Upload
carol-mcdonald
View
217
Download
1
Embed Size (px)
Citation preview
TTF-II Status & TTF-II Status & ProspectivesProspectives
Nick WalkerNick WalkerDESYDESY
55thth ITRP Meeting – 28.06.04 CALTECH ITRP Meeting – 28.06.04 CALTECH
OverviewOverview
Brief review of TTF activity this yearBrief review of TTF activity this year• Commissioning status / updateCommissioning status / update
Status of TechnologyStatus of Technology Future plansFuture plans
TTF-II 800 MeV SC linacTTF-II 800 MeV SC linac
RF gun
4 MeV 150 MeV
bunch compressor
ACC1 (M2*)
Laser
3rd harmonic
cavity diagnostic section
beam dump
12 MV/m 20 MV/m
ACC2(M1*) ACC3(M3*) ACC4(M4) ACC5(M5)
Successfully commissioned with beam
Successfully commissioned with RF power(hp coupler conditioning)
TTF-II 800 MeV SC linacTTF-II 800 MeV SC linac
RF gun
4 MeV 150 MeV
bunch compressor
ACC1 (M2*)
Laser
3rd harmonic
cavity diagnostic section
beam dump
12 MV/m 20 MV/m
ACC2(M1*) ACC3(M3*) ACC4(M4) ACC5(M5)
Dark current & radiationmeasurements at 25MV/m
Pagani
TTF-II Injector CommissioningTTF-II Injector Commissioning
RF gun
4 MeV 150 MeV
bunch compressor
ACC1 (M2*)
ACC2(M1*) ACC3(M3*)
Laser
3rd harmonic
cavity diagnostic section
beam dump
12 MV/m 20 MV/m
RF Gun:RF Gun:• 21-Feb-2004 21-Feb-2004 start conditioningstart conditioning• 6-Mar-2004 6-Mar-2004 5 Hz, 900 us, 3 MW5 Hz, 900 us, 3 MW• 16-Mar-2004 16-Mar-2004 10 Hz, 450 us, 3 MW10 Hz, 450 us, 3 MW• 17-Mar-2004 17-Mar-2004 first beam in gun sectionfirst beam in gun section
Injector:Injector:• 15-Apr-2004 15-Apr-2004 start injector commissioningstart injector commissioning• 7-Jun-2004 7-Jun-2004 end commissioningend commissioning
Linac:Linac:• 20-Aug-200420-Aug-2004 restart with complete machinerestart with complete machine
TTF-II Injector CommissioningTTF-II Injector Commissioning
RF gun
4 MeV 150 MeV
bunch compressor
ACC1 (M2*)
ACC2(M1*) ACC3(M3*)
Laser
3rd harmonic
cavity diagnostic section
beam dump
12 MV/m 20 MV/m
RF Gun:RF Gun:• 21-Feb-2004 21-Feb-2004 start conditioningstart conditioning• 6-Mar-2004 6-Mar-2004 5 Hz, 900 us, 3 MW5 Hz, 900 us, 3 MW• 16-Mar-2004 16-Mar-2004 10 Hz, 450 us, 3 MW10 Hz, 450 us, 3 MW• 17-Mar-2004 17-Mar-2004 first beam in gun sectionfirst beam in gun section
Injector:Injector:• 15-Apr-2004 15-Apr-2004 start injector commissioningstart injector commissioning• 7-Jun-2004 7-Jun-2004 end commissioningend commissioning
Linac:Linac:• 20-Aug-200420-Aug-2004 restart with complete machinerestart with complete machine
ACC1 coupler conditioning 35MV/m EP cavity test
The 35MV/m Cryomodule TestThe 35MV/m Cryomodule Test
35MV/m
5109
AC72: one of five high-performance EP cavities
The 35MV/m Cryomodule TestThe 35MV/m Cryomodule TestAC72: one of five high-performance EP cavities
35MV/m
5109
Acceptance test in vertical cryostat
• naked cavity• Low power• CW
The 35MV/m Cryomodule TestThe 35MV/m Cryomodule Test
35MV/m
5109
Acceptance test in vertical cryostat
• HP coupler• Tuner (fast/slow)• full power (system) test
Full 1/8th CM horizontal test
(CHECHIA)
Transferred to
AC72: one of five high-performance EP cavities
The 35MV/m Cryomodule TestThe 35MV/m Cryomodule Test
Acceptance test in vertical cryostat
Full 1/8th CM horizontal test
(CHECHIA)
Transferred to
Full 8 string CM TTF
Transferred to
AC72: one of five high-performance EP cavities
The 35MV/m Cryomodule TestThe 35MV/m Cryomodule Test
Acceptance test in vertical cryostat
Full 1/8th CM horizontal test
(CHECHIA)
Transferred to
Full 8 string CM TTF
Transferred to
35 MV/m EP TESLA Cavity accelerates beam for the first time 35 MV/m EP TESLA Cavity accelerates beam for the first time
0
5
10
15
20
25
30
35
40
0 500 1000 1500 2000 2500
t [us]E
acc[M
V/m
]
RF pulse with feedback in RF pulse with feedback in cavity 5 (AC72) during beam cavity 5 (AC72) during beam accelerationacceleration
AC72: one of five high-performance EP cavities
The 35MV/m Cryomodule TestThe 35MV/m Cryomodule Test
• RF measurements showed no degradation of performance (35MV/m achieved)
