45
Project Documentation Document SPEC-0126 Rev A Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ 85719 Phone 520-318-8102 [email protected] http://atst.nso.edu Fax 520-318-8500 Visible Broadband Imager Red Channel Critical Design Definition William McBride, Scott Gregory, Andrew Ferayorni, Friedrich Wöger VBI Instrument Group September 12, 2012

Visible Broadband Imager Red Channel Critical Design Definition · 2020. 1. 22. · The F/20.3 focal plane is tilted 4.29˚ (due to the tilted field provided by the ATST) and is fixed

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • Project Documentation Document SPEC-0126

    Rev A

    Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ 85719

    Phone 520-318-8102 [email protected] http://atst.nso.edu Fax 520-318-8500

    Visible Broadband Imager

    Red Channel

    Critical Design Definition

    William McBride, Scott Gregory, Andrew Ferayorni, Friedrich Wöger

    VBI Instrument Group

    September 12, 2012

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page ii

    REVISION SUMMARY:

    1. Date: June 4, 2012 Revision: Initial version Changes: Draft

    2. Date: Sept 12, 2012 Revision: Rev A Changes: Ready for VBI Red CDR. Initial formal document.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page iii

    Table of Contents

    1. INTRODUCTION ...................................................................................................... 5

    2. OPTICAL DESIGN .................................................................................................... 6

    2.1 VBI RED DESIGN REQUIREMENTS ..................................................................... 7

    2.2 INTERFACE TO VBI RED ....................................................................................... 7

    2.2.1 Image Quality ................................................................................................................. 8

    2.2.2 Angle of Incidence .......................................................................................................... 9

    2.2.3 Pupil Footprints on Filters ............................................................................................... 9

    2.2.4 Grid Distortion ...............................................................................................................10

    2.3 OPTICAL TOLERANCE ANALYSIS AND ERROR BUDGET ................................. 11

    2.3.1 The Zemax Tolerance Model .........................................................................................11

    2.3.2 Monte Carlo Results ......................................................................................................15

    2.3.3 Conclusions ...................................................................................................................17

    2.4 OPTICAL ALIGNMENT ......................................................................................... 17

    2.5 SPURIOUS LIGHT MITIGATION PLAN .......................................................................... 18

    3. HARDWARE DESIGN ............................................................................................ 19

    3.1 FOLD MIRROR #1 MOUNT .......................................................................................... 22

    3.2 FILTER WHEEL ......................................................................................................... 22

    4. SOFTWARE DESIGN ............................................................................................. 25

    4.1 VBI RED CONTROL SYSTEM SOFTWARE ................................................................... 25

    4.2 SYNCHRONIZATION OF VBI BLUE AND VBI RED ......................................................... 25

    4.2.1 Alignment of Observation Steps ....................................................................................25

    4.2.2 Establishing Initial Start Time for Cameras ....................................................................30

    5. TEST PLAN ............................................................................................................ 33

    5.1 INTERFERENCE FILTER TESTING ............................................................................... 33

    5.2 INSTRUMENT TEST PLAN .......................................................................................... 34

    5.2.1 Alpha Phase ..................................................................................................................34

    5.2.2 Beta Phase....................................................................................................................34

    5.2.3 Lab Phase .....................................................................................................................35

    5.2.4 Engineering Phase ........................................................................................................35

    5.2.5 Speckle Phase ..............................................................................................................35

    5.2.6 Periodic Integration Phases. ..........................................................................................35

    5.2.7 Shipping Phase .............................................................................................................35

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page iv

    5.2.8 IT&C Phase ...................................................................................................................36

    5.2.9 Science Verification .......................................................................................................36

    6. BUDGET ................................................................................................................. 37

    6.1 LABOR .................................................................................................................... 37

    6.2 FILTERS ................................................................................................................. 37

    6.3 OPTICS .................................................................................................................. 38

    6.4 CONTROLS & MECHANICAL ...................................................................................... 38

    6.5 DATA HANDLING SYSTEM AND SPECKLE IMAGE RECONSTRUCTION ............................. 38

    6.6 BILL OF MATERIALS ................................................................................................. 39

    7. SCHEDULE ............................................................................................................ 42

    8. HAZARD ANALYSIS .............................................................................................. 43

    9. PROJECT MANAGEMENT .................................................................................... 44

    10. RISK ASSESSMENT ............................................................................................ 45

    10.1 VBI RISK REGISTER .............................................................................................. 45

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 5 of 45

    1. INTRODUCTION

    The Visible Broadband Imager (VBI) is a first-light high spatial resolution imaging instrument for the

    Advanced Technology Solar Telescope (ATST). For many reasons related to science, mechanics, optics

    and management, there are two separate VBI channels, the "blue" channel and the "red" channel, each

    capable of imaging four discrete wavelengths and operated either simultaneously or independently.

    The VBI red design is closely related to that of the VBI blue channel described in SPEC-0107, the VBI

    Critical Design Document (CDD). In this document, the VBI red CDD, modifications and additions to

    the VBI blue design are recorded that are mainly needed to address the VBI red's optical and mechanical

    requirements, as well as the synchronization requirements of the VBI red and blue channel.

    For a more detailed description of the VBI and items that are common to both channels, refer to SPEC-

    0107.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 6 of 45

    2. OPTICAL DESIGN

    Figure 1 VBI Red Optical Design

    The primary driver for the VBI optical design choice was to keep the instrument as simple as possible

    consistent with achieving the science requirements. The decisions that led to the VBI optical designs are

    documented in SPEC-0107 the VBI blue channel CDD. The red design is very similar to the blue design;

    like the blue channel, the red channel is a four lens design which includes two doublet and two singlet

    lenses. The main difference in the design is in the folding of the optics necessitated by the location and

    orientation of the red channel in the Coudé Lab (see Figure 2).

    Figure 1 shows the four lens design. The collimator lens is used to compensate the axial chromatic

    aberration for various filters and travels a total of 21mm between the longest and shortest wavelengths.

    The F/20.3 focal plane is tilted 4.29˚ (due to the tilted field provided by the ATST) and is fixed for all

    wavelengths. Focusing is accomplished by translating the collimator lens along the optical axis.

    The objective lens forms an F/13 focal-plane ~ 2600 mm downstream. The doublet is comprised of S-

    TIL6 and BK7 glass and has one conic surface. The silica field lens works with the collimator to form a

    65 mm diameter pupil at the location of the filter. The collimator is another silica singlet whose main

    function is to collimate the F/13 focal plane. The image doublet is very similar in composition to the relay

    doublet and images the F/20.3 focal plane at the camera detector.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 7 of 45

    2.1 VBI RED DESIGN REQUIREMENTS

    The following were the requirements for the VBI red channel optical design:

    FOV: ≈ 2.8 arcmin (round)

    Performance: Diffraction limited over the FOV

    F#: 20.3 at the detector plane

    Wavelength range: 600 to 860 nm

    Optimized wavelength: 656.3 nm

    Chromatic focal shift: less than 100 mm at the detector between 600 - 860 nm

    Filter acceptance angle: ≤ 1.4 degrees

    Filter effective refractive index: ≥ 1.9

    The filter must be located near a pupil within a collimated field.

    Filter clear aperture: 65 mm

    2.2 INTERFACE TO VBI RED

    The optical interface to VBI is the facility beamsplitter shown in the red circle below. This interface is

    described in detail in the Coudé Station to VBI Interface Control Document (ICD 3.1.3 to 3.2). The VBI

    blue WBS number is 3.2.1 and the VBI red WBS number is 3.2.2.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 8 of 45

    Figure 2: VBI Red-ATST Optical Interface

    2.2.1 Image Quality

    Figure 3: Image Quality represented by Spot Diagrams. Left: Spot Diagram for 600 nm. Right: Spot Diagram for 860 nm

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 9 of 45

    2.2.2 Angle of Incidence

    The field angles produce the center ray tilt and the collimate errors produce the collimate ray tilts. In this

    design the mean value of the central ray tilt is 1.71° (Figure 4).

