MOODY NOLAN | PERKINS+WILL UPPER ARLINGTON SCHOOLS BUILDING TEAM MEETING #3 GREENSVIEW ELEMENTARY SCHOOL JANUARY 12, 2016 YOUR VOICE MATTERS MOODY NOLAN PERKINS+WILL HILLIARD JEANE KORDA EMH&T MKSK TURNER

UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

MOODY NOLAN | PERKINS+WILL

UPPER ARLINGTON SCHOOLSBUILDING TEAM MEETING #3

GREENSVIEW ELEMENTARY SCHOOLJANUARY 12, 2016

YOURVOICE MATTERS

MOODY NOLAN PERKINS+WILL HILLIARD JEANE KORDA EMH&T MKSK TURNER

Page 2: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

Affirm

Guiding

Principles

Present

Facilities

Analysis

Findings

Evaluate

Master

Plan

Options

Evaluate

Revised

Master

Plan

Options

CES 1 CES 2 CES 3 CES 4

SEPT 9+10 NOV 18+19 FEB 23+24 APR 19+20

Review

Financials

CES 5

TBD 2017

BTM 1

BTM 2

BT SUMMIT

BTM 3

SEP 29–OCT 1

NOV 10-12

DEC 3

JAN 12-14

BTM 4MAR 15-17

OUR PROGRESS

Page 3: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

••

••

••

••

••

••

Page 4: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

••••••••

•••••••••••

Page 5: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

••••••••••••

••••••

Page 6: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

Page 7: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

Page 8: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

215

758

418

598

508

407

CURRENT ENROLLMENT

BURBANK

BARRINGTON

GREENSVIEW

TREMONT

WICKLIFFE

WINDERMERE

1 Source: Upper Arlington Enrollment Projections-(November 2015)

CURRENTSF/STUDENT

177 SF

112 SF

115 SF

133 SF*

100 SF

135 SF

* With planned additions

10 YEARSF/STUDENT

N/A

96 SF

91 SF

106 SF

86 SF

111 SF

10 YEAR PROJECTION

N/A

887

526

749

589

494

1

SQUARE FEET PER STUDENT

Page 9: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

701

705

1,816

SQUARE FEET PER STUDENT

HASTINGS

JONES

UAHS

1 Source: Upper Arlington Enrollment Projections-(November 2015)

717

806

1,947

191 SF

186 SF

162 SF

187 SF

162 SF

151 SF

CURRENT ENROLLMENT

CURRENTSF/STUDENT

10 YEARSF/STUDENT

10 YEAR PROJECTION

1

Page 10: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

GREENSVIEW ELEMENTARY SCHOOLMAJOR CHALLENGES

BUILDING:

• LACK OF SECURE ENTRY VESTIBULE

• SIZE OF CLASSROOMS

• LIBRARY SIZE AND CONFIGURATION DOES NOT

SUPPORT COLLABORATION

• LACK OF COLLABORATIVE SPACE

• FOOD SERVICE CONFIGURATION INCREASES TIME TO

GET FOOD

• SOME DISJOINTED SUPPORT OFFICE LOCATIONS

• SP ED - MD ROOM IS NOT CENTRALLY LOCATED

• LIMITED ADJACENT STORAGE FOR MPR

• NOT ENOUGH STUDENT STORAGE, CONDITION OF

STUDENT STORAGE

• NO ROOM FOR SEATING IN THE GYM

SITE:

• LACK OF CLEAR MAIN ENTRY

• NO SECURE OUTDOOR LEARNING SPACE

Page 11: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

CHRONOLOGY DIAGRAMGREENSVIEW ELEMENTARY SCHOOL

Page 12: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

CIRCULATION ANALYSISGREENSVIEW ELEMENTARY SCHOOL

LENGTH FROM ONE END OF THE BUILDING TO THE OTHER: 640 LINEAR FEET

AVERAGE WIDTH OF CORRIDOR:8 FEET

Page 13: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

CLASSROOM SIZE ANALYSISGREENSVIEW ELEMENTARY SCHOOL

Page 14: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner
Page 15: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

