Unit II Project Planning Revised

Embed Size (px)

Citation preview

  • 8/11/2019 Unit II Project Planning Revised

    1/39

    310-PROJECT MANAGEMENT

    FACULTY:

    Dr. CH. VENKATAIAH

    B.Tech, MBA, PhDAssociate Professor (Operations, Quality & Project Management)

  • 8/11/2019 Unit II Project Planning Revised

    2/39

    PROJECT PLANNING

    UNIT

    II

  • 8/11/2019 Unit II Project Planning Revised

    3/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 3

    Project Planning

    Resource Availability and/or LimitsDue date, late penalties, early completion

    incentives

    Budget

    Activity Information

    Identify all required activities

    Estimate the resources required (time) to

    complete each activity Immediate predecessor(s) to each activity needed

    to create interrelationships

  • 8/11/2019 Unit II Project Planning Revised

    4/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 4

    Project Scheduling and Control Techniques

    Gantt Chart

    Critical Path Method (CPM)

    Program Evaluation and Review Technique

    (PERT)

  • 8/11/2019 Unit II Project Planning Revised

    5/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 5

    Graph or bar chart with a bar for each project activity that shows passage of time

    Provides visual display of project schedule

    Gantt Chart

  • 8/11/2019 Unit II Project Planning Revised

    6/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 6

    History of CPM/PERT

    Critical Path Method (CPM)

    E I Du Pont de Nemours & Co. (1957) for construction ofnew chemical plant and maintenance shut-down

    Deterministic task times

    Activity-on-node network construction

    Repetitive nature of jobs

    Project Evaluation and Review Technique (PERT)

    U S Navy (1958) for the POLARIS missile program

    Multiple task time estimates (probabilistic nature)Activity-on-arrow network construction

    Non-repetitive jobs (R & D work)

  • 8/11/2019 Unit II Project Planning Revised

    7/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 7

    Project Network

    Network analysis is the general name given to certain specific techniques which

    can be used for the planning, management and control of projects

    Use of nodes and arrowsArrows An arrow leads from tail to head directionally

    Indicate ACTIVITY, a time consuming effort that is required toperform a part of the work.

    Nodes A node is represented by a circle

    - Indicate EVENT,a point in time where one or more activities startand/or finish.

    Activity

    A task or a certain amount of work required in the project

    Requires time to complete

    Represented by an arrow

    Dummy Activity

    Indicates only precedence relationships

    Does not require any time of effort

  • 8/11/2019 Unit II Project Planning Revised

    8/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 8

    Event

    Signals the beginning or ending of an activity

    Designates a point in time

    Represented by a circle (node)

    Network

    Shows the sequential relationships among activities using

    nodes and arrows

    Activity-on-node (AON)

    nodes represent activities, and arrows show precedence relationships

    Activity-on-arrow (AOA)

