    NTPC/VINDHYACHAL

    UNIT OVERHAULS

    6X210 MW & 4X500 MW UNITSOF

    VINDHYACHAL SUPER THERMAL POWER PROJECT,

    NATIOANAL THERMAL POWER CORPORATION LTD.,P.O. : VINDHYANAGAR, DISTT.: SIDHI (M.P.), PIN:486885

  • 7/31/2019 Unit Overhaul

    2/23

    NTPC/VINDHYACHAL

    UNIT OVERHAULS PHILOSOPHY

    210 MW ( LMW ) UNITS

    TYPE OF OVERHAUL MAIN AREAS IDENTIFIED PERIOD OF FREQUENCY

    FOR OVERHAUL OVERHAUL

    A BOILER & AUX. 20 DAYS EVERY YEAR

    TUR. BRGS. INSP.

    X BOILER & AUX. 21 DAYS EVERY 3rd YEAR

    GENERATOR ROTOR THREAD OUT

    D BOILER & AUX. 35 DAYS EVERY 6th YEAR

    ALL TURBINE CYLINDERS O/H

    GENERATOR ROTOR THREAD OUT

  • 7/31/2019 Unit Overhaul

    3/23

    NTPC/VINDHYACHALUNIT OVERHAULS PHILOSOPHY

    500 MW ( KWU ) UNITS

    TYPE OF OVERHAUL MAIN AREAS IDENTIFIED PERIOD OF FREQUENCY

    FOR OVERHAUL OVERHAUL

    E BOILER & AUX. 15 DAYS EVERY YEARTUR. BRGS. INSPECTION

    F BOILER & AUX. 25 DAYS EVERY 3rd YEAR

    LP TURBINE INSPECTION

    G BOILER & AUX. 35 DAYS EVERY 8th YEAR

    HPT / IPT O/H

    GENERATOR ROTOR THREAD OUT

  • 7/31/2019 Unit Overhaul

    4/23

    NTPC/VINDHYACHAL

    UNIT OVERHAULS - PHILOSOPHY

    210 MW ( LMZ ) UNITS

    TO CONTROL THE O&M COST FOLLOWING ARE THE ACTIONS:

    SEQUENCE OF O/H FOR THE STATION ARE SO ADJUSTEDTHAT NOT MORE THAN TWO MAJOR O/Hs (TYPE D)

    TAKEN UP IN A YEAR.

    WHENEVER TWO MAJOR O/H COMMENCES IN A STATION

    IN A YEAR, SITE TAKES DECISION, DEPENDING ON BOILERCONDITIONS, TO RESTRICT THE O/H DURATION OF BOILER

    SUITABLY TO 17 DAYS AND 15 DAYS FOR 200 MW AND 500

    MW UNITS RESPECTIVELY.

  • 7/31/2019 Unit Overhaul

    5/23

    NTPC/VINDHYACHAL

    OBJECTIVES OF UNIT OVERHAULS

    TO MAXIMIZE PLANT AVAILABILITY

    TO MINIMIZE MAINTENANCE COST THROUGH

    OPTIMIZATION OF RESOURCE UTILIZATION

    TO CREATE SAFETY IN WORK, EQUIPMENT AND

    ENVIRONMENT

  • 7/31/2019 Unit Overhaul

    6/23

    NTPC/VINDHYACHAL

    AIMS OF UNITS OVERHAUL

    TO IMPROVE AVAILABILITY OF EQUIPMENT & SYSTEM

    TO IMPROVE QUALITY & INSPECTION OF MAINTENANCE JOBS

    TO IMPROVE MONITORING & REPORTING OF O/H PROGRESS

    TO REDUCE OVERHAUL DURATION

    TO IMPROVE THE RE-COMMISSIONING INTERFACE

    TO PROVIDE A RECORD OF WORK CARRIED OUT

    TO MINIMIZE ISOLATION RESTRICTIONS

    TO REDUCE DUPLICATION OF ENGINEERING EFFORTS TO ENSURE STATUTORY REQUIREMENT OF BOILER LICENCE

  • 7/31/2019 Unit Overhaul

    7/23

    NTPC/VINDHYACHAL

    CATEGORIZATION OF

    UNIT OVERHAUL PROCESS

    PLANNING

    UNIT SHUT DOWN COOLING DOWN OF MACHINES

    DISMANTLING

    INSPECTION FOR CONDITION

    REPAIR & RECTIFICATION

    ASSEMBLY

    TESTING & INSPECTION

    REVIVAL OF EQUIPMENT & SYSTEM

    REVIVAL & RECOMMISSIONING OF UNIT

  • 7/31/2019 Unit Overhaul

    8/23

    NTPC/VINDHYACHAL

    IMPROVEMENT AREAS IDENTIFIED

    BARRING GEAR STOPPAGE TIME CONDENSER VACUUM GENERATOR AIR TIGHTNESS TEST TIME AIR INGRESS IN BOILER

    SCOPE OF WORK OF GENERATOR OVERHAUL ELECTRICAL TESTING TIME REVIVAL TIME OF UNIT AFTER UNIT OVERHAUL-HFO

    CONSUMPTION SCOPE OF IN SITU TESTS DURING UNIT OVERHAUL SCAFFOLDING ERECTION & DISMANTLING TIME PERCENTAGE AREA OF TUBES COVERED FOR D-METERING BOILER SAFETY VALVES SETTING TIME

