Upload
halel111
View
232
Download
0
Embed Size (px)
Citation preview
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
1/22
Shore Connection
Com act ShoreBoX
Tested Validated Documented Solution
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
2/22
i
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
3/22
ii
Table of Contents
1. Introduction 11.1. Document Purpose 1
1.2. About the TVD Program 1
1.3. Context of the Solution 1
2. Essential Added Value for Customer 2
3. Architecture Selection 3
3.1.
Hardware Architecture 3
3.2. Ferry Ship Architecture up to 3 MVA 4
3.3. Container Ship Architecture up to 3 MVA 5
3.4. Devices 6
4. Tests Means 7
4.1. Compact ShoreBoX Prototype 7
4.2. GFC Platform 8
4.3. Automation Platform 9
4.4. Simulation Tools 9
5. Verification 10
5.1. Verification Goal 10
5.2. Verification Tests Results 10
6. Validation 13
6.1. Validation Goal 13
6.2.
Validation Tests Results 13
7. Documentation Delivery 15
8. Conclusion 16
9. Glossary 17
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
4/22
1
1. Introduction
1.1. Document Purpose
This document provides an overview of the Tested Validated Document Solution: Compact
ShoreBoX. It demonstrates and summarizes all the design and test efforts done on the solution
to reach a high quality level and customer satisfaction.
This document acts as a reference for verifying that the Compact ShoreBoX solution meets the
Tested Validated Documented (TVD) criteria (safe, reliable, efficient, productive and green).
1.2. About the TVD Program
This document is a Tested Validated Documented Solution (TVDS). A TVDS Report is one of the
documents created as part of the TVD activity.
A Tested Validated Documented Solution (TVDS) is typically aimed at a complete solution for a
segment, and is very specific. Depending on the documentation already produced as part of the
solution, the TVDS may simply be a report summarizing the activities that took place to meet the
TVD criteria.
TVD itself is the set of activities that result in a document or documents that are produced to
describe how to achieve a goal for an offer or solution. These activities consist of Testing (or
Verifying), Validating, and Documenting. While these activities are part of normal offer
development, the difference with TVD is that they are applied with a specific goal in mind;
Validation, for example, is done specifically to ensure that the goal of the TVD output is possible.
Another way of stating this is that these activities are narrowly focused to ensure a high standard
of quality for the system or capability the TVD document describes.
1.3. Context of the Solution
Due to increase in trade & traffic, shipping industry has become a strong source of pollution in
harbour cities (emissions, noise and vibrations). This pollution has a significant impact on human
health and environment..
Environmental global regulation MARPOL Annex VI sets a time frame to progressively reduce
pollutant emissions. Ships and ports need to invest in new technologies to reduce pollution and to
be compliant with these stricter regulations. A number of solutions are available but the shore
connection technology is the only one that can cut all emissions from ships at berth.
Compact ShoreBoX is a fully integrated and ready to use solution in a single box that allow
vessels to meet environmental regulations while at berth. It is based on Schneider Electric's
Shore Connection core design and built with the same standard components. It can deliver up to
3MVA and is compatible with ferry and container ship vessel types (as standard, it can be
adapted to other types of vessels as well).
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
5/22
2
2. Essential Added Value for Customer
The TVD program ensures customers that the solution meets the Schneider Electric requirements
(safe, reliable, efficient, productive and green). This section lists some advantages brought bythe Compact ShoreBoX solution.
Safe Compliant with IEC/ISO/IEEE 80005-1 international standard, that
guaranties the good connection between ship and High Voltage
Shore Connection system.
Green Cut all pollutant emissions from ships at berth.
Pre-engineered Ready to use, no extra engineering resource required.
Manufactured in Schneider Electric plant.
Routine tests done after manufacturing.
Optimizing lead-time and site works. Time to market reduction of
50%: 6 months of manufacturing lead time (from intake to shipment
loading)
1 week of installation on customer site (with civil engineering
ready)
2 weeks of commissioning
Cost effective Packaged solution based on Schneider Electric standard products.
Optimized footprint.
Reduced project time.
Reliable Tested according IEC/ISO/IEEE 80005-1 and IEC 62271-202
standards by Schneider Electric engineers and experts.
Developed and tested on 3 different dedicated platforms.
On load and robustness tested on real prototype in Schneider
Electric Labs.
Routine tests done on factory after manufacturing.
Factory and Site Acceptance Tests with the customer.
Energy efficient GFC modular frequency conversion units have a high efficiency
ratio level.
Efficiency ratio > 90 % down to 50 % of load (2 or 3 MVA) with
auxiliaries and roof extractors running.
