114
Guide for the Preparation of Investment Analysis Reports Prepared for: Accommodation & Portfolio Management Public Works & Government Services Canada January 2009

· Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

  • Upload
    dothuy

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Page 1: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Guide for the Preparation of Investment Analysis Reports

Prepared for:Accommodation & Portfolio Management

Public Works & Government Services Canada

January 2009

Page 2: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently
Page 3: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Table of ContentsChapter 1.0 Overview..........................................................................1

1.1 Objectives, Scope and Benefits...........................................................11.2 Principles for the Preparation of IARs................................................21.3 Purposes of Investment Analysis Reports...........................................31.4 Approval Authorities...........................................................................41.5 Project Approval..................................................................................41.6 The Role of Investment Boards (RPIB and RIMB)..............................61.7 Regional Roles, Responsibilities and Accountabilities........................61.8 Project Responsibilities and IAR Preparation.....................................71.9 Role of the Analyst Carrying Out the Investment Analysis.................71.10 Sources, Tools and References...........................................................8

Chapter 2.0 The IAR Preparation Process.......................................132.1 The National Project Management System and the Role of the IAR 132.2 The Strategic Context for IAR Preparation.......................................142.3 Preparing an IAR...............................................................................162.4 New Approaches to Investment Analysis..........................................182.5 Preparation of Treasury Board Submissions.....................................19

Chapter 3.0 Guidelines..............................................................................213.1 Key Guidelines and Criteria for a Well-Written IAR.........................213.2 Meeting Timing Requirements..........................................................223.3 Strategy for Approaching the Preparation of an IAR........................233.4 Quality Assessment Criteria..............................................................243.5 Proposed Outline of an IAR...............................................................26

Chapter 4.0 IAR Template.........................................................................27Executive Summary................................................................................................... 27

1 Problem/Opportunity Definition........................................................282 Background ................................................................................293 Project Scope ................................................................................324 Identification and Analysis of Options..............................................345 Strategic Impact...............................................................................396 Recommendation ............................................................................417 Approval Authority and Funding.......................................................438 Implementation Plan ........................................................................439 Project Team & Signatures...............................................................4510 Appendices........................................................................................45

Page 4: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Appendix A: The Investment Analysis Process..........................................48Appendix B: Space Entitlement Based on the Office Accommodation Framework 58Appendix C: Sustainable Project Delivery................................................60Appendix D: Terminology Used in Real Property Management...............70

Page 5: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Chapter 1.0: Overview1.1 Objectives, Scope and BenefitsObjectives This Guide was originally developed at the request of the Investment Management

Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently revised in 2005 to incorporate recent developments such as the fit-up and space allocation standards, improved risk management and the analysis of sustainable development issues.

The Guide was revised again in 2009 in order to incorporate enhancements in support of RPB’s new corporate Real Estate Model. More specifically, revisions were made to encourage the consideration of a wider range of investment options, such as, public-private partnerships, to improve the qualitative and quantitative consideration of risk and to improve the overall quality of IAR submissions.

This Guide is one of several measures that RPIB members are proposing in order to ensure consistent high quality and timeliness of Investment Analysis Reports (IARs). Stated more formally, the purpose of this Guide is to strengthen the role of IARs as information, approval, accountability and performance measurement documents, for meeting client requirements and ensuring the integrity of real property assets. This Guide represents RPIB’s position on how IARs should be written, both in terms of style and organization, and what information they should contain, in order for these executives to take an informed decision. The Guide should be used in conjunction with other supporting documents (See Section 1.10 for Sources, Tools and References).

Scope This document provides a guide for all persons who have responsibility whether it

be in the preparation of, contribution to, or in reviewing any type of Investment Analysis Report.

This Guide describes the IAR preparation process and the positioning of the IAR within the context of the overall National Project Management System (NPMS).

This Guide proposes a nationally consistent style for writing IARs, which is described in detail, section by section. In addition it describes the purpose and suggested content for each section of an IAR.

This Guide focuses on the preparation of Investment Analysis Reports for the national Real Property Investment Board and Regional Investment Management Boards (RIMB). It is intended for the use in both asset-based and space-based IARs for projects with a total estimated cost of more than $1.0 million. The depth and length of an IAR should be adjusted to fit the circumstances of each project. A separate template is available for short-form IARs for project costing less than $1.0 million.

- 1 -

Page 6: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

As per the NPMS, the IAR is the internal control point approval document for the Analysis Phase to obtain Preliminary Project Approval or Lease Project Approval, and Design Phase Approval Document for Effective Project Approval. Content in the IAR is intended to be built upon the approved NPMS deliverables. Specific references have been made in the IAR Template in Chapter 4 to materials, which are intended to be brought forward from the previous NPMS deliverables and included in the IAR (i.e. Statement of Requirements, Project Plan, Feasibility Report, and Project Charter). It should be noted that as per the NPMS procedure, not all of these deliverables are required for all projects. These exceptions are not referenced in this guide and reference should be made to the NPMS Procedure.

BenefitsFor writers and contributors to IARs, this Guide offers the following benefits: facilitates the involvement of a wider group of persons in preparing and

contributing to the preparation of IARs eases the process of initiating an IAR for a project increases the efficiency in which IARs are prepared, thereby, also decreasing the

elapsed time in their preparation increases the probability of “doing it right the first time”—fewer drafts and redrafts provides a handy reference for reaching the desired standard of quality in the IARs

of the Real Property Program offers users a handy guide to relevant sources of information

1.2 Principles for the Preparation of IARs This Guide for the Preparation of Investment Analysis Reports (IARs), is supported by the RPIB and RIMB and is designed to facilitate the process of preparing IARs. The IARs that are responsive to the principles below provide an assurance that the required consultations have been made and relevant interests have been taken into account; they also achieve a high degree of quality and better support the decisions that have to be made. Consistent in terms of organization (without being rigid or inflexible); this includes

the use of headings and sub-headings, and the placement of appropriate information in appendices; see Section 3.5, Proposed Outline of an IAR;

Consistent in terms of style and tone; well-written IARs are factual and objective; see Section 3.1 Key Guidelines and Criteria for a Well-Written IAR;

Concise; the IAR presents only relevant information and data, and does so in a manner that is brief and to the point; more extensive information is presented in the Appendices, if required;

Compliant; the IAR indicates if the proposed project complies with the national and community-based investment strategies, the relevant Asset Management Plan(s), the ARLU and budget allocations;

- 2 -

Page 7: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Reliable; the IAR clearly documents the requirements, the time constraints, the implementation strategy, the issues and risks associated with a given course of action;

Valid; the options presented to the RPIB and RIMB for consideration include all viable options, that are well described and continue to be feasible;

Precise; the scope, components, costs, impacts, implementation strategy, and issues surrounding the recommended option are precisely described;

Timely; the RPIB and RIMB receives the IAR for review at a point when due deliberation is possible and severe time constraints are not dictating the agenda.

In addition to the above attributes, it is important that the approach to investment analysis reflects the principle, which states that the overriding objective is always to maximize the long-term benefits of the federal government as a whole. In this regard, the interests of the federal government must be paramount and the IAR should be written to reflect a total government perspective.

1.3 Purposes of Investment Analysis Reports By definition, IARs are future oriented and help to create RPB’s “contract with

the future”. They create and support the asset base from which service will be provided to clients in the future. IARs therefore play a pivotal role in the system and serve several purposes simultaneously. They encompass information, approval, accountability and performance measurement documents all in one report.

IARs are information documents. They provide consistent, concise, reliable, precise and timely information on a specific real property context, and on a range of options facing the Real Property Branch for meeting client and asset integrity requirements. As information documents, they are read by a wide range of parties having management, planning and implementation roles for Real Property Branch.

IARs are approval documents. They enable the RPIB and RIMB to make recommendations and senior management to make decisions on future courses of action. IARs facilitate and support decision-making and are used to identify a preferred course of action to provide a relevant rationale and to fully inform the RPIB, the RIMB and RPB senior management of all relevant implications pertaining to the selected course of action.

IARs are accountability documents. They crystallize and confirm organizational accountabilities. Through the signature of the originating authorities, IARs indicate the agreement of team members, particularly those that have to implement the project and confirm the accountabilities of specific persons for the quality of the information provided in the IAR. Simultaneously, IARs are the vehicle whereby accountability for projects and initiatives are assumed at all levels within the Real Property Program — up to the level of the Assistant Deputy Minister of Real Property Branch. Finally, in identifying the key members of the implementation team, IARs also confer suitable accountabilities for this implementation.

IARs are performance measurement documents. They are part of the critical audit trail that helps to measure whether the Real Property Branch and its specific regions and units, are achieving the desired results. More specifically, IARs provide

- 3 -

Page 8: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

a critical reference point in assessing project and program performance after project completion, for example, in terms of timing, cost and measuring actual results against expected project financial and qualitative benefits (eg. sustainability).

1.4 Approval AuthoritiesThe mandate of PWGSC’s Real Property Branch is to provide office accommodation for federal government departments. Consequently, PWGSC is responsible for seeking project approval associated with the provision of office accommodation.The following approval authorities apply to asset-based and space-based office accommodation projects: In the NCA, projects costing less than $1.0 million are typically approved by the

Real Property Team Director, based on a short-form IAR. In the regions, smaller projects are approved by the Regional Director with the approval limits subject to regional delegations of authority. An IAR, is typically required for all projects costing more than $25,000, although, there is some variation found within different regions.

Projects costing up to $10.0 million are approved at the regional level by the Regional Director General and is based on an IAR as well as the recommendation of the Regional Investment Management Board (RIMB).

Projects costing up to $30.0 million are approved at the Headquarters level by the ADM of the Real Property Branch, and based on the IAR and the recommendations of the RIMB, RDG and the Real Property Investment Board (RPIB).

Currently, projects costing over $30.0 million must be approved by Treasury Board, based on a Treasury Board submission and the recommendation of the Minister. Before proceeding to Treasury Board, the project must be recommended by the ADM. The ADM’s recommendation is based on an IAR and the recommendations of the RIMB, RDG and the Real Property Investment Board (RPIB). It should be noted that, under Treasury Board’s new Policy on the Management of Projects, project approval limits would soon be based on the risk and complexity of individual projects and the capacity of the department or agency to manage projects, rather than on a dollar value threshold.

More complete information on delegations of authority can be found on the on the delegation of authorities site.

1.5 Project ApprovalsThere are three types of project approval that can be sought through an IAR: preliminary project approval (PPA), effective project approval (EPA) and lease project approval (LPA). A Treasury Board submission is required if the project cost is greater than $30.0 million (for accommodation projects). Preliminary Project Approval (PPA): PPA is sought as part of the project

identification phase, and is required to enable RPB to undertake detailed technical investigations and to disburse the funds necessary to get more precise cost estimates and to support the full definition of the project. An IAR seeking PPA must

- 4 -

Page 9: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

clearly demonstrate that a program requirement exists and that this requirement can be addressed through the implementation of the proposed project. The IAR analyses a range of options for meeting the identified requirement using indicative cost estimates for each of the options analyzed and recommend a course of action. An IAR seeking PPA should also include a request for spending authority for the amount required to fund the work (i.e. engineering investigations and architectural planning) carried out in the project definition phase, with the amount requested being supported by substantive cost estimates.

Effective Project Approval (EPA): EPA is sought once the project definition has been completed, substantive cost estimates have been developed, and the project is ready to be fully implemented. The granting of EPA provides the authority to proceed with the implementation of the project and establishes the critical objectives for the project in terms of cost, scope and timing. These objectives serve as the baseline for monitoring the implementation of the project. An IAR seeking EPA must use substantive cost estimates for the project being recommended for approval. It should also re-examine all of the available options previously identified in order to ensure that the recommended option is still the most beneficial approach for meeting the requirement.

Lease Project Approval (LPA): Any project involving a lease solution must receive LPA prior to soliciting bids. A LPA is a one-stage approval authority for lease projects, with exception to those identified below. For the purpose of determining the appropriate approval levels for lease projects, project cost is defined as the present value of net rental costs over the term of the lease (not including options), plus all one-time costs (such as fit-up) associated with bringing the property into inventory. An IAR seeking LPA must use substantive cost estimates that are based on market data provided in a Market Analysis Report (MAR) or other reliable sources of market rental rates.

Approvals for Lease Projects Involving a New Building: In the case of a lease project that will result in the creation of a new building via a P3 delivery (example: build to lease and lease purchase), a PPA is required for spending authority to run the procurement process, followed by an EPA once the procurement/solicitation of offers process is complete. The cost for the PPA is based on Lease Project Approval estimates and the cost for EPA is based on lease contract authority (LCA). The LCA amount is the total amount that will be paid to the landlord over the term of the lease (not discounted to their present value), including fit-up, O&M and taxes if these are passed through the landlord, expressed in budget year (year of disbursement) dollars.

Classes of Estimates: Cost estimates must be of a sufficiently high degree of quality and reliability to support the consideration of the project by decision makers and allow the options analysis, included in the IAR, to be meaningful. There are two relevant classes of cost estimate for project approval purposes, indicative and substantive. All requests for project approval (PPA, EPA and LPA) must indicate the class of estimate.

Indicative estimate: This is an estimate of project costs that is sufficiently refined to allow the comparison of options in an IAR seeking PPA but is not, however, sufficiently reliable to be used as a cost objective when seeking EPA.

- 5 -

Page 10: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

An indicative estimate is prepared by a person with suitable technical expertise and is based on the operational statement of requirement and on an initial assessment of the facilities. The assessment would meet the requirement as well, however, would not include engineering investigations or design work.

Substantive estimate: This is an estimate of sufficiently high quality and reliability to warrant approval as a cost objective in support of a request for EPA or for any request for spending authority. A substantive estimate is based on a detailed system, component designs and work plans. Cost estimates must include all employee salaries charged to the project, including employee benefits, as well as other costs of government project management.

1.6 The Role of Investment Boards (RPIB and RIMB)The Real Property Investment Board (RPIB) functions as the project recommendation board at the national level, while Regional Investment Management Boards (RIMB) performs the same function at the regional level. The function of these boards, at both the regional and national levels, are to oversee the review of planned real property investments within PWGSC, as well as the allocation of funds in the budget. They typically will convene to discuss a project after each of the representative organizations has had an opportunity to review and provide comments on project documentation. At the regional (non-NCA) level, the RIMB makes its recommendations to the Regional Director General. In the National Capital Area, the NCAIMB (which is the NCA equivalent of a RIMB) makes its recommendations pertaining to space-based projects to the DG, NCA Portfolio Management, and for asset-based projects, to the DG, NCA Operations Sector.The national RPIB is a committee composed of senior officials of PWGSC’s Real Property Branch. Chaired by the Director General of Accommodation & Portfolio Management, the RPIB is charged with, among other responsibilities, reviewing and making recommendations on all IARs that are above the delegation of authority of PWGSC regions. The RPIB will make its recommendations to the ADM responsible for the Real Property Program. If the RPIB or RIMB is prepared to recommend a project, it is typically passed along the approval chain to the RDG in the region (or the NCA equivalent), the ADM, the DM, the Minister’s Office and Treasury Board, as appropriate. The Board may also refuse to recommend a project or it may ask the project team to make changes in order to make the project acceptable when it comes back to the Board for review.In addition to its vetting, review and recommendation role, RPIB and RIMB also have an advisory and coaching role. Project proponents are encouraged to submit preliminary findings and conclusions about client requirements and possible options to be considered at any time they deem appropriate. Such preliminary discussions may assist officials in evaluating the factors governing the context of a given client requirement and may help in focusing on appropriate options for consideration.

- 6 -

Page 11: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

1.7 Regional Roles, Responsibilities and AccountabilitiesFor most IARs, regions will generally be the originators of the investment proposal and will see the proposal through to its ultimate approval and implementation. Thus, the regions are responsible and accountable for the full development and management of all investment analysis documents, including all of the technical aspects of the investment decision-making process, options analyses, document preparation and information management. Within the regions, Regional Directors of Accommodation and Portfolio Management are responsible for IAR document development and have overall accountability for document review and sign off prior to the IAR proceeding to RIMB and the Regional Director General.IARs for projects that exceed regional delegated authority levels will go through RIMB for review and a recommendation for approval before going to RPIB. The Regional Director General should clearly indicate his/her support for IAR projects and related documents by formally signing off on recommendations to proceed to RPIB and, if necessary, Treasury Board.For IAR documents requiring RPIB recommendation, the involvement of Headquarters staff is primarily focused on reviewing the authorities requested, the financial analysis of options, risk analysis, corporate initiatives, and linkages to strategic/national portfolio planning direction. RPB Headquarters staff is responsible for the finalization of documents that are submitted to the ADM, the Minister or Treasury Board, and are the main contact point for Treasury Board Secretariat (TBS) staff.

1.8 Project Responsibilities and IAR PreparationThe preparation of an IAR generally involves the efforts of a team of people. Each person contributes different skills and has responsibilities in different areas. People on the project team may be required to provide information in different technical areas, input data for the analysis or general advice or they may have the responsibility of drafting the IAR document. The following identifies the key responsibilities / accountabilities of the project leader and the project manager: Project leader - The project leader is responsible for identifying project

requirements (scope) and for providing funding and overall leadership for the project. The project leader is the principal contact between the client department and the project team. The project leader consults the owner/investor for projects funded by PWGSC. For projects not funded by PWGSC (e.g., custodial departments), the client acts as the project leader.

Project manager - The project manager is responsible for the management of all activities related to the delivery of the project within established project requirements and budgets.

Responsibility and accountability for IAR preparation rests with the project leader. While this responsibility may at times be delegated to another member of the project team, ultimate accountability for the completeness and quality of the document still rests with the project leader.

- 7 -

Page 12: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

1.9 Role of the Analyst Carrying Out the Investment Analysis The analyst (the person carrying out the investment analysis and preparing the IAR) works under the direction of the Project Leader. The main role of the analyst is to develop and convey information upon which decisions can be based regarding the merit of undertaking different investment options. In addition to considering a number of key financial variables, the investment analyst must also take into consideration risk and a host of qualitative factors, which complicate the real property decision-making process. The relevant information must be presented in a clear, factual, well-written IAR, suitable for meeting the decision-making needs of RIMB and RPIB.Consistent with the Treasury Board Guide to the Management of Real Property, the analyst at PWGSC must plan to make balanced investments that meet program needs while fulfilling other policy requirements. Investment decisions must consider all costs and aspects of the life cycle of the real property asset, from acquisition and construction through maintenance, payments-in-lieu of taxes, renovation (capital reinvestment) and disposal.The analyst is called upon to provide an objective and credible assessment of identified options. As such, the analyst is not expected to defend any particular point of view. Rather, he or she is expected to outline the complete costs, benefits and disadvantages associated with any particular option in an objective fashion, including options and/or decisions, which may have been defined at the political level.

1.10Sources, Tools and ReferencesThe process of preparing an IAR is potentially complex and involves many steps. Among the variety of considerations, there are numerous Treasury Board and PWGSC policies, as well as departmental strategies, which can impact project planning, investment analysis and the preparation of the IAR. In a successful IAR, relevant policies, strategies and practices are taken into account, all aspects of the analysis must be done correctly and the required elements of the IAR must be systematically addressed.Fortunately, there are many aids and sources of advice available. The following sources, tools and references that can be used are identified as follows:

Sources: The preparation of IARs should involve the combined efforts of a team of people who

represent different sectors and disciplines, and are assembled for the purpose of planning the project, considering all options, undertaking the investment analysis and preparing the IAR. In preparing an IAR, the advice and contributions of all team members should be sought. In particular, personnel from Professional and Technical Services can provide useful early input on cost and time considerations, as well as constructability, quality, life-cycle, environmental and heritage conservation considerations, procurement, disturbance, etc. Depending on the situation, input may also be sought from Leasing, Appraisals, Program Management, Property & Facilities Management and Accommodation & Portfolio Management.

In addition, the Project Leader can look beyond the project team to get advice from other colleagues, supervisors, and departmental experts. One such source of

- 8 -

Page 13: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

expertise are the Investment Analysts in the Accommodation and Portfolio Management Directorate. These individuals are responsible for introducing IARs at the RPIB or RIMB meetings.

Tools: National Project Management System (NPMS): The NPMS is a project

management process with control points (approval stages), deliverables and a consistent structure of stages and activities. All real property projects must comply with the NPMS. The NPMS includes three important tools: knowledge areas (a description of PWGSC expectations for specific subject areas), road maps (a description of inputs, activities and outputs by project type) and the Project Plan (a document that collects project information at each control point and provides a consistent tool for monitoring the project).

Financial Analysis (REFIT): An important tool for the preparation of the financial analysis in an IAR is the REFIT computerized spreadsheet software package. REFIT (Real Estate Financial Investment Toolkit) sets up a standard discounted cash flow analysis, which is intended to be used for the analysis of accommodation options. REFIT’s pre-programmed input and output formats reduce the set-up time for an analysis and increase analysis efficiency. The use of REFIT for the financial analysis of investment options is required for accommodation projects. Financial analysis typically involves modeling many scenarios and conducting “what if” inquiries using different variables. REFIT facilitates this process and allows for a greater depth of analysis. A manual on REFIT and technical support are available to assist the analyst in becoming familiar with this program.

Investment Analysis PolicyThe Investment Analysis Policy of the Real Property Branch provides a basic framework for investment analysis and decision-making. Some of the provisions of this policy include:

Investment analysis will be consistent with the objectives, principles and strategic direction of the National Investment Strategy.

Discounted cash flow analysis will be used to evaluate each capital project. Each capital project must meet or exceed a hurdle rate of return over its investment

horizon, unless it can be justified on other than financial grounds. Investment analysis of each capital project will include an analysis of all reasonable

options available to meet project requirements. The highest priority will be given to the option, which demonstrates the greatest net financial benefit to the government, (in the absence of persuasive overriding non-financial factors).

