Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
British Columbia Hydro and Power Authority, 333 Dunsmuir Street, Vancouver BC V6B 5R3 www.bchydro.com
Fred James
Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 [email protected]
May 3, 2017 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British Columbia Utilities Commission Sixth Floor – 900 Howe Street Vancouver, BC V6Z 2N3 Dear Mr. Wruck: RE: British Columbia Utilities Commission (BCUC or Commission)
British Columbia Hydro and Power Authority (BC Hydro) Mandatory Reliability Standards (MRS) TPL-001-4 Assessment Report (the Report)
BC Hydro writes to the Commission to provide its Report dated May 2017 pursuant to section 125.2(3) of the Utilities Commission Act. BC Hydro is providing an electronic copy of the Report to registered entities in the British Columbia (B.C.) MRS program.
The Report presents the reliability impacts, suitability, standard applicability and potential costs of adopting the TPL-001-4 reliability standard and five new NERC Glossary Terms intended for TPL-001-4 (TPL-001-4 Terms) for the Bulk Electric System in B.C.
The TPL-001-4 reliability standard and the TPL-001-4 Terms were originally assessed in MRS Assessment Report No. 8, filed with the Commission on May 15, 2015. In its assessment, BC Hydro recommended holding the TPL-001-4 reliability standard and the TPL-001-4 Terms in abeyance to allow time for BC Hydro to complete a full assessment. Commission Order No. R-38-15 to MRS Assessment Report No. 8 held adoption of the TPL-001-4 reliability standard and the TPL-001-4 Terms in abeyance pending reassessment. The Report is the reassessment of the TPL-001-4 reliability standard and the five new NERC Glossary Terms, dated as at November 28, 2016, that are required to be adopted in connection with the TPL-001-4 reliability standard. In the Report, BC Hydro recommends that, with the exception of Requirement 7, the TPL-001-4 reliability standard, and TPL-001-4 Terms are suitable for adoption in B.C. Requirement 7 of the TPL-001-4 reliability standard is recommended to be held in abeyance until the Planning Coordinator matter as it pertains to B.C. is resolved.
BC Hydro has included a proposed process for the Commission’s adoption of the TPL-001-4 reliability standard and the TPL-001-4 Terms in section 3.2 of the Report.
B-1
May 3, 2017 Mr. Patrick Wruck Commission Secretary and Manager Regulatory Support British Columbia Utilities Commission Mandatory Reliability Standards (MRS) TPL-001-4 Assessment Report (the Report) Page 2 of 2
For further information, please contact Geoff Higgins at 604-623-4121 or by email at [email protected].
Yours sincerely,
Fred James Chief Regulatory Officer st/tn
Enclosure Copy to: B.C. MRS Program Registered Entities.
BC Hydro Mandatory Reliability Standard
TPL-001-4 Assessment Report
May 2017
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page i
Table of Contents
1 Introduction ........................................................................................................ 1
1.1 Purpose of Report ..................................................................................... 1
1.2 Contents of the Report .............................................................................. 1
2 Special Considerations ....................................................................................... 2
2.1 Reliability Standards with Reliability Related Requirements for Planning Authority (PA)/Planning Coordinator (PC) .................................. 2
3 Report Summary ................................................................................................ 3
3.1 Draft Order ................................................................................................ 7
3.2 Proposed Process ..................................................................................... 8
4 Standards Assessment Process used in the Report .......................................... 9
4.1 Identification of the Revised Standard for Review ..................................... 9
4.2 Consultation .............................................................................................. 9
5 Assessment of Individual Standards ................................................................ 11
5.1 Analytical Approach to Assessment of Reliability Impact, Suitability, Cost of Adoption and Applicability ........................................................... 12
5.1.1 Analytical Approach in Assessing Adverse Reliability Impacts ..................................................................................... 12
5.1.2 Analytical Approach for the Suitability Assessment .................. 13
5.1.3 Analytical Approach for the Cost Assessment .......................... 14
5.1.4 Analytical Approach for the Application of the Reliability Standards ................................................................................. 14
5.2 Initial Screening of the Revised Standard for Adverse Reliability Impacts and Suitability ............................................................................ 14
5.3 Summary of Final Assessment of the Revised Standard ........................ 16
6 NERC Glossary of Terms ................................................................................. 19
6.1 NERC Glossary Terms Assessed by BC Hydro ...................................... 19
6.2 Initial Screening of the TPL-001-4 Terms and Definitions for Adverse Reliability Impacts and Suitability ............................................................ 20
6.3 Summary of Final Assessment of the NERC Glossary Terms Assessed in the Report ........................................................................... 23
7 Conclusions ...................................................................................................... 25
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page ii
List of Tables
Table 1 B.C. MRS Program Registered Entity List .......................................... 9
Table 2 Initial Screening of Revised Standards for Adverse Reliability Impact and Suitability ....................................................................... 16
Table 3 Final Assessment Summary of the Revised Standard ..................... 17
Table 4 Initial Screening of TPL-001-4 Terms for Adverse Reliability Impact and Suitability ....................................................................... 22
Table 5 Final Assessment Summary of NERC Glossary Terms ................... 24
Appendices
Appendix A Reliability Standards Assessed by BC Hydro
Appendix B-1 BC Hydro Feedback Survey Forms
Appendix B-2 Instructions for Registered Entities
Appendix B-3 External Stakeholder Feedback
Appendix C Draft Order
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 1
1 Introduction 1
1.1 Purpose of Report 2
Pursuant to the requirements of section 125.2(3) of the Utilities Commission Act 3
(UCA), British Columbia Hydro and Power Authority (BC Hydro) provides this 4
Mandatory Reliability Standard (MRS) TPL-001-4 Assessment Report (the Report), 5
pertaining to the bulk electric system (BES) in British Columbia (B.C.), to the British 6
Columbia Utilities Commission (BCUC or Commission) for consideration regarding 7
the reliability impacts, suitability, potential costs and standard applicability of 8
adopting the TPL-001-4 reliability standard (the Revised Standard), as well as 9
adopting five new defined terms (the TPL-001-4 Terms) from the North American 10
Electric Reliability Corporation (NERC) Glossary of Terms (NERC Glossary) dated 11
November 28, 2016. 12
1.2 Contents of the Report 13
The Report is organized as follows: 14
Section 2 outlines special considerations BC Hydro raises for the Commission’s 15
consideration. 16
Section 3 summarizes the Report findings, provides an outline of the Draft Order and 17
recommends a proposed process. 18
Section 4 explains BC Hydro’s assessment process. 19
Section 5 summarizes BC Hydro’s approach to assessing the Revised Standard, 20
and provides the results of that assessment in the case of the Revised Standard. 21
Section 6 summarizes the results of the assessment of the TPL-001-4 Terms 22
considered using the approach as described in section 5. 23
Section 7 provides BC Hydro’s conclusions. 24
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 2
2 Special Considerations 1
BC Hydro raises the following special considerations for this Report: 2
2.1 Reliability Standards with Reliability Related Requirements for 3
Planning Authority (PA)/Planning Coordinator (PC) 4
In the Reasons for Decision for Order No. R-41-13 (page 20), the Commission found 5
that the issue in relation to the extent of the PA/PC operations/footprint in B.C. was 6
beyond the scope of the MRS Assessment Report No. 6 review process and 7
indicated that a separate process would be established to consider the PA/PC 8
matter as it pertains to B.C. The Commission Order Nos. R 32-14, R 38-15, and 9
R-32-16 addressing the reliability standards in MRS Assessment Report Nos. 7, 8, 10
and 9, were consistent with this approach for reliability standards that reference the 11
PC function. At the time of this filing, the PC matter as it pertains to B.C. is 12
unresolved. 13
In this Report, the Revised Standard contains requirements that apply to the PC 14
function. The Revised Standard is a new reliability standard which revises, 15
consolidates, and replaces existing reliability standards TPL-001-0.1, TPL-002-0b, 16
TPL-003-0b, and TPL-004-0a which are all adopted and effective in B.C. 17
Requirement 7 in particular of the Revised Standard calls for the PC function in 18
conjunction with Transmission Planners in their PC area, to identify individual and 19
joint responsibilities for performing required studies as part of Planning 20
Assessments. The remaining requirements of the Revised Standard however, are 21
not solely dependent on the PC function and apply independently to the 22
Transmission Planner function also. 23
Therefore, BC Hydro recommends that Requirement 7 of the Revised Standard be 24
ordered by the Commission to be held in abeyance and be of no force or effect in 25
B.C. until the PC matter as it pertains to B.C. is resolved. As for the remaining 26
Revised Standard requirements, BC Hydro does not see any adverse reliability risk 27
at this time preventing a recommendation for adoption. 28
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 3
Once the PC function and footprints are defined in B.C., a reassessment of all 1
applicable reliability standards referencing the PC will go through the assessment 2
process in B.C. 3
3 Report Summary 4
The Revised Standard and the TPL-001-4 Terms recommended for adoption were 5
adopted by FERC during BC Hydro’s annual assessment period of 6
December 1, 2013 to November 30, 2014 (2014 Assessment Period). The Revised 7
Standard and the TPL-001-4 Terms were originally assessed in MRS Assessment 8
Report No. 8, filed with the Commission on May 15, 2015. In its assessment, 9
BC Hydro recommended holding the Revised Standard and TPL-001-4 Terms in 10
abeyance to allow time for BC Hydro to further assess the suitability of adopting the 11
Revised Standard and TPL-001-4 Terms in B.C. Commission Order No. R-38-15 to 12
MRS Assessment Report No. 8 held adoption of the Revised Standard and the 13
TPL-001-4 Terms in abeyance pending reassessment. Consistent with the approach 14
used to assess reliability standards in previous MRS assessment reports, BC Hydro 15
is filing a reliability standard specific assessment report for the Revised Standard 16
and the TPL-001-4 Terms. 17
The Revised Standard for Transmission System Planning Performance 18
Requirements consolidates four previously adopted transmission planning reliability 19
standards (TPL-001-0.1, TPL-002-0b, TPL-003-0b, and TPL-004-0a) into one 20
reliability standard which includes significant process revisions and now limits a 21
responsible entity’s (Transmission Planner or Planning Coordinator) use of Non 22
Consequential Load Loss (NCLL) 1 to meet performance requirements that would 23
otherwise be acceptable under the currently adopted reliability standards. 24
The currently adopted reliability standard TPL-002-0b (Table 1) sets out the 25
conditions where load shedding is and is not allowable and includes footnote ‘b’, 26
1 NCLL is defined as Non Interruptible Load loss that does not include: (1) Consequential Load Loss, (2) the
response of voltage sensitive Load, or (3) Load that is disconnected from the System by end user equipment.
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 4
which permits the use of load shedding as a planning solution for single contingency 1
events. The Revised Standard has a new Table 1 that does not allow load shedding 2
in some conditions that would otherwise be acceptable under the currently adopted 3
reliability standards and includes a more restrictive footnote ‘12’, which replaces 4
footnote ‘b’; footnote ‘12’ is set out as follows: 5
(i) An objective of the planning process is to minimize the likelihood and 6
magnitude of NCLL following planning events. In limited circumstances, NCLL 7
may be needed throughout the planning horizon to ensure that BES 8
performance requirements are met. 9
(ii) However, when NCLL is utilized under footnote 12 within the Near-Term 10
Transmission Planning Horizon to address BES performance requirements, 11
such interruption is limited to circumstances where the NCLL meets the 12
conditions shown in Attachment 1 of the Revised Standard (Attachment 1). 13
(iii) In no case can the planned NCLL under footnote 12 exceed 75 MW for US 14
registered entities. The amount of planned NCLL for a non-US Registered 15
Entity should be implemented in a manner that is consistent with, or under the 16
direction of, the applicable governmental authority or its agency in the non-US 17
jurisdiction. 18
Attachment 1 - Stakeholder Process 19
The Stakeholder Process, outlined in Attachment 1, includes the information that is 20
to be made available to stakeholders that attend meetings organized by the B.C. 21
registered entity planning to use NCLL under footnote ‘12’ as an element of a 22
Corrective Action Plan in the Near-Term Transmission Planning Horizon2 of the 23
Planning Assessment. Adoption of the Stakeholder Process as drafted within 24
Attachment 1 allows the flexibility for each responsible entity to develop their 25
process, subject to five requirements: 26
2 See NERC Glossary for definitions.
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 5
1. Meetings must be open to affected stakeholders including applicable regulatory 1
authorities; 2
2. Notice must be provided in advance of meetings to affected stakeholders 3
including applicable regulatory authorities which includes an agenda that 4
contains the date, time, and location for meetings, specific location(s) of NCLL 5
per footnote ‘12’ of the Revised Standard, and provisions for a stakeholder 6
comment period; 7
3. Purpose and scope of NCLL under footnote 12 must be made available 8
including the specific information for inclusion under Section II of Attachment 1; 9
4. A procedure for stakeholders to submit written questions or concerns and to 10
receive corresponding written responses; and 11
5. A dispute resolution process for any questions or concerns raised by 12
stakeholder written submissions that are not resolved to the stakeholder’s 13
satisfaction. 14
Attachment 1 - Instances for which Regulatory Review of NCLL under 15
Footnote 12 is required 16
Attachment 1 also outlines two instances for which Regulatory review of the use of 17
NCLL is required before NCLL under footnote ‘12’ is allowed as an element of a 18
Corrective Action Plan in Year One of the Planning Assessment: 19
1. Specific circumstances where the voltage level of the Contingency is greater 20
than 300 kV; and 21
2. The planned NCLL is greater than or equal to 25 MW. 22
Planned NCLL in B.C. 23
The Revised Standard, under footnote ‘12’, sets a limit of 75 MW of planned NCLL 24
for US registered entities. BC Hydro is not a US registered entity, and it follows that 25
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 6
if the Revised Standard is adopted as proposed, the 75 MW hard-cap on the use of 1
NCLL will not be applicable to BC Hydro. 2
Footnote ‘12’ further states that the amount of planned NCLL in B.C. should be 3
implemented in a manner that is consistent with, or under the direction of, the 4
applicable governmental authority or its agency in the non-US jurisdiction. 5
Consistent with footnote ‘12’ of the Revised Standard and Attachment 1 therein, 6
information regarding the planned use and the amount of NCLL will be provided to 7
the Commission as part of the Stakeholder Process and any Regulatory Review. In 8
this regard, the Commission will be informed of the planned use of NCLL in B.C., so 9
that it can direct its implementation, as required, on a case-by-case basis. 10
Dispute Resolution 11
As noted above, Attachment 1 sets out the requirements that must make up the 12
Stakeholder Process including a dispute resolution process for any question or 13
concern raised that is not resolved to the stakeholder’s satisfaction when registered 14
entities are planning to use NCLL. The Commission will be informed of the planned 15
use and amount of NCLL as well as any stakeholder questions and concerns as part 16
of the Stakeholder Process, and this puts it in a good position to resolve any 17
disputes between stakeholders and the responsible entity that is planning to use 18
NCLL. It is BC Hydro’s view that the Commission should be the final decision maker 19
in a dispute between stakeholders as to whether NCLL is an appropriate planning 20
element in light of the potential alternatives. This would be consistent with the 21
Commission’s ability to object to the use of NCLL under certain conditions as part of 22
a Regulatory Review contemplated in Attachment 1. 23
BC Hydro’s Adoption Recommendation 24
BC Hydro recommends that the Revised Standard and the TPL-001-4 Terms will 25
preserve or enhance the reliability of the BES in B.C., and thus are in the public 26
interest and suitable for adoption in B.C. with the exception of Requirement 7 due to 27
the PC matter as it pertains to B.C. BC Hydro is recommending the adoption of the 28
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 7
Revised Standard and the TPL-001-4 Terms assessed in the Report with the 1
exception of TPL-001-4, Requirement 7, which is recommended to be held in 2
abeyance until the PC matter as it pertains to B.C. is resolved. 3
BC Hydro has assessed its estimated incremental one-time and ongoing annual 4
costs of achieving and maintaining compliance with the adoption of the Revised 5
Standard and the TPL-001-4 Terms as mandatory in B.C. BC Hydro’s responses are 6
reproduced in full in Appendix B-1 of the Report. Consistent with the approach taken 7
in previous MRS assessment reports, BC Hydro has also sought input from B.C. 8
MRS registered entities regarding their estimated incremental one-time and annual 9
ongoing costs associated with achieving and maintaining compliance with 10
the Revised Standard and with using the TPL-001-4 Terms. 11
A complete list of the registered entities with whom BC Hydro consulted is provided 12
in Table 1, section 4.2 of the Report. A detailed breakdown of the estimated 13
incremental one-time and ongoing costs reported by BC Hydro and the registered 14
entities is provided in Table 3, section 5.3 and Table 5, section 6.3 of the Report. 15
Registered entities’ responses are reproduced in full in Appendix B-3 of the Report. 16
On the basis of BC Hydro’s own assessment and the responses received from those 17
registered entities providing cost estimates, BC Hydro estimates that the cumulative 18
cost for B.C. registered entities to achieve and maintain compliance with the Revised 19
Standard and the TPL-001-04 Terms being recommended for adoption in B.C. will 20
be at least $496,000 with respect to one-time costs, and at least $43,000 on an 21
annual ongoing basis. With respect to the costs considered herein, BC Hydro is of 22
the view that these expenditures are necessary to conduct planning assessments 23
per the new requirements, and to develop and implement a stakeholder consultation 24
process regarding the potential use of NCLL. 25
3.1 Draft Order 26
The Draft Order attached to the Report as Appendix C, includes the following draft 27
attachments: 28
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 8
Attachment A – Shows that the TPL-001-0.1, TPL-002-0b, TPL-003-0b, and 1
TPL-004-0a - reliability standards will be superseded by the Revised Standard 2
upon adoption. Attachment A also lists the TPL-001-4 Terms to be adopted in 3
B.C. The table within Attachment A includes the recommended effective dates 4
for the Revised Standard and the TPL-001-4 Terms; 5
Attachment B – Provides a list of all of the reliability standards that would be in 6
force in B.C., should the Commission adopt the Revised Standard and those 7
reliability standards held in abeyance. The table also provides the Commission 8
Order under which each of the reliability standards was adopted and under 9
which the effective date for each of the reliability standards was set; 10
Attachment C - Provides a list of the TPL-001-4 Terms and their definitions that 11
would be in force in B.C., should the Commission adopt the Revised Standard 12
and the TPL-001-4 Terms; and 13
Attachment D - For ease of reference, BC Hydro is including Table 1 in 14
Attachment D which lists all of the B.C. specific exceptions to the NERC 15
Glossary terms, starting from MRS Assessment Report No. 6.3 16
3.2 Proposed Process 17
This is a MRS specific assessment report to be submitted to the Commission. The 18
Commission is obligated by section 125.2(5) of the UCA to make the Report publicly 19
available and to consider any comments it receives in respect of the Report. 20
To make the Report publicly available, BC Hydro will publish a notice of the Report 21
on its public website and send a letter of notification to all B.C. MRS registered 22
entities. MRS registered entities with whom BC Hydro originally consulted in 23
connection with the preparation of the Report, are listed in Table 1, section 4.2. 24
3 Refer to Table 2 in Attachment D: All Commission Orders prior to Order No. R-41-13 for MRS Assessment
Report No. 6 adopted the entire NERC Glossary effective as of the date of the Order.
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 9
BC Hydro will respond to any comments on the Report. The Commission would then 1
determine whether all the issues raised in the comment process have been dealt 2
with to its satisfaction. If so, no further process would be required. If not, then a 3
written process could be established to deal with any outstanding issues. Upon 4
completion of the process, the Commission would determine whether the Revised 5
Standard and the TPL-001-4 Terms should be adopted in B.C. 6
4 Standards Assessment Process used in the Report 7
4.1 Identification of the Revised Standard for Review 8
Commission Order No. R-38-15 to MRS Assessment Report No. 8 held adoption of 9
the Revised Standard and the TPL-001-4 Terms in abeyance pending 10
reassessment. Consistent with the approach used to assess reliability standards in 11
previous MRS assessment reports, BC Hydro is filing a reliability standard specific 12
assessment report for the Revised Standard and the TPL-001-4 Terms. 13
The Revised Standard was FERC approved with an Order effective on 14
December 23, 2013 (within the 2014 Assessment Period) and superseded the 15
TPL-001-0.1, TPL-002-0b, TPL-003-0b, and TPL-004-0a reliability standards 16
effective January 1, 2016 in the U.S.4 Appendix A of the Report includes clean and 17
red-lined copies of the Revised Standard in comparison with the TPL-001-0.1 18
reliability standard adopted in B.C. 19
4.2 Consultation 20
BC Hydro consulted with the B.C. MRS registered entities listed below in Table 1. 21
Table 1 B.C. MRS Program Registered Entity List 22
Registered Entities Registered Entities (Continued)
Bear Mountain Wind Limited Partnership Meikle Wind Limited Partnership
British Columbia Hydro and Power Authority Northwood Pulp Mill
4 Docket No. RM12-1-000 and RM13-9-000; Order 786; Issue Date: October 17, 2013; Publication Date:
October 23, 2013; Effective date: December 23, 2013.
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 10
Registered Entities Registered Entities (Continued)
Cape Scott Wind LP Powerex Corp.
Capital Power Limited Partnership Prince George Pulp & Paper Mill
Cariboo Pulp & Paper Company Quesnel River Pulp and Paper
Catalyst Paper ‐ Crofton Division Rio Tinto Alcan
Catalyst Paper ‐ Port Alberni Division Shell Energy North America (Canada) Inc.
Catalyst Paper ‐ Powell River Division Shell Energy North America (U.S.) L.P.
Coast Mountain Hydro Limited Partnership Teck Metals Ltd.
Dokie General Partnership Toba Montrose General Partnership
FortisBC Inc. Tolko Industries Limited
Howe Sound Pulp & Paper Corporation TransAlta Energy Marketing Corp
Innergex Renewable Energy Inc. TransCanada Energy Sales Ltd.
Intercontinental Pulp Mill V.I. Power Limited Partnership
Jimmie Creek Limited Partnership WESCUP
Lehigh Cement
Each registered entity on the list, with the exception of Meikle Wind Limited 1
Partnership, was issued an email package on December 19, 2016 advising that 2
37 reliability standards (including the Revised Standard) and 39 NERC Glossary 3
terms (including the five TPL-001-4 Terms) would be assessed and that the 4
assessment was due to be filed on May 1, 2017 with the Commission. Meikle Wind 5
Limited Partnership was issued an email package on February 7, 2017 when 6
BC Hydro was made aware of their registration to the B.C. MRS Program on 7
February 3, 2017 under Commission Order No. R-41-16. The email package 8
contained instructions and a link to the BC Hydro Reliability internet website where 9
two survey forms (one for reliability standards and another for NERC Glossary 10
terms) were provided for completion by entities (refer to Appendix B). Entities were 11
asked to complete and return the survey forms to BC Hydro by end of day 12
February 28, 2017. A follow-up email was sent on January 6, 2017 correcting some 13
minor updates to the email package sent on December 19, 2016. On January 13, 14
2017, BC Hydro held an informational session via teleconference for all registered 15
entities in B.C. A reminder notice was also sent to each registered entity on 16
January 31, 2017. On February 15, 2017, an email was sent to FortisBC Inc. 17
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 11
correcting a minor error in a note pertaining to TPL-001-4 Requirement 3 and it’s 1
applicability to the Transmission Planner function. This email was sent to FortisBC 2
Inc. as they, aside from BC Hydro, are the only other Transmission Planner 3
registered in the B.C. MRS program. On February 23, 2017, an extension notice was 4
sent to all registered entities requesting survey forms to be returned to BC Hydro by 5
end of day March 6, 2017. 6
The entities were asked to provide information for each reliability standard 7
and NERC Glossary term as follows: 8
(a) Indicate whether there were either no changes to the entity’s processes, or 9
state the high-level incremental activities or new activities needed to be 10
completed in order to become compliant; 11
(b) For each incremental or new activity, indicate associated estimated costs in 12
dollar amounts, and identify the assumptions used in developing estimates. The 13
following costs were to be considered: 14
Activities where a one-time capital cost will incur; and 15
Activities where there are ongoing annual costs associated with compliance. 16
(c) Include an assessment of the amount of time reasonably required to come into 17
compliance with the reliability standard and NERC Glossary term once adopted 18
by the Commission. The time should be reflective of any incremental or new 19
activities identified. 20
Including BC Hydro, a total of 31 registered entities were contacted. BC Hydro’s 21
responses to the Revised Standard and TPL-001-4 Terms are attached in full in 22
Appendix B-1 and registered entities’ responses are attached in full in Appendix B-3. 23
5 Assessment of Individual Standards 24
BC Hydro has assessed the Revised Standard against the criteria stipulated by 25
legislation in B.C. (section 125.2(3) of the UCA). 26
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 12
Section 5.1 summarizes BC Hydro’s approach to addressing these criteria; 1
Section 5.2 provides a description of the Revised Standard and an explanation 2
of the reliability and suitability issues along with BC Hydro’s conclusions; and 3
Section 5.3 addresses the cost assessment and summarizes BC Hydro’s final 4
assessment of the Revised Standard. 5
5.1 Analytical Approach to Assessment of Reliability Impact, 6
Suitability, Cost of Adoption and Applicability 7
The analytical approach taken to evaluate the reliability standards against the 8
legislated assessment criteria has not changed from that used in previous MRS 9
assessment reports. Given the amendments to the UCA in October 2015, BC Hydro 10
has assessed the Application of the Revised Standard as described in section 5.1.4 11
of this Report. Compliance-related provisions included in the reliability standards are 12
not applicable to the meaning of “reliability standards” defined in section 125.2 of the 13
UCA. As a result, BC Hydro does not assess these compliance-related provisions in 14
the Report. To indicate that BC Hydro does not assess this part of the reliability 15
standards, the compliance-related provisions have been struck-through in the clean 16
and redline versions of the Revised Standard included in Appendix A of the Report. 17
Nevertheless, BC Hydro recognizes that the compliance-related provisions may be 18
adopted by the Commission. 19
In addition, BC Hydro is of the opinion that the effective dates stated in the Revised 20
Standard are likewise not applicable. Accordingly, a strike-through of section A.5 – 21
Effective Date – is included in the clean and redlined versions of the Revised 22
Standard included in Appendix A of the Report. 23
5.1.1 Analytical Approach in Assessing Adverse Reliability Impacts 24
BC Hydro has used the same approach in assessing adverse reliability impacts that 25
was used in prior MRS assessment reports. This approach relies on a determination 26
that those reliability standards that have either: (i) performance requirements that 27
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 13
are not currently employed in B.C., or (ii) requirements as stringent as, or more 1
stringent, than requirements or practices currently employed in B.C. that will, by 2
definition, have neutral or positive impacts on the reliability of the BES in B.C. 3
Consequently, BC Hydro’s approach is to identify performance requirements 4
associated with new, or revisions to, reliability standards that are less stringent than 5
the existing reliability standards already adopted in B.C., or practices otherwise 6
mandated in utility tariffs or business practices approved or endorsed by the 7
Commission. 8
5.1.2 Analytical Approach for the Suitability Assessment 9
The Report uses the same criteria to assess the suitability of a reliability standard 10
that were developed for the previous MRS assessment reports. The two criteria 11
used for this analysis are set out below: 12
(a) "Administrative Suitability" means that the requirements in the reliability 13
standard are fit and appropriate for implementation in light of the policy and 14
regulatory framework in B.C. The requirements can be implemented without 15
requiring the ongoing involvement of NERC, the U.S. Government, or other 16
extra‐jurisdictional entities in such a manner as would impair the operation and 17
enforcement of the requirement in B.C. If one or more of the requirements in 18
the reliability standard incorporate by reference reliability standards not yet 19
adopted in other jurisdictions, the remaining requirements in the reliability 20
standard can still be implemented presently in B.C. without giving effect to the 21
particular requirement(s) containing the cross reference; and 22
(b) "Technical Suitability" means that the requirements in the reliability standard 23
are fit and appropriate for implementation in B.C., taking into consideration the 24
unique geographical, structural, design, and functional aspects of the B.C. BES 25
and the assets that support the reliable operation of this system. 26
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 14
5.1.3 Analytical Approach for the Cost Assessment 1
BC Hydro’s approach to assess the potential costs of the Revised Standard in the 2
Report is consistent with the approach used to assess reliability standards in 3
previous MRS assessment reports. The objective is to provide an estimate of the 4
costs of adopting reliability standards in B.C. sufficient to inform the Commission’s 5
public interest assessment. Accordingly, only the costs that B.C. entities will 6
potentially incur in order to achieve and maintain full compliance with the Revised 7
Standard were assessed. Any costs associated with B.C. entities attaining or 8
maintaining compliance with pre-existing reliability standards in B.C. were excluded. 9
5.1.4 Analytical Approach for the Application of the Reliability Standards 10
Pursuant to the obligations contained in paragraph 125.2(3)(c.1) of the UCA, 11
BC Hydro’s approach to assess the application of the Revised Standard to persons 12
or persons in respect of specified equipment in the Report is consistent with the 13
approach used to review reliability standards in previous MRS assessment reports. 14
BC Hydro assesses the Applicability section contained in the Introduction of the 15
Revised Standard at Section A.4, to ensure consistency with the functional 16
registration categories contained in the B.C. MRS program, as contained in the MRS 17
Rules of Procedure in B.C. BC Hydro considers this approach to satisfy the new 18
obligations contained in paragraph 125.2(3)(c.1) of the UCA. 19
Any issues regarding the applicability of reliability standards to particular entities can 20
be addressed in the context of the Commission’s registration and compliance 21
regime. 22
5.2 Initial Screening of the Revised Standard for Adverse 23
Reliability Impacts and Suitability 24
In terms of the assessment of the Revised Standard against the reliability and 25
suitability criteria, BC Hydro first performed an initial screening of the Revised 26
Standard against the criteria described in section 5.1 of the Report to identify issues 27
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 15
for further examination. This initial screening does not purport to be BC Hydro’s final 1
assessment of the Revised Standard. 2
The results of BC Hydro’s initial screening of the Revised Standards for potential 3
issues regarding adverse reliability impacts and suitability are summarized below in 4
Table 2, which includes: 5
The “Standard” column, which identifies the Revised Standards assessed; 6
The “Changed from Commission Approved Standard” column, which identifies 7
whether the Revised Standard is a revision to a reliability standard already 8
adopted by the Commission; 9
The “Adverse Impact” column, which identifies potential issues relating to 10
adverse reliability impact; 11
The “Suitability Issues” columns, which identify potential suitability issues 12
related to the Revised Standards: 13
Requires NERC Approval/Participation: Identifies a potential Technical or 14
Administrative Suitability issue as related to continued reliance on approvals 15
by NERC and/or participation by NERC in order to implement the 16
requirements of a given reliability standard; 17
Requires Provisions of Information to NERC or the Western Electricity 18
Coordinating Council (WECC): Identifies a potential Technical or 19
Administrative Suitability issue with a Revised Standard that requires 20
ongoing reporting of information to NERC or WECC (i.e., lack of clarity on 21
reporting instructions, references to undefined processes or reporting tools, 22
etc.); 23
Refers to Standard not yet FERC Approved: Identifies a potential Technical 24
or Administrative Suitability issue with a Revised Standard as it contains one 25
or more references to other reliability standards that have not yet been 26
approved by FERC in the U.S., and thereby not assessed for adoption in 27
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 16
B.C., which would affect the ability to implement one or more requirements 1
of the Revised Standard; and 2
Other Suitability Issues: Identifies whether there are any other Administrative 3
Suitability, Technical Suitability or reliability standard Applicability issues identified, 4
apart from the categories already defined, that would affect the ability to implement 5
the requirements of the Revised Standard. 6
Table 2 Initial Screening of Revised Standards for 7
Adverse Reliability Impact and Suitability 8
Standard Changed from
Commission Approved
Standard
Adverse Impact
Suitability Issues
Requires NERC Approval/ Participation
Requires Provisions of Information to NERC or WECC
Refers to Standard not yet FERC Approved
Other Suitability/
Applicability Issues
To NERC
To WECC
TPL-001-4 Yes No No Yes2 No No Yes1
1 Revised Standards contain reliability related requirements for the PA/PC function. Please refer to section 2.1. 9
2 Revised Standard TPL-001-4, Attachment 1 references submitting information to the ERO. In the U.S. the ERO is NERC; however 10
there is no ERO in B.C. Similar ERO reporting requirements exist within the BCUC adopted and effective reliability standards, for 11
which B.C. entities have not been required to report events to NERC. 12
5.3 Summary of Final Assessment of the Revised Standard 13
BC Hydro’s final assessment of the Revised Standard, based on internal and 14
external responses from B.C. registered entities is summarized below in Table 3, 15
which includes: 16
BC Hydro’s final assessment as to whether the adoption of the Revised 17
Standard will give rise to adverse reliability consequences; 18
BC Hydro’s final assessment as to the suitability of the Revised Standard, 19
based on the criteria described in section 5.1.2; 20
BC Hydro’s and registered entities’ estimated incremental one time and 21
ongoing annual costs to achieve and maintain compliance associated with the 22
Revised Standards; and 23
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 17
BC Hydro’s recommended effective dates, based on comments made by 1
registered entities who responded to the stakeholder survey, for the Revised 2
Standard. BC Hydro recommends that these recommended effective dates be 3
adopted by the Commission to replace section A.5 Effective Date in the 4
Revised Standard. For informational purposes only feedback that does not align 5
with BC Hydro’s recommended effective dates are listed under ‘Feedback 6
Exceptions’ where applicable. 7
Table 3 Final Assessment Summary of the 8
Revised Standard 9
Standard Adverse Reliability
Consequences
Suitability Issues
One-time Cost ($)
Ongoing Cost ($/year)
Recommended Effective Date
TPL-001-04 None reported. R7: Yes; further clarification is requested of the standard from the BCUC regarding PC footprints and entities responsible.1
BC Hydro –
R1: $10,000 total for 100 man hours of time; equipment spares availability need to be dove tailed with power flow base cases and contingency lists. The short circuit study equipment models are to be included in existing TPL assessment planning models.
R2: $56,000 total for eight transmission planners over two weeks; study methodologies needs to be re written to take in to account the new requirements of
a) Sensitivity studies
b) equipment spares availability related analysis
c) short circuit studies and analysis of results
d) options of alternatives to reinforcements detailed in the standard.
BC Hydro –
R2: $28,000 total; about one more week in increase of studies required for about eight transmission planners (280 man hours). This incremental increase in TPL assessment activity is due to the additional TPL-001-4 requirements.
R4: Unknown at this time; to come out of future planning studies.
R7: To be determined. Unable to be assessed at this time.1
Fortis BC –
R1-R6, R8: $15,000 - $20,000; new short circuit analyses will be
BC Hydro’s Consolidated Recommendations:
R1: First day of first calendar quarter, two years after BCUC adoption.
R2-R6, R8: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following BCUC approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 18
Standard Adverse Reliability
Consequences
Suitability Issues
One-time Cost ($)
Ongoing Cost ($/year)
Recommended Effective Date
R4: $400,000 total due to the estimated use of NCLL on approximately four occasions costing ~ $100,000 each for the stakeholder process; if the TPL assessments identify there is a need to shed non-consequential load , then the use of NCLL will need to be reviewed through an open and transparent stakeholder process.
