TRD Status Report
Octagon Integration T. Siedenburg 20min
DAQ Electronics F. Hauler 10min
Gas System & Electronics B. Borgia 20min
AMS TIM
CERN, 24-Apr-2006
Aachen TRD Status Report
Th. Siedenburg
AMS TIM
CERN, 24-Apr-2006
TRD Octagon Integration (Th.Kirn)
I. Özen
21-APR-2006
TRD Octagon Integration21-APR-2006
TRD Octagon Integration• All DALLAS temperature sensors tested• All 82 flight frontend boards installed (UFE)• HV ground connections installed• UFE function tests in progress• Gas-tower interconnection tubes installed
Tower to tower finished next week• Gas-group cosmic tests in preparation
• TRD upper plate: Installation of inserts• STA M-Structure machined within specs.
Test mounting in preparation • TRD Rosengitter in preparation
Gastubing / Dallas & UFE cabeling
TRD Longterm Test
J. Hattenbach
2 Years
Gastightnessunchanged
Gasgainstable
Final Report on TRD Front End Electronics
UFE (Flight Modules)
Ch.H. Chung
Production of UFE (FM)
358 VA Chips TestsSelect 202 Chips
101 Production of 4 Types PCB
+
Functional Tests Integration
Series ofSpace Qualification
Tests
TVT 3D Vibration Coating TVT
Space Qualification Tests
1st TVTTemperature : -40oC … +80oC
Pressure : 110-5 mbarFunctional test without failure
Random VibrationX,Y and Z-DirectionaRMS = 6.8g, 20-2000 Hz for 120 secFunctional test without failure
Conformal Coating2nd TVTSame as 1st TVT condition
Operating Temperature (-20 ~ +50 oC)
: Gain Calibration Points
Thermal Profile in TVT
Noise after SQT
Common mode noise correctedNoise = 1.5 ADC == ENC = 4000 e-
Pedestal RMS
Gain Calibration
+50 oC -20 oC
All 6464 channels arecalibrated over full Temperature range
Gain vs. Temperature
Flight UFE Selection
ALL 101 produced UFEs within specificationsSelect “better“ UFEs as flight modules
TRD-UFE (FM)Pedestal Distribution :
~ 10% of full range
TRD-UFE (FM)Noise RMS Spread :
~ 4%
TRD-UFE (FM)Gain RMS Spread :
~ 3%25oC
UFE(FM) Production : Finished (Jul. 2005) Total = 101 UFEs (FM = 82, FS = 19)
UFE Space Qualification Tests (Mar.05 ~ Mar. 06) 1st Thermal Vacuum Test= 101 (Done w/o failure) Random Vibration Test = 101 (Done w/o failure) Conformal Coating = 101 (Done w/o failure) 2nd Thermal Vacuum Test = 101 (Done w/o failure) Best 82 FM selected (Mar. 2006)
Functional Tests : Finished (20.07.05)
UFE Integration : Finished (Apr. 2006)
TRD UFE Summary
TRD Gas Manifolds
• Distribute TRD gasflow into 41 segments
• Measure gastightness of individual segments
• Allow isolation of a segment when leaky
• Introduce no additional risk of gas leakage
Manifolds mounted on Octagon
OctagonTemperature
Swing
R,P,Y coldest
R,P,Y hottest
+30
0
-20
OHB TRD Thermal Report
240 days (4 periods)
MLI = 0.03
Average TRD Temperaturebetween +35oC and -20oC
Depending on ISS R, P, Y
Manifold / Flipper Valve Schematics
FVa FVb
Improve Manifold Leaktightness
FVa FVb
New Manifold Prototype ● Dry mounting of all components
● Full function test● Potting when ok
Alu. Body Viton Seal Alu. Cover
New Manifold Design
New Manifold DesignFits inside existing magnetic shielding
Gas connectionswith double-o-ringfront access
Cold Case Flipper-Valve Operation
Buerkert 6124
Viton Bag
No switching below -15oC Leakage to outsideif switched below -8oC
Flipper-Valve Temperature
TVT Tank Vacuum
Manifold operation: heated switching
SMD 100
Switching in TVT at -25oC ok if valve heated to 0oC
Heating of fully potted 2FV manifold: 2 x 2W x 30 min.