Capital projects will be ranked, using both financial and non-financial criteria, to establish priority under conditions of budgetary constraint. [Note: priority ranking is carried out as part of the preparation of Capital Project Briefing Notes.]

Other Policies, Plans and StrategiesThere are many other sources of information, which the analyst can turn to for guidance on investment analysis, or related policies, strategies and practices. Later

- 9 -

Page 14: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

sections of this Guide, which discuss the writing of particular sections of an IAR, identify relevant reference materials for each section. Key reference documents include the following:

National Investment Strategy (NIS): The NIS defines national investment priorities as well as the Branch’s approach to managing its portfolio. Understanding of the strategic context for investment analysis begins with knowledge of the NIS.

Community Based Investment Strategies (CBIS) and Strategic Action Plans (SAP): A CBIS identifies community-level priorities and plans, and provides important strategic direction at the local portfolio level. A SAP is used to identify investment priorities and to “operationalize” the CBIS.

National Portfolio Plan (NPP): The NPP is an action plan that lays out what will be done within the national portfolio in order to achieve the desired state of the portfolio.

Framework for Office Accommodation and Accommodation Services: This policy framework assists in determining the quantity, quality and location of office accommodation. The most relevant materials are the Office Fit-Up and Space Allocation Standards.

Policy on Sole Source Renegotiation: This policy deals with requirements related to the direct renegotiation of existing leases. In particular, the policy identifies six principles that must be addressed when seeking approval for the direct renegotiation of an existing lease, including the negotiation schedule, which must demonstrate sufficient time for the implementation of an alternative strategy if negotiations are not successful.

Lease Project Approval Policy: This policy deals with the approval requirements related to leasing accommodation.

Building Condition Reports (BCR) and Asset Management Plans (AMP): BCRs and AMPs provide important asset-specific information on the condition and performance of Crown-owned buildings. The BCR is prepared by technical specialists and provides a comprehensive report on deficiencies in the building and the cost of correcting them. The AMP identifies issues related to the condition and the operating, functional and financial performance of the building, makes recommendations on how performance could be improved and recommends a strategy for the future ownership of the building.

Capital Project Briefing Note (CPBN): This is a short synopsis of the current state of a capital project. It is generally prepared once a project is contemplated and must summarize the results of the priority ranking exercise. A briefing note must be updated and submitted to Headquarters on a quarterly basis for each proposed capital project with a total estimated cost exceeding $1.0 million.

Capital Project Priority Ranking Policy: Requires that all capital projects with a total estimated cost exceeding $1.0 million, and which will be fully or partially funded from the capital vote of the Real Property Program, must be priority ranked according to a set of criteria that embodies the objectives, commitments and policies of the Real Property Program. Priority ranking is carried out as part of preparing a Capital Project Briefing Note.

- 10 -

Page 15: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Sustainable Development Strategy (SDS): This strategy sets out the department’s approach to sustainable development. With respect to real property, the strategy is intended to make PWGSC a leader in sustainable buildings for its entire portfolio, both owned and leased.

Canadian Environmental Assessment Act (CEAA) Project Checklist: The CEAA and its regulations are the legislative basis for the federal practice of environmental assessment. PWGSC has established a CEAA Checklist process that ensures all projects are assessed for their applicability to the Act. The CEAA Checklist process is the mechanism by which PWGSC Environmental Services determine if an environmental assessment is required and ensure that the assessment is conducted in a timely and effective manner. By completing and sending in a CEAA Checklist, at the initiation of the project planning, project proponents will ensure that PWGSC projects are evaluated for the applicability of CEAA.

Good Neighbour Policy: This policy requires PWGSC to consult with and to consider the plans, priorities and objectives of local municipal governments as part of its decision-making process.

Heritage Policy: It is government policy to respect and conserve the heritage character of federal buildings. Under this policy, buildings forty (40) years old or older must be identified to the Federal Heritage Buildings Review Office (FHBRO) for evaluation. Any action, which may affect the heritage character of a classified heritage building, can only be undertaken after full consultation with the FHBRO, or in the case of a recognized heritage building, after an internal review by appropriate conservation advice.

Accessibility Policy: It is a PWGSC and government policy to ensure barrier-free access to and use of real property, owned or leased. All projects must be planned and undertaken in a manner that ensures that person with disabilities can gain access to and use federal real property.

Government of Canada Fit-up Standards: These standards strengthen the principles for delivery of fit-up projects and also confirm and clarify the accountability for funding various fit-up components. In addition, the set standards place emphasis on PWGSC's responsibility to apply rigour in the provision of a standardized quantity and quality of fit-up for government departments and agencies.

Custodial Parking Policy: The objective of this policy is to ensure an understanding of the custodial responsibilities for parking of the Real Property Branch of PWGSC.

- 11 -

Page 16: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

- 12 -

Page 17: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Chapter 2.0: The IAR Preparation Process

2.1 The National Project Management System and the Role of the IAR The National Project Management System (NPMS) is PWGSC’s methodology for

delivering real property projects on scope, on time, and on budget. The NPMS is intended to be a comprehensive project delivery system that assists in the management of the project from its initial inception through to its final completion. By identifying control points and deliverables at logical steps throughout this process, the NPMS allows for the effective monitoring of progress and timely decisions concerning corrective action when needed. Complete details concerning the NPMS are available on the NPMS Website.

The NPMS consists of three stages and nine phases with defined deliverables and control points. The three phases of the NPMS are as follows:

The Project Inception Stage provides a “go” or a “no go” decision to proceed. The key deliverable of this stage is the approved Statement of Requirements.

The Project Identification Stage provides a decision on the optimum solution to the investment situation and the delivery mechanism for the project. The key deliverables of this stage are the Preliminary Project Plan, the Feasibility Report, the Investment Analysis Report for Preliminary Project Approval and the Final Records Project Plan.

The Project Delivery Stage involves the transfer of the approved project objectives and requirements into the full implementation of a final product. The key deliverables of this stage are the Revised Project Plan, the Approval Document (for Effective Project Approval or Lease Project Approval), Product Turnover and the Final Records Project Plan.

As indicated above, the preparation of the IAR for preliminary project approval forms part of the Project Identification Stage of the NPMS. In this regard, it is important to emphasize that the IAR preparation process is but one element within the integrated NPMS process. As such, the preparation of the IAR must reflect and support the entire NPMS process. The implications of this for IAR preparation include:

Prior to writing the IAR, there should be an approved Statement of Requirements, Preliminary Project Plan and Feasibility Report already completed. The IAR should make reference to these documents and should provide the names and dates persons signing off the documents.

The IAR should summarize the results of the other NPMS documents that have been completed, however, there is no need for duplication. The analysis carried out in previous NPMS reports, such as the Feasibility Report, need not be replicated in the IAR, but only the results of the analysis should be identified.

- 13 -

Page 18: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

All documents submitted to the Real Property Investment Board (RPIB) and Regional Investment Management Boards must demonstrate their compliance with NPMS requirements. Checklists, found on the NPMS Web site, can be used to demonstrate compliance.

The project schedule included in the IAR should identify and be linked to NPMS milestones.

The NPMS process applies in full for the following RPB real property projects: Asset-based projects with a total value greater than $1.0 million, including GST

or HST but excluding client costs; and Space-based projects involving a space requirement greater than 3,000 m2

rentable (regions) or 5,000 m2 rentable (NCA and Parliamentary Precinct Branch)

Smaller projects that are below the thresholds identified above can make use of a reduced NPMS process known as “NPMS Lite.” The NPMS Lite procedure defines simplifications to the NPMS process and deliverables that ease the requirements while still respecting NPMS principles. More information on this procedure is available on the NPMS Web site.

2.2 The Strategic Context for IAR Preparation The projects that an organization chooses to implement are a clear manifestation of

corporate strategy. Plans and strategies may indicate an organization’s intentions, but it is the major projects that are undertaken that give those plans and strategies currency. Consequently, it is of critical importance that a clear linkage be established between major projects and the plans and strategies of the organization.

PWGSC’s program activities are expected to be aligned with the key strategic objectives of the department, which are defined through the Program Activity Architecture (PAA). The PAA is part of the government’s Management Resources and Results Structure that provides a horizontal management framework across the federal government and allows enhanced reporting on performance to Parliament and central agencies. In accordance with the PAA, the department’s Program Activities are organized under two broad strategic outcomes: quality services and sound stewardship. Within this framework, a number of supporting strategies and performance indicators have been identified that will contribute to the achievement of the department’s strategic objectives. The most relevant to real property investment decisions include the following:

The achievement of space volume reduction and fit-up efficiencies; The achievement of leasing optimization efficiencies; The achievement of an office space distribution ratio of 75:25 in the National

Capital Area; Having all Occupancy Instruments comply with the Office Accommodation

Framework; The achievement of return on investment targets for Crown-owned office

buildings;- 14 -

Page 19: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

The use of RPB risk management tools to manage the risks of real property services;

The achievement of RPB’s Sustainable Development Strategy targets; The attainment of LEED Gold standard in new buildings, and satisfy the BOMA

BEST (formerly BOMA Go Green Plus) assessment for existing buildings and leases;

The reduction of energy consumption in Crown-owned buildings; The remediation of contaminated sites; and The implementation of projects included in the National Portfolio Plan (NPP).

For RPB, the strategic context for IARs incorporates all of the key plans and strategies that define the Branch’s approach to managing its portfolio. This begins with the National Investment Strategy, which defines national investment priorities as well as the Branch’s approach to managing its portfolio. Other key strategic documents include:

Community-Based Investment Strategies (CBIS), which identify community-level issues, priorities and plans;

Strategic Action Plans (SAP), which identifies local investment priorities; Regional Investment Strategies, which define regional investment priorities; Asset Management Plans (AMPs), which recommends a management strategy

for an individual asset; The Way Forward Initiative, which seeks cost reductions through more

rigorous application of Office Accommodation Framework (OAF) space and fit-up standards and a more strategic approach to leasing; and

Sustainable Development Strategy (SDS), which sets out the departmental approach to sustainable development.

The BMP Annual Call Letter, which provides instructions for the preparation of Building Management Plans (BMPs), also provides vital information on national objectives and priorities, as well as information on how national programs should be reflected in the planning for individual buildings.

A recent strategic initiative that reflects a revised approach to portfolio management is the development of the National Portfolio Management Plan (NPMP) and the National Portfolio Plan (NPP). The NPMP is a national portfolio-based approach to strategic planning that recognizes the issues and challenges of the current portfolio and seeks to put in place the tools and methodologies to bring about change. The underlying theme is the migration of the portfolio from its current state to a desired state. The desired state of a portfolio reflects a vision of a flexible, responsive and synchronized portfolio that meets the short and long term needs of the government’s program objectives in such a way as to provide best value and to allow program dollars to be used for their intended purpose. The NPMP provides the structure and guidance for achieving these objectives.

Underlying the NPMP is the recognition that the ultimate objective for the portfolio is not necessarily to own buildings, but rather to provide good, efficient

- 15 -

Page 20: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

accommodation at an affordable cost to the federal government. This may require new ways of doing business and managing the portfolio. Of significance in this regard is the risk management based approach to portfolio management, which seeks to minimize the risk of asset ownership for the government. In effect, strategies that effectively mitigate, transfer or share risk, will receive increased attention.

The National Portfolio Plan (NPP) flows from the NPMP. The NPP provides an action plan for what will be done within the portfolio to implement the NPMP. It includes an optimal set of priority projects, listed by asset category to match supply to demand over the next 5 years. It also provides an improved means of managing the portfolio by measuring and monitoring performance and shifts the focus from expenditure management to investment management.

In 2009, PWGSC is preparing the department’s first Investment Plan, which conforms to the requirements of the new TB Policy on Investment Planning - Assets and Acquired Services. The Investment Plan will replace the National Investment Strategy (NIS) and demonstrate how PWGSC intends to create and manage a portfolio of custodial, accessed assets and acquired services. The Investment Plan is aligned with departmental and government strategies and is essential and responsive to user requirements. Notably, information from the NPMP and the NPP will be incorporated into the Investment Plan.

A key component of the NPP is its ability to triage, prioritize and measure the portfolio. The methodology for doing so is known as the “Tiering Tool.” Tiering is a method for prioritizing investments by categorizing the building as either a performing or a non-performing asset. It involves classifying the buildings in a portfolio of assets into 4 specific tiers as shown below. Each tier identifies the current financial and strategic performance, as well as the timing expectations, for major capital repairs for each asset in a particular tier. Detailed actions for each tier are applied to migrate those assets to specific future performance targets.

Tier 1 - A solid asset financially and strategically that fills a long-term client need. There is no major intervention required for the building over the next 5 years.

Tier 2 - An asset with good financial and strategic performance. Demand is relatively stable. Major intervention may be required, but can be delayed for 5 years.

Tier 3 - An asset with weaker financial and strategic performance. Major intervention is required within 5 years.

Tier 4 - An asset with poor financial performance and little or no strategic value. Requires major expenditure.

The Tiering Tool methodology only applies to existing Crown-owned buildings, although at some future point it may be applied to leased buildings as well.

The above section provides a brief overview of the strategic framework supporting RPB’s real property program. It is important for the investment analyst to fully understand the policies and strategies of the Branch in order to develop projects that reflect strategic priorities and are designed to conform with RPB policies. Each

- 16 -

Page 21: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

project should have a logical link to the strategic priorities of the Branch and it is the job of the analyst to understand and convey that linkage.

2.3 Preparing an IAR As discussed at the beginning of the chapter, the preparation of an IAR is one

element within the overall approach defined by the NPMS. Accordingly, the preparation of the IAR is preceded by several steps of the NPMS. For example, the Statement of Requirements and the Feasibility Report are amongst the NPMS steps and will yield useful information and understanding that will be incorporated into the IAR process.

Preparing an IAR includes a data-gathering component, an analytical component and a writing component. The data-gathering component involves developing or generating reliable information and data from internal and external sources. Good data is a prerequisite for a meaningful and valid analysis and is gathered and facilitated by having the appropriate people with the necessary knowledge and skills as part of the IAR team. Obtaining the necessary information can be effectively done by engaging external expertise early in the process, needed to generate design and cost information. The analytical component involves the evaluation of project requirements and the corresponding options and actions in order to meet those requirements. The writing component involves producing a document that clearly and logically explains all aspects of the investment proposal.

The analytical component of the IAR, or the investment analysis, involves a series of techniques for analyzing relevant information concerning future costs and benefits related to a project. The investment analysis process can be considered as a series of logical steps that carries the analyst through the thought processes necessary to arrive at a fully supportable conclusion. This process, known as the eight steps of investment analysis, is described in detail in Appendix A of this Guide, and is briefly summarized as follows:

1. Define scope - identify and document project or client requirements. Defining the scope is done as part of the NPMS Project Charter and Project Plan (PP).2. Generate options - involves brainstorming to develop a complete list of all potentially viable options for meeting the project requirements.3. Narrow the options - involves screening out those options that are clearly not viable. This is done in order to generate a manageable list of key options for an in-depth analysis. Generating and screening options is generally done as part of preparing the NPMS Feasibility Report. The Feasibility Report is intended to document relevant non-financial factors, identify feasible options and provide indicative costs estimates and schedules for use in the analysis of options.4. Undertake financial analysis - determine the financial viability of the main options through a discounted cash flow analysis using PWGSC’s REFIT program and by conducting a sensitivity analysis.5. Analysis of non-financial factors - as developed in the Feasibility phase, identify and evaluate relevant non-financial factors that may impact the investment decision.

- 17 -

Page 22: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

6. Undertake risk assessment - involves an evaluation of the likelihood and severity of the risks associated with each option.7. Analysis phase - Evaluate options by combining the assessments of financial factors, non-financial factors and risk to draw overall conclusions concerning the investment decision and which option provides the best overall value to the federal government.8. Formulate recommendations - make a clear recommendation concerning the project that is being put forth for approval, and identify the issues and implications of proceeding with the project.

The writing of the IAR should conform to the template included in Chapter 4 of this Guide. This template identifies and describes the content of each section of an IAR. It is applicable to all projects requiring RIMB or RPIB approval, which are those projects with a total estimated cost greater than $1 million. It also applies to both asset-based and space-based projects.

Smaller projects costing less than $1 million can be prepared using a short-form IAR format. The short-form IAR format is intended to provide for the complete analysis and justification of a project, but in a shorter document that is less onerous to prepare. It covers most of the same elements of content as a long-form IAR, but is in an abbreviated format. The short-form IAR makes use of standardized information templates to reduce the document length and to ease the task of writing. Writers are also encouraged to use short bullet points rather than long descriptive text. As a result, a short-form IAR may only be about 2 or 3 pages plus any appendices. A national template is available for preparing short-form IARs. Please note, several regions have developed their own templates.

Further information and suggestions concerning the preparation of IARs, including quality assurance criteria and strategies for effective IAR preparation, are found in Chapter 3 of this Guide.

2.4 New Approaches to Investment Analysis In undertaking an investment analysis it is a key requirement that all options for

providing accommodation be explored. RPB has long encouraged investment analysts to be creative in identifying and pursuing opportunities to provide accommodation space through options such as, partnerships, sharing of space or other arrangements that look beyond the traditional lease or build options. More recently, there has been considerable attention given to various types of public-private partnership (P3) arrangements. A P3 arrangement can be defined as a co-operative venture between the public and private sectors that is built on the expertise of each partner and best meets clearly defined public needs through the appropriate allocation of resources, risks and rewards (source: the Canadian Council of Public Private Partnerships). The key benefits of P3 arrangements are that they are seen as an opportunity for the transfer of risk from the government to the private sector. They capitalize on the perceived efficiencies of the private sector in developing and operating facilities and they equalize the flow of payments over the investment horizon instead of requiring major cash outlays at the front end. To encourage the consideration of this approach, there is now an expectation that IARs

- 18 -

Page 23: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

for major projects include the evaluation of a P3 option as part of the analysis. The P3 Centre of Expertise may be contacted to help resolve questions regarding whether or not the inclusion of a P3 option is appropriate for a specific project.

RPB is also introducing a new approach to its investment analysis to better account for the different levels of risk associated with various accommodation solutions. Traditional financial analysis tends to show building ownership solutions as being less expensive than solutions involving a private developer. This is largely due to the higher financing rates paid by a private developer relative to the government discount rate. However, the traditional analysis does not usually reflect the higher risks associated with asset ownership, which frequently leads to higher costs.

To offset this bias in favour of ownership solutions and to better reflect relative risk levels between options, RPB is adopting an approach known as the risk-based investment analysis approach. This approach involves identifying, assessing and evaluating the probability and impact of the risks that apply to each of the options. A risk adjustment for each option is calculated and then by adding the risk adjustment to the “risk neutral” present value cost of accommodation (PVCOA) to produce “risk-adjusted” results. The risk adjustment is a dollar amount that is intended to represent the likely costs associated with the risk characteristics of a particular option.

Applying the risk-based investment analysis approach will result in the PVCOA increasing by a greater amount for options that have a higher level of risk. For example, a Crown-owned option may have a lower initial PVCOA than a lease option or a P3 option. However, because Crown-owned options tend to carry a higher risk of increased costs, adding the risk adjustment to the initial risk-neutral PVCOA will produce a risk-adjusted PVCOA that could be as high or higher than that of other options where the developer bears a greater portion of the project risk.

It is expected that the use of this risk-based investment analysis approach will result in a larger number of projects being implemented through various partnership arrangements with the private sector. Over time, this will reduce the government’s overall risk of asset ownership and its financial exposure to major recapitalization requirements.

2.5 Preparation of Treasury Board Submissions Accommodation projects with a total estimated cost greater than $30 million are

above the delegated authority of PWGSC or its Minister to approve thus, requiring Treasury Board approval. A Treasury Board (TB) submission is an official document submitted to TB by a minister on behalf of his or her department seeking approval to carry out a proposal that is outside the department’s delegated authorities and that the department would therefore not be able to undertake. Every year, RPB is required to prepare numerous TB submissions for project approvals and for contract approvals that fall outside of the department’s delegated authorities.

The first draft of the TB submission is prepared by or under the direction of the Project Leader. Investment Analysts in the Accommodation and Portfolio Management Directorate at Headquarters are the main contact points for TBS staff and are responsible for providing the necessary input to allow documents to be

- 19 -

Page 24: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

finalized prior to them being sent to the ADM the Minister and Treasury Board. Treasury Board Secretariat has developed a Guide for preparing TB submissions.

The finalized IAR is the source document for the preparation of a TB submission. Analysts preparing an IAR for a project costing in excess of $30 million should contact the Headquarters Investment Analyst who will be involved with the TB submission early in the IAR process. The Analyst will then co-ordinate the informational requirements and ensure that the quality and formatting of the information provided in the IAR facilitates the preparation of the TB submission.

- 20 -

Page 25: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

- 21 -

Page 26: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Chapter 3.0: Guidelines3.1 Key Guidelines and Criteria for a Well-Written IARThe purpose of the IAR is to convey the relevant information required to make informed investment decisions. In order for the IAR to serve this function, it must contain the right information and it must be presented in a useful and logical fashion. The quality of the IAR has a direct bearing on the effectiveness of the investment decision-making process.Quality in an IAR is related to its objectivity, the precision of its information, the logic of its analysis and the compelling nature of its conclusions. Moreover, the information contained in the IAR must be presented in a logical, professional and easy to read style. The following describes some guidelines on what constitutes a well-written IAR:

9. The IAR should be an objective presentation of factual information. Reflect the point of view of the federal government as a whole, not just PWGSC interests. Provide an objective, honest and credible assessment of identified options and do not expect to defend any particular point of view. Use a neutral tone; this is not a selling document. Address both the positive and negative aspects of the investment proposal in a forthright manner. Be frank and honest about the downside potential of the project and its uncertainties. Put forward realistic expectations of future project benefits. Those who review IARs are aware of the tendency to overstate downstream benefits. Overly optimistic projections should be questioned. Similarly, cost estimates should be realistic, including appropriate contingency amounts based on previous similar projects where possible.