    Figure 4: Results for Filter AOI

    2.2.3 Pupil Footprints on Filters

    Figure 5: Pupil Footprints on all Filters (all wavelengths). Filter CA is 65mm, Filter Diameter is 70 mm.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 10 of 45

    2.2.4 Grid Distortion

    The maximum grid distortion is always below 0.197% for all wavelengths (Figure 6).

    Figure 6: Distortion Grid for 656.3 nm.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 11 of 45

    2.3 OPTICAL TOLERANCE ANALYSIS AND ERROR BUDGET

    ASE Optics performed the optical tolerance analysis. The system performance specification is a peak-to-

    valley wavefront error of less than 0.50 waves at 633 nm for all field positions. A Monte Carlo analysis

    was performed to evaluate the probability that the specification can be met given the lens element

    tolerances used.

    All the tolerances from the previous VBI-Blue analysis have been carried over. The same homogeneity

    models that were used for the non-silica elements have been carried over. The narrowband filter

    wavefront model was updated to reflect the transmitted wavefront specification on the red channel filters.

    New models were added for the interface error and the transmitted wavefront error of the three

    beamsplitters.

    A 1000 trial Monte Carlo analysis was performed as was done with the VBI-Blue analysis. This time the

    same Zemax model was used to generate the sensitivities and run the Monte Carlo analysis. The pupil

    filter was allowed to tip and tilt to minimize AOI and the merit function used in tolerancing weighted the

    filter AOI. System effective focal length was allowed to vary, but remained between 79.47 and 79.82

    meters for all Monte Carlo trials. The field lens location was fixed at 20 mm ahead of the intermediate

    focus for all Monte Carlo trials. The most critical tolerance found was the filter wavefront error.

    2.3.1 The Zemax Tolerance Model

    The table below is the Zemax model used in the Monte Carlo analysis performed by ASE Optics. The

    table shows the defined nominal, min, and max ranges of the compensators and tolerances. It uses just the

    key tolerances that individually cause more than about 0.005 increase in RMS WFE. The table is used to

    generate the Monte Carlo analysis shown in Figure 7.

    # Type Int1 Int2 Int3 Nominal Min Max Comment

    1 TOFF - - - - - -

    ** Element spacing

    compensators:

    2 COMP 74 0 - 2109.414 -300 300 L1 focus

    3 COMP 81 0 - -616.088 -200 200 Collimator focus

    4 COMP 99 0 - 0 -200 200 Image lens focus

    5 TOFF - - - - - -

    ** Filter tilt

    compensator:

    6 CPAR 87 3 - -1.31E-03 -5 5 x position

    7 CPAR 87 4 - 2.02E-03 -5 5 y position

    8 TOFF - - - - - -

    ** Image lens x-y

    position compensator:

    9 CPAR 92 1 - 0.073 -5 5 x position

    10 CPAR 92 2 - 0.255 -5 5 y position

    11 TOFF - - - - - -

    ** Focal plane tilt

    compensator:

    12 CPAR 99 3 - -4.435 -3 3 x rotation

    13 CPAR 99 4 - 0.042 -3 3 y rotation

    14 TOFF - - - - - -

    ** Focus

    compensators:

    15 CMCO 5 1 - 4.597 -10 10 Config 1 focus

    16 CMCO 5 3 - -16.584 -10 10 Config 3 focus

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 12 of 45

    17 TOFF - - - - - -

    18 TWAV - - - - 0.633 -

    Default test

    wavelength.

    19 TOFF - - - - - - ** Interface error:

    20 TEZI 49 9 5 0 -2.08E-05 2.08E-05

    21 SAVE 1 - - - - -

    22 TOFF - - - - - -

    ** Beamsplitter

    wavefront model:

    23 TEZI 52 37 5 0 -4.20E-07 4.20E-07 BS1

    24 TEZI 57 37 5 0 -1.04E-06 1.04E-06 BS2

    25 TEZI 65 37 5 0 -1.04E-06 1.04E-06 BS3

    26 TOFF - - - - - -

    ** Pupil filter

    wavefront model:

    27 TEZI 88 9 5 0 -7.56E-05 7.56E-05

    28 SAVE 2 - - - - -

    29 TOFF - - - - - -

    ** Glass homogeneity

    tolerances:

    30 TEZI 69 37 10 0 -1.69E-05 1.69E-05 L1 LLF1 grade H3

    31 TEZI 71 37 10 0 -2.97E-05 2.97E-05 L1 BK7 grade H3

    32 TEZI 93 37 10 0 -1.04E-05 1.04E-05 L4 PSK3 grade H3

    33 TEZI 96 37 10 0 -7.68E-06 7.68E-06 L4 LLF1 grade H3

    34 TOFF - - - - - -

    ** Tolerances on

    surface radii:

    35 TRAD 69 - - -2132.8 -22 22 L1 - objective

    36 TRAD 70 - - -752.6 -8 8

    37 TRAD 71 - - 3692 -40 40

    38 TRAD 76 - - 371 -4 4 L2 - field lens

    39 TRAD 77 - - 1070 -20 20

    40 TRAD 83 - - -1265 -20 20 L3 - collimate lens

    41 TRAD 84 - - 651.7 -10 10

    42 TRAD 93 - - -276.6 -3 3 L4 - image lens

    43 TRAD 94 - - 276.6 -3 3

    44 TRAD 95 - - 276.6 -3 3

    45 TRAD 96 - - -439.3 -5 5

    46 TOFF - - - - - -

    ** Tolerance on conic

    constants:

    47 TCON 71 - - -16.657 -0.2 0.2 L1 - objective

    48 TCON 84 - - -2.727 -0.1 0.1 L3 - Collimate lens

    49 TOFF - - - - - -

    ** Element thickness

    tolerances:

    50 TTHI 69 69 - -30 -0.5 0.5 L1

    51 TTHI 70 70 - -40 -0.5 0.5

    52 TTHI 76 76 - 6 -0.2 0.2 L2

    53 TTHI 83 83 - -10 -0.2 0.2 L3

    54 TTHI 93 93 - -9 -0.2 0.2 L4

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 13 of 45

    55 TTHI 95 95 - -7 -0.2 0.2

    56 TOFF - - - - - -

    ** Index of refraction

    tolerances:

    57 TIND 69 - - 1.548 -1.00E-03 1.00E-03 L1

    58 TIND 70 - - 1.517 -1.00E-03 1.00E-03

    59 TIND 76 - - 1.458 -1.00E-03 1.00E-03 L2

    60 TIND 83 - - 1.458 -1.00E-03 1.00E-03 L3

    61 TIND 93 - - 1.603 -7.00E-04 7.00E-04 L4

    62 TIND 95 - - 1.62 -7.00E-04 7.00E-04

    63 TOFF - - - - - -

    ** Abbe number

    tolerances:

    64 TABB 69 - - 45.75 -0.458 0.458

    65 TABB 70 - - 64.167 -0.642 0.642

    66 TABB 76 - - 67.821 -0.678 0.678

    67 TABB 83 - - 67.821 -0.678 0.678

    68 TABB 93 - - 60.597 -0.606 0.606

    69 TABB 95 - - 36.431 -0.364 0.364

    70 TOFF - - - - - -

    Element tilt/decenter

    tolerances:

    71 TEDX 69 71 - 0 -2 2 L1

    72 TEDY 69 71 - 0 -2 2

    73 TETX 69 71 - 0 -0.1 0.1

    74 TETY 69 71 - 0 -0.1 0.1

    75 TEDX 76 77 - 0 -2 2 L2

    76 TEDY 76 77 - 0 -2 2

    77 TETX 76 77 - 0 -0.2 0.2

    78 TETY 76 77 - 0 -0.2 0.2

    79 TEDX 83 84 - 0 -2 2 L3

    80 TEDY 83 84 - 0 -2 2

    81 TETX 83 84 - 0 -0.2 0.2

    82 TETY 83 84 - 0 -0.2 0.2

    83 TOFF - - - - - -

    ** Surface

    tilt/decenter

    tolerances:

    84 TSTX 69 - - 0 -0.05 0.05 L1

    85 TSTY 69 - - 0 -0.05 0.05

    86 TSTX 70 - - 0 -0.05 0.05

    87 TSTY 70 - - 0 -0.05 0.05

    88 TSTX 71 - - 0 -0.05 0.05

    89 TSTY 71 - - 0 -0.05 0.05

    90 TSTX 76 - - 0 -0.1 0.1 L2 - Field lens

    91 TSTY 76 - - 0 -0.1 0.1

    92 TSTX 77 - - 0 -0.1 0.1

    93 TSTY 77 - - 0 -0.1 0.1

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 14 of 45

    94 TSTX 83 - - 0 -0.1 0.1 L3 - Collimate lens

    95 TSTY 83 - - 0 -0.1 0.1

    96 TSTX 84 - - 0 -0.1 0.1

    97 TSTY 84 - - 0 -0.1 0.1

    98 TSTX 93 - - 0 -0.1 0.1 L4 - Image lens

    99 TSTY 93 - - 0 -0.1 0.1

    100 TSTX 94 - - 0 -0.1 0.1

    101 TSTY 94 - - 0 -0.1 0.1

    102 TSTX 95 - - 0 -0.1 0.1

    103 TSTY 95 - - 0 -0.1 0.1

    104 TSTX 96 - - 0 -0.1 0.1

    105 TSTY 96 - - 0 -0.1 0.1

    106 TOFF - - - - - -

    ** Irregularity

    tolerances:

    107 TIRR 69 - - 0 -0.5 0.5 L1

    108 TIRR 70 - - 0 -0.5 0.5

    109 TIRR 71 - - 0 -0.5 0.5

    110 TIRR 76 - - 0 -0.5 0.5 L2

    111 TIRR 77 - - 0 -0.5 0.5

    112 TIRR 83 - - 0 -0.25 0.25 L3

    113 TIRR 84 - - 0 -0.25 0.25

    114 TIRR 93 - - 0 -0.25 0.25 L4

    115 TIRR 94 - - 0 -0.25 0.25

    116 TIRR 95 - - 0 -0.25 0.25

    117 TIRR 96 - - 0 -0.25 0.25

    118 TOFF - - - - - -

    ** Fold mirror

    irregularity tolerances:

    119 TIRR 62 - - 0 -0.125 0.125 beamsplitter

    120 TIRR 73 - - 0 -0.125 0.125 fold mirror 1

    121 TIRR 80 - - 0 -0.125 0.125 fold mirror 2

    Table 1: Zemax Model used in the Monte Carlo

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 15 of 45

    2.3.2 Monte Carlo Results

    The Monte Carlo result indicates the design will be less than ½ wave P-V at 656nm 91.6% of the time for

    the full field 2.8 arcmin FOV. The results also indicate the design will be less than ½ wave P-V at 860nm

    98.4% of the time with the full FOV.

    Figure 7: Monte Carlo Results for full FOV.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 16 of 45

    Figure 8: Monte Carlo Results for 1.4 arcmin FOV

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 17 of 45

    Figure 9: Compensator Ranges

    2.3.3 Conclusions

    A tolerance analysis of the VBI-R system has been performed. The results show the same primary

    sensitivities as the VBI-B system. The filter wavefront dominates the other tolerances in producing the

    system performance. The beamsplitter wavefront is not critical to the system performance at λ/20 and

    could be relaxed to λ/10.

    2.4 OPTICAL ALIGNMENT

    By simplifying the optical design to an all-refractive design, we have significantly mitigated alignment

    risk. In our reflective designs, the sensitivity of off-axis parabola alignment was far more severe.

    The dichroic beamsplitter that transmits longer wavelengths to the VBI Red is the optical interface and

    provided by the facility. It is the responsibility of the appropriate ATST staff to ensure that this interface

    is properly aligned before starting the VBI Red alignment.

    It is highly likely that the VBI Red objective and fold mirror will share an optical table with other facility

    fore-optics. Thus, we expect this table to be properly aligned when installing the objective and fold

    mirror. The remaining optics and detector will most likely reside on another optical bench.

    The installation and alignment will begin with installing the objective the proper distance from the

    dichroic beamsplitter. All lenses will have masks to define the center of the lens. With the mask installed,

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 18 of 45

    we will use a GOS pinhole target with sunlight, at the Gregorian Optical Station (GOS) to center the lens

    in the optical beam. We will adjust tilt by aligning the reflection from the lens with the beam on the fore-

    optics. The large fold mirror will be installed next. The optical bench for the remaining optics and

    detector will then be installed and aligned to a row of threaded holes on the bench using the GOS pinhole

    target with sunlight. The remaining lenses will be installed and aligned using the same procedure.

    This type of alignment procedure has been used successfully at the DST for many years. In addition, we

    anticipate using the facility wavefront sensor, fiber interferometer, and the VBI detector to optimize the

    focal plane optical performance.

    2.5 SPURIOUS LIGHT MITIGATION PLAN

    Spurious light reaching a detector is always a significant concern when designing and operating a

    scientific instrument. Sources of spurious light typically come from the instrument itself, reflections from

    other instruments, and the lab itself in which they operate.

    Spurious light emitted within the instrument itself is typically introduced by front and back surface

    reflections of optical elements such as lenses, windows, beam-splitters, and filters. To mitigate this issue,

    we have minimized such reflections by optimizing the anti-reflection coatings over the wavelength range

    of the instrument. The achievable result is < 1% reflection from 600 to 1100 nm; < 0.25% for VBI-B from

    390-490 nm.

    The VBI-Red will be setup and tested within a lab equipped with a solar light feed before shipping to the

    ATST site. During this process, the team will identify and evaluate spurious light sources within the

    instrument by darkening the lab and blocking light sources from the lab itself. This is typical of custom

    observing setups at the Dunn Solar Telescope where the instrument is cloaked with darkroom cloth and

    baffles are added to eliminate spurious emissions within the instrument. Having identified the sources and

    mitigations, the team will design and construct fixed blockers and baffles to be affixed securely to the

    optical table supporting the instrument. Having installed these elements in the lab, the team will

    reevaluate the performance mitigation prior to shipping the instrument to the ATST.

    The ATST will have a laminar down-flow of conditioned air in the coudé lab to mitigate local seeing and

    dust accumulation. As such, instruments are not envisioned to require covers for the entire instrument.

    Therefore, it is critical that the coudé lab itself will not generate sources of spurious emission into the

    instruments. Should the lab generate such emissions, it is envisioned that these sources will be blocked

    within the instrument with additional tubes and baffles developed in the IT&C phase.

    It is difficult to predict spurious light sources from other instruments in the coudé lab. However, the

    mitigation within the VBI-Red is expected to resemble the mitigation from stray light coming from the

    coudé lab.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 19 of 45

    3. HARDWARE DESIGN

    The VBI Red design is mechanically identical to the VBI Blue design described in SPEC-0107 with only

    two differences. The first mirror of the VBI Red optical design has a small enough angle of incidence in

    the reflected light beam to allow the use of an off the shelf mount that fits within the Coudé room

    specified beam height of 250 mm. (In the Blue design the first fold mirror was sufficiently large that off

    the shelf mounts had a center line height of more than 250 mm, so a custom mount was designed.) The

    second difference is that the filter wheel capacity has been expanded to include a fifth filter position. A

    five position filter wheel will now be used in both the red and blue channels.

    Layouts of the VBI Red along with layouts of the Red and Blue channel combined are shown in the

    following figures.

