Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
UNIVERSITY OF ÇUKUROVA INSTITUTE OF NATURAL AND APPLIED SCIENCE
MSc THESIS
Seyfeddin Olcay BERĐKOL
RESPONSE TESTS OF LOAD-FREQUENCY CONTROL IN THERMAL POWER PLANTS REGARDING UNION FOR THE CO-ORDINATION OF TRANSMISSION OF ELECTRICITY (UCTE) POLICIES
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING
ADANA, 2009
ÇUKUROVA ÜNĐVERSĐTESĐ
FEN BĐLĐMLERĐ ENSTĐTÜSÜ
RESPONSE TESTS OF LOAD FREQUENCY CONTROL IN THERMAL POWER PLANTS REGARDING UNION FOR THE CO-ORDINATION OF TRANSMISSION OF ELECTRICITY (UCTE) POLICIES
Seyfeddin Olcay BERĐKOL
YÜKSEK LĐSANS TEZĐ
ELEKTRĐK ELEKTRONĐK MÜHENDĐSLĐĞĐ ANABĐLĐM DALI
Bu tez ..../...../2009 Tarihinde Aşağıdaki Jüri Üyeleri Tarafından Oybirliği/Oyçokluğu Đle Kabul Edilmiştir.
Đmza............………
Prof. Dr. Mehmet TÜMAY
DANIŞMAN
Đmza............……… Đmza............………
Yrd. Doç. Dr. K.Çağatay BAYINDIR Yrd. Doç. Dr. Ramazan ÇOBAN
ÜYE ÜYE
Bu tez Enstitümüz Elektrik Elektronik Mühendisliği Anabilim Dalında hazırlanmıştır Kod No: Prof. Dr. Aziz ERTUNÇ Enstitü Müdürü Đmza ve Mühür Not: Bu tezde kullanılan özgün ve başka kaynaktan yapılan bildirişlerin, çizelge, şekil ve fotoğrafların kaynak gösterilmeden kullanımı, 5846 sayılı Fikir ve Sanat Eserleri Kanunundaki hükümlere tabidir.
I
ÖZ
YÜKSEK LĐSA�S TEZĐ
AVRUPA ELEKTRĐK ĐLETĐMĐ KOORDĐ�ASYO�U BĐRLĐĞĐ (UCTE) KRĐTERLERĐ ÇERÇEVESĐ�DE TERMĐK SA�TRALLERĐ� YÜK FREKA�S TEPKĐSĐ�Đ� ARAŞTIRILMASI
Seyfeddin Olcay BERĐKOL
ÇUKUROVA Ü�ĐVERSĐTESĐ
FE� BĐLĐMLERĐ E�STĐTÜSÜ
ELEKTRĐK ELEKTRO�ĐK MÜHE�DĐSLĐĞĐ A�ABĐLĐM DALI
Danışman: Prof. Dr. Mehmet TÜMAY Yıl: Eylül 2009, Sayfa: 99
Jüri: Prof. Dr. Mehmet TÜMAY Yrd. Doç. Dr. K.Çağatay BAYI�DIR
Yrd. Doç. Dr. Ramazan ÇOBA�
Bir enerji iletim şebekesinde aktif ve reaktif gücün akışı birbirinden bağımsızdır ve farklı denetim faaliyetleri ile kontrol edilirler. Reaktif güç kontrolü, gerilim kontrolü ile bağlantılıyken, aktif güç kontrolü ile frekans kontrolü arasında yakın bir ilişki bulunmaktadır. Frekans kontrolü, hem elektrik ağının enerji kalitesini göstermesi bakımından hem de Türkiye elektrik enterkoneksiyonunun Avrupa Elektrik Đletimi Koordinasyonu Birliğine (UCTE) katılabilmesi için gerekli bir parametredir. Avrupa kıtasını kapsayan UCTE büyük bir organizasyondur ve kendine has politikaları bulunmaktadır. Bu politikalardan en önemlisi yük-frekans kontrolüdür. UCTE ağıyla, Türkiye ağının enterkoneksiyonu 90’lı yılların sonundan beri devam eden bir projedir ve TEĐAŞ aracılığıyla referans olarak seçilen hidroelektrik ve termik santrallerde testlere devam edilmektedir.
Bu tezin amacı, UCTE kapsamında belirtilen birincil yük-frekans tepkisini termik santraller için incelemektir. Tezde referans santralin, türbin kontrolörü Matlab/Simulink programı yardımıyla modellenip simülasyonu yapılmaktadır. Saha testleri sonucunda, referans santralin yük-frekans performansı elde edilmiştir. Sonuçlar Digsilent yazılımı aracılığıyla bilgisayar ortamına aktarılmış ve simülasyon da elde edilen sonuçlar ile karşılaştırılıp yorumlanmıştır. Anahtar Kelimeler: Yük-Frekans Kontrol, Birincil Kontrol, Hız Eğimi ve UCTE
II
ABSTRACT
MSc THESIS
RESPO�SE TESTS OF LOAD-FREQUE�CY CO�TROL I� THERMAL POWER PLA�TS REGARDI�G U�IO� FOR THE CO-ORDI�ATIO� OF TRA�SMISSIO� OF ELECTRICITY (UCTE) POLICIES
Seyfeddin Olcay BERĐKOL
U�IVERSITY OF ÇUKUROVA
I�STITUTE OF �ATURAL A�D APPLIED SCIE�CES
DEPARTME�T OF ELECTRICAL ELECTRO�ICS E�GI�EERI�G
Supervisor: Prof. Dr. Mehmet TÜMAY Year: September 2009, Pages: 99 Jury: Prof. Dr. Mehmet TÜMAY
Asst. Prof. Dr. K.Çağatay BAYI�DIR Asst. Prof. Dr. Ramazan ÇOBA�
Active and reactive power flows are independent from each other and they are controlled by different methods in an interconnection system. The control of active power is closely related to frequency control and the control of reactive power is related to voltage control. Frequency control is a necessary parameter in order to both indicate energy quality of electricity network and join Turkish interconnected system to Union for the Co-ordination of Transmission of Electricity (UCTE). UCTE in Europe mainland is a huge organization and has own policies. The most important parameter of those policies is load-frequency control. The interconnection of Turkish electrical network with UCTE network is an ongoing project since the end of 90’s and tests are persisting in both hydro power plants and thermal power plants chosen as references in Turkey via TEĐAŞ.
The goal of this thesis is to investigate primary load-frequency control involved in UCTE policies for thermal power plants. Turbine controller of reference power plant is modeled and simulated by using Matlab/Simulink program in the thesis. Load-frequency performance of reference power plant is achieved by the field test. The results of tests are transferred into computer via Digsilent software and results of tests are compared with results of simulations. Keywords: Load-Frequency Control, Primary Control, Speed Droop and UCTE
III
ACK�OWLEDGEME�TS
I wish to express my gratitude to my supervisor Prof. Dr. Mehmet Tümay for
his guidance, encouragement and support during my studies.
I would like to thank K. Çağatay Bayındır who has made any necessary
changes in the thesis with remarkable patience.
Many thanks to my department manager Mr. Đlker Öztürk who supports me
during my thesis. His continuous support helped me to finish this thesis.
I would like to thank my colleague Serdal Uğur for offering valuable advice
in finding this topic at the beginning of the thesis.
I would like to thank all ISKEN family for their helping in each step of
creating this thesis.
I thank Asst. Prof. Dr. Ramazan Çoban for serving as a member of my
committee.
I would like to say a special thank to M. Uğraş Cuma for his helping.
Finally, I would like to thank my family for their endless support and
encouragements.
Seyfeddin Olcay BERĐKOL
IV
CO�TE�TS PAGE
ÖZ I
ABSTRACT II
ACK�OWLEDGEME�TS III
CO�TE�TS IV
LIST OF TABLES VII
LIST OF FIGURES VIII
LIST OF SYMBOLS X
LIST OF ABBREVATIO�S XII
1. I�TRODUCTIO� 1
1.1. Frequency Control 3
1.2. Literature 5
1.3. Content 6
2. THERMAL POWER PLA�TS 8
2.1. Steam Turbine 9
2.1.1. Governor (Control) and Stop Valves 11
2.1.2. Condenser 12
2.1.3. Turbine Bypass System 13
2.2. Steam Generator 14
2.2.1. Combustion Loop 15
2.2.2. Combustion Air and Flue Gas 16
2.2.3. Pressure Part (Water / Steam) 17
2.2.4. Water / Steam Cycle 18
2.2.5. Cooling Water System 19
2.2.6. Generator System 20
3. UCTE 22
3.1. UCTE Policies 23
3.1.1. Load-Frequency Control and Performance 24
3.1.1.1. Primary Control 26
3.1.1.2. Balance between Generation and Demand 26
V
3.1.1.3. System Frequency 26
3.1.1.4. Network Power Frequency Characteristic 27
3.1.1.5. Primary Control Basics 29
3.1.1.6. Principle of Joint Action 30
3.1.1.7. Target Performance 31
3.1.1.8. Primary Control Reserve 34
3.1.1.9. Deployment Time of Primary Control Reserve 34
3.1.1.10. Secondary Control 35
3.1.1.11. Tertiary Control 37
3.1.1.12. Time Control 38
3.1.2. Scheduling and Accounting 39
3.1.3. Operational Security 39
3.1.3.1. Voltage and Reactive Power Control 40
3.1.3.2. “N-1”Network Security 41
3.1.4. Co-ordinated Operational Planning 42
3.1.5. Emergency Procedures 42
4. CO�TROL STRATEGY OF GE�ERATOR 44
4.1. General 44
4.2. Frequency and Voltage Control 46
4.2.1. Modeling the PSS 48
4.2.2. Modeling the Excitation System 49
4.2.3. Modeling the Turbine and Governor 50
4.2.3.1. Electro Hydraulic Governing System 54
4.2.3.2. Speed Controller and Power-Load Controller 55
4.2.3.3. Droop Characteristic 58
4.2.3.4. Governor insensitivity or dead band 60
4.2.3.5. Transient Speed Rise 61
5. SIMULI�K MODELI�G OF TURBOSET 63
5.1. General 63
5.2. Design Considerations 64
5.3. Proposed Configuration of Turbine Control System 66
VI
5.3.1. Synchronous Machine (Generator) 69
5.3.2. Turbine-Governor Control System 72
5.3.3. Excitation Control Block 75
5.4. Field Test Procedure 78
5.5. Simulation and Field Test Results 79
5.6. Comparison of Simulation and Test Results 91
6. CO�CLUSIO�S 93
REFERE�CES 97
BIOGRAPHY 99
VII
LIST OF TABLES
Table 3.1 Self regulating effect of load 33
VIII
LIST OF FIGURES
Figure 2.1 A turbo-generator system with five mass 13
Figure 3.1 System frequency movements
for different design hypothesis 32
Figure 4.1 Generator control system 47
Figure 4.2 Power system stabilizer 48
Figure 4.3 Voltage control of synchronous generator 50
Figure 4.4 Steam turbine governing scheme 52
Figure 4.5 Block diagram of the governing system 53
Figure 4.6 Electro-hydraulic governor scheme 54
Figure 4.7 Speed and load controllers 55
Figure 4.8 Power control and Speed control modes 57
Figure 4.9 Droop characteristic 58
Figure 4.10 Different droop with same primary control reserve 59
Figure 4.11 Dead band characteristic 60
Figure 5.1 Power responses in frequency deviations -200 mHz 65
Figure 5.2 Power responses in frequency deviations +200 mHz 65
Figure 5.3 Power-frequency curve at ±200 mHz 66
Figure 5.4 MATLAB/Simulink model of turboset 68
Figure 5.5 Parameters of generator 70
Figure 5.6 Turbine-governor block 73
Figure 5.7 Speed governor block 73
Figure 5.8 Turbine power fractions and
time constants of turbine parts 74
Figure 5.9 Simulated frequency 75
Figure 5.10 Excitation control description 76
Figure 5.11 Excitation control block 76
Figure 5.12 Parameters of excitation 77
Figure 5.13 Test mode 78
Figure 5.14 --200 mHz frequency deviation for case 1.a 80
IX
during simulation
Figure 5.15 -200 mHz frequency deviation for case 1.b 81
during simulation
Figure 5.16 Unit response to -200 mHz frequency 81
deviation for case 1.b during simulation
Figure 5.17 Unit response to -200 mHz frequency 82
deviation for case 1.b during simulation
Figure 5.18 -200 mHz frequency deviation 83
for case 1.a during field test
Figure 5.19 -200 mHz frequency deviation 83
for case 1.b during field test
Figure 5.20 Unit response to -200 mHz frequency 84
deviation for case 1.a during field test
Figure 5.21 Unit response to -200 mHz frequency 84
deviation for case 1.b during field test
Figure 5.22 +200 mHz frequency deviation 86
for case 2.a during simulation
Figure 5.23 +200 mHz frequency deviation 86
for case 2.b during simulation
Figure 5.24 Unit response to +200 mHz frequency 87
deviation for case 2.a during simulation
Figure 5.25 Unit response to +200 mHz frequency 87
deviation for case 2.b during simulation
Figure 5.26 Frequency deviation +200 mHz at time 1830 88
seconds for case 2.a during field test
Figure 5.27 Frequency deviation +200 mHz for 15 minutes 89
at time 1830 seconds for case 2.b during field test
Figure 5.28 Test result of unit response +200 mHz frequency 89
deviation at full load for case 2.a during field test
Figure 5.29 Test result of unit response +200 mHz frequency 90
deviation at full load for case 2.b during field test
X
LIST OF SYMBOLS
f Set point of frequency
fo Dead band
fn Rated nominal frequency
∆f Frequency deviation in synchronous system
∆fdyn.max Dynamic frequency deviation
Gf∆ Sensed frequency after dead band
∆P Deviation in power output of a generator
PN Active power output
Pm Mechanical power input
Pset Power set point
Ppu The total primary control reserve for the entire synchronous
area
Q Primary frequency control reserve
λi Frequency characteristic of a synchronous area for i
λu Frequency characteristic of whole synchronous area
λio Set point frequency characteristic of a synchronous area for i
λuo Set point frequency characteristic of whole synchronous area
Ei Being the electricity generated in control area i
Eu Being the total electricity production in all n control area
Ci Contribution coefficients for λ in i control area
Ppu The total primary control reserve for synchronous area
∆Pa Power deviation of a synchronous area
∆Pdi Control instruction for the activation of generating units under
secondary control in area i
βi Proportional gain of the controller in area i
Tri Integration time constant for the network controller in area i
Gi Overall control deviation (area control error) in area i
∆Pi Interchange capacity deviation for area i in relation to the
scheduled power exchange program
XI
Kri [MW/Hz] parameter applied to network controller of area I
Ke Exciter gain
Ka Regulator gain of exciter
Kf Damping filter gain
Kp Proportional gain
Te Exciter time constant
Tb Transient gain reduction
Tr Low-pass filter time constant of exciter
ef Regulator output of exciter
Efmin Minimum output of regulator
Efmax Maximum output of regulator
h Position of the governor valve
Vfd Exciter voltage
Vn RMS line-to-line voltage
Vt Terminal voltage of generator
GPV Transfer function
Xd Synchronous reactance of direct axis
Xd’ Transient synchronous reactance of direct axis
Xd’’ Sub-transient synchronous reactance of direct axis
Xq Synchronous reactance of quadrature axis
Xq’ Transient synchronous reactance of quadrature axis
Xq’’ Sub-transient synchronous reactance of quadrature axis
Xl Stator leakage reactance
Tdo’ d-axis no load transient time constant
Tdo’’ d-axis no load sub-transient time constant
Tqo’ q-axis no load transient time constant
Tqo’’ q-axis no load sub-transient time constant
H Inertia Constant
XII
LIST OF ABBREVIATIO�S
AGC Automatic Generation Control
APH Air Pre Heater
AVR Automatic Voltage Regulator
CV Control Valve
EH Electronic Highway
EHC Electro Hydraulic Converter
EHG Electro Hydraulic Governor
ESP Electro Static Precipitator
ETSO European Transmission System Operators
FACTS Flexible Ac Transmission Systems
FD Forced Draft
FGD Flue Gas Desulphurization
GENCO Generation Companies
GUI Graphical User Interface
HP High Pressure
ID Induced Draft
IP Intermediate Pressure
LFC Load Frequency Control
LSR Load Shedding Relay
LP Low Pressure
LSR Load Shedding Relay
PC Power Control
PD Proportional Derivative
PI Proportional Integral
PSS Power System Stabilizer
SC Speed Control
SD Speed Droop
SVC Static Var Compensator
TIE Tie Communication Line
XIII
TSO Transmission System Operator
TSR Transient Speed Rise
UCTE Union for the Co-ordination of Transmission of Electricity
UTC Universal Coordinated Time
VWO Valves Wide Open
1. INTRODUCTION S. Olcay BERĐKOL
1
1. I�TRODUCTIO�
Controlling frequency and voltage has always been an essential part of
operating a power system. However, since the liberalization of the electricity supply
industry, the resources required to achieve this control have been treated as services
that the system operator has to obtain from other industry participants. Because this
liberalization has proceeded independently in different parts of the world and
because of the structural differences in the underlying power systems, the technical
definitions of these services and the rules governing their trading vary considerably.