R7: To be determined. Unable to be assessed at this time.1
Fortis BC –
R1-R6, R8: $30,000-$50,000 total; studies using short circuit models with any planned generation and transmission facilities in service which could impact the study area will need to be developed and maintained. Minor modifications to the annual Fortis BC planning study will be required.
required annually. - P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
R7: To be determined. Unable to be assessed at this time.1
Feedback Exceptions:
Fortis BC –
R1-R6, R8: 24 months to 36 months after BCUC approval.
1 Revised Standards contain reliability related requirements for the PA/PC function. Please refer to section 2.1. 1
BC Hydro’s assessment is that the Revised Standard will either maintain or promote 2
the reliability of the BES in B.C. 3
BC Hydro’s final assessment as to the application of the Revised Standard is to 4
recommend that section A.4 Applicability in the Revised Standard be adopted by the 5
Commission. 6
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 19
6 NERC Glossary of Terms 1
This section outlines the TPL-001-4 Terms assessed in the Report and the results of 2
the assessment. 3
Section 6.1 provides a description of each assessed TPL-001-4 Term; 4
Section 6.2 describes the results of the initial screening of the TPL-001-4 Terms 5
and definitions for adverse reliability impacts and suitability; and 6
Section 6.3 summarizes the results of the assessment of the TPL-001-4 Terms 7
along with BC Hydro’s conclusions. 8
The Revised Standard assessed by BC Hydro in this Report is based on the defined 9
terms contained in the NERC Glossary dated November 28, 2016 that are intended 10
for the Revised Standard. Accordingly, BC Hydro has included the TPL-001-4 Terms 11
and their definitions in Attachment C to Appendix C (Draft Order) of the Report. The 12
TPL-001-4 Terms are integral to the Revised Standard, and should be adopted by 13
the Commission in conjunction with the Revised Standard assessed in the Report in 14
order to achieve and maintain consistency with NERC reliability standards going 15
forward. 16
6.1 NERC Glossary Terms Assessed by BC Hydro 17
As provided in Attachment C to Appendix C (Draft Order) of the Report, the NERC 18
Glossary contains five TPL-001-4 Terms that are intended for the Revised Standard 19
and have been adopted by NERC and approved by FERC on October 17, 2013, 20
within the 2014 Assessment Period. 21
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 20
6.2 Initial Screening of the TPL-001-4 Terms and Definitions for 1
Adverse Reliability Impacts and Suitability 2
BC Hydro applies a similar analytical approach to the assessment of the reliability 3
impact, suitability and cost of adoption of the TPL-001-4 Terms as is described in 4
section 5.1 of the Report for the assessment of the Revised Standard. The results of 5
BC Hydro’s initial screening of the TPL-001-4 Terms for potential issues regarding 6
adverse reliability impacts and suitability are summarized below in Table 4, which 7
includes: 8
The “NERC Glossary Term” column identifies the TPL-001-4 Terms; 9
The “Changed from Commission Approved Term and Definition” column, which 10
identifies whether the TPL-001-4 Term and/or its definition is a revision to a 11
Commission adopted NERC Glossary term and/or its definition, or whether it is 12
being retired; 13
The “Adverse Impact” column, which identifies potential issues relating to 14
adverse reliability impact; and 15
The “Suitability Issues” columns, which identify potential suitability issues 16
related to TPL-001-4 Terms superseding Commission approved NERC 17
Glossary terms: 18
Requires NERC Approval/Participation: Identifies a potential Administrative 19
or Technical Suitability issue as related to continued reliance on approvals 20
by NERC and/or participation in NERC in order to implement the definition of 21
a TPL-001-4 Term; 22
Requires Provisions of Information to NERC or WECC: Identifies a potential 23
Administrative or Technical Suitability issue with a TPL-001-4 Term and its 24
definition that requires ongoing reporting of information to NERC or WECC 25
(i.e., lack of clarity on reporting instructions, references to undefined 26
processes or reporting tools, etc.); 27
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 21
Refers to Standard, Term, or Definition not yet FERC Approved: Identifies a 1
potential Technical or Administrative Suitability issue with a TPL-001-4 Term 2
and/or its definition as it contains one or more references to reliability 3
standards or other NERC Glossary terms and associated definitions that 4
have not yet been approved by FERC in the U.S., and thereby not assessed 5
for adoption in B.C. This would affect the ability to implement the TPL-001-4 6
Term and its definition; and 7
Other Suitability Issues: Identifies whether there are any other 8
Administrative or Technical Suitability issues identified, apart from the 9
categories already defined, that would affect the ability to implement 10
the TPL-001-4 Term and its definition. 11
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 22
Table 4 Initial Screening of TPL-001-4 Terms for Adverse Reliability Impact and 1
Suitability 2
NERC Glossary Term Changed from Commission
Approved Term and Definition
Adverse Impact
Suitability Issues
Requires NERC Approval/ Participation
Requires Provisions of Information to NERC or WECC
Refers to Term or Definition not yet FERC Approved
Other Suitability Issues
To NERC To WECC
Bus-tie Breaker New None No No No No None
Consequential Load Loss New None No No No No None
Long-Term Transmission Planning Horizon
New None No No No No None
Non-Consequential Load Loss New None No No No No None
Planning Assessment New None No No No No None
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 23
6.3 Summary of Final Assessment of the NERC Glossary Terms 1
Assessed in the Report 2
BC Hydro’s final assessment of the five TPL-001-4 Terms based on survey 3
responses from registered entities is summarized below in Table 5, which includes: 4
BC Hydro’s final assessment as to whether the adoption of the TPL-001-4 5
Terms will give rise to adverse reliability consequences; 6
BC Hydro’s final assessment as to the suitability of the TPL-001-4 Terms, 7
based on the criteria described in section 5.1; 8
The estimated incremental one-time and ongoing annual costs to achieve and 9
maintain compliance with the reliability standards that make reference to 10
the TPL-001-4 Terms as reported by BC Hydro; and 11
BC Hydro’s recommended effective dates, based on comments made by 12
registered entities who responded to the stakeholder survey, for the TPL-001-4 13
Terms. BC Hydro recommends that these recommended effective dates be 14
adopted by the Commission.15
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 24
Table 5 Final Assessment Summary of NERC Glossary Terms 1
NERC Glossary Term
Adverse Reliability Consequences
Suitability Issues
One-time Cost
($)
Ongoing Cost
($/year)
Recommended Effective Date
Bus-tie Breaker None None
Included as part of TPL-001-4 reliability standard implementation costs
Included as part of TPL-001-4 reliability standard implementation costs
Coincide with earliest TPL-001-4 effective date in B.C.
Consequential Load Loss
None None Included as part of TPL-001-4 reliability standard implementation costs
Included as part of TPL-001-4 reliability standard implementation costs
Coincide with earliest TPL-001-4 effective date in B.C.
Long-Term Transmission Planning Horizon
None None Included as part of TPL-001-4 reliability standard implementation costs
Included as part of TPL-001-4 reliability standard implementation costs
Coincide with earliest TPL-001-4 effective date in B.C.
Non-Consequential Load Loss
None None Included as part of TPL-001-4 reliability standard implementation costs
Included as part of TPL-001-4 reliability standard implementation costs
BC Hydro’s Consolidated Recommendation: Coincide with earliest TPL-001-4 effective date in B.C.
Feedback Exceptions: Northwood Pulp Mill – Immediately after BCUC adoption.
Planning Assessment
None None Included as part of TPL-001-4 reliability standard implementation costs
Included as part of TPL-001-4 reliability standard implementation costs
Coincide with earliest TPL-001-4 effective date in B.C.
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 25
BC Hydro’s assessment is that all of the assessed TPL-001-4 Terms will either 1
maintain or promote the reliability of the BES in B.C. Based on the assessment 2
above, the minimum total costs required to adopt these five TPL-001-4 Terms have 3
been incorporated as part of the estimated costs for the implementation of the 4
Revised Standard in section 5.3 of the Report. 5
7 Conclusions 6
BC Hydro has assessed the Revised Standard adopted by FERC in the U.S. during 7
the 2014 Assessment Period. BC Hydro has concluded that the Revised Standard 8
will preserve or enhance the reliability of the BES in B.C., and thus will serve the 9
public interest and is suitable for adoption in B.C. with the exception of TPL-001-4, 10
Requirement 7, which is recommended to be held in abeyance until the PC matter 11
as it pertains to B.C. is resolved. BC Hydro recommends that the Revised Standard, 12
be adopted by the Commission and should have effective dates that are based on 13
the recommended effective dates included in Table 3, section 5.3 and Attachment A 14
to Appendix C (Draft Order) of the Report. 15
BC Hydro has assessed the five TPL-001-4 Terms adopted by FERC in the U.S. 16
during the 2014 Assessment Period. BC Hydro has concluded that the five 17
TPL-001-4 Terms in the NERC Glossary dated November 28, 2016 be adopted by 18
the Commission. The TPL-001-4 Terms assessed in the Report will preserve or 19
enhance the reliability of the BES in B.C., and thus will serve the public interest and 20
are suitable for adoption in B.C. The TPL-001-4 Terms and their definitions are 21
included in Attachment C to Appendix C (Draft Order) of the Report. BC Hydro 22
recommends that these five TPL-001-4 Terms be adopted by the Commission and 23
should have effective dates that are based on the recommended effective dates 24
included in Table 5, section 6.3 and Attachment A to Appendix C (Draft Order) of the 25
Report. 26
May 2017
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 26
Regarding the replacement of the Commission approved reliability standards 1
TPL-001-0.1, TPL-002-0b, TPL-003-0b, and TPL-004-0a being superseded by 2
the Revised Standard, BC Hydro recommends that, to avoid duplication, these 3
currently approved reliability standards be ordered to remain in effect until the 4
effective dates of the superseding Revised Standard. 5
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Appendix A
Reliability Standards Assessed by BC Hydro
Clean
Standard TPL-001-4 — Transmission System Planning Performance Requirements
1
A. Introduction 1. Title: Transmission System Planning Performance Requirements
2. Number: TPL-001-4
3. Purpose: Establish Transmission system planning performance requirements within the planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a broad spectrum of System conditions and following a wide range of probable Contingencies.
4. Applicability:
4.1. Functional Entity
4.1.1. Planning Coordinator.
4.1.2. Transmission Planner.
5. Effective Date: Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar quarter, 12 months after applicable regulatory approval. In those jurisdictions where regulatory approval is not required, Requirements R1 and R7 become effective on the first day of the first calendar quarter, 12 months after Board of Trustees adoption or as otherwise made effective pursuant to the laws applicable to such ERO governmental authorities.
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the first calendar quarter, 24 months after applicable regulatory approval. In those jurisdictions where regulatory approval is not required, all requirements, except as noted below, go into effect on the first day of the first calendar quarter, 24 months after Board of Trustees adoption or as otherwise made effective pursuant to the laws applicable to such ERO governmental authorities.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval, or in those jurisdictions where regulatory approval is not required on the first day of the first calendar quarter 84 months after Board of Trustees adoption or as otherwise made effective pursuant to the laws applicable to such ERO governmental authorities, Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted element)
P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted element)
P2-1 P2-2 (above 300 kV) P2-3 (above 300 kV) P3-1 through P3-5 P4-1 through P4-5 (above 300 kV) P5 (above 300 kV)
Standard TPL-001-4 — Transmission System Planning Performance Requirements
2
B. Requirements R1. Each Transmission Planner and Planning Coordinator shall maintain System models within its
respective area for performing the studies needed to complete its Planning Assessment. The models shall use data consistent with that provided in accordance with the MOD-010 and MOD-012 standards, supplemented by other sources as needed, including items represented in the Corrective Action Plan, and shall represent projected System conditions. This establishes Category P0 as the normal System condition in Table 1. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
1.1. System models shall represent:
1.1.1. Existing Facilities
1.1.2. Known outage(s) of generation or Transmission Facility(ies) with a duration of at least six months.
1.1.3. New planned Facilities and changes to existing Facilities
1.1.4. Real and reactive Load forecasts
1.1.5. Known commitments for Firm Transmission Service and Interchange
1.1.6. Resources (supply or demand side) required for Load
R2. Each Transmission Planner and Planning Coordinator shall prepare an annual Planning Assessment of its portion of the BES. This Planning Assessment shall use current or qualified past studies (as indicated in Requirement R2, Part 2.6), document assumptions, and document summarized results of the steady state analyses, short circuit analyses, and Stability analyses. [Violation Risk Factor: High] [Time Horizon: Long-term Planning]
2.1. For the Planning Assessment, the Near-Term Transmission Planning Horizon portion of the steady state analysis shall be assessed annually and be supported by current annual studies or qualified past studies as indicated in Requirement R2, Part 2.6. Qualifying studies need to include the following conditions:
2.1.1. System peak Load for either Year One or year two, and for year five.
2.1.2. System Off-Peak Load for one of the five years.
2.1.3. P1 events in Table 1, with known outages modeled as in Requirement R1, Part 1.1.2, under those System peak or Off-Peak conditions when known outages are scheduled.
2.1.4. For each of the studies described in Requirement R2, Parts 2.1.1 and 2.1.2, sensitivity case(s) shall be utilized to demonstrate the impact of changes to the basic assumptions used in the model. To accomplish this, the sensitivity analysis in the Planning Assessment must vary one or more of the following conditions by a sufficient amount to stress the System within a range of credible conditions that demonstrate a measurable change in System response :
• Real and reactive forecasted Load. • Expected transfers. • Expected in service dates of new or modified Transmission Facilities. • Reactive resource capability. • Generation additions, retirements, or other dispatch scenarios.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
3
• Controllable Loads and Demand Side Management. • Duration or timing of known Transmission outages.
2.1.5. When an entity’s spare equipment strategy could result in the unavailability of major Transmission equipment that has a lead time of one year or more (such as a transformer), the impact of this possible unavailability on System performance shall be studied. The studies shall be performed for the P0, P1, and P2 categories identified in Table 1 with the conditions that the System is expected to experience during the possible unavailability of the long lead time equipment.
2.2. For the Planning Assessment, the Long-Term Transmission Planning Horizon portion of the steady state analysis shall be assessed annually and be supported by the following annual current study, supplemented with qualified past studies as indicated in Requirement R2, Part 2.6:
2.2.1. A current study assessing expected System peak Load conditions for one of the years in the Long-Term Transmission Planning Horizon and the rationale for why that year was selected.
2.3. The short circuit analysis portion of the Planning Assessment shall be conducted annually addressing the Near-Term Transmission Planning Horizon and can be supported by current or past studies as qualified in Requirement R2, Part 2.6. The analysis shall be used to determine whether circuit breakers have interrupting capability for Faults that they will be expected to interrupt using the System short circuit model with any planned generation and Transmission Facilities in service which could impact the study area.
2.4. For the Planning Assessment, the Near-Term Transmission Planning Horizon portion of the Stability analysis shall be assessed annually and be supported by current or past studies as qualified in Requirement R2, Part2.6. The following studies are required:
2.4.1. System peak Load for one of the five years. System peak Load levels shall include a Load model which represents the expected dynamic behavior of Loads that could impact the study area, considering the behavior of induction motor Loads. An aggregate System Load model which represents the overall dynamic behavior of the Load is acceptable.
2.4.2. System Off-Peak Load for one of the five years.
2.4.3. For each of the studies described in Requirement R2, Parts 2.4.1 and 2.4.2, sensitivity case(s) shall be utilized to demonstrate the impact of changes to the basic assumptions used in the model. To accomplish this, the sensitivity analysis in the Planning Assessment must vary one or more of the following conditions by a sufficient amount to stress the System within a range of credible conditions that demonstrate a measurable change in performance:
• Load level, Load forecast, or dynamic Load model assumptions. • Expected transfers. • Expected in service dates of new or modified Transmission Facilities. • Reactive resource capability. • Generation additions, retirements, or other dispatch scenarios.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
4
2.5. For the Planning Assessment, the Long-Term Transmission Planning Horizon portion of the Stability analysis shall be assessed to address the impact of proposed material generation additions or changes in that timeframe and be supported by current or past studies as qualified in Requirement R2, Part2.6 and shall include documentation to support the technical rationale for determining material changes.
2.6. Past studies may be used to support the Planning Assessment if they meet the following requirements:
2.6.1. For steady state, short circuit, or Stability analysis: the study shall be five calendar years old or less, unless a technical rationale can be provided to demonstrate that the results of an older study are still valid.
2.6.2. For steady state, short circuit, or Stability analysis: no material changes have occurred to the System represented in the study. Documentation to support the technical rationale for determining material changes shall be included.
2.7. For planning events shown in Table 1, when the analysis indicates an inability of the System to meet the performance requirements in Table 1, the Planning Assessment shall include Corrective Action Plan(s) addressing how the performance requirements will be met. Revisions to the Corrective Action Plan(s) are allowed in subsequent Planning Assessments but the planned System shall continue to meet the performance requirements in Table 1. Corrective Action Plan(s) do not need to be developed solely to meet the performance requirements for a single sensitivity case analyzed in accordance with Requirements R2, Parts 2.1.4 and 2.4.3. The Corrective Action Plan(s) shall:
2.7.1. List System deficiencies and the associated actions needed to achieve required System performance. Examples of such actions include:
• Installation, modification, retirement, or removal of Transmission and generation Facilities and any associated equipment.
• Installation, modification, or removal of Protection Systems or Special Protection Systems
• Installation or modification of automatic generation tripping as a response to a single or multiple Contingency to mitigate Stability performance violations.
• Installation or modification of manual and automatic generation runback/tripping as a response to a single or multiple Contingency to mitigate steady state performance violations.
• Use of Operating Procedures specifying how long they will be needed as part of the Corrective Action Plan.
• Use of rate applications, DSM, new technologies, or other initiatives.
2.7.2. Include actions to resolve performance deficiencies identified in multiple sensitivity studies or provide a rationale for why actions were not necessary.
2.7.3. If situations arise that are beyond the control of the Transmission Planner or Planning Coordinator that prevent the implementation of a Corrective Action Plan in the required timeframe, then the Transmission Planner or Planning Coordinator is permitted to utilize Non-Consequential Load Loss and curtailment of Firm Transmission Service to correct the situation that would normally not be permitted in Table 1, provided that the Transmission Planner
Standard TPL-001-4 — Transmission System Planning Performance Requirements
5
or Planning Coordinator documents that they are taking actions to resolve the situation. The Transmission Planner or Planning Coordinator shall document the situation causing the problem, alternatives evaluated, and the use of Non-Consequential Load Loss or curtailment of Firm Transmission Service.
2.7.4. Be reviewed in subsequent annual Planning Assessments for continued validity and implementation status of identified System Facilities and Operating Procedures.
2.8. For short circuit analysis, if the short circuit current interrupting duty on circuit breakers determined in Requirement R2, Part 2.3 exceeds their Equipment Rating, the Planning Assessment shall include a Corrective Action Plan to address the Equipment Rating violations. The Corrective Action Plan shall:
2.8.1. List System deficiencies and the associated actions needed to achieve required System performance.
2.8.2. Be reviewed in subsequent annual Planning Assessments for continued validity and implementation status of identified System Facilities and Operating Procedures.
R3. For the steady state portion of the Planning Assessment, each Transmission Planner and Planning Coordinator shall perform studies for the Near-Term and Long-Term Transmission Planning Horizons in Requirement R2, Parts 2.1, and 2.2. The studies shall be based on computer simulation models using data provided in Requirement R1. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
3.1. Studies shall be performed for planning events to determine whether the BES meets the performance requirements in Table 1 based on the Contingency list created in Requirement R3, Part 3.4.
3.2. Studies shall be performed to assess the impact of the extreme events which are identified by the list created in Requirement R3, Part 3.5.
3.3. Contingency analyses for Requirement R3, Parts 3.1 & 3.2 shall:
3.3.1. Simulate the removal of all elements that the Protection System and other automatic controls are expected to disconnect for each Contingency without operator intervention. The analyses shall include the impact of subsequent:
3.3.1.1. Tripping of generators where simulations show generator bus voltages or high side of the generation step up (GSU) voltages are less than known or assumed minimum generator steady state or ride through voltage limitations. Include in the assessment any assumptions made.
3.3.1.2. Tripping of Transmission elements where relay loadability limits are exceeded.
3.3.2. Simulate the expected automatic operation of existing and planned devices designed to provide steady state control of electrical system quantities when such devices impact the study area. These devices may include equipment such as phase-shifting transformers, load tap changing transformers, and switched capacitors and inductors.
3.4. Those planning events in Table 1, that are expected to produce more severe System impacts on its portion of the BES, shall be identified and a list of those Contingencies
Standard TPL-001-4 — Transmission System Planning Performance Requirements
6
to be evaluated for System performance in Requirement R3, Part 3.1 created. The rationale for those Contingencies selected for evaluation shall be available as supporting information.
3.4.1. The Planning Coordinator and Transmission Planner shall coordinate with adjacent Planning Coordinators and Transmission Planners to ensure that Contingencies on adjacent Systems which may impact their Systems are included in the Contingency list.
3.5. Those extreme events in Table 1 that are expected to produce more severe System impacts shall be identified and a list created of those events to be evaluated in Requirement R3, Part 3.2. The rationale for those Contingencies selected for evaluation shall be available as supporting information. If the analysis concludes there is Cascading caused by the occurrence of extreme events, an evaluation of possible actions designed to reduce the likelihood or mitigate the consequences and adverse impacts of the event(s) shall be conducted.
R4. For the Stability portion of the Planning Assessment, as described in Requirement R2, Parts 2.4 and 2.5, each Transmission Planner and Planning Coordinator shall perform the Contingency analyses listed in Table 1. The studies shall be based on computer simulation models using data provided in Requirement R1. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
4.1. Studies shall be performed for planning events to determine whether the BES meets the performance requirements in Table 1 based on the Contingency list created in Requirement R4, Part 4.4.
4.1.1. For planning event P1: No generating unit shall pull out of synchronism. A generator being disconnected from the System by fault clearing action or by a Special Protection System is not considered pulling out of synchronism.
4.1.2. For planning events P2 through P7: When a generator pulls out of synchronism in the simulations, the resulting apparent impedance swings shall not result in the tripping of any Transmission system elements other than the generating unit and its directly connected Facilities.
4.1.3. For planning events P1 through P7: Power oscillations shall exhibit acceptable damping as established by the Planning Coordinator and Transmission Planner.
4.2. Studies shall be performed to assess the impact of the extreme events which are identified by the list created in Requirement R4, Part 4.5.
4.3. Contingency analyses for Requirement R4, Parts 4.1 and 4.2 shall :
4.3.1. Simulate the removal of all elements that the Protection System and other automatic controls are expected to disconnect for each Contingency without operator intervention. The analyses shall include the impact of subsequent:
4.3.1.1. Successful high speed (less than one second) reclosing and unsuccessful high speed reclosing into a Fault where high speed reclosing is utilized.
4.3.1.2. Tripping of generators where simulations show generator bus voltages or high side of the GSU voltages are less than known or assumed generator low voltage ride through capability. Include in the assessment any assumptions made.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
7
4.3.1.3. Tripping of Transmission lines and transformers where transient swings cause Protection System operation based on generic or actual relay models.
4.3.2. Simulate the expected automatic operation of existing and planned devices designed to provide dynamic control of electrical system quantities when such devices impact the study area. These devices may include equipment such as generation exciter control and power system stabilizers, static var compensators, power flow controllers, and DC Transmission controllers.
4.4. Those planning events in Table 1 that are expected to produce more severe System impacts on its portion of the BES, shall be identified, and a list created of those Contingencies to be evaluated in Requirement R4, Part 4.1. The rationale for those Contingencies selected for evaluation shall be available as supporting information.
4.4.1. Each Planning Coordinator and Transmission Planner shall coordinate with adjacent Planning Coordinators and Transmission Planners to ensure that Contingencies on adjacent Systems which may impact their Systems are included in the Contingency list.
4.5. Those extreme events in Table 1 that are expected to produce more severe System impacts shall be identified and a list created of those events to be evaluated in Requirement R4, Part 4.2. The rationale for those Contingencies selected for evaluation shall be available as supporting information. If the analysis concludes there is Cascading caused by the occurrence of extreme events, an evaluation of possible actions designed to reduce the likelihood or mitigate the consequences of the event(s) shall be conducted.
R5. Each Transmission Planner and Planning Coordinator shall have criteria for acceptable System steady state voltage limits, post-Contingency voltage deviations, and the transient voltage response for its System. For transient voltage response, the criteria shall at a minimum, specify a low voltage level and a maximum length of time that transient voltages may remain below that level. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
R6. Each Transmission Planner and Planning Coordinator shall define and document, within their Planning Assessment, the criteria or methodology used in the analysis to identify System instability for conditions such as Cascading, voltage instability, or uncontrolled islanding. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
R7. Each Planning Coordinator, in conjunction with each of its Transmission Planners, shall determine and identify each entity’s individual and joint responsibilities for performing the required studies for the Planning Assessment. [Violation Risk Factor: Low] [Time Horizon: Long-term Planning]
R8. Each Planning Coordinator and Transmission Planner shall distribute its Planning Assessment results to adjacent Planning Coordinators and adjacent Transmission Planners within 90 calendar days of completing its Planning Assessment, and to any functional entity that has a reliability related need and submits a written request for the information within 30 days of such a request. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
8.1. If a recipient of the Planning Assessment results provides documented comments on the results, the respective Planning Coordinator or Transmission Planner shall provide a documented response to that recipient within 90 calendar days of receipt of those comments.
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
8
Tabl
e 1
– St
eady
Sta
te &
Sta
bilit
y Pe
rfor
man
ce P
lann
ing
Even
ts
Stea
dy S
tate
& S
tabi
lity:
a
. T
he
Syste
m s
ha
ll re
ma
in s
tab
le.
Ca
sca
din
g a
nd u
nco
ntr
olle
d isla
ndin
g s
ha
ll n
ot o
ccu
r.
b.
Co
nse
qu
en
tia
l L
oad
Loss a
s w
ell
as g
en
era
tion
loss is a
cce
pta
ble
as a
co
nse
qu
en
ce
of a
ny e
ve
nt
exclu
din
g P
0.
c.
Sim
ula
te th
e r
em
ova
l o
f a
ll e
lem
en
ts t
ha
t P
rote
ctio
n S
yste
ms a
nd
oth
er
co
ntr
ols
are
exp
ecte
d t
o a
uto
ma
tically
dis
co
nne
ct fo
r e
ach
eve
nt.
d.
Sim
ula
te N
orm
al C
lea
rin
g u
nle
ss o
the
rwis
e s
pecifie
d.
e.
Pla
nn
ed
Syste
m a
dju
stm
en
ts s
uch
as T
ran
sm
issio
n c
on
fig
ura
tio
n c
ha
ng
es a
nd
re
-dis
pa
tch o
f g
en
era
tio
n a
re a
llow
ed
if
such
ad
justm
en
ts a
re e
xe
cu
tab
le w
ith
in t
he
tim
e
du
ratio
n a
pp
licab
le to
th
e F
acili
ty R
atin
gs.
Ste
ady
Stat
e O
nly:
f.
Ap
plic
able
Fa
cili
ty R
atin
gs s
hall
not
be
exce
ed
ed
.
g.
Syste
m s
tead
y s
tate
vo
ltag
es a
nd
po
st-
Con
ting
ency v
olta
ge
de
via
tion
s s
hall
be
with
in a
ccep
tab
le lim
its a
s e
sta
blis
hed
by th
e P
lan
nin
g C
oo
rdin
ato
r a
nd
th
e T
ran
sm
issio
n
Pla
nn
er.
h.
Pla
nn
ing
eve
nt
P0
is a
pplic
ab
le t
o s
tead
y s
tate
only
.
i.
Th
e re
sp
onse
of
vo
lta
ge
se
nsitiv
e L
oad
th
at
is d
isco
nne
cte
d fro
m th
e S
yste
m b
y e
nd
-use
r e
qu
ipm
en
t associa
ted
with
an
eve
nt
sha
ll n
ot b
e u
sed
to
me
et
ste
ad
y s
tate
p
erf
orm
ance
req
uire
men
ts.
Stab
ility
Onl
y:
j.
Tra
nsie
nt vo
lta
ge
resp
onse
sha
ll be
with
in a
cce
pta
ble
lim
its e
sta
blis
hed
by t
he P
lann
ing
Co
ord
ina
tor
an
d th
e T
ransm
issio
n P
lan
ne
r.
Cat
egor
y In
itial
Con
ditio
n Ev
ent 1
Fa
ult T
ype
2 B
ES L
evel
3 In
terr
uptio
n of
Firm
Tr
ansm
issi
on
Serv
ice
Allo
wed
4 N
on-C
onse
quen
tial
Load
Los
s A
llow
ed
P0
No
Co
nting
ency
No
rma
l S
yste
m
No
ne
N/A
E
HV
, H
V
No
N
o
P1
Sin
gle
C
on
tin
ge
ncy
No
rma
l S
yste
m
Lo
ss o
f o
ne
of
the
follo
win
g:
1.
Ge
ne
rato
r
2.
Tra
nsm
issio
n C
ircuit
3.
Tra
nsfo
rme
r 5
4.
Sh
un
t D
evic
e 6
3Ø
E
HV
, H
V
No
9
No
12
5.
Sin
gle
Po
le o
f a
DC
lin
e
SL
G
P2
Sin
gle
C
on
tin
ge
ncy
No
rma
l S
yste
m
1.
Op
en
ing o
f a
lin
e s
ection
w/o
a f
ault 7
N
/A
EH
V,
HV
N
o9
No
12
2.
Bu
s S
ection
Fau
lt
SL
G
EH
V
No
9
No
HV
Y
es
Ye
s
3.
Inte
rnal B
rea
ke
r F
ault 8
(no
n-B
us-t
ie B
reake
r)
SL
G
EH
V
No
9
No
HV
Y
es
Ye
s
4.
Inte
rnal B
rea
ke
r F
ault (
Bus-t
ie B
rea
ke
r) 8
S
LG
E
HV
, H
V
Ye
s
Ye
s
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
9
Cat
egor
y In
itial
Con
ditio
n
Even
t 1 Fa
ult T
ype
2 B
ES L
evel
3 In
terr
uptio
n of
Firm
Tr
ansm
issi
on
Serv
ice
Allo
wed
4 N
on-C
onse
quen
tial
Load
Los
s A
llow
ed
P3
Mu
ltip
le
Co
ntin
ge
ncy
Lo
ss o
f g
en
era
tor
un
it
follo
we
d b
y S
yste
m
ad
justm
en
ts9
Lo
ss o
f o
ne
of
the
follo
win
g:
1.
Ge
ne
rato
r
2.
Tra
nsm
issio
n C
ircuit
3.
Tra
nsfo
rme
r 5
4.
Sh
un
t D
evic
e 6
3Ø
E
HV
, H
V
No
9
No
12
5.
Sin
gle
po
le o
f a
DC
lin
e
SL
G
P4
Mu
ltip
le
Co
ntin
ge
ncy
(Fau
lt pl
us s
tuck
br
eake
r10)
No
rma
l S
yste
m
Lo
ss o
f m
ultip
le e
lem
en
ts c
ause
d b
y a
stu
ck
bre
ake
r 1
0(n
on
-Bus-t
ie B
reake
r) a
ttem
ptin
g to
cle
ar
a F
au
lt o
n o
ne
of
the
fo
llow
ing
:
1.
Ge
ne
rato
r
2.
Tra
nsm
issio
n C
ircuit
3.
Tra
nsfo
rme
r 5
4.
Sh
un
t D
evic
e 6
5.
Bu
s S
ection
SL
G
EH
V
No
9
No
HV
Y
es
Ye
s
6.
Lo
ss o
f m
ultip
le e
lem
en
ts c
ause
d b
y a
stu
ck b
rea
ke
r10 (
Bu
s-t
ie B
rea
ke
r)
att
em
pting
to c
lea
r a F
ault o
n th
e
asso
cia
ted b
us
SL
G
EH
V,
HV
Y
es
Ye
s
P5
Mu
ltip
le
Co
ntin
ge
ncy
(Fau
lt pl
us re
lay
failu
re to
op
erat
e)
No
rma
l S
yste
m
De
laye
d F
au
lt C
lea
rin
g d
ue
to
th
e f
ailu
re o
f a
n
on
-re
du
nda
nt
rela
y1
3 p
rote
ctin
g t
he F
aulte
d
ele
me
nt
to o
pe
rate
as d
esig
ned
, fo
r o
ne
of
the
follo
win
g:
1.
Ge
ne
rato
r
2.
Tra
nsm
issio
n C
ircuit
3.
Tra
nsfo
rme
r 5
4.
Sh
un
t D
evic
e 6
5.
Bu
s S
ection
SL
G
EH
V
No
9
No
HV
Y
es
Ye
s
P6
Mu
ltip
le
Co
ntin
ge
ncy
(Tw
o ov
erla
ppin
g si
ngle
s)
Lo
ss o
f o
ne
of
the
fo
llow
ing
fo
llow
ed
by
Syste
m a
dju
stm
en
ts.9
1.
Tra
nsm
issio
n C
ircuit
2.
Tra
nsfo
rme
r 5
3.
Sh
un
t D
evic
e6
4.
Sin
gle
pole
of a
DC
lin
e
Lo
ss o
f o
ne
of
the
follo
win
g:
1.
Tra
nsm
issio
n C
ircuit
2.
Tra
nsfo
rme
r 5
3.
Sh
un
t D
evic
e 6
3Ø
E
HV
, H
V
Ye
s
Ye
s
4.
Sin
gle
po
le o
f a
DC
lin
e
SL
G
EH
V,
HV
Y
es
Ye
s
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
10
Cat
egor
y In
itial
Con
ditio
n
Even
t 1 Fa
ult T
ype
2 B
ES L
evel
3 In
terr
uptio
n of
Firm
Tr
ansm
issi
on
Serv
ice
Allo
wed
4 N
on-C
onse
quen
tial
Load
Los
s A
llow
ed
P7
Mu
ltip
le
Co
ntin
ge
ncy
(Com
mon
S
truct
ure)
No
rma
l S
yste
m
Th
e lo
ss o
f:
1. A
ny t
wo
ad
jacen
t (v
ert
ica
lly o
r h
ori
zo
nta
lly)
cir
cuits o
n c
om
mo
n
str
uctu
re 1
1
2. L
oss o
f a
bip
ola
r D
C lin
e
SL
G
EH
V,
HV
Y
es
Ye
s
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
11
Ta
ble
1 –
Stea
dy S
tate
& S
tabi
lity
Perf
orm
ance
Ext
rem
e Ev
ents
Stea
dy S
tate
& S
tabi
lity
For
all
extr
em
e e
ve
nts
evalu
ate
d:
a.
Sim
ula
te t
he r
em
oval of
all
ele
ments
that
Pro
tectio
n S
yste
ms a
nd a
uto
matic c
ontr
ols
are
expecte
d to d
iscon
nect fo
r each C
on
tinge
ncy.
b.
Sim
ula
te N
orm
al C
learing
unle
ss o
therw
ise
specifie
d.
Stea
dy S
tate
1.
Loss o
f a s
ing
le g
en
era
tor,
Tra
nsm
issio
n C
ircu
it, sin
gle
pole
of
a D
C
Lin
e, shu
nt d
evic
e, or
transfo
rmer
forc
ed o
ut of
serv
ice
follo
wed b
y
anoth
er
sin
gle
ge
nera
tor,
Tra
nsm
issio
n C
ircu
it, sin
gle
pole
of
a
diffe
rent D
C L
ine
, shun
t de
vic
e,
or
transfo
rmer
forc
ed o
ut of
serv
ice
prior
to S
yste
m a
dju
stm
ents
.
2.
Local are
a e
vents
aff
ecting t
he T
ransm
issio
n S
yste
m s
uch a
s:
a.