Gastightness through valves and to outside ok
Heater powerline control (8H+8C 40W each) TBD
FVa FVa+b FVb
3.4×10-5 l mbar/s 3.0×10-5 18×10-5
Helium Leakrate (1 Gasgroup 50×10-5 )
TRD Integration Schedule
Octagon Integration finished in May 06Rosengitter tubing & cabeling Jun - Sep 06Manifold design & production Apr - Oct 06Box-S/C EM -> QM upgrade Apr - Jul 06UG QM Electronics Prod. & Test Apr - Oct 06Box-S/C FM Prod. & Test Apr - Dec 06TRD Cosmics EM UGcrate @ RWTH Nov - Dec 06TRD Cosmics QM UGcrate TBD Jan - Mar 07UG FM Electronics Prod. & Test Oct 06 - May 07
TRD Integration Schedule INr. Vorgangsname Dauer Anfang Ende VorgängerRessourcennamen
1 TRD Gas System 359 Tage? Feb 6 '06 Jun 21 '072 1) Thermal Model 16 Tage Apr 4 '06 Apr 25 '06 U.Becker,K.Luebelsmeyer,C.Clark8
9 2a) UG Electronics EM (Rome) 0 Tage Mrz 27 '06 Mrz 27 '0618
19 2b) UG Electronics QM (Rome) 149 Tage Feb 6 '06 Sep 1 '06 B. Borgia,A. Bartoloni20 UG Electronic Boards 115 Tage Feb 6 '06 Jul 14 '06
31 UG Backplane 0 Tage Sep 1 '06 Sep 1 '0632 UG Crate 0 Tage Sep 1 '06 Sep 1 '0633 UGPD 0 Tage Sep 1 '06 Sep 1 '0634
35 3) EM / QM Box S & C 138 Tage Apr 18 '06 Okt 26 '0636 Prepare Clean Room at CERN 4 Wochen Apr 18 '06 Mai 15 '06 J. Burger / R. Becker37 Transport (Rome to CERN with EM UG-Crate) 5 Tage Mai 15 '06 Mai 22 '06 36EE38 Installation of missing Hardware Components Box-S35 Tage Mai 23 '06 Jul 10 '06 3744 Installation of missing Hardware Components Box-C40 Tage Apr 18 '06 Jun 12 '06 P. Fisher,R.Becker58 Tests with EM Electronics and Software 50 Tage Mai 23 '06 Jul 31 '06 A.Lebedev / F.Spada / A.Bartoloni61 Tests with QM Electronics and Software 35 Tage Sep 1 '06 Okt 19 '06 A.Lebedev / F.Spada / A.Bartoloni66 Space Quali. (QM Box S&C, EM Electronics) 30 Tage Sep 15 '06 Okt 26 '06 Aachen69
70 4) Cosmic Test AC 90 Tage Okt 27 '06 Mrz 1 '07 AC / KA / MIT / Rome71 Octagon Installation QM-Gas-System & EM-UG-Crate 10 Tage Okt 27 '06 Nov 9 '06 66 Th.Kirn/U.Becker/F.Zhou/ F.Bucci72 QM-Gas-System 2xQM-Ucrate EM-UG-Crate 8 Wochen Nov 10 '06 Jan 4 '07 71 AC / KA / MIT / Rome73 QM-Gas-System 2xFM-Ucrate QM-UG-Crate 8 Wochen Jan 5 '07 Mrz 1 '07 72 AC / KA / MIT / Rome74
3/27
J. Burger / R. Becker
4/4
Feb Mrz Apr Mai2006
TRD Integration Schedule IINr. Vorgangsname Dauer Anfang Ende Vorgänger Ressourcennamen
75 5) FM Box S 132 Tage Apr 4 '06 Okt 4 '0676 Plate with Vessels 0 Tage Apr 4 '06 Apr 4 '0677 MIT Transport Box 0 Tage Apr 4 '06 Apr 4 '0678 Fill ports 50 Tage Apr 18 '06 Jun 26 '0680 Sub-Assemblies (5 pieces ARDE) 62 Tage Apr 4 '06 Jun 28 '0691 Integration & Leak Test ( ARDE ) 2 Wochen Jun 29 '06 Jul 12 '06 80 M.Green / Arde92 Wire Harness 6 Wochen Jul 13 '06 Aug 23 '06 91 MIT / Miller93 Test (Clean Room MIT) 4 Wochen Aug 24 '06 Sep 20 '06 92 F.Zhou / M.Green94 Transport to CERN 2 Wochen Sep 21 '06 Okt 4 '06 93 MIT95
96 6) FM Box C 120 Tage Apr 4 '06 Sep 18 '0697 Components at CERN 40 Tage Apr 18 '06 Jun 12 '06
103 Clean Room at CERN 15 Tage Apr 4 '06 Apr 24 '06 J. Burger / R.Becker104 Welding 10 Tage Jun 13 '06 Jun 26 '06 102,103 R.Becker105 Functional Testing with EM UG Electronics 20 Tage Aug 1 '06 Aug 28 '06 58,104 G.Rybka / P.Fisher106 Vibration Jig 80 Tage Mai 2 '06 Aug 21 '06 R. Becker / M. Wlochal107 Vibration Test (Aachen) 10 Tage Aug 29 '06 Sep 11 '06 106,105 K.Luebelsmeyer108 Shipment from Aachen to CERN 5 Tage Sep 12 '06 Sep 18 '06 107109
110 7) FM Gas System 66 Tage Okt 5 '06 Jan 4 '07111 Integration Box S & C 2 Wochen Okt 5 '06 Okt 18 '06 75,96112 Functional Test ( CERN, QM Electronics )8 Wochen Okt 20 '06 Dez 14 '06 111,61113 Gas Supply (TBD) 5 Tage Dez 15 '06 Dez 21 '06 112114 TVT (Aachen,TBD) 2 Wochen Dez 22 '06 Jan 4 '07 113115
4/4
4/4
M.Green / Arde
MIT / Miller
F.Zhou / M.Green
MIT
J. Burger / R.Becker
R.Becker
G.Rybka / P.Fisher
R. Becker / M. Wlochal
K.Luebelsmeyer
Apr Mai Jun Jul Aug2006
TRD Integration Schedule IIINr. Vorgangsname Dauer Anfang Ende Vorgänger Ressourcennamen
116 8) UG Electronics FM Components 165 Tage Okt 6 '06 Mai 24 '07128
129 9) FM Software 20 Tage Mai 25 '07 Jun 21 '07130 Functional Test 1 Monat Mai 25 '07 Jun 21 '07 127131
132 10) Supply Vessel Filling 1 Tag? Apr 4 '06 Apr 4 '06133 Procedure Definition 1 Tag? Apr 4 '06 Apr 4 '06134 Procedure Approval 1 Tag? Apr 4 '06 Apr 4 '06135 Filling 1 Tag? Apr 4 '06 Apr 4 '06 Linde US136 Transportation to KSC 1 Tag? Apr 4 '06 Apr 4 '06137
Linde US