This framework is based on the one used by the Union for the Co-ordination of
Transmission of Electricity (UCTE), which is the association of Transmission
System Operators (TSOs) operating within the synchronous system of mainland
Europe. The UCTE has been establishing the security and reliability standards for
interconnected system (Rebours et al., 2007).
As a part of the European Transmission System Operators (ETSO), the UCTE
is the association of transmission system operators in continental Europe which
interconnects and supplies the vast majority of the population of Europe with
electrical power. Even though the UCTE has developed a number of technical and
organizational rules defined in the UCTE Operation Handbook, the responsibility of
the national TSOs must still be determined in their own guidelines. Because grid
structures vary in different countries and due to the way in which the interfaces to the
other transmission systems are defined and thus to the way in which energy is
exchanged with these other systems over the interconnected power lines, it is
necessary to define specific requirements.
To ensure smooth operation of the system and to enable grid disturbances to
be controlled, a number of technical rules and recommendations need to be followed
in operation of this system. The rules and recommendations of the UCTE form a
common basis for this, providing minimum requirements to be met for grid operation
on this system, which is operated in overall synchronism. These rules and
recommendations stimulate the exchange of electric power beyond the boundaries of
1. INTRODUCTION S. Olcay BERĐKOL
2
the separate countries that form this synchronously interconnected system, and also
promote nondiscriminatory exchange of data for this task.
The technical rules and recommendations do, however, give the individual
TSOs the option of going beyond more compliance with these minimum
requirements, implementing more stringent requirements or even defining these in
greater detail. As a result, individual TSOs or regional TSO associations have drawn
up national grid codes with a number of functions such as defining the sharing of
responsibilities for security of supply, reliability and profitability for the system. For
the TSOs to be able to meet their responsibilities, transmission system users must
comply with the technical minimum requirements and rules specified in the relevant
grid codes.
Not least of all, grid operators are being challenged to make ever larger power
reserves available, to achieve improved distribution of these power reserves within
the interconnected power system and to develop new and better load shedding
concepts for response to disturbances.
There are various reasons for the size and uniformity of the power reserves.
On the one hand, it is necessary for conventional power plants to provide control
reserves corresponding to the entire output supplied by energy producers which
operate without any frequency-control capability, such as renewable energy plants
like wind power stations. These control reserves serve to compensate for power
fluctuations or outages at wind power stations.
On the other hand, liberalization of the electric power markets in Europe and
heavy emphasis on unhindered commercial trading of electric power across national
boundaries wherever possible have also presented new challenges to the transmission
systems. Shortly, members of the UCTE followed suit and reviewed their national
grid codes for the European mainland. The interconnected power system, which was
originally envisioned primarily as a source of mutual assistance and optimization, is
more and more becoming a commercial marketplace.
In the future, transmission system operators must pay even closer attention to
compliance with requirements when the generating units are connected and must also
use test programs to verify the necessary flexibility of these units for grid operation.
1. INTRODUCTION S. Olcay BERĐKOL
3
Power plant manufacturers are working intensively in close co-operation with
companies that operate the generating units to comply with these ever more intricate
rules. These companies have a vested interest in ensuring a reliable energy supply
even in the event of grid disturbances, especially if they are responsible for supplying
power to large urban areas with many industrial plants.
From the perspective of providers of voltage control services it is convenient
to divide the production of reactive power into a basic and an enhanced reactive
power service. The basic or compulsory reactive power service encompasses the
requirements that generating units must fulfill to be connected to the network. The
enhanced reactive power service is a non-compulsory service that is provided on top
of the basic requirements. The terminology of voltage control is much more uniform
than for frequency control and does not need to be discussed further here. This thesis
is especially interested in frequency control.
1.1. Frequency Control
Load-frequency control (LFC) is of importance in electric power system
design and operation. The loading in a power system is never constant. To ensure the
quality of the power supply is necessary to design a load-frequency control system
which deals with the control of loading of the generator depending on the frequency.
There has been continuing interest in designing load-frequency controllers with
better performance. Many control strategies for LFC have been proposed since the
1970s (Wang et al., 1993).
For grid system operation, it is required that the power generated is
continuously matched to demand for the power plant. One parameter for this balance
is the system frequency. If power generation and power demand in the grid system
are the same under undisturbed generation conditions, the system frequency is
exactly equal to the rated frequency 50 Hz. Unforeseen events such as perturbations
in the grid system or shutdown of power plants create an imbalance between
generation and demand, and are reflected in changes in the system frequency.
1. INTRODUCTION S. Olcay BERĐKOL
4
If the power generation is greater than power demand, generators connected
to the grid system speed up. If the power generation is less than power demand,
generators connected to the grid system slow down. When power generation and
power demand are back in balance, the frequency stabilizes. For correct operation of
the transmission system it is necessary to hold the frequency within defined narrow
limits. Minor deviations from the frequency reference value 50 Hz or absence of any
such deviations show that there is a balance of generation and power demand. Faults,
resulting from loss of power plants, shutdown of loads, short circuits, etc. in the
system, result in deviations and gradients of varying magnitudes. These faults can
result with instability of the grid or even in grid outage.
Faults within the anticipated range are controlled by provision of reserve
power. Those faults result in frequency fluctuations that remain within a control band
defined by the grid operator e.g. at UCTE = +/-200 mHz.
Serious system faults that are counteracted by disconnection from the
interconnected system can be occurred and measured such as load shedding. Fast
decreases in frequency in the case of serious system faults can not be solely
counteracted by measures on the generating side. Protection devices are implemented
which switch off loads (load shedding) in case of a specific under-frequency. In the
case of fast decreases in frequency where the frequency remains above a
disconnection limit, it is the task of the generators in order to remain in a stable load
operation mode.
The reaction on frequency deviation caused by an event in the grid is handled
by the frequency control. This is implemented in two time ranges called primary and
secondary controls.
Primary control is the automatic, stabilizing action of active power controls
for the turbine-generators interconnected in the synchronous three-phase grid. This
type of control acts in the time frame of seconds using turbine speed control. We can
say for primary control is the fast component of LFC. Generated power is adjusted
due to the speed by the action of the governor valves in thermal power plants.
Secondary control takes effect after about thirty seconds and acts in the time
frame of minutes so we can say that secondary control slow component of LFC.
1. INTRODUCTION S. Olcay BERĐKOL
5
In order to give reaction to LFC, two basic control methods are used in
thermal power plants called speed control (SC) and power control (PC). SC is used
for start-up, in disturbance states and in island operation. PC mode is used for
primary frequency control while the units are supplying power to 380 kV Turkish
network. Therefore UCTE tests are carried out in PC mode. Speed-governors
compare actual turbine speed with the governor reference 50 Hz rated frequency and
outputs a control signal to the gate controller in accordance with speed-droop set
value, while the units are operating in PC mode.
ISKEN is chosen as reference thermal power plant in Turkey to be able to
understand whether supporting load frequency control policy of UCTE or not. In this
thesis, unit frequency response of reference power plant control system is
investigated and discussed with both simulation and field tests.
1.2. Literature
In literature, a lot of studies about LFC and UCTE are available. Especially,
design of newer and faster controller, giving power reaction regarding to the
frequency, has been studied during the last 30 years. Some of them are listed as
follows.
Inoue and Amano (2006) had investigated thermal power plant model for
dynamic simulation of load frequency control. In the model, MW response of the
thermal power plant is represented using two components. One is the slow
component responding to the MW demand change from the LFC, and the other is the
fast component due to the primary frequency (governor) control. For the former,
demand rate limit, boiler response delay, and boiler steam sliding pressure control
are also considered. For the latter, turbine governor response, turbine load reference
control and steam pressure change due to turbine control valve movement are
considered. The MW control is conducted through the turbine control valve (CV)
position control to fit the generator output power to the MW demand.
Wang et al. (1993) had investigated a robust controller that is proposed for
power system load-frequency control. The proposed robust controller is simple,
1. INTRODUCTION S. Olcay BERĐKOL
6
effective and can ensure that the overall system is asymptotically stable for all
admissible uncertainties. Simulation results show that the proposed robust load-
frequency controller can achieve good performance even in the presence of
generation rate constraint.
Rebours et al. (2007) had investigated survey of the frequency and voltage
control ancillary services due to the UCTE in power systems from various parts of
the world. That study provides a basis for a comparison of frequency control
ancillary services across systems. The document also explains the important
technical features that must be taken into account when procuring or trading
frequency and voltage control ancillary services. Lastly, the specifications for these
ancillary services in eight different systems are reviewed.
Salami et al. (2006) had investigated a method to improve the frequency
response of a power system during restoration. A Load Frequency Control (LFC)
scheme with a PID controller is used. In the initial phase of restoration; the proposed
control scheme helps to increase the amount of load pick- up. Presented method is
capable of achieving better frequency response for a determined load step. The aim is
to assess desired frequency response for different power plant. The proposed
controller has been tested for different power plants, and simulation results.
1.3. Content
The content of the thesis is arranged as follows:
After this introduction chapter, chapter 2 presents to the dynamics and
fundamental systems of thermal power plants.
In chapter 3, the goals, benefits and policies of UCTE are presented. The
UCTE regulation of load frequency control is mainly presented.
In chapter 4, control strategy of a steam turbine is presented. Both frequency
control and voltage control are mentioned. Modeling of turbine governor, excitation
and droop characteristic is defined. Speed Controller and Power controller modes are
explained as detailed.
1. INTRODUCTION S. Olcay BERĐKOL
7
In chapter 5, proposed controller is modeled. The simulation results of the
proposed model and the actual test results of step response tests in reference thermal
power plant are presented. The actual test results are compared with simulation
results in this chapter and proven whether they support or not the UCTE requests
regarding primary frequency control.
In chapter 6, a general view to the thesis is presented and the important
conclusions of this study are explained.
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
8
2. THERMAL POWER PLA�TS
The power plant is a facility that transforms various types of energy into
electricity or heat for some useful purpose. The energy input to the power plant can
vary significantly, and the plant design to accommodate this energy is drastically
different for each energy source. The forms of this input energy can be as follows:
• The potential energy of an elevated body of water, which, when used,
becomes a hydroelectric power plant
• The chemical energy that is released from the hydrocarbons contained in
fossil fuels such as coal, oil, or natural gas, which becomes a fossil fuel fired
power plant
• Solar energy from the sun, which becomes a solar power plant
• The fission or fusion energy that separates or attracts atomic particles, which
becomes a nuclear power plant (Woodruff et al., 2004)
In those power plants, the conversion of water to steam is the predominant
technology, and this chapter describes this process, various systems and equipments.
A thermal power station is a power plant in which the prime mover is steam
or gas driven. The greatest variation in the design of thermal power stations is due to
the different fuel sources. Some prefer to use the term energy center because such
facilities convert forms of heat energy into electrical energy. Almost all coal, nuclear,
geothermal, solar thermal electricity, and waste incineration plants, as well as many
natural gas power plants are thermal.
The basically general process of a thermal power plant can be briefly
explained as follows. Water is heated, turns into steam and spins a steam turbine
which drives an electrical generator. After it passes through the turbine, the steam is
condensed in a condenser. This is known as a rankine cycle which originated around
the performance of the steam engine.
In a thermal power plant, the chemical energy stored in fossil fuels such as
coal, fuel oil, natural gas is converted successively into thermal energy, mechanical
energy and finally electrical energy for continuous use and distribution across a wide
geographic area. In the rankine cycle, high pressure and high temperature steam
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
9
raised in a boiler is expanded through a steam turbine that drives an electric
generator. Thermal power plants have very high availability and can operate for more
than a year between shutdowns for maintenance and inspections. Their unplanned or
forced outage rates are very low.
The electric efficiency of a conventional thermal power station, considered as
saleable energy produced at the plant bus bars compared with the heating value of
the fuel consumed, is typically 33 to 48% efficient, limited as all heat engines are by
the laws of thermodynamics called carnot cycle. The rest of the energy must leave
the plant in the form of heat. This waste heat can be disposed of with cooling water
or in cooling towers. If the waste heat is utilized for e.g. district heating, it is called
cogeneration. An important class of thermal power station is associated with
desalination facilities; these are typically found in desert countries with large
supplies of natural gas and in these plants, freshwater production and electricity are
equally important co-products.
ISKEN, our reference plant, is coal fired thermal power plant and consists of
two units with 605MW net output at valves wide open (VWO) each. The plant is
designed for base load operation between 80 and 100 % net output and is connected
to the Turkish grid via 380kV substation.
2.1. Steam Turbine
A steam turbine is a mechanical device that extracts thermal energy from
pressurized steam, and converts it into rotary motion. Steam turbines are made in a
variety of sizes ranging from small 1 hp (0.75 kW) units rarely used as mechanical
drives for pumps, compressors and other shaft driven equipment, to 2,000,000 hp
(1,500,000 kW) turbines used to generate electricity. There are several classifications
for modern steam turbines.
An ideal steam turbine is considered to be an isentropic process, or constant
entropy process, in which the entropy of the steam entering the turbine is equal to the
entropy of the steam leaving the turbine. No steam turbine is truly isentropic,
however, with typical isentropic efficiencies ranging from 20%-90% based on the
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
10
application of the turbine. The interior of a turbine comprises several sets of blades,
or called buckets as they are more commonly referred to. One set of stationary blades
is connected to the casing and one set of rotating blades is connected to the shaft. The
sets intermesh with certain minimum clearances, with the size and configuration of
sets varying to efficiently exploit the expansion of steam at each stage.
To maximize turbine efficiency, the steam is expanded, generating work, in a
number of stages. These stages are characterized by how the energy is extracted from
them so there are two principal turbine types called impulse and reaction turbines
(Bloch, 1995). Most modern steam turbines are a combination of the reaction and
impulse design. Typically, higher pressure sections are impulse type and lower
pressure stages are reaction type.
An impulse turbine has fixed nozzles that orient the steam flow into high
speed jets. These jets contain significant kinetic energy, which the rotor blades,
shaped like buckets, convert into shaft rotation as the steam jet changes direction. A
pressure drop occurs across only on the stationary blades, with a net increase in
steam velocity across the stage.
As the steam flows through the nozzle its pressure falls from steam chest
pressure to condenser pressure or atmosphere pressure. Due to this relatively higher
ratio of expansion of steam in the nozzle, the steam leaves the nozzle with a very
high velocity. The steam leaving the moving blades is a large portion of the
maximum velocity of the steam when leaving the nozzle. The loss of energy due to
this higher exit velocity is commonly called the carry over velocity or leaving loss.
In the reaction turbine, the rotor blades themselves are arranged to form
convergent nozzles. This type of turbine makes use of the reaction force produced as
the steam accelerates through the nozzles formed by the rotor. Steam is directed onto
the rotor by the fixed vanes of the stator. It leaves the stator as a jet that fills the
entire circumference of the rotor. The steam then changes direction and increases its
speed relative to the speed of the blades. A pressure drop occurs across both the
stator and the rotor, with steam accelerating through the stator and decelerating
through the rotor, with no net change in steam velocity across the stage but with a
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
11
decrease in both pressure and temperature, reflecting the work performed in the
driving of the rotor.
Steam turbine in reference thermal plant is five mass with separate casings-
arranged on one rotor with the generator. The steam turbine generator set is of the
single reheat condensing type. The turbine set consists of one high pressure (HP),
one intermediate pressure (IP) and two low pressure (LP) casings exhausting
downwards into the condenser. The greater part of the blade is designed as drum-
type blade with 50% reaction.
The HP turbine is of single flow design with full arc admission. The double-
shell casing consists of a guide blade carrier and a barrel-type outer casing. Main
steam to the HP turbine is admitted laterally via two combined stop and control
valves. At the front end of the HP turbine the steam is exhausted downward via an
exhaust branch to which the cold reheat is connected.
The IP turbine is of double flow design. The double shell casing is of a split
inner and outer casing. Reheat steam is admitted via two combined stop and control
valves into the middle of the turbine. The exhaust branch on the top of the casing is
mounted to the crossover piping which leads to the LP turbine.
The LP turbines consist of two double flow units with a horizontally split
multi-shell casing. The welded outer casing rests on the condenser to which it is
rigidly connected by means of a welded joint. The cast inner casing is supported by
four integrally cast support arms which rest on the bearing brackets protruding
through the end walls of the LP turbine.
2.1.1. Governor (Control) and Stop Valves
The governor valve is common to all turbine applications. This is the valve
between the main supply and the turbine. This valve is the primary means of
controlling unit. When the demand for energy from the turbine is changed, it is the
opening of this valve that changes to match the new demand by introducing a new
supply of steam energy (Liptàk, 2006). Hence, it can be said that governor valves
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
12
control the flow of steam to turbine according to a specified load so in literature,
governor valve is also called control valves.
The stop valves are isolating valves with protective function, triggered by
protective devices to interrupt the steam supply in the event of dangerous operating
conditions. For this reason, they are designed for high-speed closing with maximum
reliability. The stop and control valves have electro-hydraulic actuators with fluid
supply by self contained high pressure fluid system with positive displacement
pumps. The actuator travels the respective valve by hydraulic action against the force
of a spring. The valves are closed by spring force in the event of loss of power
supply.