Loss o
f a to
wer
line w
ith
thre
e o
r m
ore
circuits.1
1
b.
Loss o
f all
Tra
nsm
issio
n lin
es o
n a
com
mon R
ight-
of-
Way
11.
c.
Loss o
f a s
witchin
g s
tatio
n o
r substa
tion (
loss o
f one v
olta
ge
level plu
s tra
nsfo
rmers
).
d.
Loss o
f all
gen
era
ting u
nits a
t a g
en
era
ting s
tatio
n.
e.
Loss o
f a larg
e L
oad o
r m
ajo
r Loa
d c
ente
r.
3.
Wid
e a
rea e
ve
nts
aff
ecting t
he T
ransm
issio
n S
yste
m b
ased o
n
Syste
m topo
log
y s
uch a
s:
a.
Loss o
f tw
o g
enera
tin
g s
tations r
esultin
g f
rom
conditio
ns s
uch
as:
i.
Loss o
f a larg
e g
as p
ipelin
e into
a r
egio
n o
r m
ultip
le
regio
ns that
ha
ve
sig
nific
an
t gas-f
ired g
enera
tio
n.
ii.
Loss o
f th
e u
se o
f a larg
e b
od
y o
f w
ate
r as t
he c
oolin
g
sourc
e f
or
genera
tio
n.
iii.
Wild
fire
s.
iv.
Se
vere
weath
er,
e.g
., h
urr
icanes, to
rnado
es, etc
.
v.
A s
uccessfu
l cyber
att
ack.
vi.
Shutd
ow
n o
f a n
ucle
ar
po
wer
pla
nt(
s)
and
rela
ted
facili
ties f
or
a d
ay o
r m
ore
for
com
mon c
auses s
uch
as p
roble
ms w
ith s
imila
rly d
esig
ned p
lants
.
b.
Oth
er
events
based
up
on o
pera
ting e
xperi
ence t
hat m
ay
result in w
ide
are
a d
istu
rba
nces.
Stab
ility
1.
With a
n initia
l cond
itio
n o
f a
sin
gle
genera
tor,
Tra
nsm
issio
n c
ircu
it,
sin
gle
pole
of
a D
C lin
e, sh
unt d
evic
e,
or
transfo
rmer
forc
ed o
ut
of
serv
ice,
app
ly a
3Ø
fault o
n a
noth
er
sin
gle
genera
tor,
Tra
nsm
issio
n
circuit, sin
gle
pole
of
a d
iffe
rent D
C lin
e, sh
unt
de
vic
e,
or
transfo
rmer
prior
to S
yste
m a
dju
stm
ents
.
2.
Local or
wid
e a
rea e
vents
aff
ecting th
e T
ransm
issio
n S
yste
m s
uch a
s:
a.
3Ø
fault o
n g
enera
tor
with s
tuck b
reaker1
0 o
r a r
ela
y f
ailu
re1
3
resultin
g in D
ela
ye
d F
ault C
leari
ng
.
b.
3Ø
fault o
n T
ransm
issio
n c
ircuit w
ith s
tuck b
reaker1
0 o
r a r
ela
y
failu
re1
3 r
esultin
g in
De
laye
d F
au
lt C
leari
ng.
c.
3Ø
fault o
n tra
nsfo
rmer
with s
tuck b
reaker1
0 o
r a r
ela
y f
ailu
re1
3
resultin
g in D
ela
ye
d F
ault C
leari
ng
.
d.
3Ø
fault o
n b
us s
ection
with s
tuck b
reaker1
0 o
r a r
ela
y f
ailu
re1
3
resultin
g in D
ela
ye
d F
ault C
leari
ng
.
e.
3Ø
inte
rna
l bre
aker
fault.
f.
Oth
er
events
based
up
on o
pera
ting e
xperi
ence, such
as
consid
era
tio
n o
f in
itia
ting e
ven
ts that
experi
ence s
ugg
ests
ma
y
result in w
ide
are
a d
istu
rba
nces
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
12
Tabl
e 1
– St
eady
Sta
te &
Sta
bilit
y Pe
rfor
man
ce F
ootn
otes
(P
lann
ing
Even
ts a
nd E
xtre
me
Even
ts)
1.
If the e
vent
an
aly
ze
d in
vo
lves B
ES
ele
ments
at m
ultip
le S
yste
m v
oltage le
ve
ls, th
e lo
west S
yste
m v
oltag
e le
ve
l of
the e
lem
ent(
s)
rem
oved f
or
the a
na
lyze
d
eve
nt d
ete
rmin
es the s
tate
d p
erf
orm
ance c
rite
ria r
eg
ard
ing a
llow
ances f
or
inte
rru
ptio
ns o
f F
irm
Tra
nsm
issio
n S
erv
ice a
nd N
on-C
onseq
uential Loa
d L
oss.
2.
Unle
ss s
pecifie
d o
therw
ise,
sim
ula
te N
orm
al C
learin
g o
f fa
ults. S
ingle
lin
e to
gro
und (
SLG
) or
thre
e-p
hase (
3Ø
) are
the f
au
lt t
yp
es that
must be e
valu
ate
d in
Sta
bili
ty s
imula
tions f
or
the e
ve
nt d
escribed
. A
3Ø
or
a d
ou
ble
lin
e t
o g
roun
d f
ault s
tud
y in
dic
ating
the
crite
ria a
re b
ein
g m
et is
suff
icie
nt e
vid
ence t
hat
a S
LG
conditio
n w
ould
als
o m
eet th
e c
rite
ria.
3.
Bulk
Ele
ctr
ic S
yste
m (
BE
S)
leve
l re
fere
nces inclu
de e
xtr
a-h
igh v
oltage
(E
HV
) F
acili
ties d
efined a
s g
rea
ter
tha
n 3
00kV
and h
igh v
oltag
e (
HV
) F
acili
ties d
efined
as the 3
00kV
an
d lo
wer
vo
ltage S
yste
ms. T
he d
esig
natio
n o
f E
HV
and H
V is u
se
d to d
istingu
ish b
etw
een s
tate
d p
erf
orm
ance c
rite
ria
allo
wa
nces f
or
inte
rru
ption o
f F
irm
Tra
nsm
issio
n S
erv
ice a
nd N
on-C
on
sequen
tia
l L
oa
d L
oss.
4.
Curt
ailm
ent of
Cond
itio
na
l F
irm
Tra
nsm
issio
n S
erv
ice is a
llow
ed w
hen t
he
cond
itio
ns a
nd/o
r e
ve
nts
be
ing s
tudie
d f
orm
ed the b
asis
for
the C
ond
itio
na
l F
irm
T
ransm
issio
n S
erv
ice.
5.
For
non-g
enera
tor
ste
p u
p t
ransfo
rmer
outa
ge e
ve
nts
, th
e r
efe
rence v
oltag
e, as u
sed in f
ootn
ote
1,
applie
s t
o t
he lo
w-s
ide w
ind
ing
(exclu
din
g tert
iary
w
ind
ings).
F
or
ge
nera
tor
and G
en
era
tor
Ste
p U
p tra
nsfo
rmer
outa
ge e
ven
ts, th
e r
efe
rence v
olta
ge a
pp
lies t
o the
BE
S c
onnecte
d v
olta
ge (
hig
h-s
ide o
f th
e
Genera
tor
Ste
p U
p tra
nsfo
rmer)
. R
equir
em
ents
wh
ich a
re a
pplic
ab
le t
o tra
nsfo
rmers
als
o a
pp
ly t
o v
ari
ab
le f
reque
ncy tra
nsfo
rmers
and p
hase s
hifting
transfo
rmers
.
6.
Requ
irem
ents
wh
ich a
re a
pplic
able
to s
hunt
de
vic
es a
lso a
pp
ly t
o F
AC
TS
de
vic
es that
are
con
necte
d to g
rou
nd.
7.
Openin
g o
ne e
nd
of
a lin
e s
ection
withou
t a f
au
lt o
n a
norm
ally
ne
twork
ed T
ransm
issio
n c
ircuit s
uch th
at th
e lin
e is p
ossib
ly s
erv
ing L
oa
d r
adia
l fr
om
a s
ingle
sourc
e p
oin
t.
8.
An inte
rnal bre
aker
fault m
eans a
bre
aker
faili
ng inte
rnally
, th
us c
reating a
Syste
m fault w
hic
h m
ust be c
leare
d b
y p
rote
ction o
n b
oth
sid
es o
f th
e b
reaker.
9.
An o
bje
ctive o
f th
e p
lannin
g p
rocess s
hou
ld b
e t
o m
inim
ize t
he lik
elih
oo
d a
nd m
agnitude
of
inte
rruption o
f F
irm
Tra
nsm
issio
n S
erv
ice f
ollo
win
g C
onting
ency
eve
nts
. C
urt
ailm
ent of
Firm
Tra
nsm
issio
n S
erv
ice is a
llow
ed b
oth
as a
Syste
m a
dju
stm
ent (a
s id
entified in t
he c
olu
mn e
ntitled
‘In
itia
l C
ond
itio
n’) a
nd
a
corr
ective a
ctio
n w
hen a
chie
ve
d t
hro
ug
h t
he a
ppro
pri
ate
re-d
isp
atc
h o
f re
sourc
es o
blig
ate
d t
o r
e-d
ispatc
h,
wh
ere
it ca
n b
e d
em
onstr
ate
d t
hat
Facili
ties,
inte
rnal an
d e
xte
rnal to
the T
ransm
issio
n P
lan
ner’s p
lannin
g r
egio
n, re
main
with
in a
pp
licab
le F
acili
ty R
atin
gs a
nd t
he r
e-d
ispatc
h d
oes n
ot re
sult in
an
y N
on-
Conseq
uentia
l L
oad
Loss. W
here
lim
ited o
ptio
ns f
or
re-d
ispatc
h e
xis
t, s
ensitiv
itie
s a
ssocia
ted w
ith t
he a
va
ilab
ility
of
those r
eso
urc
es s
ho
uld
be c
onsid
ere
d.
10.
A s
tuck b
reaker
means that fo
r a g
ang-o
pera
ted b
reaker,
all
thre
e p
hases o
f th
e b
reaker
have r
em
ain
ed c
losed. F
or
an ind
epe
nde
nt p
ole
op
era
ted (
IPO
) or
an inde
pen
de
nt p
ole
trip
pin
g (
IPT
) bre
aker,
only
on
e p
ole
is a
ssum
ed to r
em
ain
clo
sed. A
stu
ck b
reaker
results in
De
layed F
au
lt C
leari
ng.
11.
Exclu
des c
ircuits th
at share
a c
om
mon s
tructu
re (
Pla
nnin
g e
ven
t P
7,
Extr
em
e e
vent ste
ad
y s
tate
2a)
or
com
mon R
ight-
of-
Wa
y (
Extr
em
e e
vent,
ste
ad
y s
tate
2b)
for
1 m
ile o
r le
ss.
12.
An o
bje
ctive o
f th
e p
lan
nin
g p
rocess is to m
inim
ize t
he lik
elih
ood a
nd m
agnitud
e o
f N
on-C
onse
que
ntial Loa
d L
oss f
ollo
win
g p
lan
nin
g e
vents
. In
lim
ited
circum
sta
nces,
Non-C
onse
quen
tia
l L
oad
Loss m
ay b
e n
eed
ed t
hro
ugho
ut th
e p
lan
nin
g h
ori
zon t
o e
nsure
th
at
BE
S p
erf
orm
ance r
equirem
ents
are
met.
H
ow
ever,
when
Non-C
onse
quen
tia
l L
oad
Loss is u
tiliz
ed u
nder
footn
ote
12 w
ith
in t
he N
ear-
Term
Tra
nsm
issio
n P
lan
nin
g H
ori
zon t
o a
ddre
ss B
ES
perf
orm
ance r
equirem
ents
, such inte
rruption is lim
ited t
o c
ircum
sta
nces w
here
the
Non-C
onsequ
entia
l Lo
ad L
oss m
eets
the c
on
ditio
ns s
ho
wn in A
ttachm
ent
1. In n
o c
ase
can t
he p
lan
ned N
on-C
onsequ
entia
l L
oad L
oss u
nder
footn
ote
12
exceed 7
5 M
W for
US
regis
tere
d e
ntities.
The a
mount
of
pla
nned N
on-
Conseq
uentia
l L
oad
Loss f
or
a n
on-U
S R
eg
iste
red E
ntity
shou
ld b
e im
ple
mente
d in a
manner
that
is c
onsis
tent
with,
or
und
er
the d
irection o
f, th
e a
pplic
ab
le
govern
menta
l a
uth
ority
or
its a
gency in th
e n
on-U
S juri
sdic
tio
n.
13.
App
lies to t
he f
ollo
win
g r
ela
y f
unctio
ns o
r ty
pes:
pilo
t (#
85),
dis
tance (
#21),
diffe
rentia
l (#
87),
curr
ent (#
50,
51,
and 6
7),
voltag
e (
#2
7 &
59),
direction
al (#
32,
&
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
13
Tabl
e 1
– St
eady
Sta
te &
Sta
bilit
y Pe
rfor
man
ce F
ootn
otes
(P
lann
ing
Even
ts a
nd E
xtre
me
Even
ts)
67),
an
d tri
pp
ing (
#86,
& 9
4).
Standard TPL-001-4 — Transmission System Planning Performance Requirements
Attachment 1
I. Stakeholder Process
During each Planning Assessment before the use of Non-Consequential Load Loss under footnote 12 is allowed as an element of a Corrective Action Plan in the Near-Term Transmission Planning Horizon of the Planning Assessment, the Transmission Planner or Planning Coordinator shall ensure that the utilization of footnote 12 is reviewed through an open and transparent stakeholder process. The responsible entity can utilize an existing process or develop a new process. .The process must include the following:
1. Meetings must be open to affected stakeholders including applicable regulatory authorities or governing bodies responsible for retail electric service issues
2. Notice must be provided in advance of meetings to affected stakeholders including applicable regulatory authorities or governing bodies responsible for retail electric service issues and include an agenda with:
a. Date, time, and location for the meeting b. Specific location(s) of the planned Non-Consequential Load Loss under footnote
12 c. Provisions for a stakeholder comment period
3. Information regarding the intended purpose and scope of the proposed Non-Consequential Load Loss under footnote 12 (as shown in Section II below) must be made available to meeting participants
4. A procedure for stakeholders to submit written questions or concerns and to receive written responses to the submitted questions and concerns
5. A dispute resolution process for any question or concern raised in #4 above that is not resolved to the stakeholder’s satisfaction
An entity does not have to repeat the stakeholder process for a specific application of footnote 12 utilization with respect to subsequent Planning Assessments unless conditions spelled out in Section II below have materially changed for that specific application.
II. Information for Inclusion in Item #3 of the Stakeholder Process
The responsible entity shall document the planned use of Non-Consequential Load Loss under footnote 12 which must include the following:
1. Conditions under which Non-Consequential Load Loss under footnote 12 would be necessary:
a. System Load level and estimated annual hours of exposure at or above that Load level
b. Applicable Contingencies and the Facilities outside their applicable rating due to that Contingency
2. Amount of Non-Consequential Load Loss with: a. The estimated number and type of customers affected
Standard TPL-001-4 — Transmission System Planning Performance Requirements
b. An explanation of the effect of the use of Non-Consequential Load Loss under footnote 12 on the health, safety, and welfare of the community
3. Estimated frequency of Non-Consequential Load Loss under footnote 12 based on historical performance
4. Expected duration of Non-Consequential Load Loss under footnote 12 based on historical performance
5. Future plans to alleviate the need for Non-Consequential Load Loss under footnote 12 6. Verification that TPL Reliability Standards performance requirements will be met
following the application of footnote 12 7. Alternatives to Non-Consequential Load Loss considered and the rationale for not
selecting those alternatives under footnote 12 8. Assessment of potential overlapping uses of footnote 12 including overlaps with adjacent
Transmission Planners and Planning Coordinators
III. Instances for which Regulatory Review of Non-Consequential Load Loss under Footnote 12 is Required
Before a Non-Consequential Load Loss under footnote 12 is allowed as an element of a Corrective Action Plan in Year One of the Planning Assessment, the Transmission Planner or Planning Coordinator must ensure that the applicable regulatory authorities or governing bodies responsible for retail electric service issues do not object to the use of Non-Consequential Load Loss under footnote 12 if either:
1. The voltage level of the Contingency is greater than 300 kV a. If the Contingency analyzed involves BES Elements at multiple System voltage
levels, the lowest System voltage level of the element(s) removed for the analyzed Contingency determines the stated performance criteria regarding allowances for Non-Consequential Load Loss under footnote 12, or
b. For a non-generator step up transformer outage Contingency, the 300 kV limit applies to the low-side winding (excluding tertiary windings). For a generator or generator step up transformer outage Contingency, the 300 kV limit applies to the BES connected voltage (high-side of the Generator Step Up transformer)
2. The planned Non-Consequential Load Loss under footnote 12 is greater than or equal to 25 MW
Once assurance has been received that the applicable regulatory authorities or governing bodies responsible for retail electric service issues do not object to the use of Non-Consequential Load Loss under footnote 12, the Planning Coordinator or Transmission Planner must submit the information outlined in items II.1 through II.8 above to the ERO for a determination of whether there are any Adverse Reliability Impacts caused by the request to utilize footnote 12 for Non-Consequential Load Loss.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
C. Measures M1. Each Transmission Planner and Planning Coordinator shall provide evidence, in electronic or
hard copy format, that it is maintaining System models within their respective area, using data consistent with MOD-010 and MOD-012, including items represented in the Corrective Action Plan, representing projected System conditions, and that the models represent the required information in accordance with Requirement R1.
M2. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as electronic or hard copies of its annual Planning Assessment, that it has prepared an annual Planning Assessment of its portion of the BES in accordance with Requirement R2.
M3. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as electronic or hard copies of the studies utilized in preparing the Planning Assessment, in accordance with Requirement R3.
M4. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as electronic or hard copies of the studies utilized in preparing the Planning Assessment in accordance with Requirement R4.
M5. Each Transmission Planner and Planning Coordinator shall provide dated evidence such as electronic or hard copies of the documentation specifying the criteria for acceptable System steady state voltage limits, post-Contingency voltage deviations, and the transient voltage response for its System in accordance with Requirement R5.
M6. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as electronic or hard copies of documentation specifying the criteria or methodology used in the analysis to identify System instability for conditions such as Cascading, voltage instability, or uncontrolled islanding that was utilized in preparing the Planning Assessment in accordance with Requirement R6.
M7. Each Planning Coordinator, in conjunction with each of its Transmission Planners, shall provide dated documentation on roles and responsibilities, such as meeting minutes, agreements, and e-mail correspondence that identifies that agreement has been reached on individual and joint responsibilities for performing the required studies and Assessments in accordance with Requirement R7.
M8. Each Planning Coordinator and Transmission Planner shall provide evidence, such as email notices, documentation of updated web pages, postal receipts showing recipient and date; or a demonstration of a public posting, that it has distributed its Planning Assessment results to adjacent Planning Coordinators and adjacent Transmission Planners within 90 days of having completed its Planning Assessment, and to any functional entity who has indicated a reliability need within 30 days of a written request and that the Planning Coordinator or Transmission Planner has provided a documented response to comments received on Planning Assessment results within 90 calendar days of receipt of those comments in accordance with Requirement R8.
D. Compliance 1. Compliance Monitoring Process
1.1 Compliance Enforcement Authority Regional Entity
1.2 Compliance Monitoring Period and Reset Timeframe Not applicable.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
1.3 Compliance Monitoring and Enforcement Processes: Compliance Audits
Self-Certifications
Spot Checking
Compliance Violation Investigations
Self-Reporting
Complaints
1.4 Data Retention The Transmission Planner and Planning Coordinator shall each retain data or evidence to show compliance as identified unless directed by its Compliance Enforcement Authority to retain specific evidence for a longer period of time as part of an investigation:
• The models utilized in the current in-force Planning Assessment and one previous Planning Assessment in accordance with Requirement R1 and Measure M1.
• The Planning Assessments performed since the last compliance audit in accordance with Requirement R2 and Measure M2.
• The studies performed in support of its Planning Assessments since the last compliance audit in accordance with Requirement R3 and Measure M3.
• The studies performed in support of its Planning Assessments since the last compliance audit in accordance with Requirement R4 and Measure M4.
• The documentation specifying the criteria for acceptable System steady state
voltage limits, post-Contingency voltage deviations, and transient voltage
response since the last compliance audit in accordance with Requirement R5 and Measure M5.
• The documentation specifying the criteria or methodology utilized in the analysis to identify System instability for conditions such as Cascading, voltage instability, or uncontrolled islanding in support of its Planning Assessments since the last compliance audit in accordance with Requirement R6 and Measure M6.
• The current, in force documentation for the agreement(s) on roles and responsibilities, as well as documentation for the agreements in force since the last compliance audit, in accordance with Requirement R7 and Measure M7.
The Planning Coordinator shall retain data or evidence to show compliance as identified unless directed by its Compliance Enforcement Authority to retain specific evidence for a longer period of time as part of an investigation:
• Three calendar years of the notifications employed in accordance with Requirement R8 and Measure M8.
If a Transmission Planner or Planning Coordinator is found non-compliant, it shall keep information related to the non-compliance until found compliant or the time periods specified above, whichever is longer.
1.5 Additional Compliance Information None
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
18
2. V
iola
tion
Seve
rity
Leve
ls
Lo
wer
VSL
M
oder
ate
VSL
Hig
h VS
L Se
vere
VSL
R1
The r
esponsib
le e
ntity
’s S
yste
m
model fa
iled
to r
epre
sent
one o
f th
e
Requ
irem
ent R
1,
Part
s 1
.1.1
th
roug
h 1
.1.6
.
The r
esponsib
le e
ntity
’s S
yste
m
model fa
iled
to r
epre
sent
two o
f th
e
Requ
irem
ent R
1,
Part
s 1
.1.1
thro
ugh
1.1
.6.
The r
esponsib
le e
ntity
’s S
yste
m
model fa
iled
to r
epre
sent
thre
e o
f th
e
Requ
irem
ent R
1,
Part
s 1
.1.1
thro
ugh
1.1
.6.
The r
esponsib
le e
ntity
’s S
yste
m m
odel
faile
d t
o r
epre
sent fo
ur
or
more
of
the
Requ
irem
ent R
1,
Part
s 1
.1.1
thro
ugh
1.1
.6.
OR
The r
esponsib
le e
ntity
’s S
yste
m m
odel
did
not re
pre
sent
pro
jecte
d S
yste
m
conditio
ns a
s d
escrib
ed in R
equ
irem
ent
R1.
OR
The r
esponsib
le e
ntity
’s S
yste
m m
odel
did
not
use d
ata
co
nsis
tent
with t
hat
pro
vid
ed in a
ccord
ance w
ith the
MO
D-
010 a
nd M
OD
-01
2 s
tan
dard
s a
nd o
ther
sourc
es, in
clu
din
g ite
ms r
epre
sente
d in
the C
orr
ective A
ctio
n P
lan
.
R2
The r
esponsib
le e
ntity
fa
iled to
com
ply
with R
eq
uirem
ent R
2, P
art
2.6
.
The r
esponsib
le e
ntity
fa
iled to
com
ply
with R
eq
uirem
ent R
2, P
art
2.3
or
Part
2.8
.
The r
esponsib
le e
ntity
fa
iled to
com
ply
with o
ne o
f th
e f
ollo
win
g
Part
s o
f R
eq
uirem
ent R
2:
Part
2.1
, P
art
2.2
, P
art
2.4
, P
art
2.5
, or
Part
2.7
.
The r
esponsib
le e
ntity
fa
iled to c
om
ply
w
ith t
wo o
r m
ore
of
the f
ollo
win
g P
art
s
of
Requir
em
ent R
2:
Part
2.1
, P
art
2.2
, P
art
2.4
, or
Part
2.7
.
OR
The r
esponsib
le e
ntity
do
es n
ot
ha
ve a
com
ple
ted a
nnua
l P
lann
ing
A
ssessm
ent.
R3
The r
esponsib
le e
ntity
did
not
ide
ntify
pla
nn
ing e
vents
as
described
in
Req
uirem
ent
R3, P
art
3.4
or
extr
em
e e
vents
as d
escribed
in R
equ
irem
ent R
3,
Part
3.5
.
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
eq
uirem
ent
R3, P
art
3.1
to
dete
rmin
e t
hat th
e
BE
S m
eets
the p
erf
orm
ance
requirem
ents
for
one o
f th
e c
ate
gori
es
(P2 thro
ugh
P7)
in T
able
1.
The r
esponsib
le e
ntity
did
not
perf
orm
stu
die
s a
s s
pecifie
d in
R
equ
irem
ent
R3,
Part
3.1
to
dete
rmin
e th
at th
e B
ES
meets
the
perf
orm
ance r
equirem
ents
for
two o
f th
e c
ate
gori
es (
P2
thro
ugh P
7)
in
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
eq
uirem
ent
R3,
Part
3.1
to d
ete
rmin
e that
the B
ES
m
eets
the p
erf
orm
ance r
eq
uirem
ents
fo
r th
ree o
r m
ore
of
the c
ate
gori
es (
P2
thro
ug
h P
7)
in T
able
1.
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
19
Lo
wer
VSL
M
oder
ate
VSL
Hig
h VS
L Se
vere
VSL
OR
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
eq
uirem
ent
R3, P
art
3.2
to
assess the im
pact of
extr
em
e e
vents
.
Table
1.
OR
The r
esponsib
le e
ntity
did
not
perf
orm
Contin
gency a
naly
sis
as
described
in
Req
uirem
ent
R3, P
art
3.3
.
OR
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s t
o d
ete
rmin
e tha
t th
e B
ES
m
eets
the p
erf
orm
ance r
eq
uirem
ents
fo
r th
e P
0 o
r P
1 c
ate
gori
es in T
able
1.
OR
The r
esponsib
le e
ntity
did
not base
its
stu
die
s o
n c
om
pute
r sim
ula
tion
models
usin
g d
ata
pro
vid
ed
in
Req
uirem
ent R
1.
R4
The r
esponsib
le e
ntity
did
not
ide
ntify
pla
nn
ing e
vents
as
described
in
Req
uirem
ent
R4, P
art
4.4
or
extr
em
e e
vents
as d
escribed
in R
equ
irem
ent R
4,
Part
4.5
.
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
eq
uirem
ent
R4, P
art
4.1
to
dete
rmin
e that th
e
BE
S m
eets
the p
erf
orm
ance
requirem
ents
for
one o
f th
e c
ate
gori
es
(P1 thro
ugh
P7)
in T
able
1.
OR
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
eq
uirem
ent
R4, P
art
4.2
to
assess the im
pact of
extr
em
e e
vents
.
The r
esponsib
le e
ntity
did
not
perf
orm
stu
die
s a
s s
pecifie
d in
R
equ
irem
ent
R4,
Part
4.1
to
dete
rmin
e th
at th
e B
ES
meets
the
perf
orm
ance r
equirem
ents
for
two o
f th
e c
ate
gori
es (
P1
thro
ugh P
7)
in
Table
1.
OR
The r
esponsib
le e
ntity
did
not
perf
orm
Contin
gency a
naly
sis
as
described
in
Req
uirem
ent
R4, P
art
4.3
.
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
eq
uirem
ent
R4,
Part
4.1
to d
ete
rmin
e that
the B
ES
m
eets
the p
erf
orm
ance r
eq
uirem
ents
fo
r th
ree o
r m
ore
of
the c
ate
gori
es (
P1
thro
ug
h P
7)
in T
able
1.
OR
The r
esponsib
le e
ntity
did
not base
its
stu
die
s o
n c
om
pute
r sim
ula
tion
models
usin
g d
ata
pro
vid
ed
in
Req
uirem
ent R
1.
R5
N/A
N
/A
N/A
T
he r
esponsib
le e
ntity
do
es n
ot
ha
ve
crite
ria f
or
accepta
ble
Syste
m s
tead
y
sta
te v
oltag
e lim
its, post-
Continge
ncy
vo
ltag
e d
evia
tions,
or
the tra
nsie
nt
vo
ltag
e r
espo
nse f
or
its S
yste
m.
R6
N/A
N
/A
N/A
T
he r
esponsib
le e
ntity
fa
iled to d
efine
and d
ocum
ent th
e c
rite
ria
or
meth
odolo
gy f
or
Syste
m in
sta
bili
ty u
se
d
with
in its
an
aly
sis
as d
escribed in
Requ
irem
ent R
6.
Stan
dard
TPL
-001
-4 —
Tra
nsm
issi
on S
yste
m P
lann
ing
Perf
orm
ance
Req
uire
men
ts
20
Lo
wer
VSL
M
oder
ate
VSL
Hig
h VS
L Se
vere
VSL
R7
N/A
N
/A
N/A
T
he P
lannin
g C
oord
ina
tor,
in
conju
nctio
n w
ith e
ach o
f its
Tra
nsm
issio
n P
lan
ners
, fa
iled to
dete
rmin
e a
nd ide
ntify
ind
ivid
ual or
join
t re
sponsib
ilities f
or
perf
orm
ing r
eq
uire
d
stu
die
s.
R8
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
adja
cent
Pla
nn
ing C
oord
inato
rs a
nd
adja
cent T
ransm
issio
n P
lanners
but
it w
as m
ore
than
90 d
ays b
ut
less
than o
r eq
ua
l to
120
da
ys f
ollo
win
g
its c
om
ple
tio
n.
OR
,
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
functiona
l e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed
who
requ
este
d the
P
lann
ing
Assessm
ent in
wri
ting
but
it w
as m
ore
than
30 d
ays b
ut
less
than o
r eq
ua
l to
40 d
ays f
ollo
win
g
the r
eq
uest.
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
adja
cent
Pla
nn
ing C
oord
inato
rs a
nd
adja
cent T
ransm
issio
n P
lanners
but
it
was m
ore
than 1
20 d
ays b
ut
less than
or
equ
al to
130 d
ays f
ollo
win
g its
com
ple
tion.
OR
,
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
functiona
l e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed
who
requ
este
d the
P
lann
ing
Assessm
ent in
wri
ting
but
it
was m
ore
than 4
0 d
ays b
ut
less tha
n
or
equ
al to
50 d
ays f
ollo
win
g the
re
quest.
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
adja
cent
Pla
nn
ing C
oord
inato
rs a
nd
adja
cent T
ransm
issio
n P
lanners
but
it w
as m
ore
than
13
0 d
ays b
ut
less
than o
r eq
ua
l to
14
0 d
ays f
ollo
win
g
its c
om
ple
tio
n.
OR
,
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
functiona
l e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed
who
requ
este
d the
P
lann
ing
Assessm
ent in
wri
ting
but
it
was m
ore
than 5
0 d
ays b
ut
less tha
n
or
equ
al to
60 d
ays f
ollo
win
g the
re
quest.
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
adja
cent
Pla
nn
ing C
oord
inato
rs a
nd
adja
cent T
ransm
issio
n P
lanners
but
it
was m
ore
than 1
40 d
ays f
ollo
win
g its
com
ple
tion.
OR
The r
esponsib
le e
ntity
did
not d
istr
ibute
its P
lan
nin
g A
ssessm
ent re
sults t
o
adja
cent
Pla
nn
ing C
oord
inato
rs a
nd
adja
cent T
ransm
issio
n P
lanners
.
OR
The r
esponsib
le e
ntity
dis
trib
ute
d its
P
lann
ing
Assessm
ent re
sults t
o
functiona
l e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed
who
requ
este
d the
P
lann
ing
Assessm
ent in
wri
ting
but
it
was m
ore
than 6
0 d
ays f
ollo
win
g th
e
request.
OR
The r
esponsib
le e
ntity
did
not d
istr
ibute
its P
lan
nin
g A
ssessm
ent re
sults t
o
functiona
l e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed
who
requ
este
d the
P
lann
ing
Assessm
ent in
wri
ting
.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
E. Regional Variances None.
Version History
Version Date Action Change Tracking 0 April 1, 2005 Effective Date New
0 February 8, 2005 BOT Approval Revised
0 June 3, 2005 Fixed reference in M1 to read TPL-001-0 R2.1 and TPL-001-0 R2.2
Errata
0 July 24, 2007 Corrected reference in M1. to read TPL-001-0 R1 and TPL-001-0 R2.
Errata
0.1 October 29, 2008 BOT adopted errata changes; updated version number to “0.1”
Errata
0.1 May 13, 2009 FERC Approved – Updated Effective Date and Footer Revised
1 Approved by Board of Trustees February 17, 2011
Revised footnote ‘b’ pursuant to FERC Order RM06-16-009
Revised (Project 2010-11)
2 August 4, 2011 Revision of TPL-001-1; includes merging and upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-004-0 into one, single, comprehensive, coordinated standard: TPL-001-2; and retirement of TPL-005-0 and TPL-006-0.
Project 2006-02 – complete revision
2 August 4, 2011 Adopted by Board of Trustees
1 April 19, 2012 FERC issued Order 762 remanding TPL-001-1, TPL-002-1b, TPL-003-1a, and TPL-004-1. FERC also issued a NOPR proposing to remand TPL-001-2. NERC has been directed to revise footnote 'b' in accordance with the directives of Order Nos. 762 and 693.
3 February 7, 2013 TPL-001-3 was created after the Board of Trustees approved the revised footnote ‘b’ in TPL-002-2b, which was balloted and appended to:
Adopted by the NERC Board of Trustees.
TPL-001-0.1, TPL-002-0b, TPL-003-0a, and TPL-004-0.
4 February 7, 2013 TPL-001-4 was adopted by the Board of Trustees as TPL-001-3, but a discrepancy in numbering was identified and corrected prior to filing with the regulatory agencies.
Adopted by the NERC Board of Trustees.
4 October 17, 2013 FERC Order issued approving TPL-001-4 (Order effective December 23, 2013).
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Appendix A
Reliability Standards Assessed by BC Hydro
Red-lined
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
1
A. Introduction
1. Title: Transmission System Planning Performance RequirementsUnder Normal (No Contingency) Conditions (Category A)
2. Number: TPL-001-40.1
3. Purpose: Establish Transmission system planning performance requirements within the
planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range of probable Contingencies.
3. Purpose: System simulations and associated assessments are needed periodically to ensure
that reliable systems are developed that meet specified performance requirements with
sufficient lead time, and continue to be modified or upgraded as necessary to meet present
and future system needs.
4. Applicability:
4.1. Functional Entity
4.1.4.1.1. Planning Coordinator.Authority
4.2.4.1.2. Transmission Planner.
5. Effective Date: Requirements R1 and R7 as well as the definitions shall become effective on
the first day of the first calendar quarter, 12 months after applicable regulatory approval. In
those jurisdictions where regulatory approval is not required, Requirements R1 and R7 become
effective on the first day of the first calendar quarter, 12 months after Board of Trustees
adoption or as otherwise made effective pursuant to the laws applicable to such ERO
governmental authorities.
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become
effective on the first day of the first calendar quarter, 24 months after applicable regulatory
approval. In those jurisdictions where regulatory approval is not required, all requirements,
except as noted below, go into effect on the first day of the first calendar quarter, 24 months
after Board of Trustees adoption or as otherwise made effective pursuant to the laws
applicable to such ERO governmental authorities.
