US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

Embed Size (px)

Citation preview

Page 1: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

US Army Corps of Engineers Budgeting Process

Sherry L. Adams

Project Manager, Huntington District

Page 2: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

“High Priority” Missions: Flood Damage Reduction Commercial Navigation Ecosystem Restoration

Beach Erosion/Hurricane ProtectionFlooding

Navigation

Environmental Infrastructure Needs

Water Supply

Lock / Dam Replacement - Inland Waterways System

Salmon Mitigation

Ecosystem Restoration

Port / Harbor Deepenings

Waterfront Development

Environmental Infrastructure Needs

Environ. Restoration

Wetland Losses

Letter to Corps District OfficeLetter to Corps District Office

Inform Congressional RepresentativeInform Congressional Representative

Page 3: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

Senate Resolution House Resolution

Authority - Congress! Study Resolutions WRDA Bills Standing Authorities Appropriations Bills

OR

- Signed by President

Transportation & Infrastructure

Committee

Environment & Public Works

Committee

MemberMember( Step 1 )

Passage ~ 2-yr. Intervals

Have we studied

the problem before?

Page 4: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

President’s Budget ( G I )

HQUSACE

DIVISION

(Step 2 )

“High Priority” Missions

Flood Damage Reduction Navigation Ecosystem Restoration

WRDA

HR/SR

Coordination

Budget Cycle 1/

Page 5: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

HQ Provides Budget Guidance ( Mar )

HQ Review & Approval

( May -Jun )

Budget Presented to Sec. Army(Jul - Aug )

OMB Passback( Nov )

Budget Submitted to OMB ( Sep )

President’s Budgetto Congress ( Feb )

Field Offices DevelopProgram Requirements

( Apr - May )

Appropriations Bills( Jul - Sep )

Cong. Hearings ( Mar - Apr )

President Signs Approp. Bill ( Sep - Oct )

OMB Provides Budget Guidance ( Jan )

Funding Alloc. To Field Offices

( Oct - Dec )

Page 6: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

• Projects with smaller scope, cost and complexity

• Delegated authority to design and construct without specific Congressional authorization

Continuing Authority Program (CAP)

Page 7: US Army Corps of Engineers Budgeting Process Sherry L. Adams Project Manager, Huntington District

Existing CAP Funding Policies

• Complete existing construction projects

• No new project cooperation agreements

• Congressional authorization for start or continuation of study (Naming or earmark)