    Figure 10: VBI Red Layout

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 20 of 45

    Figure 11: VBI Red Layout Including ATST Light Feed

    Figure 12: Left - VBI Red Layout on Coude Platform; Right – VBI Red & Blue Layout on Coude Platform (top down)

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 21 of 45

    Figure 13: VBI Red & Blue Layout Including Light Feed

    Figure 14: VBI Red & Blue Layout

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 22 of 45

    3.1 FOLD MIRROR #1 MOUNT

    Since the first fold mirror needs a clear aperture of >220mm in diameter in order to make the first fold of

    the VBI Red optical layout, a common sized 254mm (10 inch) mirror will be used. An Aerotech

    AOM110-10 mount can be used to hold this mirror. This off-the-shelf mount has a centerline distance

    slightly less than the specified Coudé beam height above the optical benches of 250mm, so a riser mount

    will be made. A COTS mirror mount will save some manufacturing time over a custom made mount.

    The mount design of the first fold mirror is shown in Figure 15.

    Fold Mirror 1 Mount Opto-Mechanical Design Requirements Compliance

    Req. Matrix Num. Req. Description Requirement Goal As Designed Value

    C303 X Tilt Adjustable (See Note 1) 0.08 arcsec (See Note 2)

    C303 Y Tilt Adjustable (See Note 1) 0.08 arcsec (See Note 2)

    Note 1: Requirement is to steer beam to within ±0.05 mm over a distance of >3 m.

    Note 2: Pointing resolution per degree of adjusting screw - equivalent to 0.0012 mm @ 3000 mm.

    Figure 15: VBI Red Fold Mirror #1 (Aerotech COTS)

    3.2 FILTER WHEEL

    The filter wheel assembly will now utilize a five, instead of four, position wheel. Everything else will

    remain identical to the original design. The purpose of the fifth position is to allow the addition of an

    alignment target/pinhole to the wheel and also to accommodate future upgrade expansion or allow the use

    of the VBI as a context imager for another instrument that would require a different wavelength. There

    was enough room on the previous Blue channel design to add another position without changing the

    overall wheel diameter or the filter center distance. In addition, the original wheel was designed and

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 23 of 45

    modeled with 13mm thick filters, but the actual filter thicknesses delivered for the Blue channel came in

    at 7.4mm thick. This lighter weight for filters and shorter move distance (72° instead of 90°) yields

    motion profile characteristics and performance very similar to the original four position design. The five

    position filter wheel meets the same performance, accuracy and timing requirements as did the four

    position filter wheel with minimal design impact. The filter wheel design is shown in Figure 16.

    Filter Wheel Opto-Mechanical Design Requirements Compliance

    Req. Matrix Num. Req. Description Requirement Goal As Designed Value

    C19 Move time 0.54 sec. 0.34 sec. 0.145 sec.

    C20 Accuracy ±0.1 mm ±0.05 mm 0.020 mm (See Note 1)

    C299 X/Y Tilt 0.05º (See Note 2)

    C21 Repeatability ±0.05 mm 0.018 mm (See Note 1)

    C22 Cell diameter 70 mm min. 70 mm

    C24 Clear aperture 65 mm min. 68 mm

    Note 1: This is maximum theoretical mechanical error. Actual prototype testing shows accuracy and

    repeatability to be within a single encoder count (5 arc seconds or 0.002mm).

    Note 2: Wheel will be assembled and inspected to comply with required tilt angle.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 24 of 45

    Figure 16: VBI 5 Position Filter Wheel

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 25 of 45

    4. SOFTWARE DESIGN

    4.1 VBI RED CONTROL SYSTEM SOFTWARE

    The VBI Red control system software is identical to that of the VBI Blue, but is deployed as an

    independent system. This was done to 1) allow construction of the Blue channel to begin after passing its

    CDR, 2) allow one channel to operate even if the other channel experiences problems and 3) to maximize

    the flexibility of using the Blue and Red channels in conjunction with other instruments. For example,

    the Blue channel can be configured to collect data in coordination with one instrument while the Red

    channel can be configured to collected data in coordination with a different instrument.

    The VBI Red system configuration differs slightly from the Blue channel to ensure user input parameters,

    such as wavelength, are validated against the range of values specific to the Red channel.

    4.2 SYNCHRONIZATION OF VBI BLUE AND VBI RED

    Observations performed by the VBI Blue and VBI Red consist of one or more observation steps. Each

    observation step represents a data acquisition that may consist of one or more camera exposures. The

    VBI Blue and VBI Red are required to synchronize their camera exposures to within +/- 5ms. Since there

    are no electronic trigger lines connecting the two instruments, achieving this level of synchronization

    requires 1) alignment of observation steps and 2) execution timing.

    Alignment of observation steps involves ensuring that the cadence of the steps defined for one instrument

    is cohesive with that of the other. Execution timing involves starting those observation steps at precise

    times and maintaining timing accuracy throughout their execution. In the following sections we will look

    at how the VBI Blue, VBI Red, and other ATST systems are used to achieve synchronization and look at

    a real example to help illustrate the process.

    4.2.1 Alignment of Observation Steps

    There are three types of alignment supported by the VBI Blue and VBI Red that may be selected when

    building an experiment. The first type is observation start, which involves ensuring both the VBI Blue

    and VBI Red start their first data acquisition at the same time. The second type of automatic alignment is

    at the observation cycle level. This type of alignment involves making sure one channel does not repeat

    its cycle of observation steps before the other channel has completed its cycle of observation steps. The

    third type of automatic alignment must occur at the observation step level. This type of alignment

    involves making sure the observation steps of one channel start at the same time as the corresponding step

    of the other channel. In the next few sections we will look at an example of each of these alignment

    types.

    Alignment Example – Observation Start

    As an example, imagine that we want the VBI Blue to take 6 frames at 10 FPS at three different

    wavelengths (A, B, and C). The time allowed for moving mechanisms (i.e. filter change) between

    wavelengths is 400ms, which is determined by finding the first multiple of the rate that is greater than or

    equal to the minimum move duration of 333ms. The cycle for the VBI Blue would therefore consist of

    three observation steps, each requiring 600ms for data acquisition (6 x 100ms per frame) and 400ms for

    filter position change. Then suppose we want the VBI Red to take a single frame at 10 FPS at two

    different wavelengths (D and E). The cycle for the VBI Red would therefore consist of two observation

    steps, each requiring 100ms for data acquisition (1 x 100ms) and 400ms for filter position change.

    To request observation start alignment, the user will select the option when building the experiment with

    the VBI Explorer. Figure 17 below shows a prototype screen shot of the VBI Blue Explorer where the

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 26 of 45

    user has selected observation start alignment. Notice that no other information regarding the observation

    step offset is required when only start alignment is requested.

    Figure 17: VBI Blue Explorer with Observation Start Alignment

    With observation start alignment, the VBI Blue and VBI Red will only ensure that the observations are

    started at the same time. After the observations are started, execution of cycles and their steps will

    continue as fast as possible. Therefore, the ability for subsequent observation steps to remain in sync

    completely depends on the duration of those steps, and is not checked by the VBI Explorer. Figure 18

    below shows how the steps of these observations would align if we ran two cycles with observation start

    alignment selected.

    Figure 18: VBI Blue and VBI Red with Observation Start alignment

    The VBI control systems will ensure the first camera data acquisition start time of the first observation

    step is the same by using the ICS rendezvous service to obtain the agreed start time. Please refer to

    section 4.2.2 for more information about this service. Once an ICS rendezvous start time is obtained, the

    Visible Broadband Imager BlueExplorer

    FixedCadence:

    Data Acquisition Sequence:

    Wavelength Frame Sets FramesRate

    (fps)

    Exposure Time

    (seconds)Binning ROI

    Offset

    (seconds)

    A 1 6 10 0.01 1x1 Full 1

    B 1 6 10 0.012 1x1 Full 1

    C 1 6 10 0.011 1x1 Full 1

    Align for Synchronization:

    5Number of Cycles:

    Load from file:

    Offsets (sec):--OR--

    BROWSE

    EDIT

    SAVE

    ALIGN

    Observe Mode Configuration:

    X

    From file:

    Start

    CycleStep

    D

    A

    Filter change

    Filter change

    B CFilter

    change

    EFilter

    changeD

    A

    Filter change

    Filter change

    BFilter

    change

    EFilter

    changeD

    Filter change

    EFilter

    changeD

    Filter change

    EFilter

    changeD

    Filter change

    EFilter

    change

    Filter change

    500 1000 1500 2000 2500 3000 3500 4000 4500 50000

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 27 of 45

    VBI Blue and VBI Red will use that time to program the “initial start time” of their cameras using the

    CSS interface. Please refer to the SPEC-0098 CSS Functional Interface for more information about this

    parameter and its use.