2.1.2. Condenser
The function of the condenser is to condense the steam exhausted from the LP
cylinders and to produce and maintain as high a vacuum as possible in order to
increase the heat drop which can be utilized in the turbine. The condensers are
single-flow box-type surface condenser with water boxes on each end. The steam
space is of rectangular cross-section to achieve optimum utilization of the enclosed
volume for the necessary condensing surface. The condensers are located below the
LP turbines shown in figure 2.1 and form an integral part of it. If the condenser can
be made cooler, the pressure of the exhaust steam is reduced and efficiency of the
cycle increases. Cooling water circulates through the tubes in the condenser's shell
and the low pressure exhaust steam is condensed by flowing over the tubes. The
tubing is designed to reduce the exhaust pressure, avoid subcooling the condensate
and provide adequate air extraction. The condenser, in effect, creates the low
pressure required to drag steam through and increase the efficiency of the turbines.
The limiting factor is the temperature of the cooling water and that, in turn, is limited
by the prevailing average climatic conditions at the power plant's location (it may be
possible to lower the temperature beyond the turbine limits during winter, causing
excessive condensation in the turbine). Powerful condensate pumps, where is in the
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
13
bottom of the condenser, recycle the condensed steam (water) back to the
water/steam cycle.
Figure 2.1 A turbo-generator system with five mass
2.1.3. Turbine Bypass System
During startup, shutdown and load disturbances in a power plant, the boiler
and steam turbine need to be isolated from one another. This is to protect the turbine
from any water carry over, but also to protect additional plant equipments from large
thermal transients. By isolating the boiler and steam turbine, it is also possible to
reduce fuel consumption during startup and shutdown. In the event of a load
rejection, reloading times can also be improved through the turbine bypass system.
The bypass system of turbine is used to send steam into condenser. After
condenser, a condensate pump is used to pump the condensate back to the feedwater
tank/deaerator (Kehlhofer et al., 1999). The turbine bypass system is designed to
provide the quickest startup time by controlling both boiler pressure and temperature.
Bypassing the steam around the turbine allows the steam to attain the desired
qualities before being routed through the turbine. If the turbine bypass system were
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
14
not used, the firing rate of the boiler would have to be reduced, which could lead to
tube failures. The bypass system allows the boiler to be fired at full capacity without
introducing large thermal gradients in the thick walled components such as the boiler
drum and any separators or flash tanks.
The steam is desuperheated by means of feedwater or condensate injection
via spray water valves. The bypass system discharges the steam into the condenser.
The bypass system is in operation when the steam turbine is not able to receive the
entire steam quantity, e. g. during start-up or in case of a load rejection.
2.2. Steam Generator
Steam generators or boilers are a central element in today’s modern thermal
power station. They convert the energy in the fuel to a useful form called steam. The
steam generating boiler has to produce steam at the high purity, pressure and
temperature required for the steam turbine that drives the electrical generator.
The steam generator includes the economizer, the steam drum, the chemical
dosing equipment, and the furnace with its steam generating tubes and the
superheater and reheater coils. Superheaters and reheaters are used in once-through
and drum boilers and consist of in-line tube bundles that increase the temperature of
the steam. They are simple single-phase heat exchangers with steam flowing inside
the tubes and the flue gas passing outside. They are typically configured to help
control steam flow pressure loss. The economizer is a counterflow heat exchanger for
energy recovery downstream of the superheater and reheater. It increases the
temperature of the feedwater before it enters the steam drum. The tube bundle is
typically an arrangement of parallel horizontal serpentine tubes with water flowing
inside but in the opposite direction (counterflow) to the flue gas. By design, steam is
usually not generated inside these tubes (Elliott et al., 1997).
The efficient combustion of fuel and transfer of heat in the boiler require that
adequate combustion air be provided and that flue gas be removed from the area of
combustion. In some small, old boilers, removal is accomplished solely by natural
convection, commonly called natural draft. The hot flue gas rises through the stack
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
15
and draws in cool air for combustion. As boilers become larger, natural draft alone
becomes inadequate, and a fan must be added to blow enough air into the furnace for
combustion. If the fan is large enough, it pressurizes the boiler furnace and aids in
the removal of the flue gas. Such a fan is called a forced-draft (FD) fan. Boilers with
FD fans and no induced-draft (ID) fans are called pressurized-furnace boilers
because flue gas, which is toxic and corrosive, and fly ash leak out of the smallest
openings in the furnace, causing maintenance and personnel safety problems. In
addition, some large boilers with considerable convective heat-transfer area need
more than just an FD fan to move the flue gas.
The solution to these problems is another fan-ID fan- that takes suction on the
furnace at the flue gas exit. Boilers having both FD and ID fans include dampers or
inlet vanes on the fans to balance them, and they operate at a slightly negative
furnace pressure.
Another feature in combustion air and flue gas systems is combustion air
heater. In order to increase the thermal efficiency of boiler, air-preheater (APH) is
used.
Also, steam generator has fly ash collectors (electro static precipitator or
baghouse), the flue gas stack for air emission controls and necessary safety valves
are located at suitable points to avoid excessive boiler pressure (Babcock & Wilcox
Co., 2005).
The steam generator in reference plant is of the subcritical, once-through
(BENSON), modified sliding pressure type, burning pulverized coal in a low-NOx
firing system. The combustion air and flue gas system is of single-train design and is
arranged in one line, including fans, air heaters, and flue gas desulphurization (FGD)
system. The steam generator is a fully welded version suspended in a steel
supporting structure and is an outdoor tower construction.
2.2.1. Combustion Loop
On the hot gas side of the boiler, two types heat transfer are available as
thermal radiation and convection. This situation exists because the fireball from the
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
16
burning fuel is so hot that a tremendous amount of energy is generated, heating the
gas to very high temperatures. Almost all heat transferred to the waterwalls of the
boiler is by thermal radiation. After the fuel burns and the combustion products (flue
gas) cool in the furnace, the gas that remains is still very hot, but much less so than in
the combustion zone. Thus there is much less radiation. Heat is primarily transferred
from the hot gas to other tubes in the boiler by convection. Usually the superheater
and reheater are in the convection section of the steam generator, while the
economizer is always in this section.
The steam generator is equipped with direct pulverized bituminous coal firing
in reference plant. To ignite the steam generator and to serve as backup for the coal
firing system at low load, a backup and ignition firing system for light oil is installed.
The coal firing system for the steam generator is an opposed firing system with
vertically staggered burner arrangement.
Raw coal is transported from the coal bunker through a feeder into the mill
where it is uniformly ground and dried. Drying as well as subsequent transport of the
pulverized coal through the various pulverized-coal pipes to the burners takes place
by means of primary air. The primary air is a mixture of hot air and cold air.
Combustion air is delivered to the firing system as follows:
• Primary air including sealing air via the coal mills
• Core air to the burners
• Secondary air to the burners
• Tertiary air to the burners
• Relatively small amount of air via the dry ash extraction system below the
furnace hopper
2.2.2. Combustion Air and Flue Gas
The air and flue gas system comprises, besides the air and flue gas lines, the
necessary facilities for instrumentation and control of the following main
components: forced draft fan, primary air fan and induced draft fan, steam air heater,
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
17
regenerative air heater, electrostatic precipitator (ESP) and flue gas desulphurization
(FGD) plant.
The flue gas from each unit is united after the two electrostatic precipitators
(for each unit) to a common bus bar and routed to the absorber system. The flue gas
ducts feeding the stack are equipped with dampers with seal air. This allows to
bypass the subsequent equipment in case of operating problems with the flue gas
desulphurization plant. The clean gas duct downstream flue gas desulphurization to
gas bus bar (to stack) is also equipped with a double damper to allow operation
without the flue gas desulphurization plant. The flue gas desulphurization process
applied is the wet process with limestone and the production of dry gypsum.
2.2.3. Pressure Part (Water / Steam)
The feedwater enters the boiler via one connection pipe at economizer inlet.
The economizer is passed parallel to the flue gas flow. From the economizer outlet
the preheated water flows via connection pipes and distributors to the evaporator
inlet headers. From the evaporator inlet the medium passes the hopper and the spiral
walls of the furnace and radiation chamber. Behind the spiral the medium is
distributed to the vertical tubing of the radiation chamber and convection part of the
boiler.
Water-steam separation is necessary for once-through boilers only at part
load, for all recirculation boilers besides the combined-circulation boiler over the
whole-load range (Kakaç, 1991). The outlet of the vertical tubing builds the outlet of
the evaporator. Depending on the load, the steam or water-steam mixture is led to the
separators for separation of steam and water. In normal Benson operation, the
medium is superheated at this point.
The steam flows via two connection pipes to the superheater 1 supporting
tubes and screen system. The supporting tubes, on which the convection heating
surfaces are suspended, are flown through in counter flow of the flue gas. The
surface is at the outlet divided into four symmetrical, parallel systems. The first spray
type attemperator is arranged behind superheater 1. The steam is cooled down by
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
18
feedwater. The bleeding point for the spray water is arranged behind the HP
preheater.
Superheater 2 is a coil tube heating surface and is arranged in counter flow to
the flue gas. The second spray water attemperator is placed behind superheater 2.
Superheater 3 is arranged in parallel flow to the flue gas and is the final superheater.
Between superheater 2 and superheater 3 there is a steam-side crossing for reducing
the temperature differences between the two parallel systems. The steam is heated up
to 541 °C and led to the turbine or to the HP-bypass station.
The steam coming from the HP turbine or from the HP Bypass, flows via the
cold reheat line to reheater 1. Reheater 1 is a coil tube heating surface and is arranged
in counter flow to the flue gas. The reheater spray water attemperator is placed
behind reheater 1. Reheater 2 is arranged in parallel flow to the flue gas and is the
final reheater. Between reheater 1 and reheater 2 there is a steam-side crossing for
reducing the temperature differences between the two parallel systems. The steam is
heated up to 539 °C and led to the IP/LP turbine or to the LP-bypass station.
To control malfunctions, the high pressure system is equipped HP bypass
station and part flow safety valves. The reheat system has also safety valves. The
safety valves discharge the steam directly to atmosphere.
2.2.4. Water / Steam Cycle
The main condensate arising through condensation of the exhaust steam, the
drains from LP feedwater heaters and the makeup water in the two condenser
hotwells is collected in the condenser hotwells and discharged by the condensate
pumps system. The heated condensate is routed via the deaerator into the feedwater
tank.
The LP feedwater heaters and the feedwater tank are heated using extraction
steam from the steam turbine. A condensate polishing plant is arranged in parallel to
the condensate system. The condensate is deaerated to deaerator before entering the
feedwater tank. The feedwater tank serves as a buffer for feedwater supply to the
steam generator. During normal operation the tank is heated by intermediate pressure
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
19
extraction steam from turbine extraction point. In the event of turbine trip or low-
load operation the deaerator is supplied with pegging steam from the cold reheat line.
During start-up, the feedwater tank is heated using auxiliary steam.
During normal operation the two main feedwater pumps pump the feedwater
from the feedwater tank through two high pressure feedwater heaters to the steam
generator.
After entering the steam generator superheated steam is produced and this is
returned to the condenser via the main steam system. A sufficient scope of
instrumentation provides information on pressures, temperatures, flowrates and valve
positions. Connections to sampling system allow steam quality to be monitored.
During start-up operation or in the event of turbine trip the pressure of the
generated HP steam is controlled by HP bypass station. The temperature is controlled
by spray attemperation using feedwater. The steam is then routed to the boiler via the
cold reheat system in order to cool the reheater. The steam leaves the boiler through
the hot reheat system and is routed to the turbine condensers via LP reducing station.
Supply lines from the cold reheat piping are provided for the auxiliary steam header.
2.2.5. Cooling Water System
Cooling water is extracted from the sea or lake, in reference plant from the
sea, and cooling water systems consist mainly of:
• Circulating water system
• Service water system
• Auxiliary cooling water system
The circulating water system is designed to remove the heat of the main
steam turbine condensers. The heat of condensation is transferred from the turbine
condenser to the circulating water which flows through the condenser tubes. A
second task of the circulating water system is to supply the service water system with
water for cooling the closed cooling water heat exchanger. The corresponding branch
to the service water system is located upstream the steam turbine condenser.
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
20
The cooling water of the circulating water system is pumped by the
circulating water pumps to the main steam turbine condensers and to the service
water system. The cooling water is taken from the intake pump house building
located at the Mediterranean sea coast and discharged via a seal pit back to sea. As
long as the circulating water is in operation, the tube cleaning system for the
condenser tubes should be in operation too. It removes any deposits which might
impair the heat transfer through the condenser tubes.
The service water system has the task to remove heat dissipated by the
various auxiliary equipments to the closed cooling water system via the closed
cooling water heat exchangers to the circulating water system. The required service
water mass flow is taken from the circulating water system upstream the condenser
and is calculated on the basis of the maximum heat to remove and required
temperature drop over the closed cooling heat exchangers.
The closed cooling water is designed as a closed circuit system and serves to
transfer the heat dissipated by components or their auxiliary equipments, such as
turbine lube oil coolers, seal oil coolers, exciter coolers etc., via the closed cooling
water heat exchanger to the service water system. The auxiliary cooling water system
has to be available during start-up, normal operation and shutdown of the plant and
standby operation of certain auxiliary equipment. The closed cooling water cycle is
filled with demineralized water which is treated with ammonia.
2.2.6. Generator System
Electric generators are rotating machines that convert mechanical energy to
electric energy. The synchronous generator is a relatively simple machine made of
two basic parts: a stator (stationary) with the output windings arranged around its
periphery and a rotor (rotating) with dc windings acting as an electromagnet. The
rotor windings are fed from a dc source either an external source or an exciter
system.
Synchronous generators are so named because an exact relationship exists
among the number of electrical poles, rotating speed, and the output frequency of the
2.THERMAL POWER PLANTS S. Olcay BERĐKOL
21
machine, which is in synchronism with all other machines on the interconnected
system. The generated frequency (in cycles per second, or hertz) is equal to the
number of rotor magnetic poles times the speed (expressed in revolutions per minute
or rpm) divided by 120. For example, a two pole machine rotating at 3000 rpm has
an output frequency 50 Hz. Changing the speed of the driving engine or turbine will
change the output frequency exactly as the speed is changed. If the synchronous
generator is connected to a large power grid, attempts to increase the turbine speed
by increasing the mechanical power output will result in a corresponding increase in
electric power output at the speed and frequency determined by the interconnected
synchronous power system.
The generator unit comprises a two-pole, hydrogen-cooled turbogenerator
which is directly coupled to the turbine, a direct water cooling system for the stator
winding, a static excitation system with a two-channel digital voltage regulator and
the requisite supply systems in reference power plant.
The stator winding (armature) is connected to the ac electrical transmission
system through the bushings and output terminals. The rotor winding (field) is
connected to the generator's excitation system. The excitation system provides the
direct-current (dc) field power to the rotor winding via carbon brushes riding on a
rotating collector ring mounted on the generator rotor.
There are five sources of heat loss in a synchronous generator: stator winding
resistance, rotor winding resistance, core, windage and friction, and stray losses.
Removing the heat associated with these losses is the major challenge to the machine
designer. The cooling requirements for the stator windings, rotor windings, and core
increase proportionally to the cube of the machine size.
The stator winding of generator in reference plant is directly cooled by water
and the rotor winding by hydrogen. The heat produced in the other components as a
result of losses such as iron losses, friction and stray losses is dissipated by hydrogen
cooling. The heat in the core is uniformly dissipated via a large number of radial
cooling slots.
3. UCTE RULES S.Olcay BERĐKOL
22
3. UCTE (Union for the Co-ordination of Transmission of Electricity)
The UCTE is the association of transmission system operators in continental
Europe, providing a reliable market base by efficient and secure electric power
highways. UCTE is keeping the lights on throughout the electric system, serving
some 500 million people. Annual electricity consumption is approximately 2100
TWh through the networks of UCTE (UCTE Operation Handbook, 2004).
UCTE has co-ordinated through a wide variety of technical rules and
recommendations for the international operation of high-voltage grids that all work
with one heart beat. The 50 Hz UCTE frequency is related to the nominal balance
between offer and demand. UCTE commits itself to the development of the system to
meet all new market requirements, but without accepting losses in terms of reliability
for the existing system. UCTE operates one of the largest electric synchronous
interconnections worldwide. This technical solution permits the functioning of a free
electricity market in general and regional markets as well.
Therefore, UCTE is an efficient, qualitative and secure operation of the
interconnected electrical power supply-demand and gives signals to markets when
system adequacy declines.
The goals of UCTE are as follows;
• to ensure reliable and secure interconnected transmission system operation
• to reduce transmission costs to the lowest possible level by
� co-ordinating electricity flows and
� sharing reserve capacities among countries
• to facilitate the functioning of the electricity market by ensuring non-
discriminatory domestic and cross-border access to the grid
• to enhance opening up of national transmission systems for international
exchanges
• to enlarge the existing electricity market place by extending the
interconnected area towards South-East Europe and neighbouring regions
• to lobby on the behalf of its members at EU institutions, regulators and other
associations of the electricity market in order to ensure the maintenance of
3. UCTE RULES S.Olcay BERĐKOL
23
reliability and the development of the electricity system in the open electricity
market.
