Upload
phungkhanh
View
213
Download
1
Embed Size (px)
Citation preview
,,,Government of Western Australia
Department of Education and TrainingShared Services Centre
STAFFING 2010
Readiness Assessment
Recruitment and Selection of School Administrators
and Teachers
I, , 75
..
~
s: I^,^L ,,191^ O
@
";^!, , ^
Version 1.0
,3 July 2009
Acceptance and Release Notice
This is a managed document. All copies of this document preceding this release areobsolete and shall be destroyed. This document has not been released for use untilaccepted by the Director, Management Support, ETSSC.
Release. Number'
0.2
1.0
Date
73 July 2009
14 July 2009
Accepted/Authorised By
Principal Consultant,HR Services (DET)
Manager, HR Services
Final draft for Review
Director,
Management Support
Final
Manager,
Reform Coordination Unit
Reason for Release
Tracy Rainford-Watson
Signatory
Cindy Barnard
Trish Fraga-Diaz
Sandra Couch
Signature Date
TABLE OF CONTENTS
I
I . I
INTRODUCTION
2
Purpose
DEFINITION
Overview
Project Assurance
Scope
Decision to Go Live
2.1
2.2
2.3
2.4
3
3. I
3.2
3.3
READINESS CRITERIA
Approach
Readiness Sign Off
Readiness Criteria
OUTSTANDING RISKSAND ISSUES4
2
2
2
2
2
3
7
INTRODUCTION
1.1 PURPOSE
The purpose of the Readiness Assessment is to record relevant factors in determining
readiness to move in-scope Local Merit Selected teaching and all other school
administrator recruitment services to the Education and Training Shared Services
Centre (ETSSC). This document is to empower key stakeholders and management with
a comprehensive resource to assist in the decision to migrate this service through
analysing progress against the readiness criteria including the risk assessment of
outstanding issues.
DEFINITION
2.1 OVERVIEW
2
The Readiness Assessment forms part of the documentation governance structure for
the Staffing 2010 project, which will be transitioned to the ETSSC through a phased
approached for 2009. This objective of assessing readiness is supplemented from other
project documentation which includes the Project Plan, Issue and Risk Log (Appendix
A), Critical Implementation Task Register (Appendix B), Documentation and Product
Configuration (Appendix C), and the Migration Strategy and Cutover Plan. These
documents function as part of a project assurance review to allow management toevaluate readiness for'Go-Live'.
2.2 PROJECTASSURANCE
The internal stakeholders are included in the table below and the decision criteria are
summarised in the section 3 "Readiness Criteria". This table identifies key stakeholdersresponsible for reviewing the project readiness for'Go-Live'.
Name
Kevin Smith
Trish Fraga-Diaz
. .
Cindy Barnard
,. .
Sandra Couch
.
, ., ' Title
Tracy Rainford-Watson
General Manager, ETSSC
Readiness Assessment - Staffing 2010 Transitional process
Director, Management Support
Manager, HR Services
Manager, Reform Coordination Unit
Principal Consultant , HR Services (DET)
, ., ..
. ,
Page I
2.3 SCOPE
The scope of this assessment is to evaluate the readiness to implement recruitment and
selection for LMS Teaching and School Administrator positions (including management
of redeployment for deputy principals) from the Staffing Directorate to ETSSC. The
detailed transition of processes from the Staffing Directorate is documented in the
Migration Strategy and Cutover Plan. This assessment substantiates the intended scope
of the project has not changed and highlights risks, issues and external considerations
which may contribute in impeding deliverables and affectthe assessment of readiness.
2.4 DECISION To Go LIVE
Depending upon the review of the criteria in Section 3 "Readiness Criteria" the decision
to "Go Live" may be contingent upon known issues in Section 4 "Outstanding Risks and
Issues". Section 4 outlines any issues associated with the various decision criteria and
the associated actions taken/planned to be taken to ensure the issue is managed toallow the project to go forward.
READINESS CRITERIA
3.1 APPROACH
3
Assessment should follow systematic criteria that reflect readiness for achieving well
defined objectives and requirements. The readiness criteria presented in section 3.3 are
catsgorised into tangible factors and indicators that shape the project objectives. These
categories reflect the ability to change and redesign processes through the project, the
technical architecture requirements for implementation, and the infrastructure readiness
to go-live. These actions are a collation of results from activities stipulated from specific
tasks in the Critical Implementation Task Register resulting in the project's documentand product deliverables.