    ULTIMATELY LEADING TO IMPROVEMENT IN PLANT

    AVAILABILITY, RELIABILITY & REDUCTION OF O&M COST

  • 7/31/2019 Unit Overhaul

    9/23

    NTPC/VINDHYACHAL

    PLANNING OF UNIT OVERHAULS

  • 7/31/2019 Unit Overhaul

    10/23

    NTPC/VINDHYACHAL

    CLASSIFICATION OF PLANNING ACTIVITIES

    PRE OVERHAUL ACTIVITIES

    DURING OVERHAUL ACTIVITIES

    POST OVERHAUL ACTIVITIES

  • 7/31/2019 Unit Overhaul

    11/23

    NTPC/VINDHYACHAL

    PRE OVERHAUL ACTIVITIES

    PLANNING & APPROVAL OF EIGHT YEAR ROLLING PLAN

    OF UNIT OVERHAULS

    PLANNING & APPROVAL OF NEXT FINANCIAL YEAR PLANFOR UNIT OVERHAULS

    PLANNING & APPROVAL OF MAJOR WORKS TO BE

    CARRIED OUT DURING UNIT OVERHAULS

    IDENTIFICATION, REQUIRED QUANTITY PROJECTIONAND REVIEW OF STATUS OF CONSUMABLES ( STOCK

    ITEMS) ON MONTHLY BASIS FOR UNIT OVERHAULS

  • 7/31/2019 Unit Overhaul

    12/23

    NTPC/VINDHYACHAL

    CONTD

    IDENTIFICATION OF CRITICAL MATERIALS REQUIRED

    FOR UNIT OVERHAULS AND REVIEW ON MONTHLY BASIS.

    PREOVERHAUL MEETING FOR REVIEW OF CONSTRAINTS& PREPAREDNESS INVOLVING ALL.

    PRE OVERHAUL CONDITION MONITORING REPORT

    PREOVERHAUL UNIT SURVEY

    UNIT OUTAGE ANALYSIS FROM LAST OVERHAUL

    FEED BACK OF UNIT FROM FIRST SYNCHRONIZATION

    REVIEW OF STATUS & COORDINATION OF WELDING

    SUPPLY, LIGHTING, LIFTS, HOISTS, CRANES ETC.

  • 7/31/2019 Unit Overhaul

    13/23

    NTPC/VINDHYACHAL

    CONTD

    PAST OVERHAULS AT A GLANCE (HISTORY OF UNITS)

    PREPARATION OF MILESTONES (PLANNED)

    COMPILATION OF UNIT DEFECT LIST

    PRE OVERHAUL SPRAY VALVES CHARACTERISTICS

    WORK REQUIRED TO BE CARRIED OUT AS PER

    OPERATION REQUIREMENT

    EFFICIENCY REQUIREMENT

    CHEMISTRY REQUIREMENT

    TRIPPING COMMITTEE RECOMMENDATIONS

    C&I REQUIREMENT

  • 7/31/2019 Unit Overhaul

    14/23

    NTPC/VINDHYACHAL

    CONTD

    BOILER TUBE LEAKAGE COMMITTEE RECOMMENDATIONS

    OS RECOMMENDATIONS

    CONDITION MONITORING GROUP RECOMMENDATIONS

    SAFETY REQUIREMENT

    R&M REQUIREMENT

    PREPARATION OF: PTW & CLEARANCE BOOKS FOR BOILER & AUX.

    PTW & CLEARANCE BOOKS FOR TG & AUX.

    CLEARANCE & RECOMMISSIONING BOOK FOR VALVES,

    DAMPERS, IGVs, SOOT BLOWERS & LRSBS

  • 7/31/2019 Unit Overhaul

    15/23

    NTPC/VINDHYACHAL

    CONTD...

    CHECK SHEET FOR MOTOR TRIALS, EQUIPMENT

    RECOMMISSIONING & PROTECTION CHECKING

    CHECK SHEET FOR VALVES REQUIRED FOR CONDENSER

    FLOOD TEST

    CHECK SHEET FOR VALVES REQUIRED FOR BOILER

    HYDRO TEST

    COMMUNICATION LOG BOOK

  • 7/31/2019 Unit Overhaul

    16/23

    NTPC/VINDHYACHAL

    DURING OVERHAUL ACTIVITIES

    PREPARATION OF DISPLAY BOARD FOR

    COMMUNICATION OF OVERHAUL PLANNING

    COORDINATION IN ISSUE OF PERMITS

    MONITORING OF WORK PROGRESS / COMPLETION

    COORDINATION OF REGULAR UNIT OVERHAUL MEETING

    AT 5:30 PM IN O&M CONFERENCE HALL

    PREPARATION & DISTRIBUTION OF RECORD NOTES

    FEEDBACK TO WRHQ & CC-OS FOR WORK PROGRESS

  • 7/31/2019 Unit Overhaul

    17/23

    NTPC/VINDHYACHAL

    MONITORING & REVIEW OF CRITICAL VALVES STATUS AS

    PER CHECK SHEETS REQUIRED FOR CONDENSER FLOOD

    TEST & BOILER HYDRO TEST

    MONITORING & REVIEW OF CLEARANCES AVAILABLE &

    RECOMMISSIONING PROGRESS ( MOTORS TRIALS /

    EQUIPMENT TRIALS)

