Sericite and muscovite in a fine-grained matrix with minor chlorite content. Where present, the low sulphide content is dominated by pyrrhotite.
• Intermediate zone: Transition of sericite to chlorite halo on stringer zones. Tremolite and chlorite alteration with minor carbonatization and silicification.
• Internal zone: Stringer zones are characterized by pervasive chlorite alteration accompanied by quartz veins. Sulphide content is dominated by chalcopyrite and pyrrhotite. Porphyroblastic magnetite and biotite locally substitutes within the sulphide matrix. The stratabound zones are dominated by tremolite, talc and carbonate alteration, accompanied by sphalerite, galena and pyrite, with minor magnetite and fluorite. The stratabound zone may be brecciated.
AREX Mineralization at the Arex deposit strikes at approximately 110° azimuth, extending over a
1,400 m strike length. Upper portions of the deposit tend to be near-vertical, while lower
portions dip at 60° to the northeast. The deposit is characterized by well-defined stringer and
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 7-8
stratabound zones. Discrete lenses of stratabound and stringer mineralization, ranging from
less than one metre to 15 m thick, interplay within a 100 m to 150 m wide zone, separated by
barren, hydrothermally altered rocks. Mineralization comes close to outcropping at surface,
and extends to almost 500 m below surface. Discrete lenses may be continuous for up to 300
m down dip. The Arex deformation pattern is made of tight, foliation-parallel folds, and reverse
faults which overthrust in the same direction. The deposit presents strong dip variations that
are often parallel to foliation and faults. In some areas, this may cause the stratabound and
stringer mineralization to be parallel, despite its original perpendicular position.
AMBREX The Ambrex deposit represents the largest of the known mineralized zones on the Project.
The Ambrex deposit is located approximately 1,300 m southeast of Arex. Mineralization strikes
at approximately azimuth 125° and has a strike extent of approximately 1,050 m, based on
current drilling. The dip varies from near vertical to 70° to the northeast. Mineralization
thicknesses typically range between 10 m and 50 m, with a maximum of 150 m. The Ambrex
deposit has an upper depth of 60 m below surface, with a lower depth of approximately 700
m. The degree of folding is gentler than at Arex and hosts well marked overthrust faults, which
are parallel to metamorphic foliation. The orientation of the stratabound mineralization is
generally parallel to the original bedding, while the stringer zone is often approximately
perpendicular to the stratabound zone.
LINK ZONE The Link Zone target, first discovered in 2014, is interpreted to be the westward extension of
the Ambrex deposit towards the Arex deposit. It is located approximately 300 m southeast of
Arex and exhibits shape, mineralization, and alteration features similar to Ambrex. Based on
current drilling, the Link Zone has a strike extent of approximately 400 m.
BABAÇÚ Located southeast of Ambrex, the Babaçú deposit is 600 m long and also dips to the northeast.
Similar to Ambrex, the stringer zone is limited in extent and is understood to occur in discrete,
thin lenses perpendicular to the stratabound mineralization.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 8-1
8 DEPOSIT TYPES The following is summarized from VMH (2012c).
The Aripuanã polymetallic deposits are typical Volcanogenic Massive Sulphide (VMS) deposits
associated with felsic bimodal volcanism. Support for this model is based on the geometry of
mineralization, host rocks, hydrothermal alteration, and sulphide paragenesis. The VMS
deposits have been subsequently deformed and metamorphosed under greenschist facies
conditions (Leyte, 2005 and Petrus, 2006, as cited in VMH, 2012c). Details observed at
Aripuanã and consistent with VMS deposits are described below.
1. Host rocks. All mineralized bodies are located on the upper levels of a felsic volcanic unit, in association with finely laminated exhalites, at or close to the contact with an overlying sedimentary unit.
2. Mineralization zonality and predominant textures. Three types of mineralization are found on the property, and are typical of VMS deposits elsewhere: • Stringer facies: Cu-Au bearing stringers in the footwall of the stratabound
mineralization, containing chalcopyrite and pyrrhotite, with stockwork and breccia textures corresponding to hydrothermal feeder zones;
• Proximal sulphide facies: mixed bodies of stratabound massive and disseminated Zn-Pb mineralization, overlying stringer mineralization;
• Distal sulphide facies: horizons of massive sulphide, stratabound Zn-Pb mineralization, often finely banded, with fine-grained pyrite, pyrrhotite, and sphalerite, sometimes associated with galena, corresponding to depositional areas distant from the feeder zones.
3. Geochemical zonality. The Cu/Cu+Zn ratio is higher in the proximity of the Cu-rich feeder zones, and decreases upward from the footwall and towards the distal Zn-rich stratabound mineralization.
Facies associated with the feeder zones are located in the middle of the volcanic unit and are
characterized by pyrrhotite and/or chalcopyrite stockworks in a zone of intense chloritic
hydrothermal alteration. The sulphide association represents a feeder zone at higher
temperature. There is Cu-Au association in these zones. A target model is shown in Figure
8-1.
Sericite-quartz
Chalcopyrite-pyrrhotite-pyrite
Pyrite-sphalerite-chalcopyrite
Pyrite-sphalerite-galena
Pyrite-sphalerite-galenatetrahedrite-Ag-Au
Chlorite-sericite
Quartz-chlorite
Barite (Au)
Carbonate/gypsum
1.3% Cu
6.1% Zn
1.8% Pb
123 g/t Ag
2.2 g/t Au
Average 5.5 Mt
Median 14.2 Mt
100 m
Felsic flow complex
Flows or volcaniclastic strataBIMODAL-FELSIC
Chalcopyrite-pyrite veins
Canadian gradeand tonnage
Ma
ssiv
e
Detrital
July 2017 Source: A.G. Galley et al., 2007.
Target Model
Aripuanã Zinc Project
VM Holding S.A.
State of Mato Grosso, Brazil
Figure 8-1
8-2
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 9-1
9 EXPLORATION 1999-2002 EXPLORATION This section is summarized from VMH (2012a).
Geochemical and geophysical surveys, including a SPECTREM airborne geophysical survey,
were conducted by Anglo American and Karmin between 1999 and 2002. The exploration
program targeted 13 different areas on the property. Limited details are available on the exact
date and operator of the various surveys conducted, however, the following information was
recovered in the Anglo American database (Table 9-1).
TABLE 9-1 ANGLO AMERICAN AND KARMIN EXPLORATION – 1999-2002 VM Holding S.A. – Aripuanã Zinc Project
Target Geological
Mapping Geochemistry Ground Geophysics Stream
Sediment Soil Gravimetry Magnetic IP VLF TDEM
Acampamento Velho x x x x Arex x x x x x x x Ambrex x x x x x x Babaçú x x x x Bigode x x x x x Cafundo x x x x x x Cone x x x x Joao Paulo x x x x Massaranduba x x x x Mocotό-Borόca x x x x x x Vaca II x x x x Valdir x x x x Vale dos Sonhos x x x x Note. IP – Induced Polarization; VLF – Very Low Frequency; TDEM – time-domain electromagnetics
GEOPHYSICS The airborne SPECTREM geophysical survey is an electromagnetic (EM) method developed
by Anglo American. Simultaneous EM, total field magnetic, and radiometric measurements are
taken from sensors inside, or towed behind, an aircraft. The survey was conducted in 2001
over 1,800 km2.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 9-2
No specific details are available with respect to ground geophysical methods.
GEOCHEMISTRY No details of sample procedures, quality assurance/quality control (QA/QC), or dates were
available. Historically, 760 stream sediment samples and up to 32,000 soil samples with wide
distribution over 2,000 km2 have been collected. Analyses were conducted by Nomos and
Mineração Morro Velho (MMV) laboratories.
GEOLOGICAL MAPPING Geological mapping was completed to varying levels of detail over the thirteen targets listed in
Table 9-1 between 1999 and 2002.
VMH EXPLORATION The following is taken from AMEC (2007) and VMH (2012b).
In 2004, VMH became Project operator and commenced a detailed geological, geochemical,
and geophysical exploration program, which included additional drilling described in Section
10.
Under contract from VMH in 2005, Geoambiente Sensoriamento Remoto (Geoambiente)
prepared a topographic map based on photogrammetric restitution of two pairs of Ikonos
panchromatic images with one metre spatial resolution (173214-0/173214-3 and 173214-
1/173214-2), and with ground control on geodesic IBGE stations. Internal control points were
surveyed using a differential global positioning system (DGPS). The topographic map has an
area 195 km2 and has 1:10,000 altimetric and 1:5,000 planimetric scales as well as five metre
contour lines (plus additional one metre interpolations).
Integração Geofísica (Intergeo) compiled and integrated in 2004 all previous geological,
geophysical, and geochemical data to allow a more complete interpretation of the regional and
local geology, and the identification of local exploration targets. A digital terrain model was
prepared and integrated with airborne gamma-spectrometric (K-Th-U channels),
magnetometric, and electromagnetic (time domain EM) survey data, soil geochemical surveys,
regional and local geological information, including most of the data previously obtained by
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 9-3
Anglo American and Karmin. As a result of this study, five groups of targets were identified in
addition to Arex and Ambrex, and additional exploration was recommended.
In 2004, VMH contracted Petrus Consultoria Geológica Limitada (Petrus) to conduct and/or
supervise geological, geochemical, and geophysical exploration at the property. Between
2004 and 2007, additional exploration at the property included relogging of old Anglo
American/Karmin core, geological mapping, and geochemical surveys.
A time domain, airborne EM survey was conducted by Fugro Airborne Surveys in 2007. The
survey covered approximately 1.8 km2, divided in four loops of 700 m x 500 m each, with
readings on a 100 m by 20 m grid. The survey was flown over 14,290 m using a base
frequency of 30 Hz. In addition, 3,860 m were surveyed at 3 Hz in order to detail the anomalies
identified with the 30 Hz survey.
In 2008, exploration efforts consisted of evaluating regional targets. Work included detailed
geological mapping and systematic rock, soil, and stream sediment geochemistry. Mobile
metal ion (MMI) soil geochemical tests were completed on the Ambrex and Babaçú targets.
Core from Arex and Ambrex was re-logged. Exploration drilling at Babaçú and in-fill drilling at
Arex and Ambrex took place.
Extensive drilling took place on Arex and Ambrex in 2012, as well as additional metallurgical
test work.
In 2013, ground magnetic surveying totalling approximately 138 line-km over the Poraquê,
Arpa, Ambrex, Babaçú, Massaranduba, Boroca, and Mocotό targets was completed.
Subsequently, a 12 line-km ground magnetic survey was completed over the Casagrande
target. An extensive program of core re-sampling was completed comprising a total of 11,067
core and pulp analyses from 159 drill holes from Arex, Ambrex, Arpa, and Babaçú. A new
structural model was developed based on LiDAR topography in the Arex-Ambrex area and the
1:25,000 scale geological map was updated.
In 2014, ground magnetic surveying totalling approximately 222.8 line-km over the Flanco W,
Poraquê, Sombra, Mocotό Sul, Jibόia, and Casagrande targets was completed. A total of 991
soil samples were taken over the Somra and Casagrande targets and 25 gold panning samples
were taken at the Flanco W, Mocotό Sul, Jobόia, Sombra, and Vaca-Bigode targets.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 9-4
In 2015, a 1,584.2 line-km helicopter-borne, combined magnetic and electromagnetic (VTEM)
survey was flown over four areas, namely Arex-Ambrex, Flanco W, Mocotό, and Casagrande
Jibόia. Soil sampling at Flanco W and geological mapping and rock sampling at the Borόca
and Mocotό target areas was undertaken. In-fill drilling at Arex and Ambrex was also
completed.
EXPLORATION POTENTIAL
BABAÇÚ Based on review of 42 drill holes totalling 19,388 m in the Babaçú mineralized body and other
exploration work on the property such as airborne and ground geophysical surveys, geological
mapping, soil geochemistry, and drill testing of other targets, RPA estimates that the potential
tonnage and grade of mineralization at the Babaçú prospect could be three million to six million
tonnes grading from 3.0% Zn to 5.0% Zn, 1.0% Pb to 2.5% Pb, 0.2% Cu to 0.5% Cu, 0.15 g/t
Au to 0.4 g/t Au, and 10 g/t Ag to 30 g/t Ag. The potential quantity and grade is conceptual in
nature as there has been insufficient exploration to define a Mineral Resource, and it is
uncertain if further exploration will result in the target being delineated as a Mineral Resource.
The upper and lower values of the above grade ranges are based on the existing drill hole
information, with consideration given to the neighbouring bodies, Ambrex and Arex. The
estimated tonnage range is based on the dimensions of the Babaçú mineralized body tested
by 42 diamond drill holes.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 10-1
10 DRILLING Drilling on the Aripuanã Zinc property has been conducted in phases by several companies
since 1993. Total drilling at the two main deposits, Ambrex, including the Link Zone, and Arex,
consists of 538 diamond drill holes totalling approximately 151,144 m. Drilling at the other
prospects on the property consists of 77 diamond drill holes totalling 29,244 m.
A drilling summary by deposit up to and including all drilling information available at December
23, 2016, is presented in Table 10-1. A map of drill hole collars is shown in Figure 10-1.
TABLE 10-1 DRILL HOLE DATABASE VM Holdings S. A. – Aripuanã Zinc Project
Historical VMH (2004-2016) Total
Deposit No. DDH Metres No.
Perc. Metres No. DDH Metres No.
Met. Metres No. Holes Metres
Arpa 9 5,359 9 5,359 Arex 76 18,174 19 1,329 231 39,914 21 2,677 307 62,095 Ambrex (incl. Link Zone) 48 17,408 183 75,648 9 3,222 231 96,278 Babaçú 7 2,224 35 17,163 42 19,388 Massaranduba 8 2,184 18 6,343 26 8,527 Total 139 39,991 19 1,329 467 139,069 30 5,899 606 186,287
Notes:
DDH: Diamond drill hole Perc: Percussion drill hole Met: Metallurgical drill hole
PREVIOUS DRILLING This section is summarized from AMEC (2007).
Limited detail on the Anglo American and Karmin drilling campaigns is available. Both RC and
diamond drilling was performed on site. Results of RC drilling have not been maintained in
the current VMH database. Diamond drill core diameter was HQ (63.5 mm) size. The DDI
Reflex Fotobor method was used for downhole survey measurements. Most holes were drilled
with azimuths ranging from 180° to 220° and inclinations ranging from -50° to -70°. Drill core
boxes are stored on site, and are adequately labelled and ordered for efficiently locating and
extracting the samples. Original drill reports are not available on site.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 10-2
RECENT DRILLING Drilling was conducted by VMH on the property from 2004 to 2008 and from 2012 to present.
The main purpose of the drill program from 2004 to 2008 was to explore and delineate
mineralization on the property and from 2012 to present, to improve confidence and support
and upgrade the classification of the Mineral Resources at the Arex and Ambrex deposits.
VMH drilled a total of 497 diamond drill holes totalling 150,327 m at Aripuanã Zinc from 2004
to year-end 2016, including 30 metallurgical drill holes totalling 5,899 m. Many drill holes were
pre-collared using RC drill rigs, with diamond drill rigs used for drilling in mineralized zones.
December 23, 2016 is the cut-off date of the Mineral Resource database; all assay results
received before this date have been considered in the Mineral Resource estimate.
Drill hole locations are spotted in the field using a hand-held GPS. Small adjustments to the
drill hole locations are made where necessary based on topographic relief and non-removable
trees. The desired collar position, foresights, and backsights are marked by technicians using
a compass. Collar surveying is performed with a differential GPS upon completion of the drill
hole and the departing collar azimuth is recorded using a total station. Casings are left in
place. Downhole surveying is completed with Deviflex and Maxibor tools by the drilling
company at three metre intervals downhole. Duplicate downhole surveys are performed on
each hole. From 2014 onwards, VMH has implemented core orientation for approximately
25% of the drilling using the Reflex ACT core orientation tool.
Drill core is currently placed in plastic boxes and labelled at the rig site prior to transport.
Previously, wooden core boxes were used. Drill core is transported by pick-up truck to the
VMH logging facility by the drill company employees, Servitec Sondagem Geologica.
Geotechnicians measure drill core runs and note core interval length, core loss, and check
core block runs. This information is then cross referenced to the driller’s notes for
discrepancies and amended where necessary. Rock Quality Designation (RQD) is measured
and a resistance value (R0 to R4) is assigned based on rock hammer tests. No other
geotechnical logging is performed on site. The core is photographed both wet and dry prior to
mark-up by geologists.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 10-3
All geological information is manually logged on paper logging sheets, and then hand entered
into formatted Microsoft Excel sheets by the logging geologist. Lithology, rock unit, texture,
alteration associated with the VMS, and regional alteration are recorded in logging sheets as
text fields. The percentage of total sulphides, pyrite, pyrrhotite, chalcopyrite, sphalerite, and
galena are recorded. Observations are noted where relevant. Digital logging sheets are
imported into the database management program GeoExplo by the database manager. For
oriented core, alpha and beta angles are recorded along with structural descriptions. The
alpha and beta angles are converted to dip and dip direction using a Microsoft Excel macro.
RPA is of the opinion that the drilling and logging procedures meet industry standards.
225,000
226,000 227,000
8,8
88,0
00
8,8
88,0
00
226,500
226,000 227,000226,500
8,8
87,5
00
8,8
88,0
00
8,8
87,5
00
8,8
88,5
00
224,500 225,500 226,000
8,8
88,0
00
8,8
88,5
00
225,000224,500 225,500 226,000
A: Arex Deposit
B: Ambrex Deposit and Link Zone
Section
Faults
Section
Faults
Mudstones and Siltstones
Legend:
Hydrothermal Alteration Zone
Gossan
Pyroclastic rocks (chloritization)
Pyroclastic Rocks
AS
GS
ZH
Chl FT
FT
Felsic VolcanicsFV
0 100 200 Metres
0 100 200 Metres
N
N
July 2017 Source: Votorantim Metais, 2017.
Drill Hole Collar Map
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 10-1
10-4
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-1
11 SAMPLE PREPARATION, ANALYSES AND SECURITY SAMPLING METHOD AND APPROACH Core is sampled 10 m above and below visible mineralization. Samples respect geological
contacts, and vary from 0.5 m to 1.5 m in length depending on core recovery, length of the
lithological unit, and mineralization. Geologists mark the samples using a felt pen on the core
boxes, and staple a sample tag wrapped in plastic to the box at the start of the sample.
The core is marked with red and blue lines to indicate where the core is to be sampled and
which half is to be assayed. The lines are drawn respecting the geological features such as
layering to help minimize sampling bias. Prior to sampling, sample numbers are recorded in
the GeoExplo data management system and cross-referenced with the interval depth
downhole and the depth recorded in the database.
Sample core is cut into two halves by technicians with a diamond saw, returning half of split
the core to the core box and submitting the other half for sample preparation and analysis.
The geologist responsible for logging the drill hole defines the insertion of QA/QC samples
including blanks, standards, and duplicates.
Each sample booklet contains four tags for each sample. One sample tag is stapled to the
clear plastic sample bag and an additional sample is placed within the bag. One tag is attached
to the core box while the remaining tag is left in the booklet for record keeping.
The samples are separated into batches of up to 250 samples and each from the same drill
hole.
DENSITY ANALYSIS The bulk density is determined by the water displacement method for each sample of drill core.
Samples are dried and then weighed using a tared Adventurer Pro scale accurate to 0.1 g.
The sample is then added to a polyvinyl chloride (PVC) tube containing a fixed amount of
water. The displaced water is removed from the PVC tube into a pre-weighed 1,000 mL
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-2
beaker. The weight and volume of displaced water is recorded by hand and then entered into
a spreadsheet. Density values are auto-calculated using both volume and weight of water.
The technician compares the values to ensure that they are similar. Any discrepancy results
in a repeat of the test. The weighted measurement is used in the final database.
Every tenth sample is also subject to an Archimedes density measurement. The Archimedes
density results are kept on site and used as a QA/QC measure. The results of the Archimedes
method are typically within 10% of the water displacement method.
SAMPLE PREPARATION Sample preparation was performed by the ACME preparation facility in Goiania, Brazil, from
2004 to 2007, and from 2007 on, by ALS Global. Both laboratories followed the same
preparation procedure, described below.
The sample was logged in the tracking system, weighed, dried, and finally crushed to better
than 70% passing a 2 mm screen. A split of up to 250 g was taken and pulverized to better
than 85% passing a 75 micron screen. This sample preparation package was coded PUL-31
by ALS Global. Following preparation, samples were shipped to the sample analysis facility
in Lima, Peru. ALS Global’s preparation facility in Goiania is accredited to the International
Organization for Standardization/International Electrotechnical Commission (ISO/IEC)
9001:2008 standards and ALS Global is accredited to ISO 9001:2008 (expires 2018) and
ISO/IEC 17025:2005 (expires 2018), for all relevant procedures.
Both laboratories are independent of VMH. In RPA’s opinion, the sample preparation methods
are acceptable for the purposes of a Mineral Resource estimate.
SAMPLE ANALYSIS Assays were processed by ACME from 2004 to 2007, and from 2007 on, by ALS Global. ALS
Global’s facilities in Lima are accredited to ISO 9001:2008 (expires 2018) and ISO/IEC
17025:2005 (expires 2018).
The following sample analysis was undertaken at the ACME facilities:
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-3
1. Gold Analysis: Fire assay (50 g) standard fusion method with an atomic absorption spectrometry (AAS) finish. The lower limit of detection is 0.01 g/t Au.
2. Multi Element Analysis: Aqua regia digestion with an AAS finish. Lower limits of detection are 0.001% for lead, zinc, and copper, 1 ppm for silver, and 0.01% for iron.
The following sample analysis is undertaken at the ALS Global facilities in Lima, Peru.
1. Gold Analysis: Au-AA24. A 50 g fire assay standard fusion method with an AAS finish. The lower limit of detection is 0.005 ppm Au and the upper limit of detection is 10 ppm Au.
2. Gold Analysis: Au-AA26. Gold analyses returned from Au-AA24 with a gold value
above 10 ppm are re-assayed using a 50 g fire assay standard fusion method with an AAS finish. Upper limit of detection is 100 ppm.
3. Multi Element Analysis: ME-ICP61. 33 multi element suite using four acid digestion and inductively coupled plasma atomic emission spectroscopy (ICP-AES) finish. The upper detection limit for lead, zinc, and copper is 1% and 100 ppm for silver.
4. Multi Element Analysis: ME-AA62. Samples that return values above the upper limits
in ME-ICP61 are re-assayed using ME-AA62. In ME-AA62, four acid digestion with an AAS finish of a 0.4 g sample is used. Lower limits of detection are 0.001% for lead, zinc, and copper, and 1 ppm for silver.
5. High Grade Zinc Analysis: Zn-VOL70. Zinc analyses returned from ME-AA62 with a zinc content over 30% are re-analyzed by dissolving in hydrochloric acid and titrated with EDTA solution with Xylenol orange as an indicator.
6. High Grade Iron Analysis: Fe-VOL51. Iron analyses returned from ME-ICP61 with
iron content over 50% are re-analyzed by dissolving in hydrochloric acid and titration.
Both laboratories are independent of VMH. In RPA’s opinion, the sample analysis methods
are acceptable for the purposes of a Mineral Resource estimate.
DATABASE MANAGEMENT Database management is performed by a dedicated onsite geologist under the supervision of
the Project Geologist. Digital logging sheets prepared by the geologist are uploaded to the
database management system GeoExplo. Original drill logs, structural logs, geotechnical logs,
details of chain of custody, site reclamation, and drilling are stored on site in a folder, specific
to a single drill hole. Folders are clearly labelled and stored in a cabinet in the office, which is
locked during out of office hours.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-4
Assay Certificates are mailed to the site by ALS Global and emailed to Julio Souza Santos,
Project Manager, and Thomas Brenner, both VMH employees. Certificates are reviewed by
Julio Souza Santos prior to uploading to GeoExplo.
SAMPLE CHAIN OF CUSTODY AND STORAGE Samples are shipped in rice bags by truck to the independent ALS Global preparation facility
in Goiania, Brazil. ALS Global purchased the facility from ACME Laboratories (ACME) in 2007.
Prior to 2007, all work was performed by ACME.
Drill core is stored at the onsite core storage facility, the grounds of which are locked at night
and surrounded by a high fence. The storage facility is open at the sides and covered with a
corrugated iron roof. Core storage map is maintained by onsite technicians. Pulp and coarse
rejects are shipped back to the onsite facility by the laboratory where they are also stored with
reference to individual sample locations.
QUALITY ASSURANCE/QUALITY CONTROL Samples are grouped into batches of 100. Five standards, two blanks, one field duplicate, one
pulp duplicate, and one reject duplicate are included in each sample batch. Total QA/QC
samples comprise 10% of the data. Blanks are inserted in the sample stream at the end of
visible mineralization, standards are randomly inserted within mineralized intervals, and pulp
and reject duplicates are randomly inserted in both mineralized and unmineralized intervals.
Field duplicates are taken within mineralization. No check assays are performed by an
alternate laboratory.
A QA/QC report is prepared monthly, by the onsite database manager and reviewed by the
Project Geologist. The report is also submitted to the head office for review. Batches of
samples identified by QA/QC as anomalous are repeated by ALS Global at the request of
VMH.
RPA reviewed results from VMH’s QA/QC program undertaken in 2016 and is of the opinion
that the results are sufficient to support Mineral Resource estimation.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-5
2004–2012 BLANKS Prior to 2012, blank material used was river sand and sandstone sourced from the property.
Subsequent to 2012, only coarsely crushed sandstone was used.
Figure 11-1 plots the blank results for zinc, lead, and copper. The highest failure rate was
observed with zinc, where 6% of samples reported a value greater than 20 times the detection
limit of the sample. All other metals reported less than 3% above a value equal to 20 times
detection limits. No time-based trends were identified. RPA is of the opinion that these results
are reasonable.
It should be noted that normal industry practice for blanks is setting a failure limit to ten times
the detection limit. In the case of the Zn, Pb, and Cu grades of interest, ten times the detection
limit is insignificant. RPA used 20 times the detection limit while VMH considers five times the
practical detection limit of 0.01%. RPA is of the opinion that either threshold is reasonable.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-6
FIGURE 11-1 BLANK RESULTS FOR ZINC, LEAD AND COPPER
CERTIFIED REFERENCE MATERIAL Results of the regular submission of certified material (standards) are used to identify problems
with specific sample batches and long-term biases associated with the primary assay
laboratory. RPA reviewed the results from seven different standards used from 2004 to 2012.
At the time of the RPA’s 2012 review, four different standards were in use on site, two of which
assess lead and zinc only. During May and June 2012, copper standards were implemented.
No gold standards were used at this time and RPA recommended the incorporation of gold
standards.
From 2004 to 2008, three, commercially sourced, certified reference materials (CRMs),
representing low, medium, and high grade zinc and lead were inserted at a rate of 5%. Copper,
silver, and gold CRMs were not used. In 2012, two CRMs sourced from VMH’s sedex mine,
Morro Agundo (MA), were used on site. In June 2012, two property specific CRMs were
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-7
generated and came into use on site. Standards were inserted in the overall sample stream
of drill core at a rate of five standards in 100 samples. The expected values and standard
deviations (SD) for the various standards are listed in Table 11-1.
TABLE 11-1 EXPECTED VALUES AND RANGES OF STANDARDS VM Holding S.A. – Aripuanã Zinc Project
AP0001 AP0002 MA002 MA004 H1 L1 M1
Date 2012 2012 2012 2012 2004 - 2008 2004 - 2008 2004 - 2008 Source Aripuanã Aripuanã MA MA Number 114 113 50 128 176 290 285 Zn (%) 4.85 9.14 14.22 2.91 7.69 0.75 2.83 SD 0.13 0.28 0.48 0.11 0.18 0.01 0.07 Pb (%) 3.07 6.15 1.613 0.938 4.82 0.47 0.99 SD 0.06 0.09 0.038 0.044 0.145 0.025 0.045 Cu (%) 0.47 1.45 0.000927 0.000650 - - - SD 0.02 0.06 0.000123 0.000097 - - - Ag (g/t) 96 207 1.53 1.18 - - - SD 2 5 0.16 0.22 - - -
A positive bias was identified in the low grade lead and zinc CRM used from 2004 to 2008, L1,
which is not expected to significantly impact the final result. The overall results from the 2004-
2008 submissions and from the 2012 Morro Agudo CRMs MA002 and MA004 are considered
acceptable.
A slight positive bias was identified in lead and zinc results of the newly created CRM AP0002.
Approximately 40% of lead results of AP0002 plotted outside of three standard deviations
(3SD) (Figure 11-2). Nine percent of zinc results from CRM AP0001 plotted above 3SD (Figure
11-3), and consecutive lead samples from AP0001 plotted below 3SD.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-8
FIGURE 11-2 CONTROL CHART FOR CRM AP0002: LEAD
FIGURE 11-3 CONTROL CHART FOR CRM AP0001: ZINC
DUPLICATES Field, pulp, and reject duplicate samples were analyzed using basic statistics, scatter plots,
quantile-quantile plots, and percent relative difference plots. All field duplicate pairs had a
better than 95% correlation, with the exception of gold, which was 90%. Pulp and reject
duplicates for all metals reported greater than 98% correlation. A graph of percent relative
differences for field, pulp, and reject duplicate zinc samples versus the mean value of the
duplicate pair is shown in Figure 11-4. The graph indicates good representation of zinc grades,
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-9
negligible bias, and good correlation. Similar findings were obtained for copper, lead, gold,
and silver (not shown).
FIGURE 11-4 PERCENT RELATIVE DIFFERENCE PLOT: ZINC DUPLICATE SAMPLES
2013 TO OCTOBER 2016 BLANKS Blank material is sandstone sourced from the property. Figure 11-5 plots the results for zinc,
lead, and copper. The highest failure rate was observed with zinc, where 11% of samples
reported a value greater than 20 times the detection limit of the sample. All other metals
reported less than 3% above a value equal to 20 times detection limits. In RPA’s opinion,
results of blank QA/QC tests are acceptable.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-10
FIGURE 11-5 BLANK RESULTS FOR ZINC, LEAD AND COPPER
CERTIFIED REFERENCE MATERIAL Results of the regular submission of certified reference material (standards) are used to identify
problems with specific sample batches and long-term biases associated with the primary assay
laboratory. RPA reviewed the results from 11 different standards used from 2012 to 2016. As
per RPA recommendation, two gold standards have been implemented since 2012. The
following summary describes the standards:
• AP series: four certified standards from the Aripuanã Zinc for Zn, Pb, Cu, and Ag
• MA series: two CRMs sourced from VMH’s sedex mine, Morro Agudo (MA) for Zn only and certified by SGS Geosol.