• RF gradient measurement calibrated using beam (energy spectrometer)
• No measurable radiation detected(no dark current)
No time for long-term system test due to TTF-II commissioning, but…
0
5
10
15
20
25
30
35
40
0 500 1000 1500 2000 2500
t [us]
Eac
c[M
V/m
]
RF pulse with feedback in RF pulse with feedback in cavity 5 (AC72) during beam cavity 5 (AC72) during beam accelerationacceleration
35 MV/m EP TESLA Cavity accelerates beam for the first time 35 MV/m EP TESLA Cavity accelerates beam for the first time
AC73 Full System Test inAC73 Full System Test in1/81/8thth Cryomodule (CHECHIA) Cryomodule (CHECHIA)
1100 hr continuous 1100 hr continuous operation at 35MV/moperation at 35MV/m
No ‘faults’ observedNo ‘faults’ observed• due to couplersdue to couplers• nor due to cavitiesnor due to cavities
Forced ‘trips’ caused Forced ‘trips’ caused no damage to no damage to cavity/couplercavity/coupler• No performance No performance
degradation observeddegradation observed
AC70: New EP Result!AC70: New EP Result!
Measured Q0 factor 2 over TESLA-800 specification
May 2004
35MV/m
5109
TTF-II Injector CommissioningTTF-II Injector Commissioning
RF gun
4 MeV 150 MeV
bunch compressor
ACC1 (M2*)
ACC2(M1*) ACC3(M3*)
Laser
3rd harmonic
cavity diagnostic section
beam dump
12 MV/m 20 MV/m
RF Gun:RF Gun:• 21-Feb-2004 21-Feb-2004 start conditioningstart conditioning• 6-Mar-2004 6-Mar-2004 5 Hz, 900 us, 3 MW5 Hz, 900 us, 3 MW• 16-Mar-2004 16-Mar-2004 10 Hz, 450 us, 3 MW10 Hz, 450 us, 3 MW• 17-Mar-2004 17-Mar-2004 first beam in gun sectionfirst beam in gun section
Injector:Injector:• 15-Apr-2004 15-Apr-2004 start injector commissioningstart injector commissioning• 7-Jun-2004 7-Jun-2004 end commissioningend commissioning
Linac:Linac:• 20-Aug-200420-Aug-2004 restart with complete machinerestart with complete machine
Problem-free commissioning of full ACC1 module for TTF-II operation
TTF Beam MeasurementsTTF Beam Measurementsbe
am e
nerg
y (M
eV)
Beam energy vs ACC1 phase
Energy spread vs ACC1 phase
rms
ener
gy s
prea
d (M
eV)
ACC1 phase (deg)
Energy stability and Energy spreadEnergy stability and Energy spread Measured in the BC dispersive section after accelerationMeasured in the BC dispersive section after acceleration LLRF with closed loopLLRF with closed loop energy stable within 0.1 %, rms = 8.5 10energy stable within 0.1 %, rms = 8.5 10-4-4 uncorrelated energy spread estimated from rising edge 25 uncorrelated energy spread estimated from rising edge 25
to 30 keVto 30 keV
Energy
Injector Commissioning:Injector Commissioning:Other HighlightsOther Highlights
Successful Successful commissioning of commissioning of bunch compressor bunch compressor BC2BC2
Emittance Emittance measurements measurements downstream of BC2 downstream of BC2 using four wire using four wire array station array station
Cavity as BPM…Cavity as BPM…
All possible due to ACC1 stable operation (turn-key system)
Measurement of Beam Position in Measurement of Beam Position in Cavity using Dipole ModeCavity using Dipole Mode
The signal of a dipole mode in a cavity can be used The signal of a dipole mode in a cavity can be used as an indication of the beam position (à la NLC)as an indication of the beam position (à la NLC)
example for vertical steering and dipole mode response in C1
mode ‘centre’
example for vertical steering and dipole mode response in C1
mode ‘centre’
Resolution: <50m
4 dipole modes which couple strongly to the beam
All modes co-axial within measurement resolution (50m)
Measurement of Beam Position in Measurement of Beam Position in Cavity using Dipole ModeCavity using Dipole Mode
The signal of a dipole mode in a cavity can be used The signal of a dipole mode in a cavity can be used as an indication of the beam position (à la NLC)as an indication of the beam position (à la NLC)
Klystrons: 3 Active CompaniesKlystrons: 3 Active Companies THALUSTHALUS
• First producer of prototype First producer of prototype achieving specs.achieving specs.