SECURITY ANALYSISGREENSVIEW ELEMENTARY SCHOOL

Main Entry

Page 16: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner
Page 17: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner
Page 18: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REPAIR +

RENOVATE +

REBUILD

Infrastructure: Maintain/upgrade to working order # of Teaching Spaces: Added spaces right-sized to accommodate year 6 enrollment projection, assumes 25 students per classroom

Program: Limited or no change Core Spaces: (Cafeteria/MPR): Sized to year 10 enrollment projection w/minimum time for lunch (max: three lunches)

Physical Appearance: No significant change Kindergarten: Assumes full-day (20 students per classroom)

Infrastructure: Change uses of existing structure or expand to allow better use

# of Teaching Spaces: Right-sized spaces added to accommodate year 6 enrollment projection, assumes 25 students per classroom

Program: Some alteration possible Core Spaces: (Cafeteria/MPR): Sized to year 10 enrollment projection (two lunches), gym sized to elementary school standard (HS court size)

Physical Appearance: Change mostly limited to interiors and/or expansion

Kindergarten: Assumes full-day (20 students per classroom)

Infrastructure: New and optimized # of Teaching Spaces: Right-sized spaces included to accommodate year 6 enrollment projection, assumes 25 students per room

Program: Addresses deficiencies Core Spaces: (Cafeteria/MPR): Sized to year 10 enrollment projection (two lunches), gym sized to elementary school standard (HS court size)

Physical Appearance: Completely new Kindergarten: Assumes full-day (20 students per classroom)

NOTE: Two or more strategies can be combined

Page 19: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

Page 20: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REPAIR• REPAIRED CLASSROOMS• REPAIR EXISTING PER

PHYSICAL ASSESSMENT REPORT

RENOVATE• ADMIN AND SECURE

VESTIBULE AT ENTRY• MEDIA CENTER

REBUILD• SOME NEW, LARGER

CLASSROOMS

NOT MODIFIED:• EXISTING TO REMAIN• MOST CLASSROOM SIZES• MULTIPURPOSE ROOM

AND KITCHEN SIZES

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 21: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 22: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REPAIR• REPAIRED CLASSROOMS• REPAIR EXISTING PER

PHYSICAL ASSESSMENT REPORT

RENOVATE• ADMIN AND SECURE

VESTIBULE AT ENTRY• MEDIA CENTER

REBUILD• SOME NEW, LARGER

CLASSROOMS

NOT MODIFIED:• EXISTING TO REMAIN• MOST CLASSROOM SIZES• MULTIPURPOSE ROOM AND

KITCHEN SIZES

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 23: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 24: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

RENOVATE• LARGER CLASSROOMS• LARGER MEDIA CENTER• LARGER ADMINISTRATION• LARGER MULTIPURPOSE

ROOM AND KITCHEN/ RECEIVING

• SECURE VESTIBULE AT ENTRY

• NEW COLLABORATION SPACE• NEW LOBBY SPACE

REBUILD• NEW, LARGER CLASSROOMS

AND COLLABORATION SPACE• NEW, LARGER GYMNASIUM

NOT MODIFIED:• EXISTING TO REMAIN

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 25: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 26: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

RENOVATE• LARGER CLASSROOMS• LARGER MEDIA CENTER• LARGER ADMINISTRATION

SECURE VESTIBULE AT ENTRY

• NEW COLLABORATION SPACE

• NEW LOBBY SPACE

REBUILD• NEW, LARGER

CLASSROOMS • NEW, LARGER MULTI-

PURPOSE ROOM AND KITCHEN/ RECEIVING

• NEW GYMNASIUM

NOT MODIFIED:• EXISTING TO REMAIN

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 27: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD

RENOVATE• LARGER CLASSROOMS• LARGER MEDIA CENTER• LARGER ADMINISTRATION

SECURE VESTIBULE AT ENTRY

• NEW COLLABORATION SPACE

• NEW LOBBY SPACE

REBUILD• NEW, LARGER

CLASSROOMS • NEW, LARGER MULTI-

PURPOSE ROOM AND KITCHEN/ RECEIVING

• NEW GYMNASIUM

NOT MODIFIED:• EXISTING TO REMAIN

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 28: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 29: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD

RENOVATE• LARGER CLASSROOMS• LARGER MEDIA CENTER• LARGER ADMINISTRATION

SECURE VESTIBULE AT ENTRY

• NEW COLLABORATION SPACE

• NEW LOBBY SPACE

REBUILD• NEW, LARGER

CLASSROOMS • NEW, LARGER MULTI-

PURPOSE ROOM AND KITCHEN/ RECEIVING

• NEW GYMNASIUM

NOT MODIFIED:• EXISTING TO REMAIN

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 30: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD

RENOVATE• LARGER CLASSROOMS• LARGER MEDIA CENTER• LARGER ADMINISTRATION

SECURE VESTIBULE AT ENTRY

• NEW COLLABORATION SPACE

• NEW LOBBY SPACE

REBUILD• NEW, LARGER

CLASSROOMS • NEW, LARGER MULTI-

PURPOSE ROOM AND KITCHEN/ RECEIVING

• NEW GYMNASIUM

NOT MODIFIED:• EXISTING TO REMAIN

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 31: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 32: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

65

NORTH

NEW BUILDING ZONE

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 33: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

65

RENOVATE• LARGER MEDIA CENTER• LARGER ADMINISTRATION

SUITE

REBUILDNEW AND LARGER: • CLASSROOMS• COLLABORATION SPACE• ART AND MUSIC

CLASSROOMS• MEDIA CENTER• GYMNASIUM• MULTIPURPOSE ROOM

AND KITCHEN• ADMINISTRATION SUITE

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 34: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD

RENOVATE• LARGER MEDIA CENTER• LARGER ADMINISTRATION

SUITE

REBUILDNEW AND LARGER: • CLASSROOMS• COLLABORATION SPACE• ART AND MUSIC

CLASSROOMS• MEDIA CENTER• GYMNASIUM• MULTIPURPOSE ROOM

AND KITCHEN• ADMINISTRATION SUITE

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 35: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 36: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

NEW BUILDING ZONE

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 37: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REBUILDNEW AND LARGER:• CLASSROOMS• COLLABORATION SPACE• ART AND MUSIC

CLASSROOMS• MEDIA CENTER• GYMNASIUM• MULTIPURPOSE ROOM

AND KITCHEN• ADMINISTRATION SUITE

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 38: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REBUILDNEW AND LARGER:• CLASSROOMS• COLLABORATION SPACE• ART AND MUSIC

CLASSROOMS• MEDIA CENTER• GYMNASIUM• MULTIPURPOSE ROOM

AND KITCHEN• ADMINISTRATION SUITE

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 39: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 40: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

NEW BUILDING ZONE

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 41: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REBUILDNEW AND LARGER:• CLASSROOMS• COLLABORATION SPACE• ART AND MUSIC

CLASSROOMS• MEDIA CENTER• GYMNASIUM• MULTIPURPOSE ROOM

AND KITCHEN• ADMINISTRATION SUITE

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 42: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

REBUILDNEW AND LARGER:• CLASSROOMS• COLLABORATION SPACE• ART AND MUSIC

CLASSROOMS• MEDIA CENTER• GYMNASIUM• MULTIPURPOSE ROOM

AND KITCHEN• ADMINISTRATION SUITE

NORTH

EXISTING TO REMAIN

DEMOLISH

REPAIR

RENOVATE

REBUILD DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016

Page 43: UPPER ARLINGTON SCHOOLS · building team meeting #3 greensview elementary school january 12, 2016 your voice matters moody nolan perkins+will hilliard jeane korda emh&t mksk turner

NORTH

DRAFT PRELIMINARY CONCEPT MASTER PLAN – JANUARY 12, 2016