    arrows represent activities and nodes are events for points in time

    Project Network

  • 8/11/2019 Unit II Project Planning Revised

    9/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 9

    AOA Project Network for House

    3

    2 0

    1

    3

    1 1

    11 2 4 6 7

    3

    5

    Lay

    foundation

    Design house

    and obtain

    financing

    Order and

    receive

    materials

    Dummy

    Finish

    work

    Select

    carpet

    Select

    paint

    Build

    house

    AON Project Network for House

    13

    2

    2

    43

    31 5

    1

    61

    71Start

    Design house

    and obtain

    financing

    Order and receivematerials

    Select paint

    Select carpet

    Lay foundations Build house

    Finish work

  • 8/11/2019 Unit II Project Planning Revised

    10/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 10

    Situations in network diagram

    AB

    C

    A must finish before either B or C can start

    A

    B

    C both A and B must finish before C can start

    D

    C

    B

    Aboth A and C must finish before either of B or D can

    start

    A

    C

    B

    D

    Dummy

    A must finish before B can start

    both A and C must finish before D can start

  • 8/11/2019 Unit II Project Planning Revised

    11/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management 11

    Concurrent Activities

    2 3

    Lay foundation

    Order material

    (a) Incorrect precedence

    relationship

    (b) Correct precedence

    relationship

    3

    42

    DummyLay

    foundation

    Order material

    1

    2 0

  • 8/11/2019 Unit II Project Planning Revised

    12/39

    Dr. CH. VENKATAIAH

    Associate Professor

    310-Project Management

    Activity. It is a clearly defined project element, a job or atask which requires the consumption of resources includingtime. It is denoted by an arrow.

    Event.An event describes the start or completion of anactivity. It is denoted by a numbered circle.

    Path. A path is an unbroken chain of activities from theinitiating node to some other node, generally to the lastnode indicating the end or completion of the project.

    Dummy Activity. A dummy activity is that activity which hasa logical function only and consumes no time or resources.It is denoted by a dotted arrow. There are two types ofdummies:

    Identity Dummy. It helps to keep the designation of eachactivity unique or different from another.

    Dependency Dummy. It helps to keep the logic correct.

    Definitions

    12

  • 8/11/2019 Unit II Project Planning Revised

    13/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Activity arrows should be drawn from left to right

    indicating progressive approach towards the

    ultimate objective or the final event.

    Crossing of activity arrows should be avoided.Arrows should be drawn as straight or bent

    lines but not curved lines.

    Avoid use of unnecessary dummies.

    Activities are set in the order of their execution.

    Events are set in the order of their occurrence.

    Rules and Conventions

    13

  • 8/11/2019 Unit II Project Planning Revised

    14/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Head event number should be greater than tail

    event number. No event is numbered until the

    tail event of each activity arrow ending into that

    event has been numbered. There should be no danglers or loops. Danglers

    are activities which lead no where. All activities

    must be connected to events and the finishing

    activities must be connected to the finish eventof the project.

    Rules and Conventions

    14

  • 8/11/2019 Unit II Project Planning Revised

    15/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 15

    CPM calculation

    Path

    A connected sequence of activities leading from

    the starting event to the ending event

    Critical Path

    The longest path (time); determines the projectduration

    Critical Activities

    All of the activities that make up the critical path

  • 8/11/2019 Unit II Project Planning Revised

    16/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 16

    Forward Pass Earliest Start Time (ES)

    earliest time an activity can start

    ES = maximum EF of immediate predecessors Earliest finish time (EF)

    earliest time an activity can finish

    earliest start time plus activity time

    EF= ES + t

    Latest Start Time (LS)

    Latest time an activity can start without delaying critical path time

    LS= LF - t

    Latest finish time (LF)latest time an activity can be completed without delaying critical path time

    LS = minimum LS of immediate predecessors

    Backward Pass

  • 8/11/2019 Unit II Project Planning Revised

    17/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 17

    CPM analysis

    Draw the CPM network

    Analyze the paths through the network Determine the float for each activity

    Compute the activitys float

    float = LS - ES = LF - EF

    Float is the maximum amount of time that this activitycan be delay in its completion before it becomes a

    critical activity, i.e., delays completion of the project

    Find the critical path is that the sequence of activities and

    events where there is no slack i.e.. Zero slack Longest path through a network

    Find the project duration is minimum project completion

    time

  • 8/11/2019 Unit II Project Planning Revised

    18/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    It is used where activity duration is known withcertainty.

    Activities are identified.

    Dependency of activities is determinedNetwork is drawn

    Earliest start times and latest finish times arecalculated

    Critical path and critical activities are identified

    Critical Path Method

    18

  • 8/11/2019 Unit II Project Planning Revised

    19/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Rasoi Appliances wants to launch a newly

    designed microwave oven.

    Activities required for the launch have been

    identified. Their relationship with each other

    and the activity duration have also been

    determined.