The benefits of UCTE are as follows;
• optimization of the use of installed capacities
• reliability improvements reducing the economic cost of power outages
• improved control of system frequency to minimize major disturbances
• stable voltage
• sharing reserve capacities and reducing the level of reserves required
• providing mutual support for the interconnected systems in case of
emergency
In this study, load-frequency control policy, which is the most important
parameter in order to be a member of UCTE network, is especially mentioned and
other policies interested by UCTE are briefly explained.
3.1. UCTE Policies
UCTE has seven strict policies/rules to provide high quality and reliability
electricity in interconnected network. Titles and subtitles of policies are listed as
below.
1. Load-Frequency Control and Performance
1.1. Primary Control
1.2. Secondary Control
1.3. Tertiary Control
1.4. Time Control
1.5. Measures for Emergency Conditions
2. Scheduling and Accounting
2.1. Scheduling
2.2. Online Observation
2.3. Accounting
3. Operational Security
3.1. N-1 Security (operational planning and real-time operation)
3. UCTE RULES S.Olcay BERĐKOL
24
3.2. Voltage control and reactive power management
3.3. Network faults clearing and short circuit currents
3.4. Stability
3.5. Outages scheduling
3.6. Information exchanges between Transmission System Operators (TSOs) for
security of system operation
4. Co-ordinated Operational Planning
4.1. Outage Scheduling
4.2. Capacity Assessment
4.3. Capacity Allocation
4.4. Day Ahead Congestion Forecast
4.5. Congestion Management
5. Emergency Procedures
6. Communication Infrastructure
6.1. The Electronic Highway (EH) Network, Architecture and Operation
6.2. Real Time Data Collection and Exchange
6.3. File Transfer data Exchange
6.4. E-Mail on the EH
6.5. Information Publication in Hypertext on EH
6.6. Procedures for future Services on EH
6.7. Non-EH communication among TSOs
7. Data Exchanges
7.1. Code of conduct and generic rules to handle the data
3.1.1. Load-Frequency Control and Performance
The generation of power units connected to the UCTE network needs to be
controlled and monitored for secure and high-quality operation of the synchronous
areas. The generation control, the technical reserves and the corresponding
performance measurements are essential to allow transmission system operators
(TSO) to perform daily operational business. Control actions are performed in
3. UCTE RULES S.Olcay BERĐKOL
25
different successive steps, each with different characteristics and qualities, and all
depending on each other (UCTE Operation Handbook Policy1, 2004)
• Primary control starts within seconds as a joint action of all undertakings
involved.
• Secondary control replaces primary control after minutes and is put into
action by the responsible undertakings / TSOs only.
• Time control corrects global time deviations of the synchronous time in the
long term as a joint action of all undertakings / TSOs.
Transmission System Operator (TSO) is the pilot of the electricity system.
The TSO is responsible for the safe operation of the system. Each of TSO in the
UCTE interconnected network (synchronous areas) has declared to follow the
technical standards and procedures that are comprised in operation handbook (UCTE
Operation Handbook, 2004). This means that
• taking care of the safe transmission of electricity
• taking care of the reliability and stability of the system
• balancing supply and demand at any time
• maintaining and developing the infrastructure: the networks and related
technical facilities.
In the liberalized electricity market that is developing in the European Union,
the TSO is not itself a market party. Rather, it is the provider of the infrastructure and
of the system management services that are the necessary prerequisites for the
functioning of the market.
As a provider of these services to market parties (generators, traders and
suppliers of electricity) the TSO has not only the technical responsibility for system
operations, but is also responsible for the fair and non-discriminatory access to these
services by market participants. The neutral and independent TSO is a precondition
for fair competition.
Each of generation companies, operating a generating unit in the UCTE
interconnected network, makes use of the transmission network and may have to
deliver products for the provision of system services that are indispensable for secure
and stable grid operation
3. UCTE RULES S.Olcay BERĐKOL
26
3.1.1.1. Primary Control
The objective of primary control is to maintain a balance between generation
and demand (consumption) within the synchronous areas, using turbine speed or
turbine governors. By the joint action of all interconnected undertakings / TSOs,
primary control aims at the operational reliability of the power system of the
synchronous areas and stabilizes the system frequency at a stationary value after a
disturbance or incident in the time-frame of seconds, but without restoring the
reference values of system frequency and power exchanges. Adequate primary
control depends on generation resources made available by generation companies to
the TSOs (UCTE Operation Handbook Policy1, 2004).
3.1.1.2. Balance between Generation and Demand
In any electric system, the active power has to be generated at the same time
as it is consumed. Power generated must be maintained in constant equilibrium with
power consumed / demanded, otherwise a power deviation occurs. Disturbances in
this balance, causing a deviation of the system frequency from its set-point values,
will be offset initially by the kinetic energy of the rotating generating sets and motors
connected. There is only very limited possibility of storing electric energy as such. It
has to be stored as a reservoir (coal, oil, water) for large power systems, and as
chemical energy (battery packs) for small systems. This is insufficient for controlling
the power equilibrium in real-time, so that the production system must have
sufficient flexibility in changing its generation level. It must be able instantly to
handle both changes in demand and outages in generation and transmission, which
preferably should not become noticeable to network users (UCTE Operation
Handbook Appendix1, 2004).
3.1.1.3. System Frequency
The electric frequency in the network (the system frequency f) is a measure
3. UCTE RULES S.Olcay BERĐKOL
27
for the rotation speed of the synchronized generators. By increase in the total demand
the system frequency (speed of generators) will decrease, and by decrease in the
demand the system frequency will increase. Regulating units will then perform
automatic primary control action and the balance between demand and generation
will be re-established. The frequency deviation is influenced by both the total inertia
in the system, and the speed of primary control. Under undisturbed conditions, the
system frequency must be maintained within strict limits in order to ensure the full
and rapid deployment of control facilities in response to a disturbance. Out of periods
for the correction of synchronous time, the set point frequency is 50 Hz (UCTE
Operation Handbook Appendix1, 2004).
Three types of operating conditions are considered where the deviation |∆f|
between the instantaneous frequency and the set point frequency is
• Equal to or less than 50 mHz, operating conditions are considered as normal
• Greater than 50 mHz but less than 200 mHz, operating conditions are deemed
to be impaired, but with no major risk, provided that control facilities in the
affected areas are ready for deployment
• Greater than 200 mHz, operating conditions are deemed to be severely
impaired, because there are significant risks of the malfunction of the
interconnected network.
Even in case of a major frequency deviation / offset, each control area will
maintain its interconnections with adjoining control areas, provided that the secure
operation of its own system is not jeopardized.
3.1.1.4. (etwork Power Frequency Characteristic
An interconnected system consists of control areas (power generation center)
connected by a tie line (TIE). A Tie line is a communication connection between
extensions of a private telephone system. For load-frequency the studies, each area
may be represented by an equivalent bus. On each bus there is equivalent generation.
The network power frequency characteristic of whole synchronous area uλ is
quotient of the power deviation ∆Pa responsible for the disturbance and the quasi-
3. UCTE RULES S.Olcay BERĐKOL
28
steady state frequency deviation ∆f caused by the disturbance (power deficits are
considered as negative values).
f
P au ∆
∆=λ in MW/ Hz (3.1)
The network power frequency characteristic, λi is measured for a given
control area i. This corresponds to the quotient of the power deviation, ∆Pi, and the
frequency deviation, ∆f, in response to the disturbance (in the control area where the
disturbance originates, it will be necessary to add the power surplus, or subtract the
power deficit, responsible for the disturbance concerned).
f
Pii
∆
∆=λ in MW/ Hz (3.2)
The contribution of each control area to the network power frequency
characteristic is based upon the set point value for the network power frequency
characteristic, λio, in the control area concerned. This set-point value is obtained by
the multiplication of the set-point network power frequency characteristic for the
entire synchronous area, λuo, and the contribution coefficients of the various control
areas, Ci :
uoiC λλ ×=io (3.3)
This formula is used to determine the requested contribution Ci of a control
area to primary control.
The network power frequency characteristic of a given control area should
remain as constant as possible, within the frequency range applied. This being so, the
insensitivity range of controllers should be as small as possible, and in any case
should not exceed ±10 mHz. Where dead bands exist in specific controllers, there
must be offset within the control area concerned. The set-point value λuo for the
overall network power frequency characteristic is defined by the UCTE on the basis
of the conditions described in the policy, taking account of measurements,
experience and theoretical considerations (UCTE Operation Handbook Appendix1,
2004).
3. UCTE RULES S.Olcay BERĐKOL
29
3.1.1.5. Primary Control Basics
Various disturbances or random deviations which impair the equilibrium of
generation and demand will cause a frequency deviation, to which the primary
controller of generating sets involved in primary control will react at any time.
The proportionality of primary control and the collective involvement of all
interconnection partners are such that the equilibrium between power generated and
power consumed will be immediately restored, thereby ensuring that the system
frequency is maintained within permissible limits. In case that the frequency exceeds
the permissible limits, additional measures out of the scope of primary control, such
as (automatic) load-shedding, are required and carried out in order to maintain
interconnected operation.
This deviation in the system frequency will cause the primary controllers of
all generators subject to primary control to respond within a few seconds. The
controllers alter the power delivered by the generators until a balance between power
output and consumption is re-established. As soon as the balance is re-established,
the system frequency stabilizes and remains at a quasi-steady-state value, but differs
from the frequency set-point because of the droop of the generators which provide
proportional type of action. Consequently, power cross-border exchanges in the
interconnected system will differ from values agreed between companies. Secondary
control will take over the remaining frequency and power deviation after 15 to 30
seconds. The function of secondary control is to restore power cross-border
exchanges to their (programmed) set-point values and to restore the system
frequency to its set-point value at the same time (UCTE Operation Handbook
Appendix1, 2004).
The magnitude of the dynamic frequency deviation is governed mainly by the
following:
• The amplitude and development over time of the disturbance affecting the
balance between power output and consumption
• The kinetic energy of rotating machines in the system
3. UCTE RULES S.Olcay BERĐKOL
30
• The number of generators subject to primary control, the primary control
reserve and its distribution between these generators
• The dynamic characteristics of the machines (including controllers)
• The dynamic characteristics of loads, particularly the self-regulating effect of
loads
The quasi-steady-state frequency deviation is governed by the amplitude of
the disturbance and the network power frequency characteristic, which is influenced
mainly by the following:
• The droop of all generators subject to primary control in the synchronous
areas
• The sensitivity of consumption to variations in system frequency
3.1.1.6. Principle of Joint Action
Each TSO must contribute to the correction of a disturbance in accordance
with its respective contribution coefficient to primary control. These contribution
coefficients Ci are calculated on a regular basis for each control area or
interconnection partner / TSO using the following formula:
uii EEC ÷= (3.4)
Ei being the electricity generated in control area/ i (including electricity
production for export and scheduled electricity production from jointly operated
units) and Eu being the total (sum of) electricity production in all N control areas of
the synchronous areas.
In order to ensure that the principle of joint action is observed, the network
power frequency characteristics of the various control area should remain as constant
as possible. This applies particularly to small frequency deviations ∆f, where the
dead bands of generators may have an unacceptable influence upon the supply of
primary control energy in the control area s concerned (UCTE Operation Handbook
Appendix1, 2004).
3. UCTE RULES S.Olcay BERĐKOL
31
3.1.1.7. Target Performance
Defining conditions for the target efficiency of primary control are based upon
the following parameters:
• the simultaneous loss of two power plant units, or the loss of a line section or
busbar
• experience has shown that incidents leading to an even greater loss of power
are extremely rare
• the control of such incidents by the activation of far greater control power
than is necessary may lead to the overloading of the transmission system,
thereby jeopardizing the interconnected network
The design hypothesis applied is based upon unfavorable parameters which
provide a margin of safety in estimated values. Consequently, it is probable that even
more serious incidents could be accommodated in practice without the need for load-
shedding. Based on the parameters above, the reference incident was defined to be
3000 MW for the entire synchronous areas.
Starting from undisturbed operation of the interconnected network, a sudden loss
of 3000 MW generating capacity must be offset by primary control alone, without
the need for customer load-shedding in response to a frequency deviation. In
addition, where the self-regulating effect of the system load is assumed according to
be 1 %/Hz, the absolute frequency deviation must not exceed 180 mHz. Likewise,
sudden load-shedding of 3000 MW in total must not lead to a frequency deviation
exceeding 180 mHz. Where the self-regulating effect of the load is not taken into
account, the absolute frequency deviation must not exceed 200 mHz. The following
figure 3.1 shows movements in the system frequency for a given design hypothesis
(case A), where dynamic requirements for the activation of control power are
fulfilled in accordance with the requirements for deployment time. Unfavorable
assumptions have been selected for all model parameters. The maximum absolute
frequency deviation is 800 mHz - this means that the threshold for load-shedding will
not be reached by some margin.
3. UCTE RULES S.Olcay BERĐKOL
32
A Loss in generating capacity: P =3000 MW, Pnetwork = 150 GW, self-regulating effect of load
1% / Hz B1 Loss in generating capacity: P =1300 MW, Pnetwork = 200 GW, self-regulating effect of
load 2% / Hz B2 Loss in generating capacity: P =1300 MW, Pnetwork = 200 GW, self-regulating effect of
load 1% / Hz
Figure 3.1 System frequency movements for different design hypothesis (UCTE Operation Handbook Appendix1, 2004)
For comparative purposes, simulations have also been undertaken using
realistic model parameters (case B), in order to allow the typical frequency deviation
associated with customary losses in generating capacity to be plotted in parallel.
These simulations show that, for a loss of capacity up to 1300 MW, the absolute
frequency deviation will remain below 200 mHz. If the target performance described
above is to be achieved, the system must be operated in such a way, depending upon
the system load, that the network power frequency characteristic for the entire
synchronous area falls within a relatively narrow band. Taking account of the self-
regulating effect of load, this gives the following table (UCTE Operation Handbook
Appendix1, 2004).
3. UCTE RULES S.Olcay BERĐKOL
33
Table 3.1 Self regulating effect of load (UCTE Operation Handbook Appendix1, 2004)
Self-regulating effect Network power Network power frequency characteristic
1 %/Hz 150 GW 16500 MW/Hz
1 %/Hz 300 GW 18000 MW/Hz
2 %/Hz 150 GW 18000 MW/Hz
2 %/Hz 300 GW 21000 MW/Hz
The following assumptions have been applied for the definition of marginal
conditions for the operation of primary control:
• Design basis / reference incident: Sudden deviation of 3000 MW in the
balance of production and consumption; system off-peak load about 150 GW
and peak load about 300 GW
• System start time constant: 10 to 12 seconds
• Self-regulating effect of load: 1 %/Hz
• Maximum permissible frequency deviation quasi-steady-state: ±180 mHz and
dynamic: ±800 mHz
The maximum dynamic frequency deviation of ±800 mHz includes a safety
margin. This margin of 200 mHz in total is intended to cover the following
influences and elements of uncertainty:
• Possible stationary frequency deviation before an incident (50 mHz)
• Insensitivity of turbine controller (20 mHz)
• Larger dynamic frequency deviation at the site of the incident, not taken into
account in the specific network model used for simulations (50 mHz)
• Other elements of uncertainty in the model (approximately 10 %, 80 mHz)
In case of load-shedding, accuracy of 50 to 100 mHz will generally suffice
for relay trip thresholds (UCTE Operation Handbook Appendix1, 2004).
3. UCTE RULES S.Olcay BERĐKOL
34
3.1.1.8. Primary Control Reserve
The total primary control reserve, Ppu, for the entire synchronous area is
determined by the UCTE on the basis of the conditions set out in the previous
subsections, taking account of measurements, experience and theoretical
considerations.
The shares Ppi of the control areas are defined by multiplying the calculated
reserve for the synchronous area and the contribution coefficients Ci of the various
control areas :
ipupi CPP ×= (3.5)
The entire primary control reserve is activated in response to a quasi-steady-
state frequency deviation of -200 mHz or more. Likewise, in response to a frequency
deviation of +200 mHz or more, power generation must be reduced by the value of
the entire primary control reserve.
In order to restrict the calling up of the primary control reserve to
unscheduled power unbalances, the system frequency should not exceed or fall
below a range of ±20 mHz for long periods under undisturbed conditions (UCTE
Operation Handbook Appendix1, 2004).
3.1.1.9. Deployment Time of Primary Control Reserve
The deployment time of the primary control reserves of the various control
areas should be as similar as possible, in order to minimize dynamic interaction
between control areas. In this instance, we are concerned with anticipated
performance, rather than with the logic of controllers.
A reference incident of 3000 MW (loss of generation or load) for the
synchronous area is considered. The primary control reserve of each control area
must be fully activated within 15 seconds in response to disturbances ∆P of less than
1500 MW (it has been assumed that, where values for reserve power to be activated
are smaller, deployment times of less than 15 seconds will be difficult to achieve), or
3. UCTE RULES S.Olcay BERĐKOL
35
within a linear time limit from 15 to 30 seconds in response to a ∆P of 1500 to 3000
MW.
3.1.1.10. Secondary Control
Any imbalance between electric power generation and consumption will
result (in real-time) in a frequency change within the complete network of the
synchronous area. As a result over time, a frequency deviation occurs. At system
frequencies below 50 Hz, the total demand has been larger than the total generation,
at frequencies above 50 Hz the total demand has been less than the total generation.