10. The credibility of the IAR is based on the validity of the information, data and input

values presented. Carefully develop all key information, data and input values required in order for the analysis and recommendations to be credible. Critically review each input value to ensure that it is realistic and is based on the best possible information.

11. The IAR should reflect an in-depth, systematic and rigorous approach to investment

analysis, which incorporates all relevant information. Structure the analysis to address clearly defined requirements. Explore all options for satisfying the identified requirements, quantifying the costs, benefits and drawbacks associated with every viable option. Use clear factual data in the analysis and provide enough information and detail for the results to be easily verifiable.

- 22 -

Page 27: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

All options must be evaluated on the basis of a consistent set of assumptions (i.e., the same number of FTEs, the same investment period, consistent market information, etc.). Any deviations from this must be clearly documented and justified. Ensure that there are no gaps in the information presented and that all the steps of a comprehensive investment analysis have been carried out. Include both financial and non-financial factors. Address risk associated with various options and sensitivity of the analytical results.

12. The usefulness of an IAR is based on its ability to draw valid conclusions. Make a strong business case for a recommended investment proposal. Support all observations and conclusions with factual evidence. Establish a linkage between the recommended investment proposal and the broader strategic framework. Ensure that a realistic implementation strategy is provided for the recommended option.

13. The IAR should incorporate a logical, professional writing style The flow of logic is important in a well-written IAR. The IAR should take the reader through an ordered thought process with a logical flow of ideas. Write in a simple, direct style. Come quickly to the point, without using long narratives. Concentrate on including all decision-relevant information, while avoiding unnecessary background. Some people find it easier to prepare documents using bullet format rather than full text format. Bullet format can be used in an IAR as long as all of the required information is provided and the content is clear and easy to read. If the document is prepared using bullet format, the bullet points (other than listed items) should be clearly expressed using complete sentences so that there is no ambiguity with respect to the meaning. Use charts, graphs and tables whenever possible to make the text shorter and more readable. Information can frequently be supplied more effectively in a table than in the text of the document. Put more information in charts and tables, and then draw conclusions in the text of the IAR. Photographs and computer simulations can also be useful additions. Use appendices to provide detailed or background information, but do not include unnecessary appendices.

3.2 Meeting Timing Requirements It is essential that IARs be reviewed and recommended by the investment board

within a reasonable time frame. “A reasonable time frame” means that the options proposed in the IAR are still valid

and have not been stale-dated by the passage of time. While there are a variety of circumstances both controllable and uncontrollable leading to this situation, the net

- 23 -

Page 28: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

result is that the decision-making process of the Real Property Branch is impaired and the client and taxpayers are poorly served. Managers are strongly advised to set, control and monitor the critical path necessary for the preparation and approval of IARs, in both the Region and in Headquarters, to ensure that they are reviewed and approved while options remain on the table.

“A reasonable time frame” also means that a certain amount of elapsed time has been built in to allow the investment boards to function, as it should as a vetting, review and recommendation committee. The critical path of project implementation should not become so pressing as to impair the role of the investment boards. Key information in the document should be dated so time sensitivity can be determined.

For timeliness to occur, it is requested that Project Leaders consult with their respective Investment Analysts in Headquarters or the Regional office throughout the preparation of the IAR. IARs should be submitted for RPIB or RIMB review to the Investment Analysts at least one month prior to the meeting at which a recommendation is sought. This will enable Investment Analysts assigned to each region to review the document in a deliberate fashion and will permit those involved with the RPIB or RIMB meeting to be prepared with their input.

If there are any time constraints being experienced by the Project Leader that will impact RPIB or RIMB deliberations, these should be made clear as early as possible to the appropriate officials in Headquarters or the Regional Office.

3.3 Strategy for Approaching the Preparation of an IARThe preparation of an IAR must reflect a rigorous process involving the carrying out of investigations, developing and questioning information, data and input values, performing quantitative and qualitative analyses and formulating recommendations. The recommendations that are put forth must be based on an economic and program assessment that considers least life-cycle cost and best-value options for delivering the requirement. Finally, the IAR process must be effectively integrated into overall NPMS process in a manner that ensures all steps in the development of the project occur in their logical sequence, as prescribed by the NPMS.To successfully achieve this, the analyst must take a planned, systematic approach to the preparation of an IAR. The elements of such an approach are discussed below:

1. Plan ahead. Develop a work plan with milestones for completing the IAR. Identify all tasks, and plan how they are to be carried out, and by whom. Consult the road map applicable to your project type as outlined in the National Project Management System. Recognize that the development and refinement of options, the research of issues, client consultations, a contracted market survey and the development of cost estimates and implementation strategies are especially time critical. Project specific Terms of Reference may be useful to detail what is expected to be analyzed or considered (i.e. a preliminary set of options).

2. Identify team members. Ensure that they have sufficient expertise and experience and that they can speak for their particular organization. Ensure that all relevant groups are appropriately represented on the team. Seek input from

- 24 -

Page 29: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

team members and obtain team buy-in for the timelines proposed in the workplan. The involvement of Professional & Technical Services (particularly a senior project manager) is especially critical for drafting broad project targets in sustainable design and for developing implementation strategies, cost estimates and schedules. Ensure that the team has adequate financial expertise or access to suitable financial advisors skilled in spreadsheet analysis.

3. Consider what information is required. Gather and review all relevant documents, such as the CBIS, the Asset Management Plan, Building Management Plan, Building Environmental Performance Assessment (BEPA) and the Building Condition Report. Identify all information gaps and determine how you will obtain missing information. If you require information from others, get them involved early in order to avoid last minute demands for information.

14. Identify all relevant issues. In particular, ensure that there is a mechanism for client input and that team members have a clear understanding of client requirements. Some projects may also require approval and funding by both PWGSC and the client department.

15. Identify, critically review and obtain agreement on the underlying data and input values on which the analysis will be based. If key data and input values are off, the analysis will be flawed.

16. The market survey and analysis are important elements in preparing the IAR as they provide critical market and economic information. Ensure that relevant and reliable market information is available. Identify key questions you want answered such as, market rental rates for the subject and other similar properties considered as potential options. Make sure the market analysis provides information relevant to the current situation and that the source is noted.

7. Ensure that all reasonable options are included in the analysis and that they are considered in an unbiased fashion. Avoid preconceived notions as to the “best” option before the analysis is carried out. Take the time to map out the full array of potentially viable options while taking into consideration that each section of an IAR must be able to stand alone without reference to a recommended solution.

8. Ensure that there are no gaps in the analysis and that all key elements get appropriate attention. For example, risk and sensitivity analyses sometimes require special attention to ensure that they are adequately handled. Exercise quality control in the analytical process.

9. Be sure that there is agreement by all key parties on the IAR. Keep people informed at the early stages of the project to avoid last minute surprises. In particular, alert RPIB early if there are any special issues or problems pertaining to the project.

- 25 -

Page 30: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

10. Allow for realistic timing in preparation of the IAR. Get started early, an IAR cannot be pulled together at the last minute. For instance, a complex project could take several months of effort.

3.4 IAR Quality Assessment CriteriaDefining Project Scope1. Is the project scope completely and clearly identified, and consistent with the NPMS

Project Plan and Project Charter?2. Are the needs of the client fully and fairly reflected in the statement of the project

scope?3. For space-based projects, is the amount and type of space identified and consistent with

the Office Accommodation Framework?4. Does the IAR relate the project and/or the project scope to the broader RPB strategic

context?Information Content1. Is the relevant history of the project clearly presented? Are NPMS control points

referred to?2. For projects involving existing assets, has all pertinent information been given

concerning the asset’s condition and performance, including identifying other project requirements related to the asset?

3. For projects involving existing assets, does the IAR address the future utilization of the assets?

4. For space-based projects, has the IAR considered the ability of existing inventory to meet the requirement?

5. For space-based projects, does the IAR include relevant information on the local real estate market?

6. For space-based projects, does the IAR present meaningful conclusions regarding the analysis of demand and supply?

Identifying Options1. Does the IAR identify a full range of options for meeting the identified project scope,

including the status quo option? 2. Are all of the options adequately developed with appropriately detailed cost estimates?Analysis of Options3. Is the financial analysis of options clear and complete and does it conform to RPB

conventions?4. Does the financial analysis include consideration of all of the life-cycle costs of the

project?5. Has a sensitivity analysis been included in the analysis?6. Has a risk assessment been carried out and does it adequately evaluate all relevant

areas of risk?7. Does the analysis consider all non-financial factors that have a bearing on the

investment decision?8. Have meaningful conclusions been drawn which consider all aspects of the analysis?Formulation of Recommendation1. Does the recommended solution address the problem statement in the Statement of

Requirements?2. Does the IAR clearly state the approvals that are being sought?3. Does the IAR present the correct class of cost estimate for the type of approval being

sought?

- 26 -

Page 31: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

4. Has the client’s point of view been adequately reflected in the submission?5. Does the IAR address potential environmental impacts and has a statement on

environmental impact been included?6. Does the IAR identify funding requirements, the source of funds, the Vote that the costs

will be charged to as well as the expected project cash flow by year?7. Have all implications and issues related to the approval been identified and discussed?8. Does the IAR contain a well thought out implementation plan that will minimize client

disruption? Is the implementation plan consistent with the NPMS?Overall Quality of Document1. Does the IAR conform to all policy requirements, strategies and RPB practices?2. Is the information, data and analysis relevant, reliable, unbiased and complete (no

gaps)?3. Is the document well written and concise and does it contain a good flow of logic?4. Has the IAR been submitted in a timely fashion with adequate time for RIMB and, if

applicable, RPIB to consider all options?5. Does the IAR include a well-written and concise Executive Summary that summarizes

all key issues?

3.5 Proposed Outline of an IAR

Executive Summary1 Problem/Opportunity Definition2 Background

2.1 Project History2.2 Building Condition2.3 Tenant Considerations2.4 Inventory Supply & Real Estate Market Analysis

3 Project Scope4 Identification & Analysis of Options

4.1 Options Considered4.2 Financial Analysis & Sensitivity Analysis4.3 Analysis of Non-Financial Factors4.4 Risk Assessment4.5 Conclusions

5 Strategic Impact6 Recommendation7 Approval Authorities and Funding8 Implementation Plan9 Project Team & Signatures10 Appendices

- 27 -

Page 32: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Chapter 4: IAR TemplateExecutive Summary Purpose:The purpose of the Executive Summary is to provide a brief overview of the most essential and decision-relevant information concerning the project.Suggested Contents:While the contents of this section will vary depending on the situation, the following elements of content should be considered when writing this section:1. Start with a clear statement of the proposal that is being recommended for

approval. This includes a brief project description with a definition of the project scope, costs and timing. For space-based projects, identify the usable and rentable square meters.

2. Identify the following: estimated project cost, including any risk allowance, the type of approvals that are being sought (preliminary project approval, effective project approval, or lease project approval), any associated spending authorities, whether this constitutes a revised approval, and the appropriate delegated authority required for project approval. The estimated total project cost should include only items funded or controlled by PWGSC. GST should be included and then shown separately. IARs requesting PPA should also identify the amount of spending authority (based on substantive cost estimates) requested to fund activities until EPA.

3. Identify the source of funding for PWGSC costs related to this project. Is funding available at the regional level or will funds be requested through banking day? What vote will the costs be charged to? Is the funding considered to fall under Capital or Operating?

4. Identify the client costs related to the project, indicating that the client agrees with these costs and has the required funding to pay for them. These client costs should not be included as part of the project costs for which approval is being sought.

5. Identify any expenditures undertaken by PWGSC on behalf of the client for which PWGSC will be reimbursed.

6. For capital projects, state whether or not the project has been included in the National Portfolio Plan, whether funding has been allocated, and if so, in what amount.

7. Provide projections of cash flow by year in budget year (year of disbursement) dollars. GST should be shown separately.

8. State the class of cost estimate. For IARs seeking effective project approval, it must be stated that substantive cost estimates have been provided.

9. Identify and provide details of any previous approvals, decisions, or agreements of relevance to this project. This would include previous RPIB, RIMB or Treasury

- 28 -

Page 33: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Board approvals, Cabinet or Ministerial decisions and interdepartmental agreements, such as Memorandums of Agreement or Memorandums of Understanding.

10. Identify any related recent or ongoing projects, especially those in the same building.

11. Include a summary of the rationale for undertaking this project. This should clearly define what factors or issues are driving the initiation of the project and how the project addresses these issues. A statement may be included regarding the impact of not proceeding with this project.

12. Identify the options that were analyzed. Illustrate the results of the financial analysis in the form of a table showing the PVCOA and the risk-adjusted PVCOA (if calculated) for each option. Clearly state and summarize the rationale for selecting the recommended option, identifying the financial, non-financial and risk factors that contribute to making this the best value approach.

13. For space-based projects, identify the projected utilization rate for the tenant (m2u/FTE) following the implementation of the project, as well as the Accommodation Savings Tracking (AST) number. State whether or not the project will generate savings.

14. Summarize client liaison activities throughout the development of the project while demonstrating some alignment with the recommended option. Identify any client concerns related to the project.

15. Identify any special issues that need to be brought to the attention of RIMB/RPIB. These issues may pertain to risk management, potential political considerations, timing, legal issues, client issues, issues regarding the department’s sustainable development targets, heritage conservation considerations or areas of public sensitivity with respect to the project.

Tips on writing this section:1. Write in a simple, direct style, avoiding long passages. Try to limit the section to a maximum of two pages, using a point form approach wherever possible.2. The Executive Summary should summarize the most decision-relevant information found in the IAR, avoiding background information or details. 3. Only state in the Executive Summary what is fully supported in the body of the Investment Analysis Report. On no account should the Executive Summary contain new information.4. Write the Executive Summary after the rest of the document is complete.

1. Problem/Opportunity DefinitionPurpose:

- 29 -

Page 34: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

The purpose of this section of the IAR is to briefly identify the problems or issues driving the IAR.1. Describe the key issues that the proposed project is addressing. Projects may be

launched for a number of reasons, such as: to meet a client requirement; to maintain or improve an asset; or to take advantage of an opportunity. Make reference to any portfolio planning considerations that may be driving the requirement for the project. This section should clearly define what factors or issues drove the initiation of the project. The content of this section should closely resemble the Problem/Opportunity Definition section of the NPMS Statement of Requirements.

2. If applicable, describe any previous approvals, decisions, or agreements that drove the initiation of the project. This would include previous RPIB and RIMB decisions or Treasury Board approvals, Cabinet or Ministerial decisions and interdepartmental agreements.

3. Identify and describe any special involvement of another department, for example, the IAR is on behalf of another department; the IAR deals with a joint undertaking; the initiative will be funded in part by the client department.

4. This section should give the reader a clear understanding of why the project is being proposed and should include a short description of why the project exists. However, care should be taken not to burden the reader with details.

Tips on writing this section:1. This section should be kept very short. It identifies the key problems or issues

that are driving the project and provides an introduction to the rest of the document.

2. Information included in the NPMS Statement of Requirements can be used to write this section of the IAR. The problem/opportunity definition included in Section I of the SoR may be sufficient for the content of this section.

2. BackgroundPurpose:The purpose of this section is to provide the reader with the necessary background to fully understand the investment situation. Suggested Contents:This section generally consists of the following: a project history, building condition, tenant considerations, inventory supply and real estate market analysis.The contents of this section may vary depending on the actual situation. Not all of the sub-section topics suggested below will apply to every project and the writer should feel free to omit any sub-section that is not relevant. The writer may also wish to change the order of the topics if this provides an improved flow of logic and greater clarity for the situation that is being described.

- 30 -

Page 35: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

2.1 Project History1. Provide a short description of the relevant history of the project. Describe any

relationship to other projects or larger programs. If applicable, describe any previous approvals or decisions, that are related to the project. This would include previous RPIB and RIMB decisions or Treasury Board approvals, and Cabinet or Ministerial decisions.

2. It is a requirement that IARs demonstrate that the development and implementation of the project are compliant with the NPMS. Include a statement indicating and describing this compliance. Describe the progress in completing other NPMS deliverables. Identify NPMS control points and deliverables that have been completed and provide the names and dates of persons signing off on these documents. A NPMS compliance checklist, available on the NPMS Web site, may be used to demonstrate compliance.

2.2 Building Condition1. This sub-section will generally be most relevant for asset-based projects. Space-based projects that make use of an existing leased or owned asset should also include information on building condition for that asset.2. Provide a brief description of the building. It is generally appropriate to provide

the details of the building description in an appendix with only a general overview and the most significant points included in the text of the IAR. Elements of the building description may include:

the age, area, location and other main characteristics of the building; the nature of any recent renovations that have been undertaken; detailed information regarding those features of the building of specific relevance to the project being proposed; building environmental performance assessment; whether this is a heritage building and whether there are any heritage considerations related to this project; description of the strategic value of the building; and whether the building is being managed by an Alternative Forms of Delivery (AFD) contractor and any implications this may have for the project.

3. Identify any future plans pertaining to the use of the building. This may include information on the remaining useful life of the building or how long PWGSC may be planning to keep the building.

4. Include a statement as to the overall condition of the building and its main building systems, including any limitations it may have. Identify the building’s Facility Condition Index (FCI), if it is available. Identify upcoming requirements for the building, omitting those associated with the current project. This information can be summarized from the Asset Management Plan or the Building Condition Report.

- 31 -

Page 36: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

5. Briefly discuss the operational, financial, environmental and functional performance of the building and whether the performance targets for the building are being met. This information can be summarized from the Asset Management Plan.

6. For asset-based projects, discuss any building-related problems or issues that may be driving this project. Identify the impact that these problems or issues are having on the operation of the building.

2.3 Tenant Considerations1. For asset-based projects, this sub-section addresses the impact of the project on

PWGSC’s tenants. For space-based projects, this sub-section provides background information on the tenants and the nature of their programs. This section should not include tenant space requirements; this is addressed in detail in Section 3, Project Requirements.

2. Identify the impact that the identified problems or issues are having on PWGSC’s tenants. Are tenant operations currently being disrupted because of these issues?

3. Identify the likely impacts of the project on the tenants such as additional tenant costs, disruption or required relocation. What are the key client concerns related to the project?

4. Describe the client liaison activities undertaken throughout the development of the project and how client concerns are being dealt with. In situations involving more than one client, the effective co-ordination of the Client Consultancy group should be demonstrated.

2.4 Inventory Supply & Real Estate Market Analysis1. This sub-section provides information on the availability of accommodation space

within the existing government inventory, as well as in the local real estate market. This section is not required for asset-based IARs for which the size or scale of the project precludes consideration of replacing the building as an option.

2. Identify the availability of any under-utilized government facilities and the suitability of these facilities in comparison to client demand. In identifying under-utilized facilities, consider the entire federal inventory, including PWGSC custodial facilities, facilities of other government departments, and leased facilities.

3. Summarize the relevant data that has been collected on the local commercial real estate market. Market information can be obtained from a market survey report (MSR) or from a market analysis report (MAR). A MSR is usually commissioned to collect more general market data for the development of an IAR, while a MAR is building specific and is used to determine the appropriateness of proposed rental rates. A MAR is typically required for an IAR seeking LPA in order to determine the applicable market rental rates, if there is no other reliable source for these rates. Although each IAR requires market data, a separately commissioned report may not be necessary if reliable information is available from other sources (eg., another relevant MSR or MAR). In summarizing the

- 32 -

Page 37: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

results of a market report, the analyst should note who carried out the report and when, the classifications of comparable buildings surveyed (A, B, or C class), vacancy rates (emphasizing properties having the required type and size of space), the effective rental rates for suitable accommodation and trends in the local commercial real estate market. It may also be useful to identify the number of properties within the relevant geographical boundaries that could potentially meet the identified requirement.

4. Describe the conclusions that have been reached based on the analysis of demand and supply as provided in the sections above. The conclusions should address the following questions:

Is there likely to be suitable accommodation space within the existing government inventory?

What is the vacancy rate and availability of suitable space in the local commercial real estate market? Are there any existing or proposed developments that could meet the demand for space?

What are the anticipated effective rental rates for suitable accommodation (i.e., rental rates adjusted for inducements)?

Tips on writing the background section:1. There will likely be a considerable amount of detailed information associated with this section of the IAR. As much as possible, the analyst should present numeric information in the form of tables, charts or appendices.2. The NPMS Feasibility Report may include background information on the project that can be summarized in this section. Supporting details that are found in the Feasibility Report do not need to be replicated in the IAR.3. Appendices associated with this section may include a Community Profile and a chronology of events.

3. Project ScopePurpose: The purpose of this section is to fully describe the key requirements of the project. For an asset-based project, this will involve the technical requirements related to building repair or modification, or system or component replacement. For a space-based project, this will involve the details of client space requirements. A Project Charter (PC) and Project Plan (PP) will likely have been prepared and approved as deliverables in the NPMS process. Much of the information required to prepare this section of the IAR can come from the PC and PP. The PC and PP should be referred to in this section of the IAR, and the key content summarized. Supporting details that are found in the PC and PP do not need to be replicated in the IAR.Suggested Content:1. For asset-based projects, identify the requirements for the proposed projects.

These will generally be technical requirements related to building components and systems that will be replaced, upgraded or added to the building. It may also

- 33 -

Page 38: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

be useful to discuss the level of urgency related to the requirements, if this has not already been addressed. Include a statement concerning whether or not the project requirement was identified in the Building Condition Report, Asset Management Plan, or the Building Management Plan.