    Example

    19

    Acti it Acti it Description Predecessor Time

  • 8/11/2019 Unit II Project Planning Revised

    20/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 20

    Activity

    Symbol

    Activity Description Predecessor Time

    (days)

    A Develop advertising plan - 6

    B Develop promotion and training

    materials plan

    - 7

    C Develop training plan - 8

    D Schedule Radio,TV and print media

    advertising

    A 20

    E Develop advertising copy A 18

    F Prepare promotional material for in-store introduction

    B 9

    G Prepare material for training of

    stores representatives

    B 8

    H Conduct pre-introduction advertising

    campaign

    D, E 7

    I Select store representatives for

    training

    C 2

    J Conduct training G, I 14

    K Final in-store launch of product F, H and J 10

  • 8/11/2019 Unit II Project Planning Revised

    21/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 21

    8

    C

    A

    B

    6

    7

    Drawing a Network. We can start withactivities A, B and C as they have nopredecessors.

    Consider the activities which can follow only A or B or C asthese have been completed. D and E follow A, F and Gfollow B and I follows C. Add these activities to the network.

    Activity H is dependent on the completion of Activities Dand E. Activity J is dependent on completion of Activities Gand I. Add these activities to the network.

    A dummy activity L has been drawn. This is an identitydummy. Add activity K which can start only when activitiesH, F and J are completed.

    Start from the left and number the nodes as we move to theright of the network in the order of their appearance. If two ormore nodes are on the same line, number from top to bottom.

    If the dummy L had not been put, then node 5 would havebeen eliminated and activity E also would have ended atnode 7. In that case, a reference to activity between nodes2-7 would refer to both D and E causing problems of

    unique reference. D

    E

    F

    G

    I

    20

    18

    9

    8

    2

    L

    J

    H

    7

    14

    K

    101

    2

    3

    4

    5

    6

    7

    8 9

  • 8/11/2019 Unit II Project Planning Revised

    22/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    The earliest that the project can start is attime zero.

    The earliest finish time for an activity is the

    earliest start time + activity duration.The earliest start time of an activity which is

    dependent on two or more activities is thetime at which all the preceding activities are

    completed.

    Calculating Earliest Start Time (EST)

    22

  • 8/11/2019 Unit II Project Planning Revised

    23/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 23

    C

    A

    B

    6

    7

    8

    D

    E

    F

    G

    I

    20

    18

    9

    8

    2

    L

    J

    H

    7

    14

    K

    10

    0

    6

    7

    8

    26

    24

    15

    33 43

    1

    2

    3

    4

    5

    6

    7

    8 9

    At Node 2, EST is = EST at Node 1 + Activity Duration of A

    = 0 + 6 = 6

    At Node 3, EST is = EST at Node 1 + Activity Duration of B

    = 0 + 7 = 7

    At Node 4, EST is = EST at Node 1 + Activity Duration of B

    = 0 + 8 = 8

    Node 7 is the starting event for activity J. Activity J can start only when

    activities I and G are completed. Activity I can be completed earliest by 8 + 2

    = 10, while G can end earliest on 7 + 8 = 15. Hence the earliest that J can

    start is the end of 15th day.

    At Node 6, EST is = EST at Node 2 + Activity Duration of D =

    6 + 20 = 26, and (from Node 5 to Node 7) 24 + 0 = 24. Earliest H can start

    is 26.

    At Node 5, EST is = EST at Node 2 + Activity Duration of E

    = 6 + 18 = 24

    At Node 8, we get

    From 7 to 8, 26 + 7 = 33. From 3 to 8, 7 + 9 = 16

    From 6 to 8, 15 + 14 = 29. Earliest K can start is 33.

    At Node 9, EST = EST at Node 8 + duration of activity K

    = 33 + 10 = 43

  • 8/11/2019 Unit II Project Planning Revised

    24/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    The project will take 43 days.