3.2 READINESS SIGN OFF
Based upon the acceptance of the key decision makers for ETSSC in consideration of the
listed readiness criteria and outstanding issues, it is recommended that ETSSC proceed
with the migration of services for LMS Teaching and School Administrators positions. This
Readiness Assessment signs-off formally the decision to "Go Live" on the 20'' July 2009.
Readiness Assessment- Staffing 2010 Transitional process Page 2
3.3
Readiness
Categories
READINESS CRITERIA
Issuel
Risk
AdvertisingRequirements
IR,
IR2
. Mapping of Notification of Vacancy to Manager Request Form (MRF) conductedwhen developing MRF on RAMS
Advertising templates, including attraction strategy, completed for RAMS.
IR3146
. JDF registered for HOD/HOLAIPC and Deputy Principals
Selection Criteria from LMS policy forteaching positions to be used inadvertisements.
.
IR415
Activities and Deliversbles
.
Communications&
ChangeManagement
IR618
The closure of JobsOnline will impact on the service required post Go-Live.
. Reviewed policy Advertising and Logo Use
Communication via Ed-Email and FAQ for change in advertising to be on JobsWA..
.
IR7
To address interdependence with other business units, meetings were held aspart of the Migration Strategy.
Process maps developed with in depth discussions with Staffing, Promotions andHousing and Transport through these meetings
.
.
IR9
Possible resistance to cultural shift is determined an 'intangible deliverable' andevaluation can only be conducted post implementation
.
IR17
Information package to other internal business units planned after implementationdate.
One page quick process reference for Staffing and Payroll, and contact referencefor Staffing and ETSSC reception areas
Readiness Assessment - Staffing 2010 Transitional process
.
IR30
. Documents and emails circulated to schools are vetted by CorporateCommunications and Marketing to reduce possible negative media implications
Additional information
. Communications with RCU maintained on a weekly basis through meetings forprogress updates and issues.
See Section 4.1R3
Overall
Readiness
Requires 'No print media'policy confirmed throughRCU. See Section 4 IR4
RCU to coordinate andadvise other business
units impact of newprocess
Excellent
Discussions indicate that
change management isoutside the control of the
Project
Page 3
Good
Readiness
Categories
Issuel
Risk
Existing Process
IRIO
IR, t
. Identified vacancy arrangements by analysing statistics on JobsOntine,
Existing Central and District pool arrangements confirmed with Staffing onpractices and any current pool
.
IR, 3
Policy andProcedures
. RAMS - WAGOT interface notrequired in the transitional phase for 2009
Ability of panel chair to validate WAGOT registration is embedded into process
IR, 8
.
.
Activities and Deliverables
IR, 9120
Identified employment status of an employee will have minimal impact onemployment offers.
IR2,122
.
ProjectOrganisationand Scope
Business rules for pools advertising to continue with no change in policy.
.
IR23/25
Decision that policy remains unchanged fortransitiona1 2009
.
IR26/45
Recommended and developed approval of selection process to be part of theindependentreview and proper assessment
.
IR, 2
Process maps streamlined to include redeployment clearance request fromStaffing
.
TransitionalProcess
IR3'I
Responsibility of appointment processes (Ie CommencemenVMovement) fromTES to HRMIS determined for Teaching and SchoolAdministrator positions
. Inadequate information provided for causalIrelief appointments and SpeciallyOrganised class teachers and swimming instructors.
IR, 6
. Scope of processes to be transitioned determined prior to implementation date,
. Project planning, analysis and documentation completed for approval and sign off
.
Readiness Assessment- Staffing 2010 Transitional process
Task
Migration Strategy and Cutover Plan developed and distributed for review
Cutover date confirmed with no vacancy closing after the 20th July
Agreement reached for activities indicated in Cutover Plan
.
IR23
.
Additional information
. Redeployment process maps developed for Deputy Principals
. Transitional process which requires vacancy and appointment clearances tocontinue for 2009
OverallReadiness
See Section 4, IR 18
See Section 4, IR 23
Very Good
See section 4.1R 3,132
See Section 4.1R 16
Good
Page 4
See Section 4.1R 23
Very Good
Good
Readiness
Categories
Issuel
Risk
IR34
SystemsReadiness
. Search criteria on JobsWA clearly provided on resources
. RAMS enhancement for MRF and Redeployment Module mapped and developed.