For 84 calendar months beginning the first day of the first calendar quarter following
applicable regulatory approval, or in those jurisdictions where regulatory approval is not
required on the first day of the first calendar quarter 84 months after Board of Trustees
adoption or as otherwise made effective pursuant to the laws applicable to such ERO
governmental authorities, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of
TPL-001-4:
P1-2 (for controlled interruption of electric supply to local network customers
connected to or supplied by the Faulted element)
P1-3 (for controlled interruption of electric supply to local network customers
connected to or supplied by the Faulted element)
P2-1
P2-2 (above 300 kV)
P2-3 (above 300 kV)
P3-1 through P3-5
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
2
P4-1 through P4-5 (above 300 kV)
P5 (above 300 kV)
B. Requirements
R1. Each Transmission Planner and Planning Coordinator shall maintain System models within its
respective area for performing the studies needed to complete its Planning Assessment. The
models shall use data consistent with that provided in accordance with the MOD-010 and
MOD-012 standards, supplemented by other sources as needed, including items represented in
the Corrective Action Plan, and shall represent projected System conditions. This establishes
Category P0 as the normal System condition in Table 1. [Violation Risk Factor: Medium]
[Time Horizon: Long-term Planning]
1.1. System models shall represent:
1.1.1. Existing Facilities
1.1.2. Known outage(s) of generation or Transmission Facility(ies) with a duration
of at least six months.
1.1.3. New planned Facilities and changes to existing Facilities
1.1.4. Real and reactive Load forecasts
1.1.5. Known commitments for Firm Transmission Service and Interchange
1.1.6. Resources (supply or demand side) required for Load
R2. Each Transmission Planner and Planning Coordinator shall prepare an annual Planning
Assessment of its portion of the BES. This Planning Assessment shall use current or qualified
past studies (as indicated in Requirement R2, Part 2.6), document assumptions, and document
summarized results of the steady state analyses, short circuit analyses, and Stability analyses.
[Violation Risk Factor: High] [Time Horizon: Long-term Planning]
2.1. For the Planning Assessment, the Near-Term Transmission Planning Horizon portion
of the steady state analysis shall be assessed annually and be supported by current
annual studies or qualified past studies as indicated in Requirement R2, Part 2.6.
Qualifying studies need to include the following conditions:
2.1.1. System peak Load for either Year One or year two, and for year five.
2.1.2. System Off-Peak Load for one of the five years.
2.1.3. P1 events in Table 1, with known outages modeled as in Requirement R1,
Part 1.1.2, under those System peak or Off-Peak conditions when known
outages are scheduled.
2.1.4. For each of the studies described in Requirement R2, Parts 2.1.1 and 2.1.2,
sensitivity case(s) shall be utilized to demonstrate the impact of changes to
the basic assumptions used in the model. To accomplish this, the sensitivity
analysis in the Planning Assessment must vary one or more of the following
conditions by a sufficient amount to stress the System within a range of
credible conditions that demonstrate a measurable change in System
response :
Real and reactive forecasted Load.
Expected transfers.
Expected in service dates of new or modified Transmission Facilities.
Reactive resource capability.
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
3
Generation additions, retirements, or other dispatch scenarios.
Controllable Loads and Demand Side Management.
Duration or timing of known Transmission outages.
2.1.5. When an entity’s spare equipment strategy could result in the unavailability
of major Transmission equipment that has a lead time of one year or more
(such as a transformer), the impact of this possible unavailability on System
performance shall be studied. The studies shall be performed for the P0, P1,
and P2 categories identified in Table 1 with the conditions that the System is
expected to experience during the possible unavailability of the long lead
time equipment.
2.2. For the Planning Assessment, the Long-Term Transmission Planning Horizon portion
of the steady state analysis shall be assessed annually and be supported by the
following annual current study, supplemented with qualified past studies as indicated
in Requirement R2, Part 2.6:
2.2.1. A current study assessing expected System peak Load conditions for one of
the years in the Long-Term Transmission Planning Horizon and the rationale
for why that year was selected.
2.3. The short circuit analysis portion of the Planning Assessment shall be conducted
annually addressing the Near-Term Transmission Planning Horizon and can be
supported by current or past studies as qualified in Requirement R2, Part 2.6. The
analysis shall be used to determine whether circuit breakers have interrupting
capability for Faults that they will be expected to interrupt using the System short
circuit model with any planned generation and Transmission Facilities in service
which could impact the study area.
2.4. For the Planning Assessment, the Near-Term Transmission Planning Horizon portion
of the Stability analysis shall be assessed annually and be supported by current or past
studies as qualified in Requirement R2, Part2.6. The following studies are required:
2.4.1. System peak Load for one of the five years. System peak Load levels shall
include a Load model which represents the expected dynamic behavior of
Loads that could impact the study area, considering the behavior of induction
motor Loads. An aggregate System Load model which represents the overall
dynamic behavior of the Load is acceptable.
2.4.2. System Off-Peak Load for one of the five years.
2.4.3. For each of the studies described in Requirement R2, Parts 2.4.1 and 2.4.2,
sensitivity case(s) shall be utilized to demonstrate the impact of changes to
the basic assumptions used in the model. To accomplish this, the sensitivity
analysis in the Planning Assessment must vary one or more of the following
conditions by a sufficient amount to stress the System within a range of
credible conditions that demonstrate a measurable change in performance:
Load level, Load forecast, or dynamic Load model assumptions.
Expected transfers.
Expected in service dates of new or modified Transmission Facilities.
Reactive resource capability.
Generation additions, retirements, or other dispatch scenarios.
2.5. For the Planning Assessment, the Long-Term Transmission Planning Horizon portion
of the Stability analysis shall be assessed to address the impact of proposed material
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
4
generation additions or changes in that timeframe and be supported by current or past
studies as qualified in Requirement R2, Part2.6 and shall include documentation to
support the technical rationale for determining material changes.
2.6. Past studies may be used to support the Planning Assessment if they meet the
following requirements:
2.6.1. For steady state, short circuit, or Stability analysis: the study shall be five
calendar years old or less, unless a technical rationale can be provided to
demonstrate that the results of an older study are still valid.
2.6.2. For steady state, short circuit, or Stability analysis: no material changes have
occurred to the System represented in the study. Documentation to support
the technical rationale for determining material changes shall be included.
2.7. For planning events shown in Table 1, when the analysis indicates an inability of the
System to meet the performance requirements in Table 1, the Planning Assessment
shall include Corrective Action Plan(s) addressing how the performance requirements
will be met. Revisions to the Corrective Action Plan(s) are allowed in subsequent
Planning Assessments but the planned System shall continue to meet the performance
requirements in Table 1. Corrective Action Plan(s) do not need to be developed solely
to meet the performance requirements for a single sensitivity case analyzed in
accordance with Requirements R2, Parts 2.1.4 and 2.4.3. The Corrective Action
Plan(s) shall:
2.7.1. List System deficiencies and the associated actions needed to achieve
required System performance. Examples of such actions include:
Installation, modification, retirement, or removal of Transmission and
generation Facilities and any associated equipment.
Installation, modification, or removal of Protection Systems or Special
Protection Systems
Installation or modification of automatic generation tripping as a response to a single or multiple Contingency to mitigate Stability
performance violations.
Installation or modification of manual and automatic generation
runback/tripping as a response to a single or multiple Contingency to
mitigate steady state performance violations.
Use of Operating Procedures specifying how long they will be needed
as part of the Corrective Action Plan.
Use of rate applications, DSM, new technologies, or other initiatives.
2.7.2. Include actions to resolve performance deficiencies identified in multiple
sensitivity studies or provide a rationale for why actions were not necessary.
2.7.3. If situations arise that are beyond the control of the Transmission
Planner or Planning Coordinator that prevent the implementation of a
Corrective Action Plan in the required timeframe, then the Transmission
Planner or Planning Coordinator is permitted to utilize Non-Consequential
Load Loss and curtailment of Firm Transmission Service to correct the
situation that would normally not be permitted in Table 1, provided that the
Transmission Planner or Planning Coordinator documents that they are
taking actions to resolve the situation. The Transmission Planner or
Planning Coordinator shall document the situation causing the problem,
alternatives evaluated, and the use of Non-Consequential Load Loss or
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
5
curtailment of Firm Transmission Service.
2.7.4. Be reviewed in subsequent annual Planning Assessments for continued
validity and implementation status of identified System Facilities and
Operating Procedures.
2.8. For short circuit analysis, if the short circuit current interrupting duty on circuit
breakers determined in Requirement R2, Part 2.3 exceeds their Equipment Rating, the
Planning Assessment shall include a Corrective Action Plan to address the Equipment
Rating violations. The Corrective Action Plan shall:
2.8.1. List System deficiencies and the associated actions needed to achieve
required System performance.
2.8.2. Be reviewed in subsequent annual Planning Assessments for continued
validity and implementation status of identified System Facilities and
Operating Procedures.
R3. For the steady state portion of the Planning Assessment, each Transmission Planner and
Planning Coordinator shall perform studies for the Near-Term and Long-Term Transmission
Planning Horizons in Requirement R2, Parts 2.1, and 2.2. The studies shall be based on
computer simulation models using data provided in Requirement R1. [Violation Risk Factor:
Medium] [Time Horizon: Long-term Planning]
3.1. Studies shall be performed for planning events to determine whether the BES meets
the performance requirements in Table 1 based on the Contingency list created in
Requirement R3, Part 3.4.
3.2. Studies shall be performed to assess the impact of the extreme events which are
identified by the list created in Requirement R3, Part 3.5.
3.3. Contingency analyses for Requirement R3, Parts 3.1 & 3.2 shall:
3.3.1. Simulate the removal of all elements that the Protection System and other
automatic controls are expected to disconnect for each Contingency without
operator intervention. The analyses shall include the impact of subsequent:
3.3.1.1. Tripping of generators where simulations show generator bus
voltages or high side of the generation step up (GSU) voltages
are less than known or assumed minimum generator steady state
or ride through voltage limitations. Include in the assessment
any assumptions made.
3.3.1.2. Tripping of Transmission elements where relay loadability limits
are exceeded.
3.3.2. Simulate the expected automatic operation of existing and planned devices
designed to provide steady state control of electrical system quantities when
such devices impact the study area. These devices may include equipment
such as phase-shifting transformers, load tap changing transformers, and
switched capacitors and inductors.
3.4. Those planning events in Table 1, that are expected to produce more severe System
impacts on its portion of the BES, shall be identified and a list of those
Contingencies to be evaluated for System performance in Requirement R3, Part 3.1
created. The rationale for those Contingencies selected for evaluation shall be
available as supporting information.
3.4.1. The Planning Coordinator and Transmission Planner shall coordinate with
adjacent Planning Coordinators and Transmission Planners to ensure that
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
6
Contingencies on adjacent Systems which may impact their Systems are
included in the Contingency list.
3.5. Those extreme events in Table 1 that are expected to produce more severe System
impacts shall be identified and a list created of those events to be evaluated in
Requirement R3, Part 3.2. The rationale for those Contingencies selected for
evaluation shall be available as supporting information. If the analysis concludes
there is Cascading caused by the occurrence of extreme events, an evaluation of
possible actions designed to reduce the likelihood or mitigate the consequences and
adverse impacts of the event(s) shall be conducted.
R4. For the Stability portion of the Planning Assessment, as described in Requirement R2, Parts 2.4
and 2.5, each Transmission Planner and Planning Coordinator shall perform the Contingency
analyses listed in Table 1. The studies shall be based on computer simulation models using
data provided in Requirement R1. [Violation Risk Factor: Medium] [Time Horizon: Long-
term Planning]
4.1. Studies shall be performed for planning events to determine whether the BES meets
the performance requirements in Table 1 based on the Contingency list created in
Requirement R4, Part 4.4.
4.1.1. For planning event P1: No generating unit shall pull out of synchronism. A
generator being disconnected from the System by fault clearing action or by
a Special Protection System is not considered pulling out of synchronism.
4.1.2. For planning events P2 through P7: When a generator pulls out of
synchronism in the simulations, the resulting apparent impedance swings
shall not result in the tripping of any Transmission system elements other
than the generating unit and its directly connected Facilities.
4.1.3. For planning events P1 through P7: Power oscillations shall exhibit
acceptable damping as established by the Planning Coordinator and
Transmission Planner.
4.2. Studies shall be performed to assess the impact of the extreme events which are
identified by the list created in Requirement R4, Part 4.5.
4.3. Contingency analyses for Requirement R4, Parts 4.1 and 4.2 shall :
4.3.1. Simulate the removal of all elements that the Protection System and other
automatic controls are expected to disconnect for each Contingency without
operator intervention. The analyses shall include the impact of subsequent:
4.3.1.1. Successful high speed (less than one second) reclosing and
unsuccessful high speed reclosing into a Fault where high speed
reclosing is utilized.
4.3.1.2. Tripping of generators where simulations show generator bus
voltages or high side of the GSU voltages are less than known or
assumed generator low voltage ride through capability. Include
in the assessment any assumptions made.
4.3.1.3. Tripping of Transmission lines and transformers where transient
swings cause Protection System operation based on generic or
actual relay models.
4.3.2. Simulate the expected automatic operation of existing and planned devices
designed to provide dynamic control of electrical system quantities when
such devices impact the study area. These devices may include equipment
such as generation exciter control and power system stabilizers, static var
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
7
compensators, power flow controllers, and DC Transmission controllers.
4.4. Those planning events in Table 1 that are expected to produce more severe System
impacts on its portion of the BES, shall be identified, and a list created of those
Contingencies to be evaluated in Requirement R4, Part 4.1. The rationale for those
Contingencies selected for evaluation shall be available as supporting information.
4.4.1. Each Planning Coordinator and Transmission Planner shall coordinate with
adjacent Planning Coordinators and Transmission Planners to ensure that
Contingencies on adjacent Systems which may impact their Systems are
included in the Contingency list.
4.5. Those extreme events in Table 1 that are expected to produce more severe System
impacts shall be identified and a list created of those events to be evaluated in
Requirement R4, Part 4.2. The rationale for those Contingencies selected for
evaluation shall be available as supporting information. If the analysis concludes
there is Cascading caused by the occurrence of extreme events, an evaluation of
possible actions designed to reduce the likelihood or mitigate the consequences of the
event(s) shall be conducted.
R5. Each Transmission Planner and Planning Coordinator shall have criteria for acceptable System
steady state voltage limits, post-Contingency voltage deviations, and the transient voltage
response for its System. For transient voltage response, the criteria shall at a minimum, specify
a low voltage level and a maximum length of time that transient voltages may remain below
that level. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
R6. Each Transmission Planner and Planning Coordinator shall define and document, within their
Planning Assessment, the criteria or methodology used in the analysis to identify System
instability for conditions such as Cascading, voltage instability, or uncontrolled islanding.
[Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
R7. Each Planning Coordinator, in conjunction with each of its Transmission Planners, shall
determine and identify each entity’s individual and joint responsibilities for performing the
required studies for the Planning Assessment. [Violation Risk Factor: Low] [Time Horizon:
Long-term Planning]
R8. Each Planning Coordinator and Transmission Planner shall distribute its Planning Assessment
results to adjacent Planning Coordinators and adjacent Transmission Planners within 90
calendar days of completing its Planning Assessment, and to any functional entity that has a
reliability related need and submits a written request for the information within 30 days of such
a request. [Violation Risk Factor: Medium] [Time Horizon: Long-term Planning]
8.1. If a recipient of the Planning Assessment results provides documented comments on
the results, the respective Planning Coordinator or Transmission Planner shall provide
a documented response to that recipient within 90 calendar days of receipt of those
comments.
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
issio
n S
yste
m P
lan
nin
g P
erf
orm
an
ce R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Cate
go
ry A
)
8
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
iss
ion
Sys
tem
Pla
nn
ing
Pe
rfo
rma
nc
e R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Ca
teg
ory
A)
9
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
iss
ion
Sys
tem
Pla
nn
ing
Pe
rfo
rma
nc
e R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Ca
teg
ory
A)
1
0
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
issio
n S
yste
m P
lan
nin
g P
erf
orm
an
ce R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Cate
go
ry A
)
1
1
Tab
le 1
– S
tead
y S
tate
& S
tab
ilit
y P
erf
orm
an
ce
Extr
em
e E
ven
ts
Ste
ad
y S
tate
& S
tab
ilit
y
For
all
extr
em
e e
vents
evalu
ate
d:
a.
Sim
ula
te the r
em
oval o
f all
ele
ments
that P
rote
ction S
yste
ms a
nd a
uto
matic c
ontr
ols
are
expecte
d to d
isconn
ect fo
r each C
ontin
gency.
b.
Sim
ula
te N
orm
al C
learing u
nle
ss o
therw
ise
specifie
d.
Ste
ad
y S
tate
1.
Loss o
f a s
ing
le g
enera
tor,
Tra
nsm
issio
n C
ircuit, sin
gle
pole
of a D
C
Lin
e, shunt de
vic
e, or
transfo
rmer
forc
ed
out of serv
ice follo
we
d b
y
anoth
er
sin
gle
genera
tor,
Tra
nsm
issio
n C
ircuit, sin
gle
pole
of a
diffe
rent D
C L
ine, shunt devic
e, or
transfo
rmer
forc
ed o
ut of serv
ice
prior
to S
yste
m a
dju
stm
ents
.
2.
Local a
rea e
vents
aff
ecting the T
ransm
issio
n S
yste
m s
uch a
s:
a.
Loss o
f a tow
er
line w
ith thre
e o
r m
ore
circuits.1
1
b.
Loss o
f all
Tra
nsm
issio
n li
nes o
n a
com
mon R
ight-
of-
Wa
y11.
c.
Loss o
f a s
witchin
g s
tation
or
substa
tion
(lo
ss o
f one v
oltage
le
vel p
lus tra
nsfo
rmers
).
d.
Loss o
f all
genera
ting
units a
t a g
enera
ting
sta
tion
.
e.
Loss o
f a larg
e L
oad o
r m
ajo
r Loa
d c
ente
r.
3.
Wid
e a
rea e
vents
aff
ecting the T
ransm
issio
n S
yste
m b
ased o
n
Syste
m topo
log
y s
uch
as:
a.
Loss o
f tw
o g
enera
ting
sta
tions r
esu
ltin
g fro
m c
onditio
ns s
uch
as:
i.
Loss o
f a larg
e g
as p
ipe
line
into
a r
eg
ion
or
multip
le
regio
ns that have s
ignific
ant gas-f
ired g
enera
tion.
ii.
Loss o
f th
e u
se o
f a larg
e b
od
y o
f w
ate
r as the c
oo
ling
sourc
e for
genera
tion.
iii.
Wild
fire
s.
iv.
Severe
weath
er,
e.g
., h
urr
icanes, to
rnadoes, etc
.
v.
A s
uccessfu
l cyber
attack.
vi.
Shutd
ow
n o
f a n
ucle
ar
po
wer
pla
nt(
s)
and r
ela
ted
fa
cili
ties for
a d
ay o
r m
ore
for
com
mon
causes s
uch
as p
roble
ms w
ith s
imila
rly d
esig
ned
pla
nts
.
b.
Oth
er
events
based u
pon o
pera
ting
experience
that m
ay
result in
wid
e a
rea d
istu
rba
nces.
Sta
bilit
y
1.
With a
n in
itia
l cond
itio
n o
f a s
ingle
genera
tor,
Tra
nsm
issio
n c
ircuit,
sin
gle
pole
of a D
C lin
e, shu
nt de
vic
e, or
transfo
rmer
forc
ed o
ut of
serv
ice, apply
a 3
Ø fault o
n a
noth
er
sin
gle
genera
tor,
Tra
nsm
issio
n
circuit, sin
gle
po
le o
f a d
iffe
rent D
C lin
e, sh
unt devic
e, or
transfo
rmer
prior
to S
yste
m a
dju
stm
ents
.
2.
Local o
r w
ide a
rea e
vents
aff
ecting
the T
ransm
issio
n S
yste
m s
uch
as:
a.
3Ø
fault o
n g
enera
tor
with
stu
ck b
reaker1
0 o
r a r
ela
y failu
re13
resultin
g in
Dela
ye
d F
ault C
leari
ng.
b.
3Ø
fault o
n T
ransm
issio
n c
ircuit w
ith s
tuck b
reaker1
0 o
r a r
ela
y
failu
re13 re
sultin
g in
Dela
ye
d F
ault C
learing.
c.
3Ø
fault o
n tra
nsfo
rmer
with s
tuck b
reaker1
0 o
r a r
ela
y failu
re13
resultin
g in
Dela
ye
d F
ault C
leari
ng.
d.
3Ø
fault o
n b
us s
ection w
ith
stu
ck b
reaker1
0 o
r a r
ela
y failu
re13
resultin
g in
Dela
ye
d F
ault C
leari
ng.
e.
3Ø
inte
rna
l bre
aker
fault.
f.
Oth
er
events
based u
pon o
pera
ting e
xperience, such
as
consid
era
tion
of in
itia
tin
g e
vents
that experience
sugge
sts
ma
y
result in
wid
e a
rea d
istu
rbances
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
iss
ion
Sys
tem
Pla
nn
ing
Pe
rfo
rma
nc
e R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Ca
teg
ory
A)
1
2
Ta
ble
1 –
Ste
ad
y S
tate
& S
tab
ilit
y P
erf
orm
an
ce
Fo
otn
ote
s
(Pla
nn
ing
Ev
en
ts a
nd
Ex
tre
me
Ev
en
ts)
1.
If the e
ve
nt a
na
lyze
d in
vo
lve
s B
ES
ele
me
nts
at m
ultip
le S
yste
m v
olta
ge le
ve
ls, th
e lo
we
st S
yste
m v
olta
ge le
ve
l of th
e e
lem
ent(
s)
rem
oved
fo
r th
e a
na
lyze
d
eve
nt d
ete
rmin
es the s
tate
d p
erf
orm
ance
crite
ria
re
ga
rdin
g a
llow
ance
s fo
r in
terr
uptio
ns o
f F
irm
Tra
nsm
issio
n S
erv
ice a
nd
No
n-C
on
se
qu
en
tia
l Lo
ad L
oss.
2.
Un
less s
pecifie
d o
the
rwis
e, sim
ula
te N
orm
al C
lea
rin
g o
f fa
ults. S
ingle
lin
e to g
rou
nd (
SL
G)
or
thre
e-p
hase
(3
Ø)
are
the fa
ult typ
es that m
ust be e
va
luate
d in
S
tab
ility
sim
ula
tio
ns fo
r th
e e
ve
nt d
escrib
ed
. A
3Ø
or
a d
ou
ble
lin
e to g
rou
nd
fa
ult s
tud
y in
dic
atin
g the c
rite
ria a
re b
ein
g m
et is
su
ffic
ient e
vid
en
ce
that a S
LG
co
nd
itio
n w
ould
als
o m
eet th
e c
rite
ria.
3.
Bu
lk E
lectr
ic S
yste
m (
BE
S)
leve
l re
fere
nces in
clu
de
extr
a-h
igh
vo
lta
ge (
EH
V)
Fa
cili
tie
s d
efin
ed
as g
rea
ter
than 3
00
kV
and
hig
h v
olta
ge (
HV
) F
acili
ties d
efin
ed
as the 3
00
kV
an
d lo
we
r vo
lta
ge S
yste
ms.
Th
e d
esig
na
tio
n o
f E
HV
an
d H
V is u
se
d to d
istin
gu
ish
betw
een
sta
ted
perf
orm
ance
crite
ria
allo
wa
nces fo
r in
terr
uptio
n o
f F
irm
Tra
nsm
issio
n S
erv
ice a
nd
No
n-C
on
se
qu
en
tia
l Loa
d L
oss.
4.
Cu
rta
ilme
nt of C
on
ditio
na
l Firm
Tra
nsm
issio
n S
erv
ice is a
llow
ed
wh
en the
co
nd
itio
ns a
nd/o
r e
ve
nts
be
ing s
tud
ied
fo
rme
d the b
asis
fo
r th
e C
on
ditio
na
l Firm
T
ransm
issio
n S
erv
ice
.
5.
Fo
r non
-gen
era
tor
ste
p u
p tra
nsfo
rme
r outa
ge
eve
nts
, th
e r
efe
rence
vo
lta
ge
, as u
se
d in
fo
otn
ote
1, a
pp
lies to th
e lo
w-s
ide
win
din
g (
exclu
din
g te
rtia
ry
win
din
gs).
F
or
gen
era
tor
and G
ene
rato
r S
tep
Up tra
nsfo
rme
r outa
ge e
ve
nts
, th
e r
efe
rence
vo
lta
ge a
pp
lies to the B
ES
co
nn
ecte
d v
olta
ge (
hig
h-s
ide o
f th
e
Ge
ne
rato
r S
tep U
p tra
nsfo
rme
r).
Re
quirem
en
ts w
hic
h a
re a
pp
lica
ble
to tra
nsfo
rmers
als
o a
pp
ly to v
ariab
le fre
qu
en
cy tra
nsfo
rme
rs a
nd p
ha
se
sh
iftin
g
tra
nsfo
rme
rs.
6.
Re
quirem
ents
wh
ich a
re a
pp
lica
ble
to s
hu
nt d
evic
es a
lso
app
ly to
FA
CT
S d
evic
es that a
re c
onn
ecte
d to g
rou
nd.
7.
Op
en
ing
one e
nd o
f a li
ne
se
ctio
n w
ith
ou
t a fa
ult o
n a
no
rma
lly n
etw
ork
ed
Tra
nsm
issio
n c
ircu
it s
uch
that th
e lin
e is p
ossib
ly s
erv
ing
Lo
ad r
adia
l fro
m a
sin
gle
so
urc
e p
oin
t.
8.
An in
tern
al b
reaker
fault m
ea
ns a
bre
aker
faili
ng in
tern
ally
, th
us c
reatin
g a
Syste
m fa
ult w
hic
h m
ust be c
lea
red
by p
rote
ctio
n o
n b
oth
sid
es o
f th
e b
reaker.
9.
An o
bje
ctive
of th
e p
lann
ing
pro
cess s
hou
ld b
e to
min
imiz
e th
e lik
elih
oo
d a
nd
ma
gn
itu
de
of in
terr
uptio
n o
f F
irm
Tra
nsm
issio
n S
erv
ice fo
llow
ing C
on
tin
gen
cy
eve
nts
. C
urt
ailm
ent of F
irm
Tra
nsm
issio
n S
erv
ice
is a
llow
ed b
oth
as a
Syste
m a
dju
stm
ent (a
s id
en
tifie
d in th
e c
olu
mn
entitle
d ‘Initial C
ondition’)
and a
co
rrective
actio
n w
hen a
ch
ieve
d th
rou
gh
th
e a
ppro
pri
ate
re-d
isp
atc
h o
f re
so
urc
es o
blig
ate
d to r
e-d
isp
atc
h, w
he
re it
ca
n b
e d
em
onstr
ate
d th
at F
acili
tie
s,
inte
rnal a
nd e
xte
rna
l to th
e T
ransm
issio
n P
lanner’s p
lan
nin
g r
egio
n, re
ma
in w
ith
in a
pp
lica
ble
Fa
cili
ty R
atin
gs a
nd the r
e-d
isp
atc
h d
oe
s n
ot re
su
lt in a
ny N
on-
Co
nse
qu
en
tia
l Loa
d L
oss.
Whe
re li
mite
d o
ptio
ns fo
r re
-dis
pa
tch
exis
t, s
ensitiv
itie
s a
sso
cia
ted
with th
e a
va
ilab
ility
of th
ose
re
so
urc
es s
hou
ld b
e c
onsid
ere
d.
10
. A
stu
ck b
reaker
me
an
s that fo
r a g
ang-o
pe
rate
d b
reake
r, a
ll th
ree
ph
ase
s o
f th
e b
rea
ke
r h
ave r
em
ain
ed
clo
se
d. F
or
an in
de
pe
nd
ent p
ole
op
era
ted
(IP
O)
or
an in
dep
end
ent p
ole
tri
pp
ing
(IP
T)
bre
aker,
only
on
e p
ole
is a
ssu
me
d to r
em
ain
clo
se
d.
A s
tuck b
reaker
resu
lts in D
ela
ye
d F
au
lt C
lea
rin
g.
11
. E
xclu
des c
ircu
its that sh
are
a c
om
mo
n s
tructu
re (
Pla
nn
ing e
ve
nt P
7, E
xtr
em
e e
ve
nt ste
ad
y s
tate
2a)
or
co
mm
on R
igh
t-of-
Wa
y (E
xtr
em
e e
ve
nt,
ste
ad
y s
tate
2b)
for
1 m
ile o
r le
ss.
12
. A
n o
bje
ctive
of th
e p
lan
nin
g p
rocess is to m
inim
ize
th
e lik
elih
oo
d a
nd
ma
gn
itu
de
of N
on-C
onse
qu
entia
l Load
Loss fo
llow
ing
pla
nn
ing
eve
nts
. In
lim
ite
d
circum
sta
nce
s, N
on-C
onseq
uen
tia
l Load
Loss m
ay b
e n
eeded th
rou
gh
ou
t th
e p
lan
nin
g h
orizo
n to
ensu
re th
at B
ES
perf
orm
ance
re
qu
irem
en
ts a
re m
et.
H
ow
eve
r, w
hen
No
n-C
onse
que
ntia
l Lo
ad L
oss is
utiliz
ed u
nder
footn
ote
12 w
ith
in th
e N
ea
r-T
erm
Tra
nsm
issio
n P
lan
nin
g H
ori
zo
n to a
dd
ress B
ES
pe
rfo
rma
nce
re
qu
irem
ents
, su
ch
inte
rru
ptio
n is
lim
ite
d to c
ircum
sta
nce
s w
here
the N
on-C
on
se
qu
entia
l Lo
ad
Lo
ss m
eets
the
co
nd
itio
ns s
how
n in
Att
ach
me
nt
1.
In n
o c
ase
ca
n th
e p
lan
ned
No
n-C
on
se
qu
entia
l L
oa
d L
oss u
nder
footn
ote
12 e
xcee
d 7
5 M
W fo
r U
S r
egis
tere
d e
ntitie
s.
Th
e a
mo
un
t of p
lann
ed N
on-
Co
nse
qu
en
tia
l Lo
ad
Loss for
a n
on-U
S R
eg
iste
red
En
tity
sh
ould
be im
ple
me
nte
d in
a m
ann
er
that is
co
nsis
ten
t w
ith
, or
under
the
dire
ctio
n o
f, th
e a
pplic
ab
le
gove
rnm
enta
l auth
ority
or
its a
ge
ncy in
th
e n
on
-US
juri
sd
ictio
n.
13
. A
pplie
s to the fo
llow
ing
re
lay fu
nctio
ns o
r ty
pes: p
ilot (#
85),
dis
tan
ce
(#
21),
diffe
rentia
l (#
87
), c
urr
ent (#
50
, 51, and 6
7),
vo
lta
ge
(#
27
& 5
9),
dire
ctio
na
l (#
32
, &
67),
and trip
pin
g (
#8
6, &
94).
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
13
Attachment 1
I. Stakeholder Process
During each Planning Assessment before the use of Non-Consequential Load Loss under
footnote 12 is allowed as an element of a Corrective Action Plan in the Near-Term Transmission
Planning Horizon of the Planning Assessment, the Transmission Planner or Planning
Coordinator shall ensure that the utilization of footnote 12 is reviewed through an open and
transparent stakeholder process. The responsible entity can utilize an existing process or develop
a new process. .The process must include the following:
1. Meetings must be open to affected stakeholders including applicable regulatory
authorities or governing bodies responsible for retail electric service issues
2. Notice must be provided in advance of meetings to affected stakeholders including
applicable regulatory authorities or governing bodies responsible for retail electric service
issues and include an agenda with:
a. Date, time, and location for the meeting
b. Specific location(s) of the planned Non-Consequential Load Loss under footnote
12
c. Provisions for a stakeholder comment period
3. Information regarding the intended purpose and scope of the proposed Non-
Consequential Load Loss under footnote 12 (as shown in Section II below) must be made
available to meeting participants
4. A procedure for stakeholders to submit written questions or concerns and to receive
written responses to the submitted questions and concerns
5. A dispute resolution process for any question or concern raised in #4 above that is not
resolved to the stakeholder’s satisfaction
An entity does not have to repeat the stakeholder process for a specific application of footnote 12
utilization with respect to subsequent Planning Assessments unless conditions spelled out in
Section II below have materially changed for that specific application.
I. Information for Inclusion in Item #3 of the Stakeholder Process
The responsible entity shall document the planned use of Non-Consequential Load Loss under
footnote 12 which must include the following:
1. Conditions under which Non-Consequential Load Loss under footnote 12 would be
necessary:
a. System Load level and estimated annual hours of exposure at or above that Load
level
b. Applicable Contingencies and the Facilities outside their applicable rating due to
that Contingency
2. Amount of Non-Consequential Load Loss with:
a. The estimated number and type of customers affected
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
14
b. An explanation of the effect of the use of Non-Consequential Load Loss under
footnote 12 on the health, safety, and welfare of the community
3. Estimated frequency of Non-Consequential Load Loss under footnote 12 based on
historical performance
4. Expected duration of Non-Consequential Load Loss under footnote 12 based on historical
performance
5. Future plans to alleviate the need for Non-Consequential Load Loss under footnote 12
6. Verification that TPL Reliability Standards performance requirements will be met
following the application of footnote 12
7. Alternatives to Non-Consequential Load Loss considered and the rationale for not
selecting those alternatives under footnote 12
8. Assessment of potential overlapping uses of footnote 12 including overlaps with adjacent
Transmission Planners and Planning Coordinators
II. Instances for which Regulatory Review of Non-Consequential Load Loss under Footnote 12
is Required
Before a Non-Consequential Load Loss under footnote 12 is allowed as an element of a
Corrective Action Plan in Year One of the Planning Assessment, the Transmission Planner or
Planning Coordinator must ensure that the applicable regulatory authorities or governing bodies
responsible for retail electric service issues do not object to the use of Non-Consequential Load
Loss under footnote 12 if either:
1. The voltage level of the Contingency is greater than 300 kV
a. If the Contingency analyzed involves BES Elements at multiple System voltage
levels, the lowest System voltage level of the element(s) removed for the
analyzed Contingency determines the stated performance criteria regarding
allowances for Non-Consequential Load Loss under footnote 12, or
b. For a non-generator step up transformer outage Contingency, the 300 kV limit
applies to the low-side winding (excluding tertiary windings). For a generator or
generator step up transformer outage Contingency, the 300 kV limit applies to the
BES connected voltage (high-side of the Generator Step Up transformer)
2. The planned Non-Consequential Load Loss under footnote 12 is greater than or equal to
25 MW
Once assurance has been received that the applicable regulatory authorities or governing bodies
responsible for retail electric service issues do not object to the use of Non-Consequential Load
Loss under footnote 12, the Planning Coordinator or Transmission Planner must submit the
information outlined in items II.1 through II.8 above to the ERO for a determination of whether
there are any Adverse Reliability Impacts caused by the request to utilize footnote 12 for Non-
Consequential Load Loss.
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
15
5. Effective Date: May 13, 2009
B. Requirements
R1. The Planning Authority and Transmission Planner shall each demonstrate through a valid
assessment that its portion of the interconnected transmission system is planned such that,
with all transmission facilities in service and with normal (pre-contingency) operating
procedures in effect, the Network can be operated to supply projected customer demands and
projected Firm (non- recallable reserved) Transmission Services at all Demand levels over
the range of forecast system demands, under the conditions defined in Category A of Table I.
To be considered valid, the Planning Authority and Transmission Planner assessments shall:
R1.1. Be made annually.
R1.2. Be conducted for near-term (years one through five) and longer-term (years six
through ten) planning horizons.