2. For space-based projects, identify the client(s) requiring the space and present their requirements in terms of the following: the amount of space required, the type of space required, the location where the space is required, the date by which the space is required and for how long the space is required.

3. Space-based IARs must include the PWGSC “Office Accommodation Allocation Limits” form and must show that PWGSC fit-up standards are being adhered to.

Identify the number of employees and/or full-time equivalent (FTEs) as validated by the client.

Based on the number of FTEs, calculate the space entitlement as per the PWGSC Office Accommodation Framework (OAF), expressing this in terms of usable square metres of space (m2u) and then converting this to rentable square metres of space (m2r). Also show the ratio of usable area to employment (m2u / FTE). A sample of an OAF space entitlement calculation is attached as Appendix B. Attach the OAF calculation as an appendix to the IAR.

Confirm that the requirement meets the PWGSC fit-up standards and identify any fit-up exemptions. Include the “Fit-up Compliance Monitoring Form” and, if necessary, the “List of Non-compliant Items and Approvals” as an appendix to the IAR.

The required forms are available through the Fit-up Standards: Technical Reference Manual.

Identify the geographical boundaries required by the client. Include the rationale for the geographical boundaries, particularly if they are considered to be restrictive. Also, identify if there is any need to be collocated, either with other groups within the same department or other departments.

4. Identify the clients’ parking requirements. PWGSC will lease and pay for parking spaces that are required by clients for operational purposes. Additional parking requested by the client that is beyond their operational requirements, is paid for by the client department.

5. Identify any special considerations that relate to either the client’s requirements or the nature of the assets. Examples of this may include a client’s requirements for a specific location or type of location, the enhanced security requirements of a highly sensitive department or the special requirements posed by a heritage building. Summary information should be provided as to why these special requirements exist.

6. Develop a forecast of all relevant client demand in this location. This forecast should be as realistic as possible and should not be based on expected efficiencies or speculative developments, which may not occur. Identify the factors that are likely to influence demand in the future. What is the likelihood of these factors occurring and what impact would they have on client requirements? The analyst should be aware of changes to funding levels, program requirements and

- 34 -

Page 39: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

activities of client departments and be able to describe whether these changes will serve to increase or decrease demand for accommodation in this location.

7. Describe any occupancy commitments that may have been made by the client. The analyst should identify the term of this commitment and discuss what is likely to happen after the commitment expires.

8. Identify any impact on the client’s national space envelope such as an adjustment to the space envelope when the space entitlement warrants a reduction. Identify whether the client is reimbursing PWGSC for any of the expenditures.

9. Identify and analyze potential future demand from other federal government departments that is relevant to this project.

Tips on writing this section:1. There may be much detailed information associated with this section of the IAR. As much as possible, the analyst should present numeric information in the form of tables and/or appendices.2. Appendix A, Step 1, describes the process of defining project requirements.

References: Fit-Up Standards Technical Reference Manual

4. Identification and Analysis of OptionsPurpose:The purpose of this section of the IAR is to identify and analyze all feasible, practical options available to PWGSC for meeting the identified project requirements.Suggested Contents:This section generally consists of the following: the identification of options; the financial analysis; the analysis of non-financial factors; and a risk and sensitivity analysis. While the contents of this section will vary depending on the situation, the following elements of content should be considered when writing this section.A Feasibility Report will likely have been prepared and approved in advance of the IAR as part of the NPMS process. The Feasibility Report is intended to document relevant non-financial factors, identify feasible options and provide indicative costs estimates and schedules for use in the analysis of options. Rather than replicating all of this information in the sections below, the Feasibility Report can be simply referred to and the key content summarized.

4.1 Options Considered1. Identify and describe all reasonable options for satisfying the project

requirements. At this stage, it is preferable to identify a greater number of options and then rule them out, rather than focusing too early on only a very limited number of options.

- 35 -

Page 40: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

2. Identify those options, which are to be carried forward for in-depth analysis, and those options which are clearly not practical and which will be eliminated from further consideration. Briefly state why the eliminated options are not being considered for further analysis.

3. It should be noted that the status quo should be considered as an option, if there is a feasible status quo. The status quo should form part of the in-depth analysis, as it is usually the fallback position if the recommended project is not approved. It is important to ensure that the status quo is fully analyzed and the consequences of maintaining the status quo are clearly identified.

4. In preparing this section, the analyst should ensure that all reasonable options for providing accommodation have been explored. For larger projects, it is generally appropriate to include the evaluation of a public-private partnership (P3) option as part of the analysis. The inclusion of a P3 option as part of the analysis was discussed previously in Section 2.4 of this Guide.

5. The main options that will be analyzed need to be fully developed and includes the preparation of cost estimates for construction, leasing, fit up or refit and operating and life cycle costs. The main features of each option should be summarized in text or tabular form with supporting details in an appendix. It is important to identify the key assumptions made and the level of risk associated with the estimates provided.

6. Ensure that the requirements of the Canadian Environmental Assessment Act are addressed and that the results of the Environmental Assessment, including any required remediation and monitoring measures, are included in the analysis.

7. Ensure that the options reflect the requirements of PWGSC’s Sustainable Development Strategy.

8. More detailed information on the identification of options can be found in Appendix A on the Investment Analysis Process, including Step 2, Generate Options, and Step 3, Narrow the Options.

9. Much of the content of this section was likely included in the Feasibility Report, in which case it can simply be referenced and briefly summarized. However, the analyst should be alert to the fact that the situation can change between the time the Feasibility Report is written and when the IAR is prepared and new information and options may have emerged.

4.2 Financial Analysis & Sensitivity Analysis1. The financial analysis should consider the full costs to the federal government for

each option. The quality of the financial analysis is only as good as the assumptions and input values on which it is based. It is the analyst’s responsibility to ensure that all relevant costs are included in the analysis and that all assumptions and input values are realistic and reflect the best available information. Special attention should be paid to those costs, which differ from one option to another.

- 36 -

Page 41: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

2. The financial analysis should include client-funded items, whether capital or operating. The cost of internal PWGSC fees should also be included and are based on 1.8 times the hourly billable rate.

3. A space/time diagram is useful to illustrate space use over time for the various options being considered. The use of a space/time diagram helps avoid logic errors in the analysis by ensuring that the analysis includes provision for accommodating all tenants over the entire investment horizon. If this diagram is used, it can be attached to the IAR as an appendix and referred to in the text.

4. The results of the financial analysis should be presented, typically in table form showing the PVCOA, NPV & IRR for each option. Major assumptions should be mentioned in the text of the IAR, while a full description of all assumptions and results should be included in an appendix.

5. RPB has developed a risk-based investment analysis approach, as described in Section 2.4 of this Guide. The general approach is to calculate the risk-neutral PVCOA (no provision for risk) as has traditionally been done using PWGSC’s REFIT program and then adding a risk adjustment for each option in order to produce a risk-adjusted PVCOA. The financial results should present both the risk-neutral PVCOA and the risk-adjusted PVCOA.

6. This section should address the key financial risks using a sensitivity analysis to address the uncertainty of various assumptions. The sensitivity analysis should focus on key areas of uncertainty such as the level of demand, residual values and major cost areas (capital outlay risks, inflation / escalator risks, project timing risks including the possible increase in rent of a short term lease extension, rental market risks, and cyclical recapitalization risks). Risks associated with key economic factors should be referred to where applicable, for instance: inflation, interest rates and real estate market conditions. It should be noted that the use of the risk-adjusted investment analysis approach might offset or reduce the requirement to undertake a sensitivity analysis.

7. Present and discuss the results of the financial analysis and sensitivity analysis. Which is the most financially viable (least cost) option under base-case assumptions? Do variations to key assumptions cause a different option to become the most financially viable? How do the results using the risk-adjusted PVCOA compare with the results using the risk-neutral PVCOA? What conclusions can be reached based on the financial analysis?

8. Additional information on carrying out the financial analysis is available in Appendix A, The Investment Analysis Process, Step 4, Undertake Financial Analysis. As well, the financial analysis process and the use of REFIT are fully described in a separate guide.

4.3 Analysis of Non-Financial Factors1. The analysis of non-financial factors is intended to ensure that all qualitative

factors that contribute to providing value to the federal government are taken into account in the investment analysis.

- 37 -

Page 42: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

2. Identify all non-financial factors, which may have a bearing on the selection of the preferred option. While the relevant factors to consider will be different for each investment situation, some of the factors that may be considered include:

How well each option satisfies the identified project requirements. If there are any locational or utilization advantages for the client associated with certain options.

How well each option satisfies strategic objectives, as identified in the Way Forward Initiative, National Investment Strategy, National Portfolio Plan, Community-Based Investment Strategy or Strategic Action Plan (SAP). The NIS requires consideration of the following:

any major impact on local economic and market conditions which might influence future investment decisions

impact on the diversity or balance of the inventory, either in terms of tenure mix or date of lease expiry

marketability to other clients The extent to which each option is responsive to identified timing requirements Differences between the options with respect to health, safety, accessibility,

environmental or heritage consideration, contribution to the community and federal presence

The degree to which the option supports heritage preservation and the Good Neighbour Policy

The extent to which each option supports the goals and objectives of the PWGSC Sustainable Development Strategy. Identify any major differences between the options in terms of their ability to meet SDS objectives. Focus on decisions that are implicit in the approval of the IAR. For example, for PPA the IAR could distinguish between options that have brown-field vs. green-field development, urban vs. suburban locations. Refer to PWGSC’s Sustainable Development Strategy 2003, Annex 3, Targets 1.1.1 to 1.1.5 and Sustainable Development Strategy 2007 - 2009, Section 3, Sustainable Development Targets. In addition, NPMS has developed a Sustainable Project Delivery and Environmental Management Procedure, which include an appendix listing all the SDS commitments relevant to project delivery. Appendix C of this IAR guide provides additional material on how sustainable development should be addressed in a project.

3. The use of an evaluation matrix can help to ensure that all feasible options are considered in an organized, consistent and methodical manner, and are evaluated against all relevant non-financial factors. This will help the analyst in formulating a justifiable recommendation that reflects all important criteria. A complete description of a qualitative analysis using an evaluation matrix can be found in Appendix A, The Investment Analysis Process, Step 5 - Undertake Analysis of Non-Financial Factors.

Example of Evaluation Matrix for Qualitative Analysis

Non-FinancialFactor

Weight Option 1 Option 2 Option 3

- 38 -

Page 43: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Rating Score Rating Score Rating ScoreFactor 1 30 4 120 3 90 4 120Factor 2 25 2 50 5 125 4 100Factor 3 20 4 80 2 40 3 60Factor 4 15 5 75 1 15 4 60Factor 5 10 2 20 3 30 3 30Total Score 100 345 300 370

4. Describe the results of the analysis, including the rationale behind the ratings and weighting factors that were applied, and the conclusions that were reached. Details of the analysis may be included as an appendix.

4.4 Risk Assessment1. In RPB’s Risk Management Manual, risk is defined as “the uncertainty that

surrounds future events and outcomes. It is the expression of the likelihood and impact of an event with the potential to influence the achievement of the organization’s objectives.” The purpose of this section of the IAR is to identify and analyze the key risk factors associated with each of the options being considered in order that the relative riskiness of each option can be determined.

2. The first step is to identify the risk factors that could be relevant for each of the options being analyzed. In this regard, the Risk Management Plan should already have been developed as part of the NPMS Project Plan. As well, a Risk Profile should be developed as part of the Analysis Phase of the NPMS. A Risk Profile is defined in the RPB Risk Management Manual as an outline of the risks to which a project is exposed. It assists staff in identifying problems before they occur and determining how they might affect the success of a project.

3. While the relevant risk factors will be different for each investment situation, some risk factors that may be considered include: Risk that the project may not fully rectify an identified problem Risk of user needs not being met Risk of changing requirements Risk that forecast demand fails to develop Risk of not meeting timing requirements Risk of cost overruns Risk of future performance being impaired Risk of environmental degradation

4. Once the risk factors have been identified, it is necessary to evaluate the relative level of risk associated with each of the options. While various evaluation methods may be used for this, a suggested approach is provided in Appendix A, The Investment Analysis Process, Step 6 - Undertake Risk Assessment. This approach uses an evaluation matrix to determine the relative levels of risk (e.g., low, medium, high) for each of the options being evaluated. The evaluation should help the analyst determine the answers to the following questions:

- 39 -

Page 44: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

What types and what level of risk are associated with each option? How does each option rank in terms of risk? Which option has the highest risk

factor? How controllable are the key risks for each option? Generally, an option that

carries risks that can be mitigated is preferable to an option that carries risks that cannot be mitigated.

5. Describe the results of the risk assessment and the conclusions that were reached. Which option carries the lowest level of risk? Do any of the options carry an unacceptably high level of risk?

6. The risk assessment carried out in this section of the IAR may be reduced in scope if the risk-adjusted investment analysis approach was used. If so, the financial analysis may have quantified the risk assessment for each option as part of calculating the risk-adjusted PVCOA. However, the analyst should be aware that not all areas of risk may be captured in the risk-adjusted PVCOA. Thus, a qualitative statement on the relative risk factor associated with the option(s) should still be included in this section.. Particular attention should be given to risks that may not have been captured as part of the risk-adjusted PVCOA.

7. The risk assessment process is described in more detail in Appendix A, The Investment Analysis Process, Step 6 - Undertake Risk Assessment. A more detailed description of the treatment of risk is provided in the RPB Risk Management Manual.

4.5 Conclusions1. The intent of this sub-section is to combine the results of all of the analyses that

were undertaken in order to determine which option provides the overall best value to the federal government.

2. Consider the results of the financial analysis, the assessment of non-financial factors and risk assessment together. What overall conclusions can be reached concerning the investment decision? Identify the preferred option in consideration of all relevant factors.

3. There should be a clear rationale in support of the preferred option. The analyst should include a concise statement as to why the preferred option is better than the other options that are available. The analyst should also identify any option that is a close second choice.

Tips on writing sections 4.1 to 4.51. The results of the financial, non-financial and sensitivity analyses should be presented in tables, rather than in text, with observations and conclusions discussed in the text. Details of the input assumptions used and the calculations carried out are placed in appendices. It may be desirable to obtain guidance on this section from your COE. 2. Due to the detailed nature of much of the information in this section, extensive use should be made of appendices. Appendices connected with this

- 40 -

Page 45: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

section may include a description of options, the time/space diagram, the assumptions and printouts from the financial analysis and details of the analysis of non-financial factors.3. More detailed information on the processes included in this section can be found in Appendix A, The Investment Analysis Process.

References: Investment Analysis Policy PWGSC Sustainable Development Strategy RPB Risk Management Manual

5. Strategic Impact Purpose:The primary purpose of this section is to identify the strategic value of proceeding with the project. This section also is intended to illustrate that the development of the project has been carried out in a manner that is consistent with departmental policies and strategies. Suggested Contents:1. As noted above, one of the purposes of this section is to illustrate that the

development of the project has been carried out in a manner that is consistent with departmental policies and strategies. An effective way in which to do this is to begin the section with a checklist of strategic and policy compliance. This should not be a standard checklist that is applied to all projects. Rather, the checklist should only include those strategies and policies that are directly relevant to the project and those which the project team have given specific consideration to as a part of planning the project. While the contents of the checklist may vary, the following is an example of the type of checklist that may be used:

Example of Strategic and Policy Compliance Checklist

Policy / Strategy ComplianceYes No

The Way ForwardFramework of Office AccommodationSustainable Development StrategyGood Neighbour PolicyCommunity-Based Investment StrategyNational Portfolio Plan

- 41 -

Page 46: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

2. If the policy or strategy is being complied with, the “Yes” cell would be checked. If the policy or strategy is not being complied with, the “No” cell would be checked. An explanation as to how each of the policies or strategies is or is not being complied with should be included following the checklist.

3. Identify any strategic considerations of relevance to this project. If necessary, identify and describe any cluster of projects that this project impacts. Identify any client investment plans or broader government objectives that may have a bearing on this project.

4. This section should identify the strategic value to the department of implementing the preferred option (see Section 2.2 of this Guide for a discussion of strategic context). Consideration may be given to the following: Will the implementation of this project further local portfolio strategies

identified in the CBIS or SAP and if so, in what way? Will the implementation of this project further the strategic objectives of the

department as defined in the Program Activity Architecture (see Section 2.2)? Was this project identified as one of the priority projects included in the NPP?

What makes this project a strategic priority? Will this project help to achieve the cost-savings objectives identified in the

Way Forward Initiative? Does this project form part of implementing a strategy recommended in an

AMP? Describe the strategic importance of the asset.Tips on writing this section:

1. Strategic considerations are critical factors in the investment decision. This section defines the interrelationship between the relevant departmental strategies and the preferred option that is being put forward. 2. It is not necessary to describe details of departmental strategies. Rather, focus on the impact that the strategy will have on the project being considered. Care should be taken not to burden the reader with details.

References: National Investment Strategy, Community Based Investment Strategy and Strategic

Action Plan. National Portfolio Management Plan and National Portfolio Plan Good Neighbour Policy Sustainable Development Strategy. NPMS Web Site

6. Recommendation:PurposeThis section summarizes the investment proposal that is being recommended and the implications of this recommendation.

- 42 -

Page 47: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Suggested Contents:While the contents of this section will vary depending on what is being proposed, the following elements of content should be considered when writing this section:1. Start with a clear and detailed statement of the proposal that is being

recommended for approval. Identify the total estimated project cost (or LPA amount), both with and without GST and the type of approval that is being sought (preliminary project approval, effective project approval, or lease project approval), any associated spending authorities, whether this constitutes a revised approval and lastly, the appropriate delegated authority required for project approval. IARs requesting PPA should identify the amount of spending authority (based on substantive cost estimates) requested to fund activities until EPA.

2. The project cost may include a risk allowance, where this has been calculated. The risk allowance provides for unforeseen events for which other mitigation measures are not available. It should be noted that the risk allowance is not necessarily the same as the risk adjustment calculated as part of the risk-adjusted investment analysis methodology. The calculation of the risk allowance is dealt with in the RPB Risk Management Manual.

3. The estimated total project cost should include only those items funded or controlled by PWGSC. Note that direct PWGSC costs (fees billable to projects) should be listed at 1.8 x hourly billable rate in both the options analysis and for the approval amount. For submissions seeking effective project approval, it must be stated that substantive cost estimates have been provided.

4. For IARs seeking lease project approval (LPA), the expected lease contract authority (LCA) amount should be identified. The LCA amount is the total amount that will be paid to the landlord over the term of the lease (not discounted to their present value), including fit-up, O&M and taxes if these are passed through the landlord, expressed in budget year (year of disbursement) dollars.

5. Provide projections of cash flow by year in budget year (year of disbursement) dollars (GST shown separately).

6. Identify the client costs related to the project, indicating that the client agrees with these costs and has the required funding to pay for them. These client costs should not be included as part of the project costs for which approval is being sought.

7. Identify any expenditures undertaken by PWGSC on behalf of the client for which PWGSC will be reimbursed.

8. Clearly define the scope and timing objectives of the project. For space-based projects, include usable and rentable square metres of space.

9. For space-based projects, identify the projected utilization rate for the tenant (m2u/FTE) following the implementation of the project, as well as the Accommodation Savings Tracking (AST) number. State whether or not the project will generate savings.

10. Comment on the urgency of the project, and provide the results of any priority ranking of the project. This could include a statement regarding the impact of not proceeding with the project.

- 43 -

Page 48: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

11. Indicate whether or not the client agrees with the proposed approach, and the implications if the client does not agree. Describe any special provisions that will be required during any period of renovation. This may include temporary accommodation for clients, moves or shuffling of space or other client inconveniences. Describe how any inconveniences will be minimized.

12. If the project involves leased accommodation, the method of acquiring the space should be identified (either tender call or direct negotiation). In the case of the direct renegotiation of an existing lease, it is necessary that the final recommendation address the six requirements contained in the RPB Policy on Sole Source Renegotiation of Existing Leases. A statement to this effect should be made in this section of the IAR. It is recommended that a schedule for negotiations be prepared to demonstrate the time required to implement alternative solutions if negotiations are unsuccessful.

13. Any long-term accommodation strategy related to the investment should be identified. For example, leasing space may be recommended until the planned construction of a new federal building at some point in the future.

14. Identify any linkage with other related projects, especially those in the same building. Ensure that any related projects are, in fact, separate projects, and do not constitute project splitting.

15. Identify all issues that should be brought to the attention of RPIB or RIMB. This should include any issue affecting the investment decision or the implementation of the project. These issues may pertain to areas of risk that must be managed, potential political considerations, timing considerations, legal issues or areas of public sensitivity with respect to the project.

16. Include a statement on the environmental impact of the project. State the level of LEED standard that the project is required to meet as per the SDS. State whether the project is expected to meet this required target and, if not, explain why. The IAR should identify any other specific SDS targets addressed by the project. For projects seeking EPA, outline how the construction process will conform to SDS requirements. Ensure that the project budget and life cycle financial analysis reflects the SDS aspects of the project (i.e., any increases in capital costs and decreases in operating costs). (See Appendix C - Sustainable Project Delivery for more information).If required, include a project specific sustainable development strategy and/or material addressing the Canadian Environmental Assessment Act (CEAA) as an appendix. This material could include a CEAA checklist and/or identification of significant impacts and how these impacts are to be mitigated and monitored. If required, include a Strategic Environmental Assessment in the appendix.

17. Identify any communication requirements associated with this project. If this is expected to draw public interest, or require public consultation under provisions of the Canadian Environmental Assessment Act, briefly describe an appropriate communication strategy, and if available, include the Communication Strategy in an appendix.