• L1, M1, H1: Low, medium and high grade CRMs for Zn and Pb
• G series: two Geostats CRMs for Au.
Standards were inserted in the overall sample stream of drill core at a rate of approximately
one standard for every 30 drill core samples. The expected values and SDs for the various
standards are listed in Tables 11-2 and 11-3.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-11
TABLE 11-2 EXPECTED VALUES AND RANGES OF STANDARDS VM Holding S.A. – Aripuanã Zinc Project – AREX
AP0001 AP0002 APPD003 APPD004 MA002 MA004 H1 L1 M1 G909-1 G312-4
Date 2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
Source Aripuanã Aripuanã MA MA
Number 264 258 53 51 50 128 25 57 35 112 116
Zn (%) 4.84 9.15 2.89 7.71 14.47 2.91 7.69 0.75 2.83 - -
SD 0.15 0.28 0.07 0.18 0.64 0.09 0.21 0.04 0.08 - -
Pb (%) 3.07 6.15 1.09 4.04 - - 4.90 0.47 1.00 - -
SD 0.07 0.24 0.03 0.56 - - 0.12 0.02 0.02 - -
Cu (%) 0.47 1.44 1.22 0.35 - - - - - - -
SD 0.02 0.04 0.03 0.01 - - - - - - -
Ag (g/t) 96.00 207.00 43.00 127.00 - - - - - - -
SD 2.64 5.80 1.551 3.184 - - - - - - -
Au (g/t) - - - - - - - - - 1.02 5.30
SD - - - - - - - - - 0.06 0.22
TABLE 11-3 EXPECTED VALUES AND RANGES OF STANDARDS VM Holding S.A. – Aripuanã Zinc Project – AMBREX
AP0001 AP0002 APPD003 APPD004 H1 L1 M1 APPD003 APPD004 G909-1 G312-4
Date 2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015
2012- 2015 2016 2016 2016 2016
Source Aripuanã Aripuanã
Number 246 259 72 73 58 118 126 187 189 103 97 Zn (%) 4.84 9.15 2.89 7.71 7.69 0.75 2.83 2.89 7.71 - - SD 0.12 0.25 0.08 0.18 0.22 0.03 0.11 0.07 0.18 - - Pb (%) 3.01 6.15 1.09 4.04 - - - 1.09 4.04 - - SD 0.07 0.23 0.03 0.07 - - - 0.03 0.08 - - Cu (%) 0.47 1.44 1.22 0.35 - - - 1.22 0.35 - - SD 0.02 0.03 0.03 0.01 - - - 0.04 0.01 - - Ag (g/t) 96.00 207.00 43.00 127.00 - - - 43.00 127.00 - - SD 2.21 5.46 1.532 3.045 - - - 1.522 3.335 - - Au (g/t) - - - - - - - - - 1.02 5.30 SD - - - - - - - - - 0.06 0.22
No positive bias was observed in any grade lead and zinc CRM used from 2012 to 2016.
Results from the 2012-2015 submissions of the Morro Agudo CRMs MA002 and MA004 are
acceptable.
The Geostats Au CRMs show no significant bias and perform well with no failures detected
based on the certified expected values and standard deviations.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-12
Slight positive bias was identified in lead and zinc results of CRMs AP0001 and AP002 in 2012,
however, it has subsided since 2013 (Figures 11-6, 11-7, and 11-8). Only less than 2% of zinc
results from CRM AP0001 plotted above 3SD, and consecutive lead samples from AP0001
plotted below 3SD.
FIGURE 11-6 CONTROL CHART FOR CRM AP0002: LEAD
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-13
FIGURE 11-7 CONTROL CHART FOR CRM AP0001: LEAD
FIGURE 11-8 CONTROL CHART FOR CRM AP0001: ZINC
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-14
DUPLICATES Field, pulp, and reject duplicate samples were analyzed using basic statistics, scatter plots,
quantile-quantile plots, and percent relative difference plots. All field duplicate pairs had a
better than 97% correlation, with the exception of gold, which was 73%. Pulp and reject
duplicates for zinc, lead, and silver reported greater than 99% correlation, while correlation for
reject duplicates for gold and copper was approximately 92%. A graph of percent relative
differences for field, pulp, and reject duplicate zinc samples versus the mean value of the
duplicate pair is shown in Figure 11-9. The graph indicates good representation of zinc grades,
negligible bias, and good correlation. Similar findings were obtained for copper, lead, gold,
and silver (not shown).
FIGURE 11-9 PERCENT RELATIVE DIFFERENCE PLOT: ZINC DUPLICATE SAMPLES
OCTOBER 2016 TO PRESENT BLANKS Blank material is sandstone sourced from the property. RPA reviewed the results for zinc,
lead, copper, and gold. The highest failure rate was observed with zinc, where 1.8% of
samples reported a value greater than ten times the detection limit of the sample (five of 280
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-15
samples). All other metals reported no values equal to ten times detection limits. In RPA’s
opinion, results of blank QA/QC tests are acceptable.
VMH uses greater than or equal to 30 times the detection limit of the analytical method to
define a blank sample failure. RPA recommends that VMH lower the failure criteria to 10 times
the detection limit.
STANDARDS Results of the regular submission of CRM standards are used to identify problems with specific
sample batches and long-term biases associated with the primary assay laboratory. RPA
reviewed the results from five different standards, summarized below:
• AP series: three certified standards from the Aripuanã Zinc for Zn, Pb, Cu, and Ag
• G series: two Geostats CRMs for Au
Standards were inserted in the overall sample stream of drill core at a rate of approximately
one standard for every 30 drill core samples. The expected values and SDs for the various
standards are listed in Table 11-4.
TABLE 11-4 LIST OF REFERENCE STANDARDS USED VM Holding S.A. – Aripuanã Zinc Project
Reference Standard Source
Zn Pb Cu Au (g/t) Grade StDev Grade StDev Grade StDev Grade StDev
APPD0003 Internal Standard 2.89 0.08 1.09 0.04 1.22 0.02 - - APPD0004 Internal Standard 7.71 0.18 4.04 0.07 0.346 0.007 - - APPD0005 Internal Standard - - - - 6.83 0.25 - -
G909-1 Geostats CRM - - - - - - 1.02 0.06 G312-4 Geostats CRM - - - - - - 5.30 0.22
RPA notes that the AP series internal standards and the Geostats Au CRM performance has
been evaluated based on population statistics. In RPA’s opinion, the upper and lower limits
applied appear reasonable.
With respect to the 2016 to 2017 standards inserted, RPA offers the following conclusions: GOLD
• Possible negative bias in G312-4 (2-3%, Figure 11-10), G909-1 does not show a bias.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-16
• Mislabelled CRM – G909-1 labelled as G312-4.
• Using certified expected grades and standard deviations, the gold CRMs performed well, with no failures detected.
ZINC
• Small positive bias observed in both AP standards (Figure 11-11).
• The observed bias was not significant (<2%).
• APPD003 appears to demonstrate a high calibration drift that is corrected to the expected value once analytical results drift near the expected value +2SD.
LEAD
• A small positive bias was observed in the internal standard data for batches analyzed from July to October 2016 (Figure 11-12).
• Conversely, a small negative bias was observed for internal standards analyzed from February to May 2016.
• No failures occurred, and neither bias was significant (<2%). COPPER
• No bias observed and the copper internal standards performed well (Figure 11-13).
• A single value plotted above 3SD in standard APPD0004, and consecutive lead samples from APD0004 plotted below 3SD.
In RPA’s opinion, the CRMs and internal analytical standard performance are acceptable.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-17
FIGURE 11-10 CONTROL CHART FOR CRM G312-4: GOLD
FIGURE 11-11 CONTROL CHART FOR INTERNAL STANDARD APPD0003: ZINC
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-18
FIGURE 11-12 CONTROL CHART FOR INTERNAL STANDARD APPD0004: LEAD
FIGURE 11-13 CONTROL CHART FOR INTERNAL STANDARD APPD0003: COPPER
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 11-19
DUPLICATES To evaluate the accuracy or reproducibility of the results by the laboratory, VMH inserted
coarse, pulp, and field duplicates into the sample stream. The order of insertion is random
and corresponds to approximately 4% of the volume of samples sent to the laboratory.
Field, pulp, and reject duplicate samples were analyzed using basic statistics, scatter, quantile-
quantile, and percent relative difference plots. Field duplicate pairs for zinc and lead had
greater than 99% correlation, copper had 96% correlation, and gold was substantially lower at
74%. Pulp and reject duplicates for zinc, lead, and silver reported greater than 99%
correlation, while correlation for reject duplicates for gold and copper was approximately 92%.
A graph of percent relative differences for field, pulp, and reject duplicate zinc samples versus
the mean value of the duplicate pair is shown in Figure 11-14. The graph indicates good
representation of zinc grades, negligible bias, and good correlation. Similar findings were
obtained for copper, lead, and gold (not shown).
In RPA’s opinion, the duplicate sample performance is acceptable.
FIGURE 11-14 PERCENT RELATIVE DIFFERENCE PLOT: ZINC DUPLICATE SAMPLES
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 12-1
12 DATA VERIFICATION VMH
VALIDATION OF ANGLO AMERICAN DATA From 1993 to 1997, assays from 56 FEX series drill holes from the Anglo American drilling
campaigns at Arex were completed by Mineração Morro Velho (MMV) and Nomos
Laboratories (Nomos) without the insertion of QA/QC samples into the sample stream. In
1997, for verification purposes, core was quartered over lengths of mineralized core and
reanalyzed either at the same lab or at a secondary lab (MMV, Nomos, ACME, or ALS
Chemex). It was noted that for Anglo American’s Salobo Project in the Carajás mineral
province, state of Pará, Brazil, Nomos was reporting significantly higher copper grades than
MMV but that MMV was comparable to ACME.
Based on this information, VMH adopted the following strategy:
1. Nomos assays were only used if MMV assays were not completed.
2. If the re-assay was performed at the same laboratory, the lower grade set of results was used.
A summary of the re-analyses is provided in Table 12-1.
TABLE 12-1 SUMMARY OF RE-ANALYSIS VM Holding S.A. – Aripuanã Zinc Project
Laboratory Number of Drill Holes
Original Analysis Nomos 19 MMV 42 ACME 1 Re-analysis Nomos 24 MMV 3 Re-analysis with QA/QC ACME 11 ALS Chemex 18
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 12-2
SOFTWARE VALIDATION VMH utilized GeoExplo and Leapfrog Geo’s validation features to identify issues including:
• Sample length issues;
• Maximum and minimum;
• Negative values;
• Detection limit / Zero values;
• Borehole deviations;
• Gaps;
• Overlaps;
• Drill hole collar versus topography;
• Datum;
• Laboratory certificate versus database values.
RPA reviewed the error report generated by Datamine Studio RM from the database text files
provided and did not note any significant errors.
RPA AUDIT OF DRILL HOLE DATABASE
LITHOLOGY RPA compared over 5% of lithology logs contained within the digital drill hole database (20
holes) to the original lithology logs stored on site. Many holes logged before 2007 had been
reinterpreted by VMH due to an update of the genetic model. RPA found these updates to be
incorporated into the lithology database. Two holes were identified as having differing
lithologies. Investigation by RPA revealed that the GeoExplo database was not updated
correctly after the lithology log was updated by the geologist. These errors were corrected in
the database by VMH geologists and are not expected to impact the Mineral Resource
estimate.
During the site visit in 2012, RPA compared drill holes FPAR339, FPAR273, and FPAR343
from the start to the end to the lithology logs and the final assay results. During the site visit
in 2017, RPA compared drill holes BRAPDD0055, BRAPDD0137, and BRAPDD0087 from the
start to the end to the lithology logs and the final assay results. Drill hole contacts agreed with
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 12-3
the logging results, and grades of zinc, lead, and copper were observed to correlate to sulphide
content. Alteration was noted where present.
ASSAY 2012 RPA compared 5% of the sample database to Assay Certificates from ALS. No major
discrepancies were found; however, the following was noted:
1. Over detection limit ICP results prior to 2007 were overwritten in the database with AA results, converted to a blank value in 2008, and recoded as 1.5x detection limit in 2012. Consistent treatment of over detection limit samples was recommended. If possible, these samples should be recorded in the database as received (>100).
2. Many certificates between August 30, 2007 and January 2008 appear to not contain any internal QA/QC data. This is evidenced by sequential sample numbering in the assay database, and cross checks with the QA/QC database provided to RPA. RPA recommended that QA/QC samples be included in every sample batch.
3. Inaccurate tabulation of assay values led to the exclusion of 35% of silver assays within the resource zone of Ambrex. RPA recommended that future updates incorporate these assays and that further QA/QC checks be put in place to prevent future exclusion of valid assay data.
2016 RPA compared 18% of the sample database to Assay Certificates from ALS received from
2013 to 2015. No material discrepancies were found.
RPA also confirmed that the 2012 tabulation error of silver values was resolved. RPA reviewed
the final grade fields and scripts used for combining a series of analytical procedures (over
limit sampling) and found the fields to be correctly tabulated.
2017 RPA compared 6% of the sample database to Assay Certificates from ALS received from 2015
to 2016. No major discrepancies were found.
DENSITY RPA compared measured density values by rock unit at Arex and Ambrex. Density values
less than 2 t/m3 (excluding oxide material) and greater than 5 t/m3 were considered outliers
based on cumulative distributions and removed from the database. Basic statistics of density
data are displayed in Figure 12-1 (Arex) and Figure 12-2 (Ambrex). Samples designated as
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 12-4
stratabound mineralization by logging geologists were found to have the highest density at
both Arex and Ambrex, followed by stringer mineralization. Little variance exists in any of the
other rock units; however, some mineralized hydrothermal zone samples reported high density
values.
RPA is of the opinion that the drill hole database has been maintained to a high standard and
is suitable to support Mineral Resource and Mineral Reserve estimation.
FIGURE 12-1 DENSITY MEASUREMENTS AT AMBREX BY ROCK UNIT
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 12-5
FIGURE 12-2 DENSITY MEASUREMENTS AT AREX BY ROCK UNIT
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-1
13 MINERAL PROCESSING AND METALLURGICAL TESTING INTRODUCTION An extensive number of studies were carried out from 2005 to 2013 for the Aripuanã Zinc
Project in order to identify the best processing option. The evolution of the key studies and
the process technologies under consideration were documented (VMH, 2015) and reported
previously (RPA, 2017). The optimum process route was defined through an advanced
metallurgical study and it was determined that sequential flotation (Cu-Pb-Zn) presented better
recoveries and concentrate grades than bulk flotation.
Additional test work on drill core from the Aripuanã Zinc Project was conducted by SGS
GEOSOL from May 2016 to January 2017 to provide experimental data to support engineering
studies. Information on sample validation and additional metallurgical testing has largely been
provided by Validaçao das Amostras Selecionadas para Teste Metalurgico (LCASSIS
Consultoria em Recursos Minerais (LCASSIS), 2017), the SGS GEOSOL Report (SGS
GEOSOL, 2017), and the Metallurgical Testwork Report (Worley Parsons, 2017a).
METALLURGICAL SAMPLING Three master composite samples representing the Arex Stratabound, Arex Stringer, and
Ambrex Stratabound deposits were prepared from original drill core. These samples were
subjected to comminution, flotation, rheology, settling, and filtration bench scale tests, as well
as chemical and mineralogical characterization (SGS GEOSOL, 2017).
Shipments of samples for testing included:
• First shipment (May 2016) – 100 kg sample from the Arex body; material was combined to form a composite sample (75% Arex Stratabound, 25% Arex Stringer) for preliminary flotation test work in Phase 1 testing.
• Second shipment (July 2016) – 550 kg sample; core samples were combined to form three master composites: Arex Stringer, Arex Stratabound, and Ambrex Stratabound, which were used for optimization and definitive flotation tests.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-2
• Variability Samples (July 2016) – 500 kg sample; core samples were combined to form ten Arex Stringer variability samples, ten Arex Stratabound variability samples, and eight Ambrex variability samples.
Detailed sample preparation for comminution was conducted by SGS GEOSOL to generate
representative aliquots of material in specific size intervals for different types of tests. The
material for comminution testing was sent to SGS Chile, while Bond Ball Mill Grindability testing
was conducted at SGS GEOSOL.
Material crushed to 2.0 mm was homogenized and separated into one kilogram sub-samples,
which were placed in plastic bags, sealed, and stored in a freezer for flotation test work.
Figures 13-1 and 13-2 illustrate the location of the metallurgical samples selected relative to
the Life of Mine (LOM) stopes and the representativeness of sampling in each deposit.
Source: Votorantim Metais, 2017.July 2017
A LOM stopes (grey wireframe) andrex samples selected (pink dots).
Location of ArexMetallurgical Samples
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 13-1
13-3
ww
w.rp
acan
.co
m
Source: Votorantim Metais, 2017.July 2017
Ambrex LOM stopes (grey wireframe) and samples selected (pink dots).
Location of AmbrexMetallurgical Samples
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 13-2
13-4
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-5
METALLURGICAL TESTING
PHASE 1 The 2016 metallurgical test program was carried out in two phases. In Phase 1, a single bulk
master composite sample of Arex Stringer and Stratabound mineralization representing both
deposits at a ratio of 75% Stratabound to 25% Stringer mineralization was tested. Twenty-
four open circuit bench scale flotation tests and two locked cycle tests (LCT) were conducted
using the blended composite sample. The purpose of the testing was to verify the primary
grind size (as this has implications for the downstream backfill plant) and to confirm if treating
a blended mineralization would result in good metallurgical performance, when compared to
treating the materials separately. Information on preliminary flotation test work is presented in
detail in Appendix G of the SGS GEOSOL Report.
Preliminary test results indicated that a sequential flotation circuit with a short talc pre-flotation
step followed by talc depression at a coarse primary grind size of P80 (80% passing) of 150 µm
produced acceptable results (see Table 13-1). The results were as follows:
• Final Cu concentrate: 30.3% Cu, 80.4% recovery.
• Final Pb concentrate: 45.4% Pb, 91.5% recovery (although zinc contamination of the lead concentrate was high).
• Final Zn concentrate: 56.3% Zn, 83.9% recovery
Although parameters were not optimized, circuit conditions were identified for use in the next
phase of testing. The overall results from LCT were consistent with previous LCT and the Zn
and Pb concentrate quality was higher than previous results. A blended composite of the Arex
mineralization resulted in acceptable metallurgical performance in Phase 1 testing.
TABLE 13-1 PHASE 1 - LCT 2 RESULTS VM Holding S.A. – Aripuanã Zinc Project
Grade (%) Recovery (%)
Product Cu Fe MgO Pb Zn S Cu Fe MgO Pb Zn S
Calculated Feed 0.59 15.5 12.1 1.61 3.50 8.40
Talc Rougher Conc. 0.57 14.9 11.0 1.60 3.80 7.59 9.52 1.43 4.14 1.17 0.70 1.31
Copper Recleaner Conc. 30.3 29.0 0.59 1.50 4.66 33.4 80.43 2.95 0.08 1.39 1.86 6.68
Lead Recleaner Conc. 0.62 12.9 1.88 45.4 11.6 20.8 3.48 2.77 0.55 91.50 9.85 8.84
Zinc Recleaner Conc. 0.20 9.02 0.10 0.44 56.3 35.5 1.99 3.43 0.05 1.57 83.92 26.55
Final Tailings 0.09 15.1 12.2 0.10 0.19 4.91 14.09 90.86 99.32 5.54 4.38 57.93
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 13-6
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-7
PHASE 2 In Phase 2 testing, a more comprehensive testing program was undertaken on both blended
and individual Arex and Ambrex materials and variability testing was conducted on the different
lithologies (SGS GEOSOL, 2017). Test work consisted of comminution, flotation, mineralogy,
thickening, filtration, and rheology testing. Bench scale flotation tests were conducted to
establish circuit parameters for various mineralization blends, before conducting LCT. A series
of LCT were carried out on each master composite sample and various blends to optimize
circuit performance and to evaluate the flowsheet configuration. Information on optimization
flotation test work is presented in detail in Appendix H of the SGS GEOSOL Report. Optimum
conditions from development test work were applied to testing various variability samples.
COMMINUTION A variety of comminution test work was completed, including:
• CWi (Crushing Work Index)
• SMC (Semi-Autogenous Grinding (SAG) Mill Comminution)
• SPI (SAG Power Index)
• BWi (Bond Work Index)
• Ai (Bond Abrasion Index)
Information on comminution test work is presented in detail in Appendix E of the SGS GEOSOL
Report. A brief description of these tests and the results are summarized below.
CWi
The Bond Impact Work Index can be determined from the CWi test and used to calculate net
power requirements for sizing crushers. Also, this index can be used to determine the required
open sized settings for jaw crushers and gyratory crushers, or closed sized settings (cone) to
achieve a given product size. Table 13-2 summarizes the results of CWi testing. Arex Stringer
mineralization is considered to be moderately hard, while Ambrex is classified as soft.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-8
TABLE 13-2 CWI RESULTS VM Holding S.A. – Aripuanã Zinc Project
Sample Maximum
Impact Work Index
Minimum Impact Work Index
Average Impact Work Index Specific gravity
Arex STB 18.47 4.39 9.13 3.31 Arex STR 18.81 4.83 9.32 2.93 Ambrex 10.91 3.87 6.35 3.67
Notes: STB – Stratabound, STR – Stringer
SMC
SMC results are used to determine the drop weight index (DWi), which is a measure of the
strength of the rock when broken under impact conditions. The DWi is directly related to the
JK rock breakage parameters A and b, which can be used to estimate these parameters. The
JKTech Abrasion Test determines the parameter, Ta, which characterizes the resistance of the
particles to fracture by abrasion. If the value of Ta is low, then there is a higher resistance to
abrasion. The results of SMC testing are summarized in Table 13-3.
TABLE 13-3 SMC RESULTS VM Holding S.A. – Aripuanã Zinc Project
Sample DWi
(kWh/m3) A b A x b SG Ta
Arex STB 5.83 56.5 0.95 53.7 3.12 0.44 Arex STR 9.42 54.2 0.57 30.9 2.92 0.27 Ambrex 6.86 59.2 0.85 50.3 3.45 0.38
SPI
SPI is a measure of the hardness of an ore from a SAG (Semi-Autogenous Grinding) or AG
(Autogenous Grinding) perspective and the test measures the energy required to perform a
standard size reduction. The tests are aimed at determining SAG and ball mill power
requirements.
SPI determinations were conducted for all master composite and variability samples (total of
30 samples) and the results are presented in Table 13-4. SGS Chile did not convert SPI
minutes into power, therefore SPI values were not used in any comminution simulations. The
results did not show a wide variation in hardness within the deposit. Samples were
characterized as soft to moderate and the average SPI value for variability samples was 59.6
minutes.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-9
TABLE 13-4 SPI RESULTS VM Holding S.A. – Aripuanã Zinc Project
Sample Number Sample SPI (minutes)
Arex Stratabound (STB) Master Composite 47 Arex Stringer (STR) Master Composite 88 Ambrex Stratabound (STB) Master Composite 48 1 Arex STB Variability – High Sulphur 44 2 Arex STB Variability – Tremolite 55 3 Arex STB Variability – Pyrrhotite 80 4 Arex STB Variability – High Zinc 68 5 Arex STB Variability – Low Iron 47 6 Arex STB Variability – Low Zinc 52 7 Arex STB Variability – Pyrite 63 8 Arex STB Variability – Talc 39 9 Arex STB Variability – Chlorites 78 10 Arex STB Variability – Carbonates 44 11 Arex STR Variability – Low Iron 66 12 Arex STR Variability –Sulphur 81 13 Arex STR Variability – High Pyrrhotite 71 14 Arex STR Variability – High Gold 79 15 Arex STR Variability – High Pyrite 67 16 Arex STR Variability – High Copper 78 17 Arex STR Variability – Talc 53 18 Arex STR Variability – High Iron 81 19 Arex STR Variability – Low Copper 69 20 Ambrex STB Variability – Low Zinc 46 21 Ambrex STB Variability – Carbonates 40 22 Ambrex STB Variability – Pyrrhotite 62 23 Ambrex STB Variability – Talc 50 24 Ambrex STB Variability – High Zinc 54 25 Ambrex STB Variability – Sulphides 55 26 Ambrex STB Variability – Pyrite 47 27 Ambrex STB Variability – Tremolite 40
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-10
TABLE 13-5 BWI RESULTS VM Holding S.A. – Aripuanã Zinc Project
Sample Number Sample BWi (kWh/t)
Arex Stratabound (STB) Master Composite 10.6 Arex Stringer (STR) Master Composite 12.4 Arex Mix 12.1 Ambrex Stratabound (STB) Master Composite 10.8 / 10.3 1 Arex STB Variability – High Sulphur 8.6 2 Arex STB Variability – Tremolite 9.9 3 Arex STB Variability – Pyrrhotite 12.1 4 Arex STB Variability – High Zinc 10.6 5 Arex STB Variability – Low Iron 8.9 6 Arex STB Variability – Low Zinc 11.8 7 Arex STB Variability – Pyrite 10.8 8 Arex STB Variability – Talc 9.9 9 Arex STB Variability – Chlorites 11.2 10 Arex STB Variability – Carbonates 11.8 11 Arex STR Variability – Low Iron 11.9 12 Arex STR Variability –Sulphur 12.4 13 Arex STR Variability – High Pyrrhotite 13.6 14 Arex STR Variability – High Gold 12.7 15 Arex STR Variability – High Pyrite 12.9 16 Arex STR Variability – High Copper 14.2 17 Arex STR Variability – Talc 14.1 18 Arex STR Variability – High Iron 14.6 19 Arex STR Variability – Low Copper 12.9 20 Ambrex STB Variability – Low Zinc 9.5 21 Ambrex STB Variability – Carbonates 9.9 22 Ambrex STB Variability – Pyrrhotite 11.1 23 Ambrex STB Variability – Talc 10.2 24 Ambrex STB Variability – High Zinc 10.3 25 Ambrex STB Variability – Sulphides 10.4 26 Ambrex STB Variability – Pyrite 9.1 27 Ambrex STB Variability – Tremolite 9.6
BWi
BWi determinations were performed on master composites and all variability samples. A total
of 31 BWi determinations were carried out using a closing screen size of 150 µm. Table 13-5
lists the BWi results. No major difference was noted between the master composites and the
variability samples. The material is classified as moderate to soft based on the BWi results.
Ai
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-11
Ai can be used to determine steel media and liner wear in crushers, rod mills, and ball mills.
The Ai results are summarized in Table 13-6 and the mineralization is moderately abrasive.
TABLE 13-6 AI RESULTS VM Holding S.A. – Aripuanã Zinc Project
Sample Ai
Arex Stratabound Master Composite 0.086 Arex Stringer Master Composite 0.1425
Ambrex Master Composite 0.1448
RWi
RWi can be used to calculate net power requirements of the mill circuit, where the mill operates
in closed circuit with a classifier. The RWi results are listed in Table 13-7.
TABLE 13-7 RWI RESULTS VM Holding S.A. – Aripuanã Zinc Project
Sample RWi
Arex Stratabound Master Composite 12.2 Arex Stringer Master Composite 15.4
Ambrex Master Composite 11.2 FLOTATION Phase 2 flotation testing was conducted using master composite samples of the Arex
Stratabound, Arex Stringer, and Ambrex Stratabound mineralization, as well as three Arex
blended mineralization with varying ratios of Stratabound to Stringer material (i.e., 75%:25%,
50%:50%, and 25%:75%). The main objective of this phase of testing was to determine the
best grade and recovery achievable for each sample under different reagent dosages and
flotation times under a sequential flotation scheme (Cu-Pb-Zn). The test program and results
were documented in detail by SGS GEOSOL.
A simplified diagram of the sequential flotation process developed is illustrated in Figure 13-3.
The optimization test work determined that the best LCT results in terms of concentrate grades
and recoveries achieved were as follows (SGS GEOSOL, 2017):
• Arex Stratabound master composite: LCT 028
• Arex Stringer master composite: LCT 011 and LCT 025 (copper flotation only)
• Arex Mixed (75% Stratabound, 25% Stringer): LCT 030
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-12
• Ambrex Stratabound master composite: LCT 029
The results from these tests are summarized in Tables 13-8 to 13-14 and the key findings are
as follows:
• Master composites of Arex Stratabound and Ambrex Stratabound mineralization were similar in Zn and Pb feed assays and Zn and Pb flotation recovery, however, the Ambrex sample exhibited low copper concentrate grade and recovery.
• The Arex Stringer master composite sample was high in Cu feed assay and the resulting Cu concentrate was also high in grade and recovery. Zn and Pb concentrate grades and recovery were low, because the feed grades of Zn and Pb were low.
• The Arex Mixed sample (75% Stratabound, 25% Stringer) exhibited the best flotation results:
o Cu concentrate: 31.3% Cu, 76.9% recovery o Pb concentrate: 51.7% Pb, 82.4% recovery o Zn concentrate: 52.4% Zn, 83.9% recovery
• Treatment of Ambrex Stratabound mineralization is still a work in progress, as
concentrate grades for Zn and Pb were below target.
• Cycles on the majority of LCT were not stabilized, thus an additional campaign of testing is recommended to confirm results.
• Flotation columns are preferred and widely accepted in industry for use in the final cleaning stage, however, column flotation testing has not been carried out at the bench scale.
FEED ROUGHER
ROUGHER
TALC PRE-FLOAT COPPER FLOTATION
TALC TAIL
CLEANER
1stCLEANER
1stCLEANER
2ndCLEANER
2ndCLEANER
2ndCLEANER
COPPERFINAL CONC
LEADFINAL CONC
ROUGHER
FINAL TAIL
ZINC RGH TAIL
ZINC FLOTATION
1stCLEANER
ROUGHER
ZINCFINAL CONC
LEAD FLOTATION
July 2017 Source: Votorantim Metais, 2017.