R1.3. Be supported by a current or past study and/or system simulation testing that
addresses each of the following categories, showing system performance following
Category A of Table 1 (no contingencies). The specific elements selected (from
each of the following categories) shall be acceptable to the associated Regional
Reliability Organization(s).
R1.3.1. Cover critical system conditions and study years as deemed appropriate by
the entity performing the study.
R1.3.2. Be conducted annually unless changes to system conditions do not warrant
such analyses.
R1.3.3. Be conducted beyond the five-year horizon only as needed to address
identified marginal conditions that may have longer lead-time solutions.
R1.3.4. Have established normal (pre-contingency) operating procedures in place.
R1.3.5. Have all projected firm transfers modeled.
R1.3.6. Be performed for selected demand levels over the range of forecast system
demands.
R1.3.7. Demonstrate that system performance meets Table 1 for Category A (no
contingencies).
R1.3.8. Include existing and planned facilities.
R1.3.9. Include Reactive Power resources to ensure that adequate reactive resources
are available to meet system performance.
R1.4. Address any planned upgrades needed to meet the performance requirements of
Category A.
R2. When system simulations indicate an inability of the systems to respond as
prescribed in Reliability Standard TPL-001-0_R1, the Planning Authority
and Transmission Planner shall each:
R2.1. Provide a written summary of its plans to achieve the required system
performance as described above throughout the planning horizon.
R2.1.1. Including a schedule for implementation.
R2.1.2. Including a discussion of expected required in-service dates of facilities.
R2.1.3. Consider lead times necessary to implement plans.
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
16
R2.2. Review, in subsequent annual assessments, (where sufficient lead time exists), the
continuing need for identified system facilities. Detailed implementation plans are
not needed.
R3. The Planning Authority and Transmission Planner shall each document the
results of these reliability assessments and corrective plans and shall
annually provide these to its respective NERC Regional Reliability
Organization(s), as required by the Regional Reliability Organization.
C. Measures
M1. Each Transmission Planner and Planning Coordinator shall provide evidence, in electronic or
hard copy format, that it is maintaining System models within their respective area, using data
consistent with MOD-010 and MOD-012, including items represented in the Corrective Action
Plan, representing projected System conditions, and that the models represent the required
information in accordance with Requirement R1.
M2. Each M1. The Planning Authority and Transmission Planner shall have
a valid assessment and corrective plans as specified in Reliability
Standard TPL-001-0_R1 and TPL-001- 0_R2.
M2. The Planning Authority and Transmission Planner and Planning Coordinator shall provide
dated evidence, such as electronic or hard copies of its annual Planning Assessment, that it
has prepared an annual Planning Assessment of its portion of the BES in accordance with
Requirement R2.
M3. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of the studies utilized in preparing the Planning Assessment, in
accordance with Requirement R3.
M4. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of the studies utilized in preparing the Planning Assessment in
accordance with Requirement R4.
M5. Each Transmission Planner and Planning Coordinator shall provide dated evidence such as
electronic or hard copies of thehave evidence it reported documentation specifying the
criteria for acceptable System steady state voltage limits, post-Contingency voltage
deviations, and the transient voltage response for its System in accordance with
Requirement R5.
M6. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of documentation specifying the criteria or methodology used in the
analysis to identify System instability for conditions such as Cascading, voltage instability, or
uncontrolled islanding that was utilized in preparing the Planning Assessment in accordance
with Requirement R6.
M7. Each Planning Coordinator, in conjunction with each of its Transmission Planners, shall
provide dated documentation on roles and responsibilities, such as meeting minutes,
agreements, and e-mail correspondence that identifies that agreement has been reached on
individual and joint responsibilities for performing the required studies and of results of its
Reliability Assessments in accordance with Requirement R7and corrective plans per
Reliability Standard TPL-001-0_R3.
M8. Each Planning Coordinator and Transmission Planner shall provide evidence, such as email
notices, documentation of updated web pages, postal receipts showing recipient and date; or a
demonstration of a public posting, that it has distributed its Planning Assessment results to
adjacent Planning Coordinators and adjacent Transmission Planners within 90 days of having
completed its Planning Assessment, and to any functional entity who has indicated a reliability
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
17
need within 30 days of a written request and that the Planning Coordinator or Transmission
Planner has provided a documented response to comments received on Planning Assessment
results within 90 calendar days of receipt of those comments in accordance with Requirement
R8.
D. Compliance
1. Compliance Monitoring Process
1.1 Compliance Enforcement Authority
Regional Entity
1.1.1.2 Compliance Monitoring Period and Reset TimeframeResponsibility
Not applicableCompliance Monitor: Regional Reliability Organization.
Each Compliance Monitor shall report compliance and violations to NERC via the NERC
Compliance Reporting Process.
1.2.1.3 Compliance Monitoring Period and Enforcement Processes:Reset Time Frame
Compliance Audits
Self-Certifications
Spot Checking
Compliance Violation Investigations Self-
Reporting
Complaints
Annually
1.3.1.4 Data Retention
The Transmission Planner and Planning Coordinator shall each retain data or evidence to
show compliance as identified unless directed by its Compliance Enforcement Authority
to retain specific evidence for a longer period of time as part of an investigation:
The models utilized in the current in-force Planning Assessment and one
previous Planning Assessment in accordance with Requirement R1 and Measure
M1.
The Planning Assessments performed since the last compliance audit in
accordance with Requirement R2 and Measure M2.
The studies performed in support of its Planning Assessments since the last
compliance audit in accordance with Requirement R3 and Measure M3.
The studies performed in support of its Planning Assessments since the last
compliance audit in accordance with Requirement R4 and Measure M4.
The documentation specifying the criteria for acceptable System steady state
voltage limits, post-Contingency voltage deviations, and transient voltage
response since the last compliance audit in accordance with Requirement R5 and
Measure M5.
The documentation specifying the criteria or methodology utilized in the analysis
to identify System instability for conditions such as Cascading, voltage
instability, or uncontrolled islanding in support of its Planning Assessments since
the last compliance audit in accordance with Requirement R6 and Measure M6.
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
18
The current, in force documentation for the agreement(s) on roles and
responsibilities, as well as documentation for the agreements in force since the
last compliance audit, in accordance with Requirement R7 and Measure M7.
The Planning Coordinator shall retain data or evidence to show compliance as identified
unless directed by its Compliance Enforcement Authority to retain specific evidence for a
longer period of time as part of an investigation:
Three calendar years of the notifications employed in accordance with
Requirement R8 and Measure M8.
If a Transmission Planner or Planning Coordinator is found non-compliant, it shall keep
information related to the non-compliance until found compliant or the time periods
specified above, whichever is longer.
None specified.
1.4.1.5 Additional Compliance Information
None
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
issio
n S
yste
m P
lan
nin
g P
erf
orm
an
ce R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Cate
go
ry A
)
1
9
Vio
lati
on
Sev
erit
y
2.
Levels
of
Non-C
om
plia
nce
Lo
wer
VS
L
Modera
te V
SL
Hig
h V
SL
Severe
VS
L
R1
T
he r
esponsib
le entity’s
Syste
m
model f
aile
d to r
epre
sent one o
f th
e
Requ
irem
ent R
1, P
art
s 1
.1.1
th
rough 1
.1.6
.
The r
esponsib
le entity’s
Syste
m
model f
aile
d to r
epre
sent tw
o o
f th
e
Requ
irem
ent R
1, P
art
s 1
.1.1
thro
ugh
1.1
.6.
The r
esponsib
le entity’s
Syste
m
model f
aile
d to r
epre
sent th
ree o
f th
e
Requ
irem
ent R
1, P
art
s 1
.1.1
thro
ugh
1.1
.6.
The r
esponsib
le entity’s
Syste
m m
odel
faile
d to r
epre
sent fo
ur
or
more
of th
e
Requ
irem
ent R
1, P
art
s 1
.1.1
thro
ugh
1.1
.6.
OR
The r
esponsib
le entity’s
Syste
m m
odel
did
not re
pre
sent pro
jecte
d S
yste
m
conditio
ns a
s d
escribed
in R
equirem
ent
R1.
OR
The r
esponsib
le entity’s
Syste
m m
odel
did
not use
data
consis
tent
with that
pro
vid
ed in
acco
rdance
with
the M
OD
- 010 a
nd M
OD
-01
2 s
tand
ard
s a
nd o
ther
sourc
es, in
clu
din
g it
em
s r
epre
sente
d in
th
e C
orr
ective
Action P
lan.
R2
T
he r
esponsib
le e
ntity
faile
d to
com
ply
with R
equ
irem
ent R
2, P
art
2.6
.
The r
esponsib
le e
ntity
faile
d to
com
ply
with R
equ
irem
ent R
2, P
art
2.3
or
Part
2.8
.
The r
esponsib
le e
ntity
faile
d to
com
ply
with o
ne
of th
e follo
win
g
Part
s o
f R
equirem
ent R
2: P
art
2.1
, P
art
2.2
, P
art
2.4
, P
art
2.5
, or
Part
2.7
.
The r
esponsib
le e
ntity
fa
iled
to c
om
ply
w
ith t
wo
or
more
of
the f
ollo
win
g P
art
s
of
Requirem
ent
R2:
Part
2.1
, P
art
2.2
, P
art
2.4
, or
Part
2.7
.
OR
The r
esponsib
le e
ntity
do
es n
ot have
a
com
ple
ted
ann
ua
l Pla
nnin
g
Assessm
ent.
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
issio
n S
yste
m P
lan
nin
g P
erf
orm
an
ce R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Cate
go
ry A
)
2
0
R3
T
he r
esponsib
le e
ntity
did
not
ide
ntify
pla
nnin
g e
vents
as
described
in R
equirem
ent R
3, P
art
3.4
or
extr
em
e e
vents
as d
escribed
in
Req
uirem
ent R
3, P
art
3.5
.
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in
Requirem
ent
R3, P
art
3.1
to d
ete
rmin
e that th
e
BE
S m
eets
the p
erf
orm
ance
re
quirem
ents
for
one o
f th
e c
ate
gories
(P2 thro
ugh
P7)
in T
able
1.
The r
esponsib
le e
ntity
did
not
perf
orm
stu
die
s a
s s
pecifie
d in
R
equ
irem
ent R
3, P
art
3.1
to
dete
rmin
e that th
e B
ES
meets
the
perf
orm
ance
requirem
ents
for
two o
f th
e c
ate
gories (
P2 thro
ugh P
7)
in
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
equ
irem
ent R
3,
Part
3.1
to
de
term
ine that th
e B
ES
m
eets
the p
erf
orm
ance
requirem
ents
fo
r th
ree o
r m
ore
of th
e c
ate
gories (
P2
th
rough P
7)
in T
able
1.
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
issio
n S
yste
m P
lan
nin
g P
erf
orm
an
ce R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Cate
go
ry A
)
2
1
Lo
wer
VS
L
Modera
te V
SL
Hig
h V
SL
Severe
VS
L
OR
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in
Requirem
ent
R3, P
art
3.2
to a
ssess the im
pact of
extr
em
e e
vents
.
Table
1.
OR
The r
esponsib
le e
ntity
did
not
perf
orm
Contin
gency a
naly
sis
as
described
in R
equirem
ent R
3, P
art
3.3
.
OR
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s to
de
term
ine tha
t th
e B
ES
m
eets
the p
erf
orm
ance
requirem
ents
fo
r th
e P
0 o
r P
1 c
ate
gories in T
able
1.
OR
The r
esponsib
le e
ntity
did
not base its
stu
die
s o
n c
om
pute
r sim
ula
tion m
odels
usin
g d
ata
pro
vid
ed in
Re
qu
irem
ent R
1.
R4
T
he r
esponsib
le e
ntity
did
not
ide
ntify
pla
nnin
g e
vents
as
described
in R
equirem
ent R
4, P
art
4.4
or
extr
em
e e
vents
as d
escribed
in
Req
uirem
ent R
4, P
art
4.5
.
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in
Requirem
ent
R4, P
art
4.1
to d
ete
rmin
e that th
e
BE
S m
eets
the p
erf
orm
ance
re
quirem
ents
for
one o
f th
e c
ate
gories
(P1 thro
ugh
P7)
in T
able
1.
OR
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in
Requirem
ent
R4, P
art
4.2
to a
ssess the im
pact of
extr
em
e e
vents
.
The r
esponsib
le e
ntity
did
not
perf
orm
stu
die
s a
s s
pecifie
d in
R
equ
irem
ent R
4, P
art
4.1
to
dete
rmin
e that th
e B
ES
meets
the
perf
orm
ance
requirem
ents
for
two o
f th
e c
ate
gories (
P1 thro
ugh P
7)
in
Table
1.
OR
The r
esponsib
le e
ntity
did
not
perf
orm
Contin
gency a
naly
sis
as
described
in R
equirem
ent R
4, P
art
4.3
.
The r
esponsib
le e
ntity
did
not perf
orm
stu
die
s a
s s
pecifie
d in R
equ
irem
ent R
4,
Part
4.1
to
de
term
ine that th
e B
ES
m
eets
the p
erf
orm
ance
requirem
ents
fo
r th
ree o
r m
ore
of th
e c
ate
gories (
P1
th
rough P
7)
in T
able
1.
OR
The r
esponsib
le e
ntity
did
not base its
stu
die
s o
n c
om
pute
r sim
ula
tion m
odels
usin
g d
ata
pro
vid
ed in
Re
qu
irem
ent R
1.
R5
N
/A
N/A
N
/A
The r
esponsib
le e
ntity
do
es n
ot have
crite
ria for
accepta
ble
Syste
m s
tead
y
sta
te v
oltage li
mits, post-
Contingency
voltage d
evia
tions, or
the tra
nsie
nt
voltage r
esponse
for
its S
yste
m.
R6
N
/A
N/A
N
/A
The r
esponsib
le e
ntity
fa
iled
to d
efine
and d
ocum
ent th
e c
rite
ria
or
meth
odolo
gy for
Syste
m in
sta
bili
ty u
se
d
within
its
analy
sis
as d
escribed
in
Requ
irem
ent R
6.
Sta
nd
ard
TP
L-0
01-4
0.1
—T
ran
sm
issio
n S
yste
m P
lan
nin
g P
erf
orm
an
ce R
eq
uir
em
en
tsU
nd
er
No
rmal (N
o C
on
tin
gen
cy)C
on
dit
ion
s (
Cate
go
ry A
)
2
2
Lo
wer
VS
L
Modera
te V
SL
Hig
h V
SL
Severe
VS
L
R7
N
/A
N/A
N
/A
The P
lannin
g C
oord
inato
r, in
conju
nction
with e
ach o
f its
Tra
nsm
issio
n P
lanners
, fa
iled to
dete
rmin
e a
nd id
entify
indiv
idua
l or
join
t re
sponsib
ilities for perf
orm
ing
requir
ed
stu
die
s.
R8
T
he r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
adja
cent P
lannin
g C
oord
ina
tors
and
adja
cent T
ransm
issio
n P
lan
ners
but
it w
as m
ore
than 9
0 d
ays b
ut le
ss
than o
r equal to
120 d
ays follo
win
g
its c
om
ple
tion.
OR
,
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
functional e
ntities h
avin
g a
relia
bili
ty
rela
ted
need w
ho r
equeste
d the
Pla
nnin
g A
ssessm
ent in
wri
ting b
ut
it w
as m
ore
than 3
0 d
ays b
ut le
ss
than o
r equa
l to 4
0 d
ays follo
win
g
the request.
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
adja
cent P
lannin
g C
oord
ina
tors
and
adja
cent T
ransm
issio
n P
lan
ners
but it
was m
ore
than 1
20 d
ays b
ut le
ss than
or
equal t
o 1
30
da
ys follo
win
g its
com
ple
tion.
OR
,
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
functional e
ntities h
avin
g a
relia
bili
ty
rela
ted
need w
ho r
equeste
d the
Pla
nnin
g A
ssessm
ent in
wri
ting b
ut it
was m
ore
than 4
0 d
ays b
ut le
ss than
or
equal t
o 5
0 d
ays follo
win
g the
request.
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
adja
cent P
lannin
g C
oord
ina
tors
and
adja
cent T
ransm
issio
n P
lan
ners
but
it w
as m
ore
than 1
30 d
ays b
ut le
ss
than o
r equal to
140 d
ays follo
win
g
its c
om
ple
tion.
OR
,
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
functional e
ntities h
avin
g a
relia
bili
ty
rela
ted
need w
ho r
equeste
d the
Pla
nnin
g A
ssessm
ent in
wri
ting b
ut it
was m
ore
than 5
0 d
ays b
ut le
ss than
or
equal t
o 6
0 d
ays follo
win
g the
request.
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
adja
cent P
lannin
g C
oord
ina
tors
and
adja
cent T
ransm
issio
n P
lan
ners
but it
was m
ore
than 1
40 d
ays follo
win
g its
com
ple
tion.
OR
The r
esponsib
le e
ntity
did
not d
istr
ibu
te
its P
lann
ing
Assessm
ent re
sults to
adja
cent P
lannin
g C
oord
ina
tors
and
adja
cent T
ransm
issio
n P
lanners
.
OR
The r
esponsib
le e
ntity
dis
trib
ute
d it
s
Pla
nnin
g A
ssessm
ent re
sults to
functional e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed w
ho r
equeste
d the
Pla
nnin
g A
ssessm
ent in
wri
ting b
ut it
was m
ore
than 6
0 d
ays follo
win
g the
request.
OR
The r
esponsib
le e
ntity
did
not d
istr
ibu
te
its P
lann
ing
Assessm
ent re
sults to
functional e
ntities h
avin
g a
relia
bili
ty
rela
ted n
eed w
ho r
equeste
d the
Pla
nnin
g A
ssessm
ent in
writing.
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
23
2.1. Level 1: Not applicable.
2.2. Level 2: A valid assessment and corrective plan for the longer-term planning
horizon is not available.
2.3. Level 3: Not applicable.
2.4. Level 4: A valid assessment and corrective plan for the near-term planning
horizon is not available.
E. Regional VariancesDifferences
1. None identified.
Version History
Version Date Action Change Tracking
0 April 1, 2005 Effective Date New
0 February 8, 2005 BOT Approval Revised
0 June 3, 2005 Fixed reference in M1 to read TPL-001-0 R2.1
and TPL-001-0 R2.2
Errata
0 July 24, 2007 Corrected reference in M1. to read TPL-001-0
R1 and TPL-001-0 R2.
Errata
0.1 October 29, 2008 BOT adopted errata changes; updated version number
to “0.1”
Errata
0.1 May 13, 2009 FERC Approved – Updated Effective Date and Footer Revised
1 Approved by
Board of Trustees
February 17, 2011
Revised footnote ‘b’ pursuant to FERC Order RM06-
16-009 Revised (Project 2010-
11)
2 August 4, 2011 Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0,
TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
Project 2006-02 –
complete revision
2 August 4, 2011 Adopted by Board of Trustees
1 April 19, 2012 FERC issued Order 762 remanding TPL-001-1, TPL-
002-1b, TPL-003-1a, and TPL-004-1. FERC also
issued a NOPR proposing to remand TPL-001-2.
NERC has been directed to revise footnote 'b' in
accordance with the directives of Order Nos. 762 and
693.
3 February 7, 2013 Adopted by the NERC Board of Trustees.
TPL-001-3 was created after the Board of Trustees
approved the revised footnote ‘b’ in TPL-002-2b,
which was balloted and appended to: TPL-001-0.1,
TPL-002-0b, TPL-003-0a, and TPL-004-0.
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
24
4 February 7, 2013 Adopted by the NERC Board of Trustees.
TPL-001-4 was adopted by the Board of Trustees as
TPL-001-3, but a discrepancy in numbering was
identified and corrected prior to filing with the
regulatory agencies.
4 October 17, 2013 FERC Order issued approving TPL-001-4 (Order
effective December 23, 2013).
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
25
Table I. Transmission System Standards – Normal and Emergency Conditions
Category Contingencies System Limits or Impacts
Initiating Event(s) and Contingency
Element(s)
System Stable and both
Thermal and
Voltage Limits within
Applicable
Rating a
Loss of Demand
or Curtailed Firm
Transfers
Cascading Outages
A
No Contingencies
All Facilities in Service
Yes
No
No
B
Event resulting in
the loss of a single element.
Single Line Ground (SLG) or 3-Phase (3Ø)
Fault, with Normal Clearing: 1. Generator
2. Transmission Circuit
3. Transformer Loss of an Element without a Fault
Yes
Yes
Yes Yes
No b
No b
No b
No b
No
No
No No
Single Pole Block, Normal Clearing e:
4. Single Pole (dc) Line
Yes
Nob
No
C
Event(s)
resulting in the loss of two or
more (multiple)
SLG Fault, with Normal Clearing e:
1. Bus Section
2. Breaker (failure or internal Fault)
e
Yes
Yes
Planned/
Controlledc
Planned/
Controlledc
No
No
elements. SLG or 3Ø Fault, with Normal Clearing ,
Manual System Adjustments, followed by another SLG or 3Ø Fault, with Normal
Clearing e:
3. Category B (B1, B2, B3, or B4)
contingency, manual system
adjustments, followed by another Category B (B1, B2, B3, or B4)
contingency
Yes
Planned/
Controlledc
No
Bipolar Block, with Normal Clearing: e
4. Bipolar (dc) Line Fault (non 3Ø), with
Normal Clearing e:
5. Any two circuits of a multiple circuit
towerlinef
Yes
Yes
Planned/
Controlledc
Planned/
Controlledc
No
No
SLG Fault, with Delayed Clearing e
(stuck breaker or protection system failure):
6. Generator
7. Transformer
8. Transmission Circuit
9. Bus Section
Yes
Yes Yes
Yes
Planned/
Controlledc
Planned/
Controlledc
Planned/
Controlledc
Planned/
Controlledc
No
No No
No
Standard TPL-001-40.1 —Transmission System Planning Performance RequirementsUnder Normal (No Contingency)Conditions (Category A)
26
a) Applicable rating refers to the applicable Normal and Emergency facility thermal Rating or system voltage limit as determined and
consistently applied by the system or facility owner. Applicable Ratings may include Emergency Ratings applicable for short
durations as required to permit operating steps necessary to maintain system control. All Ratings must be established consistent
with applicable NERC Reliability Standards addressing Facility Ratings.
b) Planned or controlled interruption of electric supply to radial customers or some local Network customers, connected to or
supplied by the Faulted element or by the affected area, may occur in certain areas without impacting the overall reliability of
the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including
curtailments of contracted Firm (non-recallable reserved) electric power Transfers.
c) Depending on system design and expected system impacts, the controlled interruption of electric supply to customers (load
shedding), the planned removal from service of certain generators, and/or the curtailment of contracted Firm (non-recallable
reserved) electric power Transfers may be necessary to maintain the overall reliability of the interconnected transmission
systems.
d) A number of extreme contingencies that are listed under Category D and judged to be critical by the transmission planning
entity(ies) will be selected for evaluation. It is not expected that all possible facility outages under each listed contingency of
Category D will be evaluated.
e) Normal clearing is when the protection system operates as designed and the Fault is cleared in the time normally expected with
proper functioning of the installed protection systems. Delayed clearing of a Fault is due to failure of any protection system
component such as a relay, circuit breaker, or current transformer, and not because of an intentional design delay.
f) System assessments may exclude these events where multiple circuit towers are used over short distances (e.g., station entrance, river
crossings) in accordance with Regional exemption criteria.
D d
Extreme event resulting in
two or more (multiple) elements removed or
Cascading out of service.
3Ø Fault, with Delayed Clearing e
(stuck breaker or protection system failure):
1. Generator 3. Transformer 2. Transmission Circuit 4. Bus Section
3Ø Fault, with Normal Clearing e:
5. Breaker (failure or internal Fault)
6. Loss of towerline with three or more circuits 7. All transmission lines on a common right-of way
8. Loss of a substation (one voltage level plus transformers)
9. Loss of a switching station (one voltage level plus transformers)
10. Loss of all generating units at a station
11. Loss of a large Load or major Load center 12. Failure of a fully redundant Special Protection System (or
remedial action scheme) to operate when required
13. Operation, partial operation, or misoperation of a fully redundant Special Protection System (or Remedial Action
Scheme) in response to an event or abnormal system
condition for which it was not intended to operate 14. Impact of severe power swings or oscillations from
Disturbances in another Regional Reliability Organization.
Evaluate for risks and consequences.
May involve substantial loss of customer Demand and
generation in a widespread
area or areas. Portions or all of the
interconnected systems may
or may not achieve a new, stable operating point.
Evaluation of these events may
require joint studies with neighboring systems.
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Appendix B-1
BC Hydro Feedback Survey Forms
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
T&D Cost
One Time ($)
T&D Cost
Ongoing ($)
Generation Cost
One Time ($)
Generation Cost
Ongoing ($)
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
FERC Order 786 dated
10/17/13
Docket No. RM12-1-000
and RM13-9-000
145 FERC ¶ 61,051
T&D: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following
BCUC approval, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance
with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
T&D: No incremental actions expected. $0 $0 N/A N/A
T&D: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following
BCUC approval, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance
with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
T&D: No incremental actions expected. $0 $0 N/A N/A
T&D: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following
BCUC approval, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance
with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
T&D: If the TPL assessments identify there is a need to shed non-
consequential load , then the use of NCLL will need to be reviewed through an
open and transparent stakeholder process.
Estimated Breakdown of Costs:
One-Time Costs - The use of NCLL is estimated to be on approximately four
occassions in lieu of transmission reinforcements. Each stakeholder process
required is estimated to cost about $100,000. The total cost of a stakeholder
process for all four events is estimated to be about $400,000.
Ongoing (Annual) - Not known at this time; will come out of future planning
studies.
$400,000 Unknown at this time N/A N/A
T&D: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following
BCUC approval, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance
with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
T&D: No incremental actions expected. $0 $0 N/A N/A
T&D: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following
BCUC approval, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance
with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
T&D: The study methodology need to be re written to take in to account the new
requirements:
a) Sensitivity studies
b) equipment spares availability related analysis
c) short circuit studies and analysis of results
d) options of alternatives to reinforcements detailed in the standard.
Estimated Breakdown of Costs:
One-Time Costs - Two weeks worth of time for about eight transmission planners
= $56,000.
Ongoing (Annual) Costs - About one more week in increase of studies required
for about eight transmission planners (280 man hours) = $28,000. This
incremental increase in TPL assessment activity is due to aforementioned
additional TPL-001-4 requirements.
$56,000 $28,000 N/A N/A
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and
curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would
not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
TPL-001-4 R2
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and
curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would
not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
TPL-001-4 R6
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and
curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would
not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
TPL-001-4 R5
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC 23-Dec-2013
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and
curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would
not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
TPL-001-4 R4
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
TPL-001-4 R3
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and
curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would
not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
23-Dec-2013
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Estimated Incremental/New Costs Associated with Revision/New Standard/Requirement, if any ($)
T&D: Modelling is an ongoing activity with minimal changes to existing process
if any. Equipment spares availability need to be dove tailed with power flow base
cases and contingency lists. The short circuit study equipment models are to be
included in existing TPL assessment planning models.There are no adverse
reliability impacts or technical / administrative suitability issues.
Estimated Breakdown of Costs:
One-Time - $10,000 (assuming 100 man hours).
Ongoing (Annual) - $0
$10,000 $0 N/A N/A T&D: First day of first calendar quarter, two years after BCUC adoption.
BC Hydro Stakeholder Comments Organizational Activities and
Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a cell)
Functional
Applicability of FERC
Approved Standards/
Requirements
FERC Order No., Order
Date and Order
Publication Date
(Each cell is linked to
the respective FERC
Order if applicable)
US Effective
Date of FERC
Order Ruling
Approving
Standard(s)
(Each cell is
linked to the
respective
effective dates
of the FERC
Approval
Ruling if
applicable)
TPL-001-4 R1
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first
calendar quarter, 12 months after applicable regulatory approval.
FERC Approved
New/Revised
Standard/Requirement
(Select the respective
link to open the
Standards)
Standard Name and DescriptionCurrent BCUC Adopted
Standards to be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Appendix B-1
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 1 of 3
T&D Cost
One Time ($)
T&D Cost
Ongoing ($)
Generation Cost
One Time ($)
Generation Cost
Ongoing ($)
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Estimated Incremental/New Costs Associated with Revision/New Standard/Requirement, if any ($)
T&D: Modelling is an ongoing activity with minimal changes to existing process
if any. Equipment spares availability need to be dove tailed with power flow base
cases and contingency lists. The short circuit study equipment models are to be
included in existing TPL assessment planning models.There are no adverse
reliability impacts or technical / administrative suitability issues.
Estimated Breakdown of Costs:
One-Time - $10,000 (assuming 100 man hours).
Ongoing (Annual) - $0
$10,000 $0 N/A N/A T&D: First day of first calendar quarter, two years after BCUC adoption.
BC Hydro Stakeholder Comments Organizational Activities and
Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a cell)
Functional
Applicability of FERC
Approved Standards/
Requirements
FERC Order No., Order
Date and Order
Publication Date
(Each cell is linked to
the respective FERC
Order if applicable)
US Effective
Date of FERC
Order Ruling
Approving
Standard(s)
(Each cell is
linked to the
respective
effective dates
of the FERC
Approval
Ruling if
applicable)
TPL-001-4 R1
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first
calendar quarter, 12 months after applicable regulatory approval.
FERC Approved
New/Revised
Standard/Requirement
(Select the respective
link to open the
Standards)
Standard Name and DescriptionCurrent BCUC Adopted
Standards to be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
T&D: First day of first calendar quarter, three years after BCUC adoption.
For 84 calendar months beginning the first day of the first calendar quarter following
BCUC approval, Corrective Action Plans applying to the following categories of
Contingencies and events identified in TPL-001-4, Table 1 are allowed to include Non-
Consequential Load Loss and curtailment of Firm Transmission Service (in accordance
with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected
to or supplied by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
T&D: No incremental actions expected. $0 $0 N/A N/A
NOTE: This requirement applies to the PC role (not yet defined in BC) in
conjunction with the TP role. Only provide feedback if necessary here.
NOTE: This requirement applies
to the PC role (not yet defined in
BC) in conjunction with the TP
role. Only provide feedback if
necessary here.
NOTE: This requirement
applies to the PC role (not yet
defined in BC) in conjunction
with the TP role. Only provide
feedback if necessary here.
N/A N/A
NOTE: This requirement applies to the PC role (not yet defined in BC) in conjunction with
the TP role. Only provide feedback if necessary here.23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first
calendar quarter, 12 months after applicable regulatory approval.
TPL-001-4 R8
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and
curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would
not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied
by the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
TPL-001-4 R7
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range
of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0,
TPL-002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
PC
Docket No. RM12-1-000
and RM13-9-000, Order
786; Issue Date: October
17, 2013; Publication
Date: October 23, 2013
Appendix B-1
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 2 of 3
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Cost
One Time ($)
Cost
Ongoing ($)
Bus-tie Breaker
*Glossary term is specific to the TPL-001-4 standard.
N/A A circuit breaker that is positioned to connect two individual substation bus configurations. New N/A 17-Oct-13 01-Jan-15
Coincide with the earliest effective date of the TPL-001-4
standard after BCUC adoption.
Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
All Load that is no longer served by the Transmission system as a result of Transmission
Facilities being removed from service by a Protection System operation designed to isolate
the fault.
New N/A 17-Oct-13 01-Jan-15
Coincide with the earliest effective date of the TPL-001-4
standard after BCUC adoption.
Long-Term Transmission Planning Horizon
*Glossary term is specific to the TPL-001-4 standard.
N/A
Transmission planning period that covers years six through ten or beyond when required to
accommodate any known longer lead time projects that may take longer than ten years to
complete.
New N/A 17-Oct-13 01-Jan-15
Coincide with the earliest effective date of the TPL-001-4
standard after BCUC adoption.
Non-Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
Non-Interruptible Load loss that does not include: (1) Consequential Load Loss, (2) the
response of voltage sensitive Load, or (3) Load that is disconnected from the System by end-
user equipment.
New N/A 17-Oct-13 01-Jan-15
Coincide with the earliest effective date of the TPL-001-4
standard after BCUC adoption.
Planning Assessment
*Glossary term is specific to the TPL-001-4 standard.
N/ADocumented evaluation of future Transmission System performance and Corrective Action
Plans to remedy identified deficiencies.New N/A 17-Oct-13 01-Jan-15
Coincide with the earliest effective date of the TPL-001-4
standard after BCUC adoption.
Effective Date of
New/Revised/Retired NERC
Term and Definition in United
States
Stakeholder Comments
(Press Alt-Enter to insert a carriage return in a cell)
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental Cost Associated with
Revised/New Term and Definition, if any ($).
(Press Alt-Enter to insert a carriage return in a cell)FERC Approved New/Revised/Retired NERC Glossary of Terms from the
February 7, 2017 Glossary of Terms
Acronym
(If Available)
FERC Approved New/Revised NERC Term Definitions against Terms and Definitions
listed in Columns "D" and "E"
(changes to definition indicated by red text; deletions are not indicated)
Current BCUC Adopted Terms
from
December 7, 2015
Glossary of Terms
(Column "D")
Current BCUC Adopted
Definition from December 7, 2015
Glossary of Terms
FERC Approval Date of
New/Revised/Retired NERC
Term and Definition
Appendix B-1
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 3 of 3
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Appendix B-2
Instructions for Registered Entities
Task # Task Description Reference Files and Links Comments
3 Compliance Leads are requested to email the Reliability Compliance department (use the email address provided in the column to the right) when all
feedback is completed.
Contact Information for help:
Patricia Robertson, Reliability Compliance Manager
British Columbia Hydro and Power Authority
(604)-455-4233
Vijay Raghunathan, Senior Reliability Compliance Engineer
British Columbia Hydro and Power Authority
(604)-516-8958
Sousheela Ramsamy, Consultant
British Columbia Hydro and Power Authority
(604) 455-4215
1 Within this feedback spreadsheet, go to the tab titled ‘CIP Stnds Feedback Survey Form’ for Critical Infrastructure Protection (CIP) standards or 'OPS
Stnds Feedback Survey Form' for operations standards (highlighted in yellow) and search for your name using the filters in Columns ‘I‘ and ‘J’ to identify
Standards/requirements (Columns 'A' & ‘B’) for which you have been identified as an internal stakeholder (i.e. Compliance Leads, Primary/Secondary
Contacts, Subject Matter Experts, Managers).
NOTE: If there are errors in identified stakeholders or individuals missing, Compliance Leads are requested to coordinate as necessary and directly with
said individuals and make corrections using red text. Please also notify Reliability Compliance (Patricia Robertson, Vijay Raghunathan, and/or Sousheela
Ramsamy) of the changes made ASAP.
The majority of the 36 new and revised standards have been presented in the feedback survey form
spreadsheet on a per requirement basis to highlight new requirements for new standards and for
revised standards, significant requirement changes to currently adopted versions. This enables
stakeholders to identify specific actions, costs, and recommended implementation times on a per
requirement basis instead of providing general comments against said standards.
