12
TSO progress towards ENTSOG IFIEC Energy Forum 22 Sep 2009 Jacques Laurelut GTE President & GTE+ Transition Manager

TSO progress towards ENTSOG IFIEC Energy Forum 22 Sep 2009 Jacques Laurelut GTE President & GTE+ Transition Manager

Embed Size (px)

Citation preview

TSO progress towards ENTSOG

IFIEC Energy Forum 22 Sep 2009

Jacques LaurelutGTE President & GTE+ Transition Manager

Contents

• Third Package & TSO role

• Progression to ENTSOG

• Trialling the Third Package processes

23rd October 2008 GIE Annual Conference 2008, Bucharest

European Network of Transmission System Operators for Gas

ENTSOG tasks will include the development of:• an annual work programme• Network codes• a 10-year network development statement• annual winter outlooks• an annual report

Consultation and development processes• To establish the annual work programme• To consider change proposals• To inform 10 year network development statement

Network Codes to provide the foundation for the marketNetwork Development Statement to inform the market

Outputs

3

Progressing towards formal ENTSOG

Progression from GTE to full ENTSOG

• GTE+ Workgroup • to start work

• “Pre-ENTSOG” • to implement ENTSOG as far as possible

• ENTSOG• requires full implementation of Third Package and ACER creation

4

ENTSOG

23rd October 2008 GIE Annual Conference 2008, Bucharest

GTE

1 Feb 2008

GTE+

1 Jan 2010

Pre-ENTSOG

Q2/3? 2011

ENTSOG(formalised post Commission/ACER opinion)

GTE+ Initiated 2008

• First transitional step to prepare for Third Package• To start work to define ENTSOG

• Make progress towards the single European Market

• 2008 achievements• Recruit small team

• Deliver Phase I Transparency Platform

• Deliver European Network Capacity Development Statement

• Winter Outlook report

• Conducted first Annual Work Programme consultation

...our first step made to explore concept and demonstrate willingness and progress

GTE+ First Annual Work Programme 2009

Delivering projects to benefit the market • Transparency Platform• Ten Year Network Development Statement• Winter Outlook• Capacity Product Co-ordination• Interoperability

– Procedure on Harmonization of Maintenance Publication– IT & Communications Roadmap

Delivering ENTSOG • Design organisation

• Deliver Statutes, Rules of Procedure, list of Members

Other Work during 2009

• Reverse flow Task Force

• Security of Supply Task Force

to inform European Policy Development development in the light of January 2009 gas supply disturbance

• Balancing ( benchmark in 2008, workshop in 2009)

Impact of Third Package

Third Package now a reality • Processes need to be “proved”

Need to trial the processes • Priority setting

• Framework Guidelines

• Network Codes

... it’s now time to create a new organisation with an efficient decision making process... TSOs want to be involved in trial Framework Guidelines processes prior to leading trial Network Code development

Delivering Network Codes

• open public processes

• enabling inputs and proposals from all stakeholders

• responsive development, having due regard to options

• justification of acceptance/rejection of ideas

• ENTSOG chaired

• ACER oversight of process

Commission & Agency set

priorities

Network Code delivery

Commission & Agency approval

processes

time

ENTSOG responsibility

Stakeholders Joint Working Sessions

Second Annual Work Programme 2010

Establishing “pre-ENTSOG”• Stakeholder and TSO support initialisation in 2010

Need to continue work to• Deliver benefits to market (TYDS, transparency,

balancing, interoperability, Tariff? ...) • Trial Third Package processes ( CAM )

Confirmation of 2010 Annual Work Programme later this year

Conclusions

• GTE+ has been a workgroup, a proxy for ENTSOG

• GTE+ has already delivering to the market

• “pre-ENTSOG” will be created in 2010 and will

• secure resource to enable the 2010 AWP

• apply the envisaged Third Package processes as much as it can

• have an efficient decision making process

• In 2010 “pre-ENTSOG will

• Participate in Trial Framework Guideline development ( CAM)

• Lead associated Network Code development (CAM)

• Lead other projects (eg: Transparency Platform, TYNDP, IT Roadmap )

• Support/commitment needed from

• regulators

• Commission

• stakeholders

• Formal and full ENTSOG will be created as soon as possible once the Acer is created

Thank youThank you

Please track our progress at:

www.gie.eu.com