Simplified SequentialFlotation Circuit
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 13-3
13-1
3
ww
w.rp
acan
.co
m
TABLE 13-8 SUMMARY OF KEY OPTIMIZATION LCT RESULTS VM Holding S.A. – Aripuanã Zinc Project
Grade DistributionCu %
Pb %
Zn %
Mg %
Fe %
Au ppm
Ag ppm
Wt. %
Cu %
Pb %
Zn %
Mg %
Fe %
Au %
Ag %
LCT 028 – Arex Stratabound Master Composite Calculated feed 0.33 1.53 4.51 7.03 12.9 0.20 33.7 100 100 100 100 100 100 100 100
Talc tail 0.04 0.73 2.30 11.6 8.21 17.5 2.11 8.36 8.92 28.9 11.1 Cu final conc. 26.7 3.63 7.16 0.79 31.7 11.3 1,068 0.86 69.5 2.05 1.37 0.10 2.11 49.7 27.2 Pb final conc. 0.81 60.6 8.39 0.54 5.89 1.53 852 2.01 4.92 79.8 3.74 0.15 0.92 15.6 50.7 Zn final conc. 0.26 0.54 48.6 0.98 9.38 0.24 40.0 7.64 6.01 2.70 82.5 1.06 5.55 9.34 9.06 Rougher tail 0.08 0.15 0.22 6.81 14.4 72.0 17.4 7.08 3.5 69.8 80.3
LCT 011 – Arex Stringer Master Composite Calculated feed 1.02 0.18 0.24 2.62 11.2 0.5 12.5 100 100 100 100 100 100 100 100
Talc tail Due to the low content of talc in feed, talc flotation was excluded from LCT circuit in this test Cu final conc. 25.4 2.68 4.45 0.43 33.1 13.5 253 3.85 95.7 55.8 71.8 0.64 11.4 93.3 77.7 Pb final conc. 1.93 10.7 3.85 1.69 31.7 4.65 210 0.67 1.26 38.6 10.8 0.43 1.89 6.3 11.2 Zn final conc. 0.46 0.20 4.89 3.80 17.5 0.31 12.0 0.48 0.21 0.50 9.5 0.67 0.72 0.29 0.44 Rougher tail 0.03 0.01 0.02 2.71 10.1 95.0 2.79 5.14 7.97 98.3 86.0
LCT 025 – Arex Stringer Master Composite (copper flotation only) Calculated feed 1.02 0.19 0.26 2.34 11.2 0.49 12.5 100 100 100 100 100 100 100 100
Talc tail Due to the low content of talc in feed, talc flotation was excluded from LCT circuit in this test Cu final conc. 26.7 1.84 2.63 0.54 36.2 13.8 252 3.73 98.1 35.4 37.5 0.87 12.1 93 75.1 Pb final conc. Due to the low content of lead in feed, lead flotation excluded from LCT circuit in this test Zn final conc. Due to the low content of zinc in feed, zinc flotation excluded from LCT circuit in this test Rougher tail 0.02 0.13 0.17 2.41 10.2 96.3 1.89 64.6 62.5 99.1 87.9
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 13-14
Grade DistributionCu %
Pb %
Zn %
Mg %
Fe %
Au ppm
Ag ppm
Wt. %
Cu %
Pb %
Zn %
Mg %
Fe %
Au %
Ag %
LCT 030 – Arex Mixed (75% Stratabound ore, 25% Stringer ore) Calculated feed 0.45 1.34 3.56 5.90 12.2 0.27 28.4 100 100 100 100 100 100 100 100
Talc tail 0.06 0.64 1.56 11.8 8.28 13.1 1.75 6.22 5.73 26.1 8.88 Cu final conc. 31.3 1.14 3.45 0.28 35.2 14.4 660 1.10 76.9 0.93 1.06 0.05 3.17 58.4 25.5 Pb final conc. 1.45 51.7 10.4 0.49 12.0 2.8 741 2.14 6.95 82.4 6.26 0.18 2.11 22.0 55.8 Zn final conc. 0.31 0.81 52.4 0.66 9.65 0.3 44.0 5.69 3.95 3.43 83.9 0.63 4.51 6.32 8.81 Rougher tail 0.06 0.12 0.14 5.52 12.7 78.0 10.5 6.97 3.1 73.1 81.3
LCT 009 – Ambrex Stratabound Master Composite Calculated feed 0.08 1.89 4.36 5.38 17.0 0.18 36.7 100 100 100 100 100 100 100 100
Talc tail 0.02 1.06 2.36 11.6 9.65 5.58 1.38 3.13 3.02 12.0 3.17 Cu final conc. 4.54 3.38 2.49 12.0 10.9 6.76 1,117 1.05 58.9 1.88 0.60 2.34 0.67 38.9 32.0 Pb final conc. 0.18 43.9 6.50 0.65 20.0 0.61 446 3.62 8.05 84.0 5.40 0.43 4.27 12.1 44.0 Zn final conc. 0.13 0.61 53.9 0.13 11.3 0.30 43.0 7.02 11.3 2.26 86.8 0.17 4.67 11.6 8.23 Rougher tail 0.02 0.20 0.22 5.54 17.9 82.7 20.4 8.74 4.2 85.1 87.2
LCT 029 – Ambrex Stratabound Master Composite Calculated feed 0.07 1.64 4.39 5.11 20.5 0.18 36.7 100 100 100 100 100 100 100 100
Talc tail 0.02 1.05 2.51 11.8 11.6 13.1 4.01 8.40 7.50 30.2 7.43 Cu final conc. 24.6 3.13 8.58 0.52 28.3 57.4 3,328 0.11 40.3 0.20 0.21 0.01 0.15 33.7 9.72 Pb final conc. 0.30 40.8 6.12 0.33 24.6 1.83 466 3.01 13.8 74.9 4.19 0.19 3.61 30.2 38.3 Zn final conc. 0.15 0.90 45.3 0.52 14.5 0.39 52.0 8.21 18.8 4.51 84.7 0.84 5.81 17.6 11.6 Rougher tail 0.02 0.26 0.20 4.65 22.5 75.6 23.1 12.0 3.44 68.8 83.0
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 13-15
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-16
TABLE 13-9 LCT 028 CONDITIONS AND RESULTS– AREX STRATABOUND MASTER COMPOSITE
VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-17
TABLE 13-10 LCT 011 CONDITIONS AND RESULTS– AREX STRINGER MASTER COMPOSITE
VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-18
TABLE 13-11 LCT 025 CONDITIONS AND RESULTS– AREX STRINGER MASTER COMPOSITE
VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-19
TABLE 13-12 LCT 030 CONDITIONS AND RESULTS– AREX MIX (75% STRATABOUND, 25% STRINGER)
VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-20
TABLE 13-13 LCT 009 CONDITIONS AND RESULTS– AMBREX STRATABOUND MASTER COMPOSITE VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-21
TABLE 13-14 LCT 029 CONDITIONS AND RESULTS– AMBREX STRATABOUND MASTER COMPOSITE VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-22
RPA has reviewed the concentrate grades and recovery assumptions in the VMH LOM cash
flow model for the Aripuanã Zinc Project and there are inconsistencies in the figures in
comparison to the metallurgical test data (Table 13-15). In some cases where the LOM
assumption differs from the test data, VMH has chosen to select the average of the last three
LCT results, however, the LOM assumptions for the silver and gold recoveries appear to be
the same as the reported test results. In RPA’s opinion, the metallurgical test results should
be referenced in a manner that is consistent for all LOM assumptions (i.e., using the final
concentrate grades and recoveries) and the assays of any penalty elements should be
reported.
Based on a review of available metallurgical data, RPA is of the opinion that any deleterious
elements that could have a significant effect on potential economic extraction should be further
examined. If tremolite material is present (Worley Parsons, 2017b), then this may have
implications in processing.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-23
TABLE 13-15 COMPARISON OF METALLURGICAL DATA VM Holding S.A. – Aripuanã Zinc Project
Description Value in LOM model
Test data Test RPA Comments
System 1 – Arex Stringer
Cu Concentrate
VMH states that LCT 025 was used to represent Arex Stringer
mineralization and that the LOM assumptions refer to the average of
the last three LCT results. Cu Recovery (%) 95.7 LCT 011
Cu Grade (%) 25.4 LCT 011 Ag Recovery (%) 77.7 LCT 011 Au Recovery (%) 93.3 LCT 011 Cu Recovery (%) 96.0 98.1 LCT 025 LOM assumption < test data
Cu Grade (%) 27.3 25.1 LCT 025 LOM assumption > test data Ag Recovery (%) 75.1 75.1 LCT 025
Au Recovery (%) 93.3 93.0 LCT 025 LOM data appears to reference LCT 011 data
Cu Concentrate Cu Recovery (%) 96.0 95.7 LCT 011
Cu Grade (%) 27.3 25.4 LCT 011 LOM assumption > test data Ag Recovery (%) 75.1 77.7 LCT 011 LOM assumption < test data Au Recovery (%) 93.3 93.3 LCT 011 System 2 – Arex Stratabound Cu Concentrate Cu Recovery (%) 67.6 69.5 LCT 028 LOM assumption < test data
Cu Grade (%) 26.8 26.7 LCT 028 Ag Recovery (%) 27.2 27.2 LCT 028 Au Recovery (%) 49.7 49.7 LCT 028 Pb Concentrate Pb Recovery (%) 83.0 79.8 LCT 028 LOM assumption > test data
Pb Grade (%) 62.8 60.6 LCT 028 LOM assumption > test data Ag Recovery (%) 50.7 50.7 LCT 028 Au Recovery (%) 15.6 15.6 LCT 028 Zn Concentrate Zn Recovery (%) 82.4 82.5 LCT 028
Zn Grade (%) 49.0 48.6 LCT 028 Ag Recovery (%) 9.1 9.06 LCT 028 Au Recovery (%) 9.34 LCT 028 System 3 – Arex Mix (75% Stratabound, 25% Stringer) Cu Concentrate Cu Recovery (%) 72.0 76.9 LCT 030 LOM assumption < test data
Cu Grade (%) 30.8 31.3 LCT 030 LOM assumption < test data Ag Recovery (%) 25.5 25.5 LCT 030 Au Recovery (%) 58.4 58.4 LCT 030
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-24
Description Value in LOM model
Test data Test RPA Comments
Pb Concentrate Pb Recovery (%) 81.3 82.4 LCT 030 LOM assumption < test data
Pb Grade (%) 55.9 51.7 LCT 030 LOM assumption > test data Ag Recovery (%) 55.8 55.8 LCT 030 Au Recovery (%) 22.0 22.0 LCT 030 Zn Concentrate Zn Recovery (%) 80.0 83.9 LCT 030 LOM assumption < test data
Zn Grade (%) 52.0 52.4 LCT 030 Ag Recovery (%) 8.8 8.81 LCT 030 Au Recovery (%) 6.32 LCT 030 System 4 – Ambrex Stringer (STR)
Cu Concentrate
LOM assumptions are the same as System 1 – Arex Stringer.
Metallurgical testing was not conducted.
Cu Recovery (%) 96.0 Cu Grade (%) 27.3
Ag Recovery (%) 75.1 Au Recovery (%) 93.0 System 5 – Ambrex Stratabound
Cu Concentrate LOM Ambrex STB data is identical to Arex STB data
Cu Recovery (%) 67.6 40.3 LCT 029 LOM assumption > test data Cu Grade (%) 26.8 24.6 LCT 029 LOM assumption > test data
Ag Recovery (%) 9.7 9.72 LCT 029 Au Recovery (%) 33.7 33.7 LCT 029
Pb Concentrate LOM Ambrex STB data is identical to Arex STB data
Pb Recovery (%) 83.0 74.9 LCT 029 LOM assumption > test data Pb Grade (%) 62.8 40.8 LCT 029 LOM assumption > test data
Ag Recovery (%) 38.3 38.3 LCT 029 Au Recovery (%) 30.2 30.2 LCT 029
Zn Concentrate LOM Ambrex STB data is identical to Arex STB data
Zn Recovery (%) 82.4 84.7 LCT 029 LOM assumption < test data Zn Grade (%) 49.0 45.3 LCT 029 LOM assumption > test data
Ag Recovery (%) 11.6 11.6 LCT 029 Au Recovery (%) 17.6 LCT 029 System 6 – Ambrex Mix (75% Stratabound, 25% Stringer)
Cu Concentrate
LOM assumptions are the same as System 2 – Arex Stratabound. Metallurgical testing was not
conducted Cu Recovery (%) 72.0
Cu Grade (%) 30.8 Ag Recovery (%) 25.5 Au Recovery (%) 58.4
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-25
Description Value in LOM model
Test data Test RPA Comments
Pb Concentrate
LOM assumptions are the same as System 2 – Arex Stratabound. Metallurgical testing was not
conducted Pb Recovery (%) 81.3
Pb Grade (%) 55.9 Ag Recovery (%) 55.8 Au Recovery (%) 22.0
Zn Concentrate
LOM assumptions are the same as System 2 – Arex Stratabound. Metallurgical testing was not
conducted Zn Recovery (%) 80.0
Zn Grade (%) 52.0 Ag Recovery (%) 8.8 Au Recovery (%)
Optimum conditions from development test work were applied to flotation testing of different
variability samples. Each variability sample was subjected to Cu, Pb, and Zn flotation via an
open cleaner circuit (same configuration used for LCT, except that there was no recirculation
of cleaner and recleaner tailings). Talc flotation was only performed on samples from Arex
Stratabound or Ambrex Stratabound mineralization.
The results from variability flotation testing are presented in detail in Appendix I of the SGS
GEOSOL Report. Figures 13-4 and 13-5 illustrate the variation of metal assays in the flotation
products. There are large variations in metal assay and metal distribution to the talc tail and
recleaner concentrates. In the cases where the variation was negative, the results for the
variability sample were below the result obtained for the respective master composite with the
exception of zinc reported in the zinc recleaner concentrate.
SETTLING, RHEOLOGY, AND FILTRATION Settling and rheology test work on feed samples from master composites of the Arex and
Ambrex individual materials and the Arex Mixed material was conducted at SGS Chile. Details
of the test work program are presented in Appendix J of the SGS GEOSOL Report. The best
settling results were obtained using 3 g/t of the BASF Magnafloc 10 flocculant (see Table 13-
16). Rheology test work on the products from settling tests was also conducted using a Hake
550 viscometer (Figures 13-6 and 13-7).
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-26
TABLE 13-16 SUMMARY OF SETTLING TESTS USING MAGNAFLOC 10 FLOCCULANT (3 G/T)
VM Holding S.A. – Aripuanã Zinc Project
Parameter Arex Stratabound Arex Stringer
Arex Mixed (75% Stratabound, 25% Stringer)
Ambrex Stratabound
Initial % solids 18 18 18 18
% solids after sedimentation 65 66 66 67
Settling velocity (mm/s) 1.5 2 2 2
Unit area (m2/tph) 0.7 0.5 0.5 0.6
Yield point no shear (PA) 52 29 42 41
Yield point full shear (PA) 1.7 0.6 2.3 2.3
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-27
FIGURE 13-4 VARIATION OF METAL ASSAYS IN FLOTATION PRODUCTS
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-28
FIGURE 13-5 VARIATION OF METAL ASSAYS IN FLOTATION PRODUCTS
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-29
FIGURE 13-6 YIELD STRESS VS. SOLIDS PERCENTAGE
FIGURE 13-7 VISCOSITY VS. SOLIDS PERCENTAGE
Settling test work on flotation tailings from Arex Stratabound, Arex Stringer, and Arex Mixed
(75% Stratabound, 25% Stringer) mineralization was conducted by ANDRITZ. Details of the
test work program are presented in Appendix K of the SGS GEOSOL Report. Filtration testing
of the Ambrex Stratabound flotation tailings was also performed. The best settling results were
obtained using the BASF Magnafloc 10 flocculant, resulting in 60% to 75% solids in the
products. A summary of the filtration test work is presented in Table 13-17.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-30
TABLE 13-17 SUMMARY OF FILTRATION TEST WORK CONDUCTED BY ANDRITZ
VM Holding S.A. – Aripuanã Zinc Project
Operating Parameter
Arex Stratabound Arex Stringer
Arex Mixed (75% Stratabound, 25% Stringer)
Ambrex Stratabound
Filtration throughput – dry
basis (tph) 211 211 211 211
Production days per year 365 365 365 365
Equipment availability (%) 90 90 90 90
Pulp density (t/m3) 1.71 1.65 1.66 1.63
Feed solids content (%) 61 61 63 63
Cake thickness (mm) 40 40 40 40
Cake moisture (%) 7 9 9 7
Cake solids content (%) 93 91 91 93
Approximate filtration rate
(kg/h·m2) 104 94 92 94
Recommended filter press model Overhead Overhead Overhead Overhead
Recommended number of units 2 2 2 2
Recommended frame 2000/180 2000/180 2000/180 2000/180
Recommended filter fabric Andritz 211k Andritz 211k Andritz 211k Andritz 211k
Feed pressure (bar) 6 6 6 6
Chamber pressure (bar) 8 8 8 8
Chamber size (mm) 2000x2000 2000x2000 2000x2000 2000x2000
Number of chambers per
unit 146 to 152 162 to 168 166 to 168 162 to 168
SUMMARY In RPA’s opinion, the metallurgical test program undertaken to date for the Aripuanã Zinc
mineralization was detailed and systematic in approach.
To process Aripuanã Zinc mineralization, the material should be fed separately to improve
copper recovery and to reduce costs particularly when processing Copper Stringer material.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 13-31
Since Copper Stringer materials do not have significant zinc and lead grades, copper
processing should be separate for flotation and filtration and it is expected that the lead and
zinc circuits will be by-passed.
RPA recommends that metallurgical test results be referenced in a manner that is consistent
for all LOM assumptions (i.e., using the final concentrate grades and recoveries) and the
recoveries and the assays of any penalty elements be reported. Also, any deleterious
elements (e.g., potential tremolite material) that could have a significant effect on potential
economic extraction should be further examined.
Additional test work should be carried out to develop and to optimize Zn/Pb recovery circuits
on Ambrex materials, to conduct additional mineralogical analysis, to extend the variability
analysis to a full geometallurgical program using samples from different locations in the
deposits, and to conduct pilot plant test work to confirm the performance of the circuit selected.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-1
14 MINERAL RESOURCE ESTIMATE The Mineral Resource estimate, dated December 23, 2016 was completed by VMH personnel
using Datamine Studio 3, Leapfrog Geo, and Isatis softwares. Wireframes for geology and
mineralization were constructed in Leapfrog Geo based on geology sections, assay results,
lithological information, and structural data. Assays were capped to various levels based on
exploratory data analysis and then composited to one metre lengths. Wireframes were filled
with blocks measuring 5 m by 10 m by 5 m with sub-celling at wireframe boundaries. Blocks
were interpolated with grade using Ordinary Kriging (OK) and Inverse Distance Squared (ID2).
Blocks estimates were validated using industry standard validation techniques. Classification
of blocks was based on distance based criteria.
RPA has audited and accepted the VMH Mineral Resource estimate.
RPA is not aware of any environmental, permitting, legal, title, taxation, socio-economic,
marketing, political, or other relevant factors that could materially affect the Mineral Resource
estimate.
A summary of the Mineral Resources is provided in Table 14-1, with Table 14-2 listing Mineral
Resources by area.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-2
TABLE 14-1 MINERAL RESOURCE STATEMENT, DECEMBER 23, 2016 VM Holding S.A. – Aripuanã Zinc Project
Grade Contained Metal
Stratabound Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 8.6 5.88 2.16 0.19 0.23 52.65 1,109.0 407.1 36.0 64.2 14.5
Indicated 9.8 5.38 2.03 0.09 0.25 47.83 1,160.8 437.2 18.7 79.5 15.0 Measured and Indicated 18.3 5.61 2.09 0.14 0.24 50.08 2,269.9 844.3 54.7 143.7 29.5
Inferred 13.2 7.20 2.80 0.10 0.38 62.50 2,099.7 815.4 29.4 162.7 26.6
Stringer Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 2.3 0.28 0.12 1.54 1.18 17.61 14.4 6.3 78.5 87.8 1.3
Indicated 1.2 0.11 0.05 0.97 1.28 11.21 2.7 1.4 24.5 47.5 0.4 Measured and Indicated 3.5 0.22 0.10 1.35 1.21 15.49 17.2 7.7 103.1 135.3 1.7
Inferred 11.4 0.08 0.05 0.78 1.55 9.31 19.3 13.5 197.0 569.7 3.4
Total Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 10.9 4.68 1.72 0.48 0.43 45.18 1,123.5 413.5 114.6 152.0 15.8
Indicated 10.9 4.83 1.82 0.18 0.36 43.97 1,163.6 438.6 43.2 127.0 15.5 Measured and Indicated 21.8 4.76 1.77 0.33 0.40 44.58 2,287.0 852.0 157.8 279.0 31.3
Inferred 24.6 3.90 1.53 0.42 0.93 37.88 2,119.0 829.0 226.4 732.4 30.0 Notes:
1. CIM definitions were followed for Mineral Resources. 2. Mineral Resources are reported using a US$46/t Net Smelter Return (NSR) block cut-off value for
stratabound material and a US$42/t NSR block cut-off value for stringer material. 3. The NSR is calculated based on metal prices of US$1.26 per lb Zn, US$1.01 per lb Pb, US$3.08 per lb
Cu, US$1,471 per troy ounce Au, and US$21.8 per troy ounce Ag. 4. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. 5. Numbers may not add due to rounding.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-3
TABLE 14-2 MINERAL RESOURCES BY TYPE AND AREA, DECEMBER 23, 2016
VM Holding S.A. – Aripuanã Zinc Project
Grade Contained Metal
Stra
tabo
und
Arex Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 3.9 6.10 2.15 0.34 0.28 55.66 526.2 185.2 29.1 34.9 7.0 Indicated 0.7 6.71 2.03 0.30 0.38 42.29 98.4 29.7 4.3 8.1 0.9 Measured and Indicated 4.6 6.19 2.13 0.33 0.29 53.72 624.6 215.0 33.4 43.0 7.9
Inferred 1.4 6.32 2.08 0.28 0.49 31.93 194.1 64.0 8.5 22.1 1.4
Ambrex Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 4.6 5.69 2.17 0.07 0.20 50.11 582.8 221.9 6.9 29.3 7.5 Indicated 9.1 5.28 2.03 0.07 0.24 48.23 1,062.5 407.5 14.4 71.4 14.1 Measured and Indicated 13.8 5.42 2.07 0.07 0.23 48.86 1,645.3 629.3 21.3 100.7 21.6
Inferred 11.8 7.31 2.88 0.08 0.37 66.10 1,905.7 751.4 21.0 140.6 25.1
Strin
ger
Arex Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 2.3 0.28 0.12 1.54 1.18 17.61 14.4 6.3 78.5 87.8 1.3 Indicated 1.2 0.11 0.05 0.97 1.28 11.21 2.7 1.4 24.5 47.5 0.4 Measured and Indicated 3.5 0.22 0.10 1.35 1.21 15.49 17.2 7.7 103.1 135.3 1.7
Inferred 1.7 0.04 0.04 0.62 3.67 9.14 1.4 1.7 23.7 203.0 0.5
Ambrex Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
Measured 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Indicated 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Measured and Indicated 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Inferred 9.7 0.08 0.06 0.81 1.18 9.34 17.9 11.9 173.3 366.6 2.9 Notes:
1. CIM definitions were followed for Mineral Resources. 2. Mineral Resources are reported using a US$46/t Net Smelter Return (NSR) block cut-off value for
stratabound material and a US$42/t NSR block cut-off value for stringer material. 3. The NSR is calculated based on metal prices of US$1.26 per lb Zn, US$1.01 per lb Pb, US$3.08 per lb
Cu, US$1,471 per troy ounce Au, and US$21.8 per troy ounce Ag. 4. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. 5. Numbers may not add due to rounding.
COMPARISON WITH PREVIOUS ESTIMATE RPA reviewed and adopted the previous estimate dated October 20, 2016 and prepared a NI
43-101 Technical Report for Karmin, VMH’s joint venture partner for the Aripuanã Zinc Project.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-4
Differences between the previous estimate reviewed by RPA and the current estimate can be
attributed to the following:
• Additional wireframes over the deposit, most significantly in the Ambrex stringer zone
• A decrease in cut-off NSR value from $48/t to $46/t and $42/t
• Higher metal prices
• Dynamic anisotropy over the whole deposit compared to only being used at the Ambrex Link Zone previously
A comparison between the current and October 2016 estimate is provided in Table 14-3.
Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)Measured 8.6 5.88 2.16 0.19 0.23 52.65 1,109.0 407.1 36.0 64.2 14.5 7.9 6.16 2.27 0.20 0.24 55.75 1,070.2 395.1 35.1 62.0 14.1Indicated 9.8 5.38 2.03 0.09 0.25 47.83 1,160.8 437.2 18.7 79.5 15.0 8.3 5.88 2.24 0.09 0.27 53.40 1,080.1 411.2 17.2 71.3 14.3Measured and Indicated 18.3 5.61 2.09 0.14 0.24 50.08 2,269.9 844.3 54.7 143.7 29.5 16.2 6.02 2.26 0.15 0.26 54.54 2,150.2 806.2 52.3 133.2 28.4Inferred 13.2 7.20 2.80 0.10 0.38 62.50 2,099.7 815.4 29.4 162.7 26.6 11.4 8.00 3.13 0.11 0.40 69.76 2,009.8 785.2 26.7 148.0 25.6
Stringer Tonnes Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz) Tonnes Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)Measured 2.3 0.28 0.12 1.54 1.18 17.61 14.4 6.3 78.5 87.8 1.3 2.1 0.31 0.14 1.65 1.25 18.86 14.0 6.2 76.0 84.1 1.3Indicated 1.2 0.11 0.05 0.97 1.28 11.21 2.7 1.4 24.5 47.5 0.4 1.0 0.12 0.06 1.08 1.35 12.39 2.7 1.3 23.7 43.1 0.4Measured and Indicated 3.5 0.22 0.10 1.35 1.21 15.49 17.2 7.7 103.1 135.3 1.7 3.1 0.25 0.11 1.47 1.28 16.77 16.7 7.6 99.7 127.2 1.7Inferred 11.4 0.08 0.05 0.78 1.55 9.31 19.3 13.5 197.0 569.7 3.4 14.3 0.08 0.06 0.98 1.34 10.61 24.4 17.8 307.7 617.3 4.9
Total Tonnes Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz) Tonnes Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)Measured 10.9 4.68 1.72 0.48 0.43 45.18 1,123.5 413.5 114.6 152.0 15.8 10.0 4.94 1.83 0.51 0.46 48.02 1,084.2 401.3 111.1 146.1 15.4Indicated 10.9 4.83 1.82 0.18 0.36 43.97 1,163.6 438.6 43.2 127.0 15.5 9.3 5.27 2.01 0.20 0.38 49.03 1,082.7 412.5 40.9 114.3 14.7Measured and Indicated 21.8 4.76 1.77 0.33 0.40 44.58 2,287.0 852.0 157.8 279.0 31.3 19.3 5.09 1.91 0.36 0.42 48.51 2,167.0 813.8 152.0 260.4 30.1Inferred 24.6 3.90 1.53 0.42 0.93 37.88 2,119.0 829.0 226.4 732.4 30.0 25.7 3.59 1.42 0.59 0.93 36.85 2,034.3 803.0 334.4 765.3 30.4
Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)Measured 9% ‐5% ‐5% ‐6% ‐5% ‐6% 4% 3% 3% 4% 3%Indicated 17% ‐8% ‐9% ‐8% ‐5% ‐10% 7% 6% 9% 12% 5%Measured and Indicated 13% ‐7% ‐7% ‐8% ‐5% ‐8% 6% 5% 5% 8% 4%Inferred 16% ‐10% ‐10% ‐5% ‐5% ‐10% 4% 4% 10% 10% 4%
Stringer Tonnes Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)Measured 11% ‐7% ‐8% ‐7% ‐6% ‐7% 3% 2% 3% 4% 4%Indicated 16% ‐12% ‐11% ‐10% ‐5% ‐10% 2% 3% 4% 10% 5%Measured and Indicated 13% ‐9% ‐10% ‐8% ‐5% ‐8% 3% 2% 3% 6% 4%Inferred ‐20% ‐1% ‐5% ‐20% 16% ‐12% ‐21% ‐24% ‐36% ‐8% ‐30%
Total Tonnes Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)Measured 9% ‐5% ‐6% ‐6% ‐5% ‐6% 4% 3% 3% 4% 3%Indicated 17% ‐8% ‐9% ‐10% ‐5% ‐10% 7% 6% 6% 11% 5%Measured and Indicated 13% ‐7% ‐7% ‐8% ‐5% ‐8% 6% 5% 4% 7% 4%Inferred ‐4% 9% 8% ‐29% 0% 3% 4% 3% ‐32% ‐4% ‐1%
TABLE 14-3 COMPARISON BETWEEN CURRENT AND OCTOBER 20, 2016 ESTIMATESVM Holding S.A. – Aripuanã Zinc Project
Tonnes
Tonnes
Tonnes
Stratabound
Stratabound
Grade Contained Metal
Contained MetalGradeOctober 20, 2016
Grade Contained Metal
Difference
Current Resource Estimate
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 14-5
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-6
RESOURCE DATABASE The resource database contains drilling information and analytical results up to December 23,
2016. Information received after this date was not used in the Mineral Resource estimate.
The database comprises 533 drill holes for a total of 142,080 meters of drilling. A total of 124
drill holes were complete by Karmin/Anglo American prior to VMH’s involvement in the Project
(pre-2004). The 124 drill holes were internally reviewed and found to be acceptable to support
Mineral Resource estimation.
VMH maintains the resource database in GeoExplo software. RPA received data from VMH
in comma separated values (.csv) format, as well as Datamine de-surveyed files (.dm). Data
were amalgamated and parsed as required and imported by RPA into Datamine Studio RM
and Aranz’s Leapfrog Geo software version for review.
For the purpose of the Mineral Resource Estimate, a total of 44 drill holes were excluded from
the database. The drill holes excluded either lacked information, were historic RC drilling or
were drilled for the purpose of metallurgical testing.
Section 12, Data Verification, describes the resource database verification steps carried out
by RPA and VMH. RPA is of the opinion that the drill hole database is valid and suitable to
estimate Mineral Resources for the Project.
TOPOGRAPHY A LiDAR topographic survey was completed over the Project in 2008. The resulting digital
terrain surface (DTM) is available in AutoCAD Drawing Exchange (DXF) and Datamine. The
surface has been validated using survey control points and drill hole collars.
GEOLOGICAL INTERPRETATION Wireframes of the stratabound and stringer mineralization for Arex and Ambrex were
constructed considering geology at a cut-off grade of 0.6% Zn in the stratabound zones and
0.5% Cu in the stringer zones in Aranz’ Leapfrog Geo software. In support of the mineralization
wireframes, a geological model, also created in Leapfrog Geo was prepared by VMH and
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-7
included oxidation, alteration, and topography surfaces, in addition to modelled faults. A zone
of discontinuous remobilized stratabound mineralization within a fault zone in the upper sector
of Ambrex was also modelled and assigned to stratabound mineralization. Samples with both
zinc and copper grades above cut-off grades were considered to be stratabound type
mineralization. Some drill hole intercepts with grades below cut-off grade were included to
maintain geological continuity.