In practice, the demand varies continuously, even without having forecast errors, so
that secondary control on a real-time basis is required on a continuous basis. A
deviation ∆f of system frequency from its set-point value of 50 Hz will activate
primary control power throughout the synchronous area (UCTE Operation Handbook
Appendix1, 2004)
fP uu ∆×=∆ λ (3.6)
With, λu is the power system frequency characteristic of the whole
synchronous area, i.e. the sum of the power system frequency characteristic of all
control areas.
Primary control allows a balance to be re-established at a system frequency
other than the frequency set-point value (at a quasi-steady-state frequency deviation
∆f), in response to a sudden imbalance between power generation and consumption
(incident) or random deviations from the power equilibrium. Since all control areas
contribute to the control process in the interconnected system, with associated
changes in the balance of generation and consumption in these control area, an
imbalance between power generation and consumption in any control area will cause
power interchanges between individual control areas to deviate from the agreed /
scheduled values (power interchange deviations ∆Pi).
The function of secondary control is to keep or to restore the power balance
in each control area and, consequently, to keep or to restore the system frequency f
to its set-point value of 50 Hz and the power interchanges with adjacent control areas
3. UCTE RULES S.Olcay BERĐKOL
36
to their programmed scheduled values, thus ensuring that the full reserve of primary
control power activated will be made available again. In addition, secondary control
may not impair the action of the primary control. These actions of secondary control
will take place simultaneously and continually, both in response to minor deviations
(which will inevitably occur in the course of normal operation) and in response to a
major discrepancy between production and consumption (associated e.g. with the
tripping of a generating unit or network disconnection). In order to fulfill these
requirements in parallel, secondary control needs to be operated by the network
characteristic method.
Whereas all control areas provide mutual support by the supply of primary
control power during the primary control process, only the control area affected by
a power unbalance is required to undertake secondary control action for the
correction. Consequently, only the controller of the control area, in which the
imbalance between generation and consumption has occurred, will activate the
corresponding secondary control power within its control area. Parameters for the
secondary controllers of all control areas need to be set such that, ideally, only the
controller in the zone affected by the disturbance concerned will respond and initiate
the deployment of the requisite secondary control power. Within a given control
area, the demand should be covered at all times by electricity produced in that area,
together with electricity imports (under purchase contracts and/or electricity
production from jointly operated plants outside the zone concerned). In order to
maintain this balance, generation capacity for use as secondary control reserve must
be available to cover power plant outages and any disturbances affecting production,
consumption and transmission. Secondary control is applied to selected generator
sets in the power plants comprising the control loop. Secondary control operates for
periods of several minutes, and is therefore timely dissociated from primary control.
This behavior over time is associated with the PI (proportional-integral)
characteristic of the secondary controller. Secondary control makes use of
measurements of the system frequency and active power flows on the TIE lines of
the control area, a secondary controller, which computes power set-point values of
3. UCTE RULES S.Olcay BERĐKOL
37
selected generation sets for control, and the transmission of these set-point values to
the respective generation sets.
When consumption exceeds production on a continuous basis, immediate
action must be taken to restore the balance between the two (by the use of standby
supplies, contractual load variation or Load-Shedding or the shedding of a proportion
of customer load as a last resort). Sufficient transmission capacity must be
maintained at all times to accommodate reserve control capacity and standby
supplies. Since it is technically impossible to guard against all random variables
affecting production, consumption or transmission, the volume of reserve capacity
will depend upon the level of risk which is deemed acceptable. These principles will
apply, regardless of the division of responsibilities between the parties involved in
the supply of electricity to consumers (UCTE Operation Handbook Appendix1,
2004).
Secondary control must begin within 30 seconds of the disturbance
concerned, i.e. when the action of primary control is complete, even under the most
stringent conditions assumed for the reference incident; secondary control must be
fully deployed within 15 minutes. If the loss of the largest generating unit supplying
the area concerned is not covered by the secondary reserve of that area, provision
must be made for an additional reserve which will offset the loss of capacity within
the requisite time. This reserve may take the form of generating plant with the
facility for rapid start-up, the adjustment of set points for generating units in service
or load shedding. This additional reserve may also be obtained from other control
areas. The operator responsible for each control area will undertake the regular
assessment of the performance of secondary control, particularly in the case of losses
of capacity exceeding 600 MW. Members will provide the information required for
this analysis.
3.1.1.11. Tertiary Control
Tertiary control is any automatic or manual change in the working points of
generators or loads participating, in order to:
3. UCTE RULES S.Olcay BERĐKOL
38
• Guarantee the provision of an adequate secondary control reserve at the right
time,
• Distribute the secondary control power to the various generators in the best
possible way, in terms of economic considerations.
Changes may be achieved by:
• connection and tripping of power (gas turbines, reservoir and pumped storage
power stations, increasing or reducing the output of generators in service);
• redistributing the output from generators participating in secondary control;
• changing the power interchange program between interconnected
undertakings;
• load control
Typically, operation of tertiary control (in succession or as a supplement to
secondary control) is bound to the time-frame of scheduling, but has on principle the
same impact on interconnected operation as secondary control.
The power which can be connected automatically or manually under tertiary
control, in order to provide / restore an adequate secondary control reserve, is known
as the tertiary control reserve / 15 minute reserve. This tertiary control reserve must
be used in such a way that it will contribute to the restoration of the secondary
control range when required (UCTE Operation Handbook Appendix1, 2004).
3.1.1.12. Time Control
If the mean system frequency in the synchronous zone deviates from the
nominal frequency of 50 Hz, this results in a discrepancy between synchronous time
and universal coordinated time (UTC). This time offset serves as a performance
indicator for primary, secondary and tertiary control (power equilibrium) and must
not exceed 30 seconds. The Laufenburg control centre in Switzerland is responsible
for the calculation of synchronous time and the organization of its correction.
Correction involves the setting of the set-point frequency for secondary control in
each control area at 49.99 Hz or 50.01 Hz, depending upon the direction of
correction, for full periods of one day (from 0 to 24 hours).
3. UCTE RULES S.Olcay BERĐKOL
39
The quality of system frequency will be regarded as satisfactory over one
month period (UCTE Operation Handbook Appendix1, 2004)
• where the standard deviation for 90% and 99% of measurement intervals is
less than 40 mHz and 60 mHz respectively for the whole month considered;
• where the number of days’ operation at a set point frequency of 49.99 Hz or
50.01 Hz does not exceed eight days per month respectively (to be confirmed
by experience).
3.1.2. Scheduling and Accounting
It is compulsory to schedule in advance the power to be exchanged at the
interconnection borders between the system operators in order to operate a large
power system like UCTE and to create the suitable conditions for commercial
electricity trade.
During daily operation, the schedules are followed by means of the load-
frequency control installed in each control area. Notwithstanding load-frequency
control, unintentional deviations invariably occur in energy exchanges. For this
reason, it is necessary to co-ordinate the schedule nomination between the system
operators, to observe in real-time unintentional deviations and to co-ordinate
accounting and computation of the compensation programs to balance unintentional
deviations (UCTE Operation Handbook Policy2, 2004)
3.1.3. Operational Security
System safety is the primary goal of the operation of the interconnected
network. In an interconnected system there exist numerous inter-dependencies of the
networks forming part of the system. In addition, there are impacts attributable to the
usage of the system by market players. In an unbundled environment, network
operators are not allowed to interfere with market forces unless system safety is at
stake. The operation of the interconnected network is founded on the principle that
each partner is responsible for its own network. To harmonize the operating methods
3. UCTE RULES S.Olcay BERĐKOL
40
for the interconnected network, UCTE has since the beginning worked out rules,
instructions and suggestions, to which the operation of each network has to make
reference in order to ease inter-operability. TSOs are in charge of managing the
security of operation of their own networks in a subsidiary way. The most relevant
rules for the security of interconnected operation are related mainly to the
functioning of interconnections. TSOs cooperatively adapt continuously such
common rules for inter-operability to be applied mainly at the borders of their control
areas and consequently at the borders of countries . These rules create favorable
conditions for cross-border exchanges at destination of network users and of TSOs
themselves. All these co-ordinating rules complement any other existing national
commitments for network access (legal and contractual) for the transmission
networks when they exist. The control of performances of facilities connected to
networks remains under the responsibility of TSOs to the extent of their national
commitments. This policy specifies the requirements for operating the transmission
system to maintain security. Each control area and transmission system operator -
TSO - is responsible of procedures for reliable operation over a reasonable future
time period in view of real-time conditions, with contingency and emergency
conditions, and of their preparation. Coordination between TSOs contributes to
enhance the common solidarity (to cope with risks) resulting from the operation of
interconnected networks, to prevent disturbances, to provide assistance in the event
of failures with a view to reducing their impact and to provide resetting strategies
after a collapse. This co-ordination is intensively developed covering today new
aspects related to market mechanisms (UCTE Operation Handbook Policy3, 2004)
3.1.3.1.Voltage and Reactive Power Control
Since reactive power transmission over long distances is virtually impossible,
the balance between reactive power generation and demand must be maintained on a
regional basis within the area of operation concerned. Reactive power transmission
will cause voltage drops and losses. It is therefore preferable that system operation
should be optimized in such a way that the balance of reactive power will be
3. UCTE RULES S.Olcay BERĐKOL
41
maintained as effectively as possible on a local basis. In reactive power (and
therefore voltage) control, a distinction is drawn between primary, secondary and
tertiary voltage control.
Primary control is implemented by the voltage regulators of generating units,
which will initiate a rapid variation in the excitation of generators when they detect a
variation in voltage across their terminals. Other controllable devices, such as static
var compensators (SVCs) may also be involved in primary voltage control.
Secondary control co-ordinates the action of voltage and reactive power control
devices within a given zone of the network in order to maintain the requisite voltage
level in the system. Tertiary control involves a process of optimization, using
calculations based upon real time measurements, in order to adjust the settings of
devices which influence the distribution of reactive power (generating unit
controllers, tap transformer controllers and compensating devices, such as
inductances and capacitors). Where the system load is high, the operator must be
certain that, in case of a loss of generation, the remaining facilities will be able to
deliver enough reactive power to keep the voltage within the required range. The
same applies to the converse situation, where the system load is low and reactive
power needs to be absorbed. Voltage profiles on either side of tie-lines must be
harmonized by the operators of adjoining systems in order to allow the effective
management of reactive power flows. Where voltage deviations lead to constraints
on adjoining systems on a regular basis, compensating equipment must be installed
in order to keep the system voltage within the normal range.
3.1.3.2.“(-1”(etwork Security
The “N-1” criterion means that, under all operating conditions, the loss of any
given element (line, transformer, generating unit, compensation facility etc.) will not
lead to operating constraints in adjoining operating zones (as a result of limit values
being exceeded for current, voltage, stability, etc.) and, by the same token, will not
cause interruptions in supply. Although, under these conditions, it will not be
necessary to interrupt network operation as a result of the loss of one element, the
3. UCTE RULES S.Olcay BERĐKOL
42
structure of the system concerned will need to be reorganized in order to comply
again with the ”N-1” criterion within the shortest possible time. In the intervening
time, the loss of a further element might indeed jeopardize continuity of operation.
Various arrangements may be prepared to ensure operational security in case
of serious outages, such as the simultaneous loss of both circuits on a double circuit
line or the loss of a bus-bar. The selection of measures to be applied will depend
upon the comparative analysis of technical and economic factors, taking account of
the following:
• the probability of the type of incident concerned;
• the consequences of that type of incident;
• expenses incurred for the provision of permanent risk cover;
• the cost of protective measures required to prevent the extension of an
incident
The entire network, including cross-border tie-lines, must be operated in such
a way that sufficient transmission capacity will be available for the delivery of
reserve primary control power to the areas which may be affected by an incident.
3.1.4. Co-ordinated Operational Planning
UCTE describes several stages of the operational planning phase. It starts
approximately one year before actual operation with an outage scheduling process
and continues through capacity assessment, day ahead congestion forecast until real-
time n-1 security management (UCTE Operation Handbook Policy4, 2006).
3.1.5. Emergency Procedures
In an extremely complex and highly meshed system, disturbances may be
propagated over a vast area within a very short period of time. Whatever precautions,
the short-term occurrence of insecure operating conditions can take place at any time
due to a cascade of contingencies. Therefore, it is necessary in the “Emergency
Operations” to anticipate any critical situation within a very few hours or a few
3. UCTE RULES S.Olcay BERĐKOL
43
minutes before the real time operation, preventing system cascading and limiting its
consequences (UCTE Operation Handbook Policy5, 2006).
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
44
4. CO�TROL STRATEGY OF GE�ERATOR
4.1. General
The frequency of a power system is dependent on real power balance. A
change in real power demand at one point of a network is reflected throughout the
system by a change in frequency (Kundur, 1994). Therefore, system frequency
provides a useful index to indicate system generation and load imbalance. Any short-
term energy imbalance will result in an instantaneous change in system frequency as
the disturbance is initially offset by the kinetic energy of the rotating plant.
Significant loss in the generation without an adequate system response can produce
extreme frequency excursions outside the working range of the plant.
Depending on the type of generation, the real power delivered by a generator
is controlled by the mechanical power output of a prime mover such as a steam
turbine, gas turbine, hydro-turbine or diesel engine. In the case of a steam or hydro-
turbine, mechanical power is controlled by the opening or closing of valves,
regulating the input of steam or water flow into the turbine. Steam (or water) input to
generators must be continuously regulated to match real power demand, failing
which the machine speed will vary with consequent change in frequency. For
satisfactory operation of a power system, the frequency should remain nearly
constant. In addition to a primary frequency control, most large synchronous
generators are equipped with a supplementary frequency control loop.
Maintaining the frequency at its target value requires that the active power
produced and/or consumed be controlled to keep the load and generation in balance.
A certain amount of active power, usually called frequency control reserve, is kept
available to perform this control. The positive frequency control reserve designates
the active power reserve used to compensate for a drop in frequency. On the other
hand, the deployment of negative frequency control reserve helps to decrease the
frequency.
Primary and secondary frequency control in a coordinated mode is required in
any transmission and distribution grid in order to keep the frequency as close as
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
45
possible to the nominal frequency. The operation of the grids is necessary in order to
protect the consumers connected as well as to keep the grid in a stable condition.
Reasons for frequency deviations
• Deviations in consumption
• Failures in the grid and transmission system respectively
• Failures in the generation; forced shut downs of generators
• Generation program is not matching the consumption
Primary frequency load control, decentralized on the generators, is a local
automatic control that adjusts the active power generation of the generating units and
the consumption of controllable loads to restore quickly the balance between load
and generation and counteract frequency variations (Ingleson et al., 2005). Hence,
the purpose of primary control is to balance the energy in interconnected system
between demand and supply.
In particular, it is designed to stabilize the frequency following large
generation or load outages. It is thus indispensable for the stability of the power
system. All generators that are located in a synchronous zone and are fitted with a
speed governor perform this control automatically. The demand side also participates
in this control through the self-regulating effect of frequency-sensitive loads such as
induction motors (Kundur, 1994) or the action of frequency-sensitive relays that
disconnect or connect some loads at given frequency thresholds. However, this
demand-side contribution is not always taken into account in the calculation of the
primary frequency control response.
The provision of this primary control is subject to some constraints. Some
generating units that increase their output in response to a frequency drop cannot
sustain this response for an indefinite period of time. Their contribution must
therefore be replaced before it runs out. It is also important that the contributors to
primary control be distributed across the interconnected network to reduce unplanned
power transits following a large generation outage and enhance the security of the
system. In addition, a uniform repartition helps maintain the stability of islanded
systems in case of a power system separation.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
46
Secondary frequency control is a centralized automatic control that adjusts
the active power production of the generating units to restore the frequency and the
interchanges with other systems to their target values following an imbalance. In
other words, while primary control limits and stops frequency excursions, secondary
control brings the frequency back to its target value. Only the generating units that
are located in the area where the imbalance originated should participate in this
control as it is the responsibility of each area to maintain its load and generation in
balance. Note that loads usually do not participate in secondary frequency controls.
Contrary to primary frequency control, secondary frequency control is not
indispensable. This control is thus not implemented in some power systems where
the frequency is regulated using only automatic primary and manual tertiary control.
However, secondary frequency control is used in all large interconnected systems
because manual control does not remove overloads on the tie lines quickly enough
(Rebours et al., 2007).
Tertiary frequency control refers to manual changes in the dispatching and
commitment of generating units. This control is used to restore the primary and
secondary frequency control reserves, to manage congestions in the transmission
network, and to bring the frequency and the interchanges back to their target value
when the secondary control is unable to perform this last task. Some aspects of
tertiary control relate to the trading of energy for balancing purposes. This paper
does not deal with secondary and tertiary frequency control because they do not
represent a criteria applied to the TSO by the UCTE.
4.2. Frequency and Voltage Control
The turboset is mainly controlled by the turbine governor, which consists of a
power and a speed controller, and the voltage regulator (see figure 4.1). The turbine
governor influences the position h of the control valves that regulate a mass flow of
gas or steam to the turbine. By means of the governor droop, it is able to perform a
frequency response contribution to slow changes in the grid frequency but, owing to
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
47
the limited dynamic range of the valves, it cannot intervene at frequencies above
approximately 0.1Hz.