    Start form Node 9 as 43 days and work

    backward to find out the latest time when

    the starting event of an activity must occur,

    or the latest time by which all preceding

    activities must finish so that the project is

    not delayed

    Latest Finish Time

    24

  • 8/11/2019 Unit II Project Planning Revised

    25/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 25

    C

    A

    B

    6

    7

    8

    D

    E

    F

    G

    I

    20

    18

    9

    8

    2

    L

    J

    H

    7

    14

    K

    10

    0

    6

    7

    8

    26

    24

    15

    33 43

    4333

    26

    19

    26

    17

    0

    11

    6

    At Node 8, LFT is = LFT at Node 9Activity Duration of K

    = 4310 = 33

    At Node 6, LFT is = LFT at Node 8Activity Duration of H

    = 337 = 26At Node 7, LFT is = LFT at Node 8Activity Duration of J

    = 3314 = 19

    At Node 5, LFT is = LFT at Node 7Activity Duration of L

    = 260 = 26

    At Node 3, LFT is = LFT at Node 6Activity Duration of G or

    LFT at Node 8Activity Duration of F

    = 198 =11 or 339 = 24

    If event 3 occurs at 24 then the project will get delayed. LFT is = 11

    At Node 4, LFT is = LFT at Node 6Activity Duration of I

    = 192 = 17At Node 2, LFT at Node 5Activity Duration of E or

    LFT at Node 7Activity Duration of D.

    Take the smallest value. At Node 2, LFT is = 6

    At Node 1, LST = 0

    1

    2

    3

    4

    5

    6

    7

    8 9

  • 8/11/2019 Unit II Project Planning Revised

    26/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Spare time in an activity is called float. It isused to economise on resources withoutaffecting the overall duration of the project.

    Types of floatsTotal float

    Free float

    Interference float

    Independent float

    Floats

    26

  • 8/11/2019 Unit II Project Planning Revised

    27/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Total Float. It is the spare time available on any given

    activity if the tail event occurred at its earliest time

    and the head event at its latest time.Total Float = Time Latest at HeadTime Earliest at

    TailActivity Duration.

    = 3043 = 23

    27

    4EST 26EFT

    30LST8LFT

    G

    3

    Total Float. = 3043 = 23

    Free Float. The spare time available on an activity if both the tail and thehead events occur at their earliest time. If this spare time is used up

    during the execution of this activity, it will have no effect on subsequent

    activities.

    Free Float = Time Earliest HeadTime Earliest Tail

    Activity Duration

    = 2643 = 19

    Total Float. = 3043 = 23

    Free Float. = 2643 = 19

    Interference Float.It is equal to total float less free float. If this float is used

    up in an activity, it will interfere with the availability of floats available for

    subsequent activities.

    Interference Float = Total FloatFree Float

    = 2319 = 4

    Total Float. = 3043 = 23

    Free Float. = 2643 = 19

    Interference Float.= 2319 = 4Independent Float.The spare time available in an activity which is

    neither affected by the use of float by preceding activities nor

    does it affect the float available in subsequent activities.

    Independent Float = Time Earliest HeadTime

    Latest TailDuration.

    = 2683 = 15

  • 8/11/2019 Unit II Project Planning Revised

    28/39

  • 8/11/2019 Unit II Project Planning Revised

    29/39

  • 8/11/2019 Unit II Project Planning Revised

    30/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    PERTProgramme Evaluation andReview Techniqueis used inprobabilistic situations when the durationof activities is not known with certainty.

    Three time estimates are used for activitydurationpessimistic time, optimistic timeand most likely time.

    Mean time for each activity is calculated.

    Network is drawn as for CPM with meantimes as activity durations

    PERT Network

    30

  • 8/11/2019 Unit II Project Planning Revised

    31/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Critical activities are identified.

    Standard deviation on the critical path iscalculated.

    Using the standard deviation and the meanand assuming normal distribution, projectduration with different levels of confidence orvice versa can be computed.