2
For each Standard/requirement listed in the 'CIPStnds Feedback Survey Form' or 'OPS Stnds Feedback Survey Form' tab for which you are a
stakeholder, please review each referenced FERC adopted new/revised Standard and corresponding redline (for revised standards only indicating changes
from current BCUC adopted standard versions) located in the Assessment Report No. 10 page on MRS SharePoint and provide feedback as applicable
under either Columns 'K' to 'V' of the 'CIP Stnds Feedback Survey Form' or Columns ‘K’ to 'P' of the ‘OPS Stnds Feedback Survey Form’ tabs
highlighted in yellow (see below for details):
IMPORTANT: Designated Compliance Leads identified per Column 'I' from business units (i.e. Transmission, Generation, etc.) are requested to
coordinate/collaborate with other identified Compliance Leads and Supporting Contacts per Column 'J' prior to providing feedback.
a. BC Hydro Stakeholder Comments (Column "K"): Please advise if there are no changes to BC Hydro's current processes, or if changes are
required, describe a list of high-level incremental activities required to reach compliance. Please also indicate if there are any technical/administrative
suitability issues that could impede adoption (i.e. specific NERC reporting tools or NERC membership required OR undefined processes/procedures
referenced from Standard/requirement).
b. Estimated Incremental/New Costs Associated with Revision/New Standard/requirement, if any ($) (Columns 'L' to 'U' of the 'CIP Stnds
Feedback Survey Form' tab or Columns 'L' to 'O' of the 'OPS Stnds Feedback Survey Form' tab)*, if any associated with:
- a revision to a Standard compared to the immediately preceding version currently adopted by the BCUC; or.
- the adoption of a new Standard.
Please indicate which costs are one-time versus ongoing (in dollars $), and identify the assumptions associated with each estimate (assumptions should be
documented in Column 'K' and linked with the actions identified per Column 'K'.
c. BCUC Implementation Time (Column "V" of the 'CIP Stnds Feedback Survey Form' tab or Column “P” of the 'OPS Stnds Feedback Survey
Form' tab):
Please include an assessment of the amount of time BC Hydro would reasonably require to come into compliance with the Standard/requirement once
adopted by the BCUC (i.e. 6 months from adoption, immediately after adoption, etc.). BC Hydro will use this information, in conjunction with external
stakeholder feedback, to recommend an overall implementation time for each Standard/requirement for inclusion in the Report. The BCUC will then use
this information to develop Effective Dates in BC for each Standard/requirement. Please Note: Implementation times in the U.S. have been provided
for you to use as a benchmark.
1) The ‘Compliance’ sections are to be determined by the BCUC and are not included in this
assessment.
2) The ‘Effective Date’ sections will be subject to assessment by internal BC Hydro and external
stakeholders in B.C. Please ignore the existing US dates.
Assessment Report No. 10 Standards Library
Appendix B-2
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 1 of 2
Task # Task Description Reference Files and Links
NERC Glossary of Terms Nov 28, 2016
1
Please review the NERC Glossary of Terms November 28, 2016 and provide feedback under Columns 'H', ‘I’, ‘J’, and ‘K’ of
the ‘Glossary Feedback Survey Form’ tab. For each Term assessed, please complete the following fields highlighted in
yellow: (Note the link to the right is to the complete NERC Glossary, the terms for this assessment have been duplicated in
the ‘Glossary Feedback Survey Form’ tab for your convenience.
IMPORTANT: When providing your comments in the columns below, please use the following format to allow us to follow
who has commented: First Name Last Name: Comment
a. Stakeholder Comments (Column "H"): Please provide a high-level list of activities required to mitigate/eliminate
impacts based on the revised or new Terms definitions.
b. The Estimated Incremental Cost Associated with Revised/New Term/Definition (Columns “I" and "J”), if any
associated with:
- a revision to a Term/Definition compared to the version adopted by the BCUC; or
- the adoption of a new Term/Definition.
Please indicate which costs are one-time versus ongoing (in dollars $), and identify the assumptions associated with each
estimate.
c. BCUC Implementation Time (Column “K”):
Please include an assessment of the amount of time reasonably required to come into compliance with the Term's definition
once adopted by the BCUC (i.e. 6 months from adoption, immediately after adoption, etc.). BC Hydro will use this
information to recommend an overall implementation time for inclusion in the Report.
2
Compliance Leads are requested to email the Reliability Compliance department (use the email address provided in the
column to the right) when all feedback is completed. [email protected]
Assessment Report No. 10 Standards Library
Appendix B-2
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 2 of 2
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Appendix B-3
External Stakeholder Feedback
Cost
One Time ($)
Cost
Ongoing ($)
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-4 R1
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
FERC Approved
New/Revised
Standard/Requirement
(Select the respective link
to open the Standards)
Standard Name and DescriptionCurrent BCUC Adopted Standards to
be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Functional Applicability of
FERC Approved
Standards/Requirements
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
FERC Order 786 dated 10/17/13
Docket No. RM12-1-000 and RM13-9-
000
145 FERC ¶ 61,051
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in
a cell)
US Effective Date of
FERC Order Ruling
Approving Standard(s)
(Each cell is linked to the
respective effective
dates of the FERC
Approval Ruling if
applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Stakeholder Comments Organizational Activities
and Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a
cell)
Estimated Incremental/New Costs Associated with Revision/New
Standard/Requirement, if any ($)
FERC Order No., Order Date and
Order Publication Date
(Each cell is linked to the
respective FERC Order if
applicable)
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar quarter, 12
months after applicable regulatory approval.
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
TPL-001-4 R2
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the
first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1
are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
TPL-001-4 R4
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
TPL-001-4 R3
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the
first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1
are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
NOTE: This requirement applies to the PC role
(not yet defined in BC). Only provide feedback
if necessary here.
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the
first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1
are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the
first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1
are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
TPL-001-4 R5
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC 23-Dec-2013
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
TPL-001-4 R6
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the
first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1
are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Catalyst Paper Corporation, Crofton Division (CPCD), Port Alberni Division (CPPAD), Powell River Division (CPPR) (all registered as DP only with UFLS)
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 1 of 12
Cost
One Time ($)
Cost
Ongoing ($)
TPL-001-4 R1
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
FERC Approved
New/Revised
Standard/Requirement
(Select the respective link
to open the Standards)
Standard Name and DescriptionCurrent BCUC Adopted Standards to
be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Functional Applicability of
FERC Approved
Standards/Requirements
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in
a cell)
US Effective Date of
FERC Order Ruling
Approving Standard(s)
(Each cell is linked to the
respective effective
dates of the FERC
Approval Ruling if
applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Stakeholder Comments Organizational Activities
and Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a
cell)
Estimated Incremental/New Costs Associated with Revision/New
Standard/Requirement, if any ($)
FERC Order No., Order Date and
Order Publication Date
(Each cell is linked to the
respective FERC Order if
applicable)
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar quarter, 12
months after applicable regulatory approval.
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
NOTE: This requirement applies to the PC role (not
yet defined in BC) in conjunction with the TP role.
Only provide feedback if necessary here. This
standard was originally included for assessment
under Assessment Report No. 8, but adoption was
held by the BCUC pending reassessment per Order
R-38-15. As such, this standard is now up for
reassessment.
NOTE: This requirement applies to
the PC role (not yet defined in BC) in
conjunction with the TP role. Only
provide feedback if necessary
here.
NOTE: This requirement applies to the PC
role (not yet defined in BC) in conjunction
with the TP role. Only provide feedback if
necessary here.
NOTE: This requirement applies to the PC role
(not yet defined in BC) in conjunction with the TP
role. Only provide feedback if necessary
here.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar quarter, 12
months after applicable regulatory approval.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first day of the
first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4, Table 1
are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in accordance with
Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the Faulted
element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for
assessment under Assessment Report No. 8, but
adoption was held by the BCUC pending
reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
TPL-001-4 R8
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-9-
000, Order 786; Issue Date: October
17, 2013; Publication Date: October
23, 2013
TPL-001-4 R7
Name: Transmission System Planning Performance
Requirements
Description: Establish Transmission system planning
performance requirements within the planning horizon to develop
a Bulk Electric System (BES) that will operate reliably over a broad
spectrum of System conditions and following a wide range of
probable Contingencies.
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 2 of 12
Cost
One Time ($)
Cost
Ongoing ($)
Bus-tie Breaker
*Glossary term is specific to the TPL-001-4 standard.
N/A A circuit breaker that is positioned to connect two individual substation bus configurations. New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report
No. 8, however, adoption was held by the BCUC pending further
reassessment per Order R-38-15. As such, this Glossary Term is now up for
reassessment. A separate TPL-001-4 specific report will be filed per the
BCUC's request. Please provide any feedback here.
No comments.
Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
All Load that is no longer served by the Transmission system as a result of Transmission
Facilities being removed from service by a Protection System operation designed to isolate the
fault.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report
No. 8, however, adoption was held by the BCUC pending further
reassessment per Order R-38-15. As such, this Glossary Term is now up for
reassessment. A separate TPL-001-4 specific report will be filed per the
BCUC's request. Please provide any feedback here.
No comments.
Long-Term Transmission Planning Horizon
*Glossary term is specific to the TPL-001-4 standard.
N/A
Transmission planning period that covers years six through ten or beyond when required to
accommodate any known longer lead time projects that may take longer than ten years to
complete.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report
No. 8, however, adoption was held by the BCUC pending further
reassessment per Order R-38-15. As such, this Glossary Term is now up for
reassessment. A separate TPL-001-4 specific report will be filed per the
BCUC's request. Please provide any feedback here.
No comments.
Non-Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
Non-Interruptible Load loss that does not include: (1) Consequential Load Loss, (2) the
response of voltage sensitive Load, or (3) Load that is disconnected from the System by end-
user equipment.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report
No. 8, however, adoption was held by the BCUC pending further
reassessment per Order R-38-15. As such, this Glossary Term is now up for
reassessment. A separate TPL-001-4 specific report will be filed per the
BCUC's request. Please provide any feedback here.
No comments.
Planning Assessment
*Glossary term is specific to the TPL-001-4 standard.
N/ADocumented evaluation of future Transmission System performance and Corrective Action
Plans to remedy identified deficiencies.New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report
No. 8, however, adoption was held by the BCUC pending further
reassessment per Order R-38-15. As such, this Glossary Term is now up for
reassessment. A separate TPL-001-4 specific report will be filed per the
BCUC's request. Please provide any feedback here.
No comments.
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Catalyst Paper Corporation, Crofton Division (CPCD), Port Alberni Division (CPPAD), Powell River Division (CPPR) (all registered as DP only with UFLS)
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental/New Costs Associated
with Revised/New Glossary Term and Definition if
any ($) FERC Approved New/Revised/Retired NERC Glossary of Terms from the
November 28, 2016 Glossary of Terms
Acronym
(If Available)
FERC Approved New/Revised NERC Term Definitions against Terms and Definitions
listed in Columns "E" and "F"
(changes to definition indicated by red text; deletions are not indicated)
Current BCUC Adopted Terms from
December 7, 2015 Glossary of Terms
(Column "B")
Current BCUC Adopted
Definition from December 7, 2015
Glossary of Terms
FERC Approval Date of
New/Revised/Retired NERC
Term and Definition
Effective Date of
New/Revised/Retired NERC
Term and Definition in
United States
Stakeholder Comments
(Press Alt-Enter to insert a carriage return in a cell)
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 3 of 12
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
FortisBC Inc. (TO, TOP, GO, GOP, PSE, LSE, DP, RP, TP, TSP)
Cost
One Time ($)
Cost
Ongoing ($)
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
See TPL-001-4, R1.
TPL-001-4 R7
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first
calendar quarter, 12 months after applicable regulatory approval.
NOTE: This requirement applies to the PC role (not yet defined in BC)
in conjunction with the TP role. Only provide feedback if necessary here.
This standard was originally included for assessment under
Assessment Report No. 8, but adoption was held by the BCUC
pending reassessment per Order R-38-15. As such, this standard
is now up for reassessment.
NOTE: This requirement
applies to the PC role (not
yet defined in BC) in
conjunction with the TP
role. Only provide
feedback if necessary
here.
NOTE: This requirement
applies to the PC role (not
yet defined in BC) in
conjunction with the TP
role. Only provide
feedback if necessary
here.
NOTE: This requirement applies to the PC role
(not yet defined in BC) in conjunction with the TP role.
Only provide feedback if necessary here.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events
identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of
Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be
permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1.
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
TPL-001-4 R6
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
TPL-001-4 R5
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC 23-Dec-2013
TPL-001-4 R4
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
See TPL-001-4, R1.
TPL-001-4 R3
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events
identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of
Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be
permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events
identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of
Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be
permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1.TPL-001-4 R2
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
Recommended effective date is 24 - 36 months after
BCUC approval.23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first
calendar quarter, 12 months after applicable regulatory approval.
Studies using short circuit models with any planned generation and
transmission facilities in service which could impact the study area will
need to be developed and maintained.
Minor modifications to the annual FortisBC planning study will be
required and a new short circuit analyses will be required annually.
30,000-50,0000 15,000-20,000TPL-001-4 R1
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
FERC Order No., Order Date and
Order Publication Date
(Each cell is linked to the
respective FERC Order if
applicable)
FERC Approved
New/Revised
Standard/Requirement
(Select the respective link
to open the Standards)
Standard Name and Description
Current BCUC Adopted
Standards to be
Superseded
FERC Approved Revision(s) to Standard/Requirement listed in
Standard Version History
Functional Applicability of FERC
Approved
Standards/Requirements
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
US Effective Date of
FERC Order Ruling
Approving Standard(s)
(Each cell is linked to the
respective effective
dates of the FERC
Approval Ruling if
applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement
Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Stakeholder Comments Organizational Activities and
Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental/New Costs Associated with
Revision/New Standard/Requirement, if any ($)
See TPL-001-4, R1.
See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1.
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
FERC Order 786 dated 10/17/13
Docket No. RM12-1-000 and RM13-
9-000
145 FERC ¶ 61,051
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events
identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of
Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be
permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
See TPL-001-4, R1.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events
identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of
Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be
permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1.
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 4 of 12
Cost
One Time ($)
Cost
Ongoing ($)
Recommended effective date is 24 - 36 months after
BCUC approval.23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first
calendar quarter, 12 months after applicable regulatory approval.
Studies using short circuit models with any planned generation and
transmission facilities in service which could impact the study area will
need to be developed and maintained.
Minor modifications to the annual FortisBC planning study will be
required and a new short circuit analyses will be required annually.
30,000-50,0000 15,000-20,000TPL-001-4 R1
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
FERC Order No., Order Date and
Order Publication Date
(Each cell is linked to the
respective FERC Order if
applicable)
FERC Approved
New/Revised
Standard/Requirement
(Select the respective link
to open the Standards)
Standard Name and Description
Current BCUC Adopted
Standards to be
Superseded
FERC Approved Revision(s) to Standard/Requirement listed in
Standard Version History
Functional Applicability of FERC
Approved
Standards/Requirements
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
US Effective Date of
FERC Order Ruling
Approving Standard(s)
(Each cell is linked to the
respective effective
dates of the FERC
Approval Ruling if
applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement
Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Stakeholder Comments Organizational Activities and
Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental/New Costs Associated with
Revision/New Standard/Requirement, if any ($)
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
See TPL-001-4, R1.23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on
the first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events
identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of
Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be
permitted by the requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by
the Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
See TPL-001-4, R1. See TPL-001-4, R1. See TPL-001-4, R1.TPL-001-4 R8
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad spectrum of System conditions
and following a wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes merging and
upgrading requirements of TPL-001-0, TPL-002-0, TPL-003-0, and TPL-
004-0 into one, single, comprehensive, coordinated standard: TPL-001-2;
and retirement of TPL-005-0 and TPL-006-0.
TP, PC
Docket No. RM12-1-000 and RM13-
9-000, Order 786; Issue Date:
October 17, 2013; Publication Date:
October 23, 2013
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 5 of 12
Cost
One Time ($)
Cost
Ongoing ($)
Bus-tie Breaker
*Glossary term is specific to the TPL-001-4 standard.
N/A A circuit breaker that is positioned to connect two individual substation bus configurations. New N/A 17-Oct-13 01-Jan-15No additional comments. Please see comments provided to each respective
standard in the Standards feedback survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments. Please see comments
provided to each respective standard in the
Standards feedback survey form.
Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
All Load that is no longer served by the Transmission system as a result of Transmission
Facilities being removed from service by a Protection System operation designed to isolate
the fault.
New N/A 17-Oct-13 01-Jan-15No additional comments. Please see comments provided to each respective
standard in the Standards feedback survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments. Please see comments
provided to each respective standard in the
Standards feedback survey form.
Long-Term Transmission Planning Horizon
*Glossary term is specific to the TPL-001-4 standard.
N/A
Transmission planning period that covers years six through ten or beyond when required to
accommodate any known longer lead time projects that may take longer than ten years to
complete.
New N/A 17-Oct-13 01-Jan-15No additional comments. Please see comments provided to each respective
standard in the Standards feedback survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments. Please see comments
provided to each respective standard in the
Standards feedback survey form.
Non-Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
Non-Interruptible Load loss that does not include: (1) Consequential Load Loss, (2) the
response of voltage sensitive Load, or (3) Load that is disconnected from the System by end-
user equipment.
New N/A 17-Oct-13 01-Jan-15No additional comments. Please see comments provided to each respective
standard in the Standards feedback survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments. Please see comments
provided to each respective standard in the
Standards feedback survey form.
Planning Assessment
*Glossary term is specific to the TPL-001-4 standard.
N/ADocumented evaluation of future Transmission System performance and Corrective Action
Plans to remedy identified deficiencies.New N/A 17-Oct-13 01-Jan-15
No additional comments. Please see comments provided to each respective
standard in the Standards feedback survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments.
Please see comments
provided to each
respective standard in the
Standards feedback
survey form.
No additional comments. Please see comments
provided to each respective standard in the
Standards feedback survey form.
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
FortisBC Inc. (TO, TOP, GO, GOP, PSE, LSE, DP, RP, TP, TSP)
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental/New Costs Associated
with Revised/New Glossary Term and Definition
if any ($) FERC Approved New/Revised/Retired NERC Glossary of Terms from
the November 28, 2016 Glossary of Terms
Acronym
(If Available)
FERC Approved New/Revised NERC Term Definitions against Terms and Definitions
listed in Columns "E" and "F"
(changes to definition indicated by red text; deletions are not indicated)
Current BCUC Adopted Terms from
December 7, 2015 Glossary of Terms
(Column "B")
Current BCUC Adopted
Definition from December 7, 2015
Glossary of Terms
FERC Approval Date of
New/Revised/Retired NERC Term
and Definition
Effective Date of
New/Revised/Retired NERC
Term and Definition in
United States
Stakeholder Comments
(Press Alt-Enter to insert a carriage return in a cell)
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 6 of 12
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Cost
One Time ($)
Cost
Ongoing ($)
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
N/A
TPL-001-4 R7
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar
quarter, 12 months after applicable regulatory approval.
NOTE: This requirement applies to the PC role (not yet defined
in BC) in conjunction with the TP role. Only provide feedback
if necessary here. This standard was originally included for
assessment under Assessment Report No. 8, but adoption was
held by the BCUC pending reassessment per Order R-38-15. As
such, this standard is now up for reassessment.
NOTE: This requirement
applies to the PC role (not yet
defined in BC) in conjunction
with the TP role. Only
provide feedback if
necessary here.
NOTE: This requirement
applies to the PC role (not
yet defined in BC) in
conjunction with the TP role.
Only provide feedback if
necessary here.
NOTE: This requirement applies to the PC role (not yet
defined in BC) in conjunction with the TP role. Only
provide feedback if necessary here.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first
day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4,
Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in
accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-
001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
0 0
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
TPL-001-4 R6
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
0 0
00TPL-001-4 R5
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC 23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first
day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4,
Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in
accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-
001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first
day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4,
Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in
accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-
001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment.
TPL-001-4 R4
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
N/A
TPL-001-4 R3
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first
day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4,
Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in
accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-
001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
0 0
NOTE: This requirement applies to the PC role (not yet
defined in BC). Only provide feedback if necessary
here.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first
day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4,
Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in
accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-
001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
0 0TPL-001-4 R2
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
N/A23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar
quarter, 12 months after applicable regulatory approval.
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
0 0TPL-001-4 R1
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
N/A
N/A
Docket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
FERC Order 786 dated 10/17/13
Docket No. RM12-1-000 and RM13-9-000
145 FERC ¶ 61,051
NORTHWOOD PULP MILL - CANFOR PULP LIMITED PARTNERSHIP (DP)
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
US Effective Date of FERC Order Ruling
Approving Standard(s)
(Each cell is linked to the respective effective
dates of the FERC Approval Ruling if
applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)Stakeholder Comments Organizational Activities and
Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental/New Costs Associated with
Revision/New Standard/Requirement, if any ($) FERC Order No., Order Date and Order Publication
Date
(Each cell is linked to the respective FERC Order if
applicable)
FERC Approved
New/Revised
Standard/Requirement
(Select the respective link
to open the Standards)
Standard Name and DescriptionCurrent BCUC Adopted Standards to
be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Functional Applicability of FERC
Approved
Standards/Requirements
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 7 of 12
Cost
One Time ($)
Cost
Ongoing ($)
N/A23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar
quarter, 12 months after applicable regulatory approval.
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
0 0TPL-001-4 R1
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
US Effective Date of FERC Order Ruling
Approving Standard(s)
(Each cell is linked to the respective effective
dates of the FERC Approval Ruling if
applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)Stakeholder Comments Organizational Activities and
Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return in a cell)
Estimated Incremental/New Costs Associated with
Revision/New Standard/Requirement, if any ($) FERC Order No., Order Date and Order Publication
Date
(Each cell is linked to the respective FERC Order if
applicable)
FERC Approved
New/Revised
Standard/Requirement
(Select the respective link
to open the Standards)
Standard Name and DescriptionCurrent BCUC Adopted Standards to
be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Functional Applicability of FERC
Approved
Standards/Requirements
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
N/A23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the first
day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory approval,
Corrective Action Plans applying to the following categories of Contingencies and events identified in TPL-001-4,
Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission Service (in
accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the requirements of TPL-
001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included for assessment
under Assessment Report No. 8, but adoption was held by the
BCUC pending reassessment per Order R-38-15. As such, this
standard is now up for reassessment. N/A to DP
0 0TPL-001-4 R8
Name: Transmission System Planning Performance Requirements
Description: Establish Transmission system planning performance
requirements within the planning horizon to develop a Bulk Electric
System (BES) that will operate reliably over a broad spectrum of
System conditions and following a wide range of probable
Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date: October
23, 2013
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 8 of 12
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Cost
One Time ($)
Cost
Ongoing ($)
Bus-tie Breaker
*Glossary term is specific to the TPL-001-4 standard.
N/A A circuit breaker that is positioned to connect two individual substation bus configurations. New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report No. 8,
however, adoption was held by the BCUC pending further reassessment per Order R-
38-15. As such, this Glossary Term is now up for reassessment. A separate TPL-001-
4 specific report will be filed per the BCUC's request. Please provide any feedback
here.
N/A to DP
0 0 N/A
Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
All Load that is no longer served by the Transmission system as a result of Transmission
Facilities being removed from service by a Protection System operation designed to isolate the
fault.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report No. 8,
however, adoption was held by the BCUC pending further reassessment per Order R-
38-15. As such, this Glossary Term is now up for reassessment. A separate TPL-001-
4 specific report will be filed per the BCUC's request. Please provide any feedback
here.
Long-Term Transmission Planning Horizon
*Glossary term is specific to the TPL-001-4 standard.
N/A
Transmission planning period that covers years six through ten or beyond when required to
accommodate any known longer lead time projects that may take longer than ten years to
complete.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report No. 8,
however, adoption was held by the BCUC pending further reassessment per Order R-
38-15. As such, this Glossary Term is now up for reassessment. A separate TPL-001-
4 specific report will be filed per the BCUC's request. Please provide any feedback
here.
N/A to DP
0 0 N/A
Non-Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
Non-Interruptible Load loss that does not include: (1) Consequential Load Loss, (2) the
response of voltage sensitive Load, or (3) Load that is disconnected from the System by end-
user equipment.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report No. 8,
however, adoption was held by the BCUC pending further reassessment per Order R-
38-15. As such, this Glossary Term is now up for reassessment. A separate TPL-001-
4 specific report will be filed per the BCUC's request. Please provide any feedback
here. No change
0 0 Immediately after
adoption
Planning Assessment
*Glossary term is specific to the TPL-001-4 standard.
N/ADocumented evaluation of future Transmission System performance and Corrective Action
Plans to remedy identified deficiencies.New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under Assessment Report No. 8,
however, adoption was held by the BCUC pending further reassessment per Order R-
38-15. As such, this Glossary Term is now up for reassessment. A separate TPL-001-
4 specific report will be filed per the BCUC's request. Please provide any feedback
here.
N/A to DP
0 0 N/A
BCUC
Implementation Time
(Press Alt-Enter to
insert a carriage return
in a cell)
NORTHWOOD PULP MILL - CANFOR PULP LIMITED PARTNERSHIP (DP)
Estimated Incremental/New Costs
Associated with Revised/New Glossary
Term and Definition if any ($) FERC Approved New/Revised/Retired NERC Glossary of Terms from the
November 28, 2016 Glossary of Terms
Acronym
(If Available)
FERC Approved New/Revised NERC Term Definitions against Terms and Definitions
listed in Columns "E" and "F"
(changes to definition indicated by red text; deletions are not indicated)
Current BCUC Adopted Terms from
December 7, 2015
Glossary of Terms
(Column "B")
Current BCUC Adopted
Definition from December 7, 2015
Glossary of Terms
FERC Approval Date of
New/Revised/Retired NERC Term
and Definition
Effective Date of
New/Revised/Retired NERC
Term and Definition in United
States
Stakeholder Comments
(Press Alt-Enter to insert a carriage return in a cell)
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 9 of 12
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Cost
One Time ($)
Cost
Ongoing ($)
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
Docket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
FERC Order 786 dated 10/17/13
Docket No. RM12-1-000 and RM13-9-000
145 FERC ¶ 61,051
Teck Metals Ltd. (TO, TOP, GO, GOP)
BCUC Implementation Time
(Press Alt-Enter to insert a
carriage return in a cell)
US Effective Date of FERC Order Ruling Approving
Standard(s)
(Each cell is linked to the respective effective dates
of the FERC Approval Ruling if applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Stakeholder Comments Organizational
Activities and Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return
in a cell)
Estimated Incremental/New Costs Associated with
Revision/New Standard/Requirement, if any ($) FERC Order No., Order Date and Order Publication
Date
(Each cell is linked to the respective FERC Order if
applicable)
FERC Approved
New/Revised
Standard/Requirement
(Select the respective
link to open the
Standards)
Standard Name and DescriptionCurrent BCUC Adopted Standards to
be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Functional Applicability of FERC Approved
Standards/Requirements
TPL-001-4 R1
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar
quarter, 12 months after applicable regulatory approval.
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
TPL-001-4 R2
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the
first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in
TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission
Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
TPL-001-4 R4
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC
TPL-001-4 R3
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the
first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in
TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission
Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
NOTE: This requirement
applies to the PC role (not yet
defined in BC). Only provide
feedback if necessary here.
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the
first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in
TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission
Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the
first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in
TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission
Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
TPL-001-4 R5
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PC 23-Dec-2013
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
TPL-001-4 R6
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the
first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in
TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission
Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 10 of 12
Cost
One Time ($)
Cost
Ongoing ($)
BCUC Implementation Time
(Press Alt-Enter to insert a
carriage return in a cell)
US Effective Date of FERC Order Ruling Approving
Standard(s)
(Each cell is linked to the respective effective dates
of the FERC Approval Ruling if applicable)
FERC Approved Standard/Requirement Implementation Time Provided and US Enforcement Date
(Each cell is linked to the respective implementation plan and effective dates if applicable)
Stakeholder Comments Organizational
Activities and Reliability/Suitability Impact
(Press Alt-Enter to insert a carriage return
in a cell)
Estimated Incremental/New Costs Associated with
Revision/New Standard/Requirement, if any ($) FERC Order No., Order Date and Order Publication
Date
(Each cell is linked to the respective FERC Order if
applicable)
FERC Approved
New/Revised
Standard/Requirement
(Select the respective
link to open the
Standards)
Standard Name and DescriptionCurrent BCUC Adopted Standards to
be Superseded
FERC Approved Revision(s) to
Standard/Requirement listed in Standard Version
History
Functional Applicability of FERC Approved
Standards/Requirements
TPL-001-4 R1
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar
quarter, 12 months after applicable regulatory approval.
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-0.1
TPL-002-0b
TPL-003-0b
TPL-004-0a
TPL-001-4 R7
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013Requirements R1 and R7 as well as the definitions shall become effective on the first day of the first calendar
quarter, 12 months after applicable regulatory approval.
NOTE: This requirement applies to the PC role
(not yet defined in BC) in conjunction with the
TP role. Only provide feedback if necessary
here. This standard was originally included for
assessment under Assessment Report No. 8,
but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
NOTE: This requirement
applies to the PC role (not yet
defined in BC) in conjunction
with the TP role. Only provide
feedback if necessary here.
NOTE: This requirement
applies to the PC role (not yet
defined in BC) in conjunction
with the TP role. Only
provide feedback if
necessary here.
NOTE: This requirement
applies to the PC role (not yet
defined in BC) in conjunction
with the TP role. Only provide
feedback if necessary here.
TPL-001-4 R8
Name: Transmission System Planning
Performance Requirements
Description: Establish Transmission system
planning performance requirements within the
planning horizon to develop a Bulk Electric System
(BES) that will operate reliably over a broad
spectrum of System conditions and following a
wide range of probable Contingencies.
4 - Complete revision. Revision of TPL-001-1; includes
merging and upgrading requirements of TPL-001-0, TPL-
002-0, TPL-003-0, and TPL-004-0 into one, single,
comprehensive, coordinated standard: TPL-001-2; and
retirement of TPL-005-0 and TPL-006-0.
TP, PCDocket No. RM12-1-000 and RM13-9-000, Order 786;
Issue Date: October 17, 2013; Publication Date:
October 23, 2013
23-Dec-2013
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become effective on the
first day of the first calendar quarter, 24 months after applicable regulatory approval.
For 84 calendar months beginning the first day of the first calendar quarter following applicable regulatory
approval, Corrective Action Plans applying to the following categories of Contingencies and events identified in
TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss and curtailment of Firm Transmission
Service (in accordance with Requirement R2, Part 2.7.3.) that would not otherwise be permitted by the
requirements of TPL-001-4:
- P1-2 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P1-3 (for controlled interruption of electric supply to local network customers connected to or supplied by the
Faulted element)
- P2-1
- P2-2 (above 300 kV)
- P2-3 (above 300 kV)
- P3-1 through P3-5
- P4-1 through P4-5 (above 300 kV)
- P5 (above 300 kV)
NOTE: This standard was originally included
for assessment under Assessment Report No.
8, but adoption was held by the BCUC pending
reassessment per Order R-38-15. As such,
this standard is now up for reassessment.
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 11 of 12
Disclaimer: This information has been prepared as input into BC Hydro's tenth assessment report on Mandatory Reliability Standards and is based on information available to BC Hydro as of the date sent. It should not be relied upon for any other purpose.
Cost
One Time ($)
Cost
Ongoing ($)
Bus-tie Breaker
*Glossary term is specific to the TPL-001-4 standard.
N/A A circuit breaker that is positioned to connect two individual substation bus configurations. New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under
Assessment Report No. 8, however, adoption was held by the
BCUC pending further reassessment per Order R-38-15. As
such, this Glossary Term is now up for reassessment. A
separate TPL-001-4 specific report will be filed per the BCUC's
request. Please provide any feedback here.
No comments.
Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
All Load that is no longer served by the Transmission system as a result of Transmission
Facilities being removed from service by a Protection System operation designed to isolate the
fault.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under
Assessment Report No. 8, however, adoption was held by the
BCUC pending further reassessment per Order R-38-15. As
such, this Glossary Term is now up for reassessment. A
separate TPL-001-4 specific report will be filed per the BCUC's
request. Please provide any feedback here.
No comments.
Long-Term Transmission Planning Horizon
*Glossary term is specific to the TPL-001-4 standard.
N/A
Transmission planning period that covers years six through ten or beyond when required to
accommodate any known longer lead time projects that may take longer than ten years to
complete.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under
Assessment Report No. 8, however, adoption was held by the
BCUC pending further reassessment per Order R-38-15. As
such, this Glossary Term is now up for reassessment. A
separate TPL-001-4 specific report will be filed per the BCUC's
request. Please provide any feedback here.
No comments.
Non-Consequential Load Loss
*Glossary term is specific to the TPL-001-4 standard.
N/A
Non-Interruptible Load loss that does not include: (1) Consequential Load Loss, (2) the
response of voltage sensitive Load, or (3) Load that is disconnected from the System by end-
user equipment.
New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under
Assessment Report No. 8, however, adoption was held by the
BCUC pending further reassessment per Order R-38-15. As
such, this Glossary Term is now up for reassessment. A
separate TPL-001-4 specific report will be filed per the BCUC's
request. Please provide any feedback here.
No comments.
Planning Assessment
*Glossary term is specific to the TPL-001-4 standard.
N/ADocumented evaluation of future Transmission System performance and Corrective Action
Plans to remedy identified deficiencies.New N/A 17-Oct-13 01-Jan-15
NOTE: This Glossary Term was included initially under
Assessment Report No. 8, however, adoption was held by the
BCUC pending further reassessment per Order R-38-15. As
such, this Glossary Term is now up for reassessment. A
separate TPL-001-4 specific report will be filed per the BCUC's
request. Please provide any feedback here.
No comments.