    Alignment Example – Observation Cycle

    In some scenarios the user may wish to synchronize the VBI Blue and VBI Red at the start of every cycle.

    The observation cycle alignment type can be used for this purpose, and will ensure that the first

    observation step of each cycle for the VBI Blue and VBI Red will begin at the same time. To accomplish

    this, the system must take the VBI channel with the shorter total cycle duration and add a delay at the end.

    When selecting this alignment type it is therefore necessary that the user enter the observation step

    durations from the other instrument as a comma separated list so that the correct alignment calculations

    can be performed. Figure 19 below shows a prototype screenshot of the VBI Blue explorer for the

    example given before. Notice that the user has selected “cycle” type alignment and provided the offsets

    from the VBI Red channel (500ms per observation step) as a comma separated list.

    Figure 19: VBI Blue Explorer with Observation Cycle Alignment

    When the user clicks the “Align” button, the VBI Blue Explorer will look at the offsets for the VBI Blue

    and those provided for the VBI Red and determine which has the shorter cycle length. It will then present

    the suggested alignment results to the user. For this example, the VBI Red has a shorter total cycle

    duration of 1s (500ms x 2), compared to the VBI Blue cycle duration of 3s (1s x 3). Therefore the system

    Visible Broadband Imager BlueExplorer

    FixedCadence:

    Data Acquisition Sequence:

    Wavelength Frame Sets FramesRate

    (fps)

    Exposure Time

    (seconds)Binning ROI

    Offset

    (seconds)

    A 1 6 10 0.01 1x1 Full 1

    B 1 6 10 0.012 1x1 Full 1

    C 1 6 10 0.011 1x1 Full 1

    Align for Synchronization:

    5Number of Cycles:

    Load from file:

    Offsets (sec):--OR--

    0.5, 0.5

    BROWSE

    EDIT

    SAVE

    ALIGN

    Observe Mode Configuration:

    X

    From file:

    Start

    CycleStep

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 28 of 45

    will suggest adjusting the offset for the second step of the VBI Red to 2s. Figure 20 below shows a

    prototype screen of the alignment results presented to the user.

    Figure 20: VBI Blue Explorer Cycle Alignment Result

    With observation cycle alignment, the VBI Blue and VBI Red will only ensure that the start of each

    observation cycle is at the same time. After each cycle begins, execution of the observation steps will

    continue as fast as possible. Therefore, the ability for subsequent observation steps to remain in sync

    completely depends on how those steps are defined, and is not checked by the VBI Explorer. Figure 21

    below shows how the steps of these observations would align if two cycles are run with observation cycle

    alignment selected.

    Figure 21: VBI Blue and VBI Red with Cycle Alignment

    Alignment Example – Observation Step

    In some scenarios the user may wish to synchronize the VBI Blue and VBI Red at the start of every

    observation step. The observation step alignment type can be used for this purpose, and will ensure that

    each corresponding observation step for the VBI Blue and VBI Red are started at the same time. To

    accomplish this, the system must analyze each observation step for the two channels, and add a delay to

    the end of the shorter steps to align with the longer steps. When selecting this alignment type it is

    therefore necessary that the user enter the observation step durations from the other instrument as a

    comma separated list so that the correct alignment calculations can be performed. Figure 22 below shows

    a prototype screenshot of the VBI Blue explorer for the example given before. Notice that the user has

    selected “step” type alignment and provided the offsets from the VBI Red channel (500ms per

    observation step) as a comma separated list.

    Alignment Calculator Results:

    Data Acquisition Offsets (seconds):

    0.5, 2.0

    VBI Blue:

    External Instrument:

    SAVE TO FILE

    X

    No changes required

    D

    A

    Filter change

    Filter change

    B CFilter

    changeA

    Filter change

    BFilter

    changeFilter

    change

    500 1000 1500 2000 2500 3000 3500 4000 4500 50000

    EFilter

    changeD

    Filter change

    EFilter

    change

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 29 of 45

    Figure 22: VBI Blue Explorer with Observation Step Alignment

    When the user clicks the “Align” button, the VBI Blue Explorer will look at the offsets for the VBI Blue

    and those provided for the VBI Red and for each step, determine which has the shorter duration. It will

    then present the suggested alignment results to the user. For this example, the VBI Red has a duration of

    500ms for step 1 while the VBI Blue has a duration of 1s for step 1. The system will therefore suggest

    step 1 of the VBI Red be padded with 500ms so that step 1 for both channels will have a duration of 1s.

    The same adjustment will be applied to the second step of the VBI Red, since it is 500ms shorter than the

    second step of the VBI Blue. Figure 23 below shows a prototype screen of the alignment results

    presented to the user.

    Figure 23: VBI Blue Explorer Step Alignment Result

    Visible Broadband Imager BlueExplorer

    FixedCadence:

    Data Acquisition Sequence:

    Wavelength Frame Sets FramesRate

    (fps)

    Exposure Time

    (seconds)Binning ROI

    Offset

    (seconds)

    A 1 6 10 0.01 1x1 Full 1

    B 1 6 10 0.012 1x1 Full 1

    C 1 6 10 0.011 1x1 Full 1

    Align for Synchronization:

    5Number of Cycles:

    Load from file:

    Offsets (sec):--OR--

    0.5, 0.5

    BROWSE

    EDIT

    SAVE

    ALIGN

    Observe Mode Configuration:

    X

    From file:

    Start

    CycleStep

    Alignment Calculator Results:

    Data Acquisition Offsets (seconds):

    1.0, 1.0

    VBI Blue:

    External Instrument:

    SAVE TO FILE

    X

    No changes required

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 30 of 45

    With observation step alignment, the VBI Blue and VBI Red will ensure that the start of each

    corresponding observation step occurs at the same time. Figure 24 below shows how the steps of these

    observations would align if we ran two cycles with observation step alignment selected.

    Figure 24: VBI Blue and VBI Red with Step Alignment

    4.2.2 Establishing Initial Start Time for Cameras

    Alignment of data acquisition blocks between the VBI Blue and VBI Red using the calculator tool

    ensures that if the cameras start executing the sequence of blocks at the same time, the data acquisitions

    will remain synchronized. Therefore, it is imperative that both the VBI Blue camera and VBI Red camera

    be programmed with the same initial start time.

    Several options were explored for establishing the initial start time. They included 1) User specified start

    time, 2) ICS coordinated start time, and 3) ICS rendezvous. Option 1 was the simplest approach, and

    only involved the user entering the desired start time before starting the observing task. The downside to

    this approach was that picking a start time far enough in the future to accommodate the setup time of all

    synchronized instruments could lead to wasted observing time (too far out), or possibly a missed

    synchronized start (not far enough). Option 2 improved on Option 1 by having the ICS calculate the start

    time only after all instruments involved in the synchronization were done with their setup. This solution

    was sufficient for synchronizing the initial start of data collection for instruments, but did not support re-

    establishing synchronization at different points during the observation. Option 3 was introduced by the

    ATST Software Group as an improvement on Option 2 by allowing instruments to “rendezvous” with

    other instruments at any time during the observation by communicating back with the ICS. Although

    Option 2 was suitable for synchronization between the VBI Blue and VBI Red, Option 3 was chosen for

    its flexibility to handle other synchronization needs that are likely to be required in future ATST

    observation use cases.

    Figure 25 below shows the context of the ICS Rendezvous solution. The Rendezvous component will be

    used by all instruments requiring synchronization, and therefore it resides and is managed by the ICS.

    The event service is used for communications between the observe script running in the instrument ICs

    and the Rendezvous component in the ICS.