Mineralization at Arex strikes at approximately 110° azimuth, extending over a 1,500 m strike
length. Thin lenses of intermingling stratabound and stringer mineralization within two principal
limbs dip from ten degrees to 60° to the northeast, and are modelled to join in some areas near
surface. The main mineralized zone comes close to outcropping at surface. It is characterized
by tightly folded, well defined stringer and stratabound zones. Individual lens thicknesses
range from less than one metre to fifteen metres, but are generally from two metres to seven
metres. The mineralization zone is approximately 125 m thick overall, and individual lenses
are separated by barren, hydrothermally altered rock from one metre to tens of metres thick.
The main mineralization is delineated between two dipping faults.
The Ambrex deposit is located approximately 1,300 m southeast of Arex and approximately
100 m southeast of Link Zone. Mineralization strikes at approximately 125° and has a strike
extent of approximately 1,050 m based on current drilling. Mineralization at Ambrex is
dominated by stratabound mineralization, with volumetrically smaller, less well defined stringer
zone perpendicular to and to the east of it. Stratabound mineralization above the Gossan Fault
Zone dips at approximately 40º to the southeast. At depth, the mineralization is folded and
dips from near vertical to 70° to the southwest. Mineralization thicknesses typically range from
10 m to 60 m. Ambrex has an upper depth of 60 m below surface, but generally is 100 m
below surface. The deepest mineralization intersection within the Ambrex model is over 700
m below surface and the deposit remains open at depth. The stratabound mineralization is
well defined and follows stratigraphy. The stringer mineralization is poorly defined due to poor
drilling angles and crosses stratigraphy, following structural features.
The Link Zone is located between and along strike of Ambrex and Arex over a strike length of
approximately 850 m. There is an approximate 300 m overlap to the northwest with Arex. The
mineralization bears a closer similarity to Ambrex in that the stringer zone occurs at a high
angle to the stratabound zone. The stratabound mineralization comes close to surface and
extends to a depth of 500 m below surface while the stringer zone mineralization occurs
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-8
approximately 200 m below surface and extends to a depth of approximately 400 m below
surface.
The stratabound mineralization lenses range from one metre to 30 m thick, with an average
thickness of approximately nine metres while the stringer zone thickness ranges from one
metre to 20 m with an average of approximately five metres true thickness.
Figure 14-1 shows a 3D perspective view of the wireframes and Figures 14-2 and 14-3 show
example sections of Ambrex and Arex, respectively.
RPA’s review of the mineralized wireframes included comparison with geological sections
prepared by on-site geologists, drill hole information, and a Net Smelter Return (NSR) value
calculated by RPA from drill hole assays. Assumptions used in NSR calculation are described
under Net Smelter Return Cut-Off Value in this section.
A geological model has been prepared over the deposit areas, delineating a hydrothermal
alteration zone, a series of faults, and weathering profiles. Meta-sedimentary and meta-
volcanic rocks have also been distinguished over Ambrex. RPA found mineralization
wireframes to be snapped to drill hole assay intervals, and to match well with the geological
interpretation. RPA notes that the cut-off grade value of 0.6% Zn chosen by VMH is low when
compared with the NSR cut-off value and has caused the inclusion of low grade samples. RPA
recommends increasing the wireframe modelling cut-off grade to exclude sub-economic
mineralization not related to massive or disseminated sulphides in the stratabound zone.
A total of 26 and 15 individual wireframes were constructed over Ambrex and Link Zone to
represent the stratabound and stringer zones, respectively. Many of the stringer zone
wireframes at Ambrex are defined by a limited amount of drill hole information. A total of 20
and 21 individual wireframes were constructed over Arex to represent the stratabound and
stringer zones, respectively.
Stratabound
Legend:
Stringer
1000 Metres
July 2017 Source: RPA, 2017.
Drill Hole Trace
AmbrexAmbrex Link Zone
Arex
3D Isometric View ofGeological Wireframes
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 14-1
14-9
ww
w.rp
acan
.co
m
Source: Votorantim Metais, 2016.July 2017
Ambrex Geological Model
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 14-2
14-10
www.rpacan.com
Source: Votorantim Metais, 2016.July 2017
Arex Geological Model
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 14-3
14-11
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-12
CAPPING OF HIGH GRADES VMH applied high grade capping to Zn, Pb, Cu, Au, and Ag assays in order to limit the influence
of a small amount of extreme values located in the upper tail of the metal distributions. Log
probability plots were inspected for each individual wireframe and applied a capping grade
according to inflections on log probability plots (example given in Figure 14-4 and 14-5). No
capping was performed in the hydrothermal zone and for the variables Fe, S, MgO, and
density. Raw assays were capped prior to compositing. A summary of capping grades used
is provided in Table 14-4 and capped versus uncapped statistics is provided in Table 14-5.
RPA reviewed the capping levels utilized by VMH and is of the opinion that, in general, the
capping grades are reasonable. RPA notes that some of the gold capping values appear high
and impart undue influence on the total contained metal.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-13
TABLE 14-4 GRADE CAPPING LEVELS VM Holding S.A. – Aripuanã Zinc Project
Ambrex Arex
Body Zn (%)
Pb (%)
Cu (%) Au (g/t) Ag (g/t) Body
Zn (%)
Pb (%)
Cu (%)
Au (g/t)
Ag (g/t)
1 - - 1 1 - 60 - - - 0.17 - 3 - - 0.4 - - 62 - - - - 80 4 40 15 0.2 - - 63 - - 0.45 - - 5 - 3.5 0.1 - 40 64 3 - 0.04 - - 7 10 2.5 - - - 65 - 3 0.1 - 11.5 8 - - 0.2 0.9 - 66 3 0.8 - - - 9 10 1.5 - - 30 72 - - 0.25 0.25 - 10 - - 0.2 1.5 - 80 - - 1.3 - 160 11 - - 0.5 - - 101 1 - - 4.42 - 12 5 3 - - 45 102 - - - - 171 20 4 - - - - 103 5 2 - - 116 21 6 6 0.5 0.7 - 104 0.5 - - - - 23 6 - - - - 105 0.8 0.4 - - - 30 17 10 1 2.5 358 106 1.5 - - 5.5 - 31 6 3 1.5 1 45 108 0.3 - 3.3 - - 32 30 - 1 - 178 109 - - 0.8 - - 33 - 22 5.5 5 428 110 0.2 - 4.3 10 - 34 8 5 - 1 133 112 0.6 - - 7 - 35 21 11 2.5 5 187 116 0.025 - 0.85 - - 50 - 10 - - 250 51 30 10 0.2 0.5 - 52 - - 0.7 2 - 53 15 8 0.2 0.9 130 54 - - 1.2 2.3 - 55 - - 0.6 1 290 121 - - - 2 - 131 - - - 47.5 - 141 - - 4 - - 142 - - - 3 - 143 - - 2 10 - 144 - - 4 - - 180 - - - 2 - 181 - - 2.5 - - 184 - - 7 - - 191 - - 1.5 - -
TABLE 14-5 UNCAPPED VERSUS CAPPED ASSAY STATISTICS VM Holding S.A. – Aripuanã Zinc Project
Uncapped Capped
Area Type Grade Count Sampled Minimum Maximum Mean Stdev Variance CV Maximum Mean Stdev Variance CV Metal Loss
Are
x
Stratabound
ZN (%) 6,901 6,815 0.0020 60.90 4.80 6.69 44.79 1.39 46.90 4.72 6.47 41.81 1.37 -2%
PB (%) 6,901 6,815 0.0000 42.81 1.78 3.16 10.01 1.78 42.81 1.76 3.10 9.64 1.76 -1%
CU (%) 6,901 6,815 0.0000 11.74 0.08 0.34 0.12 4.53 5.50 0.07 0.21 0.04 3.15 -11%
AU (g/t) 6,901 5,718 0.0000 16.95 0.22 0.55 0.31 2.55 5.00 0.21 0.39 0.15 1.91 -6%
AG (g/t) 6,901 6,795 0.0500 1,240.00 41.05 81.24 6,599.91 1.98 1,240.00 40.49 78.69 6,192.07 1.94 -1%
Stringer
ZN (%) 3,160 3,134 0.0002 30.60 0.14 0.87 0.75 6.05 30.60 0.14 0.87 0.75 6.05 0%
PB (%) 3,160 3,134 0.0001 8.98 0.06 0.39 0.15 6.20 8.98 0.06 0.39 0.15 6.20 0%
CU (%) 3,160 3,134 0.0001 11.10 0.51 0.87 0.75 1.71 8.79 0.49 0.79 0.63 1.63 -4%
AU (g/t) 3,160 3,134 0.0025 96.70 0.82 3.42 11.66 4.14 68.90 0.79 2.85 8.11 3.61 -4%
AG (g/t) 3,160 3,136 0.0050 605.00 6.71 15.64 244.48 2.33 605.00 6.71 15.64 244.48 2.33 0%
Am
brex
Stratabound
ZN (%) 3,145 3,137 0.0050 48.88 5.16 7.09 50.21 1.37 48.88 5.15 7.08 50.19 1.38 0%
PB (%) 3,145 3,137 0.0002 34.40 1.86 3.06 9.34 1.65 34.40 1.85 3.05 9.33 1.65 0%
CU (%) 3,145 3,137 0.0001 16.70 0.30 0.98 0.96 3.32 14.03 0.23 0.70 0.49 2.99 -21%
AU (g/t) 3,145 2,770 0.0025 10.56 0.23 0.59 0.35 2.57 10.56 0.23 0.59 0.35 2.58 -1%
AG (g/t) 3,145 3,126 0.0100 2,180.00 49.54 102.46 10,497.52 2.07 1,530.00 43.04 77.91 6,069.98 1.81 -13%
Stringer
ZN (%) 2,256 2,252 0.0001 21.00 0.20 1.05 1.10 5.23 21.00 0.19 1.02 1.04 5.32 -4%
PB (%) 2,256 2,252 0.0001 27.50 0.08 0.57 0.33 7.55 27.50 0.07 0.57 0.33 7.64 -1%
CU (%) 2,256 2,252 0.0001 20.44 1.36 2.39 5.70 1.76 20.44 1.35 2.37 5.61 1.76 -1%
AU (g/t) 2,256 2,231 0.0025 138.90 1.45 4.68 21.90 3.23 138.90 1.35 4.19 17.53 3.10 -7%
AG (g/t) 2,256 2,218 0.0500 536.00 14.77 30.19 911.37 2.04 536.00 14.77 30.19 911.37 2.04 0%
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 14-14
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-15
FIGURE 14-4 CAPPING ANALYSIS FOR BODY=4 (AMBREX STRATABOUND)
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-16
FIGURE 14-5 CU CAPPING ANALYSIS FOR BODY=116 (AREX STRINGER)
COMPOSITING VMH composited the capped assays to one metre, which corresponds to the dominant
sampling length for the deposit (Figure 14-6). Composites were weighted by length and
unsampled core intervals were ignored. Gold is sampled to a lesser extent than other
economic variables.
While the total length of unsampled intervals is insignificant compared to the total length of the
composites, RPA notes that the majority of unsampled intervals were not related to
mineralization and recommends substituting zeroes. RPA recommends substituting zeroes
for unsampled intervals.
The univariate statistics for the composites is provided in Table 14-6.
TABLE 14-6 COMPOSITE STATISTICS VM Holding S.A. – Aripuanã Zinc Project
Uncapped Capped
Area Type Grade Count Sampled Minimum Maximum Mean Stdev Variance CV Maximum Mean Stdev Variance CV Metal Loss
Are
x
Stratabound
ZN (%) 6,422 6,281 0.0025 46.78 4.87 6.17 38.04 1.27 46.78 4.79 5.97 35.62 1.25 -2%
PB (%) 6,422 6,281 0.0000 29.53 1.80 2.87 8.23 1.59 29.53 1.79 2.83 7.98 1.58 -1%
CU (%) 6,422 6,281 0.0001 10.83 0.08 0.32 0.10 4.17 5.50 0.07 0.19 0.04 2.86 -11%
AU (g/t) 6,422 5,244 0.0025 15.05 0.22 0.50 0.25 2.30 5.00 0.20 0.35 0.13 1.75 -6%
AG (g/t) 6,422 6,270 0.1000 1,035.49 41.47 72.71 5,286.32 1.75 1,035.49 40.92 70.91 5,028.43 1.73 -1%
Stringer
ZN (%) 2,979 2,908 0.0002 11.40 0.12 0.67 0.44 5.42 11.40 0.12 0.67 0.44 5.42 0%
PB (%) 2,979 2,908 0.0001 8.37 0.06 0.34 0.12 5.71 8.37 0.06 0.34 0.12 5.71 0%
CU (%) 2,979 2,908 0.0002 10.95 0.49 0.77 0.60 1.59 6.80 0.47 0.71 0.50 1.51 -4%
AU (g/t) 2,979 2,909 0.0025 68.94 0.79 2.69 7.23 3.39 45.27 0.76 2.26 5.12 2.98 -4%
AG (g/t) 2,979 2,910 0.0050 514.65 6.52 14.10 198.88 2.16 514.65 6.52 14.10 198.88 2.16 0%
Am
brex
Stratabound
ZN (%) 2,727 2,629 0.0064 44.42 5.05 6.28 39.43 1.24 44.42 5.04 6.28 39.42 1.25 0%
PB (%) 2,727 2,629 0.0002 20.35 1.82 2.69 7.26 1.48 20.35 1.81 2.69 7.24 1.48 0%
CU (%) 2,727 2,629 0.0001 16.67 0.32 0.99 0.98 3.13 13.25 0.25 0.77 0.59 3.05 -20%
AU (g/t) 2,727 2,314 0.0025 8.64 0.23 0.52 0.27 2.24 8.64 0.23 0.52 0.27 2.25 -1%
AG (g/t) 2,727 2,621 0.0108 1,553.06 48.84 91.47 8367.27 1.87 808.14 42.59 69.36 4,811.15 1.63 -13%
Stringer
ZN (%) 1,918 1,873 0.0001 16.73 0.18 0.87 0.75 4.79 16.73 0.18 0.85 0.72 4.84 -3%
PB (%) 1,918 1,873 0.0001 11.27 0.07 0.42 0.18 5.94 11.27 0.07 0.42 0.18 6.01 -1%
CU (%) 1,918 1,873 0.0001 20.44 1.32 2.17 4.71 1.65 20.44 1.31 2.15 4.64 1.65 -1%
AU (g/t) 1,918 1,853 0.0025 126.95 1.42 4.19 17.58 2.96 126.95 1.32 3.81 14.54 2.88 -7%
AG (g/t) 1,918 1,847 0.0500 373.09 14.35 27.20 739.76 1.90 373.09 14.35 27.20 739.76 1.90 0%
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 14-17
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-18
FIGURE 14-6 HISTOGRAMS FOR ASSAY (LEFT) AND COMPOSITE (RIGHT) LENGTHS
EXPLORATORY DATA ANALYSIS VMH performed exploratory statistical analysis including boundary, bivariate and univariate
statistical analysis.
VMH generated contact plots for material inside and outside of the wireframes and concluded
that hard boundaries should be used during estimation (e.g., Figure 14-7).
The bivariate analysis results show strong correlations between stratabound Pb-Zn, Pb-Ag
and Cu-Au, while for stringer mineralization, good correlations between Cu-Ag and Fe-S exist.
In general, stratabound and stringer mineralization Fe and S show strong correlations (Figure
14-8). The results are consistent with the deposit type.
Given the large quantity of individual wireframes, VMH divided the wireframe domains up into
groups based on the geological continuity, Zn statistics for stratabound, and Cu statistics for
stringer mineralization (Table 14-7 and Figure 14-9). The grouping was applied to variography
and the interpolation strategy.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-19
TABLE 14-7 WIREFRAME GROUPING FOR VARIOGRAPHY AND SEARCH PARAMETERS
VM Holding S.A. – Aripuanã Zinc Project
Area Group Min Type Body
Ambr
ex
G1 Stratabound 5, 6, 7, 9, 12 G2 Stratabound 1, 4, 8, 10, 11 G3 Stratabound 30, 31, 32, 33, 34, 35 G4 Stratabound 20, 21, 23 G5 Stratabound 22 G6 Stratabound 51 G7 Stratabound 52, 53 G8 Stratabound 50 G9 Stratabound 54, 55 G10 Stringer 170, 171, 172, 173, 174, 175, 176 G11 Stringer 120, 121, 122, 123, 131, 132, 141, 142, 143, 144, 180, 181, 184, 191, 192
Arex
G21 Stratabound 62, 67, 68, 70, 71, 73, 77, 79, 80 G22 Stratabound 72, 74, 75, 76, 81 G23 Stratabound 63, 65 G24 Stratabound 64, 66 G25 Stratabound 60, 61 G30 Stringer 113, 150 G31 Stringer 108, 111, 115, 153 G32 Stringer 104, 107, 114, 117, 151 G33 Stringer 105, 106, 152 G34 Stringer 109, 110, 116 G35 Stringer 101, 112 G36 Stringer 160, 161
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-20
FIGURE 14-7 AREX STRATABOUND CONTACT ANALYSIS
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-21
FIGURE 14-8 CORRELATION MATRICES FOR AMBREX AND AREX (STB=STRATABOUND, STR=STRINGER)
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-22
FIGURE 14-9 ZN AND CU STATISTICS BY BODY AND GROUP
VARIOGRAPHY Experimental traditional variograms were fit by one to three spherical models in three directions
for variables Zn, Pb, Cu, Au, Ag, Fe, S, MgO, and density in Isatis. Variograms were not-
standardized. Examples of VMH variograms are shown in Figures 14-10 to 14-12. The
stratabound and stringer relative nugget effects for Zn, Pb, Cu, Au, and Ag are shown in
Figures 14-13 and 14-14, while the ranges of the variograms are shown in Figures 14-15 and
14-16.
For many of the variograms, the sill was fit to different levels for different directions giving the
impression of a zonal anisotropy present in the mineralization. The different sills were
accounted for by fitting long tails for the second and third structures for the direction with the
lower variance. The variograms were used for OK interpolation and as a guide for selecting
search ellipse ranges (range at 80% of the total sill).
In cases where the data did not support directional variograms, omni-directional variograms
were modelled.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-23
FIGURE 14-10 AREX STRATABOUND, GROUP 21 ZN DIRECTIONAL VARIOGRAMS
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-24
FIGURE 14-11 AMBREX LINK ZONE STRATABOUND, GROUP 3 ZN DIRECTIONAL VARIOGRAMS
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-25
FIGURE 14-12 AREX STRINGER, GROUP 36 ZN DIRECTIONAL VARIOGRAMS
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-26
FIGURE 14-13 RELATIVE NUGGET EFFECT STRATABOUND
FIGURE 14-14 RELATIVE NUGGET EFFECT STRATABOUND
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-27
FIGURE 14-15 VARIOGRAM RANGES STRATABOUND
*Note: Ranges shown exclude structures fit to zonal anisotropy
FIGURE 14-16 VARIOGRAM RANGES STRINGER
*Note: Ranges shown exclude structures fit to zonal anisotropy
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-28
RPA is of the opinion that, in general, the variograms are reasonable. RPA notes that many
variograms have been fit with a strong zonal anisotropy. RPA recommends modelling
correlograms to avoid fitting second and third variogram model structures with long ranges.
BLOCK MODEL Ambrex and Arex wireframes were filled with blocks in Datamine Studio 3. The final block
model covers both zones. The block model was sub-celled at wireframes boundaries with
parent cells measuring 10 m by 5 m by 5 m and minimum sub-cell sizes of 1.00 m by 0.25 m
by 0.25 m. The block model setup is given in Table 14-8, while a description of the block
model attributes is given in Table 14-9.
The block size is appropriate for the drill spacing and proposed mining method and is suitable
to support the estimation of Mineral Resources and Mineral Reserves. Comparisons between
wireframe and block model volumes are reasonable.
TABLE 14-8 BLOCK MODEL SETUP VM Holding S.A. – Aripuanã Zinc Project
Parameter X Y Z Origin (m) 224,400 8,886,800 -600 Block Size (m) 10 5 5 Number of Blocks 297 440 210
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-29
TABLE 14-9 BLOCK MODEL ATTRIBUTE DESCRIPTIONS VM Holding S.A. – Aripuanã Zinc Project
FIELD DESCRIPTION FIELD DESCRIPTION ZN Estimated Zn
ALT_PRIM
Primary alteration
PB Estimated Pb 1 Carbonate
CU Estimated Cu 2 Chlorite
AU Estimated Au(g/t) 3 Sericite
AG Estimated Ag(g/t) 4 Silica
FE Estimated Fe 5 Talc
MGO Estimated MgO 6 Tremolite
S Estimated S 7 Weathered Rock
DENSITY Density (g/cm³)
ALT_SEC
Secondary alteration
TON Tonnes 1 Biotite
CLASS
1 Measured 2 Magnetite
2 Indicated 3 Absent
3 Inferred
CLORIT
Chloritization
99 Not Classified 1 High
*CLI
1 Stratabound 2 Low
2 Stringer 3 Residual
3 Soil
INTENS
Intensity
4 Hydrothermal Zone 1 High
BODY
Deposit identification 2 Low
0-59 Ambrex Stratabound
PIRITA
Quantity of Pyrite
60-99 Arex Stratabound 1 High
100-199 Stringer bodies 2 Medium
1000 Hydrothermal Zone 3 Low
AREA Target 4 Weathered Rock
1 Arex 5 Absent
2 Ambrex
PIRROT
Quantity of Pyrrhotite
COLOUR
11 Arex Stratabound 1 High
17 Arex Stringer 2 Medium
2-3 Ambrex Stratabound 3 Absent
47 Ambrex Stringer
SULF Sulphur
5 Link Stratabound 1 Present
53 Link Stringer 2 Absent
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-30
INTERPOLATION STRATEGY Grades were interpolated into blocks on a parent cell basis using OK. ID2 was used for groups
that did not yield interpretable variograms. Variables Zn, Pb, Cu, Au, Ag, Fe, S, MgO, and
density are interpolated and estimates are not density weighted.
Quantitative Kriging Neighbourhood Analysis (QKNA) was used for selecting minimum and
maximum samples per holes, and the minimum number of octants to be used during
interpolation. VMH found that the Kriging Efficiency and Slope of Regression was relatively
insensitive to the minimum number of samples and maximum samples per hole as compared
to the minimum number of octants used.
Search ellipsoids were oriented based on dynamic anisotropy angles extracted for the
mineralization wireframes. The search ranges were determined as follows:
• Pass 1: The range at 80% of the sill (25 m by 25 m by 25 m in the case of ID2)
• Pass 2: The range of the variogram (50 m by 50 m by 50 m in the case of ID2)
• Pass 3,4 and 5: Two, four and 10 times the range of the variogram (to interpolate remaining blocks)
The sample selection strategy is given in Table 14-10, while the search ranges for the Zn
stratabound and Cu stringer are given in Figures 14-17 and 14-18 respectively.
TABLE 14-10 SAMPLE SELECTION STRATEGY VM Holding S.A. – Aripuanã Zinc Project
Wireframes Group Search Pass
Min Samples
Max Samples
Max per hole
Min Samples
per Octant
Max Samples
per Octant
Minimum Octants
Used Method G1, G2 1 6 16 3 2 4 5 OK
G1, G2 2 6 16 3 2 4 5 OK
G1, G2 3 1 16 10 - - - OK
G1, G2 4 2 16 10 - - - OK
G3 1 4 16 5 2 4 4 OK
G3 2 4 16 5 2 4 4 OK
G3 3 3 16 10 - - - OK
G3 4 3 16 10 - - - OK
G4 1 3 16 5 2 4 4 OK/ID
G4 2 3 16 5 2 4 4 OK/ID
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-31
Wireframes Group Search Pass
Min Samples
Max Samples
Max per hole
Min Samples
per Octant
Max Samples
per Octant
Minimum Octants
Used Method G4 3 2 16 5 2 4 4 OK/ID
G5, G6, G7 1 6 16 3 2 4 5 OK
G5, G6, G7 2 6 16 3 2 4 5 OK
G5, G6, G7 3 3 16 10 - - - OK
G5, G6, G7 4 1 16 10 - - - OK
G8 1 3 16 5 2 4 4 OK
G8 2 3 16 5 2 4 4 OK
G8 3 3 16 5 2 4 4 OK
G8 4 3 16 5 2 4 4 OK
G8 5 1 16 5 2 4 4 OK
G9 1 3 16 5 2 4 4 OK
G9 2 3 16 5 2 4 4 OK
G9 3 3 16 5 - - - OK
G9 4 3 16 5 - - - OK
G9 5 1 16 5 - - - OK
G10 1 3 16 5 2 4 5 OK
G10 2 3 16 5 2 4 5 OK
G10 3 2 16 5 2 4 5 OK
G11 1 3 16 8 - - - OK/ID
G11 2 3 16 8 - - - OK/ID
G11 3 3 16 8 - - - OK/ID
G11 4 1 16 8 - - - OK/ID
G11 5 1 16 8 - - - OK/ID G21, G23, G30, G31, G32, G33, G34, G35, G36
1 4 16 5 1 4 4 OK/ID
G21, G23, G30, G31, G32, G33, G34, G35, G36
2 4 16 5 1 4 4 OK/ID
G21, G23, G30, G31, G32, G33, G34, G35, G36
3 3 16 5 - - - OK/ID
G21, G23, G30, G31, G32, G33, G34, G35, G36
4 2 16 5 - - - OK/ID
G21, G23, G30, G31, G32, G33, G34, G35, G36
5 2 16 5 - - - OK/ID
G22 1 3 16 5 1 4 4 OK
G22 2 3 16 5 1 4 4 OK
G22 3 3 16 5 - - - OK
G22 4 2 16 5 - - - OK
G22 5 2 16 5 - - - OK
G24 1 3 16 5 1 4 3 OK
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-32
Wireframes Group Search Pass
Min Samples
Max Samples
Max per hole
Min Samples
per Octant
Max Samples
per Octant
Minimum Octants
Used Method G24 2 2 16 5 - - - OK
G24 3 2 16 5 - - - OK
G24 4 2 16 5 - - - OK/ID
FIGURE 14-17 SEARCH RANGES FOR ZN STRATABOUND
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-33
FIGURE 14-18 SEARCH RANGES FOR CU STRINGER
NET SMELTER RETURN CUT-OFF VALUE An NSR value was assigned to blocks for the purposes of validation of the geological
interpretation and resource reporting. NSR is the estimated dollar value per tonne of
mineralized material after allowance for metallurgical recovery and consideration of smelter
terms, including revenue from payable metals, treatment charges, refining charges, price
participation, penalties, smelter losses, transportation, and sales charges.
Input parameters used to develop the NSR calculation have been derived from metallurgical
test work on the Aripuanã Zinc property, smelter terms from comparable projects, and
information provided by VMH. These assumptions are dependent on the processing scenario,
and will be sensitive to changes in inputs from further metallurgical test work. Key assumptions
are listed below.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-34
Metal prices and exchange rate:
US$1.26 per pound of zinc US$1.01 per pound of lead US$3.08 per pound of copper US$1,471 per ounce of gold US$21.8 per ounce of silver US$1.00 equals R3.30
Metal prices were selected by VMH, and are based on consensus, long term forecasts from
banks, financial institutions, and other sources.
Metallurgical recoveries are based on preliminary metallurgical testing, and are summarized
by zone and deposit:
Arex Stratabound Copper Concentrate
27% Ag recovery to Cu concentrate 50% Au recovery to Cu concentrate 68% Cu recovery to Cu concentrate grading 27% copper
Lead Concentrate
16% Au recovery to Pb concentrate 51% Ag recovery to Pb concentrate 83% Pb recovery to Pb concentrate grading 63% lead
Zinc Concentrate
9% Ag recovery to Zn concentrate 82% Zn recovery to Zn concentrate grading 49% zinc
Arex Stringer Copper Concentrate
93% Au recovery to Cu concentrate 75% Ag recovery to Cu concentrate 96% Cu recovery to Cu concentrate grading 27% copper
Ambrex Stratabound Lead Concentrate
30% Au recovery to Pb concentrate 38% Ag recovery to Pb concentrate 83% Pb recovery to Pb concentrate grading 63% lead
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-35
Zinc Concentrate
12% Ag recovery to Zn concentrate 82% Zn recovery to Zn concentrate grading 49% zinc
Copper Concentrate
34% Au recovery to Cu concentrate 10% Ag recovery to Cu concentrate 68% Cu recovery to Cu concentrate grading 27% copper
Ambrex Stringer Copper Concentrate
93% Au recovery to Cu concentrate 75% Ag recovery to Cu concentrate
Standard smelting and refining charges were applied to the various concentrates. It was
assumed that the concentrates would be marketed internationally.
The NSR factors are shown in Table 14-11 which can be used to calculate the NSR for any
set of metal grades.
TABLE 14-11 NSR FACTORS VM Holding S.A. – Aripuanã Zinc Project
Metal Units Arex Ambrex
Stratabound Stringer Stratabound Stringer Au US$ per g Au 23.99 38.63 22.3 38.3 Ag US$ per g Ag 0.47 0.44 0.28 0.43 Cu US$ per % Cu 33.59 47.9 33.41 47.65 Pb US$ per % Pb 12.03 - 11.97 - Zn US$ per % Zn 11.96 - 11.89 -
For the purposes of developing an NSR cut-off value, a total unit operating cost of US$46.00
per tonne of stratabound mineralization and US$42.00 per tonne of stringer mineralization
milled was estimated, which included mining, processing, and general and administrative
expenses.