Figure 4.1 Generator control system
The purpose of the voltage regulator is to keep the terminal voltage of the
generator as constant as possible, thus making it independent of external interference.
If the voltage then behaves like an impressed quantity, the generator is able to make
a substantial contribution towards supporting the grid. Thus, one of the most
important tasks of a voltage regulation facility is to adjust the available excitation
power in the case of a short circuit in the grid so as to enable tracing of the fault
location and its isolation from the grid. When this has taken place, the task of the
voltage regulator is to stabilize the required terminal voltage as swiftly as possible to
prevent the failure of station-service equipment. The same applies conversely in the
case of load rejection. A high quality of voltage regulation is therefore an important
requirement. As mentioned above, the dynamic range of voltage regulation must not
be increased at random.
The high dynamics of the excitation system basically permits a reaction to
active power oscillations, but the voltage is fed to the voltage regulator as a
controlled variable.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
48
After a consideration of the turboset in its entirety as a controlled system, the
approach towards combating oscillations becomes apparent. The manipulated
variable of voltage regulation, the exciter voltage Vf, not only influences the
generator’s terminal voltage Vt, but also the active power P
e delivered to the grid
(transfer function GPV). Although the steady state portion of the active power cannot
be modified by the exciter voltage (this can only be done by the turbine governors),
the dynamic portions can be influenced by exciter voltage transients.
The link between the exciter voltage and the output active power can be used
to realize an additional stabilization control loop shown in figure 4.2. The component
used for stabilization is the power system stabilizer (PSS) (Kutzner, 1999). PSS is
not a must to control a generator or to operate a power plant. It is used as an option.
Figure 4.2 Power system stabilizer (Kutzner, 1999)
4.2.1. Modeling the PSS
The use of a PSS can be looked upon as being an option. Basically, a power
plant can also be operated without a PSS if the voltage regulator is set to a low gain.
If noteworthy grid support is to be realized, however, the proportional gain of the
voltage regulator must be increased in order to have a greater effect in the event of
grid interference. The resulting quick response of the modes of the turboset on the
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
49
grid should, however, be counteracted by a PSS that has been harmonized to the
voltage regulator.
The arrangement of the PSS clearly indicates the factors that restrict its
performance capabilities:
• Only oscillating components of the active power can be influenced. The
DC component and the low-frequency components can only be
influenced by a variable supply of power by the way of the control
valves.
• If the effect of the PSS in the lower frequency range is not suppressed
by the design criteria or by other measures, extreme interactions
between voltage regulation and the PSS may be the result. It is
therefore necessary to harmonize the regulator design and the
parameters of the PSS.
• Extreme power transients may trigger considerable shifts of the reactive
power, which might lead to tripping of protective facilities. This must
be avoided by means of suitable switch-off criteria.
• The dynamic range of the PSS is limited only by the exciter system. At
the same time, in comparison with the frequencies of the occurring
generator oscillations, the fact that the dynamic range is restricted by
the time constant of the main exciter hardly is of any importance
(Kutzner, 1999).
4.2.2. Modeling the Excitation System
Control of the excitation system of a synchronous machine has a very strong
influence on its performance, voltage regulation, and stability. Not only is the
operation of a single machine affected by its excitation, but also the behavior of the
whole system is dependent on the excitation system of separate generators. For
example, inter-area oscillations are directly connected to the excitation of separate
generators. These are only a few arguments justifying the necessity for accurate and
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
50
precise modeling of the excitation system of a synchronous machine. A basic scheme
of excitation control is shown in figure 4.3.
Figure 4.3 Voltage control of synchronous generator
The purpose of the automatic voltage controller (AVR) is to control the
machine terminal voltage. This is achieved by the adjusting the setting of the
excitation system which ultimately adjusts the field voltage seen by the machine. It is
a common practice to use the AVR to fix the terminal voltage of the machine and
adjust the HV grid voltage by tapping the generator transformer.
This subsection therefore presents the modeling principles of the excitation
system. A detailed treatment of all aspects of the modeling is far beyond the scope of
the thesis; we only synoptically present a literature survey on the subject.
4.2.3. Modeling the Turbine and Governor
The number of poles of a synchronous generator and the speed of the prime
mover determine the frequency of the ac current produced by the generator. In order
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
51
to control the primer mover, turbine with associated controls is used in power
systems.
The MW response of the thermal power plant to the frequency regulation can
be divided into two components; one is the slow component responding to the MW
demand change due to secondary control, and the other is the fast component around
the slow component due to the action of the primary frequency (governor) control to
the generator speed error.
Demand rate limit, boiler response delay, and boiler steam sliding pressure
control are considered while designing a LFC. For the fast action, turbine governor
response, turbine load reference control and steam pressure change due to turbine
control valve movement are also considered. This study is dealing with primary
frequency control due to the UCTE policy.
Governing system is an important control system in the power plant as it
regulates the turbine speed, power and participates in the grid frequency regulation.
For starting, loading governing system is the main operator interface. Steady state
and dynamic performance of the power system depends on the power plant response
capabilities in which governing system plays a key role. With the development of
electro- hydraulic governors, processing capabilities have been enhanced but several
adjustable parameters have been provided. A thorough understanding of the
governing process is necessary for such adjustment.
The load on a turbine generating unit does not remain constant and can vary
as per consumer requirement. The mismatch between load and generation results in
the speed (or frequency) variation. When the load varies, the generation also has to
vary to match it to keep the speed constant. This job is done by the governing
system. Speed which is an indicator of the generation - load mismatch is used to
increase or decrease the generation.
Governing system controls the steam flow to the turbine in response to the
control signals like speed error, power error. It can also be configured to respond to
pressure error. It is a closed loop control system in which control action goes on till
the power mismatch is reduced to zero.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
52
As shown in the basic scheme given in figure 4.4, the inlet steam flow is
controlled by the control valve or the governor valve. It is a regulating valve. The
stop valve shown in the figure ahead of control valve is used for protection. It is
either closed or open. In emergencies steam flow is stopped by closing this valve by
the protective devices.
Figure 4.4 Steam turbine governing scheme
The governing process can be functionally expressed in the form of signal
flow block diagram shown in figure 4.5. The electronic part output is a voltage or
current signal and is converted into a hydraulic pressure or a piston position signal by
the electro- hydraulic converter (EHC). Some designs use high pressure servo valves.
The control valves are finally operated by hydraulic control valve servo motors.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
53
Figure 4.5 Block diagram of the governing system
The steam flow through the control valve is proportional to the valve opening
in the operating range. So when valve position changes, turbine steam flow changes
and turbine power output also changes proportionally. Thus governing system
changes the turbine mechanical power output.
In no load unsynchronized condition, all the power is used to accelerate the
rotor only (after meeting rotational losses) and hence the speed changes. The rate of
speed change is governed by the inertia of the entire rotor system. In the grid
connected condition, only power pumped into the system changes when governing
system changes the valve opening.
When the turbine generator unit is being started, governing system controls
the speed precisely by regulating the steam flow. Once the unit is synchronized to the
power system grid, same control system is used to load the machine. As the
connected system has very large inertia (infinite bus), one machine cannot change the
frequency of the grid. But it can participate in the power system frequency regulation
as part of a group of generators that are used for automatic load frequency control.
As shown in the block diagram figure 4.5, the valve opening changes either
by changing the reference setting or by the change in speed (or frequency). This is
called primary regulation. The reference setting can also be changed remotely by
power system load frequency control (secondary regulation). Only some generating
units in a power system may be used for secondary regulation.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
54
4.2.3.1. Electro Hydraulic Governing System
Basically the controls can be described as speed control when the machine is
not connected to the grid or in isolation and load control when the machine is
connected to the grid. The governing system has three functional parts: sensing part,
processing part and amplification. These functions are realized using a set of
electronic, hydraulic and mechanical elements, in the electro-hydraulic governor
(EHG), as shown in figure 4.6.
Figure 4.6 Electro-hydraulic governor scheme
Sensing is to sense speed and power. The well known fly ball governor is a
mechanical speed sensor which converts speed signal into a mechanical movement
signal. Nowadays electronic sensors using Hall Effect principle and/or hydraulic
sensor (a special pump whose output pressure varies with pump speed linearly) is
used for speed measurement.
Processing is to evolve the desired valve opening command signal
proportional (P) or proportional integral (PI) or proportional integral derivative (PID)
or a combination of these. In digital governors the processing is done using software
blocks.
Amplification is necessary to obtain sufficient power to operate the steam
control valve.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
55
4.2.3.2. Speed Controller and Power-Load Controller
Speed control provides the primary method of controlling the speed of the
turbine by comparing the feedback from the power grid or two speed signals to the
speed set point. This comparison generates an error term which is used to generate
the control output. The control output is low selected with the output of the valve
ramp function and the auxiliary loop function to obtain the value for the valve output
function.
Speed Control (SC) is used for start-up, in disturbance states and in island
operation. Power Control (PC) mode is used for primary frequency control. Speed
control loop demands additional capability to dampen the speed oscillations. This is
obtained using so called proportional derivative (PD) controller. In this the valve
opening command is proportional to the rate of change (or derivative) of the error
also. This can improve the dynamic response considerably. Power-Load control loop
deals only with MW error, which is obtained using a MW- transducer and is mainly a
proportional integral (PI) controller. This loop is active when the steam turbine
generator is connected to the grid. There is a selection logic which decides which
control loop should prevail. Separate control actions incorporated for speed and load
control are shown in figure 4.7.
Figure 4.7 Speed and load controllers
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
56
During grid operation the speed controller is deactivated. There is only
frequency droop that modifies power. Therefore this mode is referred to as power
control mode shown in figure 4.8.
The expression “island” in figure 4.8 refers to the formation of a partial grid
after a system fault with disconnection from the interconnected system, with one or
more generators then supplying the remaining loads. At the moment of disconnection
from the interconnected system the terminal load of the generators must suddenly
adapt to the new load level. The transient and the remaining generation must be
managed by the frequency/load controller.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
57
ISLA�D OPERATIO�
PARALLELGRID
Figure 4.8 Power control and Speed control modes
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
58
4.2.3.3. Droop Characteristic
Whenever there is a mismatch in power, speed changes. As mentioned earlier,
the governing system senses this speed change and adjusts valve opening which in
turn changes power output. This action stops once the power mismatch is made zero.
But the speed error remains. What should be the change in power output for a change
in speed is decided by the regulation. If 4% change in speed causes 100% change in
power output, then the droop is said to be 4% (or in per unit 0.04).
Speed-droop is the change in active power output of the unit proportional to
the frequency deviation as shown in figure 4.9. At 100 % load the generation is also
100 %, frequency (or speed) is also 100%. When load reduces frequency increases,
as generation remains the same. When load reduces by 50 %, frequency increases by
2 %, in the characteristic shown. When load reduces by 100 %, frequency increases
by 4 %. In other words 4 % rise in frequency should reduce power generation by 100
%. The characteristic is of drooping type. Droop or regulation is an important
parameter in the frequency regulation. In thermal power plants droop value is
generally between 4 % and 6 %.
Figure 4.9 Droop characteristic
In terms of control system steady state gain is expressed as inverse of droop:
gain of 25 in per unit corresponds to 4 % (or 0.04 p.u.) droop.
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
59
The speed droop (S.D.) of a generator is briefly defined as a ratio (without
dimension) and a percentage;
%100P / P
f / f-..
N
n×
∆
∆=DS (4.1)
The variation in system frequency ∆f is defined as follows, with fn being the
nominal frequency and f is the set frequency (50 Hz).
nfff −=∆ (4.2)
The relative variation in power output is defined as the quotient of the
variation in power output ∆P of a generator (in steady-state operation, provided that
the primary control range is not completely used up) and its rated active power
output PN .The contribution of a generator to the correction of a disturbance on the
network depends mainly upon the droop of the generator and the primary control
reserve of the generator concerned. The following figure 4.10 shows a diagram of
variations in the generating output of two generators “a” and “b” of different droop
under equilibrium conditions, but with identical primary control reserves (UCTE
Operation Handbook Appendix1, 2004).
Figure 4.10 Different droop with same primary control reserve (UCTE Operation
Handbook Appendix1, 2004)
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
60
In case of a minor disturbance (frequency offset < ∆fb), the contribution of
generator “a”, which has the controller with the smaller droop, to the correction of
the disturbance will be greater than that of generator “b”, which has the controller
with the greater droop. The frequency offset (∆fa) at which the primary control
reserve of generator a will be exhausted (i.e. where the power generating output
reaches its maximum value Pmax) will be smaller than that of generator b (∆fb), even
where both generators have identical primary control reserves In case of a major
disturbance (frequency offset > ∆fb), the contributions of both generators to primary
control under quasi-steady-state conditions will be equal (UCTE Operation
Handbook Appendix1, 2004).
4.2.3.4. Governor insensitivity or dead band
The governing system action depends on speed sensing. There is a minimum
value of speed which cannot be picked by the sensing mechanism and hence may
remain uncorrected. This minimum value is called governor insensitivity or dead
band. The characteristic is shown in figure 4.11.
Figure 4.11 Dead band characteristic
Valve Opening
Speed Frequency
Dead band or insensitive zone
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
61
Sometimes due to wear and tear dead band increases over a period of time.
This is detrimental to the frequency regulation. In control system analysis, it is well
known that dead band or hysteresis in a closed loop causes instability or limit cycle
oscillations. Governor hunting may occur. At the same time, governor should not
react for very small changes in frequency, so dead band is introduced intentionally in
the electronic governor which is an adjustable feature.
4.2.3.5. Transient Speed Rise
The governing system, as noted earlier is a closed loop control system.
Stability is an important parameter in any feedback control system. Stability and
speed of response depend on the signal modifications done by various blocks in the
loop. The closed loop gain depends on the individual block gains and the adjustable
gains provided in the speed controller and load controller. The gain at the steady state
and during the transient is important in deciding the performance. If the gain is not
proper there can be hunting in the system. Various parameters like speed, power,
valve opening will be oscillating continuously and may ultimately result in the trip of
the turbine.
Governing system maintains the turbine speed as set by the reference. When
there are disturbances, the response should be quick otherwise speed may continue to
deviate. Transient speed rise (TSR) is one important criterion that is used to judge the
response capability of the governing system. Load shedding or load rejection is a
major disturbance. When the turbogenerator unit is running at full load, if the circuit
breaker opens, load is cut off. The full load steam flow causes the rotor to accelerate.
The steam inflow is to be cutoff as soon as possible. It cannot be done
instantaneously as the hydro mechanical elements take certain time to respond.
Speed shoots up and then falls gradually due to the closure of control valve. The
peak value of speed is called transient speed rise (TSR).
4.CONTROL STRATEGY OF GENERATOR S.Olcay BERĐKOL
62
Even when the control valves are closed steam remaining in the steam
volume of reheater piping, turbine cylinders (entrained steam) continue to do the
work and increase the speed for few seconds.
There is an emergency governor provided to stop the turbine if the speed
crosses its setting. The standards specify that the TSR value should be less than the
emergency governor setting. That means when there is a full load throw-off,
governing system should act fast so that turbine does not trip.
There are other devices provided in the governing system which help in
minimizing transient speed rise like load shedding relay (LSR) which cause feed
forward action to close governing valves before speed variation is sensed by the
speed transducer.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
63
5. SIMULIK MODELIG OF TURBOSET
5.1. General
Simulink is a graphical extension to MATLAB for the modeling and
simulation of systems. In simulink, systems are drawn on screen as block diagrams.
Many elements of block diagrams are available (such as transfer functions, summing
junctions, etc.), as well as virtual input devices (such as function generators) and
output devices (such as oscilloscopes). Simulink is integrated with MATLAB and
data can be easily transferred between the programs. Simulink is supported on
UNIX, Macintosh, and Windows environments.
Simulink supports linear and non-linear systems modeled in continuous time,
sampled time or a hybrid of the two. Simulink includes a comprehensive block
library of sinks, sources, linear and non-linear components and connectors (Dynamic
System Simulation for Matlab, 1998). It has an extensive control library that allows
easy implementation of any control algorithm, including linear control, fuzzy logic,
neural networks and others. Simulink provides a graphical user interface (GUI) for
building models as block diagrams. Simulink encourages you to try things out. You
can easily build models from scratch or take an existing model and add to it. You
have instant access to all the analysis tools in MATLAB, so the results can be taken,
analyzed and visualized.
The power system blockset is designed to provide a modern design tool that
allows scientists and engineers to rapidly and easily build models that simulate
power systems. Models are hierarchical, so we can build models using both top-
down and bottom-up approaches. After a model is defined, it can be simulated, using
a choice of integration methods, either from the Simulink menus or by entering
commands in the MATLAB command window.
SimPowerSystems extends simulink with tools for modeling and simulating
the generation, transmission, distribution, and consumption of electrical power. It
provides models of many components used in these systems, including three-phase
machines, electric drives, and libraries of application-specific models such as flexible
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
64
ac transmission systems (FACTS) and wind-power generation. SimPowerSystems
models can be discretized to speed up simulations. The sensor blocks can be used in
SimPowerSystems to measure current and voltage in your power network, and then
pass these signals into standard simulink blocks. Source blocks enable simulink
signals to assign values to the electrical variables current and voltage. Sensor and
source blocks can be connected a control algorithm developed in simulink to a
SimPowerSystems network.