BCUC Implementation Time
(Press Alt-Enter to insert a carriage return in a cell)
Teck Metals Ltd. (TO, TOP, GO, GOP)
Estimated Incremental/New Costs Associated with
Revised/New Glossary Term and Definition if any ($) FERC Approved New/Revised/Retired NERC Glossary of Terms from the
November 28, 2016 Glossary of Terms
Acronym
(If Available)
FERC Approved New/Revised NERC Term Definitions against Terms and Definitions
listed in Columns "E" and "F"
(changes to definition indicated by red text; deletions are not indicated)
Current BCUC Adopted Terms from
December 7, 2015 Glossary of Terms
(Column "B")
Current BCUC Adopted
Definition from December 7, 2015
Glossary of Terms
FERC Approval
Date of
New/Revised/Re
tired NERC
Term and
Definition
Effective Date of
New/Revised/Re
tired NERC Term
and Definition in
United States
Stakeholder Comments
(Press Alt-Enter to insert a carriage return in a cell)
Appendix B-3
Mandatory Reliability Standard TPL-001-4 Assessment Report
Page 12 of 12
BC Hydro Mandatory Reliability Standard TPL-001-4 Assessment Report
Appendix C
Draft Order
Sixth floor, 900 Howe Street Vancouver, BC Canada V6Z 2N3 TEL: (604) 660-4700 BC Toll Free: 1-800-663-1385 FAX: (604) 660-1102
…/2
ORDER NUMBER R-xx-xx
IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473
and
British Columbia Hydro and Power Authority (BC Hydro)
Mandatory Reliability Standards TPL-001-4 Assessment Report
BEFORE: Commissioner Commissioner Commissioner
on Date
ORDER
WHEREAS:
A. Pursuant to section 125.2(2) of the Utilities Commission Act (UCA) the British Columbia Utilities Commission (Commission) has exclusive jurisdiction to determine whether a “reliability standard” as defined in the UCA, is in the public interest and should be adopted in British Columbia (BC);
B. The Rules of Procedure for Reliability Standards in BC, adopted by Commission Order G-123-09, dated October 15, 2009, and amended by Commission Order R-12-17, states that a reliability standard does not include Compliance Provisions and defines Compliance Provisions as “the compliance-related provisions that accompany, but do not constitute part of, a Commission adopted Reliability Standard”;
C. In order to facilitate the Commission’s consideration of reliability standards, British Columbia Hydro and Power Authority (BC Hydro) is required under section 125.2(3) of the UCA to review each reliability standard established by a standard-making body such as the North American Electric Reliability Corporation (NERC) and the Western Electricity Coordinating Council (WECC) and provide the Commission with a report (MRS Assessment Report) assessing:
(a) any adverse impact of the reliability standard on the reliability of electricity transmission in BC if the
reliability standard were adopted;
(b) the suitability of the reliability standard for B.C.;
(c) the potential cost of the reliability standard if it were adopted;
(c.1) the application of the reliability standard to persons or persons in respect of specified
equipment if the reliability standard were adopted; and
(d) any other matter prescribed by regulation or identified by order of the Commission;
Order R-xx-xx Page 2 of 4
Filepath
D. Compliance Provisions, including effective dates, are not assessed by BC Hydro. This approach is consistent with that taken in previous Mandatory Reliability Standards (MRS) Assessment Reports;
E. On May 3, 2017, BC Hydro filed the TPL-001-4 Assessment Report (Report) assessing the revised TPL-001-4 reliability standard. BC Hydro assessed the reliability standards excluding the accompanying Compliance Provision. If adopted, the TPL-001-4 revised reliability standard would supersede the existing reliability standards previously adopted by the Commission;
F. The TPL-001-4 reliability standard assessed by BC Hydro in the Report are based on defined terms contained in the NERC Glossary of Terms Used in Reliability Standards dated November 28, 2016 (NERC Glossary). The Report included an assessment of five new defined glossary terms intended for the TPL-001-4 reliability standard (Glossary Terms);
G. To date, BC Hydro has acted as the Planning Authority/Planning Coordinator (PA/PC) for the BC Hydro asset footprint only. The PA/PC responsibilities for the province require clarification at this time. TPL-001-4 considered in the Report contains requirement 7 that pertains to the PC function and BC Hydro recommends that requirement 7 of the revised TPL-001-4 reliability standard be held in abeyance and be of no force or effect in BC until the PC function is resolved;
H. In the Report, BC Hydro concludes that the TPL-001-4 reliability standard, with the exception of requirement 7, and five Glossary Terms are suitable for adoption in B.C. at this time;
I. By Commission Order R–xx-17 dated xxxx, 2017, BC Hydro was directed to publish a Notice of Mandatory Reliability Standard TPL-001-4 Assessment Report and Process for Public Comments and established the Regulatory Timetable for a public comment process;
J. Comments were received from xxxxxxxx;
K. On xxxx, 2017 BC Hydro provided comments in response;
L. Pursuant to section 125.2(6) of the UCA, the Commission must adopt the reliability standard(s) addressed in the Report if the Commission considers that the reliability sandard(s) are required to maintain or achieve consistency in BC with other jurisdictions that have adopted the reliablity standard(s);
M. The Commission has reviewed and considered the Report, the TPL-001-4 reliability standard and Glossary Terms assessed therein, as well as the comments received and considers that the adoption of the recommendations in the Report is warranted; and
N. Although not assessed by BC Hydro, the Commission considers that the Compliance Provisions of the reliability standards should be adopted to maintain compliance monitoring consistency with other jurisdictions that have adopted the reliability standards with the Compliance Provisions and finds it appropriate to provide effective dates for entities to come into compliance with the TPL-001-4 reliability standard and Glossary Terms adopted in this order.
Order R-xx-xx Page 3 of 4
Filepath
NOW THEREFORE pursuant to subsections 125.2(6) and 125.2(10) of the Utilities Commission Act, the British Columbia Utilities Commission (Commission) orders as follows:
1. The Commission adopts the TPL-001-4 reliability standard recommended for adoption in the British Columbia Hydro and Power Authority Mandatory Reliability Standard TPL-001-4 Assessment Report with effective dates in Table 1 of Attachment A to this order and each reliability standard to be superseded by the TPL-001-4 reliability standard adopted in this order shall remain in effect until the effective date of the TPL-001-4 reliability standard superseding it.
2. As a result of this order and previous Commission orders, all the reliability standards listed in Attachment B to this order are in effect in British Columbia (BC) as of the dates shown. The effective dates for the reliability standards listed in Attachment B supersede the effective dates that were included in any similar list appended to any previous order. Attachment B to this order also includes those reliability standards with effective dates held in abeyance to be assessed at a later date.
3. Individual requirements within reliability standards that incorporate, by reference, reliability standards that have not been adopted by the Commission, are of no force and effect in BC.
4. Individual requirements or sub-requirements within reliability standards, which the Commission has adopted but for which the Commission has not determined an effective date, are of no force and effect in BC.
5. The Commission adopts the North American Electric Reliability Corporation (NERC) Glossary of Terms Used in TPL-001-4 reliability standard, found in Attachment C to this order, to define terms employed in the TPL-001-4 reliability standard (Glossary Terms). The effective date of each of the new Glossary Terms adopted in this order is the date in Table 2 of Attachment A to this order.
6. As a result of this order and previous Commission orders, the Glossary Terms listed in Attachment D to this order are Glossary Terms in effect in BC as of the effective dates indicated. The effective dates for the Glossary Terms listed in Attachment D supersede the effective dates that were included in any similar list appended to any previous order.
7. The Commission adopts the Compliance Provisions as defined in the Rules of Procedure for Reliability Standards in British Columbia, that accompany each of the adopted reliability standards, in the form directed by the Commission and as amended from time to time.
8. The reliability standards adopted in BC by the Commission will be posted on the Western Electricity Coordinating Council website with a link from the Commission website.
9. The Commission confirms that entities subject to Mandatory Reliability Standards are required to report to the Commission and may, on a voluntary basis, report to NERC as an Electric Reliability Organization or to the Federal Energy Regulatory Commission.
10. The reliability standards are adopted as set out in Attachment X to this order.
Order R-xx-xx Page 4 of 4
Filepath
DATED at the City of Vancouver, in the Province of British Columbia, this (XX) day of (Month Year).
BY ORDER
(X. X. last name) Commissioner
Attachment Options
Ta
ble
1
Bri
tis
h C
olu
mb
ia U
tiliti
es
Co
mm
iss
ion
Re
lia
bilit
y
Sta
nd
ard
s w
ith
Eff
ec
tive
Da
tes
as
Ad
op
ted
Sta
nd
ard
S
tan
dar
d N
ame
Eff
ecti
ve D
ate
Typ
e C
om
mis
sio
n A
pp
rove
d
Sta
nd
ard
(s)
Bei
ng
S
up
erse
ded
1
TP
L-00
1-4
Tra
nsm
issi
on S
yste
m P
lann
ing
Per
form
ance
Req
uire
men
ts
R1:
Firs
t day
of f
irst c
alen
dar
quar
ter,
two
year
s af
ter
BC
UC
ado
ptio
n.
R2-
R6,
R8:
Firs
t day
of f
irst c
alen
dar
quar
ter,
thre
e ye
ars
afte
r B
CU
C
adop
tion.
For
84
cale
ndar
mon
ths
begi
nnin
g th
e fir
st d
ay o
f the
firs
t cal
enda
r qu
arte
r fo
llow
ing
BC
UC
app
rova
l, C
orre
ctiv
e A
ctio
n P
lans
app
lyin
g to
th
e fo
llow
ing
cate
gorie
s of
Con
tinge
ncie
s an
d ev
ents
iden
tifie
d in
T
PL-
001-
4, T
able
1 a
re a
llow
ed to
incl
ude
Non
-Con
sequ
entia
l Loa
d Lo
ss a
nd c
urta
ilmen
t of F
irm T
rans
mis
sion
Ser
vice
(in
acc
orda
nce
with
R
equi
rem
ent R
2, P
art 2
.7.3
.) th
at w
ould
not
oth
erw
ise
be p
erm
itted
by
the
requ
irem
ents
of T
PL-
001-
4:
- P
1-2
(for
con
trol
led
inte
rrup
tion
of e
lect
ric s
uppl
y to
loca
l net
wor
k cu
stom
ers
conn
ecte
d to
or
supp
lied
by th
e F
aulte
d el
emen
t)
- P
1-3
(for
con
trol
led
inte
rrup
tion
of e
lect
ric s
uppl
y to
loca
l net
wor
k cu
stom
ers
conn
ecte
d to
or
supp
lied
by th
e F
aulte
d el
emen
t)
- P
2-1
- P
2-2
(abo
ve 3
00 k
V)
- P
2-3
(abo
ve 3
00 k
V)
- P
3-1
thro
ugh
P3-
5
- P
4-1
thro
ugh
P4-
5 (a
bove
300
kV
)
- P
5 (a
bove
300
kV
)
R7:
Ado
ptio
n he
ld in
abe
yanc
e at
this
tim
e.2
Rev
ised
TP
L-00
1-0.
1
TP
L-00
2-0b
TP
L-00
3-0b
TP
L-00
4-0a
1
Com
mis
sio
n a
ppro
ved r
elia
bili
ty s
tandard
(s)
to b
e s
up
ers
ed
ed b
y t
he r
evis
ed r
elia
bili
ty s
tand
ard
assesse
d.
2
Una
ble
to a
sse
ss b
ased o
n u
ndefin
ed P
lann
ing C
oord
inato
r/P
lannin
g A
uth
ority
fo
otp
rints
and e
ntities r
esp
on
sib
le.
Ta
ble
2
Bri
tis
h C
olu
mb
ia U
tiliti
es
Co
mm
iss
ion
NE
RC
G
los
sa
ry T
erm
s w
ith
Eff
ec
tive
Da
tes
as
Ad
op
ted
NE
RC
Glo
ssar
y T
erm
1 E
ffec
tive
Dat
e C
om
mis
sio
n A
pp
rove
d T
erm
to
be
Rep
lace
d o
r R
etir
ed
Bus
-tie
Bre
aker
A
lign
with
the
earli
est e
ffect
ive
date
of
TP
L-00
1-4
New
Ter
m
Con
sequ
entia
l Loa
d Lo
ss
Alig
n w
ith th
e ea
rlies
t effe
ctiv
e da
te o
f T
PL-
001-
4 N
ew T
erm
Long
-Ter
m T
rans
mis
sion
Pla
nnin
g H
oriz
on
Alig
n w
ith th
e ea
rlies
t effe
ctiv
e da
te o
f T
PL-
001-
4 N
ew T
erm
Non
-Con
sequ
entia
l Loa
d Lo
ss
Alig
n w
ith th
e ea
rlies
t effe
ctiv
e da
te o
f T
PL-
001-
4 N
ew T
erm
Pla
nnin
g A
sses
smen
t A
lign
with
the
earli
est e
ffect
ive
date
of
TP
L-00
1-4
New
Ter
m
1
FE
RC
appro
ved term
s in the N
ER
C G
lossary
of
Term
s a
s o
f N
ovem
ber
28,
2016.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
BAL-001-2 Real Power Balancing Control Performance
R-14-16 July 1, 2016
BAL-002-11 Disturbance Control Performance R-41-13 December 12, 2013
BAL-002-2
Disturbance Control Standard – Contingency Reserve for Recovery from a Balancing Contingency Event
BAL-002-WECC-21 Contingency Reserve R-32-14 October 1, 2014
BAL-002-WECC-2a Contingency Reserve
BAL-003-1.1 Frequency Response and Frequency Bias Setting
R-32-16 October 1, 2016
BAL-004-0 Time Error Correction G-67-09 November 1, 2010
BAL-004-WECC-2 Automatic Time Error Correction R-32-14 October 1, 2014
BAL-005-0.2b Automatic Generation Control R-41-13 December 12, 2013 R2: Retired January 21, 20142
BAL-006-2 Inadvertent Interchange R-1-13 April 15, 2013
CIP-002-31 Cyber Security – Critical Cyber Asset Identification
G-162-11 July 1, 2012
CIP-002-5.1 Cyber Security – BES Cyber System Categorization
R-38-15 October 1, 2018
CIP-003-31, 3, 4 Cyber Security – Security Management Controls
G-162-11
July 1, 2012 R1.2, R3, R3.1, R3.2, R3.3, and R4.2: Retired January 21, 20142
CIP-003-51 Cyber Security – Security Management Controls
R-38-15 October 1, 2018
1 Reliability standard is superseded by the revised/replacement reliability standard listed immediately below it as of the
effective date(s) of the revised/replacement reliability standard. 2 On November 21, 2013, FERC Order 788 (referred to as Paragraph 81) approved the retiring of the reliability standard
requirements. 3 Reliability standard is superseded by CIP-010-1 as of the CIP-010-1 effective date. 4 Reliability standard is superseded by CIP-011-1 as of the CIP-011-1 effective date.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
CIP-003-6 Cyber Security — Security Management Controls
Adoption held in abeyance at this time5
CIP-004-3a1 Cyber Security - Personnel & Training
R-32-14 August 1, 2014
CIP-004-5.11 Cyber Security – Personnel & Training
R-38-15 October 1, 2018
CIP-004-6 Cyber Security — Personnel & Training
CIP-005-3a1, 3 Cyber Security – Electronic Security Perimeter(s)
R-1-13 July 15, 2013 R2.6: Retired January 21, 20142
CIP-005-5 Cyber Security – Electronic Security Perimeter(s)
R-38-15 October 1, 2018
CIP-006-3c1 Cyber Security – Physical Security of Critical Cyber Assets
G-162-11 July 1, 2012
CIP-006-51 Cyber Security – Physical Security of BES Cyber Systems
R-38-15 October 1, 2018
CIP-006-6 Cyber Security — Physical Security of BES Cyber Systems
CIP-007-3a1, 3, 4 Cyber Security - Systems Security Management
R-32-14 August 1, 2014 R7.3: Retired January 21, 20142
CIP-007-51 Cyber Security – System Security Management
R-38-15 October 1, 2018
CIP-007-6 Cyber Security — System Security Management
CIP-008-31 Cyber Security – Incident Reporting and Response Planning
G-162-11 July 1, 2012
CIP-008-5 Cyber Security – Incident Reporting and Response Planning
R-38-15 October 1, 2018
CIP-009-31 Cyber Security – Recovery Plans for Critical Cyber Assets
G-162-11 July 1, 2012
CIP-009-51 Cyber Security – Recovery Plans for BES Cyber Systems
R-38-15 October 1, 2018
CIP-009-6 Cyber Security — Recovery Plans for BES Cyber Systems
5 BC Hydro recommends that the CIP-003-6 reliability standard be held in abeyance and be of no force or effect in BC due to
technical suitability issues that will not improve reliability and instead place undue burden on responsible entities. When adopted by FERC, the NERC approved CIP-003-7(i) reliability standard will retire CIP-003-6. CIP-003-7(i) is anticipated to be assessed in the next MRS Assessment Report.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
CIP-010-11 Cyber Security – Configuration Change Management and Vulnerability Assessments
R-38-15 October 1, 2018
CIP-010-2 Cyber Security – Configuration Change Management and Vulnerability Assessments
CIP-011-11 Cyber Security – Information Protection
R-38-15 October 1, 2018
CIP-011-2 Cyber Security – Information Protection
CIP-014-2 Physical Security R-32-16 October 1, 2017 and as per BC-specific Implementation Plan
COM-001-1.11, 6 Telecommunications G-167-10 January 1, 2011
COM-001-2.11 Communications R-32-16 October 1, 2017
COM-001-3 Communications
COM-002-4 Operating Personnel Communications Protocols
R-32-16 April 1, 2017
EOP-001-2.1b7 Emergency Operations Planning R-32-14 August 1, 2014
EOP-002-3.17 Capacity and Energy Emergencies R-32-14 August 1, 2014
EOP-003-18 Load Shedding Plans G-67-09 November 1, 2010
EOP-003-29 Load Shedding Plans Adoption held in abeyance at this time10
EOP-004-21 Event Reporting R-32-14 August 1, 2015
EOP-004-3 Event Reporting
EOP-005-2 System Restoration and Blackstart Resources
R-32-14 August 1, 2015 R3.1: Retired January 21, 20142
EOP-006-2 System Restoration Coordination R-32-14 August 1, 2014
6 Requirement 4 of the reliability standard is superseded by COM-002-4 as of the COM-002-4 effective date. 7 Reliability standard is superseded by EOP-011-1 as of the EOP-011-1 effective date. 8 Reliability standard would be superseded by EOP-003-2 if adopted in B.C. Adoption of EOP-003-2 pending reassessment. 9 Reliability standard is superseded by EOP-011-1 as of the EOP-011-1 effective date in conjunction with PRC-010-2
Requirement 1 if adopted in B.C. Adoption of PRC-010-2 pending reassessment. 10 Unable to assess based on undefined Planning Coordinator/Planning Authority footprints and entities responsible. The
Commission Reasons for Decision for Order No. R-41-13 (page 20), indicated that a separate process would be established to consider this matter as it pertains to B.C.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
EOP-008-1 Loss of Control Center Functionality
R-32-14 August 1, 2015
EOP-010-111 Geomagnetic Disturbance Operations
R-38-15 R1, R3: October 1, 2016
R2:
EOP-011-1 Emergency Operations
FAC-001-2 Facility Interconnection Requirements
R-38-15 October 1, 2016
FAC-002-2 Facility Interconnection Studies R-38-15 October 1, 2015
FAC-003-31 Transmission Vegetation Management
R-32-14 August 1, 2015
FAC-003-4 Transmission Vegetation Management
FAC-501-WECC-1 Transmission Maintenance R-1-13 April 15, 2013
FAC-008-3 Facility Ratings R-32-14 August 1, 2015 R4 and R5: Retired January 21, 20142
FAC-010-2.11 System Operating Limits Methodology for the Planning Horizon
G-162-11 October 30, 2011 R5: Retired January 21, 20142
FAC-010-3 System Operating Limits Methodology for the Planning Horizon
FAC-011-21 System Operating Limits Methodology for the Operations Horizon
G-167-10 January 1, 2011 R5: Retired January 21, 20142
FAC-011-3 System Operating Limits Methodology for the Operations Horizon
FAC-013-112 Establish and Communicate Transfer Capability
G-67-09 November 1, 2010
FAC-013-2
Assessment of Transfer Capability
for the Near-Term Transmission
Planning Horizon
Adoption held in abeyance at this time10
11 Requirement 2 of the reliability standard will be effective upon the retirement of IRO-005-3.1a Requirement 3 which follows
the effective date of IRO-002-4. 12 Reliability standard would be superseded by the FAC-013-2 if adopted in B.C. Adoption of FAC-013-2 pending
reassessment.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
FAC-014-2 Establish and Communicate System Operating Limits
G-167-10 January 1, 2011
INT-004-3.1 Dynamic Transfers R-38-15 R1, R2: October 1, 2015
R3: January 1, 2016
INT-006-4 Evaluation of Interchange Transactions
R-38-15 October 1, 2015
INT-009-2.1 Implementation of Interchange R-38-15 October 1, 2015
INT-010-2.1 Interchange Initiation and Modification for Reliability
R-38-15 October 1, 2015
INT-011-1.1 Intra-Balancing Authority Transaction Identification
R-38-15 October 1, 2015
IRO-001-1.113 Reliability Coordination Responsibilities and Authorities
G-167-10 January 1, 2011
IRO-001-4 Reliability Coordination – Responsibilities
IRO-002-213 Reliability Coordination – Facilities R-1-13 April 15, 2013
IRO-002-4 Reliability Coordination – Monitoring and Analysis
IRO-003-213 Reliability Coordination – Wide Area View
G-67-09 November 1, 2010
IRO-004-213 Reliability Coordination – Operations planning
R-1-13 April 15, 2013
IRO-005-3.1a13,14 Reliability Coordination - Current Day Operations
R-32-14 August 1, 2014
IRO-006-5 Reliability Coordination – Transmission Loading Relief
R-1-13 April 15, 2013
IRO-006-WECC-2 Qualified Transfer Path Unscheduled Flow (USF) Relief
R-38-15 October 1, 2015
IRO-008-113 Reliability Coordinator Operational Analyses and Real-time Assessments
R-1-13 April 15, 2013
IRO-008-2 Reliability Coordinator Operational Analyses and Real-time Assessments
13 See “IRO and TOP Reliability Standards Supersession Mapping” section below. 14 Requirement 3 of the reliability standard is superseded by EOP-010-1 Requirement 2 as of the IRO-002-4 effective date.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
IRO-009-11 Reliability Coordinator Actions to Operate Within IROLs
R-1-13 April 15, 2013
IRO-009-2 Reliability Coordinator Actions to Operate Within IROLs
IRO-010-1a13 Reliability Coordinator Data Specification and Collection
R-1-13 April 15, 2013
IRO-010-2 Reliability Coordinator Data Specification and Collection
IRO-014-113 Procedures, Processes, or Plans to Support Coordination Between Reliability coordinators
G-67-09 November 1, 2010
IRO-014-3 Coordination Among Reliability Coordinators
IRO-015-113 Notification and Information Exchange
G-67-09 November 1, 2010
IRO-016-113 Coordination of Real-Time Activities
G-67-09 November 1, 2010 R2: Retired January 21, 20142
IRO-017-1 Outage Coordination
IRO-018-1 Reliability Coordinator Real-time Reliability Monitoring and Analysis Capabilities
MOD-001-1a Available Transmission System Capability
G-175-11 November 30, 2011
MOD-004-1 Capacity Benefit Margin G-175-11 November 30, 2011
MOD-008-1 Transmission Reliability Margin Calculation Methodology
G-175-11 November 30, 2011
MOD-010-015
Steady-State Data for Modeling and Simulation for the Interconnected Transmission System
G-67-09 November 1, 2010
15 Reliability standard will be superseded by MOD-032-1 and MOD-033-1 if adopted in B.C. Adoption of MOD-032-1 and
MOD-033-1 pending reassessment.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
MOD-012-015 Dynamics Data for Modeling and Simulation of the Interconnected Transmission System
G-67-09 November 1, 2010
MOD-020-0
Providing Interruptible Demands and Direct Control Load management Data to System Operators and Reliability Coordinators
G-67-09 November 1, 2010
MOD-025-2
Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability
R-38-15
40% by October 1, 2017
60% by October 1, 2018
80% by October 1, 2019
100% by October 1, 2020
MOD-026-1
Verification of Models and Data for Generator Excitation Control System or Plant Volt/Var Control Functions
R-38-15
R1: October 1, 2016
R2: 30% by October 1, 2019
50% by October 1, 2021
100% by October 1, 2025
R3-R6: October 1, 2015
MOD-027-1
Verification of Models and Data for Turbine/Governor and Load Control or Active Power/Frequency Control Functions
R-38-15
R1: October 1, 2016
R2: 30% by October 1, 2019
50% by October 1, 2021
100% by October 1, 2025
R3-R5: October 1, 2015
MOD-028-2 Area Interchange Methodology R-32-14 August 1, 2014
MOD-029-1a1 Rated System Path Methodology G-175-11 November 30, 2011
MOD-029-2a Rated System Path Methodology
MOD-030-21 Flowgate Methodology G-175-11 November 30, 2011
MOD-030-3 Flowgate Methodology
MOD-031-11 Demand and Energy Data R-32-16 October 1, 2016
MOD-031-2 Demand and Energy Data
MOD-032-1 Data for Power System Modeling and Analysis
R-38-15 Effective date held in abeyance10
MOD-033-1 Steady-State and Dynamic System Model Validation
R-38-15 Effective date held in abeyance10
NUC-001-3 Nuclear Plant Interface Coordination
R-38-15 January 1, 2016
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
PER-001-0.213 Operating Personnel Responsibility and Authority
R-41-13 December 12, 2013
PER-002-0 Operating Personnel Training G-67-09 November 1, 2010
PER-003-1 Operating Personnel Credentials R-41-13 January 1, 2015
PER-004-2 Reliability Coordination – Staffing R-1-13 January 15, 2013
PER-005-2 Operations Personnel Training R-38-15 R1-R4, R6: October 1, 2016
R5: October 1, 2017
PRC-001-1.1(ii) System Protection Coordination R-32-16 October 1, 2016
PRC-002-2 Disturbance Monitoring and Reporting Requirements
R-32-16
R1, R5: April 1, 2017
R2-R4, R6-R11: staged as per BC-specific Implementation Plan
R12: July 1, 2017
PRC-004-2.1a1 Analysis and Mitigation of Transmission and Generation Protection System Misoperations
R-32-14 August 1, 2014
PRC-004-5(i) Protection System Misoperation Identification and Correction
R-32-16 October 1, 2017
PRC-004-WECC-11 Protection System and Remedial Action Scheme Misoperation
R-1-13 July 15, 2013
PRC-004-WECC-2 Protection System and Remedial Action Scheme Misoperation
PRC-005-1.1b1,18 Transmission and Generation Protection System Maintenance and Testing
R-32-14 January 1, 2015
PRC-005-21 Protection System Maintenance R-38-15
R1, R2, R5: October 1, 2017
R3, R4: staged as per BC-specific Implementation Plan
PRC-005-2(i)1 Protection System Maintenance R-32-16
R1, R2, R5: October 1, 2017
R3, R4: staged as per BC-specific Implementation Plan
PRC-005-6 Protection System, Automatic Reclosing, and Sudden Pressure Relaying Maintenance
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
PRC-006-216 Automatic Underfrequency Load Shedding
Adoption held in abeyance at this time10
PRC-007-017 Assuring consistency of entity Underfrequency Load Shedding Program Requirements
G-67-09 November 1, 2010
PRC-008-018
Implementation and Documentation of Underfrequency Load Shedding Equipment Maintenance Program
G-67-09 November 1, 2010
PRC-009-017
Analysis and Documentation of Underfrequency Load Shedding Performance Following an Underfrequency Event
G-67-09 November 1, 2010
PRC-010-01
Technical Assessment of the Design and Effectiveness of Undervoltage Load Shedding Program
G-67-09 November 1, 2010 R2: Retired January 21, 20142
PRC-010-2 Under Voltage Load Shedding Adoption held in abeyance at this time10
PRC-011-018 Undervoltage Load Shedding system Maintenance and Testing
G-67-09 November 1, 2010
PRC-015-01 Special Protection System Data and Documentation
G-67-09 November 1, 2010
PRC-015-1 Remedial Action Scheme Data and Documentation
PRC-016-0.11 Special Protection System Misoperations
G-167-10 January 1, 2011
PRC-016-1 Remedial Action Scheme Misoperations
PRC-017-01,18 Special Protection System Maintenance and Testing
G-67-09 November 1, 2010
PRC-017-118 Remedial Action Scheme Maintenance and Testing
PRC-018-119 Disturbance Monitoring Equipment Installation and Data Reporting
G-67-09 November 1, 2010
16 Reliability standard supersedes PRC-006-1 which has been held in abeyance due to the undefined Planning
Coordinator/Planning Authority footprints and entities responsible. 17 Reliability standard will be superseded by PRC-006-2 if adopted in B.C. Adoption of PRC-006-2 pending reassessment. 18 Reliability standard is superseded by PRC-005-6 as per the PRC-005-6 BC specific Implementation Plan. 19 Reliability standard is superseded by PRC-002-2 as of the PRC-002-2 effective date.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
PRC-019-2
Coordination of Generating Unit or Plant Capabilities, Voltage Regulating Controls, and Protection
R-32-16
40% by October 1, 2017
60% by October 1, 2018
80% by October 1, 2019
100% by October 1, 2020
PRC-021-120 Under Voltage Load Shedding Program Data
G-67-09 November 1, 2010
PRC-022-120 Under Voltage Load Shedding Program Performance
G-67-09 November 1, 2010 R2: Retired January 21, 20142
PRC-023-21,21 Transmission Relay Loadability R-41-13
R1-R5: For circuits identified by sections 4.2.1.1 and 4.2.1.4: January 1, 2016 For circuits identified by sections 4.2.1.2, 4.2.1.3, 4.2.1.5, and 4.2.1.6: To be determined10 R6: To be determined10
PRC-023-31 Transmission Relay Loadability R-38-15
R1-R5: regarding circuits 4.2.1.1 and 4.2.1.4 January 1, 2016
R1-R5: Circuits 4.2.1.2, 4.2.1.3, 4.2.1.5 and 4.2.1.6: To be determined7
R6: To be determined10
PRC-023-4 Transmission Relay Loadability
PRC-024-2 Generator Frequency and Voltage Protective Relay Settings
R-32-16
40% by October 1, 2017
60% by October 1, 2018
80% by October 1, 2019
100% by October 1, 2020
PRC-025-1 Generator Relay Loadability R-38-15
40% by October 1, 2017
60% by October 1, 2018
80% by October 1, 2019
100% by October 1, 2020
PRC-026-1 Relay Performance During Stable Power Swings
Adoption held in abeyance at this time10
TOP-001-1a13 Reliability Responsibilities and Authorities
R-1-13 January 15, 2013
20 Reliability standard is superseded by PRC‐010‐2 if adopted in B.C. Adoption of PRC-010-2 pending reassessment. 21 PRC-023-2 Requirement 1, Criterion 6 only is superseded by PRC-025-1 as of PRC-025-1’s 100 per cent Effective Date.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
TOP-001-3 Transmission Operations
TOP-002-2.1b13 Normal Operations Planning R-41-13 December 12, 2013
TOP-002-4 Operations Planning
TOP-003-113 Planned Outage Coordination R-1-13 April 15, 2013
TOP-003-3 Operational Reliability Data
TOP-004-213 Transmission Operations G-167-10 January 1, 2011
TOP-005-2a13 Operational Reliability Information R-1-13 April 15, 2013
TOP-006-213 Monitoring System Conditions R-1-13 April 15, 2013
TOP-007-013
Reporting System Operating Unit (SOL) and Interconnection Reliability Operating Limit (IROL) Violations
G-67-09 November 1, 2010
TOP-007-WECC-1a System Operating Limits R-38-15 October 1, 2015
TOP-008-113 Response to Transmission Limit Violations
G-67-09 November 1, 2010
TOP-010-1 Real-time Reliability Monitoring and Analysis Capabilities
TPL-001-0.122 System Performance Under Normal (No Contingency) Conditions (Category A)
G-167-10 January 1, 2011
TPL-001-4 Transmission System Planning Performance Requirements
TPL-002-0b22 System Performance Following Loss of a Single Bulk Electric System Element (Category B)
R-1-13 January 15, 2013
TPL-003-0b22
System Performance Following Loss of Two or More Bulk Electric System Elements (Category C)
R-32-14 August 1, 2014
TPL-004-0a22
System Performance Following Extreme Events Resulting in the Loss of Two or More Bulk Electric System Elements (Category D)
R-32-14 August 1, 2014
22 Reliability standard will be superseded by TPL‑001‑4 Requirements 2-6, and 8 as of their effective dates.
B.C. Reliability Standards
Standard Name Commission
Order Adopting Effective Date
TPL-007-1 Transmission System Planned Performance for Geomagnetic Disturbance Events
Adoption held in abeyance at this time10
VAR-001-4.1 Voltage and Reactive Control R-32-16 October 1, 2016
VAR-002-4 Generator Operation for Maintaining Network Voltage Schedules
R-32-16 October 1, 2016
VAR-002-WECC-2 Automatic Voltage Regulators (AVR)
R-32-16 October 1, 2016
VAR-501-WECC-2 Power System Stabilizer (PSS) R-32-16 October 1, 2016
IRO and TOP Reliability Standards
Supersession Mapping
This following mapping shows the supersession of Requirements for the following IRO, TOP, and PER reliability standards
by the revised/replacement IRO and TOP reliability standards adopted or yet to be adopted in B.C. as of the effective date in
the “B.C. Reliability Standards” section above:
IRO-001-1.1 — Reliability Coordination - Responsibilities and Authorities
IRO-002-2 — Reliability Coordination - Facilities
IRO-003-2 — Reliability Coordination - Wide-Area View
IRO-004-2 — Reliability Coordination - Operations Planning
IRO-005-3.1a — Reliability Coordination - Current Day Operations
IRO-008-1 — Reliability Coordinator Operational Analyses and Real-time Assessments
IRO-010-1a — Reliability Coordinator Data Specification and Collection
IRO-014-1 — Procedures, Processes, or Plans to Support Coordination Between Reliability Coordinators
IRO-015-1 — Notifications and Information Exchange Between Reliability Coordinators
IRO-016-1 — Coordination of Real-time Activities Between Reliability Coordinators
PER-001-0.2 — Operating Personnel Responsibility and Authority
TOP-001-1a — Reliability Responsibilities and Authorities
TOP-002-2.1b — Normal Operations Planning
TOP-003-1 — Planned Outage Coordination
TOP-004-2 — Transmission Operations
TOP-005-2a — Operational Reliability Information
TOP-006-2 — Monitoring System Conditions
TOP-007-0 — Reporting System Operating Limit (SOL) and Interconnection Reliability Operating Limit (IROL)
Violations
TOP-008-1 — Response to Transmission Limit Violations
Standard IRO-001-1.1 — Reliability Coordination - Responsibilities and Authorities
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirements R1-R6, R8, R9 IRO-001-4
Requirement R7 IRO-014-3
Standard IRO-002-2 — Reliability Coordination – Facilities
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirements R1, R3-R5, R7, and R8 IRO-002-4
Requirement R2 IRO-010-2
Requirement R6 IRO-008-2
Standard IRO-003-2 — Reliability Coordination - Wide-Area View
Requirement Being Superseded Superseding BCUC Approved Standard(s)
All Requirements IRO-002-4
IRO and TOP Reliability Standards
Supersession Mapping
Standard IRO-004-2 — Reliability Coordination - Operations Planning
Requirement Being Superseded Superseding BCUC Approved Standard(s)
All Requirements IRO-001-4
IRO-008-2
Standard IRO-005-3.1a — Reliability Coordination - Current Day Operations
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirements R1-R3 IRO-002-4
Requirement R4 IRO-008-2
Requirements R5 and R8 IRO-001-4
IRO-002-4
Requirements R6 and R7 IRO-008-2
IRO-017-1
Requirement R8 IRO-001-4
IRO-002-4
Requirement R9 IRO-002-4
IRO-010-2
Requirement R10 IRO-009-1
TOP-001-3
Requirement R11 MOD-001-2, Requirement R2 (pending FERC adoption in the
U.S. and subsequent assessment and adoption in B.C.)