    D

    A

    Filter change

    Filter change

    B CFilter

    changeA

    Filter change

    BFilter

    changeFilter

    change

    500 1000 1500 2000 2500 3000 3500 4000 4500 50000

    EFilter

    changeD

    Filter change

    EFilter

    change

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 31 of 45

    Figure 25: Context diagram for Synchronization via ICS Rendezvous

    Figure 26 below shows a sequence diagram of the communications between systems in the ICS

    Rendezvous solution. The ICS will instruct each instrument IC to first complete its setup activities, such

    as moving mechanisms to their initial positions and programming the camera with data acquisition

    settings. Once all instruments involved have completed setup, the ICS will instruct them to begin

    execution of their data acquisition steps.

    At this point, all instrument ICs that need to synchronize will communicate with the ICS Rendezvous

    component via the CSF event service. They will post an event (atst.ics..rendezvous) stating

    1) that they are ready to begin data collection (.action=rendezvous),

    2) what other instruments they are expecting to synchronize with (.components[]),

    3) how much time is required to start the camera (.offset), and

    4) how much time to wait before timing out (.timeOut).

    Upon receipt, the ICS rendezvous component will respond with an event (atst.ics.rendezvous)

    acknowledging receipt of the request (.action=ack).

    Once the ICS Rendezvous component has received the rendezvous request event from all instruments

    involved in a synchronized observation, it will compute an initial camera start time by adding the current

    time, the ICS Rendezvous response latency, and the longest time required to start the camera from any

    instrument. This initial camera start time (.rendezvousTime) will be broadcast back to the instruments as

    an attribute of an event (atst.ics.rendezvous) using the CSF Event service. Finally, the instruments will

    receive the response event, program their cameras accordingly, and data acquisition will start on all

    cameras at the same time.

    Instrument Control System (ICS)

    Observation Management System

    VBI Blue Instrument Adapter VBI Red Instrument Adapter

    Rendezvous

    VBI Blue Instrument Controller VBI Red Instrument Controller

    CSF Event Service

    Rendezvous event Rendezvous event

    Rendezvous event

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 32 of 45

    Figure 26: Sequence diagram for VBI Blue and VBI Red synchronization using ICS Rendezvous

    If the ICS does not receive all rendezvous requests from the instruments in the list before the shortest time

    out period of any instrument, it will generate an event (atst.ics.rendezvous) indicating the rendezvous was

    cancelled due to a time out (.action=timeOut).

    The rendezvous request event (atst.ics..rendezvous) also provides the ability to cancel a request

    (.action=cancel). If an instrument requests a cancel, the ICS will respond with an event

    (atst.ics.rendezvous) acknowledging the cancel (.action=ack).

    The ICS rendezvous functionality will be implemented as a service provided by the ICS and the user is

    not directly involved in the details of the synchronization implementation (the Rendezvous component

    and the specific events used). Because the service has not yet been implemented, some of the

    implementation details may change in order to maximize efficiency and robustness. The details will be

    documented in the relevant ICS documents (TN-0102, ICS Reference Design, SPEC-0113, Facility

    Instrument Interface Specification, and TN-0152, Standard Instrument Framework).

    ICS Rendezvous VBI Blue VBI Red

    Start setup

    Start setup

    Setup complete

    Setup complete

    Start data acquisitions

    Start data acquisitions

    Wait for rendezvous

    Wait for rendezvous

    Start time = T

    Start time = T

    Data acquisitions complete

    Data acquisitions complete

    Start camera at T Start camera at T

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 33 of 45

    5. TEST PLAN

    5.1 INTERFERENCE FILTER TESTING

    All filters will be tested using the Horizontal Spectrograph (HSG), a facility instrument installed at the

    Dunn Solar Telescope (DST) in Sunspot, NM.

    The steps of the filter acceptance testing are described below:

    1. All used filters will be placed near a focal plane for the measurements.

    2. A reference scan will be acquired using a broad, line selecting prefilter for the spectrograph. This is achieved by taking an image that encodes spectral information in one axis, and spatial

    information along the other axis (slit), and subsequently stepping the slit to the next position in

    the 2D spatial field of view and acquiring the next image.

    A ‘super mean profile’ computed from this reference scan (see step 4 below) is compared against

    a profile taken from a peer reviewed atlas profile in order to determine an absolute wavelength

    axis for the used spectrograph and camera configuration, as well as the residual profile of the

    broad, line selecting prefilter.

    3. The broad, line selecting filter will be replaced with the interference filters that are to be tested for acceptance. Potentially, the slit length and range of the scan mechanism of the spectrograph does

    not suffice for a test of the full interference filter aperture (Ø 70 mm). Therefore, the filter may have to be physically moved to mosaic the full aperture. This way, a grid of mosaic scan cubes

    can be acquired; where the mosaic scan cubes slightly overlap.

    4. The reference scan from step 2 above is used in the following computation:

    a. The line curvature along the spatial axis inherent to the spectrograph is removed and, subsequently, all profiles along the spatial axis as well as from all scan steps are averaged

    to create a ‘super mean profile’.

    b. The filter profile of the broad, line selecting prefilter is removed from the ‘super mean profile’.

    c. The 1D ‘super mean profile’ in return is used to create a synthetic 2D image that reproduces the line curvature along the spatial axis inherent to the spectrograph.

    5. Out-of-band blocking over the spectral range will be tested by creating a mean profile for one mosaic scan, with camera read-out noise offset (‘dark noise’) subtracted.

    6. Subsequently, all of the mosaic scan cube images are divided by the synthetic 2D image created in step 4b to remove the solar spectral signature in the data. Finally, remaining background -

    estimated from unexposed ‘dark’ frames - is subtracted.

    This creates the filter curve profiles. Filter transmission is encoded relative to the broad, line

    selecting filter.

    7. After correcting for the line curvature along the spatial axis inherent to the spectrograph, each of the filter curve profiles are fitted using the function:

    ( ) [ ]

    ( [ ] [ ] ⁄

    )

    In this case, the fit parameter P[1] corresponds to the filter central wavelength, P[2] corresponds

    to the full width at half maximum (FWHM), and α corresponds to the number of cavities.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 34 of 45

    8. The resultant mosaic fit data are re-assembled into a full map of the filter for the parameter P[1] (central wavelength) and P[2] (FWHM), after solar structure remaining from step 6 has been

    removed to best effort.

    The preceding test method was developed and used for qualification of the VBI blue filters. The detailed

    procedure and results can be found in ATST technical note TN-0164 VBI Filter Acceptance Test.docx.

    5.2 INSTRUMENT TEST PLAN

    The two channels of the VBI will be tested together. Testing of the VBI instruments will happen in

    phases. Each phase consists of a development phase followed by a user acceptance test (UAT). UATs

    are used to provide periodic exposure of the VBI and user interface to a limited set of users so that user

    feedback may guide the software effort. All testing is performed to ensure compliance with the VBI

    compliance matrix CMX-0001.

    At the conclusion of each phase, a milestone is reached and a software release is announced. There are no

    users of the releases in the early phases with the exception of the ATST software team who may elect to

    use a particular release as a test tool to aid their own development effort. The release phases are: Alpha,

    Beta, Lab, Engineering, Speckle, Integration phases (as needed), Shipping, and Operations.

    5.2.1 Alpha Phase

    Alpha phase includes the development of the mechanical assemblies, the VBI control system hardware

    and software, and concludes with both channels of the VBI operable in a limited-functionality, stand-

    alone configuration.

    Mechanical

    The mechanical tests ensure that the mechanical sub-assemblies meet VBI mechanical tolerance

    specifications. These measurements will be performed during the final sub-assembly in Sunspot by the

    VBI mechanical engineer. Fabrication of all VBI mechanical components is scheduled for completion by

    March 2013.

    Software

    Software development occurs in parallel with mechanical construction and test. The VBI Red software is

    identical to the VBI Blue software with the addition of the synchronization requirement as described in

    section 4.2.