UserAcceptance Testing conducted forthese enhancements
Enhancements in production 12' July to allow further testing before Go-Live date.
.
.
IR35
.
Activities and Deliverables
RAMS functionality ready for Go-Live with vacancy and emailtemplates loaded.
460 Manager Access Types created to allow Principals to request for a vacancyvia RAMS
.
,
IR36
Nominate function on RAMS nottested
Functions in the User Permissions Statement of Works in production by Go-Live.
RAMS - HRMIS interface notrequired forthis transitional phase
.
IR40
Skills and
TrainingRequirements
.
. Written confirmation of RAMS network and database capabilities to be confirmed,
.
IR41
RAMS Training scoped, developed and delivered for approximately 170employees,
Training manuals and resources developed for Panel Chair including a processoverview
.
IR42
.
IR43
Online Learning Packages are being developed for regional staff with options of aself pace learning program, as well as training through web conferencing.
.
IR14
Applicantresources have been provided to include tips on application process
.
Readiness Assessment - Staffing 2010 Transitional process
As part of the training package, information developed by WP&C regarding theSelection and Recruitment guide which includes a CD Rom had been provided
. External panel members (for example community members) will be directed toOpsSC website on the User Guide for Panel Members to ensure conducting a fairand equitable process.
Additional information OverallReadiness
See Section 4, IR35
See Section 4.1R36
Very Good
See Section 4, IR41
External panel membershave not been fullyaddressed due to limited
time and scope. This willbe centrally coordinated byWP&C
Page 5
Very Good
Readiness
Categories
Issuel
Risk
IR38139
IR7
OperationalReadiness
. Resources approved and positions advertised.
Operational staff recruited
Accommodation for new staff allocated
Necessary hardware and software have been procured forthe new team
Generic mailbox and Hotline established,
Operational procedures, manuals and registers developed for Recruitment -Schools
.
.
.
IR39
.
Activities and Deliverables
.
IR26
IR26
.
IR3/71
8/10
Training of new staff on procedures and policies
. Standard letters and templates developed as contingency for non-online process
. Offer of Contractletterto be standardised by Labour Relations
. Recruitment Schools intranet website developed and running
Relevant documents and resources uploaded prior to Go - Live.
Readiness Assessment- Staffing 2010 Transitional process
Additional information OverallReadiness
See Section 4, IR39
Pending final copy from LR
Excellent
Page 6
4 OUTSTANDING RISKSAND ISSUES
The following outlines any issues related to why readiness criteria may not have been signed off. The following documents any contingenciesassociated within the a reementto o forward with the jin Iementation.
No
IR31
IR46
Category
Advertising
Steps have been undertaken to minimise the impact of the above issue. These includes:
. Creating a JobsWA mirror site be incorporated to a DET website
. Obtain list of all JobsOntine administrators to send an email notification of change.
. Redirection and migration of JobsOnline users to JobsWA.
. Further notification to current users will be delivered through Staffing when schools contactthem on school establishment management
Although the volume and probability is high, the impact has been considered manageable given the above countermeasures in place.
Possible confusion regarding location ofadvertisements if Jobs Online site
continues
IssuelRisk
Expanding scope of project will inverselyaffectthe objectives of the project
IR4 Advertising
Confirmation will be required from RCU on policy decision on print media.
IR191
IR20
Policy
Schools may be unaware of processesand business rules for placement ofadvertisements
The scope of this issue has expanded as the JobsOnline board which isprimarily owned by Staffing Directorate is closing as of the 20'' July. Thiscreates a risk for all users who may not be aware of this change. Currentadministrators and authors of the SitVac system will need to be informedof change. While the redirection is part of mitigating this risk, the actualclosing of the entire JobsOnline is outside the scope of project.
Current policy with regards to the LMSfor Teachers will not match the new
process
Action Plan I Description
Readiness Assessment- Staffing 2010 Transitional process
Policy changes may expose theDepartment to industrial issues
It has been identified that certain schools (eg Indian Ocean TerritoriesSchools - commonwealth funded) will be allowed options for print media(eg Saturday West)
Forthe transitional 2009 process, it has been decided that there will beno changes in the current LMS policy. However, it has been identifiedcertain policies may clash with the new process. For example applicantsare required to respond to an offer in I day, Permanent Teachers cannotbe placed in Temporary positions in LMS schools. Additionally, changesto the General Agreement have not been recommended to reduce therisk of exposing the Department to industrial issues
(Further information in recorded in issue/Risk Log, IR 19)
Probability
High
Impact
Medium
Low
Page 7
High
Low
Low
No
A list of all policy change requirements have been documented to be addressed in the fullimplementation phase of the project in 20.0.
