38
TNPA 2 nd Strategic Customer Forum Update on Infrastructure Projects 13 August 2014

Update on Infrastructure Projects

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Update on Infrastructure Projects

1

TNPA 2nd Strategic Customer Forum

Update on Infrastructure Projects 13 August 2014

Page 2: Update on Infrastructure Projects

THE TNPA WORLD OF

PORT INFRASTRUCTURE

Page 3: Update on Infrastructure Projects

Pixman Images 2010 Dredging International - Pallieter

Complete

Page 4: Update on Infrastructure Projects

Overview of Presentation

• TNPA’s 7 year Capital Program starting 2014/15.

• Projects already Sanctioned

• Projects being planned in 7 year capital program

TNPA Infrastructure Projects 4

Page 5: Update on Infrastructure Projects

8 x Commercial South African Ports

Richards Bay

Durban

East London

Cape Town Mossel Bay

Port Elizabeth

Ngqura (Coega)

Saldanha

Port Nolloth

Johannesburg

SOUTH AFRICA

2,798 km of

Coastline Courtesy Google earth

Page 6: Update on Infrastructure Projects

The 8 x Existing Ports + DDOP

WESTERN PORTS Saldanha Bay Cape Town Mossel Bay

CENTRAL PORTS Port Elizabeth Ngqura East London

EASTERN

PORTS Durban New Durban dig-out Port Richards Bay

Page 7: Update on Infrastructure Projects

7

TNPA 7 year Capital Program – Starting 14/15 per PORT

PORT Rand

billions %

Cape Town 1.26 2.9

Durban 14.31 32.9

Dredging Services 0.89 2.1

East London 1.70 3.9

Head Quarters 4.23 9.7

Lighthouses 0.42 1.0

Mossel Bay 0.06 0.1

Ngqura 12.85 29.5

Port Elizabeth 0.82 1.9

Richards Bay 2.83 6.5

Saldanha 4.14 9.5

TOTAL TNPA 43.51 100

Page 8: Update on Infrastructure Projects

8

TNPA 7 year Capital Program – Starting 14/15 per YEAR

TRANSNET AUDITED RESULTS 2014

Year Financial

year

Rand

billions %

1 2014/15 2.37 5.4

2 2015/16 6.01 13.8

3 2016/17 8.58 19.7

4 2017/18 9.93 22.8

5 2018/19 5.50 12.6

6 2019/20 5.74 13.2

7 2020/21 5.38 12.4

TOTAL 43.51 100

Page 9: Update on Infrastructure Projects

9

Major Projects Sanctioned

# Project FFC million Start Completion

1 Durban Sand Hopper Station 188.95 3 July 2012 22 Jan 2016

2 Durban Maydon Wharf Rehabilitation 1,456.40 1 May 2014 1 Dec 2016

Durban HV electrical Upgrade 103.02 11 July 2013 1 Aug 2014

3 Richards Bay Truck Staging 126.73 27 Jan 2014 13 June 2015

Richards Bay Power supply to Harbour

West upgrade 40.00 25 March 2014 10 March 2015

4 East London Foreshore 191.25 1 April 2014 10 March 2016

5 Port Elizabeth Slipways x 2 229.00 1 Oct 2014 26 Oct 2016

6 Ngqura Administration Building & Small

Craft Basin

Included in overall port

sanction Started 28 July 2016

7 Ngqura Berth A100 & Tank Farm

landside services 2,487.68 1 April 2015 4 July 2018

8 Ngqura Manganese Busy with detail

design 27 July 2018

9 Cape Town Fire Fighting 89.15 16 Apr 2014 16 Apr 2016

10 Saldanha General Maintenance Quay

(GMQ) 200.83 30 Oct 2014 31 March 2016

Page 10: Update on Infrastructure Projects

New Sand Hopper Berth & Pump Station

Page 11: Update on Infrastructure Projects

New Sand Hopper Berth & Pump Station

Scope:

• Construction of New Sand Hopper and Pump Station at A Berth to replace

the original hopper station that was demolished during Entrance Channel

Widening

Purpose:

• To reinstate the natural migration of sand along the coast by supplying sand

to the city beaches.

• Prevent the entrance channel from silting up

Page 12: Update on Infrastructure Projects

Durban New Sand Hopper Berth & Pump Station

Page 13: Update on Infrastructure Projects

Sand Hopper progress as at July 2014

13

Page 14: Update on Infrastructure Projects

Maydon Wharf rehabilitation of berths 1 to 4 and 13 to 14

14

Scope

• Replace old steel sheet pile berths 1-4, and 12-14, with new deep water berths.

Purpose:

• Provide infrastructure to sustain existing port operations and cater for growth in cargo volumes.

