Unique Dredging and Placement Projects 1 Unique Dredging and Placement Projects Presented by Wendell Mears October 22, 2015

Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects1

Unique Dredging and Placement

Projects

Presented by

Wendell Mears

October 22, 2015

Page 2: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects2

• Dredging Basics, A Short Review

• On-site Aquatic Placement

• Confined Aquatic Disposal

• Beneficial Use Sites

• Coastal Mississippi: An Update

Presentation Overview

Page 3: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects3

In situ, Intermediate, and End State

Review—A Yard Is Not a Yard Is Not a Yard

Page 4: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects4

On-site Placement

Page 5: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects5

Inner Harbor Berths

Page 6: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects6

Dredging Method

Page 7: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects7

Commercial Landfill

• Regulations

– Federal: U.S. Environmental

Protection Agency (USEPA)

– State: DEP, DEQ, etc.

– Local

• Processing for transport

– Additives (e.g., Portland cement,

etc.)

• Transport

– Marine

– Truck

– Rail

Page 8: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects8

On-site Placement

• Regulations

– Federal: USEPA

– State: DEP, DEQ, etc.

– Local

• Transport

– Barge

– Truck and rail

– Conveyor

Page 9: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects9

On-site Placement

• Measurement and payment

– Cubic yard (CY) in situ

• Liabilities and risks

– Owner vs. landfill

– Managed risks

• Contaminant stability

– AVS SEM

– Hydric conditions

Page 10: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects10

On Site Placement for Restoration

• Location

• Size

• Sediment Properties

• Dredge Size

• Decant & Water Quality

• Return Waters

• Operations & Management

Location, location, location

Page 11: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects11

Confined Aquatic Sites

Page 12: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects12

Page 13: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects13

13

Port Hueneme Impacted Sediment Locations

Oxnard Harbor District

Naval Base Ventura County

USACE Federal

Channel

Page 14: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects14

14

Construction Sequence

Naval Base Ventura County

Oxnard Harbor District

Page 15: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects15

15

Step 1: Excavate

Cell

Beach

Nourishment

CAD Excavation

Page 16: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects16

16

Step 2: Place Contaminated

Sediment in Cell

Contaminated Sediment Dredging

Page 17: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects17

17

Step 3: Place Cap

Material

CAD Cell Capping

Page 18: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects18

Port Hueneme CAD Cross Section

-85’ MLLW

-56’ MLLW

-46’ MLLWClean

Cap

Contaminated

Sediments

-43’ MLLW

Page 19: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects19

Beneficial Use Sites

Page 20: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects20

Beneficial Use (BU)

• Beach nourishment

• Agriculture and products

– Topsoil

– Aquaculture

• Berms

– Stable and feeder

• Land creation

• Land improvement

• Marsh and intertidal habitat

Page 21: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects21

BU Marsh Design

• Design Considerations

– Foundation

– Dredge material properties

– Placement methods

– Density phases

• Lessons learned

– Marsh now

– Larger sites and adaptive

management

Page 22: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects22

Coastal Mississippi: An Update

Page 23: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects23

• 2001 & 2002

– USACE and DMR identify potential BU sites

– Develops Master Plan for BU in Mississippi

– Deer Island identified as a pilot project and completed in 2003

• 2008

– Beneficial Users Group (BUG) formed

– State and federal agencies, co-chaired by DMR and USACE

– Private stakeholders (e.g., local ports)

• 2010

– BUG recommends revised legislation

– House Bill 1440 passed March 2010

– Coastal Wetlands Protection Act § 49-27-61,

History and the BU Law

Page 24: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects24

Deer Island Marsh Creation

Project: 2001 to 2003

• Components:

– 7- to 8-foot-high dike

– Easterly wing dike

– Flash board riser weirs

– Offset to provide bayou

• Dredged material from Biloxi

Lateral Channel

• Approximately 40 acres were

filled with 365,000 cy of

sediment

Page 25: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects25

Pre-Katrina

Page 26: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects26

Post-Katrina

Page 27: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects27

Deer Island BU and Port of Gulfport 2012

• Designed with DMR, Port, and

Stakeholders

• USACE rebuilt existing cell under

MsCIP

• Refill existing BU cell and construct

additional expansion area BU cell

– Open at the western end to encourage

circulation and habitat development

– Can be expanded for additional material

– Mimics the historic 1850s footprint

– Intertidal plant species

– Chenier for nesting

Page 28: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects28

Port of Gulfport—2012 Restoration

Page 29: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects29

Deer Island BU Construction 2012

Page 30: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects30

Port of Gulfport—2012 Restoration (cont.)

Page 31: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects31

Current Views

Page 32: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects32

Current Views

Page 33: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects33

BU to Enhance Existing Marsh

Illustration of conceptual model for marsh

recovery after thin-layer disposal

Page 34: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects34

Regional Sediment Management Sites

Page 35: Unique Dredging and Placement Projectsaapa.files.cms-plus.com/SeminarPresentations...Deer Island BU and Port of Gulfport 2012 • Designed with DMR, Port, and Stakeholders • USACE

Unique Dredging and Placement Projects35

Questions /Discussion

[email protected]