User friendly Ship power up procedure is automatic and completed in less than 5
minutes.Compatible with vessels working at 50 or 60 Hz.
Designed for maintenance easiness.
End user is autonomous to handle its Compact ShoreBoX thanks to
a set of trainings and user documentation (installation guide, user
guide, )
Technical support The Compact ShoreBoX is supported by the continuous
engineering team.
A technical support is provided to the customer.
Scalable and movable Can be relocated when there's a change in berth configuration
Different Compact ShoreBoX units can be installed in parallel
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
6/22
3
3. Architecture Selection
This section provides an overview of the solution architectures, as well as the key functions that
were selected for delivery.
3.1. Hardware Architecture
The image above represents the main devices present in the solution, and their location with
respect to a power-distribution flow. During both the Verification and Validation phases of the
project, testing was done using the Shore Connection Automation platforms and Compact
ShoreBoX prototype located in Grenoble (France).
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
7/22
4
3.2. Ferry Ship Architecture up to 3 MVA
The following pictures describe the architecture of ferry ship type that has been tested and
validated.
Electricalarchitecture
Automationarchitecture
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
8/22
5
3.3. Container Ship Architecture up to 3 MVA
The following pictures describe the architecture of container ship type that has been tested and
validated.
Electricalarchitecture
Automationarchitecture
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
9/22
6
3.4. Devices
The following table gives the lists of the devices included in the tested and validated Compact
ShoreBoX solution:
Designation Reference FW versionHW
versionQuantity
Main Devices
MVEDiSwitchboard
HV Input Cell RM6 NE-B - - 1
Protection RelaySepam T87
Application version v08.01 -
1Base version v8.01 -
UMI version v0745 -
Com. Interface ACE850 TP v0.00 V2.00 1
Temp. Interface MET148 V0150 - 1
Input Transformer Trihal AF 3.3 MVA 6.6 / 0.4 kV - - 1
GFC G7TQ500CS - - 4 or 6
Output Transformer Trihal AF 3.3 MVA 0.4 / 6.6 kV - - 1
MVEDoSwitchboard
HV Output Cell Premset D06H - - 1
Output Grounding Premset D06H-NE - - 1
Output Measurement Premset VTM - - 1
Protection Relay(Main-OUT)Sepam T87
Application version v08.01 -
1Base version v8.01 -
UMI version v0745 -
Com Interface (Main-OUT) ACE850 TP v0.00 V2.00 1
Temp. Interface MET148 V0150 - 1
Ship Feeder Premset I06T 1 to 3
Protection Relay(SSI-OUT)
Sepam T87 (*)
Application version v08.01 -
1 to 3Base version v8.01 -
UMI version v0745 -Com Interface (SSI-OUT) (*) ACE850 TP v0.00 V2.00 1 to 3
Power Meter PM870 - - 1
Auxiliary Components
GCS CabinetPLC modules
Power Supply BMX CPS 3020 - - 1
Processor BMX P34 2020 V2.50 - 1
Ethernet Interface BMX NOE 0100 V2.60 - 2
Modbus Com BMX NOM 0200 V1.30 - 1
32 Inputs BMX DDI 3202K V2.0 - 1
16 In / 16 Out BMX DDM 3202K V2.0 - 1
LVC CabinetRemote Modules
Eth interface 12I/8O OTB 1E0 DM9LP V2.20 - 1
2 Analog IN TM2 AMI 2HT V2.0 - 3
LVG CabinetRemote Modules
Eth interface 12I/8O OTB 1E0 DM9LP V2.20 - 1
16 Digital IN TM2 DDI 16DT V1.0 - 1
8 Tra OUT TM2 DDO 8TT V1.0 - 1
LVSI CabinetRemote Modules
Eth interface 12I/8O OTB 1E0 DM9LP V2.20 - 1
16 Digital IN TM2 DDI 16DT V1.0 - 3
8 Tra OUT TM2 DDO 8TT V1.0 - 2
Magelis HMI screen HMIGTO6310 - - 1
GSM Gateway TSXETG3021 - - 1
Software
PLC application Compact_ShoreBoX_plc.sta.stu V0.4.1.5 - 1
HMI application Compact_ShoreBoX.vdz V0.4 - 1
(*): Only for Container version
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
10/22
4. Tests Means
This section makes
its verification and v
4.1. Compact Shore
A prototype of Co
system. It has bee
reproduce actual co
The test performed i
verification
functional te
on-load testi
verification
verification
full Compac
Connection
characteriz
a quick description of the means deployed by
lidation tests on the Compact ShoreBoX solutio
oX Prototype
pact ShoreBoX was built in order to validate
installed in Volta Lab in Grenoble (France) a
ditions of operation.
ncluded
f mechanical integration of devices inside enclo
sting on complete system
ing up to 3MVA
f electrical performances (EMC, sound level, effi
f system safety
ShoreBoX system validation
of additional temperature probes (100x)
tion, fine tuning and validation
Prototype overview
A prototype
manufactured in the
Schneider Electric factory
located Fabrgues
(France) was installed in
our Grenoble laboratory.