    COORDINATION IN

    FURNACE AIR TIGHTNESS TESTS

    CONDENSER FLOOD TESTS

    BOILER HYDRO TESTS

  • 7/31/2019 Unit Overhaul

    18/23

    NTPC/VINDHYACHAL

    POST OVERHAUL ACTIVITIES

    PREPARATION OF UNIT-WISE UNIT OVERHAUL REPORTIN BOOK FORM HARD COPY FOR LIBRARY & ISO

    PREPARATION OF UNIT OVERHAUL REPORT IN CD-

    FORMAT POST OVERHAUL REVIEW OF WORKS PLANNED AND

    ACTUALLY COMPLETED.

    POST OVERHAUL REVIEW OF IMPROVEMENT IN

    PARAMETERS & EFFICIENCY POST OVERHAUL PLAN Vs ACTUAL DEVIATION SHEET

  • 7/31/2019 Unit Overhaul

    19/23

    NTPC/VINDHYACHAL

    PROCESS IMPROVEMENTS

    BOILER EXTERNAL WATER WASHING WAS CAUSINGDAMAGE TO INSULATION AND DELAY IN START OFOVERHAUL ACTIVITIES, DRY BOILER CLEANINGSTARTED.

    QUICK ERECT SCAFFOLDING IS BEING USED FOR BOILERINTERNAL CLEANING & INSPECTION

    HIGH PRESSURE WATER JET CLEANING IS BEING DONEFOR BOILER TUBES

    ALL PA FANS & MILL MOTORS VIBRATION MEASUREMENTALSO STARTED DURING UNIT OVERHAULS

    ALL HT MOTORS TRIAL RUN IS BEING TAKEN FOR 8 HRSAND LT MOTORS FOR 4 HRS

  • 7/31/2019 Unit Overhaul

    20/23

    NTPC/VINDHYACHAL

    PROCESS IMPROVEMENTS

    CONDENSER TUBE CLEANING IS BEING DONE USINGCONCO BULLETS

    INVOLVEMENT OF FQA IS INCREASED IN MAIN TURBINE &GENERATOR AREA

    BOILER DRUM FILLING USING HOT WATER STARTED

    BOILER TUBES D-METERING SCOPE INCREASED UPTO25000 LOCATIONS.

    24-VOLT HAND LAMPS ARE BEING USED

    PREOVERHAUL / DURING OVERHAUL SAFETY SURVEYBEING CARRIED OUT

  • 7/31/2019 Unit Overhaul

    21/23

    NTPC/VINDHYACHAL

    ADDITIONAL RESPONSIBILITIES

    DRAWING SECTION: O&M DRAWING SECTION IS PIONEERIN DEVELOPMENT OF DRAWINGS IN AUTO CAD.MANPOWER: TWO DRAFTMENTRAINED IN AUTO-CAD

    PRINT ROOM: O&M PRINT ROOM COPE UP THE DAY TODAY REQUIREMENT OF

    PHOTCOPYING, CYCLOSTYLLING & AMMONIA PRINTINGOF DRAWINGS REQUIRED FOR INDENTING PURPOSES.MANPOWER: ONE ATTENDANT

    DISPLAY ROOM: O&M DISPLAY ROOM LOCATED ATSERVICE BUILDING O MR IS BEING MAINTAINED AND

    UPDATED REGULARLY

  • 7/31/2019 Unit Overhaul

    22/23

    NTPC/VINDHYACHAL LONG TERM PLANNINGCONSTRAINTS

    UNIT OVERHAUL REPORTS: INSPITEOF ALL BEST POSSIBLEEFFORTS, PROBLEM IS BEING FACED TO GET THE FEEDBACKFROM OTHER DEPARTMENTS FOR THE JOBS COMPLETED,MEASUREMENTS TAKEN AND EXPENDITURE INCURRED

    DURING UNIT OVERHAULS, WHICHCAUSES DELAY INCOMPILATION OF UNIT OVERHAUL REPORTS.

    OVERHAUL COST: PRESENTLY IT IS DIFFICULT TO GET THEFINANCIAL DATA i. e. UNIT OVERHAULS COST (THE

    EXPENDITURE INCURRED DURING RESPECTIVE UNITOVERHAULS). CONTINUOUSLY THESE DATA ARE BEINGASKED BY CC & WR.

    ISSUE OF MATERIALS: MATERIALS PROCURRED FOR UNITOVERHAULS MUST BE TAGGED BY STORES AND NOT TO BE

    ISSUED TO ANY OTHER DEPARTMENT WITHOUT CONSENT.

  • 7/31/2019 Unit Overhaul

    23/23

    NTPC/VINDHYACHAL

    THANK YOU