- 44 -

Page 49: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Tips on writing this section:1. Be focused in your observations. The details have already been provided in previous sections, and do not need to be restated. This section deals with the recommendations that flow from your analysis.2. Ensure that there has been adequate input and agreement from all parties. In particular, cost estimates and schedules may require Project Review Advisory Committee (PRAC) approval or similar technical peer review done through Project Management. Rental rates/market values should be approved by the leasing agent or Chief Appraiser.

References: Policy on Sole Source Renegotiation of Existing Leases Lease Project Approval Policy

7. Approval Authority & FundingPurposeTo identify the funding requirement, source of funding and the type and level of approval authority required. Suggested Contents:

1. Identify the Delegated Approval Authority (e.g. RDG, ADM, Minister, TB).2. Identify the source of funding. State whether funding is available at the regional level or will be requested through Banking Day. Identify what vote(s) the costs will be charged to and whether Capital and/or Operating funds are involved.3. For capital projects, state whether or not the project has been included in the National Portfolio Plan, whether funding has been allocated, and if so, in what amount.4. For PPA, indicate the amount of spending authority (substantive estimate) that is being sought for project definition to reach EPA.

8. Implementation Plan PurposeThis section contains an implementation plan that describes all major steps that must be taken to successfully implement the project once approvals have been granted. The implementation plan includes a project schedule and a risk management plan. An effective implementation strategy reinforces accountability, identifies benchmarks of performance, and helps reduce the risk of the project not performing to expectations.Suggested Contents1. Describe the project implementation tasks and activities, including engineering

surveys, planning studies and other documentation that are required to move a project forward. If this is a request for preliminary project approval, include a

- 45 -

Page 50: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

description of the tasks and schedule to bring the project to EPA. Ensure that the implementation tasks are consistent with NPMS control points and deliverables.

2. Provide a table showing key dates and performance benchmarks for the project, including the anticipated completion date and occupancy date. Ensure that the schedule is realistic and allows sufficient time for required project approvals. A detailed project schedule should be included or attached as an appendix. In addition, the analyst should ensure that the schedule has been approved by Professional and Technical Services and, in the NCA, by the Project Review Advisory Committee (PRAC) for asset-based projects or by the Leasing Officer for space-based projects.

3. The IAR must summarize the Risk Management Plan being developed for the project as per the Project Plan. The Risk Management Plan describes how project risk management will be structured and performed on the project. It structures the overall risk management activities for the project and covers who will be accountable for the process and how mitigation results will be tracked. The Risk Management Plan should be developed in accordance with the RPB Risk Management Manual, and more specifically, the Risk Management Plan Template found in the NPMS Risk Management Procedure. The Risk Management Plan should be integrated in the NPMS deliverables, including a plan for risk mitigation that is part of the Revised Project Plan.

4. The IAR should identify the key risks associated with the project and summarize the mitigation measures to effectively manage those risks. IARs seeking PPA should specifically address risks associated with the project identification phase, the approval process, the timing required to take the project to EPA, as well as the risk mitigation measures that will be required to manage the risks that have been identified for the recommended option.

5. IARs seeking EPA should identify risks associated with the implementation of the project and summarize how these risks will be managed. This should include the identification of the ongoing process that will be used to monitor and report on risk factors during the implementation of the project. The Project Leader is responsible for ensuring that risk mitigation measures are acted upon during the implementation of the project and reporting on the outcome of unresolved risk issues. Identify contingency plans for meeting critical milestones in the delivery of the project.

References: Real Property Branch Risk Management Policy Treasury Board Secretariat Integrated Risk Management Framework. PWGSC Integrated Risk Management (IRM) Policy, Nov. 2004 PWGSC National Project Management System /Knowledge Area/ Risk RPB Risk Management Manual

9. Project Team & SignaturesSuggested Contents

- 46 -

Page 51: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

1. Identify the Project Leader and the members of the Project Team. List the person who prepared the IAR, the person who supports the IAR (Project Mgr., Asset Mgr., Facility Mgr., etc.) and the person who recommends the IAR.

2. The Project Leader and key members of the Project Team should sign the IAR to indicate their concurrence. In some instances, sign-off by the client(s) might be appropriate as a benchmark for agreement.

10. AppendicesPurpose:The appendices serve the purpose of providing detailed information of relevance to the project. The use of appendices for detailed information allows the main document to be shorter and more readable. All appendices should contain decision-relevant information. Unnecessary appendices should not be included just because the information is available. All appendices should be referred to in the text.Suggested Contents:The contents of the appendices will vary depending on the situation. The following are some of the appendices that may be included with an IAR: “Fit-up Compliance Monitoring Form” and the “List of Non-Compliant Items &

Approvals,” these forms are available on the intranet “Office Accommodation Allocation Limits” form Chronology of events (history of the project) NPMS Project Charter NPMS Feasibility Report NPMS Project Plan NPMS Compliance Checklist Risk Management Plan Community profile Market survey or summary of the market survey Summaries of building condition and building performance Description of options and relevant costs Time/space diagram List of assumptions from the financial analysis Analysis of non-financial factors Canadian Environmental Assessment Act, Environmental Assessment Report Project Sustainable Development Strategy with targets (LEED, energy efficiency,

GhG emissions reduction, water conservation, etc.) Project implementation schedule Detailed cost estimates for the proposed project

- 47 -

Page 52: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Communications Strategy

- 48 -

Page 53: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

- 49 -

Page 54: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Appendix A

The Investment Analysis ProcessInvestment analysis is a generic approach to decision making, embracing a range of evaluative techniques that challenge the judgement and analytical skills of the analyst. Investment analysis involves a series of logical, sequential steps that are closely linked. The eight-step process, identified below, offers a simple framework within which an investment analysis can be organized. It is recommended that the analyst document the findings and conclusions that he or she has reached at the conclusion of each of the eight steps. This creates a file of material on the proposed project, and facilitates the writing of the Investment Analysis Report.

The Eight Steps of Investment Analysis1. Define requirements2. Generate options3. Narrow the options4. Undertake financial analysis5. Undertake analysis of non-financial factors6. Undertake risk assessment7. Evaluate options8. Formulate recommendations

Step 1: Define RequirementsObjective:All projects start out with a need that must be met or a requirement that must be fulfilled. It is the duty of the analyst to determine, in appropriate detail, what this project is calling for. Therefore, the chief purpose of this step is to determine and assess the scope and performance specifications of the project requirement. At this stage, it is imperative for the analyst to determine essential and basic facts that will have to be considered throughout the life of the project ("project determinants") this will form the basis for a judgement about project success. Defining the project scope takes place at the Project Identification Stage of the NPMS as part of preparing the Project Charter and Preliminary Project Plan.Tasks:The analyst usually takes the following actions during this step: Visit the relevant sites, whether they be existing premises, or proposed sites (if

already identified)- 50 -

Page 55: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Hold discussions with the client or user groups Gauge the role, influence and expectations of stakeholders and hold preliminary

discussions as required Develop the PWGSC team that will review and assess objectives and requirements

of the proposed project. Consult relevant PWGSC policies and documents, such as the CBIS, AMP, BCR, etc.

Review all the relevant short, medium and long-term factors that may impinge on project success

Document objectives and scope fully in the NPMS Statement of Requirements and Project Charter/Project Plan respectively. For example, a space-based project may include the amount of space required by the client, the type of space required and when and where it is required

To the extent feasible, obtain client concurrence with objectives and scopeKey Questions:ü What are the relevant context and surrounding conditions (opportunities and

constraints) in which this project is being undertaken?ü What are the objectives of this project or undertaking?ü How urgent is the requirement? What are the timing constraints?ü Have all codes, standards, and policies, which may be applicable, been determined?ü Who are the stakeholders and what is their role and interest? Do they concur with

the objectives and scope as defined? Why or why not?ü What is the likely role of other departments or other levels of government in this

project?ü Are there any longer term trends that will impact (positively or negatively) on the

requirement for the facility under consideration?

Step 2: Generate OptionsObjective:Now that the objectives and operational requirements of the project have been firmly defined (in Step 1), the analyst is called upon to develop the full range of options that might plausibly meet the project requirements. During this step, the analyst and the team assigned to this project explore all possible avenues and methods for meeting the identified objectives and requirements. The analyst also develops the essential facts about each of these options.

Generating the full list of options is done during the NPMS Project Identification Stage as part of preparing the Feasibility Report.Tasks:The analyst usually takes a number of the following actions during this step:

- 51 -

Page 56: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Hold a brainstorming session with members of the project team to identify a complete list of options that may be considered

For space-based projects, check whether any buildings within the existing Crown inventory are potentially able to meet the objectives and requirements of the project

Survey local real estate markets to determine whether any existing or proposed private sector buildings are able to meet the objectives and requirements of the project

Consult with stakeholders about options they might be interested in and concerns that they may have

Depending on the nature of the project, it may be necessary to consult with municipal and urban community officials about possible options and any concerns that they might have concerning the project

Establish the basic facts and implications about each of the identified options without passing judgement

Key Questions:ü Have all plausible options for meeting the objectives and requirements of this project

been identified? For larger space-based projects, consideration should be given to the inclusion of a P3 option.

ü What are the basic facts and determinants about each of these options?

Step 3: Narrow the OptionsObjective:At this point, the analyst has a complete list of all available options for meeting the proposed project objectives and requirements and has completed an informative description of each option. It is not justifiable to give all options an in-depth treatment that PWGSC requires in an investment analysis. Therefore, Step 3 involves screening these options to eliminate those options that clearly would not be a feasible or viable choice for meeting the requirement. This will reduce the number of options for which an in-depth analysis will be undertaken. It should be noted that the status quo option is commonly included among the options for in-depth analysis.Narrowing down the list of potentially viable options for in-depth analysis is done during the NPMS Project Identification Stage as part of preparing the Feasibility Report.Tasks:The analyst usually takes a number of the following actions during this step: Review the objectives, requirements, context and conditions of the proposed project Develop a list of criteria or decision rules to be applied fairly and equally to all

options under consideration. Consistency with portfolio objectives should be one of the criteria for screening the options

- 52 -

Page 57: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Apply the criteria to screen out those options that cannot reasonably meet objectives and requirements

Document the selection of options meriting in-depth consideration through the preparation of the NPMS Feasibility Report

Key Questions:ü Were the options that were screened out clearly unfavourable? Is there any way that

the discarded options could be screened in and what is the likelihood of these conditions occurring? (i.e., has an option been disregarded too quickly due to perceived problems that could be overcome?)

ü Has the rationale for selection of options for in-depth analysis been documented?

Step 4: Undertake Financial AnalysisObjective:Step 4 involves the determination of the degree of financial viability of the potentially viable options using discounted cash flow analysis. The measures of financial viability include net present value (NPV), internal rate of return (IRR), and present value of the cost of accommodation (PVCOA). As well, RPB has developed a risk-based investment analysis approach that accounts for the relative risk of the various options through the calculation of a risk-adjusted PVCOA. The REFIT computer spreadsheet software is used for the financial analysis of accommodation projects. Tasks:The financial analysis process and the use of REFIT are fully described in a separate guide. The following is a summary of the main actions undertaken by the analyst during this step: In consultation with subject matter experts, determine and document all financial

assumptions, project costs and the life-cycle costs of long-term asset ownership associated with each option. Ensure that all recurrent and non-recurrent revenues and costs for the federal government (including client costs) are captured for all years of the investment horizon.

Use REFIT to calculate the DCF measures for each of the options: net present value, internal rate of return, and present value cost of accommodation (PVCOA). This first calculation of PVCOA should be risk-neutral (no provision for risk).

Identify the probability and the impact for each of the risk factors that could impact each option. Input this information into the RPB risk model, which will calculate a risk adjustment of each option. Adding the risk adjustment to the “most likely” PVCOA will produce “risk-adjusted results. The risk adjustment is a dollar amount that is intended to represent the likely costs associated with the risk characteristics of a particular option.

Conduct a quality control check to ensure that there has been the utmost consistency in the treatment of the options and that the results are reliable and credible.

- 53 -

Page 58: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Conduct a sensitivity analysis to determine to what extent the financially more attractive option is sensitive to variations in key input variables. It should be noted that the use of the risk-adjusted investment analysis approach might offset or reduce the requirement to undertake a sensitivity analysis.

Interpret the results of the discounted cash flow analysis. Ensure the assumptions and the results of the financial analysis are fully

documented.Key Questions:ü Have each of the options been treated consistently in terms of assumptions and input

variables?ü How do these options rank in terms of financial viability, both before adjusting for

risk and after, using the risk-adjusted PVCOA?ü Based on the sensitivity analysis, does a change in the assumptions result in a

different option becoming the preferred option? ü How is PWGSC to interpret the results from the discounted cash flow analysis?

Step 5: Undertake Analysis of Non-Financial FactorsObjective:In addition to the financial perspective, the analyst is called upon to address the qualitative non-financial issues relating to each of the options under consideration. Therefore, the purpose of this step is to review and evaluate the qualitative factors surrounding an investment decision. Non-financial issues primarily relate to strategy, timing, health and safety, environmental impact, tenant/user effects (such as program impacts or locational advantages), and policy considerations (such as heritage or the Good Neighbour Policy).Tasks:The analyst usually takes a number of the following actions during this step: Identify all of the non-financial factors that may have a bearing on the selection of

the preferred option. Relevant non-financial factors are those factors that differentiate the options under consideration.

Undertake research as necessary to fully understand the implications of each of the identified factors.

Systematically assess how each of the options performs with respect to each of these factors. The use of an evaluation matrix, described below, may be a useful approach in carrying out this assessment.

Document the results and overall conclusions of the analysis.Key Questions:ü What regulations, strategies, codes, policies and practices apply to this decision?

- 54 -

Page 59: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

ü Which non-financial factors have the greatest impact on the selection of the preferred option?

ü What overall findings can be drawn from the qualitative analysis with respect to the preferred option or options?

A Suggested Approach - Use of an Evaluation MatrixThe suggested approach for evaluating non-financial factors relative to the options under consideration is based on the development of an evaluation matrix, also known as a weighting and rating framework. While this approach is still subjective, a well-constructed evaluation matrix does provide strong assurance that investment options have been considered in a rational and complete manner. The evaluation matrix consists of a list of relevant factors, along with weightings that reflect their relative significance. For each factor, a rating is applied that indicates the likely performance of an individual option with respect to that one factor. Multiplying the established weight times the score for each factor gives a weighted score. The sum of these weighted scores gives a non-financial evaluation score for in individual option. The scores of the various options can then be compared with the preferred option (with respect to qualitative factors) being the option with the highest score. Criterion Weights: The criterion weight is a number that reflects the relative

importance of a particular criterion. Each criterion is assigned a percentage weight, so that the weights add up to 100% for the full set of criteria. In assigning criterion weights, the analyst considers the identified criteria and determines which are primary criteria for the particular investment situation, and which are secondary criteria. The difference in the weights for the criteria should not be so large as to negate the importance of all but the top weighted criterion.

Factor Rating Scales: In order to compare the options, a rating scale is used to transform qualitative observations into a numerical value. In this approach, each criterion has a scale of 0 (lowest) to 5 (highest). A rating of 5 would indicate that the option is highly responsive with respect to the factor, and the option enables objectives associated with the factor to be met. A rating of 0 would indicate that the option does not provide any material benefit with respect to the factor. The analyst uses the highest applicable rating, based on a combination of analysis and professional judgement. Ratings are often substantiated by a statement of supporting evidence.

The evaluation framework can assist the analyst in making appropriate trade-offs between the benefits provided by different options, and arriving at a recommended approach, which provides the greatest overall utility. The following example illustrates the layout of an evaluation matrix.

Example of Evaluation Matrix for Qualitative Analysis

Non-FinacialFactor

Weight Option 1 Option 2 Option 3

Rating Score Rating Score Rating ScoreFactor 1 30 4 120 3 90 4 120Factor 2 25 2 50 5 125 4 100

- 55 -

Page 60: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Factor 3 20 4 80 2 40 3 60Factor 4 15 5 75 1 15 4 60Factor 5 10 2 20 3 30 3 30Total Score 100 345 300 370

Step 6: Undertake Risk AssessmentObjective:The purpose of the risk assessment is to analyse the key risk factors associated with each of the options being considered in order that the relative riskiness of each option can be determined. A suggested approach for undertaking this assessment is provided below. However, other methodologies may be employed.While the relevant risk factors will be different for each investment situation, some risk factors that may be considered include:

Risk that the project may not fully rectify an identified problem; Risk of user needs not being met; Risk of changing requirements; Risk that forecast demand fails to develop; Risk of not meeting timing requirements; Risk of cost overruns; Risk of future performance being impaired; Risk of environmental degradation.

Tasks:The analyst may take the following actions during this step:

Identify all sources of risk associated with each option under consideration. Undertake a risk assessment for each element of risk for each option. The risk assessment is a product of the likelihood times the severity of the impact, as indicated below.

Very High Risk (10)

High impact and high likelihood

High Risk (5) High impact and medium likelihood, orMedium impact and high likelihood

Medium-High Risk (3)

Medium impact and medium likelihood

Medium Risk (2) Low impact and high likelihood, orHigh impact and low likelihood

Low Risk (1) Low impact and medium likelihood, orMedium impact and low likelihood

Very Low Risk (0) Low impact and low likelihood

- 56 -

Page 61: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Evaluate the overall level of risk associated with each option. This can be done using an evaluation matrix. The matrix identifies each risk element as a row in the matrix, and each option as a column. Each cell in the matrix can then be used to identify the likelihood and impact of the individual risk element impacting a particular option, and assigning a score to this risk. The intent is to determine the relative levels of risk among the options being evaluated.

Example of Evaluation Matrix for Risk Assessment

RiskFactor

Option 1 Option 2 Option 3

Risk Score Risk Score Risk ScoreFactor 1 High 5 Medium 2 Medium 2Factor 2 Medium 2 Low 1 Medium 2Factor 3 Low 1 Very

Low0 Low 1

Factor 4 Very Low

0 High 5 Low 1

Factor 5 Medium 2 High 5 Low 1Total Score 10 13 7

Determine an appropriate risk response. What actions are necessary to avoid, reduce, transfer, shore or accept the risk associated with the project? For example, one risk response may be to choose an option with a lower level of risk, or an option that allows risk to be transferred to a private sector partner. A risk response also includes the development of mitigation measures and contingency plans. Risk response strategies can be developed using scenario analysis, which involves developing an appropriate course of action to be taken in the event of a particular unfavourable event or outcome occurring.

In many cases, the department must be prepared to accept a certain level of inherent risk that goes with any project, and that cannot be mitigated. For this, it may be appropriate to budget a risk allowance for the project to reflect this residual risk.

Prepare a risk management plan for the preferred option. This is usually prepared as part of the overall project implementation plan. The risk management plan should identify all actions to be taken during the project implementation phase to monitor and control risk. Effective risk management also includes risk reporting to ensure that risk information is communicated to senior managers in the department, that corrective action is taken if required, and that the organizational learning occurs on the better management of risk.

Key Questions:ü What types and what level of risk is associated with each option?ü How does each option rank in terms of risk? Which option is the most risky and which is the least risky?ü How controllable are the key risks for each option? Generally, an option that carries risks that can

be mitigated is preferable to an option that carries risks that cannot be mitigated.

ü What mitigation measures could be employed to minimize the level of risk for the preferred option?

- 57 -

Page 62: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Step 7: Evaluate OptionsObjective:In this step, the analyst takes the findings of Steps 4, 5 and 6 and draws conclusions concerning which is the preferred option for this investment decision. In selecting a preferred option among the options under consideration, the analyst is challenged to demonstrate that financial, non-financial and risk considerations have been weighted appropriately, that all the options have received due and careful consideration, and that reasons for selecting one option over the others are clearly articulated. Tasks:The analyst usually takes the following actions during this step: Addresses the financial, non-financial and risk considerations systematically in

summary fashion. Selects the preferred option. This is the option that provides the greatest overall

value to the federal government once all relevant factors are considered. Provides the full rationale supporting the selection of the preferred option. In cases where there is a close second option, document the rationale supporting

this option and indicate under what conditions this option might be considered.Key Questions:ü Does the preferred option provide good "value for money". Do the benefits outweigh the costs?ü Does the preferred option excel by a clear margin? Is there a close second option?

Step 8: Formulate RecommendationsObjective:Once the preferred option has been identified, the analyst puts forward the recommendations associated with supporting this option. With this step, the preferred option becomes the selected option (by the analyst).Tasks:The analyst usually takes the following actions during this step: Prepares the recommendations that represent the investment decision, including

the appropriate approval authority to be sought. Prepares an Implementation Plan for the project. Proposes a project schedule, including the optimal date for project initiation and the

completion date. Identifies the source and availability of funding. Reviews briefly the involvement of the client and other parties and recommends the

steps to be taken to secure their role in the project. Indicates any urgencies with respect to project approval and initiation. Initiates the preparation of a Communications Plan, if required.

- 58 -

Page 63: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

- 59 -

Page 64: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

APPENDIX B

SPACE ENTITLEMENT BASED ON THEOFFICE ACCOMMODATION FRAMEWORK

- 60 -

Page 65: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

- 61 -

Page 66: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

APPENDIX C

SUSTAINABLE PROJECT DELIVERYINTRODUCTION

Sustainable development as an element of project delivery is mandated principally under four Federal Government initiatives, Canadian Environmental Assessment Act (CEAA), 1999 Cabinet Directive on Environmental Assessment of Policy, Plan and Program

Proposals, a "Strategic Environmental Assessment" (SEA), An amendment to the Auditor General Act establishing the Office of the

Commissioner of the Environment and Sustainable Development, and Canada's commitments under the Kyoto Protocol. Of these, the first two are focused on assessing the environmental impacts of a project or activity and identifying mitigation measures where required while the last two are more focused on establishing performance targets in support of a more sustainable society. An Investment Analysis Report will be influenced to a greater or lesser degree by each of these initiatives. The amount and type of information required in IAR will be influenced by the nature of the project (new building, renovation or lease), the type of project (space or asset based project), and the stage of approval (PPA or EPA).