    Alpha software development makes use of limited-functionality simulators for the Camera Control

    Software (CSS) and Instrument Control Software (ICS) – these simulators are provided by the ATST

    software team and are separate from the VBI effort. The Alpha release coincides with the completion of

    all mechanical sub-assemblies.

    The Alpha release is scheduled for March 2013.

    5.2.2 Beta Phase

    Development of the Beta release makes use of the VBI mechanical assemblies, instead of the simulators.

    This work will be performed in the Tucson instrument lab and will incorporate the full CSS, the mini-

    DHS, and a limited functionality ICS (provided by the ATST software group). Testing will focus on

    individual sub-assemblies, and finally, all of the mechanical assemblies (minus optics) will be tested

    together. The Beta release is scheduled for July 2013.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 35 of 45

    Utilizing the sub-assemblies early in the development of the instrument is advantageous because

    operating the mechanical stages for a period of time allows the team to gain experience with the

    assemblies and mitigates the risk of infant mortality.

    The Beta release is scheduled for July 2013.

    5.2.3 Lab Phase

    The Lab phase finishes the instrument controller development and the data processing plug-ins; together

    these components provide a fully functional stand-alone instrument using the project provided camera

    simulator and mini-DHS.

    The Lab release is scheduled for October 2013.

    5.2.4 Engineering Phase

    Following the Lab release, development will switch to speckle reconstruction development. During

    speckle development, the project provided Engineering Camera, Tucson Camera Line, and Camera

    Software Systems for Engineering Camera will be released. The engineering phase will conclude with a

    fully integrated camera system using a Beta version of the speckle reconstruction engine. Speckle testing

    will be done using simulated image files.

    The Engineering release is scheduled for July 2014.

    5.2.5 Speckle Phase

    The Speckle phase will complete the speckle reconstruction development. Speckle testing will be done

    using simulated image files. The complete VBI instruments will be assembled with the optics and optical

    testing and a detailed optical alignment plan will be tested and documented.

    The Speckle release is scheduled for January 2015.

    5.2.6 Periodic Integration Phases.

    At this point, the VBI will be fully functional using an engineering camera, the project provided camera

    systems software, the project provided data handling system, the project provided instrument control

    system, and the VBI software and mechanical assemblies. The project will be completing the final

    versions of the Instrument Control System software and the Maui DHS. As these products become

    available, along with updates to other software systems, they will be integrated and tested with the VBI

    instruments.

    The periodic integration phases are scheduled to be completed by April 2016.

    5.2.7 Shipping Phase

    The science cameras will be received in April 2016, along with the final release of the camera control

    software. At this point, the final cameras will be integrated into the VBI in preparation of the VBI

    readiness review. Integration testing with the latest releases of project provided software will be

    performed and a full end-to-end test will be performed, including the final development and

    documentation of the VBI installation and alignment plan.

    The Shipping release will culminate in the VBI readiness review where the VBI team will demonstrate

    complete compliance of the VBI instruments to the VBI Compliance Matrix CMX-0001. The review will

    include a detailed test, installation, and alignment plan as developed during the Speckle and Shipping

    phases. Installation and operations manuals will be deliverables at the readiness review.

    The Shipping release is scheduled for October 2016.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 36 of 45

    5.2.8 IT&C Phase

    Upon arrival at the telescope, the VBI instruments will be re-assembled in the instrument lab and the test

    plan used for the readiness review will be repeated to ensure instrument readiness. Following these tests,

    the VBI instruments will be installed into the Coude Lab as the first light ATST instruments. Training of

    the operations staff will take place. Testing of the VBI channels will be repeated and proof that the

    instruments meet the VBI Compliance Matrix CMX-0001 will result in operational readiness acceptance.

    Upon proof of operational readiness, as defined by demonstration that both VBI channels are compliant

    with the compliance matrix, the VBI team will have concluded their responsibilities to the project, and the

    instruments will become the responsibility of the ATST project and will be handed over to the science

    staff for science verification. At this point, the VBI instruments will be considered ATST facility

    instruments.

    5.2.9 Science Verification

    The science verification plan is detailed in SPEC-0107 VBI CDD.docx. Science verification will test the

    VBI instruments against the top-level science objectives for the instruments. Successful science

    verification will result in the VBI being accepted for operation, at which point, responsibility for the VBI

    instruments will be transferred to ATST Operations.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 37 of 45

    6. BUDGET

    The VBI red construction budget is broken into three work packages: procurement (S-WANS3-222),

    construction (S-WANS3-223), and integration / test / commissioning (S-WANS3-226). The top-level

    budget is shown in Table 2 and the details are broken out in the tables that follow.

    VBI-red Top Level Budget

    S-WANS3-222 - Fabrication Drawings / Project Management $48,704

    S-WANS3-222 - Filters $117,270

    S-WXNS3-222 - Optics - Lenses / Mirrors $97,120

    S-WANS3-222 - Controls & Mechanical $87,179

    S-WANS3-223 - Construction $31,775

    S-WXNS3-226 - Integration / Test / Commission $290,373

    Total $672,422

    Table 2

    6.1 LABOR

    Labor for the VBI is shown in Table 3. Upon a successful CDR, a change request will be submitted to the

    project to encumber labor for the procurement, construction, and integration / test / commissioning phases

    of the VBI red. Considerable savings in labor are achieved by “catching up” the construction of the red

    channel to the blue channel, allowing for both to be assembled and tested together.

    Workpackage Labor Start date End date

    S-WANS3-222 Fabrication Drawings / Project

    Management

    $48,704 Sep-12 Apr-14

    S-WANS3-223 Fabrication / Assembly $31,775 Sep-12 Jul-13

    S-WXNS3-226 Test / IT&C $290,373 Jan-13 Feb-19

    Total $370,852

    Table 3

    6.2 FILTERS

    The VBI filter cost is shown in Table 4. The fourth filter wavelength has not yet been determined, but the

    Science Working Group is expected to recommend a suitable wavelength by the end of 2012. This filter

    is expected to be similar to the Red Continuum filter and is priced accordingly.

    Filter Wavelength Cost

    Hα 656.282 nm $51,540

    Red Continuum 668.4 nm $22,380

    TiO 705.8 nm $20,970

    TBD TBD $22,380

    Total Total $117,270

    Table 4

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 38 of 45

    6.3 OPTICS

    The VBI blue CDR committee recommended the procurement of the optics blanks early to mitigate

    availability and price risk. The objective lens blank has been procured as risk mitigation. The other

    lenses use commonly available glass and the procurement will begin immediately upon successful

    completion of the CDR.

    The vendor that is manufacturing the VBI blue lenses has quoted the lenses for the VBI red. We were

    able to have the vendor hold the manufacture of the blue lenses to wait for the red lenses. The lenses are

    very similar to the blue lenses (the objective lens is identical with the exception of the coatings). By

    holding the procurement of the blue lenses, the blue and red lenses can be manufactured together at a cost

    savings.

    The VBI blue lens cost is $83,550; the price of the red lenses was brought down to $74,530, a savings of

    $9,020.

    Lenses $69,750

    Objective blank $4,780

    Fold mirror 1 $12,040

    Fold mirror 2 $700

    2nd objective lens $9,850

    Total $97,120

    Table 5

    6.4 CONTROLS & MECHANICAL

    The camera is provided by the Project. The control, thermal, and electrical systems are identical to the

    blue channel and the mechanical assemblies are identical with the exception of the first fold lens mount

    and filter wheel as described in section 3.

    Camera project

    Control System $39,436

    Thermal system $1,102

    Electrical (from electrical sheet) $7,195

    Mechanical (from mechanical sheet) $39,446

    Total $87,179

    Table 6

    6.5 DATA HANDLING SYSTEM AND SPECKLE IMAGE RECONSTRUCTION

    The addition of the VBI red instrument to the ATST instrument suite adds another channel to the Data

    Handling System (DHS); this extra channel has already been included in in the DHS design and budget.