5.2. Design Considerations
The design consideration of turboset is mainly affected by the concept of
primary control. Primary control of the power unit is described by the following
equation:
(5.1)
in which f∆ is the change in frequency in Hz, nomf is the nominal frequency (50
Hz), P∆ is the change in power in MW, nomP is the nominal power in MW and S.D
is the droop as %.
Selected reference power plants in Turkish interconnected system have an
obligation to give support to the system frequency. Each of selected power plants in
Turkey must support the primary frequency control due to their abilities. Those
contractual obligations are 10% of the nominal power for hydroelectric power plants
and 5% of the nominal power for coal and gas fired thermal power plants based on
UCTE regulations. Contractual obligation of the reference thermal power plant for
the primary frequency control reserve to be maintained is %5 of nominal power.
When units are scheduled only for primary control, they are operated at 100% of
nominal load and in case of a frequency deviation of ±200 mHz, they can take load
up to 105% of nominal and maintain this output. Each unit of the power plants
joining primary control will put in operation its reserve power, defined as primer
frequency reserve capacity in mandatory auxiliary services agreement, whenever the
%100. ×∆
=∆
×
nomnom f
f
P
PDS
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
65
frequency oscillates ±200 mHz from nominal value. This reserve power must be
given to the interconnected system in 30 seconds. When frequency oscillates ±200
mHz at nominal frequency 50 Hz, ideal turboset control response will be as shown in
figure 5.1 and figure 5.2 respectively. On those graphics, we assume that generators
do not be connected to real grid.
Figure 5.1 Power responses in frequency deviations -200 mHz
Figure 5.2 Power responses in frequency deviations +200 mHz
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
66
setP is the setting power and P∆ is reserve power for both negative and positive
power.
The ideal power-frequency graphic can be shown in figure 5.3 for both -200
mHz and +200 mHz.
Figure 5.3 Power-frequency curve at ±200 mHz
of is the dead band, Q is primary frequency control reserve, Gf∆ is sensed frequency
after dead band and f∆ is frequency deviation of the system.
5.3. Proposed Configuration of Turbine Control System
Steam turbine in reference thermal plant is five mass with separate casings-
arranged on one rotor with the generator. The steam turbine generator set is of the
single reheat condensing type. The turbine set consists of one HP, one IP and two
LP.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
67
In proposed turboset model, power must be increased or decreased up to 5% of
nominal power in 30-50 seconds due to UCTE primary control whenever frequency
deviates ±200 mHz. A generator control system is mainly consisting of two parts
called turbine governor control and excitation control as mentioned in chapter 4.2. In
the scope of this thesis, governor control part is especially investigated because
primary control is directly proportional to turbine governor control block. Since
excitation control affects voltage control, available simulink block of MATLAB will
be used.
The proposed turboset control is built in MATLAB / Simulink shown in
figure 5.4. Basically, proposed model can be observed as two parts steam turbine
governor control, excitation system control blocks. Generator is controlled by those
two parts and generator output bus is connected to an infinite network through 3
phase 21 kV/400 kV voltage transformer (733 MVA / 50 Hz).
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
68
Figure 5.4 MATLAB/Simulink model of turboset
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
69
5.3.1. Synchronous Machine (Generator)
The shaft models a five-mass system, which is coupled to the mass in the
synchronous machine model. In parameters of the proposed controller, the machine's
mass, generator is labeled mass #1. The mass in the steam turbine and governor
block, which is closest to the machine's mass, is mass #2 (LP2 turbine), and
respectively mass #3 (LP1 turbine) and mass #4 (IP turbine) while the mass farthest
from the machine is mass #5 (HP turbine). The model takes into account the
dynamics of the stator, field, and damper windings. The equivalent circuit of the
model is represented in the rotor reference frame (q-d frame). All rotor parameters
and electrical quantities are viewed from the stator. They are identified by primed
variables. The subscripts used are defined as follows:
d,q: d and q axis quantity,
R,s: Rotor and stator quantity,
l,m: Leakage and magnetizing inductance,
f,k: Field and damper winding quantity,
Fundamental parameters in synchronous machine (generator) are shown in
figure 5.5.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
70
Figure 5.5 Parameters of generator
Mechanical input allows you to select either the torque applied to the shaft or
the rotor speed as the simulink signal applied to the block's input. Mechanical power
Pm specifies a mechanical power input, in pu. The machine speed is determined by
inertia constant H and by the difference between the mechanical torque Tm, resulting
from the applied mechanical power Pm. The sign convention for the mechanical
power is the following: when the speed is positive, a positive mechanical power
signal indicates generator mode.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
71
Specified rotor types can be salient-pole or round (cylindrical). This choice
affects the number of rotor circuits in the q-axis (damper windings). Proposed model
due to reference power plant is round.
Nominal power, voltage, frequency, and field current are chosen due to
reference thermal power plant parameters. The total three-phase apparent power Pn
(VA), rms line-to-line voltage Vn (V), frequency fn (Hz).
733=nP MVA,
21)( =rmsn VV kV,
50=nf Hz
Damper reactances are like below;
Synchronous reactance of direct axis, 13.2)( =puXd
Transient synchronous reactance of direct axis, 26.0)(' =puXd
Sub-transient synchronous reactance of direct axis, 18.0)('' =puXd
Synchronous reactance of quadrature axis, 02.2)( =puXq
Transient synchronous reactance of quadrature axis, 74.0)(' =puXq
Sub-transient synchronous reactance of quadrature axis, 18.0)('' =puXq
Stator leakage reactance, 156.0)( =puXl
D-axis and q-axis time constants are defined. These values must be consistent with
choices made on the two previous lines.
d-axis no load transient time constant, 51.5' =Tdo
d-axis no load sub-transient time constant, 04.0'' =Tdo
q-axis no load transient time constant, 93.1' =Tqo
q-axis no load sub-transient time constant, 26.0'' =Tqo
Inertia Constant (whole shaft including turbine), 6)/( =MVAMWsH
Inputs of generators are “Pm”, “Vf” while output of it is “m” as mentioned below.
“Pm” is the first simulink input is the mechanical power at the machine's
shaft. In generating mode, this input can be a positive constant or function or the
output of a prime mover block.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
72
“Vf” is the second simulink input of the block is the field voltage. This
voltage can be supplied by a voltage regulator in generator mode.
The “m” is the simulink output of the block is a vector containing twenty two
signals. We can use any parameter that we want. Rotor speed value is only used as
feedback to control system in this model.
When synchronous machine blocks are used in discrete systems, a small
parasitic resistive load should be better, connected at the machine terminals, in order
to avoid numerical oscillations. Large sample times require larger loads. The
minimum resistive load is proportional to the sample time. As a rule of thumb, with a
25 µs time step on a 50 Hz system, the minimum load is approximately 2.5% of the
machine nominal power. For example, a 733 MVA synchronous machine in a power
system discretized with a 50 µs sample time requires approximately 5% of resistive
load about 36 MW. If the sample time is reduced to 20 µs, a resistive load of 15 MW
should be sufficient as shown in figure 5.4. That load is used between generator and
transformer.
5.3.2. Turbine-Governor Control System
The main consideration for control system of a steam turboset due to active
power is steam turbine-governor control. The dynamics of speed governing system,
steam turbine, and multimass shaft are shown in figure 5.6. The steam turbine and
governor block implements a complete tandem-compound steam prime mover,
including a speed governing system, a five-stage steam turbine, and a shaft with up
to five masses.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
73
Figure 5.6 Turbine-governor block
As seen on figure 5.6, turbine-governor blocks consists of other parts as
defined below.
The speed governing system, which is part of turbine-governor block,
consists of a proportional regulator, a speed relay, and a servomotor controlling the
gate opening as shown in figure 5.7.
Figure 5.7 Speed governor block
Rp is speed droop and be set 4%. Dead zone is also mentioned in chapter
4.2.3.4 and be set to 0mHz in proposed model because it is reduced to 0mHz in
reference thermal power plant during real test. Normally, dead band can be ranged
between 0 mHz and 50 mHz permitted by UCTE. At the operating condition of a
power plant, dead band should be higher value for power plant dynamics. Gain of
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
74
generator is set to 1. Since flow and pressure of steam cannot be modeled in this
thesis, it is accepted to have no effect on system by adjusting 0.
Governor part is electro-hydraulic. The necessary parameters in governor
control are speed relay, servomotor time constant, servomotor speed limit and
servomotor position. Design values of them are 0.01 second for speed relay, 0.15
second for servomotor time constant, -0.1 and 0.1 pu/s for gate opening limits, 0 pu
for minimum gate opening, and 1 pu for maximum gate opening.
The steam turbine has five stages, each modeled by a first-order transfer
function. The first stage represents the steam chest while the three other stages
represent reheater and crossover piping. Since the boiler simulation is out of this
thesis, boiler pressure is assumed a constant value at 1.0 pu. Fractions F2 to F5 are
used to distribute the turbine power to the various shaft stages shown in figure 5.8.
Each turbine contribution is different to generated power. Those values are as
follows:
A generated power consists of 26% power (F5) by HP turbine, 38% power by
IP (F4), 18% power (F3) by LP1, and 18% power (F2) by LP2. Also each turbine has
time constant. Those time constants show that the duration of steam produced by
superheater and reheater. Typical values are taken from reference power plant; 30 sec
for HP, 50 sec for IP, 0.01 sec for LP1, 0.01 sec for LP2 respectively.
Figure 5.8 Turbine power fractions and time constants of turbine parts
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
75
Normally, actual speed coming from generator is used as rotor frequency
sensed by the system. In simulated control system, a simulated frequency must be
applied as externally. Speed information comes from generator but system senses
simulated frequency as seen in figure 5.9. When frequency is simulated, firstly step
time is adjusted to a value we want. Then, an initial and a final value are entered as
parameters of simulated frequency block. Since pu is used, data conversion can be
calculated as follows
for +200 mHz; puHz
Hz004.1
50
2.50= (5.2)
for -200 mHz; puHz
Hz996.0
50
8.49= (5.3)
Figure 5.9 Simulated frequency
5.3.3. Excitation Control Block
Excitation system regulates its terminal voltage in generating mode for
synchronous machine. Because this control block does not directly affect load-
frequency relationship, this control block is not modeled as detailed in this thesis.
Excitation block built for generator is taken from simulink library. Used excitation
block in proposed model can be seen in figure 5.10.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
76
Figure 5.10 Excitation control description
Vref is the desired value, in pu, of the stator terminal voltage. Vd is the
component, in pu, of the terminal voltage. Vq component, in pu, of the terminal
voltage. Vstab is connected to a power system stabilizer to provide additional
stabilization of power system oscillations, we connected a ground. Vf is the output
and it is field voltage, in pu, for the generator.
The excitation system block is a simulink system implementing a DC exciter
described in [1], without the exciter's saturation function in figure 5.11. The basic
elements that form the excitation system block are the voltage regulator and the
exciter. It is shown in figure 5.11
Figure 5.11 Excitation control block
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
77
The exciter is represented by the following transfer function between the
exciter voltage Vfd and regulator’s output ef
eef
fd
sTKe
V
+=
1 (5.4)
Exciter is the gain Ke and time constant Te, in seconds (s), of the first-order
system representing the exciter. The parameters of excitation system are shown in
figure 5.12.
Figure 5.12 Parameters of excitation
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
78
Low-pass filter time constant is the time constant Tr, in seconds (s), of the
first-order system that represents the stator terminal voltage transducer.
Regulator gain and time constant are the gain Ka and time constant Ta, in
seconds (s), of the first-order system representing the main regulator.
Transient gain reduction is the time constants Tb, in seconds (s), and Tc, in
seconds (s), of the first-order system representing a lead-lag compensator.
Damping filter gain and time constant are the gain Kf and time constant Tf, in
seconds (s), of the first-order system representing a derivative feedback.
Regulator output limits and gain are limits Efmin and Efmax are imposed on
the output of the voltage regulator. The upper limit can be constant and equal to
Efmax, or variable and equal to the rectified stator terminal voltage Vt times a
proportional gain Kp.
5.4. Field Test Procedure
In reference thermal power plant, the tests carried out on the load-frequency
control system shall be realized according to the UCTE test procedure, by directly
simulating the frequency measurement signal of the unit control system. Method to
be applied is given below:
Figure 5.13 Test mode
The power plant has built-in frequency simulator therefore there is no need to
connect any signal generator. An artificial input signal ±200 mHz shall be added to
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
79
the turbine governor input signal, corresponding to the rated frequency 50 Hz. The
dead-band of the governor shall be adjusted to “0” prior to the tests.
At the beginning of the test, frequency is disconnected from grid and adjusted
50 Hz via simadyn, a special fast controller. Then system was reached to nominal
power 660 MW by system operator and frequency was manually decreased 49.8 Hz
for case 1 by simadyn software. After frequency stayed in 49.8 Hz during 15
minutes, it was adjusted to 50 Hz again and power was reached to nominal frequency
660 MW. For case 2, frequency was increased to 50.2 Hz by simadyn. Tests for each
cases continued 15 minutes.
The power plant has measurement recording for turbine speed measurement,
voltage measurement by voltage transformer, current measurement by current
transformer. Turbine speed (Hz) and turbine output power (MW) shall be recorded.
The measurements shall be recorded as 10 samples per second. All test results are
taken into computer environment via Digsilent software.
5.5. Simulation and Field Test Results
A speed /load-control system is capable of controlling and regulating the
speed of the turbine in conformity with the performance characteristics hereinafter
specified. The speed/load-control system should include means by which the steady-
state speed regulation is adjusted to values within the limits herein specified.
In order to show whether reference thermal power plant fulfills UCTE
requests due to primary control, proposed turboset control mechanism, taken values
from reference power plant, is simulated for the following case studies. Also, real
test results will be presented and compared with simulation results.
Case (1) -200 mHz frequency deviation:
Two conditions for this case must be fulfilled during tests as below:
a. taking reserve power within 30 seconds
b. hold its power during 15 minutes:
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
80
In simulation, system is operated up to 660 MW nominal power at 50 Hz.
Frequency is decreased 49.8 Hz from 50 Hz. Frequency in a short period is shown in
figure 5.14 for case 1.a and all simulation is represented in figure 5.15 for case 1.b.
Power response to frequency is shown in figure 5.16 for case 1.a and 5.17 for case
1.b. Power of proposed model is operated 660 MW at 50 Hz and frequency is
suddenly deviated by -200 mHz at 30th seconds shown in figure 5.14 and 5.15.
Figure 5.14 -200 mHz frequency deviation for case 1.a during simulation
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
81
Figure 5.15 -200 mHz frequency deviation for case 1.b during simulation
Figure 5.16 Unit response to -200 mHz frequency deviation for case 1.a during simulation
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
82
Figure 5.17 Unit response to -200 mHz frequency deviation for case 1.b during
simulation
At the beginning of field tests, reference power plant is operated at 50 Hz
simulated frequency and frequency was suddenly deviated and then steam turbine
shows response to deviations. The figure 5.19 shows simulated frequency for 15
minutes and figure 5.18 shows a short period of figure 5.19. Power response to
frequency is presented in figure 5.20 and 5.21. The primary control test results are
presented in figure 5.20 for a defined period. Figure 5.21 starts at the end of figure
5.20 in order to observe during 15 minutes.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
83
t/s140 150 160 170 180 190 200 210 220 230 240 250 260 270 280
Frequency/Hz
49,7
49,8
49,9
50,0
50,1
50,2
Figure 5.18 -200 mHz frequency deviation for case 1.a during field test
t/s100 200 300 400 500 600 700 800 900 1000
Frequency/Hz
49,7
49,8
49,9
50,0
50,1
50,2
Figure 5.19 -200 mHz frequency deviation for case 1.b during field test
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
84
Figure 5.20 Unit response to -200 mHz frequency deviation for case 1.a during field
test
Figure 5.21 Unit response to -200 mHz frequency deviation for case 1.b during field test
Case 1.a
Reserve primary control according to UCTE policy for proposed thermal
power plant must be;
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
85
MWMW 33%5660 =× (5.5)
In simulation, system starts to take reserve power up to 34 MW in first 30
seconds shown in figure 5.16 when frequency is deviated. This is in the acceptable
range due to UCTE. As it can be seen on figure 5.16, system continues to take power
by first 40 seconds from its starting. It takes about 43 MW ( )MW660%7 ×≈ in 40
seconds and stay with 700 MW. Because frequency is still 49.8 Hz, system tries
frequency to reach to 50 Hz by increasing its power 10 MW more so this is better for
Turkish interconnected system.
As it can be seen on figure 5.20, for the 200 mHz frequency deviation, unit
responds with 25 MW ( )MW660%4 ×≈ and reaches +45 MW respond within 90
seconds in field test.
Case 1.b
After frequency decreases, reserve power must be taken in 30 seconds and
stay there during 15 minutes according to UCTE load frequency regulation.
