11
Update of anchoring procedures for the ALS floor 09/19/2007

Update of anchoring procedures for the ALS floor 09/19/2007

Embed Size (px)

Citation preview

Page 1: Update of anchoring procedures for the ALS floor 09/19/2007

Update of anchoring procedures for the ALS floor

09/19/2007

Page 2: Update of anchoring procedures for the ALS floor 09/19/2007

Why now?

• Retrofit of beamlines often replace equipment leaving behind abandoned shells/anchors/studs

• Review of HILTI Technical Guide and phone calls to HILTI highlighted some issues

• Drawings for HDI anchor details often used in BOM were incorrect

Page 3: Update of anchoring procedures for the ALS floor 09/19/2007

Non “Greenfield” installation

• Removed old 4.0.2 switchyard assembly

• Found ~40 cutoff studs or shells – – Eng. Note didn’t discuss this situation– 4” no-go zone for new shells was default

• Concrete patch (which sounded hollow) filling in old wire trench under shield wall

• Steel plate for shield door

Page 4: Update of anchoring procedures for the ALS floor 09/19/2007

Hilti Information• Table for derating of HDI anchors

– Copies for all– Will be added to new version of Engineering Note

M7696

• Multiple derating factors are multiplicative• Abandoned shells / studs need minimum of 3

diameters (of loaded shell) clearance for loaded shell to be fully rated – Conversation with HILTI and testing done at HILTI – “Effect of Abandoned Holes on Capacity of Wedge

Bolts”

Page 5: Update of anchoring procedures for the ALS floor 09/19/2007

For ½” HDI shells, need 7” between loaded shells and 6” from edge to be fully rated. Between 4” and 7” (or 6”) there is a derating factor; below 4” isn’t allowed. Derating factors are per shell / edge and are multiplicative.

Page 6: Update of anchoring procedures for the ALS floor 09/19/2007

Engineering Documentation• Engineering Note M7696 “Concrete Floor

Anchor Applications” controls our work for installing equipment at the ALS.– Version A is most current but needs revisions based

on the information presented here– Does not reference anchor detail drawings– Basic method for calculating seismic loads – uniform

loading, symmetric, no derating• In Work Manager:

– 26D412 : Anchor detail for HILTI ½” HDI– 26D409 : Anchor detail for HILTI HIS (epoxy)– Often are called out in BOM for installation drawings

along with the Engineering Note M7696– Current versions are incorrect; new versions are

being made

Page 7: Update of anchoring procedures for the ALS floor 09/19/2007

Seismic Calculations

• Dave Plate has a spreadsheet for basic calculations – best place to start

• For more complex situations (e.g. derated bolts) need to check all scenarios– Examples from MERLIN– Can have OSD calculate CG but need to have

correct density for parts.

Page 8: Update of anchoring procedures for the ALS floor 09/19/2007

2.13”

4”6”

What is rating of new ½” anchor for tension and shear during a seismic event?

From Eng. Note: ½” HDI has a load of 2380 lbs in tension and 1780 lbs in shear.

(takes into account 33% increase in load for short-term loading)

New anchor

(cutaway of floor)

Trench edge

1.88”

Page 9: Update of anchoring procedures for the ALS floor 09/19/2007

4”

4”6”

Note: Abandoned shell has no effect as 3x diameter away (1/2” HDI has .625” diameter)

Load = 2380 lbs x .5 (for 4” a-a) x .83 (for 6” a-a) x .8 (for 4” a – e) = 790 lbs in tension

= 1780 lbs x .5 (for 4” a-a) x .83 (for 6” a-a) x .65 (for 4” a – e) = 480 lbs in shear

Page 10: Update of anchoring procedures for the ALS floor 09/19/2007

Takeaways• Use revised anchor detail drawings in

BOM / drawing notes (let me know if you are using a different anchor detail).

• If a new shell/anchor is placed too close to existing anchor (e.g. a utility pole or a stand for another beamline), must derate both anchors and recalculate seismic.

• Careful of edges – concrete patches, trenches, steel plates in floor, etc.

Page 11: Update of anchoring procedures for the ALS floor 09/19/2007

Takeaways cont.

• Keep loaded ½” HDI anchors > 4” away from each other and edges at absolute minimum; 7” is necessary to be fully rated.

• Stay > 2” away from abandoned shells- – Possible to core out abandoned shell / stud and grout –

then need 1.5 diameters for fully rated.

• Visit and revisit location to make sure everything is captured in your model – will save rework later – For installations in non-Greenfield areas, consider

adding extra anchor holes in base.