This prototype gives theadvantage to Schneider
Electric to test and
validate the system in
real situation.
GFC room
The Grid Frequency
Conversion technology,patented by Schneider
Electric, is a key element
in the shore connection
solution.
GFCs maximize the
solutions flexibility, and
are at the heart of its
energy efficiency and
energy cost savings.
7
chneider Electric to perform
.
the complete design of the
nd connected to the grid to
ure
ciency)
for thermal management
Remote HMI
System was
connected to a
remote control panel
with HMI for external
operation.
Systemmonitoring
Supervision
application was
developed with Power
SCADA Expert and
integrated to the
system.
Powertransformer
Connection to theSchneider Lab MV
network through a
20/6.6kV 1MVA power
transformer for main
supply.
Connection to the
Volta Lab LV network
for auxiliary supply.
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
11/22
8
4.2. GFC Platform
The GFC platform was used to simulate the behavior of the Frequency Conversion functional unit
of the Compact ShoreBoX. This section illustrates the Shore Connection GFC platform located in
Montbonnot (France) and gives a quick description of each part composing the platform.
Test platform overview
Up to 10 GFC units can be
connected in parallel.
Automation system of the
Compact ShoreBoX is
developed on this platform.
This system includes HMI,
PLC and LVG OTB
modules.
The platform includes also
some low voltage
switchboards for load
transfer management.
Ship load simulation
This shelter contains a load
network simulating a ship
load.
Inside load and overload
testing.
Load variations.
Short-circuit withstand.
Ship generatorsimulation
A 1MVA GENSET was
temporarily connected for
load transfer and
synchronization tests.
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
12/22
9
4.3. Automation Platform
The Compact ShoreBoX system has been fully simulated in order to validate the complete control
and monitoring system, as well as all safety functions. Automation platform is installed on the
Schneider Electric R&D center located in Eybens (France):The tests performed on this platform were:
Verification of technical and functional requirements for PLC application
Verification of environment management (forced ventilation, heating)
Verification of shore to ship interface and safety functions (including safety loop)
Verification of MV intertripping functions
Validation of HMI content and display
It contains the following elements
GFC and LV distribution simulation test bench
HMI
PLC and OTB modules Ship to shore interface relays (LVSI cabinet) switchable between ferry and container ship
architectures
MV protection test bench
Ship and connection point interface simulation bench for ferry
Ship and connection point interface simulation bench for container ship
GFC and LV distributionsimulation test bench
Test bench is dedicated to
verification of technical
requirements for PLC
application.
HMI content and behavior is
also simulated on this test
bench.
MV Protection TestBench
Test bench dedicated to
verify the good operation
of MV intertripping
functions.
It contains Sepam T87
protection relays.
4.4. Simulation Tools
Some tests that cannot be done in real situation were performed on PC platform by using some
calculation software, for example:
Electrical Simulation: Matlab Simulink, ETAP, ATP Thermal simulation: ANSYS Icepak, AmeSim Mechanical simulation: Advance Design, Pro Mechanica
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
13/22
10
5. Verification
5.1. Verification Goal
The objective of system verification ('T' of TVD process) is to demonstrate compliance of the
developed system with corresponding technical specifications. The main prerequisite to this
phase is completion of integration phase.
5.2. Verification Tests Results
The following table summarizes the tests efforts done to check the good operation of the
Compact ShoreBoX.
Test name Mean Requirement Result
Environment
Temperature risePrototype +Simulation tools
Endurance test at 3 MVA.Monitoring of 100 temperature test points insideand outside the Compact ShoreBoX.
Passed
Environmentmanagement
Prototype +Simulation tools
Check that the environment inside the CompactShoreBoX is monitored and maintained to thefollowing operating range:[-10;+35]C in normal mode [+35;+40]C with 5% of power deratingRelative humidity
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
14/22
11
Test name Mean Requirement Result
Resistance to UVradiations
PrototypeThe Compact ShoreBoX must be resistant to UVradiations.