After generator takes reserve power in case of -200 mHz frequency deviation
in simulation, generator stays there during 15 minutes. As it can be seen on figure
5.17, power response of system is never less than 40 MW ( )MW660%6 ×≈ .
In field test, unit responds with 45 MW ( )MW660%7 ×≈ for the first 4
minutes and at the end of 15 minutes the response is never less than +30
MW ( )MW660%5 ×≈ shown in figure 5.21.
Case (2) +200 mHz frequency deviation:
Two conditions for this case must be fulfilled as below:
a. throwing reserve power within 30 seconds
b. hold its power during 15 minutes:
In simulation, system is operated up to 660 MW nominal power at 50 Hz.
Frequency is increased 50.2 Hz from 50 Hz. Frequency in a short period is shown in
figure 5.22 for case 2.a and all simulation is represented in figure 5.23 for case 2.b.
Power response to frequency is shown in figure 5.24 for case 2.a and 5.25 for case
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
86
2.b. Power of proposed model is operated up to 660 MW at 50 Hz and frequency is
suddenly deviated by +200 mHz at 30th seconds shown in figure 5.22 and 5.23.
Figure 5.22 +200 mHz frequency deviation for case 2.a during simulation
Figure 5.23 +200 mHz frequency deviation for case 2.b during simulation
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
87
Figure 5.24 Unit response to +200 mHz frequency deviation for case 2.a during
simulation
Figure 5.25 Unit response to +200 mHz frequency deviation for case 2.b during
simulation
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
88
During field test, reference power plant is operated at 50 Hz simulated
frequency and frequency was suddenly deviated and then steam turbine shows
response to deviations. The figure 5.27 shows simulated frequency for 15 minutes
and figure 5.26 shows a short period of figure 5.27. Power response to frequency is
presented in figure 5.28 and 5.29. The primary control test results are presented in
figure 5.28 for a defined period. Figure 5.28 starts at the end of figure 5.27 in order
to observe during 15 minutes.
t/s1820 1830 1840 1850 1860 1870 1880 1890 1900 1910 1920
Frequency/Hz
49,7
49,8
49,9
50,0
50,1
50,2
Figure 5.26 Frequency deviation +200 mHz at time 1830 seconds for case 2.a during field test
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
89
t/s1900 2000 2100 2200 2300 2400 2500 2600
Frequency/Hz
49,7
49,8
49,9
50,0
50,1
50,2
Figure 5.27 Frequency deviation +200 mHz for 15 minutes at time 1830 seconds for
case 2.b during field test
Figure 5.28 Test result of unit response +200 mHz frequency deviation at full load
for case 2.a during field test
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
90
Figure 5.29 Test result of unit response +200 mHz frequency deviation at full load
for case 2.b during field test
Case 2.a
Reserve primary control according to UCTE policy for proposed thermal
power plant must be ( )MWMW 33%5660 =× .
In simulation, unit responds with -34 MW in first 30 seconds shown in figure
5.24 when frequency is deviated. This is in the acceptable range due to UCTE. As it
can be seen on figure 5.24, unit responds with -40 MW ( )MW660%6 ×≈ in 40
seconds and stay with 618 MW. Because frequency is still 50.2 Hz, system tries
frequency to reach to 50 Hz by decreasing its power 8 MW more so this is better for
Turkish interconnected system.
As it can be seen on the figure 5.28 due to field test results, unit responds
with -45 MW ( )MW660%7 ×≈ to +200 mHz frequency deviation for the first 30
seconds, but with the pressure increase, gives back ~15 MW of its initial response
duration of 90 seconds transiently.
Case 2.b
After frequency increases, reserve power must be given in 30 seconds and
stay there during 15 minutes according to UCTE load frequency regulation.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
91
After generator gives reserve power in case of +200 mHz frequency
deviation, generator stays there during 15 minutes. As it can be seen on figure 5.25,
power response of system is never less than -40 MW ( )MW660%6 ×≈ .
At the end of 15 minutes in the field test, response is never below -30
MW ( )MW660%5 ×≈ .
5.6. Comparison of Simulation and Test Results
Results of proposed turboset model and results of the test are seen above
figures. They are different each other because our proposed model cannot include
mechanical loss, operating conditions of equipments and some mechanical parts.
Also, ideal curves for test are represented in figure 5.1 and figure 5.2. Results can be
compared as follows.
When frequency deviations -200 mHz:
Ideal curve must be like figure 5.1. System must take its reserve power within
30 seconds.
In the first 30 seconds, unit responds with ~34MW ( )MW660%5 ×≈ and
reaches to +43 MW ( )MW660%7 ×≈ within 40 seconds during the simulation.
During the test unit responds with ~25 MW ( )MW660%4 ×≈ and reaches +45 MW
respond within 90 seconds.
In simulation, as it can be seen on figure 5.15, it takes about 40 MW and stay
within 700 MW. When we can not model boiler, no pressure fluctuations or any
peak, falling and rising could not be seen in the proposed model.
In the test, as it can be seen on figure 5.24, for the 200 mHz frequency
deviation, unit responds with 45 MW ( )MW660%7 ×≈ for the first 4 minutes, and at
the end of 15 minutes the response is never less than +30 MW ( )MW660%5 ×≈
shown in figure 5.25. The reason of this fluctuation is fast pressure drop and it is
normal to be not seen in the simulation because boiler could not be modeled in the
scope of this.
5.SIMULINK MODELING OF TURBOSET S. Olcay BERĐKOL
92
When frequency deviations +200 mHz:
Ideal curve must be like figure 5.2. System must throw out its reserve power
within 30 seconds.
For the first 30 seconds, unit responds with ~-34 MW ( )MW660%5 ×≈ during
both test and simulation. For the duration of 90 seconds, the response goes back to -
30 MW ( )MW660%5 ×≈ transiently in test but power is kept in the same level after
first 30 seconds in simulation.
In simulation, as it can be seen on figure 5.19, power responds about -40
MW ( )MW660%6 ×≈ in 40 seconds and stay within 618 MW. When we can not
model boiler, no pressure fluctuations or any peak, falling and rising could not be
seen in the proposed model.
As it can be seen on the figure 5.28, unit responds with -45 MW (~7 % *660
MW) to +200 mHz frequency deviation, but with the pressure increase, gives back
~15 MW of its initial response transiently. At the end of 15 minutes, response is
never below -30 MW (~5 %* 660 MW) shown in figure 5.29. The reason of this
fluctuation is fast pressure changing and it is normal to be not seen in the simulation
because boiler could not be modeled.
As a result of the tests that were carried out reference thermal power plant, it
can be stated that the obligatory primary frequency control participation is realized
with:
%4 turbine control droop value without any limitation on the turbine,
~40 MW limited boiler control system response
Although the transient response is higher, the contractual obligation of 5%
reserve is provided in 30-50 seconds and maintained for the duration of 15 minutes
in both real test results and simulation results.
6. CONCLUSIONS S. Olcay BERĐKOL
93
6. CO�CLUSIO�S
In this thesis, primary load-frequency control related with UCTE policies is
investigated.
Load frequency control (LFC) investigated in this study has recently come
into question in operation of interconnected power networks. Frequency is a sensitive
parameter which affects the system operation so it must be controlled certainly.
Therefore power utilities consider the frequency and active power balance
throughout their networks to sustain the interconnection so that load-frequency
control is of importance in both electric power system design and operation. The
loading in a power system is never constant. To ensure the quality of the power
supply is necessary to design a load-frequency control system which deals with the
control of loading of the generator depending on the frequency.
The literature research was carried out in order to explain and design load
frequency control. The main desire, expected from LFC, was explained in chapter 3
and chapter 4. UCTE regulations including load frequency policy were clarified in
chapter 3 as detailed. A load frequency controller for the thermal power plant was
designed in chapter 5. Primary control response tests of reference thermal power
plant were carried and also results of the tests were given and then compared with
results of simulation in chapter 5.
The main consideration of the proposed turbine model was to investigate
primary control support of reference power plant needed to meet UCTE requirements
to Turkish power network. The proposed turbine control system for thermal power
plant was connected to interconnected network through 3 phase 21/400 kV step-up
voltage transformer. The turboset is controlled by the turbine governor, which
consists of a power and a speed controller, and the voltage regulator. Turbine
governor control block was especially designed because this thesis is directly
interested in primary control. By means of the governor droop, it is able to perform a
frequency response contribution to slow changes in the grid frequency. Governing
system is an important control system in the power plant as it regulates the turbine
speed, power and participates in the grid frequency regulation. For grid system
6. CONCLUSIONS S. Olcay BERĐKOL
94
operation, it is required that the power generated is continuously matched to demand
for the power plant. If power generation and power demand in the grid system are the
same under undisturbed generation conditions, the system frequency is exactly equal
to the rated frequency and we can say that grid system is in the balance.
The proposed turboset model consisted of five mass. Each turbine had
different torque fractions in generation of electricity. Their contributions in
producing power were also considered while the turboset controller was designing.
The studies of two cases due to UCTE tests had been realized to verify the
operation and performance of the designed system in MATLAB/Simulink program.
When grid frequency deviations +200 mHz defined in UCTE operation handbook, it
means that the power generation is greater than power demand, so generators
connected to the grid system speed up. If the power generation is less than power
demand or grid frequency deviations -200 mHz defined in UCTE policy, generators
connected to the grid system slow down.
While proposed turboset system was simulated, system operated up to 660
MW. As far as frequency was artificially deviated -200 mHz at 50 Hz by a signal
generator proposed turboset took its reserve power about 34 MW in 30 seconds
which is in the acceptable range due to UCTE policy. System kept its power up to
700 MW during 15 minutes.
System was reached up to 660 MW. Then frequency was suddenly fluctuated
+200 mHz at 50 Hz by signal generator, proposed turboset decreased its power -34
MW for the first 30 seconds and -40 MW in 40 seconds which is in the acceptable
range due to UCTE policy. System kept its power level at 618MW during 15
minutes.
The synchronization of Turkish grid to UCTE through 380 kV network will
enlarge the capacity of UCTE system by 40.000 MW roughly when the project is
realized. Preliminary works for this interconnection have been carried out by Turkish
utility according to UCTE regulations. Primary frequency control performance test of
the power plants planned for primary control is one of those works which were
carried out at ISKEN power plant.
6. CONCLUSIONS S. Olcay BERĐKOL
95
In order to give reaction to LFC, two basic control methods are used in
thermal power plants called speed control (SC) and power control (PC). SC is used
for start-up, in disturbance states and in island operation. PC mode is used for
primary frequency control while the units are supplying power to 380 kV Turkish
network. Therefore UCTE tests were carried out in PC mode.
While tests were applied on reference plant, the frequency was disconnected
from the grid. The frequency measurement signal of the unit control system was
directly simulated by signal generator. An artificial input signal ±200 mHz shall be
added to the turbine governor input signal, corresponding to the rated frequency 50
Hz. During the test and simulation, speed droop of turbine governor parameter is set
4% and dead band is adjusted to 0 mHz. All test results were taken into computer
environment via Digsilent software.
During test, system operates up to 660 MW. Frequency was deviated -200
mHz, system took 30 MW of its power reserve in 30 seconds. However generator
had continued to take power up to 45MW within 100 seconds, with the pressure
decreases. Then system had decreased its power and held in 700 MW during 15
minutes.
When frequency was deviated +200 mHz, system decreased its rated power
about 45 MW in 35 seconds which is in the acceptable range due to UCTE policy.
Then, generator took a little bit power reserve about 10MW, with the pressure
increase, and kept its power level at 620MW during 15 minutes.
As a result of the tests that were carried to the reference thermal power plant,
it can be stated that the obligatory primary frequency control participation is realized
with %4 turbine control droop value without any limitation on the turbine and ~40
MW limited boiler control system response
Although the transient response is higher, the primary support obligation of
5% reserve is provided in 30-50 seconds and maintained for the duration of 15
minutes.
In the tests, when frequency initiated to deviate -200 or +200 mHz at 50 Hz,
the power of generator fast increased or decreased. Peak points were seen on the
graphics and after a few seconds system protected stabilization of its output power
6. CONCLUSIONS S. Olcay BERĐKOL
96
during the test. Those peaks occurred because pressure was changing suddenly. It is
normal that peaks cannot be seen in simulation results because boiler cannot be
modeled in the scope of this thesis.
Test and simulation results showed that the load-frequency control ability of
reference thermal power plant was enough in order to respond frequency fluctuations
on the interconnected system. In this thesis, observed simulation results and test
results of reference thermal power plant were closely matched with each other and
cover load frequency criteria defined UCTE policies.
97
REFERE�CES
Babcock & Wilcox Co., 2005. Steam: Its Generation and Use 41st edition
BENGIAMIN, N.N., and CHAN, W.C., 1978. Multilevel load-frequency control of
interconnected power systems, IEE Proc. C, Gen., Trans.& Distrrb., 125, pp.
521-526
BLOCH, H., P., 1995. A Practical Guide To Steam Turbine Technology. McGraw-
Hill Professional, New York
CHANG-CHIEN, L.R., HOONCHAREON N.B., ONG, C.M., and KRAMER, R.A.,
May 2003. Estimation of β for Adaptive Frequency Bias Setting in Load
Frequency Control, IEEE Trans. Power Syst., Vol. 18, No. 2, pp. 904–911
Dynamic System Simulation for Matlab, Using Simulink Version 2, 1998. The
Mathworks Inc.
ELLIOTT, T.C., CHEN, K., SWANEKAMP, R., 1997. Standard Handbook of
Power Plant Engineering, 2nd edition. McGraw-Hill Professional Publishing,
New York, pg 2.33-2.43
INGLESON, J. W., and ELLIS, D. M., 2005. Tracking the eastern interconnection
frequency governing characteristic. IEEE Power Eng. Soc.General Meeting,
pp. 2484–2489
INOUE, T., and AMANO, H., 2006. A Thermal Power Plant Model for Dynamic
Simulation of Load Frequency Control. IEEE Power Systems Conference and
Exposition, 6: 1442-1447
KAKAÇ, S., 1991. Boilers, Evaparators, and Condensers. John Wiley & Sons,
Canada, pp. 297
KEHLHOFER, R., WARNER, J., NIELSEN, H., and BACHMANN, R., 1999.
Combined Cycle Gas & Steam Turbine Power Plants. nd2 edition PennWell,
Oklahoma.
KUNDUR, P., 1994. Power System Stability and Control. McGraw- Hill, New York,
1147 pg.
KUTZNER, R., January 1999. Siemens AG, Erlangen, pp. 3-5
98
LIPTẢK, B., G., 2006. Instrument Engineer’s Handbook: Process Control and
Optimization. th4 edition CRC Press, New York, pp. 2141
REBOURS, Y.G., KIRSCHEN, D.S., and TROTIGNON, M., February 2007. A
Survey of Frequency and Voltage Control Ancillary Services- Part1:
Technical Features, IEEE Transactions on Power Systems., Vol. 22, No. 1,
pp. 350-352
KENT, R., T., 1936. Kents Mechanical Engineers Handbook. Eleventh Edition John
Wiley & Sons, New York.
SALAMI, A., JADID, S., and RAMEZANI, N., November 2006. The Effect of Load
Frequency Controller on Load Pickup During Restoration. First international
power and energy conference, Malaysia.
TROTIGNON, M., Dec. 1997. Load Frequency Control, Operational Studies for the
Interconnection of the Electrical Power Systems of the EIJST Countries,
EIJST Workshop, EDF
UCTE Introduction to the Operation Handbook, 2004.
UCTE Operation Handbook Policy1, July 2004. Load-Frequency Control and
Performance Available: http://www.ucte.org/_library/ohb/policy1_v22.pdf
UCTE Operation Handbook Appendix1, June 2004. Load-Frequency Control and
Performance
UCTE Operation Handbook Policy2, July 2004. Scheduling and Accounting
Available: http://www.ucte.org/_library/ohb/policy2_v22.pdf
UCTE Operation Handbook Policy3, July 2004. Operational Security Available:
http://www.ucte.org/_library/ohb/policy3_v13.pdf
UCTE Operation Handbook Policy4, May 2006. Co-ordinated Operational Planning
Available:http://www.ucte.org/_library/ohb/policy4_ v2.0_03.05.2006.pdf
UCTE Operation Handbook Policy5, May 2006. Emergency Procedures Available:
http://www.ucte.org/_library/ohb/policy5_ v1.0_03.05.2006.pdf
WANG, Y., ZHOU, R., and WEN, C., 1993. Robust load-frequency controller
design for power systems. IEE PROCEEDINGS-C. Vol 140. No.1 : 11-16
WOODRUFF, E., B., LAMMERS, H., B., LAMMERS, T., F., 2004. Steam Plant
Operation. th8 edition McGraw-Hill Professional, New York, 850 pp.
99
BIOGRAPHY
I was born in Adana, Turkey in 1982. I completed the high school education
in Adana. I received the B.S degree in Electrical and Electronics Engineering from
Çukurova University, Adana, Turkey in 2004. After completion my B.S. training, I
have started to work in EKĐNCĐLER steel and iron industry as electrical maintenance
engineer from september 2005 to november 2006. I have been studying MSc degree
in the department of Electrical and Electronics Engineering at Çukurova University
and also have been working in ISKEN thermal power plant as instrumentation and
control maintenance engineer since 2006.