8/7/2019 vetrivel
1/11
An analysis of the Quality of Delivery
Commitment in finished products with special
Reference to Lapp India, Bangalore
Lapp India private Limited
( August 7th to September 20th )
Date: 2nd February 2011
B. Vetrivel
(09p35f1213)
Guided by,
Ms. Krishnan Hemamala
8/7/2019 vetrivel
2/11
Lapp India Private Limited
Lapp groups was formed in 1957 in Germany by OskarLapp.
Lapp India Pvt
Ltd deals with the production of cables and
connectors.
Major competitors are Finolex, Pura Cables, Azjazeera Cables.
8/7/2019 vetrivel
3/11
Introduction to the study
Lapp India, Bangalore has a coordinated and effective mode of supply
chain management which controls the entire process from procurement of
raw material to dispatch of finished goods to the end users.
But still finds a serious difficulty in dispatching its finished products to the
end users even after the material is in hand. And hence to minimize this gap
to lessen its inventory cost and to increase profitability.
Month of study is September - October
8/7/2019 vetrivel
4/11
Objectives
Lapp India, Bangalore found dispatching the materials at the
committed date a difficult feat to achieve. In order to analyse
the sources for delay the objectives of this study were defined as
follows:
To analyse the gap in the actual material delivery and committed
dates.
To identify reasons attributable to this delay
8/7/2019 vetrivel
5/11
Scope of the study
Lapp officials refused to disclose the entire resources and hence
limited resources are available for the study and Inadequate time.
Very narrow study as it is limited only to the analysis ofTime gap
between Material Available Date and Delivery Date.
Sample Size is also limited because officials are not able to disclose
entire information (busy schedule) due to time limits.
8/7/2019 vetrivel
6/11
Research Methodology Research type
Descriptive and Diagnostic study- There occurs consistent delay in delivering the
materials to end consumers. The problem in hand is described as delay between
MAD and DEV date and data is given. The reasons are found based upon the data.
Sampling plan
Data type Primary data
Sample size 473 sale orders
Data collection sources Observation and Interview method.
Sampling mode Probability Random sampling
Data analysis tools
Test ofSignificance->Z test to test the hypothesis of causal relationships between
the variable -> material available date and committed date.
8/7/2019 vetrivel
7/11
Findings1. Payment block - delay in the payment from the customer
2. Customer block - customer not ready to get the material
3. One lot order - requires complete delivery
4. Road permit - no proper license and documents
5. Letter of credit
6. Lack of space in warehouse - because of consistency in delay in dispatching
7. Unavailability of truck when needed
8. Lack of communication with the dealers
and suppliers
And other reasons are considered to be very minor like Manual faults, Strikes of
Truck owners, Festival Holidays etc.. The probability of occurrence of such cases is
very minimal.
8/7/2019 vetrivel
8/11
Conclusion
The major reason for the gap lies in payment block
because of which most of the stocks were held up in the
warehouse.
Specifically, the reason for the holdup is payment, one
lot order ie., waiting for the entire materials to get
dispatched at the same time. The major problem lies withthe customer and therefore the profit or amount is locked in
the inventory in the form finished goods.
8/7/2019 vetrivel
9/11
Suggestions
Lapp India Pvt ltd may take the customer perspective
by having a regular follow-up with the customers about
their payments and update them on the availability of finished products
Lapp India can make sure to receive the letter of credit
from the customers
Lapp India Pvt ltd can take effective measures to reducethe risks in one lot order
8/7/2019 vetrivel
10/11
Learning during Internship
As a supply chain manager , the major to be taken
parameters to minimize the delay
Discipline and coordination to handle pressures
How to behave and communicate with officials
8/7/2019 vetrivel
11/11
Thank you