CANADIAN ENVIRONMENTAL ASSESSMENT ACT (CEAA)

Space, rather than asset-based, IARs will have the greater possibility of being significantly effected by the CEAA and the 1999 Cabinet Directive on Environmental Assessment of Policy, Plan and Program Proposals. At the moment, CEAA requires Federal Departments and Agencies, including PWGSC to conduct an Environmental Assessment (EA) for all projects, as defined under the Act for which there is a "trigger". Under the Act and for the purposes of this discussion, a project is defined as an activity "in relation to a physical work, any proposed construction, operation, modification, decommissioning, abandonment or other undertaking in relation to that physical work". A "trigger" can be described in general terms as meeting any one of four conditions: A Federal Authority (Department or Agency) is the proponent of the project or

commits in some manner to having the project carried out in whole or in part; Makes or authorizes payments or provides a guarantee for a loan or any other form

of financial assistance to the proponent for the purpose of enabling the project to be carried out in whole or in part;

Sells, leases or otherwise disposes of land or any interests in land, or transfers the administration and control of those lands for the purpose of enabling the project to be carried out in whole or in part; or

Issues a permit or license, grants an approval or takes any other action for the purpose of enabling the project to be carried out in whole or in part.

- 62 -

Page 67: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Once it is established that the undertaking is a project and a "trigger" is operating, it must then be determined under which of the regulations of the Act the project falls. At the moment, a project that involves a new building or substantial modification to an existing building (changing its footprint or height by greater than 10%, or carrying out work with 100m of a surface body of water) will require an assessment. However, amendments to the CEAA will result in most PWGSC projects (with the exception of those project meeting either of the two criteria above), particularly those that relate to office accommodation, will fall within the category of projects included in the "Exclusion List" regulations. This regulation lists those types of projects that either are known to have insignificant environmental impacts or those projects that will be required to complete an environmental assessment under the jurisdiction of some other level of government, such as a province or municipality.The first stage of the EA process is a “Screening," which determines the degree of likely environmental impacts and the necessity for a more rigorous or comprehensive assessment. Because the CEAA requires that the EA must be undertaken before any irrevocable decisions are made, it is appropriate to examine these issues for the completion of an IAR at the earliest point because the options examined here can significantly affect the environmental impacts of a project. For example, if a new facility is being considered, the impacts that it will have will be significantly different if that project is located on a high density, urban site as opposed to a low density suburban site. If an investment decision is made on the basis of an analysis that did not take these environmental impacts into consideration, then the intent of the CEAA is not being respected. Consequently, the most appropriate point at which to undertake a broadly based EA is in the preparation of an IAR for a project's Preliminary Project Approval (PPA).Expert advice on the implications of CEAA can be obtained from the Environmental Assessment and Sustainable Project Delivery Group of Environmental Services Directorate, Professional and Technical Services Management, Real Property Branch.

STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA) - 1999 CABINET DIRECTIVE

Space Based IARsStrategic Environmental Assessments are required where decisions are to be taken by Cabinet, or in some circumstances, by Treasury Board Secretariat. Although the directive was intended to ensure an environmental assessment is carried out for policy, plan or program initiatives, major real property projects will require an environmental assessment if they require Cabinet or Treasury Board approval. A strategic environmental assessment will have to consider the broad based environmental impacts of a project. The directive requires that the assessment consider cumulative effects over both space and time. This statement means: that the issues must be examined and analyzed not only for a project's own

immediate impact but also how the environment is affected by that specific project as well as other past, current or future projects in its vicinity. A SEA must be integrated with other strategic planning tools such as the National Investment Strategy, the Community Based Investment Strategy, the Good Neighbour Policy, the

- 63 -

Page 68: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

current PWGSC Sustainable Development Strategy, and Plan for honouring our Kyoto Commitments.

in terms of "cumulative effects over both space and time,” the SEA must examine how the project may interact with other projects in its immediate vicinity and not only immediately but over an extended period of time. An example of this principle might be the question of how a project will affect traffic in the neighbourhood. Taken alone, the project's impact on traffic patterns may be minimal. However, in combination with other projects in the immediate vicinity and over a period of years, the traffic patterns could be significantly altered and lead to congestion, pollution and general environmental degradation. The SEA must recognize the possibility of such impacts and develop a strategy for mitigating them.

Environmental issues that should be considered in a SEA for a Space Based project include:Site: Ÿ urban core vs suburban perimeter

Ÿ transportation accessibility - personal vehicle use vs alternatives (traffic/parking)Ÿ local ecological valuesŸ landscaping and storm water management

Energy: Ÿ energy efficiencyŸ energy source mix - carbon fuels, hydro, nuclear, green powerŸ on-site power generation

Water: Ÿ reduced water consumptionŸ strategies for reuse and management

Occupant Issues:

Ÿ indoor environmental quality - air, light, noiseŸ occupant ability to control their local conditions

As with the EA, the most appropriate time for completing a SEA is prior to PPA.

Asset Based IARsStrategic Environmental Assessments for an asset-based IAR should be closely aligned with the Asset Management Plan, which in turn is based on NIS and CBIS. The examination of issues should be expanded to include the Good Neighbour Policy and the current PWGSC Sustainable Development Strategy. From the SEA perspective, if the asset itself has not been assessed, then one should be undertaken and then, for the project, a further assessment should be carried out to determine how the project would affect the asset and its environmental and sustainable development impacts.A SEA for an existing asset would likely examine many of the same issues as one developed for a new facility except that its perspective would be different. The issues include:Site: Ÿ Does the project enhance or detract from alternative modes of transportation?

Ÿ Does the project affect the local ecological values?Ÿ Does the project affect the site landscape and contribute to more effective storm?

- 64 -

Page 69: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Energy: Ÿ Does the project affect the assets energy efficiency?Ÿ Does the project affect the energy source mix - carbon fuels, hydro, nuclear, green power?Ÿ Does the project provide for on-site power generation?

Water: Ÿ Does the project reduce water consumption?Ÿ Does the project provide to water management and reuse?

Occupant Issues:

Ÿ Does the project affect indoor environmental quality - air, light, noise?Ÿ Does the project affect the occupants’ ability to control their local conditions?

PWGSC SUSTAINABLE DEVELOPMENT STRATEGY (current)

Space Based IARsThe 1995 amendments to the Auditor General Act included the requirement that Federal Departments and Agencies, including PWGSC, develop and table a Sustainable Development Strategy. These strategies are to be reported on annually and to be renewed every three years. They are subject to audit by the Office of the Commissioner of the Environment and Sustainable Development as well as the office of the Commissioner reporting directly to Parliament on its assessment of the progress made by individual departments and the Federal Government overall.PWGSC, in its third Sustainable Development Strategy (SDS), submitted for the period 2003 to 2006, made some significant commitments with respect to the management of its assets and project delivery. 1 These commitments were followed by further commitments in the SDS 2007 to 2009, which added a focus on leased buildings. The commitments of these two Departmental SDSs for sustainable project delivery, are summarized below (see the SDS for a more detailed version of the targets): Implement a Sustainable Building Policy and supporting guidelines by 2010; New construction designs, major renovations and acquisitions will meet LEED Silver

or BREEAM/Green Leaf or equivalent ratings. (In addition to the departments SDS commitments, public statements require that the construction of all new government of Canada office buildings meet LEED Gold, and that the same standard will be sought for long term leases);

Major projects will be compared on the basis of a building life-cycle assessment tool; New or rejuvenated buildings must be more energy efficient; Reduce water consumption; Reduce or eliminate toxic substances; Divert waste for construction activities and for building operations from landfills;

and Introduction of these principles into the Department's lease agreements.And specifically for leases:

1Document is available at http://www.pwgsc.gc.ca/sd-env/pdf/sds2003-e.pdf.

- 65 -

Page 70: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

All leases of 500 m2 the building will be managed to the equivalent of BOMA Go Green;

For leases of 10,000 m2 and greater, the lessor will conduct a BOMA Go Green Plus assessment.

Lease purchase buildings will meet the LEED Gold standard.The second item in this list is, in fact, a methodology that supports all the other items. The Leadership in Energy and Environmental Design (LEED ™) and Building Research Establishment Environmental Assessment Method (BREEAM) Green Globes™ are both recognized tools for measuring the environmental performance of a building in its design and construction. (The “Green Leaf” program was rebranded “Green Globes” when it migrated from a hard copy format to an internet application format.) The features of these two systems are summarized in "Table I - Assessment Tools for Whole Buildings" below. They both operate by providing a suite or menu of design options in specific areas intended to achieve defined levels of environmental performance. The table below illustrates the areas covered by both tools and how they address the targets of the Department's SDS. When assessing the various options for a project in an IAR, the degree to which these options successfully address these individual targets and the overall target of a LEED Silver or BREEAM Green Globes 3 Leaf rating must be taken into consideration. The overall targets have a built in flexibility as to how they are achieved but the objective to achieve a level of LEED Silver or 3 Green Globes is a solid commitment of the Department and has been included in the funding allotment for capital projects. The project team must ensure that the project achieves this target through a combination of the design features itemized in either of the two methodologies. As noted above, in the case of new office buildings, long term leases, or lease purchase, the appropriate target is LEED Gold.Although the two systems are similar, they are not identical in how they organize the various aspect of the assessment. For instance, while LEED places "Alternative Transportation" under the "Site" category on the argument that it is intimately associated with the characteristics of the site, BREEAM/Green Leaf places "Energy-efficient Transportation" under the "Energy" category on the argument the most significant aspect of the transportation issue is the energy associated with the daily commute to and from work. Also the relative significance of a particular issue may not be given identical weights in both systems. In the transportation example above, LEED assigns 4 points out of 70 to this aspect, or about 6% of the total points available. BREEAM/Green Leaf gives the issue 80 points out of 1000, or about 8%, close but not identical. Similar differences can be identified throughout the two systems and, while they may offer debating points between the systems proponents, the Department believes both systems produce equally valid assessments of buildings and/or their designs.Under the LEED system, there are a number of "Prerequisites" or aspects that must be included in the project in order for it to even be considered, such as "Erosion Control" under "Sustainable Sites" and "Building Commissioning" under "Energy & Atmosphere". The other aspects are "Credits" and design team selects which one under the six categories the project will try to incorporate into its specifications. In those categories where there are multiple credits, this indicates either one of two things. First, that there are a number of approaches to meet the requirement of the credit which can be

- 66 -

Page 71: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

applied individually or in combination or, two, that there are graded levels of achievement for that category and more points are awarded for greater achievement. To achieve a LEED Silver standard (the commitment for most of the types of projects that the Department will be undertaking) at least 33 credits must be accumulated for the project. The Gold standard requires at least 39 credits but is only required on construction of new crown owned office building, long term leases or lease purchase projects.Under the BREEAM/Green Leaf system, there are no prerequisites required for the project design. Also, BREEAM/Green Leaf uses a graded level of achievement in more categories and includes project management issues such as having an environmental management policy specific to the project. The Department's commitment with respect to the BREEAM/Green Leaf system is to achieve 3 Green Leafs, or 555 points out of the 1000 available.

- 67 -

Page 72: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Table I - Assessment Tools for Whole BuildingsLEED-Canada BREEAM Green GlobesSustainable Sites 14 Project Management Policies &

Practices50

Erosion Control P 0 Env. Management & Integrated Design

20

Site Selection C 1 Procurement Policy 10Urban Redevelopment C 1 Commissioning & Emergency

Response20

Brownfield Redevelopment C 1 Site 115Alternative Transportation C 4 Identification of Appropriate Area 30Reduced Site Disturbance C 2 Site Microclimate & Ecology 30Storm Water Management C 2 Enhanced Watershed Features 20Landscape & Ext. Design (Heat Island)

C 2 Enhance Local Ecology 35

Light Pollution C 1 Energy 380Energy & Atmosphere 17 Energy Performance 380Building Commissioning P 0 Energy Demand Minimization 114Minimum Energy Performance P 0 Energy-efficient Systems 66CFC Reduction in HVAC&R Equip.

P 0 Renewable Energy 20

Optimized Energy Performance C 10 Energy-efficient Transportation 80Renewable Energy C 3 Water 85Additional Commissioning C 1 Water Performance 30Ozone Depletion C 1 Water-conserving Features 45Measurement & Verification C 1 Minimize Off-site Water Treatment 10Green Power C 1 Resources - Systems & Bldg

Materials100

Water Efficiency 5 Low Life-cycle Environmental Impact

35

Water Efficient Landscaping C 2 Minimize Consumption of Material Res.

20

Innovative Waste Water Technologies

C 1 Reuse of Existing Building 20

Reduced Water Consumption C 2 Building Adaptability 5Materials & Resources 14 Building Disassembly 5Storage & Collection of Recyclables

P 0 Reuse & Recycling of Demolition Waste

5

Building Reuse C 3 Facilities for Recycling & Composting

10

Construction Waste Management C 2 Emission, Effluents & Other Impacts

70

Resource Reuse C 2 Minimize Air Emissions 15Recycled Content C 2 Minimize Ozone Depletion 20Local Regional Materials C 2 Surface Run-off/Sewer

Contamination10

Rapidly Renewable Materials C 1 Pollution Minimization 25Certified Wood C 1 Indoor Environment 200Durable Building C 1 Effective Ventilation Systems 55Indoor Environmental Quality 9 Source Control of Indoor

Pollutants50

Minimum IAQ P 0 Lighting Design/Integration 45Tobacco Smoke Control P 0 Thermal Control 20Carbon Dioxide (CO2) Monitoring C 1 Acoustic Control 30Increased Ventilation C 1

- 68 -

Page 73: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

EffectivenessChemical & Pollutant Source Control

C 1

Controllability of Systems C 2Thermal Comfort C 2Daylight & Views C 2 1 Green Globe: 150 - 354Innovation in Design 5 2 Green Globe: 355 - 554Innovation in Design C 4 3 Green Globe: 555 - 704LEED Accredited Professional C 1 4 Green Globe: 705 - 854P = Prerequisite C = CreditCertified: 26 - 32 Silver: 33 - 38Gold: 39 - 51 Platinum: 52 - 70

5 Green Globe: 855 - 1000

Note: These are simplified outlines of these two rating systems. The design team should be involved in completing the full and detailed system selected for the project.

Where the "space" under consideration does not constitute an entire building but only a portion of it, for example the leasing of space, the Department's sustainable development commitment is to try to locate such space in a building that would meet the same level of environmental performance as a crown-owned building (using the LEED or BREEAM/Green Leaf rating systems). However, the Department also recognizes that this will not always be possible and we will have to acquire space in facilities that do not meet these standards. Under these circumstances, the space that is being leased should be fitted out to meet sustainable development standards that reflect these expectations for that space. To assist the planning and design process for these space fit-up projects and to measure their success, assessment tools exist for both the LEED and BREEAM/Green Leaf system, referred to as "Commercial Interior" systems. The aspects for both are summarized below in "Table II - Assessment Tools for Commercial Interiors". These two systems operate in the same way relative to their original systems except they have been adapted to limit the assessments to those issues that are relevant to a space fit-up project. There is a major exception, however, in the case of the LEED system. The LEED CI, as it is known, has been developed only for the US at this point and is not yet adapted to the Canadian market. This is anticipated in the future, but the timing is uncertain. The BREEAM/Green Leaf system, on the other hand, was developed specifically for a PWGSC project and reflects Canadian market conditions. In the case of either system, it is clear that they are both closely related to the original assessment system but do not include issues that are beyond the scope of space fit-up projects. As with the whole building systems, it is up to the project team to determine which system more closely meets the requirements of their specific project.

Table II - Assessment Tools for Commercial InteriorsLEED-Canada BREEAM Green GlobesGREEN

LEAFSustainable Sites 7 Project Mgmt Policies & Practices 70Select LEED Certified Building or C 3 Goal Setting & Prioritizing 20select building which includes some Environmental Purchasing 20combination of following options: Commissioning Plan - Documentation 10-- Brownfield Redevelopment- Energy Demand Minimization 100-- Water Efficient Irrigation Space Optimization 15-- Reduced Water Use (for entire bldg.)

Ventilation & Thermal Control 25

- 69 -

Page 74: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

-- Innovative Wastewater Tech.- Illumination 30-- Storm Water Management Building Envelope - Retrofitted

Windows20

-- Reduced Light Pollution Energy Metering 10-- Reduced Heat Island Effect Water 20-- Onsite Renewable Energy Water Efficient Fixtures - If Added 10-- Other Quantifiable Env. Performance

Landscaping - If Affected 10

Urban Redevelopment C 1 Resources - Systems & Bldg Materials

150

Alternative Transportation C 3 Low Life-cycle Environmental Impact 200Energy & Atmosphere 12 Minimize Use of Non-Renewable

Res.60

Minimum Energy Performance P 0 Durable, Low-maintenance Materials 20CFC Reduction in HVAC&R Equip. P 0 Adaptability, Disassembly & Reuse 22Energy Perform., Lighting Power C 3 Reuse & Recycling of Demolition

Waste10

Energy Perform., Lighting Controls C 1 Facilities for Recycling & Composting 18Energy Perform., HVAC C 2Energy Perform., Equip. & App. C 2 Emission, Effluents & Other

Impacts50

Enhanced Commissioning C 1 Pollutant Control - Asbestos 20Measurement & Verification C 2 Hazardous Materials Storage &

Control20

Green Power C 1 Integrated Pest Management 10Water Efficiency 2 Indoor Environment 160Reduced Water Consumption C 2 Effective Ventilation Systems 25Materials & Resources 14 Source Control of Indoor Pollutants 40Storage & Collection of Recyclables P 0 Day Lighting 32Commitment to Tenant Space Reuse

C 1 Lighting Design 21

Reuse of Interior Non-Strut. Component

C 2 Thermal Comfort 20

Construction Waste Management C 2 Acoustic Control 22Resource Reuse C 3Recycled Content C 2Local Regional Materials C 2Rapidly Renewable Materials C 1Certified Wood C 1Indoor Environmental Quality 17Minimum IAQ P 0Tobacco Smoke Control P 0Outdoor Air Delivery Monitoring C 1Increased Ventilation C 1Chemical & Pollutant Source Control

C 1

Construction IAQ Management C 2Low Emitting Materials C 5Controllability of Systems C 2Thermal Comfort C 2Daylight & Views C 3Innovation in Design 5 1 Green Globe: 83 - 195Innovation in Design C 4 2 Green Globe: 196 - 305LEED Accredited Professional C 1 3 Green Globe: 306 - 387P=Prerequisite C=Credit Certified: 21-26 4 Green Globe: 388 - 470Silver: 27-31, Gold: 32-42, Platinum: 43-57 5 Green Globe: 471 - 550

- 70 -

Page 75: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Asset Based IARsAn asset-based IAR will approach the issue of sustainable development in a slightly different manner. Progress towards sustainable development in these cases will be tied to the individual asset's Asset Management Plan (AMP) and through it to the asset’s Strategic Environmental Assessment. Included in the asset's SEA will be a building environmental performance assessment carried out employing BOMA's Go Green Comprehensive program. (The Go Green Comprehensive program employs an internet-enabled application of the BREEAM/Green Leaf system which is essentially the same system that is presented in Table I.) Managing the asset-based IARs in this manner does presuppose that these asset evaluations are already in place and integrated into the asset's SEA, which is not the case for all PWGSC assets. However, BOMA Go Green Plus assessments are a requirement of the SDS 2007 to 2009 for PWGSC Crown-owned office buildings and must be completed for all these assets by March 2010.The significance of this approach is that the Department will not evaluate individual projects for their sustainability but will do so as these projects affect the asset in which they are taking place through the impact they will have on the Go Green Comprehensive assessment for that asset. For example, if a BMP recommends the replacement of an asset’s heating boiler, the sustainability of that replacement project will be judged by the difference it makes in the overall asset performance. The project may increase the energy efficiency of the asset sufficiently to increase the score for the energy section of the assessment and improve the overall score of the asset. It may even move the asset into a new, higher level of recognition. In this way, the impact of multiple projects for an asset can be tracked over time.