The sensitivity of the Mineral Resource to NSR cut-off grade is shown in Tables 14-12 and 14-
13.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-36
TABLE 14-12 SENSITIVITY TO CUT-OFF GRADE - STRATABOUND VM Holding S.A. – Aripuanã Zinc Project
Measured and Indicated
NSR Cut-off Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
$14.00 21.4 5.07 1.87 0.12 0.22 44.47 2,388.4 880.4 57.7 153.7 30.6
$30.00 20.7 5.19 1.92 0.13 0.23 45.67 2,370.3 875.1 57.3 152.4 30.4
$46.00 18.3 5.61 2.09 0.14 0.24 50.08 2,269.9 844.3 54.7 143.7 29.5
$62.00 15.4 6.18 2.33 0.15 0.26 56.56 2,093.2 789.9 51.1 129.0 27.9
Inferred
NSR Cut-off Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
$14.00 18.4 5.60 2.14 0.08 0.31 47.29 2,271.8 869.1 34.2 185.3 28.0
$30.00 16.0 6.26 2.41 0.09 0.35 53.58 2,205.2 850.7 32.9 178.5 27.5
$46.00 13.2 7.20 2.80 0.10 0.38 62.50 2,099.7 815.4 29.4 162.7 26.6
$62.00 10.8 8.30 3.26 0.11 0.42 72.66 1,967.3 773.6 25.8 144.5 25.1
TABLE 14-13 SENSITIVITY TO CUT-OFF GRADE - STRINGER VM Holding S.A. – Aripuanã Zinc Project
Measured and Indicated
NSR Cut-off Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
$18.00 3.7 0.21 0.09 1.27 1.16 14.70 17.4 7.8 104.7 139.0 1.8
$30.00 3.7 0.21 0.10 1.29 1.17 14.90 17.4 7.8 104.4 138.3 1.8
$42.00 3.5 0.22 0.10 1.35 1.21 15.49 17.2 7.7 103.1 135.3 1.7
$54.00 3.1 0.25 0.11 1.46 1.29 16.73 16.7 7.6 99.3 128.0 1.7
Inferred
NSR Cut-off Tonnes (Mt) Zn (%) Pb (%) Cu (%) Au (g/t) Ag (g/t) Zn (Mlb) Pb (Mlb) Cu (Mlb) Au (koz) Ag (Moz)
$18.00 15.4 0.10 0.06 0.65 1.25 8.36 33.8 19.5 219.7 619.6 4.1
$30.00 13.7 0.09 0.06 0.70 1.37 8.85 27.3 17.2 211.9 603.2 3.9
$42.00 11.4 0.08 0.05 0.78 1.55 9.31 19.3 13.5 197.0 569.7 3.4
$54.00 9.0 0.07 0.05 0.90 1.80 10.28 13.8 10.5 177.0 518.2 3.0
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-37
CLASSIFICATION Definitions for resource categories used in this report are consistent with those defined by CIM
(2014) and adopted by NI 43-101. In the CIM classification, a Mineral Resource is defined as
“a concentration or occurrence of solid material of economic interest in or on the Earth’s crust
in such form, grade or quality and quantity that there are reasonable prospects for eventual
economic extraction”. Mineral Resources are classified into Measured, Indicated, and Inferred
categories. A Mineral Reserve is defined as the “economically mineable part of a Measured
and/or Indicated Mineral Resource” demonstrated by studies at Pre-Feasibility or Feasibility
level as appropriate. Mineral Reserves are classified into Proven and Probable categories.
Blocks were classified as Measured, Indicated, and Inferred based on drill hole spacing
requirements determined from global variograms for the Arex stratabound, Arex stringer,
Ambrex stratabound, and Ambrex Link Zone stratabound domains. Flagging of the blocks by
drill hole spacing was done by using a search pass with dimensions as described in Table 14-
14 and capturing at least three drill holes.
The first pass involved a numerical classification as described of blocks followed by a post
processing of the classification to remove isolated blocks classified as Measured or Indicated.
The entire stringer zone at Ambrex was classified as Inferred due to the drill holes intersecting
the mineralization at low angles.
The classification criteria for each area are listed in Table 14-14 and the global variograms
used as a basis for the classification scheme are shown in Figure 14-19. A longitudinal section
showing the final classification is provided in Figure 14-20.
With regard to the classification, RPA notes the following:
• The overall classification is reasonable for the level of study.
• The average drill hole spacing for Measured and Indicated categories is slightly wider than the distances given in Table 14-14 due to the methodology used to flag blocks by distance.
• There are areas in Ambrex where wireframes have been extrapolated to greater distances than the Inferred classification criteria. The majority of this material has been included as Inferred.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-38
With respect to classification RPA recommends the following:
• Performing a visual review of the classification of all blocks with a minimum distance to the closest drill hole greater than 25 m, and consider downgrading blocks where appropriate to Inferred.
• Restricting wireframe extrapolation to distances consistent with the classification criteria.
TABLE 14-14 VMH SEARCH ELLIPSE RANGES FOR CLASSIFICATION CRITERIA
VM Holding S.A. – Aripuanã Zinc Project
Area Type Measured Indicated Inferred Arex Stratabound 25 m X 25 m 50 m X 50 m 100 m X 100 m
Stringer 20 m X 20 m 50 m X 50 m 100 m X 100 m Ambrex Stratabound 20 m X 20 m 50 m X 50 m 100 m X 100 m
Stringer - - 100 m X 100 m Ambrex Link Zone Stratabound 25 m X 25 m 50 m X 50 m 200 m X 200 m
Stringer - - 100 m X 100 m Minimum DDH in ellipse* All 3 3 -
*Minimum DDH in ellipse refers to the isotropic search ellipsoid used to flag the distances in the blocks
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-39
FIGURE 14-19 GLOBAL VARIOGRAMS USED FOR CLASSIFICATION CRITERIA
1000 Metres
Measured
Classification
Legend:
Indicated
Inferred
July 2017 Source: RPA, 2017.
Drill Hole Trace
Final Classification Designation
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
V Holding S.A.M
Figure 14-20
14-4
0
ww
w.rp
acan
.co
m
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-41
VALIDATION
VMH A number of validation steps were performed by VMH including:
• Comparison between OK, NN, and composite mean grades (Table 14-15, Figures 14-21 and 14-22).
• Swath plots (Figure 14-23 to 14-26).
• Visual inspection of composites versus block grades (example Figure 14-27 to 14-30).
For many of the variables, areas and mineralization types, there is a better agreement between
the NN and OK means than the composite and OK means, which would suggest that the
composite data is clustered. Similar trends are observed on the swath plots. Gold block
grades show a large deviation from both the composite and NN mean although the deviation
is negative. The Cu composites versus block grades show discrepancies as high as 26% in
the stringer zone although the NN grades are within two percent. Mean comparisons on a
wireframe by wireframe basis show much larger discrepancies between the means.
In RPA’s opinion, the validation performed are typical industry standard validation techniques
and in general, the results presented look reasonable.
TABLE 14-15 COMPARISON BETWEEN OK, NN AND COMPOSITE MEANS (ZN AND CU)
VM Holding S.A. – Aripuanã Zinc Project
Area Arex Arex Ambrex Ambrex Type Stratabound Stringer Stratabound Stringer Variable Zn Cu Zn Cu OK mean 5.72 1.04 5 0.6 NN Mean 5.08 1.03 5.19 0.61 Composite Mean 5.04 1.31 4.79 0.47 OK/NN 113% 101% 96% 98% OK/Composites 113% 79% 104% 128%
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-42
FIGURE 14-21 COMPARISON BETWEEN OK AND NN MEANS (ZN STRATABOUND)
FIGURE 14-22 COMPARISON BETWEEN OK AND NN MEANS (CU STRINGER)
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-43
FIGURE 14-23 AREX ZN SWATH PLOT – EASTING
FIGURE 14-24 AREX CU SWATH PLOT – EASTING
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-44
FIGURE 14-25 AMBREX ZN SWATH PLOT – EASTING
FIGURE 14-26 AMBREX CU SWATH PLOT – EASTING
0 25
Metres
50 75 100
Source: Votorantim Metais, 2016.August 2017
Arex Vertical Section ShowingZn Block vs Composite Grades
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 14-27
14-45
www.rpacan.com
0 25
Metres
50 75 100
Source: Votorantim Metais, 2016.July 2017
Arex Vertical Section ShowingCu Block vs Composite Grades
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 14-28
14-46
www.rpacan.com
0 25
Metres
50 75 100
Source: Votorantim Metais, 2016.July 2017
Ambrex Vertical Section ShowingZn Block vs Composite Grades
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 14-29
14-47
www.rpacan.com
0 25
Metres
50 75 100
Source: Votorantim Metais, 2016.July 2017
VM Holding S.A.
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
Ambrex Vertical Section ShowingCu Block vs Composite Grades
Figure 14-30
14-48
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-49
RPA In addition to reviewing VMH’s validation, RPA performed the following validation steps:
• Check Estimates
• Global Change of Support Check (GCOS) (Figure 14-31)
• Visual inspection of the block model and composites provided
RPA tested a number of parameters including the substitution of zeroes for unsampled
intervals, more restrictive across strike search distance, density weighting of estimates and
downgraded classification designation according to RPA’s preferred criteria. The estimates
were most sensitive to density weighting and RPA’s preferred classification. Density weighting
would result in an overall positive deviation from VMH’s estimate while RPA’s re-classification
would result in a negative impact on the total Measured and Indicated. RPA found the
variances to be immaterial and is of the opinion that VMH’s estimate is reasonable.
RPA performed GCOS on selected wireframe domains and found that compared to the
theoretical grade and tonnage curve, the Ambrex model was reasonable while the Arex model
reported more tonnes at a lower grade.
Overall, the block grades are in agreement with the underlying composite data on sections and
plans. Dynamic anisotropy appears to be working as planned for most zones. RPA noted
minor areas where grade trends appeared to be perpendicular to the wireframe. At Arex there
appears to be a level of over-smoothing which is consistent with the observations from RPA’s
GCOS study.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 14-50
FIGURE 14-31 GLOBAL CHANGE OF SUPPORT CHECK FOR BODIES 53, 54 AND 80
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 15-1
15 MINERAL RESERVE ESTIMATE No Mineral Reserves have been estimated for the Project.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-1
16 MINING METHODS INTRODUCTION The current Project is targeted on mining three main elongate mineralized zones, Arex, Link,
and Ambrex that have been defined in the central portion of the Aripuanã Project.
The Arex and Ambrex deposits are separate VMS deposits with differing mineral compositions
in stratabound and stringer forms and complex geometric shapes.
The deposit geometry is amenable to a number of underground mechanized mining techniques
including cut-and-fill and bulk stoping methods. A nominal production target of 5,000 tpd has
been used as the basis for the mine production schedule.
Mining will be undertaken using conventional mechanized underground mobile mining
equipment via a network of declines, access drifts and ore drives. Access to the Arex and
Ambrex deposits will be from separate portals, which will access the deposits from the most
favorable topographic locations.
Due to the presence of high grade mineralization in the upper levels of Arex, production will
commence in the Arex deposit and then move into the Ambrex deposit.
MINE DESIGN The mine design has been based around using modern mobile trackless equipment with
independent decline accesses into the Arex and Ambrex deposits.
The Arex deposit extends over a strike length of approximately 1,400 m. Upper portions of the
deposit are near-vertical, reducing at depth to a dip of approximately 60° to the northeast.
Mineralization occurs in discrete stratabound and stringer lenses of stratabound, ranging from
less than one metre to 15 m thick in width interspersed with some zones between 100 m to
150 m wide. Mineralization extends from close to surface to about 500 m below surface (mbs).
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-2
The Ambrex deposit is located approximately 1,300 m southeast of Arex and represents the
largest of the known mineralized zones on the Project. The deposit has a strike extent of
approximately 1,050 m, based on current drilling. The dip varies from near vertical to 70° to
the northeast. Mineralization thicknesses typically range between 10 m and 50 m, with a
maximum of 150 m. The deposit extends vertically from 60 mbs to approximately 700 mbs.
The two deposits will be accessed from two independent surface cut and cover portals and the
ramps are designed at a gradient of 14% to be driven with an arched profile and a cross-
sectional area (CSA) of 27 m2 to accommodate the selected major equipment. The main
loading and hauling equipment will be 12.5 t class load haul dump (LHD) combined with 35.5 t
class haul trucks.
Main mining sublevels are spaced 75 m apart, with stope sublevels currently placed at 25 m
spacing.
Figures 16-1, 16-2, and 16-3 shows the mine design for the two deposits
July 2017
Portal
Portal
Arex Ambrex
Source: Votorantim Metais, 2017.
Mine Layout ofBoth Deposits
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
V Holding S.A.M
Figure 16-1
16-3
ww
w.rp
acan
.co
m
July 2017
Portal
Ambrex
Source: Votorantim Metais, 2017.
Layout of Ambrex
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
V Holding S.A.M
Figure 16-2
16-4
ww
w.rp
acan
.co
m
July 2017
Portal
Arex
Source: Votorantim Metais, 2017 .
Layout of Arex
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
V Holding S.A.M
Figure 16-3
16-5
ww
w.rp
acan
.co
m
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-6
The secondary lateral ore and waste development including FW drifts and crosscuts, stope
access drives are designed with an arched profile and a CSA of 22.5 m2.
Table 16-1 shows the development dimensions used in the current mine design.
TABLE 16-1 DEVELOPMENT DIMENSIONS VM Holding S.A. – Aripuanã Zinc Project
Activity Type Dimensions (m)
Primary Development Raisebore Ramps
3.0 Dia 5.0 x 6.0
Secondary Lateral Development
Sublevels Cross Cuts
Footwall Drives Ore Drives
5.0 x 5.0
In total, the LOM development plan includes approximately 180 km of development,
comprising primary ramps, lateral ore and FW drives (levels, stope access and ventilation
infrastructure), production and service drifts and vertical development (raises).
The total development included in the LOM is shown in Table 16-2.
TABLE 16-2 LOM TOTAL DEVELOPMENT VM Holding S.A. – Aripuanã Zinc Project
Development Type Total Metres
Primary Development 42,944
Ramps 26,068
Ventilation drives 16,878
Secondary Lateral 129,665
Crosscuts 35,238
FW Drives 19,231
Ore Drives – VRM Stopes 22,846
Ore Drives - BS 52,350
Slot and Orepass Raises 2,988
Ventilation Raise Bores 3,961
TOTAL 179,558
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-7
MINING METHOD The deposit geometry is suited to a number of underground mechanized mining techniques
including cut-and-fill and bulk longhole open stoping methods.
A nominal production target of 5,000 tpd (1.8 Mtpa) has been used as the basis for the mine
production schedule.
VMH has undertaken a number of mining method option studies, the result of which has been
the selection, for the conceptual mine design and mine plan, of longitudinal longhole retreat
stoping (bench stoping) for the narrower zones of the deposits with Vertical Retreat Mining
(VRM) applied for the thicker zones. To increase the extraction ratio, a primary and secondary
stoping sequence will be used in the VRM areas with cemented paste and rock fill used to
backfill primary stopes and uncemented rock fill placed in the secondary stopes. Finished
longhole retreat stopes will also be backfilled with rock fill.
The majority of the production from the Arex deposit is based on longitudinal longhole retreat
mining, however, in areas where the deposit is wider (greater than 15 m), Vertical Retreat
Mining (VRM) longhole mining with primary and secondary stopes will be used. The method
applied in the Ambrex deposit will be predominantly the VRM method.
Stope sizes are nominally 15 m long x 25 m high with various widths from hanging wall (HW)
to footwall (FW).
An estimate of the potentially mineable tonnage has been generated based upon the estimated
Mineral Resources. The estimate includes both Inferred and Indicated Mineral Resources.
Deswik Stope Optimizer (DSO) was used to generate stope shapes down to a minimum dip of
40°. This results in some flat stopes being included in the mine plan. A Minimum Mining Width
(MMW) of four metres has been applied.
No hanging wall or footwall dilution was added in the DSO analysis but was added later in the
mine scheduling.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-8
For the narrow vein stopes 10% dilution was added, which RPA considers to be acceptable
for the steeper dipping stopes. However, for stopes flatter than 50° to 55°, RPA’s opinion is
that dilution should be increased to between 15% and 20%.
A mining recovery of 95% has been applied to primary and vein stopes with 90% applied to
the secondary stopes.
GEOMECHANICS AND GROUND SUPPORT The available geomechanical data indicates that generally good ground conditions may be
anticipated in the Aripuanã underground. This assumption will need to be confirmed at the
next study stage to improve the geomechanical characteristics confidence level of the
geomechanical model, to confirm the proposed underground openings design, and to support
engineering used to determine cost and schedule assumptions for the PEA.
An additional and comprehensive geomechanical investigation and study will therefore be
needed during the next stage of project development.
For the Aripuanã mine design, the Rock Mass Rating (RMR) system developed by Bieniawski
(1989) was used based on the data collected during the FEL1 investigation program. From
the results of the investigation, the host rock was categorized into two main domains named
“Weathered Rock” and “Fresh Rock” with five RMR Classes.
The Weathered Rock represents the lower quality rock mass with RMR Classes of III, IV and
V; III/IV being Poor (RMR 40) and IV and V Exceptionally Poor (RMR 20) beneath the overlying
overburden with RMR. The overburden thickness ranges between approximately 25 m and
50 m, and the Weathered Rock has thickness of approximately 50 m to 60 m. Both of these
lithologies will be encountered during the excavation of ramp portals and the upper section of
the ramps. Approximately 80% of the Weathered Rock in the two deposits is placed in RMR
Class IV.
The Fresh Rock domain categorized by RMR Class II/III (RMR 60) represents the competent
host rock of the deposits and in which the majority of mining underground works (stopes,
declines, drifts, etc.) will be excavated. Approximately 70% of the Fresh Rock in the two
deposits is placed in RMR Class II.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-9
Three RMR classes are expected in the underground developments in both Arex and Ambrex.
Predominantly the ground conditions are expected to be in the Good/Normal category with a
typical RMR of 60. This results in a recommended pattern bolt spacing of 1.5 m x 1.5 m in the
hanging wall and sidewalls with 2.4 m long bolts used in decline/access drifts, crosscuts, and
footwall drives in waste rock, with 1.8 m long bolt for ore drives. Only relatively small sections
of lower class ground conditions are expected and for these closer spacing of bolts will be
required.
Additional temporary cable bolting using 4.5 m to 6.0 m long cable bolts will be needed in the
hanging wall at the access drive /stope brow locations with cable bolts maintained
approximately 1.0 m to 1.5 m back from the brow edge.
Stability analyses were carried out on stopes with a height of 20 m, lengths of 45 m and 60 m
for various stope widths and dips (hanging wall angle). The stope stability analysis showed
that hanging wall support is generally required for all of the likely stope configurations, although
it should be noted that support, stability and dilution will additionally benefit from a good drill
and blast performance (explosive properties, drill hole design, drilling accuracy and explosive
distribution etc.).
Cable length will vary in most cases from 6 m to 13 m, dependent on stope configuration and
hanging wall angle. Cable bolts on a regular pattern of about 2 m x 2 m spacing for both Arex
and Ambrex is envisaged based on the currently available geomechanical data.
Based on an assessment of unplanned stope dilution, the maximum recommended stope
length is 60 m for Arex and 45 m for Ambrex.
As the Arex mineralisation is relatively close to surface, and to mitigate against the possibility
of any surface subsidence, which would create environmental damage and breaches of the
permit conditions, a crown pillar needs to be left above the mining zone in Arex. An
assessment carried out in the geomechanical study recommended a crown pillar of 45 m to
46 m in thickness. No crown pillar is envisaged for Ambrex.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-10
MINE INFRASTRUCTURE
MATERIAL HANDLING Production and waste will be handled via internal ore and waste passes.
Mine trucks will dump material into a grizzly to control the size of broken rock passing through.
A rock breaker will be installed at the entrance of the grizzly to handle oversized material. After
the grizzly, material will flow into a storage bin Material is then fed from the bin into haul trucks
that haul directly up the surface ramp to the surface stockpile at the process plant.
BACKFILL For tailings disposal at Aripuanã approximately 50% of the tailings dry solids is expected to be
placed back underground as backfill, in order to reduce the environmental impact.
Backfill is also required in order to allow a primary and secondary extraction sequence in the
VRM areas of the mine. Based on the available testwork data on tailings, cemented paste fill
is considered to be the best solution.
A paste plant of sufficient capacity to meet the demand for paste backfill underground, will be
located at surface. Paste will be delivered underground via dedicated boreholes. The delivery
of paste to stopes will be by pipeline. The geometry of the Arex and Ambrex deposits suggests
that much of the paste can be delivered by gravity, however outlying stopes may require the
use of a paste pump. Typically, the paste piping comprises ASTM Grade A53 mild steel with
a wall thickness of Schedule 80 or Schedule 120.
Further engineering and testwork will be required during the next phase of study to confirm the
tailings characteristics and the design of the paste facility.
VENTILATION A preliminary ventilation design has been prepared for Aripuanã Mine using generic
parameters to determine the overall mine airflow for both Arex and Ambrex. The ventilation
design criteria used conform to established international best practices. Although acceptable
for a PEA, further ventilation modelling using industry standard software, such as Ventsim or
VUMA, will be needed for the next level of study.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-11
Under best practice ventilation requirements would be determined based on diesel fleet
schedule however at this level of study it is appropriate to use an empirical model to determine
the ventilation requirements.
The air requirements are based upon the active mining fleet and the other standard mine
ventilation criteria. An air diesel power ratio of 0.05 m³/s/kW is widely accepted as an
underground minimum, however, it may be necessary to raise this to 0.07 m³/s/kW for
Aripuanã to provide extra airflow for cooling purposes. This can be confirmed when ventilation
simulation modelling is conducted.
The empirical model is relationship between annual production rate and quantity of air required
to circulate through the mine.
This type of estimate is sufficient for the Aripuanã PEA report, although for a bankable
feasibility study detailed calculations and ventilation simulations will need to be conducted.
From the empirical relationship above, the airflow requirement for a 1.8 Mtpa mine steady state
production is approximately 610 m³/s.
With an airflow velocity of 6.5 m/s down the main access decline 5.0 m W x 6.0 m H
(approximately 30 m² section) an intake of 195 m³/s is achievable. The remaining intake
requirement will be obtained from two intake ventilation raises with a CSA of 32 m2. The
exhaust return airway system would consist of three raises with a CSA of 32 m2 to handle 610
m³/s at a velocity of 13 m/s.
The main variable drive fans will consist of 2 x 250 kW axial fans located in a station at the top
of each ventilation raise. The nominal operating point of the fans is approximately 100m/s3 at
1.95 kPa.
MINE DEWATERING A hydrogeological study, including a site-wide stochastic model, has been undertaken in an
earlier phase of the Project development based on the available hydrological and
hydrogeological data. This provided a preliminary assessment of the likely inflow into the mine
as well as the likely drawdown around the deposits.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-12
The study suggests that total inflow into the mien will be relatively low, peaking in years 7 and
8 of operation at 160 m3/hr. The Arex operations are expected to produce the most flow
because the deposit is located in an area of higher aquifer potential.
The mine dewatering will make a significant contribution to the total water demand of the
Project.
An allowance has been made for provision of underground dewatering pumps in the capital
cost estimate.
MAINTENANCE FACILITIES An underground mechanical maintenance shop is envisaged for both areas of the mine will be
constructed. This shop is envisaged to handle all maintenance requirements, and will include
a welding area, tire bay, wash bay, lubricants area, tool storage, and training area. Major
equipment rebuilds would be sent offsite.
POWER AND COMPRESSED AIR The mine is envisaged to have a relatively high degree of machine mechanization, and
consequently, an extensive electrical distribution system is required. A central substation will
be located in the vicinity of each portal from where electrical power will be distributed
underground to other substations located underground throughout the mine.
The electrical load is split between mine equipment, pumping systems, compressors, mine
stationary equipment, ventilation systems, and miscellaneous facilities.
A compressed air system will be installed in the mine, which will be used by some of the mine
equipment. The system will also comprise a storage tank, and an air dryer with compressors
will be stationed in the vicinity of the portals. The air will be distributed through varying sizes
of pipe starting with 100 mm and getting smaller as the air reaches the working areas.
REFUGE STATIONS AND ESCAPEWAYS The mine will be provided with second means of egress from the workings to the surface. This
will be catered for by equipping the ventilation drop raises from level to level with a ladder way
with an escape door at the main fan stations.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-13
Refuge stations equipped a supply of fresh air will be provided at strategic locations
underground. The locations will be such that workers are able to reach them from the work
places within the duration of the self-contained self-rescue apparatus worn by all underground
personnel.
MINE EQUIPMENT The mine will be operated with a fully mechanized mobile mining equipment fleet, with a
minimum of hand equipment.
The list of equipment prepared by VMH is shown in Table 16-3. The following equipment has
been provided for the Project:
TABLE 16-3 EQUIPMENT FLEET VM Holding S.A. – Aripuanã Zinc Project
RPA is of the opinion that the fleet estimate may be somewhat short in the number of units of
certain equipment.
In particular the number of production drills (fan drills) may have been underestimated. In
order to meet the production targets, there will be a minimum of four stopes in production
(drill/blast/muck). In addition to the stopes in full production there will be the stopes that being
prepared for production. RPA is of the opinion that two to three more production drills will be
required in order to maintain the production requirements. In the early years of the mine life,
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-14
Arex and Ambrex are not connected, and use separate portals, making it more difficult to share
equipment efficiently.
The equipment list will be reassessed as part of the next, more comprehensive and detailed
study.
LIFE OF MINE PLAN
PRE-PRODUCTION SCHEDULE A pre-production period of two years is envisaged for the initial development of the mine.
MINE PRODUCTION The mine development and production schedule was generated using the rates shown in Table
16.4.
TABLE 16-4 ADVANCE RATES VM Holding S.A. – Aripuanã Zinc Project
Heading Size Rate
Ramp 5.0mW x 6.0mH 80m/mo
Vent Access 4.0mW x 4.0mH 60m/mo
Ore Headings Level development 5.0mW x 5.0mH 60m/mo
Raises Alimak -bore 3m Dia. 90m/mo
Stope Various 20,000 - 40,000 t/mo
RPA considers the monthly for the secondary capital development and operating development
rates used in the LOM to be generally acceptable for this level of study. An advance rate of
60 m/mo for lateral access drives is reasonable and within industry standards.
However, the assumed ramp development rate to be at the top end of what may be achievable
over a sustained period, in RPA’s opinion. Similarly, RPA considers the raiseboring rates used
to be aggressive. These rates should be reassessed in the next phase of study and the impact
on the schedule evaluated.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 16-15
The majority of the stopes are scheduled at 20,000 t/mo, which RPA considers to be
reasonable.
RPA recommends that daily rather monthly rates should be used in the next so that the varying
available days per month can be more accurately allowed for.
The mine is assumed to be operating on a 360 days per year rotation, with three 8-hour shifts
per day. The effective operating hours per day were calculated to be 18 hours per day.
The mine plan envisages a production rate of 5,000 tpd or 1.8 Mtpa. Production is assumed
to ramp up to full production over a two year period.
The production schedule is shown in Table 16-5.