Requirement R12 IRO-008-2
Standard IRO-008-1 — Reliability Coordination - Current Day Operations
Requirement Being Superseded Superseding BCUC Approved Standard(s)
All Requirements IRO-008-2
Standard IRO-010-1a — Reliability Coordinator Data Specification and Collection
Requirement Being Superseded Superseding BCUC Approved Standard(s)
All Requirements IRO-010-2
Standard IRO-014-1 — Procedures, Processes, or Plans to Support Coordination Between Reliability Coordinators
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 IRO-014-3
IRO-010-2
Requirements R2-R4 IRO-014-3
IRO and TOP Reliability Standards
Supersession Mapping
Standard IRO-015-1 — Notifications and Information Exchange Between Reliability Coordinators
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirements R1 and R2 IRO-014-3
Requirement R3 IRO-010-2
Standard IRO-016-1 — Coordination of Real-time Activities Between Reliability Coordinators
Requirement Being Superseded Superseding BCUC Approved Standard(s)
All Requirements IRO-014-3
Standard PER-001-0.2 — Operating Personnel Responsibility and Authority
Requirement Being Superseded Superseding BCUC Approved Standard(s)
All Requirements TOP-001-3
Standard TOP-001-1a — Reliability Responsibilities and Authorities
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirements R1, R2, R4, R5, R6 TOP-001-3
Requirement R3 IRO-001-4
TOP-001-3
Requirement R7 TOP-001-3
TOP-003-3
IRO-010-2
Requirement R8 EOP-003-2, Requirement 1 (adoption held in abeyance in B.C.
due to PA/PC dependencies)
IRO-009-1
IRO and TOP Reliability Standards
Supersession Mapping
Standard TOP-003-1 — Planned Outage Coordination
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 IRO-010-2
TOP-003-3
Requirement R2 IRO-017-1
TOP-003-3
Requirement R3 TOP-001-3
Requirement R4 IRO-008-2
IRO-017-1
Standard TOP-002-2.1b — Normal Operations Planning
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 TOP-001-3
TOP-002-4
Requirements R2, R5-R9, R12 TOP-002-4
Requirement R3 IRO-017-1
TOP-003-3
Requirement R4 IRO-017-1
IRO-008-2
Requirement R10 IRO-017-1
TOP-001-3
TOP-002-4
TOP-003-3
Requirement R11 TOP-001-3
TOP-002-4
Requirement R13 TOP-001-3
TOP-003-3
Requirements R14, R15, and R19 TOP-003-3
Requirements R16, R17, and R18 IRO-010-2
IRO and TOP Reliability Standards
Supersession Mapping
Standard TOP-004-2 — Transmission Operations
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 TOP-001-3
Requirement R2 TOP-001-3
TOP-002-4
Requirements R3 and R4 TOP-001-3
Requirement R5 Retired
Requirement R6 IRO-017-1
TOP-001-3
Standard TOP-005-2a — Operational Reliability Information
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 IRO-010-2
TOP-003-3
Requirement R2 TOP-003-3
Requirement R3 Retired
Standard TOP-006-2 — Monitoring System Conditions
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 IRO-010-2
TOP-001-3
TOP-003-3
Requirement R2 IRO-002-4
TOP-001-3
Requirement R3 IRO-010-2
TOP-003-3
Requirement R4 TOP-003-3
Requirement R5 IRO-002-4
TOP-001-3
Requirement R6 TOP-003-3
Requirement R7 IRO-002-4
TOP-001-3
IRO and TOP Reliability Standards
Supersession Mapping
Standard TOP-007-0 — Reporting System Operating Limit (SOL) and Interconnection Reliability Operating Limit
(IROL) Violations
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirement R1 IRO-008-2
TOP-001-3
Requirement R2 IRO-009-1
TOP-001-3
Requirement R3 EOP-003-2, Requirement 1 (adoption held in abeyance in B.C.
due to PA/PC dependencies)
IRO-009-1
Requirement R4 IRO-008-2
Standard TOP-008-1 — Response to Transmission Limit Violations
Requirement Being Superseded Superseding BCUC Approved Standard(s)
Requirements R1 EOP-003-2, Requirement 1 (adoption held in abeyance in B.C.
due to PA/PC dependencies)
TOP-001-3
Requirements R2 and R3 TOP-001-3
Requirement R4 TOP-001-3
TOP-002-4
TOP-003-3
Ta
ble
1
NE
RC
Glo
ssa
ry T
erm
s U
se
d in
TP
L-0
01
-4 R
elia
bilit
y S
tan
da
rd
Ter
m
BO
T
Ap
pro
ved
D
ate
FE
RC
A
pp
rove
d D
ate
Def
init
ion
Bus
-tie
Bre
aker
8/
4/20
11
10/1
7/20
13
(Bec
omes
ef
fect
ive
1/1/
2015
)
A c
ircui
t bre
aker
that
is p
ositi
oned
to c
onne
ct tw
o in
divi
dual
sub
stat
ion
bus
conf
igur
atio
ns.
Con
sequ
entia
l Loa
d Lo
ss
8/4/
2011
10
/17/
2013
(B
ecom
es
effe
ctiv
e 1/
1/20
15)
All
Load
that
is n
o lo
nger
ser
ved
by th
e T
rans
mis
sion
sys
tem
as
a re
sult
of T
rans
mis
sion
Fac
ilitie
s be
ing
rem
oved
from
ser
vice
by
a P
rote
ctio
n S
yste
m o
pera
tion
desi
gned
to is
olat
e th
e fa
ult.
Long
-Ter
m T
rans
mis
sion
P
lann
ing
Hor
izon
8/
4/20
11
10/1
7/20
13
(Bec
omes
ef
fect
ive
1/1/
2015
)
Tra
nsm
issi
on p
lann
ing
perio
d th
at c
over
s ye
ars
six
thro
ugh
ten
or b
eyon
d w
hen
requ
ired
to
acco
mm
odat
e an
y kn
own
long
er le
ad ti
me
proj
ects
that
may
take
long
er th
an te
n ye
ars
to c
ompl
ete.
Non
-Con
sequ
entia
l Loa
d Lo
ss
8/4/
2011
10
/17/
2013
(B
ecom
es
effe
ctiv
e 1/
1/15
)
Non
-Int
erru
ptib
le L
oad
loss
that
doe
s no
t inc
lude
: (1)
Con
sequ
entia
l Loa
d Lo
ss, (
2) th
e re
spon
se o
f vo
ltage
sen
sitiv
e Lo
ad, o
r (3
) Lo
ad th
at is
dis
conn
ecte
d fr
om th
e S
yste
m b
y en
d-us
er e
quip
men
t.
Pla
nnin
g A
sses
smen
t 8/
4/20
11
10/1
7/20
13
(Bec
omes
ef
fect
ive
1/1/
15)
Doc
umen
ted
eval
uatio
n of
futu
re T
rans
mis
sion
Sys
tem
per
form
ance
and
Cor
rect
ive
Act
ion
Pla
ns to
re
med
y id
entif
ied
defic
ienc
ies.
Bri
tish
Co
lum
bia
(B
.C.)
Excep
tio
ns t
o t
he
Glo
ssary
of
Term
s U
se
d i
n N
ort
h
Am
eri
can
Ele
ctr
ic R
elia
bilit
y C
orp
ora
tio
n (
NE
RC
) R
eli
ab
ilit
y S
tan
dard
s
(NE
RC
Glo
ss
ary
) U
pdate
d
,
2017
Intr
od
ucti
on
:
This
docu
ment
is to b
e u
sed in c
onju
nction
with t
he N
ER
C G
lossary
date
d N
ovem
ber
28,
2016.
The N
ER
C G
lossary
term
s lis
ted in T
able
1 b
elo
w a
re e
ffective in B
.C.
on the d
ate
specifie
d in t
he “
Effective D
ate”
colu
mn
.
Table
2 b
elo
w o
utlin
es t
he a
doption h
isto
ry b
y t
he C
om
mis
sio
n o
f th
e N
ER
C G
lossar ies in B
.C.
Any N
ER
C G
lossary
term
s a
nd
definitio
ns in t
he N
ER
C G
lossary
that
are
not
appro
ved b
y F
ER
C o
n o
r befo
re
Novem
ber
30,
2016 a
re o
f no f
orc
e o
r eff
ect
in B
.C.
With t
he e
xce
ptions o
f eig
ht
NE
RC
Glo
ssary
term
s a
nd
definitio
ns inte
nded f
or
the B
AL-0
02-2
relia
bili
ty s
tandard
that
were
FE
RC
app
roved in the N
ER
C G
lossary
of
Term
s
as o
f F
ebru
ary
7,
2017
and a
ssessed in M
RS
Assessm
ent
Report
No.
10. T
hese e
ight N
ER
C G
lossary
term
s a
re
inclu
de
d in T
able
1 b
elo
w.
Any N
ER
C G
lossary
term
s that
have b
een r
em
anded o
r re
tire
d b
y N
ER
C a
re o
f no forc
e o
r eff
ect in
B.C
., w
ith the
exce
ption o
f th
ose r
em
anded o
r re
tire
d N
ER
C G
lossary
term
s w
hic
h h
ave n
ot
yet
been r
etire
d in B
.C.
The E
lectr
ic R
elia
bili
ty C
ouncil
of T
exas, N
ort
heast
Pow
er
Coord
inating C
oun
cil
and R
elia
bili
ty F
irst re
gio
na
l definitio
ns lis
ted a
t th
e e
nd o
f th
e N
ER
C G
lossary
have b
een a
dopte
d b
y t
he N
ER
C B
oard
of
Tru
ste
es f
or
use in
regio
na
l sta
ndard
s a
nd a
re o
f no forc
e o
r effect in
B.C
.
Ta
ble
1
B.C
. E
ffe
cti
ve
Da
te E
xc
ep
tio
ns
to
De
fin
itio
ns
in
th
e N
ove
mb
er
2
8, 2
01
6 V
ers
ion
of
the
NE
RC
Glo
ss
ary
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Adj
acen
t Bal
anci
ng A
utho
rity
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Alte
rnat
ive
Inte
rper
sona
l C
omm
unic
atio
n -
Rep
ort N
o. 9
R
-32-
16
Ado
ptio
n O
ctob
er 1
, 201
7
Are
a C
ontr
ol E
rror
(fro
m N
ER
C s
ectio
n of
the
Glo
ssar
y)
AC
E
Rep
ort N
o. 7
R
-32-
14
Ado
ptio
n O
ctob
er 1
, 201
4
Are
a C
ontr
ol E
rror
(fro
m th
e W
EC
C R
egio
nal D
efin
ition
s se
ctio
n of
the
Glo
ssar
y)
AC
E
Rep
ort N
o. 7
R
-32-
14
Ret
irem
ent
Oct
ober
1, 2
014
Arr
ange
d In
terc
hang
e -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n O
ctob
er 1
, 201
5
Atta
inin
g B
alan
cing
Aut
horit
y -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n O
ctob
er 1
, 201
5
Aut
omat
ic T
ime
Err
or C
orre
ctio
n -
Rep
ort N
o. 7
R
-32-
14
Ado
ptio
n O
ctob
er 1
, 201
4
Bal
anci
ng C
ontin
genc
y E
vent
1 -
Rep
ort N
o. 1
0
Ado
ptio
n
BE
S C
yber
Ass
et2
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
BE
S C
yber
Ass
et
BC
A
Rep
ort N
o. 1
0
Ado
ptio
n
BE
S C
yber
Sys
tem
-
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
1
FE
RC
app
rove
d te
rms
in th
e N
ER
C G
loss
ary
of T
erm
s as
of F
ebru
ary
7, 2
017;
inte
nded
for
BA
L-00
2-2.
2
N
ER
C G
loss
ary
term
def
initi
on is
sup
erse
ded
by th
e re
vise
d N
ER
C G
loss
ary
term
def
initi
on li
sted
imm
edia
tely
bel
ow it
as
of th
e ef
fect
ive
date
(s)
of th
e re
vise
d N
ER
C
Glo
ssar
y te
rm d
efin
ition
.
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
BE
S C
yber
Sys
tem
Info
rmat
ion
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Bla
ckst
art C
apab
ility
Pla
n -
Rep
ort N
o. 7
R
-32-
14
Ret
irem
ent
Aug
ust 1
, 201
5
Bla
ckst
art R
esou
rce2
- R
epor
t No.
6
R-4
1-13
A
dopt
ion
Dec
embe
r 12
, 201
3
Bla
ckst
art R
esou
rce
- R
epor
t No.
10
A
dopt
ion
Bul
k E
lect
ric S
yste
m
BE
S
Rep
ort N
o. 8
R
-38-
15
- O
ctob
er 1
, 201
5
Bul
k-P
ower
Sys
tem
2 -
Rep
ort N
o. 8
R
-38-
15
- O
ctob
er 1
, 201
5
Bul
k-P
ower
Sys
tem
-
Rep
ort N
o. 1
0
Ado
ptio
n
Bus
-tie
Bre
aker
-
TP
L-00
1-4
Rep
ort
A
dopt
ion
Cas
cadi
ng
- R
epor
t No.
10
A
dopt
ion
CIP
Exc
eptio
nal C
ircum
stan
ce
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
CIP
Sen
ior
Man
ager
-
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Com
posi
te C
onfir
med
Inte
rcha
nge
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Con
firm
ed In
terc
hang
e -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n O
ctob
er 1
, 201
5
Com
posi
te P
rote
ctio
n S
yste
m
- R
epor
t No.
9
R-3
2-16
A
dopt
ion
Oct
ober
1, 2
017
Con
sequ
entia
l Loa
d Lo
ss
- T
PL-
001-
4 R
epor
t
Ado
ptio
n
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Con
tinge
ncy
Eve
nt R
ecov
ery
Per
iod1
- R
epor
t No.
10
A
dopt
ion
Con
tinge
ncy
Res
erve
1 -
Rep
ort N
o. 1
0
Ado
ptio
n
Con
tinge
ncy
Res
erve
Res
tora
tion
Per
iod1
- R
epor
t No.
10
A
dopt
ion
Con
trol
Cen
ter
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Crit
ical
Ass
ets
- R
epor
t No.
9
R-3
2-16
R
etire
men
t S
epte
mbe
r 30
, 201
8
Crit
ical
Cyb
er A
sset
s -
Rep
ort N
o. 9
R
-32-
16
Ret
irem
ent
Sep
tem
ber
30, 2
018
Cyb
er A
sset
s -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Cyb
er S
ecur
ity In
cide
nt
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Dem
and-
Sid
e M
anag
emen
t D
SM
R
epor
t No.
9
R-3
2-16
A
dopt
ion
Oct
ober
1, 2
016
Dia
l-up
Con
nect
ivity
-
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Dis
trib
utio
n P
rovi
der
DP
R
epor
t No.
10
A
dopt
ion
Dyn
amic
Inte
rcha
nge
Sch
edul
e or
D
ynam
ic S
ched
ule
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Ele
ctro
nic
Acc
ess
Con
trol
or
Mon
itorin
g S
yste
ms
EA
CM
S
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Ele
ctro
nic
Acc
ess
Poi
nt
EA
P
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Ele
ctro
nic
Sec
urity
Per
imet
er
ES
P
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Ele
men
t -
Rep
ort N
o. 1
0
Ado
ptio
n
Ene
rgy
Em
erge
ncy
- R
epor
t No.
9
R-3
2-16
A
dopt
ion
Oct
ober
1, 2
016
Ext
erna
l Rou
tabl
e C
onne
ctiv
ity
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Fre
quen
cy B
ias
Set
ting
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
arlie
st e
ffect
ive
date
of B
AL-
003-
1 st
anda
rd
whe
re th
is te
rm is
ref
eren
ced
Fre
quen
cy R
espo
nse
Mea
sure
F
RM
R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
arlie
st e
ffect
ive
date
of B
AL-
003-
1 st
anda
rd
whe
re th
is te
rm is
ref
eren
ced
Fre
quen
cy R
espo
nse
Obl
igat
ion
FR
O
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n A
lign
with
ear
liest
effe
ctiv
e da
te o
f BA
L-00
3-1
stan
dard
w
here
this
term
is r
efer
ence
d
Fre
quen
cy R
espo
nse
Sha
ring
Gro
up
FR
SG
R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
arlie
st e
ffect
ive
date
of B
AL-
003-
1 st
anda
rd
whe
re th
is te
rm is
ref
eren
ced
Gen
erat
or O
pera
tor
GO
P
Rep
ort N
o. 1
0
Ado
ptio
n
Gen
erat
or O
wne
r G
O
Rep
ort N
o. 1
0
Ado
ptio
n
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Geo
mag
netic
Dis
turb
ance
Vul
nera
bilit
y A
sses
smen
t or
GM
D V
ulne
rabi
lity
Ass
essm
ent
GM
D
Rep
ort N
o. 1
0
Ado
ptio
n T
o be
det
erm
ined
3
Inte
ract
ive
Rem
ote
Acc
ess
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Inte
rcha
nge
Aut
horit
y IA
R
epor
t No.
10
A
dopt
ion
Inte
rcon
nect
ed O
pera
tions
Ser
vice
-
Rep
ort N
o. 1
0
Ado
ptio
n
Inte
rcon
nect
ion
- R
epor
t No.
10
A
dopt
ion
Inte
rcon
nect
ion
Rel
iabi
lity
Ope
ratin
g Li
mit
IRO
L R
epor
t No.
6
R-4
1-13
A
dopt
ion
Dec
embe
r 12
, 201
3
Inte
rmed
iate
Bal
anci
ng A
utho
rity
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Inte
rmed
iate
Sys
tem
-
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Inte
rper
sona
l Com
mun
icat
ion
- R
epor
t No.
9
R-3
2-16
A
dopt
ion
Oct
ober
1, 2
017
Load
-Ser
ving
Ent
ity
LSE
R
epor
t No.
10
A
dopt
ion
Long
-Ter
m T
rans
mis
sion
Pla
nnin
g H
oriz
on
- T
PL-
001-
4 R
epor
t
Ado
ptio
n
Low
Impa
ct B
ES
Cyb
er S
yste
m
Ele
ctro
nic
Acc
ess
Poi
nt4
LEA
P
Rep
ort N
o. 1
0
Ado
ptio
n N
ot r
ecom
men
ded
for
adop
tion
in B
.C a
t thi
s tim
e.
3
The
NE
RC
Glo
ssar
y te
rm is
ass
ocia
ted
with
rel
iabi
lity
stan
dard
that
is d
epen
dent
on
the
Pla
nnin
g A
utho
rity/
Pla
nnin
g C
oord
inat
or fu
nctio
n. T
he B
CU
C R
easo
ns fo
r D
ecis
ion
for
Ord
er N
o. R
-41-
13 (
page
20)
, ind
icat
ed th
at a
sep
arat
e pr
oces
s w
ould
be
esta
blis
hed
to c
onsi
der
this
mat
ter
as it
per
tain
s to
BC
. 4
Inte
nded
for
CIP
-003
-6 a
nd to
be
held
in a
beya
nce
and
be o
f no
forc
e or
effe
ct in
B.C
. due
to te
chni
cal s
uita
bilit
y is
sues
. Whe
n ad
opte
d by
FE
RC
, the
NE
RC
app
rove
d
CIP
-003
-7(i)
will
ret
ire th
e N
ER
C G
loss
ary
term
s. C
IP-0
03-7
(i) is
ant
icip
ated
to b
e as
sess
ed in
the
next
MR
S A
sses
smen
t Rep
ort.
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Low
Impa
ct E
xter
nal R
outa
ble
Con
nect
ivity
4 LE
RC
R
epor
t No.
10
A
dopt
ion
Not
rec
omm
ende
d fo
r ad
optio
n in
B.C
at t
his
time.
Min
imum
Veg
etat
ion
Cle
aran
ce
Dis
tanc
e M
VC
D
Rep
ort N
o. 7
R
-32-
14
Ado
ptio
n A
ugus
t 1, 2
015
Mis
oper
atio
n -
Rep
ort N
o. 9
R
-32-
16
Ado
ptio
n O
ctob
er 1
, 201
7
Mos
t Sev
ere
Sin
gle
Con
tinge
ncy1
MS
SC
R
epor
t No.
10
A
dopt
ion
Nat
ive
Bal
anci
ng A
utho
rity
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Non
-Con
sequ
entia
l Loa
d Lo
ss
- T
PL-
001-
4 R
epor
t
Ado
ptio
n
Ope
ratin
g In
stru
ctio
n -
Rep
ort N
o. 9
R
-32-
16
Ado
ptio
n A
pril
1, 2
017
Ope
ratio
nal P
lann
ing
Ana
lysi
s2 -
Rep
ort N
o. 6
R
-41-
13
Ado
ptio
n D
ecem
ber
12, 2
013
Ope
ratio
nal P
lann
ing
Ana
lysi
s2 -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n O
ctob
er 1
, 201
5
Ope
ratio
nal P
lann
ing
Ana
lysi
s -
Rep
ort N
o. 9
R
-32-
16
Ado
ptio
n O
ctob
er 1
, 201
6
Ope
ratio
ns S
uppo
rt P
erso
nnel
-
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n A
lign
with
effe
ctiv
e da
te o
f Req
uire
men
t 5 o
f the
P
ER
-005
-2 s
tand
ard
whe
re th
is te
rm is
ref
eren
ced
Phy
sica
l Acc
ess
Con
trol
Sys
tem
s P
AC
S
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Phy
sica
l Sec
urity
Per
imet
er
PS
P
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Pla
nnin
g A
sses
smen
t -
TP
L-00
1-4
Rep
ort
A
dopt
ion
Pla
nnin
g A
utho
rity
PA
R
epor
t No.
10
A
dopt
ion
Poi
nt o
f Rec
eipt
P
OR
R
epor
t No.
10
A
dopt
ion
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Pre
-Rep
ortin
g C
ontin
genc
y E
vent
AC
E
Val
ue1
- R
epor
t No.
10
A
dopt
ion
Pro
tect
ed C
yber
Ass
ets2
PC
A
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Pro
tect
ed C
yber
Ass
ets
PC
A
Rep
ort N
o. 1
0
Ado
ptio
n
Pro
tect
ion
Sys
tem
-
R
epor
t No.
6
R-4
1-13
A
dopt
ion
Janu
ary
1, 2
015
for
each
ent
ity to
mod
ify it
s pr
otec
tion
syst
em m
aint
enan
ce a
nd te
stin
g pr
ogra
m to
ref
lect
the
new
def
initi
on (
to c
oinc
ide
with
rec
omm
ende
d ef
fect
ive
date
of P
RC
-005
-1b)
and
unt
il th
e en
d of
the
first
co
mpl
ete
mai
nten
ance
and
test
ing
cycl
e to
impl
emen
t any
ad
ditio
nal m
aint
enan
ce a
nd te
stin
g fo
r ba
ttery
cha
rger
s as
re
quire
d by
that
ent
ity’s
pro
gram
.
Pro
tect
ion
Sys
tem
Mai
nten
ance
P
rogr
am
PS
MP
R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of R
equi
rem
ent 1
of t
he
PR
C-0
05-2
sta
ndar
d w
here
this
term
is r
efer
ence
d
Pro
tect
ion
Sys
tem
Mai
nten
ance
P
rogr
am (
PR
C-0
05-4
)5 P
SM
P
Rep
ort N
o. 9
- N
ot r
ecom
men
ded
for
adop
tion
in B
.C a
t thi
s tim
e.
Pro
tect
ion
Sys
tem
Mai
nten
ance
P
rogr
am (
PR
C-0
05-6
) P
SM
P
Rep
ort N
o. 1
0
Ado
ptio
n
Pse
udo-
Tie
-
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n O
ctob
er 1
, 201
5
Rea
ctiv
e P
ower
-
Rep
ort N
o. 1
0
Ado
ptio
n
Rea
l Pow
er
- R
epor
t No.
10
A
dopt
ion
Rea
l-tim
e A
sses
smen
t2 -
Rep
ort N
o. 6
R
-41-
13
Ado
ptio
n Ja
nuar
y 1
, 201
4
Rea
l-tim
e A
sses
smen
t -
Rep
ort N
o. 9
R
-32-
16
Ado
ptio
n O
ctob
er 1
, 201
6
5
Inte
nded
for
relia
bilit
y st
anda
rd P
RC
-005
-4 w
hich
was
def
erre
d by
FE
RC
and
is n
ot in
clud
ed in
Ass
essm
ent R
epor
t No.
9.
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Rel
iabi
lity
Adj
ustm
ent A
rran
ged
Inte
rcha
nge
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Rel
iabi
lity
Coo
rdin
ator
R
C
Rep
ort N
o. 1
0
Ado
ptio
n
Rel
iabi
lity
Dire
ctiv
e -
Rep
ort N
o. 9
R
-32-
16
Ret
irem
ent
Juky
18,
201
6
Rel
iabi
lity
Sta
ndar
d2 -
Rep
ort N
o. 8
R
-32-
14
Ado
ptio
n O
ctob
er 1
, 201
5
Rel
iabi
lity
Sta
ndar
d -
Rep
ort N
o. 1
0
Ado
ptio
n
Rel
iabl
e O
pera
tion2
- R
epor
t No.
8
R-3
2-14
A
dopt
ion
Oct
ober
1, 2
015
Rel
iabl
e O
pera
tion
- R
epor
t No.
10
A
dopt
ion
Rel
ief R
equi
rem
ent (
WE
CC
Reg
iona
l T
erm
) -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n A
lign
with
effe
ctiv
e da
te o
f IR
O-0
06-W
EC
C-2
sta
ndar
d w
here
this
term
is r
efer
ence
d
Rem
edia
l Act
ion
Sch
eme
R
AS
R
epor
t No.
1
G-6
7-09
A
dopt
ion
June
4, 2
009
Rem
edia
l Act
ion
Sch
eme
RA
S
Rep
ort N
o. 9
- T
o be
det
erm
ined
3
Rem
ovab
le M
edia
-
Rep
ort N
o. 1
0
Ado
ptio
n
Rep
orta
ble
Bal
anci
ng C
ontin
genc
y E
vent
1 -
Rep
ort N
o. 1
0
Ado
ptio
n
Rep
orta
ble
Cyb
er S
ecur
ity In
cide
nt
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
whe
re th
is te
rm is
ref
eren
ced.
Req
uest
for
Inte
rcha
nge
RF
I R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Res
erve
Sha
ring
Gro
up
- R
epor
t No.
10
A
dopt
ion
Res
erve
Sha
ring
Gro
up R
epor
ting
AC
E1
- R
epor
t No.
10
A
dopt
ion
Res
ourc
e P
lann
er
RP
R
epor
t No.
10
A
dopt
ion
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Sin
k B
alan
cing
Aut
horit
y -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n O
ctob
er 1
, 201
5
Sou
rce
Bal
anci
ng A
utho
rity
- R
epor
t No.
8
R-3
8-15
A
dopt
ion
Oct
ober
1, 2
015
Spe
cial
Pro
tect
ion
Sys
tem
(R
emed
ial
Act
ion
Sch
eme)
S
PS
R
epor
t No.
1
G-6
7-09
A
dopt
ion
June
4, 2
009
Spe
cial
Pro
tect
ion
Sys
tem
(R
emed
ial
Act
ion
Sch
eme)
S
PS
R
epor
t No.
10
A
dopt
ion
Sys
tem
Ope
ratin
g Li
mit
- R
epor
t No.
10
A
dopt
ion
Sys
tem
Ope
rato
r -
Rep
ort N
o. 8
R
-38-
15
Ado
ptio
n
Alig
n w
ith e
ffect
ive
date
of C
IP V
ersi
on 5
sta
ndar
ds
(CIP
-002
-5.1
, CIP
-003
-5, C
IP-0
04-5
, CIP
-005
-5,
CIP
-006
-5, C
IP-0
07-5
, CIP
-008
-5, C
IP-0
09-5
, CIP
-010
-1,
and
CIP
-011
-1)
as r
efer
ence
is m
ade
to th
e te
rm C
ontr
ol
Cen
ter
as p
art o
f the
def
initi
on o
f Sys
tem
Ope
rato
r. T
he
term
Con
trol
Cen
ter
is in
turn
ref
eren
ced
from
the
CIP
V
ersi
on 5
sta
ndar
ds.
Tot
al In
tern
al D
eman
d -
Rep
ort N
o. 9
R
-32-
16
Ado
ptio
n O
ctob
er 1
, 201
6
Tra
nsie
nt C
yber
Ass
et
- R
epor
t No.
10
A
dopt
ion
Tra
nsm
issi
on C
usto
mer
-
Rep
ort N
o. 1
0
Ado
ptio
n
Tra
nsm
issi
on O
pera
tor
TO
P
Rep
ort N
o. 1
0
Ado
ptio
n
Tra
nsm
issi
on O
wne
r T
O
Rep
ort N
o. 1
0
Ado
ptio
n
Tra
nsm
issi
on P
lann
er
TP
R
epor
t No.
10
A
dopt
ion
Tra
nsm
issi
on S
ervi
ce P
rovi
der
TS
P
Rep
ort N
o. 1
0
Ado
ptio
n
Und
er V
olta
ge L
oad
She
ddin
g P
rogr
am
- R
epor
t No.
9
-
To
be d
eter
min
ed3
Rig
ht-o
f-W
ay
RO
W
Rep
ort N
o. 7
R
-32-
14
Ado
ptio
n A
ugus
t 1, 2
015
TLR
(T
rans
mis
sion
Loa
ding
Rel
ief)
Log
-
Rep
ort N
o. 7
R
-32-
14
Ado
ptio
n A
ugus
t 1, 2
014
NE
RC
Glo
ssar
y T
erm
A
cro
nym
A
sses
smen
t R
epo
rt N
um
ber
C
om
mis
sio
n
Ord
er
Nu
mb
er
Co
mm
issi
on
A
do
pti
on
or
Ret
irem
ent
Eff
ecti
ve D
ate
Veg
etat
ion
Insp
ectio
n -
Rep
ort N
o. 7
R
-32-
14
Ado
ptio
n A
ugus
t 1, 2
015
Ta
ble
2
NE
RC
Glo
ssa
ry A
do
pti
on
His
tory
in
B.C
.
NE
RC
Glo
ssar
y o
f T
erm
s V
ersi
on
Dat
e
Ass
essm
ent
Rep
ort
N
um
ber
Co
mm
issi
on
Ord
er
Ad
op
tio
n D
ate
Co
mm
issi
on
O
rder
A
do
pti
ng
Eff
ecti
ve D
ate
Feb
ruar
y 12
, 200
8 R
epor
t No.
1
June
4, 2
009
G‐6
7‐09
T
he N
ER
C G
loss
ary
is e
ffect
ive
as
of th
e da
te o
f the
Ord
er (
June
4, 2
009)
Apr
il 20
, 201
0 R
epor
t No.
2
Nov
embe
r 10
, 201
0 G
-167
-10
The
NE
RC
Glo
ssar
y is
effe
ctiv
e a
s of
the
date
of t
he O
rder
(N
ovem
ber
10, 2
010)
Aug
ust 4
, 201
1 R
epor
t No.
3
Sep
tem
ber
1, 2
011
G-1
62-1
1 R
epla
cing
G‐1
51‐1
1 T
he N
ER
C G
loss
ary
is e
ffect
ive
as o
f the
dat
e of
the
Ord
er (
Sep
tem
ber
1, 2
011)
Dec
embe
r 13
, 201
1 R
epor
t No.
5
Janu
ary
15, 2
013
R-1
-13
The
NE
RC
Glo
ssar
y is
effe
ctiv
e as
of t
he d
ate
of th
e O
rder
(Ja
nuar
y 15
, 201
3)
NE
RC
Glo
ssar
y te
rms
whi
ch h
ave
not b
een
appr
oved
by
FE
RC
are
of n
o fo
rce
or
effe
ct
Dec
embe
r 5,
201
2 R
epor
t No.
6
Dec
embe
r 12
, 201
3 R
-41-
13
The
NE
RC
Glo
ssar
y is
effe
ctiv
e as
of t
he d
ate
of th
e O
rder
(D
ecem
ber
12, 2
013)
The
effe
ctiv
e da
te o
f the
new
and
rev
ised
NE
RC
Glo
ssar
y te
rms
adop
ted
in th
e O
rder
is
the
date
app
earin
g in
the
tabl
e fo
und
in A
ttach
men
t A to
the
Ord
er
NE
RC
Glo
ssar
y te
rms
whi
ch h
ave
not b
een
appr
oved
by
FE
RC
are
of n
o fo
rce
or
effe
ct
NE
RC
Glo
ssar
y o
f T
erm
s V
ersi
on
Dat
e
Ass
essm
ent
Rep
ort
N
um
ber
Co
mm
issi
on
Ord
er
Ad
op
tio
n D
ate
Co
mm
issi
on
O
rder
A
do
pti
ng
Eff
ecti
ve D
ate
Janu
ary
2, 2
014
Rep
ort N
o. 7
Ju
ly 1
7, 2
014
R-3
2-14
The
NE
RC
Glo
ssar
y is
effe
ctiv
e as
of t
he d
ate
of th
e O
rder
(Ju
ly 1
7, 2
014)
The
effe
ctiv
e da
te o
f the
new
and
rev
ised
NE
RC
Glo
ssar
y te
rms
adop
ted
in th
e O
rder
is
the
date
app
earin
g in
the
tabl
e fo
und
in A
ttach
men
t A to
the
Ord
er. E
ach
Glo
ssar
y te
rm to
be
supe
rsed
ed b
y a
revi
sed
Glo
ssar
y te
rm a
dopt
ed in
the
Ord
er s
hall
rem
ain
in e
ffect
unt
il th
e ef
fect
ive
date
of t
he G
loss
ary
term
sup
erse
ding
it.
The
NE
RC
Glo
ssar
y te
rms
liste
d in
the
tabl
es fo
und
in A
ttach
men
t C to
the
Ord
er a
re
all o
f the
NE
RC
Glo
ssar
y te
rms
in e
ffect
in B
.C. a
s of
the
effe
ctiv
e da
tes
liste
d in
the
tabl
es o
f Atta
chm
ent C
to th
e O
rder
. T
he e
ffect
ive
date
s fo
r th
e N
ER
C G
loss
ary
term
s th
at a
re li
sted
in th
e ta
bles
foun
d in
Atta
chm
ent C
sup
erse
de th
e ef
fect
ive
date
s th
at w
ere
incl
uded
in a
ny s
imila
r lis
t app
ende
d to
any
pre
viou
s or
der.
NE
RC
Glo
ssar
y te
rms
whi
ch h
ave
not b
een
appr
oved
by
FE
RC
are
of n
o fo
rce
or
effe
ct.
The
Ele
ctric
Rel
iabi
lity
Cou
ncil
of T
exas
, Nor
thea
st P
ower
Coo
rdin
atin
g C
ounc
il an
d R
elia
bilit
y F
irst r
egio
nal d
efin
ition
s lis
ted
at th
e en
d of
the
NE
RC
Glo
ssar
y of
Ter
ms
are
of n
o fo
rce
or e
ffect
in B
.C.
Oct
ober
1, 2
014
Rep
ort N
o. 8
Ju
ly 2
4, 2
015
R-3
8-15
T
he N
ER
C G
loss
ary
is e
ffect
ive
as o
f the
dat
e of
Com
mis
sion
Ord
er R
-38-
15.
Dec
embe
r 7,
201
5 B
AL-
001-
2 A
pril
21, 2
016
R-1
4-16
The
BA
L-00
1-2
Glo
ssar
y T
erm
s (I
nter
conn
ectio
n, R
egul
atio
n R
eser
ve S
harin
g G
roup
, R
epor
ting
Ace
and
Res
erve
Sha
ring
Gro
up R
epor
ting
Ace
) ar
e ef
fect
ive
as o
f Ju
ly 1
, 201
6.1
Dec
embe
r 7,
201
5 R
epor
t No.
9
July
18,
201
6 R
-32-
16
The
NE
RC
Glo
ssar
y is
effe
ctiv
e as
of J
uly
18, 2
016.
The
effe
ctiv
e da
te o
f the
new
and
rev
ised
NE
RC
Glo
ssar
y te
rms
adop
ted
in th
e O
rder
is
the
date
app
earin
g in
the
tabl
e fo
und
in A
ttach
men
t A to
the
Ord
er.
Nov
embe
r 2
8, 2
016
Rep
ort N
o. 1
0
1
With
the
adop
tion
of th
e N
ER
C G
loss
ary
as p
art o
f MR
S A
sses
smen
t Rep
ort N
o. 9
, the
BA
L-00
1-2
Glo
ssar
y T
erm
s ar
e no
long
er e
xcep
tions
to th
e N
ER
C G
loss
ary
and
so a
re
not i
nclu
ded
in T
able
1.