- 71 -

Page 76: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Appendix DTerminology Used in Real Property ManagementGeneral Real Estate Terms

ABANDONMENT - The act of giving up or relinquishing all rights to a property without intention of reclaiming it, thereby causing the availability of the property for appropriation by another person or authority. The act of abandoning an intention to expropriate or an expropriated interest under the Expropriation Act. (Fr. - Abandon)

ABSTRACT OF TITLE - A condensed summary or synopsis of a title to a parcel of real estate, showing the original letters patent, subsequent conveyances, mortgages, and all recorded transactions pertaining to the title. (Fr. - Résumé des titres)

ACCELERATION CLAUSE - A clause in a loan contract or mortgage which permits the lender to require the immediate repayment of the entire balance if certain term of the contract is breached or a condition for repayment met. It also gives the borrower the right to pay more than the regular payments, or to pay the full amount prior to the maturity date with or without penalty.(Fr. - Clause de remboursement anticipée)

ACCESS - The means of approach to real property. It could be a walkway, or in the case of an easement, a right-of-way.(Fr. - Accès)

ACCESS RIGHT - The right an owner has to enter onto and exit from his property by street or highway, by right-of-way, or by other means.(Fr. - Droit d'accès)

ACCOMMODATION OPERATION REVOLVING FUND (AORF) - A fund created to account for all revenues obtained from the provision of service and management of accommodation and for all expenses and expenditures required to manage and provide the service and accommodation. Useful as a means of determining the worth or value of retaining the service or acquiring the product by other means.(Fr. - Fonds renouvelable de l'exploitation des locaux (FREL))

ACCUMULATED COST - Total of all historical costs to the date the accumulated cost is prepared. Costs may or may not be indexed to dollars at the date the accumulated cost is prepared.(Fr. - Coût cumulatif)

ADDITION - An approach to increasing Crown-owned accommodation whereby the Crown calls tenders on complete plans and specifications to construct an addition to an existing improvement on Crown land. A construction contract is agreed upon with the lowest acceptable bidder.(Fr. - Agrandissement)

AD VALOREM - A latin legal term: "According to the value".(Fr. - Ad valorem)

ADVERSE POSSESSION - A way of acquiring title to property without a deed, by making a claim and meeting certain statutory requirements. The law gives an occupant of land who maintains "actual, open, notorious, exclusive and continuous occupancy of property" for a specific statutory period the right to claim legal title to that property. The owner who has either abandoned or "remained silent" during a statutory time may not later claim title to the property. The process is similar for easements, except in Quebec. In Quebec it is known as acquiring property by prescription.(Fr. - Possession acquisitive)

- 72 -

Page 77: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

AFFIDAVIT OF TITLE - A sworn written statement by a seller declaring that he owns the property in question, that no one made any claim to it, and that there are no liens or judgments against him which affects the title to the said property.(Fr. - Affidavit relatif au droit de propriété)

AGREEMENT OF PURCHASE AND SALE - A written contract whereby a purchaser agrees to buy and a seller agrees to sell certain property under specific terms and conditions.(Fr. - Convention de vente et d'achat)

AIR RIGHTS - The right to inclusive and undisturbed use and control of a designated air space within the perimeter of a stated land area and within stated elevations. Such rights may be acquired for the construction of a building above the land or building of another, or for the protection of the light and air of an existing or proposed structure on an adjoining lot.(Fr. - Droits sur l'espace aérien)

APPRAISED VALUE - Value estimated by an appraiser.(Fr. - Valeur estimative)

ARM'S LENGTH TRANSACTION - A transaction freely arrived at in the open market, unaffected by abnormal pressure or by the absence of normal competitive negotiation as might be true in the case of a transaction between related parties.(Fr. - Transaction sans lien de dépendance)

ASSESSED VALUE - The value of property as determined for taxation purposes in accordance with assessment law.(Fr. - Valeur imposable)

ASSIGNMENT - The transfer of contractual or other rights to another person such as the transfer of an interest in a bond, mortgage, lease or other instrument. (Fr. - Cession)

ASSIGNMENT OF MORTGAGE - Legally, a mortgage is considered personal property except in Quebec, and thus can be transferred by a simple bill of sale. But, for his own protection, the person buying the mortgage takes a formal written instrument - called the assignment of mortgage - which fully describes the assignee of the mortgage, the amount due on the principal, and the interest on the mortgage debt. It normally gives a description of the mortgaged property and indicates the Land Registry Office in which it is registered. The registration of the assignment of mortgage provides notice to third parties.(Fr. - Cession de l'hypothèque)

BALANCE SHEET - A statement of financial position of an economic unit disclosing as at a given moment its assets, liabilities and ownership equities.(Fr. - Bilan)

BALLOON PAYMENT - In finance, the term refers to the unamortized principal amount of a mortgage or long-term loan, which is paid off in a lump sum at the end of the term.(Fr. - Dernier paiement majoré)

BILL OF SALE - A document that testifies to the sale of personal property, such as an automobile. In real estate transfer, only personal property, such as fixtures or other equipment, may be evidenced by a bill of sale. (Fr. - Acte de vente)

BLANKET MORTGAGE - A mortgage, which affects several properties. Several properties under one mortgage. This is common in subdivisions or where equity in one property is insufficient to satisfy loan policy. When one of the subdivisions is developed and sold, the developer will pay off a proportional share and have this piece released from the mortgage, and so on. (Fr. - Hypothèque générale)

- 73 -

Page 78: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

BOOK VALUE - The net amount at which an asset or asset group appears on the books of account, as distinguished from its market value or some intrinsic value. The face amount of a liability less any unamortized discount and expense.(Fr. - Valeur comptable)

BUILD TO LEASE - An agreement, which provides for the development of real property (erecting a building) by the property (land) owner in accordance with the specifications of the lessee of the said property. The building is usually constructed for only one tenant. Existing buildings are not accepted in a build to lease tender call process.(Fr. - Construction à des fins de location)

BUY BACK - An approach to providing Crown-owned accommodation whereby a party agrees to construct an improvement on his or the Crown's land and the Crown agrees to purchase the improvement (and land) at a specific price after construction is complete. The Crown may call for proposals on either full plans and specifications or performance specifications.(Fr. - Vente à terme)

CAPITAL COST ALLOWANCE (CCA) - The allowable capital depreciation claim against an asset, which produces an income. As it affects leases, the owner is entitled to claim depreciation on his buildings or improvements thus reducing the income tax payable on certain profits arising from the rental of the same.(Fr. - Déduction pour amortissement (DPA))

CASH FLOW (pretax) - Amount of residual income after allowing for all charges relating to the operation of the property and mortgage debt service (interest and principal payments). (Fr. -  Flux Monétaire)

CAVEAT EMPTOR - Latin sentence meaning "Let the buyer beware". .(Fr. - Caveat emptor)

CBD - Central business district.(Fr. - Centre-ville)

CHAIN OF TITLE - A compilation, in chronological order, of the transfers of the title to real property as extracted from the records in the Land Registry Office.(Fr. - Titres successifs)

CHATTEL - Any property other than (freehold land) real property. Chattels personal are movable, tangible articles of property.(Fr. - Biens meubles)

CLOSING DATE - The date stipulated in the Agreement of Purchase and Sale for the completion of the real estate transaction.(Fr. - Date de Transfert de Propriété)

CLOSING STATEMENT - The adjustment of accounts between the Vendor and the Purchaser of real property relating to the sale price, taxes, public utilities, mortgage, fuel, etc. The vendor pays all his expenses to that date (such as his proportional share of fuel, real estate taxes etc.). He credits money prepaid and debits bills not paid; the end calculation will show either a credit or a debit. The closing statement is normally prepared by the lawyer, or notary in Quebec.(Fr. - Relevé de clôture)

CONFORMING USE - A development of land, which is compatible with zoning restrictions.(Fr. - Utilisation conforme)

CONTRACT - An agreement enforceable at law. An essential feature of a contract is a promise by one party to another, or by two parties to each other, to do or forbear from doing certain specified acts.In order for a contract to be valid and legally enforceable there must be:

- 74 -

Page 79: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

capacity to contract; intention to contract; consensus as to the terms of the contract; valuable consideration; legality of purpose; and certainty of terms.

(Fr. - Contrat)

CONTRACT RENT - Payment for the use of property designated in a lease. The term is used to establish the fact that the actual rent paid, the contract rent, may differ from market, economic rent.(Fr. - Loyer contractuel)

CONVEYANCE - The transferring of real estate or the interest in it from one person to another. It may be a deed, mortgage, lease, but not a will. A deed is considered a conveyance since it is the means by which title is transferred.(Fr. - Transfert de proriété)

COVENANT - An agreement, convention or promise of two or more parties, by deed in writing, signed, sealed and delivered, by which either of the parties pledges himself to the other that something is either done or shall be done, or stipulates for the truth of certain facts. In common parlance, any agreement, whether under seal or not. (See also Restrictive Covenant)(Fr. - Engagement formel)

COVENANT OF QUIET ENJOYMENT - The contractual right of a grantee of property (and also of any person deriving title from him) to the enjoyment of the property without any interruption or disturbance by the person conveying the property (or by any person on his behalf, or claiming through him).(Fr. - Droit de jouissance paisible)

CROWN-FINANCED CONSTRUCT - An approach to providing Crown-owned accommodation whereby the Crown calls tenders on complete plans and specifications to construct an improvement on Crown land. A construction contract is agreed upon with the acceptable bidder.(Fr. - Construction financée par la Couronne)

CURRENT VALUE - Representative of value in use to the owner. Assumes that a market value is not required as the use is intended to continue, and if the property was sold would have to be replaced in order to continue in that use. Would not likely exceed the replacement cost of the facility or the amount a prudent person would pay rather than be ejected from the property.(Fr. - Valeur courante)

DEBT - Money, goods or services owing to another by virtue of an agreement, expressed or implied, giving rise to a legal duty to pay.(Fr. - Passif, dette)

DEBT/EQUITY RATIO - Ratio of debt to equity expressed as a ratio or a percentage.(Fr. - Ratio d'endettement)

DECREE - An edict, a law, an order from one in authority, or a court order that compels someone to do something.(Fr. - Décret)

DEDICATION - The voluntary giving of private property to some public use by the owner, as the dedication of land for streets, schools, etc., in a development.(Fr. –  Affectation)

DEED - A written instrument, signed, sealed and delivered, by which one person conveys land or an interest in land to another. The term may include a mortgage of real property. In Civil law "notarial deed" means a deed

- 75 -

Page 80: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

executed en minute or en brevet before one or more practicing notaries.(Fr. - Acte Formaliste))

DEED, ADMINISTRATOR'S - A deed by a person lawfully appointed to manage and settle the estate of a deceased person who has left no executor. (Fr – Acte d’un Administrateur)

DEED, BARGAIN AND SALE - A contract for the sale of any interest or estate in land, or of chattels, followed by payment of the agreed price. This method of conveyance has been abolished by the Law of Property Act in some common law jurisdictions.(Fr. - Acte de négociation et de vente)

DEED DESCRIPTION - A recitation of legal boundaries of a parcel of land as contained in a deed of conveyance.(Fr. - Description de l'acte)

DEED, QUITCLAIM - A form of conveyance whereby whatever interest the grantor possesses in the property described in the deed is conveyed to the grantee without warranty of title.(Fr. - Acte de transfert par renonciation)

DEED RESTRICTION - For any number of reasons, a seller may impose restrictions on the land he is conveying, perpetually or for a limited time. Thus, deed restriction is a limitation, which passes with the land regardless of owner, most commonly limiting the type of use or intensity of use of the real estate.(Fr. - Restriction à l'acte)

DEED WITH FULL COVENANTS - Also called a warranty deed, it contains full covenants and is considered the best deed to the purchaser of real property. There is a statutory short form that lists the five covenants. They are: 1) That said . . . is seized of said premises in fee simple, and has good right to convey the same; 2) that the party of the second part shall quietly enjoy the said premises; 3) that the said premises are free from encumbrances; 4) that the party of the first part will execute or procure any further necessary assurance of the title to said premises; and 5) that said . . . will forever warrant the title to said premises.(Fr. - Acte formaliste avec garantie complète)

DESCRIPTION OF PROPERTY - Because real property is fixed and permanent, it must be given an exact description, especially when conveying title. There are many ways to describe land, including: metes and bounds (the measure and direction); by tract subdivision, by lot or street number, by monuments (identifying boundaries by streams, etc.), or by a government survey. See also Deed Description, Legal Description.(Fr. - Description du bien (immobilier))

DOMINANT ESTATE or TENEMENT - A property that benefits from an easement. That to which a servitude or easement is due, or for the benefit of which it exists. The property subject to an easement is known as the servient tenement. (Fr. - Fonds dominant ou Tènement)

EASEMENT - An easement is a right enjoyed by one land owner over the land of another and is obtained for a special purpose rather than for general use or occupation. Once granted, an easement attaches to the land and binds subsequent owners. An essential requirement of an easement is that there must be a dominant tenement (the land which is to benefit from the easement) and a servient tenement (the land subject to the easement). The most common type of easement is a right-of-way. (Fr. - Servitude (de Common Law))

ECONOMIC RENT - A synonym for market rent, it is the amount a person dealing at arm's length (the market) would be willing to pay for the use of property designated in a lease. Unlike contract rent, economic rent varies over the period of a lease and is always stated in relation to a specific date. It is the amount for which the property could have been rented for at the date of valuation if it had been available for rent to a new tenant.(Fr. - Loyer économique)

- 76 -

Page 81: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

ECONOMIC VALUE - Value as determined by the Income Approach to value.(Fr. - Valeur économique)

EMPHYTEUTIC LEASE or EMPHYTEUSIS - In Quebec only, is a contract by which the proprietor of an immovable conveys it for a time to another, the lessee subjecting himself to make improvements, to pay the lessor an annual rent and to such other charges as may be agreed upon. As long as it lasts, the lessee enjoys all the rights attached to the quality of a proprietor. The duration of emphyteusis cannot exceed ninety-nine years and must be for more than nine. [6](Fr. - Bail emphytéotique ou Emphytéose)

ENCROACHMENT - The unauthorized extension of the boundaries of land. A situation in which any building or part of a building goes outside the boundary line of a parcel of land and intrudes on the land of another. (Fr. - Empiètement)

ENCUMBRANCE - A claim, lien, charge or liability attached to and binding on real property. Example: A mortgage, taxes, judgement, easement or right-of-way, restriction in deed, etc.(Fr. - Charge)

EQUITY - Any right or claim to assets. An interest in property or in business, subject to claims of creditors.(Fr. - Valeur Nette)

ESCALATION or ESCALATOR CLAUSE - A clause in a mortgage or lease, which provides for an increase of payment at will or at periodic intervals, upon specific situations as stated in the mortgage or lease. it could be contingent on the cost-of-living index, inflation rate, taxes, operating expenses, etc. (Fr. - Clause d'échelle mobile)

ESCROW - A writing, deed or funds delivered by the grantor, promisor or obligor into the hands of a third person, to be held by the third person until the happening of a contingency or performance of certain obligation, and then by him delivered to the grantee, promisee or obligee.(Fr. - Contrat de Dépôt entre les mains d’un tiers)

EXPROPRIATION - The compulsory (i.e. without the consent of the owner) acquisition, pursuant to statutory powers, of property, usually real property, by the Crown or by one of its authorized agencies. Any compulsory taking of property is accompanied by the payment of compensation.(Fr. - Expropriation)

FEE, FEE SIMPLE, FEE ABSOLUTE - The absolute ownership of real property with unlimited possession, control, and enjoyment, unconditional power to dispose of the property during the owner's life. An inheritable estate. (Fr. - Fief, Fief simple, Fief absolu)

FINANCIAL LEASE - A contractual commitment on the part of a lessee, which requires a series of payments to be made for the use of an asset over the service life of the asset. Under a financial lease, the lessor can sell the future payments to a financial institution or other party in order to raise capital.(Fr.  Crédit Bail)

FLOOR SPACE INDEX (FSI) - A ratio of the gross floor area of a building to the total area of the site. Also known as FAR (Floor Area Ratio) or FSR (Floor Space Ratio).(Fr. - Indice de superficie des locaux)

FORESHORE - The strip of land that lies between the high and low tide lines and that is alternately wet and dry according to the flow of the tide. Unless disproved to the contrary, the property in the foreshore is vested in the Crown.(Fr. - Lais)

GRADUATED LEASE - A lease, which provides for a certain rent for the initial period followed by periodic increases or decreases in the rent over the years of the lease.(Fr. - Bail à loyer variable)

- 77 -

Page 82: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

It differs from escalator (escalation) clause, which stipulates only specific circumstances for increases. (Fr. - Bail à loyer variable)

GRANT - A transfer of title to property real or personal by deed or any other document. A generic term applicable to all transfers of real property.(Fr. - Cession)

GRANTEE - The person who receives title to real property; the buyer.(Fr. - Cessionnaire)

GROSS INCOME - Revenues before deducting any expenses. The term is synonymous with gross revenue.(Fr. - Recettes brutes)

GROSS LEASE - The antonym of a net lease. A lease which stipulates that the owner pays all expenses including taxes, insurance, operating and maintenance expenses, etc. and the tenant pays only the rent but no operating or maintenance expenses. (Fr. - Bail brut)

GROUND LEASE - A lease, which gives the right of use of land. Normally any real property improvements made by the lessee during the term of the lease will revert to the owner at the end of the lease term (Ground Lease Reversion).(Fr. - Bail Foncier)

GROUND RENT - The rent paid for the right of use and occupancy of a parcel of land; or that portion of the total rental paid that is considered to represent a return upon land only.(Fr. - Loyer foncier)

HABENDUM CLAUSE - Portion of deed beginning with words "To have and to hold". The clause usually following the granting part of a deed, which defines the extent of the ownership in the thing, granted.(Fr. - Clause de Désignation)

HISTORICAL COST - Original cost of acquisition of a property at the date of acquisition.(Fr. - Coût d'origine)

HYPOTHEC - In Quebec law, real right or charge, which encumbers an immovable property to secure the fulfillment of an obligation of a debtor (usually repayment of a loan). It has similar function as mortgage.(Fr. - Hypothèque)

INDEMNIFY - Legally it means, to save harmless, to secure against loss or damage; to give security for the reimbursement of a person in case of an anticipated loss falling upon him. To make good a loss which one person has suffered in consequence of the act or default of another. For example, landlords use this clause to relieve them of any claims by a tenant; sellers use it to protect other brokers from claiming commissions, etc.(Fr. - Indemniser)

INTEREST - Right in real property. (Has also other meanings)(Fr. - Droit réel immobilier)

INSTRUMENT - In relation to real estate, a written legal document such as a deed, a contract of sale, lease, will, or the like. (Fr. - Acte instrumentaire)

JOINT TENANCY - A situation, in which two or more individuals own inseparable interests (an undivided interest) in a real property, i.e. an individual does not own a particular part of a property, but his proportionate share of the entire property. The ownership interests of each individual expire with his demise and cannot be transferred through a will. Thus, if one owner dies, the other receives his share or interest.(Fr. - Propriété conjointe)

- 78 -

Page 83: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

LAND - In law, land includes not only the surface but all that is under the surface, including minerals and oil and everything above the surface including the buildings on the land and the column of air as well.(Fr. - Bien-fonds)

LAND SURVEY - As all parcels of land must have definite and indisputable boundaries and identifications, it is necessary to physically chart (survey) the land to get its accurate boundaries. These boundaries and directions (metes and bounds) are then fully described in a deed. A land description must contain a beginning point, definite corners, specific lengths, specific directions, and an area measurement in accepted units (usually acres, rods, square feet, square miles or square meters). [2](Fr. - Arpentage)

LEASE - A contract between the owner of real property (lessor) and another party (lessee) for the possession and use of the property for a specified term in return for rent or other income.(Fr. –  Bail)

LEASEBACK - A simultaneous sale of real estate and lease of the property to the seller. The buyer becomes the lessor, or landlord.(Fr. - Cession-retour locatif)

LEASEHOLD - A property held under tenure of lease. The right of use and occupancy of real property by virtue of a lease agreement.(Fr. - Tenure à bail)

LEASEHOLD IMPROVEMENTS - The improvements and/or additions to leased property made by either the landlord or the tenant. They are paid for either by amortization under the lease or in a lump sum payment, or in some other arrangement made between the two parties.(Fr. - Améliorations locatives)

LEASE PURCHASE - A lease wherein the owner of the real property has agreed to sell the property upon the termination of the lease contract. Various forms of the lease purchase are as follows:(Fr. - Bail-achat)

LEASE WITH AN OPTION TO PURCHASE - The option to purchase the real property at a determined amount during or at the end of the lease term. The lessee exercises this option by terminating the lease contract at one of the pre-specified dates during the lease or at the end of the lease term and paying the purchase price applicable to the date of termination. The purchase price is predetermined and usually based on some pricing formula such as the present worth of the unpaid rent.(Fr. - Bail avec option d'achat)

LEASE - LEASEBACK - An approach to creating a real property improvement whereby the owner of a land, leases it to another party (ground lease) under an agreement whereby the party will construct an improvement and lease it back to the owner. Under varying agreements the landowner may have an option(s) to purchase the improvement during or at the end of the leaseback term. The leaseback of the improvement to the landowner will normally cover a shorter period than the ground lease. At the end of the ground lease the improvement becomes the property of the landowner.(Fr. - Bail-retour locatif)

BUILD TO LEASE PURCHASE - A form of the above (A and B) whereby a party constructs an improvement for the landowner, having entered into a lease purchase agreement.(Fr. - Construction/bail-achat)

LEASE TENDER (PROPOSALS) - The Crown invites bids from the private sector property owners offering to lease space. The bids received are point rated against pre-established criteria. Certain minimum specifications must be met. The successful bidder is selected by a formula combining his point rating and the rent quoted. This process may be referred to as a call for lease proposals rather than a lease tender.(Fr. - Appel d'offres de location (concours))

LEGAL DESCRIPTION - A statement containing a designation by which land is identified according to a system set up by law or approved by law.(Fr. -  Description Officielle)

- 79 -

Page 84: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

LETTING - A letting is in law the same as a lease. As the term is used in Public Works, the Department, in the position of the landlord, agrees to "let" another government entity use the real property for a specific period of time for rent or other income.(Fr. - Concession de loyer)

LICENCE (OF OCCUPATION) - Permission or authority to enter on land and to do particular act or series of acts on land of another. A licence passes no interest in land, and is always revocable. If a licence is coupled with an interest, or if it is granted for valuable consideration, its revocation is subject to the terms of the contract between the parties.(Fr. - Licence (d'occupation))

MARKET VALUE

The highest price in terms of money which a property will bring in a competitive and open market under all conditions requisite to a fair sale, the buyer and seller each acting prudently, knowledgeably and assuming the price is not affected by undue stimulus.

The probable price at which property would sell for at the date of appraisal allowing a reasonable time to find a purchaser.