UNITS TOTAL 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044MINING
AREX StringerProduction '000 tonnes 3,450 114 242 176 110 42 48 73 115 145 47 98 45 59 39 207 363 455 277 399 206 191
Zn Grade % 0.10% 0.18% 0.15% 0.05% 0.10% 0.23% 0.34% 0.09% 0.12% 0.09% 0.06% 0.08% 0.02% 0.05% 0.02% 0.14% 0.04% 0.11% 0.19% 0.05% 0.04% 0.02%Pb Grade % 0.06% 0.07% 0.07% 0.02% 0.08% 0.08% 0.21% 0.03% 0.06% 0.08% 0.03% 0.07% 0.06% 0.06% 0.02% 0.04% 0.06% 0.07% 0.11% 0.02% 0.02% 0.01%Cu Grade % 0.83% 1.11% 1.24% 1.04% 1.74% 1.28% 1.39% 0.85% 0.99% 0.99% 0.94% 1.17% 0.58% 0.40% 0.49% 1.11% 0.46% 0.63% 0.90% 0.70% 0.59% 0.41%Ag Grade oz/t 0.31 0.40 0.36 0.23 0.33 0.36 0.49 0.24 0.40 0.23 0.35 0.34 0.24 0.22 0.29 0.30 0.23 0.32 0.43 0.30 0.28 0.19 Au Grade oz/t 0.07 0.03 0.03 0.04 0.07 0.02 0.03 0.03 0.02 0.02 0.02 0.03 0.10 0.19 0.03 0.05 0.23 0.07 0.04 0.05 0.04 0.07
AREX StrataboundProduction '000 tonnes 4,280 390 366 339 130 92 69 51 73 81 129 53 100 100 52 158 360 447 745 349 189 6
Zn Grade % 5.21% 6.85% 6.11% 4.98% 4.12% 5.17% 4.16% 4.59% 4.02% 4.19% 4.95% 5.43% 7.41% 4.64% 5.37% 5.01% 4.69% 4.53% 5.27% 5.17% 4.64% 3.16%Pb Grade % 1.79% 2.36% 2.03% 1.64% 1.22% 2.29% 1.41% 1.32% 1.16% 1.47% 1.76% 1.66% 2.47% 1.94% 1.83% 1.93% 1.66% 1.49% 1.76% 1.87% 1.56% 0.83%Cu Grade % 0.23% 0.35% 0.21% 0.16% 0.29% 0.22% 0.17% 0.29% 0.40% 0.47% 0.20% 0.37% 0.21% 0.18% 0.25% 0.20% 0.18% 0.18% 0.23% 0.24% 0.13% 0.02%Ag Grade oz/t 1.34 2.22 2.18 1.42 0.88 1.47 0.90 1.47 1.01 1.67 1.01 0.77 1.14 1.15 1.02 1.14 0.84 1.14 1.12 1.49 0.99 0.56 Au Grade oz/t 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.00
AREX MixProduction '000 tonnes 1,839 67 197 206 59 52 59 63 40 49 77 4 37 15 7 320 199 11 159 144 74
Zn Grade % 2.61% 2.29% 2.26% 2.63% 2.35% 2.51% 2.36% 1.78% 1.30% 1.20% 3.07% 2.60% 2.07% 3.36% 3.19% 2.19% 2.38% 2.13% 4.30% 3.43% 3.47%Pb Grade % 0.89% 0.72% 0.61% 0.74% 0.65% 1.02% 0.73% 0.67% 0.35% 0.37% 1.16% 0.85% 0.67% 1.07% 1.36% 0.83% 0.86% 0.72% 1.84% 0.75% 1.53%Cu Grade % 0.86% 1.18% 1.30% 1.00% 1.18% 0.51% 0.78% 0.59% 0.97% 0.97% 0.71% 0.69% 1.34% 0.53% 0.30% 0.67% 0.86% 0.93% 0.84% 0.58% 0.48%Ag Grade oz/t 0.85 0.84 0.77 0.82 1.00 0.75 0.82 0.74 0.54 0.60 1.13 0.42 0.59 1.07 0.72 0.80 0.82 0.77 1.29 0.66 1.21 Au Grade oz/t 0.02 0.02 0.02 0.02 0.01 0.02 0.01 0.01 0.01 0.02 0.01 0.01 0.02 0.01 0.01 0.02 0.02 0.02 0.03 0.02 0.01
AMBREX StringerProduction '000 tonnes 6,470 - - 6 118 94 188 230 734 512 921 743 720 302 630 142 37 38 172 346 236 229 61 11 ‐
Zn Grade % 0.05% 0.00% 0.00% 0.06% 0.14% 0.04% 0.10% 0.11% 0.10% 0.09% 0.05% 0.04% 0.03% 0.02% 0.02% 0.02% 0.04% 0.04% 0.04% 0.03% 0.03% 0.03% 0.03% 0.02%Pb Grade % 0.04% 0.00% 0.00% 0.02% 0.06% 0.04% 0.04% 0.04% 0.06% 0.07% 0.02% 0.02% 0.04% 0.02% 0.04% 0.04% 0.05% 0.03% 0.03% 0.04% 0.02% 0.02% 0.01% 0.01%Cu Grade % 0.78% 0.00% 0.00% 0.62% 0.86% 0.99% 0.81% 1.02% 0.90% 0.69% 1.02% 0.96% 0.65% 0.57% 0.51% 0.33% 0.66% 1.00% 0.78% 0.64% 0.58% 0.72% 0.97% 0.84%Ag Grade oz/t 0.27 - - 0.42 0.35 0.36 0.26 0.34 0.30 0.25 0.30 0.38 0.29 0.21 0.18 0.21 0.25 0.26 0.19 0.19 0.15 0.24 0.24 0.36 Au Grade oz/t 0.04 - - 0.01 0.02 0.02 0.02 0.04 0.04 0.03 0.03 0.03 0.04 0.04 0.05 0.06 0.04 0.04 0.05 0.04 0.04 0.02 0.03 0.06
AMBREX StrataboundProduction '000 tonnes 20,067 2 98 624 1,355 1,433 1,389 1,208 796 1,007 619 861 814 1,297 1,085 956 784 859 433 579 848 1,082 1,232 496 209
Zn Grade % 5.94% 5.69% 6.59% 5.02% 4.76% 4.87% 4.67% 4.62% 4.53% 5.92% 6.67% 9.12% 7.19% 10.35% 10.72% 7.93% 5.24% 5.61% 5.08% 5.05% 4.77% 4.52% 3.66% 3.56% 3.24%Pb Grade % 2.39% 1.98% 2.43% 1.88% 2.07% 1.97% 2.13% 1.87% 1.59% 2.05% 2.40% 4.36% 3.16% 4.53% 5.11% 3.15% 2.01% 1.95% 1.72% 1.95% 1.60% 1.42% 1.08% 1.25% 1.12%Cu Grade % 0.06% 0.04% 0.04% 0.04% 0.05% 0.05% 0.04% 0.06% 0.05% 0.08% 0.07% 0.07% 0.06% 0.07% 0.07% 0.04% 0.07% 0.06% 0.10% 0.13% 0.12% 0.09% 0.05% 0.03% 0.02%Ag Grade oz/t 1.79 2.00 2.56 1.58 1.75 1.81 1.81 1.55 1.13 1.49 1.91 2.88 2.22 3.18 3.37 2.61 1.87 1.46 1.07 1.38 1.09 0.81 0.72 0.81 0.88 Au Grade oz/t 0.01 0.00 0.01 0.00 0.01 0.01 0.01 0.01 0.00 0.01 0.01 0.01 0.01 0.02 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
AMBREX MixProduction '000 tonnes 846 - - 19 10 85 43 182 61 22 29 15 86 21 1 23 73 2 30 5 0 123 16
Zn Grade % 3.42% 0.00% 0.00% 2.89% 3.12% 2.83% 3.92% 2.92% 2.80% 1.07% 5.97% 2.28% 4.92% 5.79% 10.41% 3.49% 3.62% 0.81% 4.22% 2.21% 1.09% 3.10% 3.15%Pb Grade % 1.16% 0.00% 0.00% 0.57% 1.01% 0.81% 1.27% 0.86% 1.08% 0.32% 1.46% 0.94% 1.96% 3.58% 4.15% 1.44% 1.33% 0.30% 1.98% 0.89% 0.37% 0.85% 0.55%Cu Grade % 0.37% 0.00% 0.00% 0.16% 0.33% 0.38% 0.21% 0.39% 0.15% 0.42% 0.12% 0.43% 0.24% 0.12% 0.05% 0.09% 0.18% 1.46% 0.58% 0.10% 0.26% 0.81% 0.34%Ag Grade oz/t 0.91 - - 0.34 1.05 0.63 0.83 0.86 0.98 0.45 1.06 0.59 1.36 2.23 1.03 1.38 0.78 0.50 1.19 0.53 0.20 0.75 0.76 Au Grade oz/t 0.01 - - 0.00 0.01 0.01 0.00 0.01 0.01 0.01 0.00 0.01 0.01 0.02 0.02 0.00 0.01 0.05 0.02 0.01 0.02 0.04 0.01
TOTAL MinedProduction '000 tonnes 36,953 574 903 1,369 1,781 1,798 1,796 1,807 1,819 1,815 1,822 1,774 1,802 1,794 1,814 1,806 1,815 1,812 1,817 1,822 1,553 1,632 1,308 508 209
Zn Grade % 4.06% 4.98% 3.73% 3.96% 4.03% 4.36% 3.97% 3.59% 2.31% 3.55% 2.87% 4.63% 3.95% 7.84% 6.59% 5.09% 3.61% 3.81% 3.85% 2.89% 3.34% 3.25% 3.49% 3.48% 3.24%Pb Grade % 1.59% 1.71% 1.24% 1.38% 1.70% 1.76% 1.76% 1.40% 0.81% 1.24% 1.02% 2.19% 1.69% 3.44% 3.13% 2.01% 1.36% 1.31% 1.35% 1.05% 1.14% 1.01% 1.03% 1.22% 1.12%Cu Grade % 0.33% 0.60% 0.71% 0.35% 0.26% 0.16% 0.19% 0.27% 0.49% 0.37% 0.61% 0.52% 0.35% 0.17% 0.23% 0.31% 0.27% 0.26% 0.41% 0.41% 0.27% 0.27% 0.10% 0.05% 0.02%Ag Grade g/t 39 53 44 38 46 50 47 39 23 32 29 50 39 76 66 53 36 33 29 27 26 20 22 25 27 Au Grade g/t 0.61 0.42 0.52 0.38 0.35 0.22 0.25 0.36 0.60 0.55 0.69 0.62 0.75 0.79 0.89 0.64 1.73 0.74 0.62 0.72 0.53 0.62 0.20 0.22 0.21
Contained MetalZn kt 1,500 29 34 54 72 78 71 65 42 64 52 82 71 141 120 92 66 69 70 53 52 53 46 18 7 Pb kt 587 10 11 19 30 32 32 25 15 23 19 39 30 62 57 36 25 24 24 19 18 17 13 6 2 Cu kt 120 3 6 5 5 3 3 5 9 7 11 9 6 3 4 6 5 5 8 7 4 4 1 0 0 Ag kozs 46,852 971 1,285 1,685 2,628 2,865 2,727 2,243 1,328 1,840 1,723 2,847 2,273 4,386 3,836 3,060 2,077 1,924 1,691 1,601 1,294 1,060 917 406 183 Au kozs 725 8 15 17 20 13 14 21 35 32 41 35 44 46 52 37 101 43 36 42 27 33 9 4 1
FINA
L DR
AF
T
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 16-16
TABLE 16-5 SUMMARY MINE SCHEDULE VM Holding S.A. – Aripuanã Zinc Project
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-1
17 RECOVERY METHODS The description of the processing plant is largely taken from information presented in the
Votorantim Metais Technical Report (Votorantim, 2015) and the Basis of Design Report
(Worley Parsons, 2017b).
PROCESS DESCRIPTION Based on the metallurgical test program completed to date, the Aripuanã Zinc process
flowsheet has been developed by considering conventional technologies for treatment and
copper, lead, and zinc recovery as separate concentrates. Plant throughput is forecasted to
be 1.8 million tpa. A simplified process flowsheet is shown in Figure 17-1. Key elements of
the process flowsheet include primary crushing, SAB (semi-autogenous grinding (SAG)
followed by Ball milling) circuit, talc pre-flotation of Stratabound mineralization, sequential
flotation of copper, lead, and zinc, and single copper flotation for Stringer mineralization. A
description of the key processing plant unit operations is described below.
COMMINUTION The crushing circuit will consist of one stage. Production will be trucked from the underground
mine to the Run-of-Mine (ROM) stockpile, close the plant crushing area. Production will be
directly discharged into a hopper or held temporarily in two stockpiles (each approximately
11,000 m3 in size) based on mineralization type and grade and recovered later by wheel loader.
Under the loading hopper, a fixed grizzly scalper will be installed with an aperture of 600 mm.
Oversize material from the grizzly scalper will be broken down by a rock breaker and fed again
to the hopper.
ROM/Stockpile SAB Milling Talc FlotationPrimary
Crushing
Lead Flotation Zinc FlotationCopper
FlotationThickening andrejects filtration
LeadConcentrate
Filtration
ZincConcentrate
Filtration
CopperConcentrate
Filtration
Concentrate storage and transportation
Dry stackingBackfill
Float
Float Float Float
July 2017 Source: 5Karmin Exploration Inc., 201 .
Simplified Process Flow Sheet
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 17-1
17-2
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-3
Production will be extracted from the hopper at a nominal rate of 182.6 tonnes per hour (tph)
by an apron feeder to feed a 150 mm aperture vibratory scalper. Oversize material from the
vibratory scalper will feed a jaw crusher. Crushed product below 150 mm in size will be
transferred by a belt conveyor to an elongated silo for homogenization. Both Stratabound and
Stringer mineralization will be recovered from below the silo using belt feeders at a nominal
rate of 152.2 tph (dry basis) to feed the SAG mill feeding belt conveyor.
A trommel at the SAG mill will separate coarse material for recirculation as SAG mill feed. To
maintain the ideal chemistry and slurry density in the SAG circuit, the addition of recovered
water without chemical reagents is controlled. Undersize trommel material is discharged into
a pump box and the slurry will feed a set of hydrocyclones. Hydrocyclone underflow material
will return to the ball mill and the hydrocyclone overflow with P80 (80% passing size) of 0.125
mm (Stringer) and 0.075 mm (Stratabound) will be directed to copper flotation (Stringer) or to
talc flotation (Stratabound). An online particle size analyzer will be installed to control partition
and grinding of the hydrocyclone overflow stream. The ball mill discharge is combined with
the trommel underflow and recirculated as feed to the hydrocyclones.
FLOTATION Flotation will be conducted sequentially, i.e., the production from the comminution circuit will
pass through four independent circuits in sequence. The first flotation circuit is talc/light
mineral flotation (e.g., minerals containing magnesium) to remove naturally hydrophobic
minerals and to prevent them from contaminating the sulphide concentrates. Due the high
content of light minerals in Stratabound mineralization, these minerals must be removed before
sulphide flotation. Only Stratabound mineralization will be treated via talc flotation. Talc
removal is not generally required for Stringer mineralization due to their low talc content and
any talc present can be depressed by using CMC (carboxymethyl cellulose). The flotation and
recovery of copper, lead, and zinc follow talc flotation.
Hydrocyclone overflow slurry will directly feed the rougher talc flotation cells. Reagents added
for talc flotation include MIBC (methyl isobutyl carbinol) as a frother and SMBS (sodium
metabisulphite) as a depressor. The rougher talc flotation concentrate produced will be
pumped to tailings filtration, dewatered, and disposed. The rougher talc flotation tailings
(containing copper, lead, and zinc minerals) will proceed to the copper flotation circuit.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-4
Prior to copper rougher flotation, rougher talc flotation tailings (Stratabound) or hydrocyclone
overflow (Stringer) will be conditioned in a tank using the following reagents:
• Stratabound: AERO 3894 or A3894 (dialkyl thionocarbamate collector for copper), zinc sulphate (depressor), SMBS (depressor), and CMC (talc depressor)
• Stringer: A3894 (collector), MIBC (frother), and CMC (talc depressor)
Prior to conditioning and cleaner flotation, copper rougher flotation concentrate will be
reground to a P80 of 30 µm (Stratabound) or 45 µm (Stringer), to increase sulphide liberation
and to promote higher cleaner stage recovery. The product from the copper cleaner flotation
circuit is the final copper concentrate. Copper rougher flotation tailings will be pumped to feed
the lead flotation circuit (Stratabound) or in the case of Stringer mineralization, delivered to
tailings filtration.
The lead flotation circuit is similar to the copper flotation circuit, but the quantity of flotation
cells and the types of reagents used are different. Lead and zinc flotation are only performed
for Stratabound mineralization. The reagents used for lead flotation include:
• AEROPHINE 3418A (dialkyl dithiophosphinate collector for lead)
• Zinc sulphate (depressor)
• SMBS (depressor)
• Lime (pH regulator)
• CMC (talc depressor)
Prior to lead rougher flotation, the feed slurry is conditioned with these reagents in a tank. The
lead circuit consists of rougher flotation, rougher concentrate regrinding, and cleaner flotation.
The product from the lead cleaner flotation circuit is the final lead concentrate. The Lead
rougher flotation tailings will be pumped to feed the zinc flotation circuit.
The zinc flotation circuit is similar to the copper and lead flotation circuits, but the quantity of
flotation cells and the types of reagents used are different. The reagents used for zinc flotation
include:
• AERO 208 or A208 (dialkyl dithiophosphate collector for zinc)
• Copper sulphate (depressor)
• Lime (pH regulator)
• CMC (talc depressor)
• MIBC/IF50 (frothers)
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-5
Prior to zinc rougher flotation, the feed slurry is conditioned with these reagents in a tank. The
zinc circuit consists of rougher flotation, rougher concentrate regrinding, and cleaner flotation.
The product from the zinc cleaner flotation circuit is the final zinc concentrate. Zinc rougher
flotation tailings will be pumped to tailings filtration, dewatered, and disposed.
THICKENING AND FILTRATION Thickening and filtration will be performed on flotation concentrates and tailings. Three
concentrates (copper, lead, and zinc) will be produced and will require separate thickening and
filtration. Tailings generated from flotation will consist of talc concentrate, copper flotation
tailings (Stringer) and zinc flotation tailings (Stratabound).
Each concentrate slurry (estimated solids percentage will range from 20% to 25%), will be
pumped to a storage tank feeding two press filters, which will reduce the moisture to
approximately 10%. The filtered copper and zinc concentrates will fall by gravity onto belt
conveyors that will deliver the material to segregated covered storage areas. The copper and
zinc concentrates will be reclaimed by wheel loader for transport by truck. After filtration, the
lead concentrates will be bagged in one metric tonne bags. All filtrates will be recovered for
use in flotation.
Copper flotation tailings (Stringer) and zinc flotation tailings (Stratabound) will be classified
using hydrocyclones to separate the tailings into a fine fraction (overflow stream) and a coarse
fraction (underflow stream). The hydrocyclone overflow will be diverted to a 15 m diameter
thickener for dewatering, prior to combination with the talc concentrate and filtration by press
filter. A flocculant (BASF Magnafloc 10) will be added to the thickener to increase the solids
sedimentation rate. The hydrocyclone underflow will be filtered by vacuum belt filtration to
approximately 12% to 15%, transported by conveyor or truck, and disposed of in the dry tailings
dump or re-slurried with the addition of cement and pumped as material for mine backfill
(optional). The filtrates from the press and belt filter will be pumped to a recovered water pond
and reclaimed for return to the process.
RECOVERED AND MAKE-UP WATER SYSTEMS The water system is designed to maximize water recovery and recirculation. Water from
tailings thickener overflow and tailings filtration will be pumped to a recovered water pond with
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-6
a two-day retention capacity. After treatment with hydrogen peroxide, the water is pumped to
a 600 m3 recovered water tank, which will receive make-up water as required.
Water collected from concentrate filtration will be segregated and recirculated for use in the
respective flotation circuit.
Make-up water will be collected from a storage pond close to the facilities and will be pumped
to a 400 m3 make-up water tank. This water will be used as make-up for recovered water and
for specific uses including feed for the Water Treatment Station (WTS), pump sealing, fire
suppression, vacuum pump sealing, reagent preparation, potable water, and feed to various
points in the plant circuit.
REAGENT PREPARATION AERO 3894 This collector is supplied as liquid product in 200 L drums. The solution from the drums will
be transferred to a storage tank and distributed without dilution in copper flotation.
AEROPHINE 3418A AND AERO 208 The collectors will be supplied as liquid products in 200 L drums and will have identical
preparation systems. Solutions will be transferred to dosage tanks, prepared in solubilization
tanks to 10% by weight, and transferred to storage tanks. The collector will be pumped and
delivered at required dosage rates in several flotation stages for the respective flotation
circuits.
SODIUM METABISULPHITE This reagent will be supplied in 850 kg bags and delivered to a storage hopper. A screw
feeder-doser will transfer the material from the storage hopper to an agitator tank, where SMBS
will be dissolved in water to reach a concentration of 10%. The solution will be transferred to
a storage tank and pumped at required dosages to talc, copper, and lead flotation.
COPPER SULPHATE Copper sulphate will be supplied in bags and delivered to a storage hopper. A screw feeder-
doser will transfer the material from the storage hopper to an agitator tank, where the copper
sulphate will be dissolved in water to reach a concentration of 10%. The solution will be
transferred to a storage tank and pumped at required dosages to zinc flotation.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-7
ZINC SULPHATE Zinc sulphate will be supplied in one metric tonne bags and delivered to a storage hopper. A
screw feeder-doser will transfer the material from the storage hopper to an agitator tank, where
the copper sulphate will be dissolved in water to reach a concentration of 10%. The solution
will be transferred to a storage tank and pumped at required dosages to copper and lead
flotation.
MIBC AND IF50 Both MIBC and IF50 will be supplied in 200 L drums or 1,000 L containers in liquid form. The
frothing agents will be transferred by pump to respective storage and distribution tanks. The
frother will be added in separate lines to various flotation stages. MIBC will be added to
maintain froth stability as required in all flotation stages, while IF50 will only be added in zinc
flotation.
CMC CMC will be supplied in one metric tonne bags and delivered to a storage hopper. A screw
feeder-doser will transfer the material from the storage hopper to an agitator tank, where the
CMC will be dissolved in water to reach a concentration of 10%. The solution will be
transferred to a storage tank and pumped at required dosages to copper, lead, and zinc
flotation.
HYDRATED LIME Hydrated lime will be supplied in bulk by truck and pneumatically transported to storage silos.
All dust generated during material transfer will be collected by a de-dusting system comprised
of exhaust fans and bag filters. Lime will be transferred using a rotating valve coupled with a
screw feeder-doser to a covered mixing tank and combined with water to prepare a slurry
containing 10% to 15% solids. Lime slurry will be pumped to various process stages and the
reagent will be added at required dosages to control circuit pH.
CEMENT Cement will be supplied in bulk by truck and pneumatically transferred to storage silos. All
dust generated during material transfer will be collected by a de-dusting system comprised of
exhaust fans and bag filters. Cement will be transferred using a rotating valve coupled with a
screw feeder-doser to a backfill re-slurrying tank and delivered to an agitated slurry mix tank.
Cement slurry will be pumped to the mine via a pipeline along the access road from the plant
to the mine.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-8
FLOCCULANT Flocculant will be delivered in 25 kg sealed bags and transferred to a storage hopper. Material
will be transferred from the storage hopper by screw feeder to an agitated tank and a 1%
solution will be prepared. The prepared solution will be pumped to a storage tank and
distributed to the thickener.
COMPRESSED AIR SYSTEMS A dedicated compressed air system will be provided for the press filters for each type of
concentrate. One or more compressors, with a stand-by unit, will be available for each filtration
system. These compressors will be screw type, air cooled, oil-free, and at a pressure of 7
kg/cm2.
An exclusive small-size compressor will be installed, without a stand-by unit, to generate dry,
oil-free air for the laboratory.
Screw compressors will be installed, with one stand-by unit, to generate dry oil-free air for the
beneficiation plant and workshop service and instrumentation air.
Dedicated blowers will be installed, with one stand-by unit, to generate low pressure, oil-free
air (approximately 0.4 kg/cm2) for the flotation stage (tank cells).
DUST SUPPRESSION SYSTEM The dust suppression system for primary crushing and the homogenization silo will consist of
a central unit with pumping and filtration systems, as well as piping and spray nozzles.
DRAINAGE A drainage system has been devised throughout the operational area, which includes:
• Process drainage – restricted to process facility buildings of operational units. The aim is to contain leakage and overflows that may occur during the development of activities and process. The effluent collected returns to the production process itself.
• Industrial drainage – restricted to access areas within the industrial unit and entrance gate areas, which may be reached by leakage from piping and its supporting structures, cargo transportation, etc. This drainage must be connected to the emergency drainage and/or effluent treatment station. A water, oil, and grease separation system will be installed in the workshop and in areas with industrial effluents.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 17-9
• Pluvial drainage – aimed at collecting rainwater in areas without risk of contamination, which can be disposed of in the hydrographic network without treatment.
• Emergency drainage – aimed at controlling emergency situations related to liquid effluents and industrial drainage and installed in an appropriate location so as to prevent pollution of the local drainage network.
EFFLUENT TREATMENT STATION (ETS) Compact effluent treatment system (or Compact ETS) is a modular system for biological
treatment of wastewater (sewage). The water treatment system includes a pretreatment stage
with grid, sandbox, grease box, septic tank, and screen or flotation. In case the system is
aerobic, there is typically an aeration/digestion chamber. A Compact ETS based on aerobic
reactors requires oxygen supply to allow for the development of aerobic organisms (activated
sludge) and includes decantation. Water can be disinfected by chlorination, ozonization or UV
radiation, and reused or discharged to the environment.
The treatment stages are as follows:
• Effluent intake through an inlet diffuser to avoid turbulence of any material already deposited.
• Decantation and segregation of material in the septic tank.
• Effluent flow out through an outlet prefilter filled with number 3 gravel.
• A passage and inspection box between the septic tank and the biological septo-diffuser filters to facilitate distribution.
• Effluent treatment through anaerobic filtration.
• Treated effluent may be discharged, collected and taken to a receiving body, or reused for other industrial purposes.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 18-1
18 PROJECT INFRASTRUCTURE The overall waste management strategy for the Aripuanã Zinc Project is largely taken from
information presented in a Waste Management Strategy Report (Worley Parsons, 2017c) and
the Basis of Design Report (Worley Parsons, 2017b). The current waste management strategy
includes the following aspects:
• Surface water management to minimize water entering the tailings area.
• Adoption of dry stack (filtered) tailings disposal on surface and tailings disposal as cemented paste backfill underground.
• Site selection for the Tailings Management Facility (TMF) sites.
• Minimizing the size and space required for the fresh water pond and thus, providing more space for adjacent TMF sites. A portion of the process plant water demand will be supplied from mine dewatering, which will be supplemented by pumping from an aquifer in the vicinity of the mine site.
• Utilization of non-acid forming mine waste rock to provide supplemental perimeter containment of the tailings.
WASTE PRODUCTION
TAILINGS PRODUCTION Up to 4,750 tpd of tailings solids will be generated at full plant production and approximately
17 million tonnes of tailings will require secure disposal over a period of ten years. In
accordance with a regulatory commitment, a minimum of 50% of the tailings must be disposed
of in underground mine workings and plans for tailings disposal as cemented paste backfill has
been considered. The remainder of the tailings (approximately 8.5 million tonnes of solids) will
be stored on surface in accordance with the filtered dry stack method of disposal. If properly
filtered, tailings can be spread and compacted in lifts similar to typical earth embankment
construction. Preliminary design and management of the dry stack facilities, or TMF sites,
have been considered.
TAILINGS PROPERTIES The metallurgical properties of the mineralization and the grind size during crushing and the
concentration of talc will significantly impact the physical properties of tailings. Talc content is
expected to be in the range of 5% to 10% of the tailings by weight.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 18-2
A laboratory test program has recently been completed by RCS (Rheological Consulting
Services) of the University of Melbourne in Victoria, Australia to determine the effect of grind
size (P80 of 150 µm vs. P80 of minus 75 µm) and talc content on rheological and geotechnical
properties of the tailings. The test data is currently under review.
TAILINGS MANAGEMENT FACILITY DESIGN Twelve sites were considered by VMH for above ground tailings deposition in a trade-off study.
The site layout for Option 10A is currently under consideration and is shown in Figure 18-1
and in greater detail in Appendix B of the Waste Management Strategy Report. The process
plant site would be centrally located with the Arex deposit to the north, the Ambrex deposit to
the east, and four TMF sites to the west and south. The water supply dam is located at the
south end of the lease area. Topsoil, excess waste rock, and waste soil will be stockpiled to
the southwest of the water supply reservoir.
A preliminary conceptual design of the TMF is shown in Figure 18-2 and the following aspects
have been considered:
• Perimeter containment to enhance stability of the TMF using waste rock from the mine.
• Placement and management of potentially saturated tailings in internal cells during the wet season.
• Surface water management at each TMF site.
• Any requirements for a liner and seepage collection system at the base of the tailings deposit.
• The ease of reclaiming and closing the facility and the end of mining.
An acid base accounting (ABA) test program is currently in progress for both the tailings and
waste rock and the conceptual design of the TMF sites should be reviewed based on the ABA
test results. The next stage of design should also assess slope stability and geotechnical
parameters based on current laboratory test results.
PAIOL DE EXPLOSIVOS
29
0 2 05
Metres
5 00 750 10 00
Ju 2017ly Source: Votorantim Metais, 2017.
General Site Plan and ProposedTMF Sites for Option 10A
Aripuanã Zinc ProjectState of Mato Grosso, Brazil
VM Holding S.A.
Figure 18-1
18-3
ww
w.rp
acan
.co
m
0 100 400
Metres
200 300
TMF Conceptual Design
July 2017 Source: Votorantim Metais, 2017.
Aripuanã Zinc ProjectMato Grosso State, Brazil
VM Holding S.A.
Figure 18-2
18-4
www.rpacan.com
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 18-5
POWER SUPPLY Electrical power is proposed to be provided to the Aripuanã Project by the Dardenelos
Hydroelectric Plant, connected to the National Energy System, and located near the Project.
The Project requires the installation of a 69 kV transmission line and associated infrastructure,
such as substations and switchyards, to connect to the Dardenelos transmission system.
RPA understands that the authorization from the Ministry of Mines and Energy for the
connection has not yet been obtained, however, it is not expected to be a significant obstacle
to advancing the Project.
WATER SUPPLY The Project water balance requires a top-up of fresh water supply of approximately 150 m3/h.
VMH has undertaken a water supply engineering study based on the construction of a water
dam and creation of a fresh water lake in a valley adjacent to the Project site (see Figure 18-
1).
VMH has obtained authorization from the regional authority to construct the dam and to draw
up to 378 m3/h of fresh water from the dam to supply the Project.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 19-1
19 MARKET STUDIES AND CONTRACTS MARKETS The principal commodities at the Project are freely traded, at prices and terms that are widely
known, so that prospects for sale of any production are virtually assured. RPA reviewed the
concentrate terms provided by VMH and found them to be consistent with current industry
norms.
Metal prices are based on long-term consensus forecasts by independent banks and financial
institutions. A year-by-year price curve was used to cash flow modelling.
CONTRACTS No contracts for operations have been negotiated yet.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-1
20 ENVIRONMENTAL STUDIES, PERMITTING, AND SOCIAL OR COMMUNITY IMPACT ENVIRONMENTAL AND SOCIAL SETTING The surface components of the Aripuanã Zinc Project are located around 25 km northwest of
the municipality of Aripuanã, in the northwestern corner of the Mato Grosso State, Brazil,
approximately 1,200 km northwest from Brasília, the federal capital.
The Aripuanã Zinc property contains 22 contiguous EPs, mining concessions, and EPs in
application, covering an area of approximately 740 m². The EPs are owned by Dardanelos, a
joint venture between Karmin (30%) and VMH (70%), with VMH acting as the operator.
The Project area has two creeks, Arrainha Creek and Maranhã Creek, both of which are
tributaries of Guaribal Creek, which is a tributary of the Aripuanã River, which drains part of
the extreme northwest of the state of Mato Grosso and belongs to the Amazon River basin.
The Project area is located within an area called Depressão Amazonica Meridional (RADAM
Brasil 1982) and the Depressão Norte do Mato Grosso (Seplan 1999). This depression
includes the drainage network of the Aripuanã River and Tenente Marques River. The area is
hilly with elevations from 129 MASL to 361 MASL and a general northwest-southeast direction.
The area does not have a climate station. According to the Köppen-Geiger climate
classification, the climate in Aripuanã is AM – a Monsoon tropical, megathermal with
temperatures in the coolest months above 18°C, with no winter season. Annual precipitation
is above 2,000 mm, concentrated in the warmer months, and averages below 600 mm in the
driest months.
In the Aripuanã River basin regimen follows the precipitation pattern, with the wet season
spanning from November until May. Low flows start in June and end in October. The minimum
flows are observed in September and October.
Regarding the surface water quality, due to the geological conditions in the region, metals
which presented concentrations above the detection limit are: aluminum, dissolved iron,
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-2
manganese, barium, and zinc. These are part of the rock composition in the area and do not
indicate contamination or pollution.
In August 2008, the parameters which did not meet the limits established by the Ministry of
Environment (CONAMA) Resolution No. 357/05 for Class II water bodies were: phosphorus
(all sampling locations, except one), dissolved iron (two locations) and manganese (one
location). In April, the parameters were: turbidity (one location), dissolved oxygen (one
location), phosphorus (all), dissolved iron (all), dissolved aluminum (two locations),
manganese (five locations), thermotolerant coliforms (all, except two) and Escherichia coli
(three locations). In December, the parameters were: colour (five locations), BOD (one
location), total phosphorus (four locations), dissolved iron (one location), manganese (two
locations), and E. coli and thermotolerant coliforms (four locations).
Descriptions of vegetation in the area, the terrestrial fauna, or aquatic fauna baseline
campaigns are being finalized and will be included in an EIA to be filed on 7 August.
There are two conservation areas described in the municipality located 100 km to 200 km away
from the Project: Estação Ecológica Rio Flor do Prado, with an area of 9 ha, and Reserva
Extrativista Guariba Roosevelt, with an area of approximately 165 ha.