    PERT Network

    31

  • 8/11/2019 Unit II Project Planning Revised

    32/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Standard deviation cannot be added. Variance can be

    added. Standard deviation on the critical path is

    PERT - Network

    32

    4Mean Time

    6

    o m pt t t

    Standard Deviation6

    p ot t

    2 2 ...A BSD SD

  • 8/11/2019 Unit II Project Planning Revised

    33/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    PERT - Example

    33

    Activity Predecessor Optimistic Time

    (to)

    Most likely

    Time (tm)

    Pessimistic

    Time (tp)

    A - 1 2 3

    B - 1 2 3

    C - 1 2 3

    D A 1 2 9

    E A 2 3 10

    F B 3 6 15

    G B 2 5 14

    H D, E 1 4 7

    J C 4 9 20

    K J, G 1 2 9

    L H, F, K,

    Finish

    4 4 4

  • 8/11/2019 Unit II Project Planning Revised

    34/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Solution

    34

    Activity OptimisticTime (to)Mostlikely

    Time (tm)

    PessimisticTime (tp)MeanTime StandardDeviation

    A 1 2 3 2 0.33

    B 1 2 3 2 0.33

    C 1 2 3 2 0.33D 1 2 9 3 1.33

    E 2 3 10 4 1.33

    F 3 6 15 7 2.00

    G 2 5 14 6 2.00

    H 1 4 7 4 1.00

    J 4 9 20 10 2.67

    K 1 2 9 3 1.33

    L 4 4 4 4 0

  • 8/11/2019 Unit II Project Planning Revised

    35/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    Draw the network and find critical activities

    35

    51

    1

    1 98

    7

    6

    5

    4

    3

    2

    B

    HE

    D

    A

    LF

    C

    G

    J K

    2

    3

    4 4

    2

    6

    7

    2 10 3

    4

    1915

    122

    6

    0

    2

    2

    1

    91

    5

    1

    2

    2

    0

    1

    1

    7

    6

    C, J, K and L are critical activities. Critical path is 14789

    Project will be completed in 19 days or less with 50% confidence.

  • 8/11/2019 Unit II Project Planning Revised

    36/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 36

    Activity Optimistic

    Time (to)

    Most

    likely

    Time (tm)

    Pessimistic

    Time (tp)

    Mean

    Time

    Standard

    Deviation

    C 1 2 3 2 0.33

    J 4 9 20 10 2.67

    K 1 2 9 3 1.33

    L 4 4 4 4 0

    2 2 2 2

    2 2 2 2

    S. D.

    0.33 2.67 1.33 0

    3

    C J K LSD SD SD SD

  • 8/11/2019 Unit II Project Planning Revised

    37/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management 37

    With 84% level of confidence how much time would theproject take?

    PERT assumes that the distribution of the total projectcompletion time is normal. 84% represents Mean + 1

    standard deviation. We can say with 84% level ofconfidence that the project will finish in 22 weeks.

    What are the chances that the project will finish in 20weeks?

    20 19 0.33

    3

    x

    z

    19 20

    0.33 SD

    From normal distribution tables the probability when z =0.33 is 0.6290.

    There is a 63% chance that the project will finish in 20 weeks.

  • 8/11/2019 Unit II Project Planning Revised

    38/39

    Dr. CH. VENKATAIAH

    Associate Professor310-Project Management

    PERT is a probabilistic model and is based on three timeestimates. It is used mainly for projects where the activitydurations are uncertain, like research and developmentprojects. Levels of confidence and probabilities can be

    associated with the completion date of a project. CPM is based on certainty of the activity durations. It is

    used for projects where there is certainty about the timethat each activity would take. The project completionduration is not probabilistic but is certain.

    DifferencesPERT and CPM

    38

  • 8/11/2019 Unit II Project Planning Revised

    39/39

    Dr. CH. VENKATAIAH

    Associate Professor

    Any Queries???

    39