Category
IR23 Procedure
IR3, I32
Delays in vacancy clearances and joboffers through Staffing may negativelyimpact on perceptions of effectivenessof new system
ProjectScope
IssuelRisk
Most positions originally outside the scope of the project have been accounted for. Management and support in advertising these positions will be provide post Go-Live. Also the existing processes will continue for 2009 for School Psychologist as part of the 'bulk run' recruitment conducted centrally.
As such, the impact of this risk is deemed Low.
Lack of clarity about specific services tobe provided by ETSSC
Possible confusion about which
positions are included in project scope
IR35 RAMS
The Nominate function is not unused untilthe next phase of the project in 2010. For User Permission, this enhancement is riot essential at Go-Live and the currentprocedure will be in place untilfull UAT is completed.
These enhancements are riot essential on Go-Live and manual workaround will continue to allow a robust and comprehensive testing plan.
This risk has been mitigated by ensuring that Staffing Consultants arecontacted during the School FTE establishment phase which occursprior to advertising to confirm FTE approval and subsequent advertisingof vacancy. This way, the likelihood of nori-clearance by Staffing isminimised
Lack of funding, time and/or approvalsresulting in RAMS enhancements beingriot developed
IR36
Action Plan I Description
RAMS
The shift of the project scope causes the constant change of prioritiesand uncertainty of a specific working model. This preventedcomprehensive research and analysis for certain positions (ie SchoolPsychologist) to be included on implemented date. Additionally, close toimplementation date, this 'scope creep' expounded by havingJobsOnline closing on the same date
RAMS may be unable to cope with ananticipated increase in the volume ofdata
Readiness Assessment- Staffing 2010 Transitional process
The User Permissions and Nominate functions have riot gone throughUAT prior to Go-Live. This is due to limited resources by BRS to deliverboth the more urgentfunctions for MRF and Redeployment Module.Furthermore, priority for skinning the JobsWA board on DET websitehad taken precedence before Go-Live
Probability
Pending response from BigRedSky to reassure system ability to handlelarge volume of network traffic and database storage.
Medium
Impact
Low
High Low
Medium
Page 8
Medium
Medium Low
No
Preliminary evaluation from BRS indicated that 15% of spare data and network capabilities will be used for expected 560 vacancies in the firstthree months postimplementation.
A comprehensive reply from BRS is required prior to Go-Live.
Category
IR4, Training
IssuelRisk
Limited timeframe to ensure all
appropriate staff are familiar and trainedIn new processes
This issue of inadequate training can be addressed in a number of ways. Ifthe decision for schools to revertto a manual process, the risk can be assessed asMedium - Low
IR42 Training
With the available resources online and the support from the operational team, this risk can be considered low.
IR39
Applicants may riot be able to effective Iyuse RAMS to seek and apply forpositions
OperationalReadiness
Considering that most staffin the new team (with an exception of two external) are competent in recruitment practices as well as HRMIS and RAMS, andthat thorough resources are provided, this risk can be considered negligible.
While a number of schools will be ready, there are still approximately390 schools which have not have training on the RAMS system. Furthertraining is being provided in Term 3 as well as a self paced learningmodule. A decision is required ifthe option of allowing a manualselection process as opposed to online only process. This option isprovided by ETSSC only after offering the online solutions have beenexhausted. These options include attending training either face to faceor online, hiring a HR Consultantfamiliar with RAMS through the CUAand assigning additional support from either ETSSC or District Office
Limited timeframe to recruit, select andtrain appropriate staff for ETSSC todeliver services.
Action Plan I Description
Readiness Assessment - Staffing 2010 Transitional process
Due to procedural fairness, applicanttraining is riot developed at thistime to prevent up skilling targeted groups of applicant. Any training willbe in cooperation with WP&C. Tips and resources have been developedtop assist applicants on job search and the application process
Due to limited timeframe, there will be more hands on training providedto the new staff postimplementation. This risk is also managed bypreparing detailed operational procedures and manuals forthe newteam to ensure guidance and supportis available.
Probability Impact
High Medium
Medium Low
High
Page 9
Low