The Project area is located on the left banks of Rio Guariba and right banks of the Roosevelt
River. This area is dedicated to farming of Rubber Trees (Hevea Brasiliensis), Nuts
(Bertholletia excelsa), and Copaíba Oil (Copaífera landsdorfii).
ENVIRONMENTAL STUDIES The environmental licensing process for the Aripuanã Zinc Project started in 2008 following
the Terms of Reference (ToR) (Ofício nº 20084/CM/SUIMIS/2008) issued by Mato Grosso
environmental agency (SEMA/MT). For strategic reasons, the process was put on hold and
the field activities performed in 2008 were consolidated into a document in the format of a
“Diagnosis of an EIA – Environmental Impact Assessment of the Project” (EIA). In 2012, a
new ToR was requested (Ofício nº 85522/CM/SUIMIS/2012), and many of the studies
performed as a result were consolidated into a comprehensive EIA. The EIA was completed
in 2012, however, was not filed with the authorities, due to low commodity prices at that time.
In 2014, with zinc prices increasing, the EIA was filed. Taking into account further exploration
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-3
on the property, increased production levels were presented in 2015 with productions
increasing from 1.2 Mtpa to 1.8 Mtpa. SEMA performed many inspections and the Public
Hearing was held on August 26, 2015. During 2015 and 2016, the permitting process was
analyzed by SEMA/MT, however, due to changes in the engineering process, the analyses
were put on hold until all changes were performed. There were also updates in the biotic media
campaigns and the inclusion of the noise and vibration studies. Therefore, a new ToR was
requested (Protocolo nº 79893/2017). At the time of report writing, VMH was in the process
of finalizing an updated EIA for submittal.
RPA has been provided with the following reports regarding social and environmental areas:
• Environmental Impact Study – Estudo de Impacto Ambiental – Projeto Aripuanã/MT-Mina Subterrânea de Polimetálicos. – Mineração Dardanelo ltda; GeoMinas Geologia Mineração e Assessoria, ltda – July 2017.
• Volume I – General Information on the Project (Informações Gerais sobre o Empreendimento).
Volume II – Physiography Study (Diagnóstico do meio físico).
Volume IV –Social Studies (Meio Antrópico).
• Impact Matrix – Excel spreadsheet.
• Volume III was not available for review, as it is currently being finalized.
Project impacts (described in the Impact Matrix prepared by VMH) for construction, operations,
and closure phases are listed below. These impacts were considered during Project planning.
Each potential effect was evaluated considering their magnitude, probability, and duration.
• Air quality due to particulate material generation and combustion gases;
• Noise;
• Vibration due to the use of explosives;
• Soil structure and erosion processes
• Water bodies dredge due to sediments presence and silting;
• Interventions in the Arrainha and Maranhão Creeks due to the formation of the Dam, the waste pile and recovered water pond.
• Changes in the terrain and landscape;
• Changes in the surface water and soil quality;
• Changes in the aquifers recharge load;
• Changes in the springs load;
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-4
• Changes in groundwater flow;
• Changes in groundwater quality;
• Reduction of the open forest cover, with losses in the flora and threatened flora;
• Interventions in Permanent Preserved Areas;
• Reduction in the connectivity between native vegetation;
• Loses in the vegetation cover anthropized;
• Fauna displacement due to machines, vehicles and people movement and noise generation.
• Risk to fauna due to vehicles and hunting activities;
• Losses of fauna specimens due to vegetation suppression;
• Mammal representatives losses due to habitat loss; including endangered species;
• Lontra longicaudis (lontra) habitat loss;
• Scientific information loss regarding small mammals and herpetofauna;
• Changes in the fish populations due to changes in the water bodies flow;
• Changes in the freshwater biota due water bodies silting;
• Changes in vectors insects populations;
• Potential increase in prostitution indexes, violence and drugs consumption and social cultural conflicts due to immigrants arrival in Aripuanã Municipality;
• Potential decrease in the number of residences in Aripuanã’s urban area;
• Employment and wage generation;
• New business opportunities generation;
• Increase in taxes collection;
• Potential increase in endemic diseases due to the arrival of immigrants;
• Increase in the need of social basic service;
• Water quality changes due to backfill movement and effluent generation in the sterile deposit, waste and minerals (Acidic drainage);
• Springs suppression or changes in the flow;
• Changes in the Amphibia population due to sediments in water bodies;
• Changes in the fishes populations due to changes in the water bodies;
• Uncomfortable situations generation due to traffic in MT 208 highway;
• Tax collection increase;
• Springs recovery;
• Vegetation recovery in recovered areas;
• Work demand decrease. Work force decommissioning;
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-5
• Decrease in tax collection and consequent decrease in the money transferences to public services during the closure phase;
• Community expectations and worries.
PROJECT PERMITTING No permits, exploration or environmental, were available for review.
SOCIAL OR COMMUNITY REQUIREMENTS The municipality of Aripuanã was founded in 1943 and has a total area of approximately 25,107
km² and a population or approximately 20,600. The Project is located approximately 20 km
northwest from Aripuanã. The municipality is away from the main economical centres of the
state (i.e., Cuiaba, Sinop, and Lucas do Rio Verde). Until 1995, there were gold and diamond
artisanal mining activities in the area.
The EIA describes two indigenous villages located approximately 10 km to 12 km from the
Project: Arara do Rio Branco with an area of approximately 11 ha and Aripuanã with an area
or approximately 750 ha. The total population is 512, 74 of which live in areas outside of the
villages.
Consultation with indigenous peoples to date regarding Project impacts and mitigation have
been under the tutelage and consent of National Historical and Artistic Heritage Institute
(IPHAN) with National Indian Foundation (FUNAI).
No resettlement will be required to implement the Aripuanã Zinc Project.
Archaeological studies performed in the direct and indirect area of influence of the Project
showed no archaeological remains, however, additional studies will be performed to confirm
these findings.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-6
MINE CLOSURE REQUIREMENTS Based on the EIA, Dardanelos is preparing a Mine Closure Plan for the Aripuanã Project,
including alternatives for future use. No other information regarding the mine closure plan was
available for review.
RPA included an allowance of US$10 million at the end of the mine life for closure and
reclamation.
KEY ISSUES AND RECOMMENDATIONS FOR FUTURE WORK Based on the information reviewed and the Project knowledge obtained during this review,
RPA is of the opinion that the current EIA is compliant with Brazilian standards and regulation
needs for the current stage of the Project. As the Project is advanced, more detailed EIA
submissions will be required with regard to the following:
• Establishing existing environmental and socio-economic conditions in the Project area and the influence in the Project.
• Predicting Project effects.
• Specifying and detailing mitigation measures to prevent significant impacts.
• Detailing future monitoring and management activities of the Project.
• Continuing baseline data collection. This will also include community and stakeholder consultation and impact generated by the Project in each area.
• Testing to determine geochemistry baseline data.
• Confirming that there are no fauna or flora species of importance or any endangered or threatened species affected by the Project.
• An ecological and human health risk assessment should be carried out, with the aim of identifying if water quality, air quality, and noise combined with local uses of the areas have the potential of affecting the health of local wildlife, feedstock, and/or the local population.
• Site closure will require large amounts of soil. A detailed soil balance should be developed with the aim of ensuring that the required amounts of soils will be available to support closure activities.
• Historically, closure of mine sites has the potential to result in significant economic impacts. To avoid these impacts a detailed social management plan should be
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 20-2
developed, which includes ongoing consultation, training and planning of workers and local community members, with the aim of mitigating the economic and social effects of mine closure.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 21-1
21 CAPITAL AND OPERATING COSTS VMH has completed engineering studies on the Project, involving detailed cost estimates built
up from first principles. Costs were estimated as of Q2 2017, in Brazilian currency. RPA
reviewed the estimates and converted to US$ using an exchange rate of US$1.00 = R$3.30.
CAPITAL COSTS Capital costs were estimated using a combination of first principles, quotations, and factored
estimates. Capital costs are estimated at a +/- 20% confidence level.
The estimates are based on a two-year construction schedule.
PRE-PRODUCTION CAPITAL Pre-production capital costs totalling US$354 million are summarized in Table 21-1.
TABLE 21-1 PRE-PRODUCTION CAPITAL COST ESTIMATE VM Holdings S.A. – Aripuanã Project
Area Category Units Initial Costs
Mine Development US$ millions 23.9 Mobile Equipment US$ millions 31.4 Plant & Infrastructure Site Prep & Earthworks US$ millions 22.8 Civil & Roadwork US$ millions 24.2 Steelwork US$ millions 16.7 Electrical US$ millions 36.1 Instrumentation US$ millions 9.6 Mechanical Equipment US$ millions 75.3 Piping US$ millions 14.8 Communications US$ millions 6.0 Subtotal Direct Costs US$ millions 260.9 Indirect Costs EPCM US$ millions 18.9 Temporary Services US$ millions 10.4 Owner’s Team US$ millions 19.2 Other US$ millions 13.4 Subtotal Indirects US$ millions 69.7 Contingency US$ millions 23.6 Total Capital Cost US$ millions 354.3
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 21-2
In RPA’s opinion, the estimate can be classified as Class 4, per American Association of Cost
Engineers (AACE) guidelines, which generally corresponds to pre-feasibility studies.
Contingency comprises 7% of direct and indirect capital costs, which RPA considers to be low
for the current stage of the Project.
SUSTAINING CAPITAL Sustaining capital costs totalling US$229 million over the operating life of mine are summarized
in Table 21-2.
TABLE 21-2 SUSTAINING CAPITAL COST ESTIMATE VM Holding S.A. – Aripuanã Zinc Project
Parameter Units Sustaining Costs
Mine Equipment US$ millions 44.8 Capital Development US$ millions 139.5 Plant Equipment US$ millions 28.7 Tailings US$ millions 6.1 Closure and Remediation US$ millions 10.0 Total Capital Cost US$ millions 229.0
RPA added an allowance of US$10 million for Closure and Reclamation to the estimate
provided by VMH.
Exclusions from the capital cost estimate include, but are not limited to, the following:
• Project financing and interest charges • Working capital • Escalation during construction
OPERATING COSTS Operating costs, averaging US$64 million per year at full production, were estimated for
Mining, Processing, and General and Administration (G&A). Operating cost inputs such as
labour rates, consumables, and supplies were based on VMH operating data. A summary of
operating costs is shown in Table 21-3.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 21-3
TABLE 21-3 OPERATING COST ESTIMATE VM Holding S.A. – Aripuanã Zinc Project
Parameter Total LOM
(US$ millions) Average Year
(US$ millions / yr) LOM Unit Cost
(US$ / t) Mining 763 35.0 20.65
Processing 572 26.4 15.47
G&A 85 3.6 2.31
Total 1,420 64.0 38.43
LOM average unit costs are influenced by three higher-cost years during ramp-up to full
production and by five years of lower production at the end of the mine life.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 22-1
22 ECONOMIC ANALYSIS The economic analysis contained in this report is based, in part, on Inferred Resources, and
is preliminary in nature. Inferred Resources are considered too geologically speculative to
have mining and economic considerations applied to them and to be categorized as Mineral
Reserves. There is no certainty that economic forecasts on which this Preliminary Economic
Assessment is based will be realized.
RPA has generated a Cash Flow Projection from the LOM production schedule and capital
and operating cost estimates, and this is summarized in Table 22-1. A summary of the key
criteria is provided below.
ECONOMIC CRITERIA REVENUE
• LOM processing of 37 Mt, grading 4.06% Zn, 1.59% Pb, 0.33% Cu, 39 g/t Ag and 0.61 g/t Au
• LOM average metallurgical recovery of 82% Zn, 82% Pb, 86% Cu, 66% Ag and 82% Au
• LOM average metal payable of 84% Zn, 95% Pb, 96% Cu, 77% Ag and 87% Au
• LOM payable metal of 1,028 kt Zn, 459 kt Pb, 101 kt Cu, 23,638 koz Ag and 529 koz Au
• LOM metal prices based on forward-looking independent forecasts, averaging US$1.06/lb Zn, US$0.88/lb Pb, US$2.74/lb Cu, US$18.95/oz Ag, and US$1,278/oz Au.
• All revenues are received in US$.
• Total gross revenue of US$5,024 million.
• Total offsite treatment, transportation, and refining charges of US$1,383 million.
• Total royalties of US$192 million.
• Net revenue of US$3,449 million.
• Average unit net revenue of US$93/t processed.
• Revenue is recognized at the time of production.
COSTS
• Pre-production period: 24 months.
• Mine life: 24 years.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 22-2
• Life of Mine production plan as summarized in Section 16.
• Pre-production capital totals US$354.3 million.
• Sustaining capital over the LOM totals US$229.0 million.
• Average operating cost over the mine life is US$38.43 per tonne processed.
TAXATION AND ROYALTIES RPA has relied on a VMH taxation model for calculation of income taxes applicable to the cash
flow.
As discussed in Section 4, the Project is subject to royalties which differ for the two deposits.
In addition, a corporate income tax rate of 34% was applied to taxable income. The calculation
of taxable income takes into consideration the depreciation schedule, assuming a 10 year fixed
rate method. Over the LOM, the Project will pay US$390 million in corporate income taxes,
net of credits for working capital.
Date:INPUTS UNITS TOTAL 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044
MININGUnderground
Operating Days 350 days 8,400 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 350 Tonnes milled per day tonnes / day 765 1,639 2,581 3,912 5,090 5,139 5,132 5,162 5,199 5,187 5,206 5,070 5,147 5,126 5,182 5,161 5,187 5,177 5,191 5,206 4,437 4,664 3,738 1,451 598
Production '000 tonnes 36,953 574 903 1,369 1,781 1,798 1,796 1,807 1,819 1,815 1,822 1,774 1,802 1,794 1,814 1,806 1,815 1,812 1,817 1,822 1,553 1,632 1,308 508 209 Zn Grade % 4.06% 4.98% 3.73% 3.96% 4.03% 4.36% 3.97% 3.59% 2.31% 3.55% 2.87% 4.63% 3.95% 7.84% 6.59% 5.09% 3.61% 3.81% 3.85% 2.89% 3.34% 3.25% 3.49% 3.48% 3.24%Pb Grade % 1.59% 1.71% 1.24% 1.38% 1.70% 1.76% 1.76% 1.40% 0.81% 1.24% 1.02% 2.19% 1.69% 3.44% 3.13% 2.01% 1.36% 1.31% 1.35% 1.05% 1.14% 1.01% 1.03% 1.22% 1.12%Cu Grade % 0.33% 0.60% 0.71% 0.35% 0.26% 0.16% 0.19% 0.27% 0.49% 0.37% 0.61% 0.52% 0.35% 0.17% 0.23% 0.31% 0.27% 0.26% 0.41% 0.41% 0.27% 0.27% 0.10% 0.05% 0.02%Ag Grade g/t 39 53 44 38 46 50 47 39 23 32 29 50 39 76 66 53 36 33 29 27 26 20 22 25 27Au Grade g/t 0.61 0.42 0.52 0.38 0.35 0.22 0.25 0.36 0.60 0.55 0.69 0.62 0.75 0.79 0.89 0.64 1.73 0.74 0.62 0.72 0.53 0.62 0.20 0.22 0.21
PROCESSING
Mill Feed '000 tonnes 36,953 574 903 1,369 1,781 1,798 1,796 1,807 1,819 1,815 1,822 1,774 1,802 1,794 1,814 1,806 1,815 1,812 1,817 1,822 1,553 1,632 1,308 508 209Zn Grade % 4.06% 4.98% 3.73% 3.96% 4.03% 4.36% 3.97% 3.59% 2.31% 3.55% 2.87% 4.63% 3.95% 7.84% 6.59% 5.09% 3.61% 3.81% 3.85% 2.89% 3.34% 3.25% 3.49% 3.48% 3.24%Pb Grade % 1.59% 1.71% 1.24% 1.38% 1.70% 1.76% 1.76% 1.40% 0.81% 1.24% 1.02% 2.19% 1.69% 3.44% 3.13% 2.01% 1.36% 1.31% 1.35% 1.05% 1.14% 1.01% 1.03% 1.22% 1.12%Cu Grade % 0.33% 0.60% 0.71% 0.35% 0.26% 0.16% 0.19% 0.27% 0.49% 0.37% 0.61% 0.52% 0.35% 0.17% 0.23% 0.31% 0.27% 0.26% 0.41% 0.41% 0.27% 0.27% 0.10% 0.05% 0.02%Ag Grade g/t 39 53 44 38 46 50 47 39 23 32 29 50 39 76 66 53 36 33 29 27 26 20 22 25 27Au Grade g/t 0.61 0.42 0.52 0.38 0.35 0.22 0.25 0.36 0.60 0.55 0.69 0.62 0.75 0.79 0.89 0.64 1.73 0.74 0.62 0.72 0.53 0.62 0.20 0.22 0.21 Contained Zn '000 tonnes 1,500 29 34 54 72 78 71 65 42 64 52 82 71 141 120 92 66 69 70 53 52 53 46 18 7Contained Pb '000 tonnes 587 10 11 19 30 32 32 25 15 23 19 39 30 62 57 36 25 24 24 19 18 17 13 6 2Contained Cu '000 tonnes 120 3 6 5 5 3 3 5 9 7 11 9 6 3 4 6 5 5 8 7 4 4 1 0 0Contained Ag koz 46,852 971 1,285 1,685 2,628 2,865 2,727 2,243 1,328 1,840 1,723 2,847 2,273 4,386 3,836 3,060 2,077 1,924 1,691 1,601 1,294 1,060 917 406 183 Contained Au koz 725 8 15 17 20 13 14 21 35 32 41 35 44 46 52 37 101 43 36 42 27 33 9 4 1
Net RecoveryZn 82% 82% 81% 82% 82% 82% 82% 82% 81% 82% 81% 82% 82% 82% 82% 82% 82% 82% 81% 82% 82% 82% 82% 82% 82%Pb 82% 82% 82% 83% 83% 83% 82% 82% 80% 81% 82% 83% 82% 83% 83% 83% 82% 82% 82% 82% 82% 83% 83% 83% 83%Cu 86% 79% 83% 81% 86% 83% 86% 86% 92% 89% 93% 93% 90% 85% 90% 83% 80% 87% 83% 87% 85% 84% 81% 79% 68%Ag 66% 87% 81% 71% 62% 62% 62% 64% 66% 64% 66% 62% 64% 61% 61% 65% 68% 68% 79% 72% 67% 64% 60% 60% 60%Au 82% 78% 83% 81% 80% 73% 75% 81% 89% 83% 87% 82% 86% 79% 83% 81% 89% 86% 83% 87% 82% 83% 71% 69% 64%
Concentrate ProductionZn Concentrate '000 tonnes 2,499 47 55 90 120 131 119 108 69 107 87 138 119 236 201 153 109 115 115 87 87 89 77 30 11
Zn % 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49% 49%Ag g/t 61 55 65 60 75 76 80 70 53 55 57 66 61 65 66 67 62 52 41 53 47 39 42 49 58
Pb Concentrate '000 tonnes 774 13 15 25 40 42 42 34 19 29 25 51 40 82 75 48 33 31 32 25 23 22 18 8 3Pb % 62% 62% 62% 62% 63% 63% 63% 62% 62% 63% 62% 63% 62% 63% 63% 62% 62% 63% 62% 62% 62% 62% 63% 63% 63%Ag g/t 723 1,137 1,235 888 784 826 774 803 702 711 739 595 641 639 595 781 797 744 708 769 660 552 610 585 705 Au g/t 2.75 1.99 3.12 2.71 2.15 2.05 2.03 2.68 2.29 3.45 3.42 2.35 2.32 2.44 2.10 3.12 3.63 2.70 3.29 3.06 3.74 5.35 3.52 3.35 4.31
Cu Concentrate '000 tonnes 379 10 19 13 14 9 11 15 30 22 38 31 21 10 14 17 14 15 22 23 13 13 4 1 0Cu % 27.6% 27.8% 28.4% 28.5% 27.6% 27.7% 27.6% 27.8% 27.4% 27.4% 27.4% 27.3% 27.5% 27.2% 27.2% 28.3% 28.3% 27.3% 27.7% 27.5% 27.4% 27.8% 27.2% 27.0% 26.8%Ag g/t 636 903 576 704 722 1,244 972 676 340 453 330 486 606 1,601 1,024 809 774 784 621 510 556 413 826 1,828 5,605 Au g/t 44.29 16.65 18.60 26.02 28.26 23.54 23.35 28.70 30.51 33.92 26.80 25.20 52.02 94.14 84.58 47.57 192.25 71.57 36.75 45.83 45.53 54.53 33.05 70.65 151.17
Concentrate Moisture 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 10%
Total RecoveredZn '000 tonnes 1,228 23 27 44 59 64 58 53 34 53 43 67 58 116 98 75 54 57 57 43 43 44 38 15 6Pb '000 tonnes 483 8 9 16 25 26 26 21 12 18 15 32 25 51 47 30 20 19 20 16 15 14 11 5 2Cu '000 tonnes 105 3 5 4 4 2 3 4 8 6 10 9 6 3 4 5 4 4 6 6 4 4 1 0 0Ag koz 30,643 840 1,044 1,197 1,631 1,780 1,679 1,434 879 1,171 1,144 1,760 1,462 2,677 2,322 1,975 1,402 1,313 1,335 1,156 864 675 552 243 109 Au koz 608 6 13 13 16 9 11 17 31 27 35 29 38 36 43 30 91 37 30 37 22 27 6 3 1
REVENUEMetal Prices
Zn 2,338 US$/lb 1.06$ 1.09$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ 1.06$ Pb 1,933 US$/lb 0.88$ 0.89$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ 0.88$ Cu 6,042 US$/lb 2.74$ 2.73$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ 2.74$ Ag 18.91 US$/oz 18.95$ 19.31$ 19.45$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ 18.91$ Au 1,276 US$/oz 1,278$ 1,294$ 1,297$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$ 1,276$
Exchange Rate $3.30 R$/US$ $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30 $3.30
Concentrate Payable %Zn % 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84% 84%Pb % 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95% 95%Cu % 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96% 96%Ag % 77% 84% 82% 79% 76% 76% 76% 77% 78% 77% 78% 76% 77% 75% 74% 77% 78% 79% 81% 80% 77% 76% 74% 74% 74%Au % 87% 85% 87% 86% 84% 79% 80% 85% 88% 88% 89% 86% 87% 85% 86% 86% 89% 88% 88% 88% 88% 89% 84% 83% 84%
Payable MetalZn '000 tonnes 1,028 19.5 22.9 37.2 49.3 53.9 48.8 44.5 28.4 44.0 35.7 56.4 48.8 96.9 82.3 63.1 45.0 47.3 47.7 36.0 35.7 36.5 31.5 12.2 4.7Pb '000 tonnes 459 7.6 8.7 14.9 23.7 24.9 24.8 19.8 11.3 17.4 14.6 30.4 23.7 48.6 44.5 28.5 19.2 18.5 18.9 14.9 13.9 12.9 10.6 4.9 1.8Cu '000 tonnes 101 2.6 5.1 3.7 3.8 2.3 2.8 4.0 8.0 5.7 9.9 8.2 5.5 2.6 3.7 4.5 3.8 3.9 6.0 6.2 3.4 3.6 1.0 0.2 0.0Ag koz 23,638 702 859 947 1,237 1,356 1,272 1,102 689 897 892 1,330 1,125 1,999 1,724 1,518 1,098 1,033 1,085 925 669 510 409 179 81Au koz 529 5.1 11.0 11.5 13.3 7.3 8.6 14.3 27.5 23.5 31.2 25.1 33.0 30.6 37.1 26.2 80.8 32.8 26.3 32.7 19.3 24.1 5.1 2.1 0.8
Gross RevenueZn US$ '000 $2,405,464 $47,047 $53,536 $87,085 $115,179 $126,085 $114,170 $103,971 $66,376 $102,791 $83,403 $131,926 $114,129 $226,655 $192,528 $147,436 $105,153 $110,618 $111,510 $84,245 $83,394 $85,259 $73,559 $28,499 $10,911Pb US$ '000 $887,469 $14,962 $16,738 $28,731 $45,839 $48,042 $47,988 $38,346 $21,757 $33,572 $28,126 $58,838 $45,861 $93,858 $86,104 $55,020 $37,119 $35,792 $36,583 $28,860 $26,878 $25,017 $20,431 $9,440 $3,569Cu US$ '000 $607,550 $15,729 $30,642 $22,237 $23,222 $14,004 $17,213 $24,208 $48,119 $34,401 $60,013 $49,592 $33,170 $15,531 $22,249 $27,385 $23,040 $23,729 $36,131 $37,345 $20,778 $21,565 $5,972 $1,121 $153Ag US$ '000 $447,746 $13,561 $16,706 $17,917 $23,390 $25,642 $24,055 $20,838 $13,027 $16,953 $16,875 $25,159 $21,270 $37,794 $32,604 $28,714 $20,763 $19,531 $20,516 $17,492 $12,651 $9,651 $7,725 $3,378 $1,534Au US$ '000 $675,626 $6,629 $14,281 $14,676 $16,991 $9,360 $11,026 $18,200 $35,112 $29,991 $39,802 $31,980 $42,068 $38,995 $47,369 $33,446 $103,134 $41,835 $33,500 $41,732 $24,623 $30,796 $6,451 $2,655 $971
Total Gross Revenue US$ '000 $5,023,854 $97,928 $131,903 $170,646 $224,622 $223,132 $214,452 $205,562 $184,391 $217,708 $228,219 $297,495 $256,498 $412,831 $380,854 $292,002 $289,211 $231,504 $238,241 $209,674 $168,325 $172,289 $114,137 $45,094 $17,138
Concentrate ChargesTotal Charges US$ '000 $1,382,981 $26,799 $33,614 $48,931 $66,251 $69,362 $65,276 $59,350 $44,008 $59,427 $55,467 $82,698 $67,780 $124,719 $110,004 $82,892 $59,547 $61,189 $64,183 $51,219 $46,493 $46,503 $37,081 $14,639 $5,551
Net Smelter Return US$ '000 $3,640,873 $71,130 $98,289 $121,715 $158,370 $153,770 $149,175 $146,212 $140,383 $158,282 $172,752 $214,796 $188,719 $288,113 $270,850 $209,110 $229,664 $170,316 $174,058 $158,455 $121,831 $125,786 $77,057 $30,455 $11,586
Royalty NSRArex Royalties 4.90% US$ '000 $48,154 $3,476 $4,257 $3,292 $1,610 $839 $712 $676 $840 $1,063 $1,071 $655 $1,115 $1,125 $395 $3,040 $7,168 $4,196 $5,871 $4,043 $1,821 $888 $0 $0 $0Ambrex Royalties 5.40% US$ '000 $143,540 $10 $616 $2,945 $6,778 $7,379 $7,271 $7,150 $6,654 $7,376 $8,148 $10,877 $8,962 $14,318 $14,190 $7,942 $4,503 $4,573 $2,929 $4,101 $4,572 $5,814 $4,161 $1,645 $626Total Royalties US$ '000 $191,693 $3,486 $4,873 $6,237 $8,388 $8,218 $7,983 $7,826 $7,495 $8,439 $9,219 $11,532 $10,077 $15,443 $14,586 $10,982 $11,670 $8,769 $8,800 $8,144 $6,393 $6,702 $4,161 $1,645 $626
Net Revenue US$ '000 $3,449,179 $67,643 $93,416 $115,478 $149,983 $145,552 $141,192 $138,385 $132,888 $149,843 $163,533 $203,264 $178,642 $272,669 $256,265 $198,128 $217,994 $161,547 $165,258 $150,311 $115,438 $119,084 $72,896 $28,810 $10,961Unit NSR US$ / t proc $93 $118 $103 $84 $84 $81 $79 $77 $73 $83 $90 $115 $99 $152 $141 $110 $120 $89 $91 $82 $74 $73 $56 $57 $52
Net Revenue by MetalZn % 41% 42% 34% 44% 45% 51% 47% 44% 29% 40% 30% 38% 37% 49% 44% 44% 28% 40% 40% 33% 42% 42% 59% 58% 58%Pb % 17% 14% 12% 16% 20% 21% 22% 18% 11% 14% 11% 19% 16% 22% 22% 18% 11% 14% 14% 12% 15% 13% 18% 21% 21%Cu % 13% 17% 25% 15% 12% 7% 9% 13% 27% 17% 27% 18% 14% 4% 6% 10% 8% 11% 16% 19% 13% 14% 6% 3% 1%Ag % 11% 18% 16% 14% 14% 15% 15% 13% 9% 10% 9% 11% 10% 12% 11% 13% 8% 11% 11% 10% 10% 7% 9% 10% 12%Au % 18% 9% 14% 12% 11% 6% 7% 12% 25% 19% 23% 15% 22% 13% 17% 16% 45% 24% 19% 26% 20% 24% 8% 9% 8%
OPERATING COST
Mining (Underground) US$ / t proc $20.65 $35.41 $24.23 $20.77 $18.70 $18.16 $18.28 $18.18 $18.41 $18.88 $18.83 $19.00 $19.33 $19.52 $19.06 $19.22 $19.23 $19.96 $21.21 $23.50 $23.66 $19.29 $23.26 $42.44 $62.43Processing+Tailings US$ / t proc $15.47 $17.21 $16.83 $15.07 $14.99 $15.64 $14.92 $15.06 $14.28 $14.46 $13.80 $14.05 $14.08 $15.09 $14.51 $15.00 $14.93 $14.94 $14.50 $14.13 $15.27 $16.07 $23.27 $26.73 $40.96G&A US$ / t proc $2.31 $5.16 $3.97 $2.62 $2.01 $2.00 $2.00 $1.99 $1.97 $1.98 $1.97 $2.02 $1.99 $2.00 $1.98 $1.99 $1.98 $1.98 $1.98 $1.97 $2.31 $2.20 $2.74 $7.07 $17.15Total Operating Cost US$ / t proc $38.43 $57.78 $45.03 $38.46 $35.70 $35.79 $35.20 $35.23 $34.66 $35.31 $34.60 $35.07 $35.40 $36.61 $35.55 $36.21 $36.14 $36.88 $37.69 $39.60 $41.25 $37.57 $49.27 $76.24 $120.55
Mining (Underground) US$ '000 $762,941 $20,313 $21,892 $28,436 $33,315 $32,661 $32,829 $32,838 $33,491 $34,265 $34,311 $33,722 $34,833 $35,021 $34,575 $34,718 $34,919 $36,160 $38,537 $42,824 $36,750 $31,497 $30,428 $21,545 $13,059Processing US$ '000 $571,541 $9,870 $15,202 $20,635 $26,695 $28,121 $26,808 $27,218 $25,984 $26,249 $25,149 $24,927 $25,358 $27,076 $26,312 $27,102 $27,108 $27,079 $26,346 $25,750 $23,719 $26,241 $30,451 $13,572 $8,568G&A US$ '000 $85,494 $2,961 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588 $3,588Total Operating Cost US$ '000 $1,419,976 $33,144 $40,682 $52,659 $63,599 $64,370 $63,225 $63,645 $63,063 $64,102 $63,049 $62,237 $63,780 $65,685 $64,475 $65,409 $65,615 $66,828 $68,471 $72,162 $64,058 $61,327 $64,468 $38,705 $25,216
Operating Cashflow US$ '000 $2,029,204 $34,499 $52,733 $62,819 $86,384 $81,182 $77,967 $74,740 $69,824 $85,741 $100,485 $141,027 $114,862 $206,985 $191,789 $132,719 $152,378 $94,719 $96,786 $78,148 $51,381 $57,757 $8,428 -$9,895 -$14,255
TABLE 22-1 CASH FLOW SUMMARYVM Holding S.A. - Aripuana Zinc Project
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 22-3
Date:INPUTS UNITS TOTAL 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044
CAPITAL COSTDirect Cost
Mining US$ '000 55,325$ 14,204$ 24,523$ 16,597$ Plant & Infrastructure US$ '000 197,715$ 29,336$ 83,164$ 85,215$
Total Direct Cost US$ '000 253,040$ 43,541$ 107,687$ 101,812$
EPCM / Owners / Indirect Cost US$ '000 77,803$ 11,544$ 32,726$ 33,533$ Subtotal Costs US$ '000 330,843$ 55,085$ 140,413$ 135,345$
Contingency US$ '000 23,609$ 3,503$ 9,930$ 10,175$ Initial Capital Cost US$ '000 354,452$ 58,588$ 150,344$ 145,521$
Sustaining Capital US$ '000 219,037$ $5,534 $12,715 $11,975 $17,210 $8,784 $17,486 $8,446 $14,947 $9,155 $18,247 $7,004 $12,105 $7,868 $9,329 $9,506 $15,948 $6,703 $14,756 $4,803 $2,606 $1,303 $1,303 $1,303 Reclamation and closure US$ '000 10,000$ $5,000 $5,000
Total Capital Cost US$ '000 583,489$ 58,588$ 150,344$ 145,521$ 5,534$ 12,715$ 11,975$ 17,210$ 8,784$ 17,486$ 8,446$ 14,947$ 9,155$ 18,247$ 7,004$ 12,105$ 7,868$ 9,329$ 9,506$ 15,948$ 6,703$ 14,756$ 4,803$ 2,606$ 1,303$ 1,303$ 6,303$ 5,000$
CASH FLOWNet Pre-Tax Cashflow US$ '000 1,445,715$ (58,588)$ (150,344)$ (111,021)$ 47,199$ 50,104$ 74,408$ 63,972$ 69,183$ 57,254$ 61,379$ 70,794$ 91,329$ 122,780$ 107,858$ 194,879$ 183,921$ 123,391$ 142,872$ 78,771$ 90,083$ 63,393$ 46,577$ 55,151$ 7,124$ (11,198)$ (20,558)$ (5,000)$ Cumulative Pre-Tax Cashflow US$ '000 (58,588)$ (208,931)$ (319,953)$ (272,753)$ (222,649)$ (148,241)$ (84,269)$ (15,086)$ 42,168$ 103,547$ 174,341$ 265,670$ 388,450$ 496,308$ 691,188$ 875,109$ 998,499$ 1,141,371$ 1,220,143$ 1,310,226$ 1,373,619$ 1,420,196$ 1,475,346$ 1,482,471$ 1,471,273$ 1,450,715$ 1,445,715$
Taxes (net of Working Capital credit) US$ '000 389,827$ 961$ (2,096)$ (976)$ 3,380$ 6,303$ 5,376$ 4,633$ 3,273$ 8,616$ 9,774$ 23,377$ 32,118$ 76,610$ 59,411$ 35,549$ 48,969$ 23,673$ 29,699$ 20,995$ (7,334)$ 16,993$ 86$ (2,830)$ (6,733)$
After-Tax Cashflow US$ '000 1,055,888$ (58,588)$ (150,344)$ (111,983)$ 49,295$ 51,080$ 71,028$ 57,669$ 63,807$ 52,621$ 58,106$ 62,178$ 81,556$ 99,403$ 75,740$ 118,269$ 124,510$ 87,841$ 93,903$ 55,098$ 60,384$ 42,397$ 53,912$ 38,158$ 7,039$ (8,368)$ (13,825)$ (5,000)$ Cumulative After-Tax Cashflow US$ '000 (58,588)$ (208,931)$ (320,914)$ (271,619)$ (220,539)$ (149,510)$ (91,842)$ (28,034)$ 24,587$ 82,692$ 144,870$ 226,426$ 325,829$ 401,569$ 519,839$ 644,348$ 732,189$ 826,092$ 881,191$ 941,575$ 983,972$ 1,037,884$ 1,076,042$ 1,083,081$ 1,074,713$ 1,060,888$ 1,055,888$
PROJECT ECONOMICS 0.5 1.5 2.5 3.5 4.5 5.5 6.5 7.5 8.5 9.5 10.5 11.5 12.5 13.5 14.5 15.5 16.5 17.5 18.5 19.5 20.5 21.5 22.5 23.5 24.5 25.5 26.5Pre-Tax IRR % 18.98%Pre-tax NPV at 7.0% discounting 7.0% US$ '000 $461,147 (56,639)$ (135,834)$ (93,745)$ 37,247$ 36,953$ 51,287$ 41,210$ 41,651$ 32,214$ 32,275$ 34,791$ 41,947$ 52,703$ 43,268$ 73,064$ 64,444$ 40,406$ 43,725$ 22,530$ 24,080$ 15,837$ 10,875$ 12,034$ 1,453$ (2,134)$ (3,662)$ (832)$ Pre-tax NPV at 9% discounting 9.0% US$ '000 $324,172 (56,117)$ (132,113)$ (89,504)$ 34,909$ 33,998$ 46,321$ 36,536$ 36,249$ 27,522$ 27,069$ 28,643$ 33,900$ 41,812$ 33,697$ 55,857$ 48,364$ 29,768$ 31,622$ 15,995$ 16,781$ 10,834$ 7,303$ 7,933$ 940$ (1,356)$ (2,284)$ (510)$ Pre-tax NPV at 11.0% discounting 11.0% US$ '000 $220,912 (55,609)$ (128,558)$ (85,526)$ 32,757$ 31,327$ 41,913$ 32,463$ 31,628$ 23,581$ 22,775$ 23,665$ 27,504$ 33,311$ 26,363$ 42,912$ 36,486$ 22,052$ 23,004$ 11,426$ 11,772$ 7,463$ 4,940$ 5,270$ 613$ (868)$ (1,436)$ (315)$
After-Tax IRR % 16.79%After-Tax NPV at 7.0% discounting 7.0% US$ '000 $320,716 (56,639)$ (135,834)$ (94,557)$ 38,901$ 37,673$ 48,958$ 37,149$ 38,414$ 29,607$ 30,554$ 30,557$ 37,458$ 42,668$ 30,384$ 44,341$ 43,627$ 28,765$ 28,738$ 15,759$ 16,141$ 10,592$ 12,587$ 8,326$ 1,435$ (1,595)$ (2,463)$ (832)$ After-Tax NPV at 9% discounting 9.0% US$ '000 $217,170 (56,117)$ (132,113)$ (90,279)$ 36,460$ 34,660$ 44,217$ 32,936$ 33,433$ 25,295$ 25,625$ 25,157$ 30,273$ 33,851$ 23,663$ 33,899$ 32,741$ 21,191$ 20,783$ 11,188$ 11,249$ 7,246$ 8,453$ 5,489$ 929$ (1,013)$ (1,536)$ (510)$ After-tax NPV at 11.0% discounting 11.0% US$ '000 $138,694 (55,609)$ (128,558)$ (86,267)$ 34,212$ 31,937$ 40,009$ 29,265$ 29,171$ 21,673$ 21,560$ 20,785$ 24,561$ 26,969$ 18,513$ 26,043$ 24,700$ 15,699$ 15,119$ 7,992$ 7,891$ 4,991$ 5,718$ 3,646$ 606$ (649)$ (966)$ (315)$
www.rpacan.com
VM
Ho
ldin
g S
.A. – A
ripu
anã Z
inc P
roject, P
roject #2779
Tech
nical R
epo
rt NI 43-101 – Ju
ly 31, 2017 P
age 22-4
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 22-5
CASH FLOW ANALYSIS Considering the Project on a stand-alone basis, the undiscounted after-tax cash flow totals
US$1,055 million over the mine life, and simple payback occurs six years from start of
production.