(Fr. - Valeur marchande)

METES AND BOUNDS - Metes (measures in meters) and bounds (direction in degrees) make possible to describe completely and accurately boundaries in real property.(Fr. - Bornes et limites)

MORTGAGE - Conveyance of an interest in land as security for a debt. A contract by which a person binds the whole or a portion of his property in favour of another, to secure the execution of some engagement, such as the payment of money. (Fr. - Hypothèque)

NET INCOME - Ordinarily, net income is synonymous with net profit (See: Net profit).(Fr. - Bénéfice net)

NET LEASE - The antonym of a gross lease. A lease whereby in addition to the rental stipulated, the lessee pays all or part of the expenses of operating and maintaining the property. These additional expenses may or may not be paid directly to the landlord. In common usage, the degree to which various items of expense are to be borne by the landlord or by the tenant has been expressed by one or more repetitions of the word "net", as for example:

Net Lease, the tenant pays basic rental plus taxes. Net Net Lease, the tenant pays basic rental plus taxes and maintenance. Net Net Net Lease, the tenant pays basic rental plus taxes, maintenance and operating expenses. Net Net Net Net Lease, the tenant pays basic rental plus taxes, maintenance, operating expenses and

structural maintenance.

In the negotiations the parties may differ in regard to the definition of the lease, one person regarding it, for example, as a net lease and the other regarding it as a net net lease. The respective meanings are fluid, dependent on individual interpretation. There is no one "right" meaning.(Fr. –Bail à loyer Net ou(Bail net))

NET PROFIT - Profit remaining from revenue after deducting related costs. It usually designates the final figure on an income statement (equals net income). Ordinarily, net profit is synonymous with net income.(Fr. - Profit net)

NET RENT - In current market phraseology because of changing conditions, a net rent has come to equate with triple net leasing: as most elements, taxes, operating and maintenance costs are subject to escalation and therefore netted out. Thus, a tenant would agree to pay a certain rental plus additional amount equal to the

- 80 -

Page 85: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

escalated cost and taxes.(Fr. - Loyer net)

NON-CONFORMING USE - A use of land, which is not compatible with zoning regulations but may be tolerated with certain restrictions.(Fr. - Utilisation non conforme)

OFFER TO LEASE or LET - A promise subject to certain conditions specified by the offering party to lease or let real property. If the terms of the offer are in law sufficiently complete (i.e. are not deficient in omitting any one of the basic elements required to form a lease, for example, the amount and particulars of payment of rent), then, where accepted, it results in a contract.(Fr. - Offre de location)

OFFER TO PURCHASE/OFFER TO SELL - A promise subject to certain conditions specified by the offering party to purchase or sell real property. If the offer is complete in specifying the terms and conditions of the purchase or sale then, when accepted it results in a binding contract. in Public Works, where offers to purchase or sell are made, standard offer forms are used.(Fr. - 0ffre d'achat ou de vente)

O&M COST (Operating and Maintenance) Includes:

Fixed expenses realty taxes insurance Variable expenses management superintendent supplies and materials utilities heat site maintenance miscellaneous expenses Repairs and Maintenance Reserves for Replacement

Excludes:

Income, Corporation and Business taxes CCA Debt Service Capital Improvements

(Fr. - Coûts de Fonctionnement et d'entretien (E. et E.))

OPTION - A right of choice. An agreement, in consideration for the payment of a certain sum of money or signed under seal, to hold an offer open for a definite period of time. It is but continuing offer, which is merged in contract resulting from acceptance thereof. If the option is not exercised the payment is forfeited.(Fr. - Option)

OPTION TO PURCHASE - Where a party obtains from an owner (vendor) the exclusive right and opportunity to purchase a property within a certain time at an agreed price and on specified conditions. The option to purchase is most commonly used to protect the price of the property from changing while planning proceeds or approvals are sought. Generally, a fee is paid to the vendor for this right. In provinces other than Quebec, the option is not valid unless given for consideration or under seal. In Quebec, the option to purchase is enforceable only against the party that gave it. In other words, it does not "run with the land" and if that owner sells, the subsequent owner is not bound by the option. The option to purchase is also found in lease purchase agreements.(Fr. - Option d'achat)

- 81 -

Page 86: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

OPTION TO RENEW A LEASE - The right of the tenant to renew an existing lease at the same or pre-negotiated terms and conditions.(Fr. - Option de renouvellement)

PERCENTAGE LEASE - A lease stipulating that a percentage of the tenant's gross or net sales, as defined by the lease, will constitute the rent. A minimum rent is usually included although a straight percentage is occasionally encountered. A ceiling rent may also be provided for.(Fr. - Bail à pourcentage)

PROBATE - The act or process of proving a will. The proof is Surrogate Court that the document produced before the Court for official recognition and registration, and alleged to be the last will and testament of a certain deceased person is such in reality. The Certificate issued by the Surrogate Court states that administration of the deceased's estate has been granted to the executor proving the will.(Fr. - Homologation)

PROFORMA - A term applied to a balance sheet or other statement, or an account which contains a) in whole or in part assumed figures or other facts, some indication of the character and purpose of the contents of the statement or account and the assumptions on which it is based ordinarily accompanying the use of the phrase; or b) no figures and is intended to indicate form, range, descriptions or other characteristics of a proposed presentation. (Fr. - Pro forma)

PROPOSALS - An invitation for proposals is an alternative to a tender call where the private sector is invited to develop proposals to provide accommodation to the Crown under general conditions with flexible design specifications. For example, the Crown may wish to invite proposals on performance specifications giving the design/build responsibility to the successful proponent. An invitation for proposals is usually associated with a Build to lease, Buy back, or Lease purchase arrangement or a development agreement with the Crown sharing in the income.(Fr. - Concours)

PURCHASE - The acquisition of land by lawful act. Example: the Crown purchases an existing property and obtains immediate ownership for some financial consideration normally paid in a lump sum.(Fr. - Achat)

QUIET ENJOYMENT - A right of a property owner to enjoy his property without interference or fear of claims. It is one of the five covenants found in a full covenant or warranty deed. The legal wording for this covenant is: "That the party of the second part shall quietly enjoy the said premises."(Fr. - Jouissance paisible)

QUIT CLAIM DEED - A deed of conveyance whereby whatever interest the grantor has in the property described in the deed is conveyed to the grantee without any warranty of title.(Fr. - Acte de renonciation)

QUIT LEASES PENALTY - Where the Crown vacates leased premises and ceases to make rental payments before the end of the lease term, the Crown will normally be required to pay a quit lease penalty, which will compensate the lessor for lost revenue.(Fr. - Indemnité de résiliation)

REAL ESTATE - Landed property. The interest (right), which any one has in lands. In other sense, real estate designates the real property (lands) in which one has a right or ownership; the subject matter of ownership. Real estate and real property may be used synonymously.(Fr. - Bien-fonds ou Propriété foncière)

REAL PROPERTY - Land, and generally whatever is erected or growing upon or affixed to land. Also rights issuing out of, annexed to, and exercisable within or about land. The term corresponds very nearly with immovables of the civil law. It is usually synonymous with REAL ESTATE.(Fr. - Bien-fonds ou Propriété foncière)

- 82 -

Page 87: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

RENOVATION - An approach to rendering existing accommodation functional for a specified need. The Crown calls tenders on complete plans and specifications to renovate an existing improvement on Crown land. A construction contract is agreed upon with the lowest acceptable bidder.(Fr. - Rénovations)

RENT - The amount paid for the use of land and or improvements. Synonymous with Rental.(Fr. - Loyer)

RESTRICTION - A term or condition, which restricts the transfer or use of land. A restriction may be statutory or contractual. Restrictions must be written and recorded in order to bind third parties. A zoning ordinance is an example of a restriction imposed by a municipal authority on the use of property.(Fr. - Restriction)

RETURN ON INVESTMENT - Is the net income divided by investment. The term "investment" is used in three different senses in financial analysis, thus giving three different return on investment figures: return on assets, return on owner's equity, and return on invested capital.(Fr. - Rendement du capital investi)

REVERSION - The returning of rights in real estate to the grantor, such as the return of the use of real estate to the lessor at the expiration of a lease. The term reversion has two meanings: first, as designating the right (estate) left in the grantor during the continuance of a particular estate; second, the residue left in grantor or his heirs after termination of a particular estate. It differs from a remainder in that it arises by act of the law, whereas a remainder is by act of the parties.(Fr. - Droit de retour ou Réversion)

REVOLVING FUND - A fund from which moneys are continuously expended, replenished and again expended. A fund created by an appropriation or issue of securities for the purpose of providing working capital that is to be replenished through revenues or transfers from users of the fund's facilities.(Fr. - Fonds renouvelable)

RIGHT OF FIRST REFUSAL TO LEASE - The right given by the landlord to a party requiring the landlord to offer to lease certain premises at the same rent and under the same conditions as have been offered to him by a third party. If the person who has the right of first refusal refuses to accept the offer, then the landlord may lease to the third party at that rent and on those conditions, but not any other rent or conditions.(Fr. - Droit de préférence à la location)

RIGHT OF FIRST REFUSAL TO PURCHASE - The right given by the owner of real property to a party requiring the owner to offer to sell the property to that party at the same price and under the same conditions as have been offered to the owner by a third party. If the person who has the right of first refusal refuses the offer, then the owner may sell the property to the third party at that price and on those conditions, but not any other price or conditions.(Fr. - Droit de préférence a l'achat)

RIGHT-OF-WAY - An easement; the right of passing through the property of another. A right-of-way is either public or private.(Fr. - Droit de passage)

RIPARIAN OWNER - A person who owns land that is bounded by a waterway such as a river or stream.(Fr. - Riverain)

RIPARIAN RIGHTS - The right of an owner to the use and enjoyment of water which flows across or along his land. It includes a right of an owner of land abutting a body of water to make use of the water area for piers, boat houses, for fishing, boating and navigation, and the right of access for such purposes, which right is limited by public need if on a navigable stream.(Fr. - Riveraineté)

SALE-LEASEBACK - An agreement whereby the owner of real property sells the property and enters into a long-term lease with the buyer for the same property. A method of raising investment capital in the private

- 83 -

Page 88: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

sector. Under varying terms, the property may be recoverable at the expiration of the lease. (See also Leaseback.)(Fr. - Cession- Bail)

SANDWICH LEASE - (see sublease)(Fr. - Voir sous-location)

SERVICES MANAGEMENT REVOLVING FUND (SMRF) - A fund created to account for all revenues obtained from delivery of a service and for all expenses and expenditures required to manage and provide the service. Useful as a method of determining the worth or value of retaining the service or acquiring the product by other means.(Fr. - Fonds renouvelable des services et de la gestion (F.R.S.G.))

SINKING FUND - A fund in which periodic deposits of equal amounts of money are made for the purpose of ultimately paying a debt, or replacing assets. Usually it is a fund in which is placed equal annual or monthly deposits, which, with compound interest thereon, will accumulate to a predetermined amount at the end of a stated period of time.(Fr. - Fonds d'amortissement)

SUBLEASE - An agreement conveying the right of use and occupancy of a property in which the lessor is the lessee in a prior (main) lease. Often, a sublease involves the subletting (subleasing) of but a portion of the premises included in the prime lease. The distinction between a sublease or subletting and an assignment of lease is that an assignment is a transfer of the whole of the tenant's term to the assignee whereas a sublease is a transfer of part only of the tenant's term to the subtenant. The sublease covenants may differ from those of the main lease. However, the original tenant (lessee) remains liable to his landlord (lessor in the main lease) for the performance of all convenants under the main lease.(Fr. - Sous-Bail)

TENANCY IN COMMON - The holding of property by two or more persons each of whom has an undivided interest which, upon his death, passes to his heirs and not to the survivor or survivors. The heirs become tenants in common with the survivors. The holding of an estate in land by different persons under different titles, but there must be unity of possession and each must have right to occupy the whole in common with his co-tenants. (Fr. - Tenance Commune)

TITLE - In real property law, title means the union of all the elements, which constitute ownership; full, independent and fee ownership.(Fr. - Titre)

TORRENS SYSTEM - A system of land registration in which the governmental authority issues title certificates covering the ownership of land which tend to serve as title insurance. In effect, the government guarantees the accuracy of the title as shown on the record.(Fr. - Système Torrens)

TOWNSHIP - A territory subdivision that is six miles long, six miles wide, and contains 36 sections each one-mile square. (Fr. - Canton)

TURN-KEY LEASE - A lease stipulating that the rent includes all services and the cost of alterations and fitting up carried out by the landlord at his direction and expense amortized over the period of the lease.(Fr. - Bail clés en mains)

WARRANTY DEED - A deed conveying to the grantee title to the property free and clear of all encumbrances, except those specifically set forth in the document.(Fr. - Acte Formaliste de Garantie)

ZONING BY-LAW - Regulations governing the use and improvement of land.(Fr. - Règlement de zonage)

- 84 -

Page 89: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

Real Estate Investment Terms

AMORTIZATION - The process of recovering, over a stated period of time, a capital investment: the provision for the gradual liquidation of an obligation, usually by equal payments at regular intervals over a specific period of time.(Fr. - Amortissement)

ANNUAL EQUIVALENT OCCUPANCY COST (A.E.O.C.) - The A.E.O.C. is a measure of the cost per rentable unit of occupancy. This cost combines the capital costs of the project amortized over its economic life, interest on the current land value, and an estimate of first year grants in lieu of taxes, operation and maintenance costs and building management fees.(Fr. - Coût annuel d'occupation)

APPRECIATION - An increase in the monetary value of a property.(Fr. - Plus-value)

BREAK-EVEN RENT - In the department's Real Estate Investment Analysis System, break-even rent refers to the first year rent which under forecast market forces (i.e. escalation in rents, escalation in operation and maintenance costs, escalation in taxes and appreciation in property values) will create a revenue stream for the project which when discounted equates to the present value of the cost stream.(Fr. - Loyer-rentabilité)

CAPITALIZATION - The process of converting into a present value, a series of anticipated future annual installments of income by discounting them into a present worth at a capitalization rate which is attracting purchase capital to investments with similar characteristics, such as risk and term.(Fr. - Capitalisation)

COST OF ACCOMMODATION (PRESENT VALUE) - Present value cost of accommodation refers to the cost stream elements (initial capital, O&M, taxes, management and additional downstream costs associated with the project) discounted from their date of occurrence back to the planning date minus the revenue stream from the private sector (if any) and the residual property value also discounted back to the planning date. The present value cost of accommodation is used to measure the cost to the Crown of providing the accommodation over the investment horizon and is comparable between alternatives with the same investment horizon.(Fr. - Coût des locaux (valeur actualisée))

DEFLATION - A decrease in the general price level, a period when the purchasing power of money is rising.(Fr. - Déflation)

DEPRECIATION - A loss in building value caused by deterioration and/or obsolescence.(Fr. - Dépréciation)

DISCOUNT RATE - The discount rate is the value an investor places on his investment dollar, that is, it is an expression of the rate of return he would expect from a project before spending this dollar. An investor's discount rate varies with the type of project, duration of the investment, risk and the scarcity of capital. The only discount rate calculated for the government as a whole is published by the Department of Finance based on government bond rates and thus represents the cost of money to the public sector. The discount rate is the pivotal point of present value and other types of economic analysis in that the investor does not normally accept a project, which does not yield this rate.(Fr. - Taux d'actualisation)

DISCOUNTING - The discounting process allows the investor to express the value of project costs and revenues which are spread over time in one common denominator. This common denominator is referred to as a present value equivalent. The present value equivalent of each item of project costs and revenues is the amount which would have to be put aside at the planning date compounding at the discount rate to equate to the actual future

- 85 -

Page 90: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

value of the cost of revenue item by its date of occurrence. (Fr. - Actualisation)

ECONOMIC LIFE - The estimated period over which it is anticipated that a property may profitably be utilized. The period over which a property will yield a return on and of the investment, over and above the economic rent due to land. This period can never exceed and generally is shorter than the physical life of the improvements.(Fr. - Durée économique)

ECONOMIC RENT (MARKET RENT) - The reasonable rental expectancy if the property were available for renting at the time of its estimation; the rental warranted to be paid in the open real estate market based upon current rentals being paid for comparable space as distinguished from contract rent under an existing lease.(Fr. - Loyer économique (value locative marchande))

ESCALATION - The annual rate of change in the real and nominal value of goods and services. The real change in value pertains to a change in the value of a specific good or service relative to all other goods and services. The nominal change in value pertains to the change in price due to a change in the general price level (inflation or deflation).(Fr. - Indexation)

FIXED RENT - In the department's Real Estate Investment Analysis System, fixed rent refers to that portion of total contract rent which is fixed for a specified lease term and is not subject to annual increases during this term.(Fr. - Loyer fixe)

INFLATION - An increase in the general price level, a period when the purchasing power of money is decreasing.(Fr. - Inflation)

INTERNAL RATE OF RETURN (I.R.R.) - The I.R.R. is a measure of the annual return on the capital invested in a project. The internal rate of return is an interest rate at which the project's total future earnings discounted from the time they occur to the date of the original capital investment equate to that investment. It may be used to determine whether a project is acceptable or unacceptable by comparing the project's rate of return with the investor's standard. The I.R.R. is given in the following formula:(Fr. - Taux de rendement interne)

INVESTMENT HORIZON - The period of time over which project costs and revenues are estimated and analyzed. In order to provide a comparison of cost and revenue streams for each accommodation alternative, the department's Real Estate Investment Analysis System discounts costs and revenues over the same investment horizon. The length of the investment horizon is normally equivalent to the shortest economic life among the project alternatives or the length of the functional requirement, whichever is shorter. Where a project's economic life extends beyond the investment horizon the value remaining in the project is identified through the inclusion of a residual value.(Fr. - Période de calcul)

NET PRESENT VALUE (N.P.V.) - The N.P.V. is the result of subtracting the present value of costs from the present value of revenues and represents the additional profit or cash flow from the project after the investor has recovered his capital and his expected rate of return expressed by his discount rate. A project yielding a positive N.P.V. is considered to be an economically attractive investment.(Fr. - Valeuractualisée nette)

OCCUPANCY DATE - In the department's Real Estate Investment Analysis System, this is the date at which proposed accommodation solution would be in-service and commence to create revenues.(Fr. - Date d'occupation)

PRESENT VALUE - Is the discounted value of aggregate future payments.(Fr. - Valeur actualisée)

- 86 -

Page 91: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

PRESENT VALUE ANALYSIS - As conducted within the department's Real Estate Investment Analysis System, present value analysis is a comprehensive method of identifying various measures of economic performance for accommodation alternatives as of the planning date. Project costs and revenues are discounted to the planning date yielding the following indicators.

Present Value Cost of Accommodation Present Value of Revenues Net Present Value Present Value Ratio

(Fr. - Analyse des valeurs actualisées)

PRESENT VALUE RATIO (P.V.R.) - The P.V.R. is the ratio of the present value of revenues over the present value of costs. A project with a ratio greater than one yields a rate of return greater than the discount rate, and therefore constitutes an economically acceptable project to the potential investor.(Fr. - Indice de rentabilité)

RESIDUAL VALUE - The residual value is the estimated value to the owner remaining in a property at the end of the investment horizon. In the department's Real Estate Investment Analysis System, the residual value facilitates the fair comparison of investment alternatives with different economic lives (where one alternative may have additional income potential beyond the investment horizon) and varying rates of appreciation in the market place (where one alternative appreciates faster than another and therefore has additional speculative value).(Fr. - Valeur résiduelle)

REVENUES (PRESENT VALUE) - The present value of revenues is the discounted value of aggregate revenue stream attributable to a project. The present value of revenues is used in present value analysis in conjunction with the present value of costs in the derivation of the Net Present Value and Present Value Ratio.(Fr. - Revenus (valeur actualisée)

REQUIREMENT DATE - In the department's Real Estate Investment Analysis System, this is the date at which the client requires new accommodation and PWGSC assumes responsibility for providing this accommodation. Costs associated with interim accommodation between the requirement date and occupancy date is included in the total cost attributable to the project.(Fr. - Date d'occupation souhaitée)

Building Measurement Terms

ACCESSORY AREA - Common use areas which serve all occupants on the floor or within the building including lavatories, janitor closets, electrical closets, public corridors, elevator lobbies, lunchrooms and common service boardrooms.(Fr. - Secteurs auxiliaires)

BUILDING SERVICE AREA - Those areas that are necessary to the operation of the building, such as main entrance lobbies, public stairs, elevators, boiler and machine rooms, stacks and flues.(Fr. - Aire de service du bâtiment)

FUNCTIONAL AREA - That area within the outside walls measured and computed in the same manner as "Rentable Area" but excluding Accessory Areas and columns and projections necessary to the building structure which are in excess of four square feet in area (or equivalent expressed in an alternative unit of area). This calculation is utilized only in evaluating lease tender proposals and its use is outlined in the "Leased Accommodation Quality Index Point Score Rating System".(Fr. - Aire fonctionnelle)

OUTSIDE GROSS AREA (CONSTRUCTION GROSS) - That area measured from the outside surface of the outer building wall to the outside surface of the opposite outer building wall, for the area of each floor without any deductions for opening, which occur within the floor area. Where balconies and mezzanine floors occur

- 87 -

Page 92: · Web viewThis Guide was originally developed at the request of the Investment Management Board members (now the Real Property Investment Board or RPIB). The Guide was subsequently

within the exterior walls of the building, the actual area of these is measured and included.(Fr. - Superficie extérieure brute)

RENTABLE FLOOR AREA - That area within the outside walls computed by measuring from the inside surface of the outer building wall to the inside surface of the opposite outer building wall, except where the outer building wall consists of 30% or more glass. In which case, that area is computed by measuring the innermost inside surface of such glass to the inside surface of the opposite outer building wall or glass whichever is applicable. The area includes columns and projections necessary to the building structure but excludes Building Service Area. (Fr. - Superficie louable)

USABLE FLOOR AREA - That area within the outside walls measured and computed in the same manner as "Rentable Area" but excluding common use areas which serve the entire floor or building, known as Accessory Areas. (Fr. - Superficie utilisable)

- 88 -