Risks:

• Berths at risk of failure, if not reconstructed.

• Berth capacity constraint during construction.

Mitigations:

• Implement Berth Monitoring Surveys.

• Fast track reconstruction program.

• Berth 12 is being reconstructed to create additional capacity for when the remainder of the sheet

pile berths are reconstructed.

Page 15: Update on Infrastructure Projects

Maydon Wharf - Berth Reconstruction

Steel Sheet Pile Walls (Current Project)

Page 16: Update on Infrastructure Projects

Maydon Wharf berth 1 – start of construction

16

Page 17: Update on Infrastructure Projects

Completed Maydon Wharf berth 12

17

Page 18: Update on Infrastructure Projects

18

Projects being planned in 7 year capital program

1. Durban Berth Deepening

2. Durban Pier 1 Phase 2

3. Durban Dig Out Port (DDOP) – including land acquisition

4. RB Land Acquisition

5. Ngqura Liquid Berth A100 and Landside services

6. Ngqura General Cargo Berth B101

7. Saldanha Iron Ore Quay

8. Saldanha Oil & Gas Repair Quay

9. Saldanha Mosgas Quay extension

Page 19: Update on Infrastructure Projects

Berth Deepening Durban

• Deepen Container Terminal berths from -12.8m CD (Port) to -17.0m CD (Port)

• Extend length of existing quay wall from 915 m to 1190 m to accommodate 3 x 350 m

long vessels

• Ensure the larger container vessels with a draft of 14.5 m can be accommodated

• Vessel size 9,200 TEU or (14,000 TEU light)

• 4.0 million m3 of dredging

• 1.0 million m3 reclamation

19

Page 20: Update on Infrastructure Projects

Project Motivation

1,000 TEU Vessel and 4 ton Wharf Crane

6,000 TEU Vessel and 80 ton STS crane (12,000 TEU already calling light)

Page 21: Update on Infrastructure Projects

21

North Quay - berths 203 to 205

Existing Sandbank

Page 22: Update on Infrastructure Projects

Caisson Deepening Solution

Page 23: Update on Infrastructure Projects
Page 24: Update on Infrastructure Projects

Existing dredged limits

Proposed dredged limit

Proposed quay wall extension

Page 25: Update on Infrastructure Projects

• Reclaim 12 hectares to create a Container Terminal of 1.8 million TEU per

annum

• Design vessel size 9,200 TEU to 14,000 TEU light

• Draft of 14.5 m

• Water depth required = 16.5 m

• 1,180 m of productive quay length

• 1.0 million m3 of dredging

• 2.8 million m3 reclamation

Pier 1 Phase 2 (Salisbury Island) Container Terminal Durban

Page 26: Update on Infrastructure Projects

Salisbury Island

Existing Navy boundary

Proposed Navy Boundary

New Terminal boundary

Page 27: Update on Infrastructure Projects

2.8 million m3

of reclamation

Page 28: Update on Infrastructure Projects
Page 29: Update on Infrastructure Projects

Durban Dig Out Port

Example of the typical terminal layouts from CONCEPT stage

Page 30: Update on Infrastructure Projects

Aerial View – Old DIA Site

Page 31: Update on Infrastructure Projects

Artist’s Impression of Durban Dig Out Port

Page 32: Update on Infrastructure Projects

Port of Ngqura: Proposed New Liquid Bulk Berth & General Cargo

Berth

• Purpose is to construct

• New Liquid bulk berth A100 with capacity of 4 Mtpa

• New General Cargo berth B101 with capacity of 1 Mtpa

• Design vessel sizes 100 000 DWT carriers

• Water Depth required = 18 m

• Dredging volume = 1.2 million m3 of dredging

Page 33: Update on Infrastructure Projects

Port of Ngqura Aerial View of Proposed Developments

B101

Cargo Berth

A100

Tanker berth Basin dredging

New Admin Building

Small Craft Basin

Page 34: Update on Infrastructure Projects

B101 General Cargo berth A100 Tanker berth

Future development up the river

Page 35: Update on Infrastructure Projects

Saldanha Proposed Developments

•Aerial picture of Port

Proposed Iron

Ore Berth

Proposed Mosgas

Quay Extension

Proposed Oil & Gas Repair Berth

General Maintenance Quay

Page 36: Update on Infrastructure Projects

Saldanha Proposed Quay Walls

Proposed Iron Ore Berth

General

Maintenance

Quay

Proposed Oil & Gas Repair Berth

Page 37: Update on Infrastructure Projects

The End – Session # 1

A brief overview of

The TNPA World of Port Infrastructure

The End

Page 38: Update on Infrastructure Projects

Thank you