Monitoring
Resistance to corrosion Enclosure samplesTest on sample according ISO 12 944-6:salt mistwater condensation
Passed
Resistance toenvironment
Simulation tools
Resistance to :seismic conditions Eurocode 8
wind effects up to 50 m/ssnow loads up to 4700 N.m
Passed
Performance
Dielectric withstand Prototype
According IEC 61439-1 10.9 and between LVinterconnection:Physical measurements of creepage
distances7.2 kV impulse withstand
Passed
Continuity of theprotection circuit
Prototype
Check correct connection of metallic covers anddoors to the main earthing conductor by physicaltesting as per IEC 62271-202 6.4.
Inject 30Adc on each connection and checkvoltage drop does not exceed 3V.
Passed
Voltage and frequencytolerance
Simulation tools
According IEC/ISO/IEEE 80005-1 5.2:
Continuous voltage variation toleranceContinuous frequency variation toleranceVoltage and frequency transientsUtility voltage drop tolerance
Passed
Voltage harmonicdistortion
GFC platform
According IEC/ISO/IEEE 80005-1 5.2 for no-load conditions:< 3% for individual voltage< 5% for total voltage
Passed
Evaluation of powerefficiency ratio
Prototype
Measured at different levels of power:
> 90 % @ rated power> 90 % @ 50 % of rated power> 80 % @ 25 % of rated power
Passed
Full load and overloadPrototype +GFC platform
Endurance test at full load (2MVA and 3MVA).Different ship load profiles tested.
Passed
Short-circuit withstandGFC platform +Simulation tools
Test done on different phase and neutralconfiguration.
Passed
Ship load variationtesting
GFC platform +Simulation tools
Following item tested:Ship motor startLoad sheddingShip transformer inrush current
Passed
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
15/22
12
Test name Mean Requirement Result
Compatibility withGenset synchronizer
GFC platform +Simulation platform
Following item tested:Manual couplingAutomatic coupling with Genset synchronizer
Passed
Safety
MV protectionPrototype +Automation platform
Check the good operation of the Medium Voltageprotection relay (Sepam T87).
Passed
System safety Prototype
Following items were tested:Safety loop operationGround check operationFault managementComponent failure mode tests
Passed
Component failurePrototype +Automation platform
Impact of following component failure on globalsystem safety were tested:
safety loop relayspilot wiresearth and neutral wirescircuit breakers
System remains safe at any step of failureoccurrence.
Passed
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
16/22
13
6. Validation
6.1. Validation Goal
The goal of the Validation ('V' of TVD process) effort is to make sure that the system meets the
customer expectations for quality, feature set, safety and reusability. To achieve the quality goal,
the team reviewed the marketing documentation, created test cases, and executed these test
cases on an environment representative of a live system. The team also reviewed the Quality
Assurance collateral to make sure that in addition to the marketing requirements, the software
also satisfied expected quality criteria.
6.2. Validation Tests Results
All the validation tests were done on the Compact ShoreBoX prototype.
Test name Requirement Result
Quality
Reception andinstallation of theCompact ShoreBoX
All installation operations are documented in the installation guide:
reception and inspection checklists (accessories, enclosure)managing the Compact ShoreBoX on sitewiring to the grid and connection pointwiring electrical components and utilities$
Installation procedures were checked during prototype installation.
Passed
Commissioning time Commissioning is done by trained Schneider services. 10 days
Maintenance operation
Check that maintenance operations are made easy for the operator:
GFC can be extracted easilyroof is removablefilter boxes are easy to maintain
maintenance procedures allowed to customer are documented
Passed
Training A set of training units can be proposed to the customer. Passed
Customer
documentation
A full set of document is provided to the customer in order tomanage its Compact ShoreBoX: installation guideuser guidemaintenance guideSingle line diagramsmechanical plans
Passed
Feature Set
Conformity withIEC/ISO/IEEE 80005-1
The Compact ShoreBoX was designed and tested in conformity withIEC/ISO/IEEE 80005-1.
Passed
HMI ergonomicCheck that the Compact ShoreBoX HMI is easy to understand by theend user.HMI screens are documented.
Passed
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
17/22
14
Test name Requirement Result
Connection anddisconnection to the grid
Manage input switchgear to feed the Compact ShoreBoX with thecustomer grid and check that the Compact ShoreBoX startscorrectly.
Passed
Connection anddisconnection to the ship
Select the desired connection point in case of multiple shipinterfaces and launch an automatic connection procedure.Check correct operation of shore power up sequence in normal andabnormal conditions.Check consistency between procedure progress and informationdisplayed on the HMI.
Passed
Frequency conversionrange
Check that the operator is able to change the output frequency.Check that output frequency can be 50 Hz or 60 Hz.
Passed
Connection timeTime measured between launching a ship power up procedure andenergy availability on connection point.