    The DHS speckle reconstruction hardware was originally sized and budgeted to fully reconstruct every

    burst of a single channel of VBI data. The speckle hardware was later de-scoped to provide near-real-

    time reconstruction of every third burst of a single channel of VBI data, with the remaining bursts being

    reconstructed over-night. This plan would have provided the horsepower for a reconstructed image

    approximately every 9 seconds.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 39 of 45

    But, between the expected advances in GPU hardware and recent successes by the VBI team in speeding

    up the core reconstruction algorithms, the VBI team hopes to obtain higher performance from the

    budgeted GPU hardware than originally anticipated. Continued development of the parallelization of the

    speckle algorithms is ongoing, and it is difficult to predict the final capability of the reconstruction

    engine, but the team is hopeful that it will be possible to reconstruct every 2nd

    or 3rd

    burst of both VBI

    instruments simultaneously. This will produce one reconstructed image every 3 to 4.5 seconds. It is also

    important to note that the system is scalable, allowing improved performance with the simple addition of

    more GPU blades in the speckle hardware system in the future.

    6.6 BILL OF MATERIALS

    Qty Part Description Filters

    1 Hα

    1 Red Continuum

    1 TiO

    1 TBD

    Optics

    1 Objective Lens

    1 FM1 254mm Flat Mirror

    1 Field Lens

    1 FM2 100mm Flat Mirror

    1 Collimator Lens

    1 Image Lens

    1 2nd image lens

    Mechanical Components

    1 Objective Lens Mount (275mm)

    1 Fold Mirror 1 Mount (254mm)

    1 Field Lens Mount (50mm)

    1 Fold Mirror Mount 2 (150mm)

    1 Collimator Lens Mount (75mm)

    1 Collimator stage

    1 Collimator stage bench mount

    1 Collimator stage motor

    1 Filter Wheel

    1 Filter Wheel Assembly Tool

    1 Imaging Lens Mount (75mm)

    1 Camera mount

    1 Camera stage x/y bracket

    2 Camera stage

    2 Camera stage motor

    1 Camera stage bench mounting plate

    28 Optical bench hold-down mounts w/ hardware

    1 Proportioning valve

    2 Coolant hoses

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 40 of 45

    Optical bench cables

    1 Collimator Stage motor cable

    1 Collimator Stage encoder cable

    1 Collimator Stage limit switch cable

    1 Collimator Stage brake cable

    1 Filter Wheel Motor cable

    1 Filter Wheel Encoder cable

    1 Proportioning valve cable

    1 Temperature sensor cable

    1 Camera x stage motor cable

    1 Camera x stage encoder cable

    1 Camera x stage limit switch cable

    1 Camera x stage brake cable

    1 Camera y stage motor cable

    1 Camera y stage encoder cable

    1 Camera y stage limit switch cable

    1 Camera y stage brake cable

    Control System

    1 Instrument computer

    1 Instrument computer monitor

    1 Instrument computer keyboard

    1 Instrument computer mouse

    1 24V power supply

    1 24V distribution panel

    1 Delta Tau UMAC controller chassis

    1 UMAC power supply

    1 Power PMAC card

    2 4 axis PWM card with quadrature encoder reader

    1 Universal serial card with BISS reader

    1 Delta Tau UMAC drive chassis

    2 Dual 4A motor Amp

    1 8A motor Amp

    1 Regeneration resistor

    1 120V power distribution strip

    Control system cables

    4 PWM cables

    3 24V drive cables

    1 Copley 24V Amp

    1 Copley PWM cable

    1 Copley 24V cable

    1 208/120V power cable

    3 IEC 320 power cable

    1 USB cable

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 41 of 45

    1 Misc. 24V cables to encoder cards

    Coude Lab Bench

    1 Optical bench

    4 Optical bench legs

    4 Optical bench beam support interface clamps

    1 Optical bench seismic restraint kit

    2 Optical bench power distribution strip

    1 Optical bench cable raceway / wiring tray

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 42 of 45

    7. SCHEDULE

    The supplemental documents contain an excerpt from the ATST project schedule containing only those

    items that pertain to the VBI red and blue instruments. The dependencies on the other aspects of the

    project, particularly the telescope software systems, were presented in the VBI blue CDR and remain

    unchanged except for minor schedule adjustments.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 43 of 45

    8. HAZARD ANALYSIS

    The Hazard analysis for the VBI blue is also applicable to the VBI red, since the designs are almost

    identical. Please refer to SPEC-0107 VBI CDD.docx for the blue channel hazard analysis.

    The only hazard identified as being different from the VBI blue channel is the glint hazard, since the

    power density in the red beam is higher than the power density in the blue beam primarily due to the

    broader wavelength range. Table 7 shows the glint hazard analysis for the red channel of the VBI at the

    focus. Blink time is assumed to be 250ms, so the risk of eye damage is minimal. Worst-case values were

    used for these calculations.

    An additional point, which is the result of overlapping the blue and red channel optics on the same

    benches, is that the focal points of the beams are now physically difficult to get to. In the original blue

    channel design, it was conceivable that a person could put their eye into the beam, but with the current

    design, a person would have to lie on a busy optical bench to get their eye into a focus.

    Specific Heat Capacity

    Substance cp [J·g−1·K−1] density [g·cm−3]

    Skin 3.48 1.2

    Power at VBI Focus [W] 13.305622

    Diameter of VBI Focus [cm] 4.3

    Power / area at VBI Focus [W·cm-2] 0.916238188

    Skin Area considered [cm2] 1

    Skin Depth considered [cm] 0.1

    Skin Volume considered [cm3] 0.1

    Skin Mass considered [g] 0.12

    Minimum Time regarded safe [s] 20

    Maximum Temperature

    increase regarded safe [K] 4

    Time to critical increase [s] 1.823106722 Hazard

    Table 7

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 44 of 45

    9. PROJECT MANAGEMENT

    The VBI blue CDR committee recommended that the VBI be treated as a subcontractor with the

    implementation of clear interfaces between the project and the VBI team. The committee also

    recommended the implementation of earned value tracking to detect cost and schedule variances. Both of

    these recommendations have become a reality for the VBI blue and red instruments. Formal procedures

    for change requests, technical directives, and controlled interfaces documents have been established. In

    addition, a project-wide earned value system has been implemented; the VBI budgets and schedule

    updates are input into the system monthly; monthly variance reports are generated, and this enables

    accurate budget and schedule tracking.

    The VBI red WBS can be seen in the project schedule. The Fabrication of the VBI components will take

    place in the Sunspot machine shop where Scott Gregory will supervise the machining and assembly of the

    sub-assemblies. Bill McBride and Andy Ferayorni will take the sub-assemblies (with the exception of the

    optics) to the Tucson instrument lab for software testing and qualification. The sub-assemblies will also

    be tested with the ATST high level software systems being developed in Tucson.

    Final instrument assembly will take place in either Sunspot (where the Hilltop lab, Dunn telescope, and

    Sunspot Instrument lab are available) or in the new labs being constructed in Boulder.

    The final instrument cameras will be delivered to the VBI team by the project in early 2016. Integration

    of the cameras into the VBI instruments and final verification will take place in either Sunspot or Boulder.

    Following final verification, the VBI instruments will be transported to Hawaii to be integrated into

    ATST as the first light instruments. See section 5 for further details.

  • VBI-R Critical Design Definition

    SPEC-0126, Rev A Page 45 of 45

    10. RISK ASSESSMENT

    ATST Spec 37 defines the project approach to risk analysis and mitigation. A summary of the approach

    can be found in SPEC-0107 VBI CDD.docx.

    10.1 VBI RISK REGISTER

    The VBI red risk register spreadsheet (provided as a separate document) contains a distillation of the

    unmitigated risk items for the VBI red instrument from the ATST project risk register.

    The primary risks to the VBI red instrument remain the manufacturability of the filters, the cost and

    feasibility of the speckle reconstruction engine, key person loss, and shipping damage. Additionally, the

    project carries risk with the integration of the instrument into the facility.

    All of these risks are being mitigated with early development and integration of the VBI instruments. In

    addition, the VBI has been selected as the early first-light instrument to work through integration

    problems at the summit earlier than was previously planned.