• 2 additional ‘production’ 2 additional ‘production’ modelsmodels
• Tests of modified tubes in Tests of modified tubes in July.July.
CPI• 1st prototype development• Achieved 10MW for short
pulse (tens of s, =60%)• Problems with longer pulse
(understood and being addressed)
TOSHIBA• First prototype being
prepared for initial testing (July)
Klystrons: 3 Active CompaniesKlystrons: 3 Active Companies THALUS
• First producer of prototype achieving specs.
• 2 additional ‘production’ models
• Tests of modified tubes in July.
CPICPI• 1st prototype development1st prototype development• Achieved 10MWAchieved 10MW for short for short
pulse (tens of pulse (tens of s, h=60%)s, h=60%)• Problems with longer pulse Problems with longer pulse
(understood and being (understood and being addressed)addressed)
TOSHIBA• First prototype being
prepared for initial testing (July)
Klystrons: 3 Active CompaniesKlystrons: 3 Active Companies THALUS
• First producer of prototype achieving specs.
• 2 additional ‘production’ models
• Tests of modified tubes in July.
CPI• 1st prototype development• Achieved 10MW for short
pulse (tens of ms, h=60%)• Problems with longer pulse
(understood and being addressed)
TOSHIBATOSHIBA• First prototype being First prototype being
prepared for initial testing prepared for initial testing (July)(July)
In addition: pulse cable testing starts this week at DESY
Immediate TTF-II ScheduleImmediate TTF-II Schedule
We are here
2004 2005
20.08.04
Beam in modules 3-5
35MV/m TEST
Saturation in wavelength range 30-120 nm July 2005
User operation (extended period)
Operation with full electron beam current (to be defined; 2.25 MHz?) Dec. 2005
User operation (extended period)
3rd Harmonic RF system and ACC6 installed Feb. 2006
1 GeV beam energy April 2006
Saturation 6 nm June 2006
User operation (extended period)
Seeding Option installed Dec. 2006
Seeding demonstration April 2007
Longer TermLonger Term
Saturation in wavelength range 30-120 nm July 2005
User operation (extended period)
Operation with full electron beam current (to be defined; 2.25 MHz?) Dec. 2005
User operation (extended period)
3rd Harmonic RF system and ACC6 installed Feb. 2006
1 GeV beam energy April 2006
Saturation 6 nm June 2006
User operation (extended period)
Seeding Option installed Dec. 2006
Seeding demonstration April 2007
Longer TermLonger Term
High-Gradient ProgramHigh-Gradient Program 30 new cavities from industry on order30 new cavities from industry on order
• First delivery August 2004 (total ~110)First delivery August 2004 (total ~110) Will be put through our established Will be put through our established
proceduresprocedures• Electro-polishing, HPR etc.Electro-polishing, HPR etc.• No modifications to any aspect foreseenNo modifications to any aspect foreseen
8 >35MV/m cavities 8 >35MV/m cavities willwill be installed into be installed into Cryomodule #6Cryomodule #6• Tests will either be in TTF linac orTests will either be in TTF linac or• New Module Test StandNew Module Test Stand
(supported in part by new EUROFEL money)(supported in part by new EUROFEL money)• Date: 2006Date: 2006
High-Gradient ProgramHigh-Gradient Program 30 new cavities from industry on order
• First delivery August 2004 Will be put through our established Will be put through our established
proceduresprocedures• Electro-polishing, HPR etc.Electro-polishing, HPR etc.• No modifications to any aspect foreseenNo modifications to any aspect foreseen
8 >35MV/m cavities will be installed into Cryomodule #6• Tests will either be in TTF linac or• New Module Test Stand
(financed by new EU XFEL money)• Date: 2006
Final CommentsFinal Comments TTF-II (on-going) commissioning on scheduleTTF-II (on-going) commissioning on schedule
• Turn-key stable operationTurn-key stable operation TTF-II (5 accelerating modules, 800 MeV) will be fully TTF-II (5 accelerating modules, 800 MeV) will be fully
commissioned this yearcommissioned this year• All the demands of a light source user facilityAll the demands of a light source user facility
ACC6 (35MV/m) scheduled for 2006ACC6 (35MV/m) scheduled for 2006 Successful transfer of 35MV/m to a standard TTF Successful transfer of 35MV/m to a standard TTF
cryomodule has been demonstrated in ACC1cryomodule has been demonstrated in ACC1• Acceleration with beamAcceleration with beam• No radiation measured (no dark current)No radiation measured (no dark current)
Process to produce 35MV/m cavities now established and Process to produce 35MV/m cavities now established and well understoodwell understood• Quality control required already exceeded by standard industry Quality control required already exceeded by standard industry
practisepractise Dark current under control Dark current under control Pagani Pagani XFEL activity rapidly ramping up XFEL activity rapidly ramping up Brinkmann Brinkmann