The Net Present Value (NPV) at a 9% discount rate is $217 million (based on mid-period
discounting), and the Internal Rate of Return (IRR) is 16.8%.
SENSITIVITY ANALYSIS Project risks can be identified in both economic and non-economic terms. Key economic risks
were examined by running cash flow sensitivities:
• Metal price
• Head grade
• Metallurgical recovery
• Operating costs
• Capital costs
IRR sensitivity over the base case has been calculated for a variety of ranges depending on
the variable. The sensitivities are shown in Figure 22-1 and Table 22-2.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 22-6
FIGURE 22-1 SENSITIVITY ANALYSIS
TABLE 22-2 SENSITIVITY ANALYSES VM Holding S.A. – Aripuanã Zinc Project
Description Units Low Case
Mid-Low Case
Base Case
Mid-High Case
High Case
Head Grade (Zn) % Zn 3.25 3.65 4.06 4.46 4.87 Overall Recovery (Zn) % 79 80 82 83 85 Metal Prices (Zn) US$ / lb Zn 0.85 0.96 1.06 1.17 1.27 Operating Costs US$/t 31 35 38 42 46 Capital Cost US$ millions 284 319 355 390 426
Adjustment Factor
Head Grade (ZnEq) % 80 90 100 110 120 Overall Recovery % 96 98 100 102 104 Metal Prices (Zn) % 80 90 100 110 120 Operating Costs % 80 90 100 110 120 Capital Cost % 80 90 100 110 120
Post-Tax NPV @ 9%
Head Grade (ZnEq) US$ millions -114 51 217 382 547 Overall Recovery US$ millions 151 184 217 250 283 Metal Prices (Zn) US$ millions -114 51 217 382 547 Operating Costs US$ millions 315 266 217 168 119 Capital Cost US$ millions 278 247 217 186 155
($200)
($100)
$0
$100
$200
$300
$400
$500
$600
0.7 0.8 0.9 1 1.1 1.2 1.3
Afte
r-Ta
x N
PV a
t 9%
Dis
coun
t Rat
e (U
S$
mill
ions
)
Percent Change From Base Case
Head Grade
Recovery
Metal Price
Operating Cost
Capital Cost
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 22-7
Factors were applied to all metals in the various categories, however, in the table, zinc is shown
because it provides the most revenue.
The Project is most sensitive to changes in metal prices and head grade, and least sensitive
to capital costs.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 23-1
23 ADJACENT PROPERTIES RPA is not aware of any significant deposits or properties adjacent to Aripuanã.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 24-1
24 OTHER RELEVANT DATA AND INFORMATION No additional information or explanation is necessary to make this Technical Report
understandable and not misleading.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 25-1
25 INTERPRETATION AND CONCLUSIONS The Project merits further work to improve economic outcomes, including completion of an
advanced engineering study.
RPA offers the following conclusions for each area:
GEOLOGY AND MINERAL RESOURCES • The Aripuanã Zinc deposits are located within the central-southern portion of the
Amazonian Craton, in which Paleoproterozoic and Mesoproterozoic lithostratigraphic units of the Rio Negro-Juruena province (1.80 Ga to 1.55 Ga) predominate.
• The Aripuanã Zinc polymetallic deposits are typical VMS deposits associated with felsic bimodal volcanism. Three main elongate mineralized zones, Arex, Link, and Ambrex, have been defined in the central portion of the Project. A smaller, deeper zone, Babaçú, lies to the south of Ambrex.
• The drilling, sampling, sample preparation, analysis, and data verification procedures are appropriate for the estimation of Mineral Resources.
• As prepared by VMH and adopted by RPA, the Aripuanã Measured and Indicated Mineral Resources comprise 21.8 Mt at 4.8% Zn, 1.8% Pb, 0.3% Cu, 0.4 g/t Au, and 45 g/t Ag for 2.3 billion pounds of Zn, 852 million pounds of Pb, 158 million pounds of Cu, 279,000 ounces of Au, and 31 million ounces of Ag. The Aripuanã Inferred Mineral Resources comprise 24.6 Mt at 3.9% Zn, 1.5% Pb, 0.42% Cu, 0.93 g/t Au, and 38 g/t Ag for 2.1 billion pounds of Zn, 829 million pounds of Pb, 226 million pounds of Cu, 732,000 ounces of Au, and 30 million ounces of Ag.
• The Mineral Resource estimate is consistent with the CIM definitions as incorporated by reference into NI 43-101.
• Limited exploration has identified additional, possible mineralized bodies including Massaranduba, Boroca, and Mocoto to the south and Arpa to the north.
MINING • The deposits support a production rate of 1.8 Mtpa, however, several years are
required to advance ramps and development sufficiently to access the required number of workplaces.
• The large resource base provides a long mine life (24 years). There may be opportunities to be more selective in the mining of high-grade areas in the early years of the LOM, to improve capital payback.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 25-2
• Deposit geometry and geomechanical properties are amenable to bulk longhole mining methods, with some cut and fill mining in narrower areas.
• Dilution and extraction estimates appear reasonable, ranging from 5% to 12% (dilution) and 90% to 95% (extraction). There is a risk of poorer recovery and additional dilution in flat-dipping stopes (below 50°).
• Arex and Ambrex deposits are not connected until later in the mine life, making it difficult to share the mobile equipment fleet efficiently. More units may be required in the early years.
• The issues identified above can be addressed in the next stage of study.
PROCESS • The results from recent SGS GEOSOL metallurgical testing form the current basis for
engineering design of the sequential Cu/Pb/Zn flotation circuit.
• Separation of material types is necessary to improve copper recovery and to reduce costs, particularly when processing Copper Stringer material. Since Copper Stringer mineralization does not have significant zinc and lead grades, copper processing should be separate for flotation and filtration and it is expected that the lead and zinc circuits will be bypassed.
• To process Arex and Ambrex Stratabound mineralization, talc removal by flotation is required prior to sequential flotation of Cu, Pb, and Zn.
• Data for the final concentrate grades and recoveries for Arex and Ambrex mineralization in the Aripuanã LOM financial model did not rely consistently on metallurgical test data. The assumptions for the concentrate grades and recoveries for Ambrex Stringer and Ambrex Mixed materials were based on identical LOM assumed data for Arex mineralization and not on any metallurgical test results.
• The presence or absence of any deleterious elements that could impact extraction have not yet been clearly identified through metallurgical testing.
ENVIRONMENTAL CONSIDERATIONS • The EIA, currently being finalized by VMH, is compliant with Brazilian standards and
regulation needs for the current stage of the Project. As the Project is advanced, more detailed EIA submissions will be required with regard to the following: o Establishing existing environmental and socio-economic conditions in the Project
area and the influence on the Project. o Predicting Project effects. o Specifying and detailing mitigation measures to prevent any significant impacts. o Detailing future monitoring and management activities of the Project. o Continuing baseline data collection. This will also include community and
stakeholder consultation and impact generated by the Project in each area. o Testing to determine geochemistry baseline data.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 25-3
o Confirming that there are no fauna or flora species of importance or any endangered or threatened species affected by the Project.
o An ecological and human health risk assessment should be carried out, with the aim of identifying if water quality, air quality, and noise combined with local uses of the areas have the potential of affecting the health of local wildlife, feedstock, and/or the local population.
o Completing plans for site closure and reclamation.
COSTS AND ECONOMICS • Pre-production capital costs total US$355 million.
• In RPA’s opinion, the capital cost estimate can be classified as Class 4, per AACE
guidelines, which generally corresponds to pre-feasibility studies.
• Contingency comprises 7% of direct and indirect capital costs, which RPA considers to be low for the current stage of the Project.
• Operating costs average US$38.43 per tonne over the LOM, with higher unit costs at the start and end when full production is not achievable.
• Economic results are adversely affected by a relatively long ramp-up to full production. Optimization of the mine design and schedule will help to improve the Project economics.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 26-1
26 RECOMMENDATIONS RPA offers the following recommendations for each area:
GEOLOGY AND MINERAL RESOURCES • Increase the wireframe modelling cut-off grade to limit the amount of sub-economic
material not related to massive or disseminated sulphides in the stratabound zone in the wireframes.
• Substitute zeroes for unsampled intervals.
• Model correlograms to avoid fitting long second and third variogram model structures when an apparent zonal anisotropy is observed.
• Perform a visual review of the classification of all blocks with a minimum distance to the closest drill hole greater than 25 m, and consider downgrading blocks where appropriate to Inferred.
MINING • Use only Measured and Indicated Resources at the next stage of study.
• Optimizing the ramp-up to full production will help improve economic outcomes.
PROCESS • Reference the metallurgical test data for the final concentrate grades and recoveries
and report the assays of any penalty elements for Arex and Ambrex mineralization.
• Further examine any deleterious elements (e.g., potential tremolite material) that could have a significant effect on potential economic extraction.
• Carry out additional test work to develop and optimize Zn/Pb recovery circuits on Ambrex mineralization, to conduct additional mineralogical analysis, to extend the variability analysis to a full geometallurgical program using samples from different locations in the deposits, and to conduct pilot plant test work to confirm the performance of the circuit selected.
INFRASTRUCTURE • Complete a review of the ABA program test results for both the tailings and waste rock
and assess the conceptual design of the TMF sites based on the ABA test results.
• The next stage of design of the TMF should assess slope stability and geotechnical parameters based on current laboratory test results on grind size and talc content.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 26-2
ENVIRONMENTAL AND SOCIAL CONSIDERATIONS • Update the EIA in parallel with the next stage of study on the Project.
• Continue collection of baseline data.
RECOMMENDED BUDGET A 2018 budget for field work, testing, and a Feasibility Study is summarized in Table 26-1.
TABLE 26-1 2018 PROJECT ADVANCEMENT BUDGET VM Holding S.A. – Aripuanã Zinc Project
Item Units Cost
Exploration Drilling US$ millions 5.0 Metallurgical Testwork US$ millions 1.0 VMH Project Team US$ millions 3.0 Feasibility Study US$ millions 2.0 Total US$ millions 11.0
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 27-1
27 REFERENCES AMEC International (Chile) S.A., 2007: Aripuanã Property NI 43-101 Technical Report Mato
Grosso State, Brazil, prepared for Karmin Exploration Inc., filed on SEDAR/available at www.sedar.com October 31, 2007.
Azevedo Sette Advogados, 2017: Title Opinion – Projects Aripuanã and Caçapava do Sul,
Belo Horizonte, June 14, 2017. Engler, A., 2009: The Geology of South America. GEOLOGY Vol. IV, pp. 374-405. LCASSIS Consultoria em Recursos Minerais, 2017, Relatório de Validação das Amostras
Selecionadas para Teste Metalúrgico, Projecto Aripuanã – MT, prepared for Votorantim Metais (March 2017).
RPA, 2017, Technical Report on the Aripuanã Zinc Project, Mato Grosso State, Brazil,
prepared for Karmin Exploration Inc. (March 1, 2017). SGS GEOSOL, 2017, Bench Scale Metallurgical Testwork on Drill Core Samples from the
Aripuanã Project, Final Report, prepared for Votorantim Metais (February 15, 2017). Simon, A., Marinho, R., and Lacroix, P., 2007: Aripuanã Property NI43-101 Technical Report,
Mato Grosso, Brazil. A technical report prepared by AMEC Americas Limited for Karmin Exploration Inc.
Tassinari, C.C.G., Cordani, U.G., Nutman, A.P., Van Schmus, W.R., Bettencourt, J.S., and
Taylor, P.N., 2010: Geochronological systematics on basement rocks from the Rio Negro-Juruena Province (Amazonian Craton) and tectonic implications. International Geology Review, Vl. 38, Issue 2.
Votorantim Metais Ltda., 2015, Technical Report, FEL 2 Study, Location: Aripuanã, MT,
Commodity: Zn, Pb, Cu, Rev. 00, internal report. Votorantim Metais Ltda. (2016). Relatório De Recursos Minerais Projeto Aripuanã by Talita C.
de O. Ferreira and Rafael Moniz Caixeta (30 December 2016) Worley Parsons, 2017a, Projeto Aripuanã, Fase V1, Metallurgical Testwork, 7MI-0401-RL-
0200PCD0804, Rev. 1, prepared for Votorantim Metais (April 26, 2017). Worley Parsons, 2017b, Projeto Aripuanã, FEL2, Basis of Design, 7MI-0401-RL-
0000COR1021R01, Rev. 1, prepared for Votorantim Metais (January 19, 2017). Worley Parsons, 2017c, Projeto Aripuanã, Fase V1, Waste Management Strategy, Technical
Report, 7MI-0401-RL-0300PRO0801, Rev. 5, prepared for Votorantim Metais (May 16, 2017).
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 28-1
28 DATE AND SIGNATURE PAGE This report titled “Technical Report on the Preliminary Economic Assessment of the Aripuanã
Zinc Project, State of Mato Grosso, Brazil” and dated July 31, 2017 was prepared and signed
by the following authors:
(Signed and Sealed) “Jason J. Cox” Dated at Toronto, ON July 31, 2017 Jason J. Cox, P.Eng. Principal Mining Engineer (Signed and Sealed) “Sean Horan” Dated at Toronto, ON July 31, 2017 Sean Horan, P.Geo. Senior Geologist (Signed and Sealed) “Brenna J.Y. Scholey” Dated at Toronto, ON July 31, 2017 Brenna J.Y. Scholey, P.Eng. Principal Metallurgist (Signed and Sealed) “Stephan Theben” Dated at Toronto, ON July 31, 2017 Stephan Theben, Dipl.-Ing. SLR Consulting
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-1
29 CERTIFICATE OF QUALIFIED PERSON JASON J. COX I, Jason J. Cox, P.Eng., as an author of this report entitled “Technical Report on the Pre-Feasibility Study of the Aripuanã Zinc Project, State of Mato Grosso, Brazil” prepared for VM Holding S.A. and dated July 31, 2017, do hereby certify that:
1. I am a Principal Mining Engineer and Executive Vice President, Mine Engineering, with Roscoe Postle Associates Inc. of Suite 501, 55 University Ave Toronto, ON, M5J 2H7.
2. I am a graduate of the Queen’s University, Kingston, Ontario, Canada, in 1996 with a
Bachelor of Science degree in Mining Engineering.
3. I am registered as a Professional Engineer in the Province of Ontario (Reg. #90487158). I have worked as a Mining Engineer for more than 20 years since my graduation. My relevant experience for the purpose of the Technical Report is: • Review and report as a consultant on many mining operations and projects around
the world for due diligence and regulatory requirements • Feasibility Study project work on several mining projects, including five North
American mines • Operational experience as Planning Engineer and Senior Mine Engineer at three
North American mines • Contract Co-ordinator for underground construction at an American mine
4. I have read the definition of "qualified person" set out in National Instrument 43-101 (NI
43-101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101.
5. I visited the Aripuanã Zinc Project on June 2 to 5, 2017.
6. I am responsible for Sections 15, 16, 19, 21, and 22 and contributed to Sections 1, 2, 3, 18, 25, 26, and 27 of the Technical Report.
7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43-101.
8. I have had no prior involvement with the property that is the subject of the Technical Report.
9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI 43-101 and Form 43-101F1.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-2
10. At the effective date of the Technical Report, to the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 31st day of July, 2017. (Signed and Sealed) “Jason J. Cox” Jason J. Cox, P.Eng.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-3
SEAN HORAN I, Sean Horan, P.Geo., as an author of this report entitled “Technical Report on the Pre-Feasibility Study of the Aripuanã Zinc Project, State of Mato Grosso, Brazil” prepared for VM Holding S.A. and dated July 31, 2017, do hereby certify that: 1. I am Senior Geologist with Roscoe Postle Associates Inc. of Suite 501, 55 University Ave
Toronto, ON, M5J 2H7. 2. I am a graduate of Rhodes University, South Africa, in 2003 with a B.Sc. (Hons.) degree in
Environmental Studies, and in 2004 with a B.Sc. (Hons.) degree in Geology. I also have a post-graduate certificate in Geostatistics from the University of Alberta, Canada.
3. I am registered as a Professional Geologist in the Province of Ontario (Reg.#2090). I have
worked as a geologist for a total of 10 years since my graduation. My relevant experience for the purpose of the Technical Report is: • Geological consulting to the mining and exploration industry in Canada and worldwide,
including resource estimation and reporting, due diligence, geostatistical studies, QA/QC, and database management.
• Geologist responsible for all geological aspects of underground mine development, underground exploration, resource definition drilling planning, and resource estimation at a gold mine in Ontario, Canada.
• Geologist with an alluvial diamond mining and prospecting company in Angola. • Experienced user of AutoCAD, Datamine Studio 3. SQL Database Administration,
Visual Basic, Javascript (Datamine Studio 3), Century Systems (Fusion SQL drill hole database tools), Snowden Supervisor, and GSLIB.
4. I have read the definition of "qualified person" set out in National Instrument 43-101 (NI 43-
101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101.
5. I visited the Aripuanã Zinc Project on January 30 to February 3, 2017. 6. I am responsible for Sections 4 to 12 and 14 and contributed to Sections 1, 2, 3, 25, 26,
and 27 of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43-101. 8. I have had prepared a previous NI 43-101 Technical Report on the Aripuanã Zinc Project
for Karmin Exploration Inc. dated March 1, 2017 and a resource audit report for Votorantim Metais Ltda. dated May 24, 2017 on the property that is the subject of the Technical Report.
9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI
43-101 and Form 43-101F1.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-4
10. At the effective date of the Technical Report, to the best of my knowledge, information, and belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 31st day of July, 2017. (Signed and Sealed) “Sean Horan” Sean Horan, P.Geo.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-5
BRENNA J.Y. SCHOLEY I, Brenna J.Y. Scholey, P.Eng., as an author of this report entitled “Technical Report on the Pre-Feasibility Study of the Aripuanã Zinc Project, State of Mato Grosso, Brazil” prepared for VM Holding S.A. and dated July 31, 2017, do hereby certify that: 1. I am Principal Metallurgist with Roscoe Postle Associates Inc. of Suite 501, 55 University
Ave., Toronto, ON, M5J 2H7. 2. I am a graduate of The University of British Columbia in 1988 with a B.A.Sc. degree in
Metals and Materials Engineering. 3. I am registered as a Professional Engineer in the Province of Ontario (Reg. #90503137)
and British Columbia (Reg. #122080). I have worked as a metallurgist for a total of 29 years since my graduation. My relevant experience for the purpose of the Technical Report is: • Reviews and reports as a metallurgical consultant on a number of mining operations
and projects for due diligence and regulatory requirements. • Senior Metallurgist/Project Manager on numerous base metals and precious metals
studies for an international mining company. • Management and operational experience at several Canadian and U.S. milling,
smelting and refining operations treating various metals, including copper, nickel, and precious metals.
4. I have read the definition of "qualified person" set out in National Instrument 43-101 (NI 43-
101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101.
5. I did not visited the Aripuanã Zinc Project. 6. I am responsible for preparation of Sections 13 and 17 and contributed to Sections 1, 2, 3,
18, 25, 26, and 27 of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43-101. 8. I have had no prior involvement with the property that is the subject of the Technical Report. 9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI
43-101 and Form 43-101F1. 10. At the effective date of the Technical Report, to the best of my knowledge, information, and
belief, the Technical Report contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 31st day of July, 2017. (Signed and Sealed) “Brenna J.Y. Scholey” Brenna J.Y. Scholey, P.Eng.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-6
STEPHAN THEBEN I, Stephan Theben, Dipl.-Ing., as an author of this report entitled “Technical Report on the Pre-Feasibility Study of the Aripuanã Zinc Project, State of Mato Grosso, Brazil” prepared for VM Holding S.A. and dated July 31, 2017, do hereby certify that: 1. I am Mining Sector Lead and Managing Principal with SLR Consulting (Canada) Ltd. at 36
King Street East, 4th floor, Toronto, M5C1E5. 2. I am a graduate of RWTH Aachen Technical University in 1997 with a Mining Engineering
Degree. I also passed the State Exam for Mining Engineering in 2000. 3. I am registered as a Professional Member with the Society for Mining, Metallurgy and
Exploration (Membership # 04231099). I have worked as a mining environmental professional for a total of 19 years since my graduation. My relevant experience for the purpose of the Technical Report is: • Responsible for the preparation and success approval of several Environmental Impact
Assessment Reports • Responsible for environmental aspects of mine permitting for several projects • Responsible for the environmental and geotechnical components of several PEA, PFS
and FS studies • Experience if reviewing and auditing environmental and permitting data for a multitude
of projects • Work as a government official in Germany and as a technical expert for the European
Union in the area of mine permitting 4. I have read the definition of "qualified person" set out in National Instrument 43-101 (NI 43-
101) and certify that by reason of my education, affiliation with a professional association (as defined in NI 43-101) and past relevant work experience, I fulfill the requirements to be a "qualified person" for the purposes of NI 43-101.
5. I did not visit the Aripuanã Zinc Project. 6. I am responsible for the preparation of Section 20 and contributed to Sections 1, 2, 3, 25,
and 26 (environmental aspects) of the Technical Report. 7. I am independent of the Issuer applying the test set out in Section 1.5 of NI 43-101. 8. I have had no prior involvement with the property that is the subject of the Technical Report. 9. I have read NI 43-101, and the Technical Report has been prepared in compliance with NI
43-101 and Form 43-101F1.
www.rpacan.com
VM Holding S.A. – Aripuanã Zinc Project, Project #2779
Technical Report NI 43-101 – July 31, 2017 Page 29-7
10. At the effective date of the Technical Report, to the best of my knowledge, information, and belief, Section 20 of the Technical Report for which I am responsible contains all scientific and technical information that is required to be disclosed to make the Technical Report not misleading.
Dated this 31st day of July, 2017. (Signed and Sealed) “Stephan Theben” Stephan Theben, Dipl.-Ing.