< 5 min
Energy consumptionCheck that ship energy consumption can be visualized on the powermeter inside the Compact ShoreBoX or on the HMI.Check that HMI can provide a time stamped consumption report.
Passed
Hibernation modeIsolate Compact ShoreBoX from the grid and check that safetyfunctions and environment management are maintained.
Passed
SCADA connectionData of the Compact ShoreBoX can be visualized on SCADAsoftware.
Passed
Operator Safety
Emergency shutdown
operation
Check that emergency shutdown occurs in all situations defined inthe standard IEC/ISO/IEEE 80005-1 4.9.
Check that Compact ShoreBoX cannot be restarted until the fault iscleared.
Passed
Safety equipment foroperator
Compact ShoreBoX is delivered with safety equipment for operator(insulating gloves, rescue hook, VAT).Warning plates are displayed on each room and on the doors of theCompact ShoreBoX.
Passed
AlarmingCheck that in case of default, an alarm is raised by the CompactShoreBoX (siren, flash light) and displayed on the HMI.Check that each alarm on HMI is time stamped.
Passed
Interlocking
Check that the correct interlocking arrangement prevent operator
from dangerous operation.Check interlocking between:
MV switchgearstransformer roomscustomer substation input cell
ship connection pointclosing condition of output breakeropening condition of ship interface grounding system
Passed
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
18/22
15
7. Documentation Delivery
The goal of this section ('D' of the TVD process) is to deliver a full set of documentation
necessary for the installation, exploitation and maintenance of the Compact ShoreBoX. For eachdocument, the customer is able to access to it through the link provided in the table below.
Document Localization
Installation guide Provided with the delivery of the Compact ShoreBoX.
User guide Provided with the delivery of the Compact ShoreBoX.
Maintenance guide Provided with the delivery of the Compact ShoreBoX.
Single line diagrams Provided with the delivery of the Compact ShoreBoX.
Training A set of trainings can be proposed to the customer.
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
19/22
16
8. Conclusion
The Compact ShoreBoX is a Tested, Validated Documented Solution. All tests were done in
accordance with the Schneider Electric requirements on physical platforms (refer to chapter 4. ofthis document). A final system testing was done on the Compact ShoreBoX prototype according
IEC/ISO/IEEE 80005-1 and IEC 62271-202 standards.
The Verification phase ensures that the Compact ShoreBoX solution performances and safety
level are compliant with the technical specifications and regulations. On-load testing up to 3 MVA
was done on Compact ShoreBoX prototype during verification phase
The Validation phase ensures to customers that the Compact ShoreBoX solution meets their
expectations in terms of quality and reliability of operation.
The following versions of Compact ShoreBoX were validated in accordance with the TVD
program:
Name Version Ship Type Power Level
Compact ShoreBoX Standard
Ferry2 MVA
3 MVA
Container2 MVA
3 MVA
These architectures met the TVD standard for Schneider Electric. This ensures a high level of
reliability and safety of the solution regarding its performance during operation, and therefore,maximizes customer satisfaction.
Architectures listed above have a dedicated technical support and supported by Schneider
Electric continuous engineering team.
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
20/22
17
9. Glossary
EMC : ElectroMagnetic Compatibility
GFC : Grid Frequency ConverterHMI : Human Machine Interface
MAIN-IN : Main input breaker
MAIN-OUT : Main output breaker
LAN : Local Area Network
LV : Low Voltage
MARPOL : MARitime POLlution
MV : Medium Voltage
MVEDi : Input Medium Voltage Electrical Distribution switchboard
MVEDo : Output Medium Voltage Electrical Distribution switchboard
PLC : Programmable Logic Controller
Pn : Nominal power of the Compact ShoreBoXSCADA : Supervisory Control And Data Acquisition
SSI-GND : Shore to Ship Interface grounding breaker
SSI-OUT : Shore to Ship Interface feeder
TRAi : Input Transformer unit
TRAo : Output Transformer unit
TVD : Tested, Validated and Documented
VAT : Voltage Absence Tester
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
21/22
18
8/10/2019 TVDS Report CompactShoreBoX Rev01 ENG
22/22
2014 Schneider Electric All RightsReserved
19
Compact ShoreBoX is a trademark of Schneider Electric. Other trademarks used herein are the property of theirrespective owners.
Schneider Electric Industries SAS
Head Office
35, rue Joseph Monier
92506 Rueil-Malmaison Cedex
FRANCE
www.schneider-electric.com
Due to evolution of standards and equipment,characteristics indicated in texts and images in thisdocument are binding only after confirmation by our
departments.
TVD_MAR_30.0.0 01/2014