    United Crane

    CompanyTeam United Project

  • 8/13/2019 United Crane Power Point

    2/19

    Team United

  • 8/13/2019 United Crane Power Point

    3/19

  • 8/13/2019 United Crane Power Point

    4/19

    Ariel Platform Cranes

  • 8/13/2019 United Crane Power Point

    5/19

    Team United Mission

    Our mission is to conduct a thoroughinvestigation of the companys twocrane accidents. Clear writtenprocedures will be implemented andmonitored. This will ensure a safeand profitable future for the

    company.

  • 8/13/2019 United Crane Power Point

    6/19

    Team United Goals

    Implement a thorough investigation of theaccidents in full cooperation with OSHA.

    Make necessary adjustments to

    procedures or implement new proceduresthat will eliminate the root cause of theaccidents.

    Present to OSHA, insurers, and customersproof that the root cause of the accidentshas been eliminated.

  • 8/13/2019 United Crane Power Point

    7/19

    Team United Goals

    Address customer, employee, and publicrelations areas to ensure that clearwritten training procedures will be

    evaluated, implemented, and monitored.Will refer any legal issues to the

    companys lawyer of choice.

    Will plan and manage project within the

    Team United unit.

  • 8/13/2019 United Crane Power Point

    8/19

    Operating Principles

    Team United will treat each other withrespect.

    Every member will give their full cooperationand have open lines of communication.

    The team will listen to all ideas andsuggestions without interruption.

    All members are responsible for completingassigned tasks on time.

    Maintain a positive attitude toward reachingthe team goals.

  • 8/13/2019 United Crane Power Point

    9/19

    Constraints

    Customer Relations Assure our present andfuture customers that safety, training andquality are very important to our company.

    Employee Relations Getting employees tocommit to changes, and sustain the changes.

    Public Relations Letting the public knowthat we are committed to preventing futureincidents.

    Legal Dealing with lawsuits from employeesand fines from government.

  • 8/13/2019 United Crane Power Point

    10/19

    Barriers

    Support Cooperation from all companyowners.

    Resources Data and participation

    Time Insufficient for investigation andplanning

    Knowledge Outside resources neededfor investigation and legal issues.

    Money Unable to stay within budget

  • 8/13/2019 United Crane Power Point

    11/19

    Measurement

    Feedback from company management

    Feedback from company employeesSurvey from customers

    Team Evaluation using a checklist andranking system

  • 8/13/2019 United Crane Power Point

    12/19

    Plan and Time Line

    Gantt Chart Tasks charted to keep theteam on schedule to reach goal

    Regular meetings to discuss progress and

    identify problems

  • 8/13/2019 United Crane Power Point

    13/19

    Investigation

    We have hired an independent firm toinvestigate the incident for the rootcauses of the accidents.

    FindingsThe crate was improperly erected. Bolts thatholt the turret to the vertical base were nottorqued to the proper specifications.Operator failed to do a daily check onequipment.Crane was over stressed lifting a load thatwas to heavy.

  • 8/13/2019 United Crane Power Point

    14/19

    Time Line

  • 8/13/2019 United Crane Power Point

    15/19

    Training

    We have contacted a crane trainingcompany. CraneTech is going to visit outcrane sites.CraneTech is going to give instruction to all

    operators and all operators will be certified under

    NCCCO (National Commission for the Certificationof Crane Operators) regardless if they already havetheir certificate.They will provide training to our operators and

    riggers.They will be visiting all of our active sites and

    provide site specific training.CraneTech is also creating a safety check list. This

    is a daily operator checklist to be competed daily.Also to be signed off by the site manager.

  • 8/13/2019 United Crane Power Point

    16/19

    Training Budget

    Initially, Training is going to cost about 3thousand dollars per site.The checklist is going to cost about 500 dollarsfor its creation.

  • 8/13/2019 United Crane Power Point

    17/19

    Project Budget

    0 20000 40000

    Investigation30,000

    CustomerRelation 1,425

    Public Relations5,000

    Legal 8,000

    Training 9,500

    Tasks Total 53,925

    Tasks Total53,925

  • 8/13/2019 United Crane Power Point

    18/19

    Executive Summary

    Our company was able to incorporate investigation,training, public/customer relations, legal language, andemployee relations into our six week solution. We believethat the implementation of our plan will be extremely

    effective and will eventually benefit our company.

    We were able to overcome our organizational barriers andwe will continue to focus on the future of ourimplementation of our plan.

    Our company has been able to maintain our operatingprinciples throughout our problem solving journey and weplan to keep our operating principles one of our mainpriorities throughout our implementation of our plan.

  • 8/13/2019 United Crane Power Point

    19/19

    Executive Summary (Cont.)

    Our independent investigation firm reachedtheir conclusion on the primary causes of our

    crane accidents.

    We immediately started planning and decidedto have Cranetech visit our crane sites.Instruction will be given to all operatorswithin our company from this point forward.