Upload
duongbao
View
221
Download
4
Embed Size (px)
Citation preview
INCENTIVE FOR
TRANSMISSION EFFICIENCY
- T. UMESH , SEE, RETD. KPTCL
- &
- N. RAGHUPRAKASH , EE, RA, KPTCL
IN THIS SESSION
Brief introduction to Transmission System
Efficiency Parameters in Transmission Activity
Transmission Loss & its calculation
System Availability & its calculation
Incentive Calculation by KERC.
INTRODUCTION TO TRANSMISSION NETWORK
Transmission Voltages in Karnataka
Transmission System Elements
AC/ DC lines
Power Transformers ( ICTs)
STATIC VAR Compensators
BUS REACTORS
TRANSMISSION SYSTEM EFFICIENCY
Measured in terms of
Transmission loss
Transmission system availability
TRANSMISSION LOSS
MYT Regulation , clause 3.4 deals with treatment of losses.
In the tariff order KERC stipulates the normative transmission losses to be achieved by KPTCL during MYT period.
If the loss is less, then incentive is allowed. This gain is to be shared in the ratio of 70: 30 between STU and the users of transmission system.
SLDC works out the Transmission loss month on month based on the input to the transmission system and the quantum of energy supplied to ESCOMs at the Inter Face points. This information is furnished to KERC based on which the Order for sharing of loss / gain on account of Transmission loss is issued.
INCENTIVE FOR TRANSMISSION EFFICIENCY
KERC vide its MYT Regulations -2006 Order
dated 31.05.2006 has stipulated that KPTCL
shall maintain a minimum of 98% availability for
recovery of full transmission charges.
Recovery of fixed charges below the level of target
availability shall be on pro-rata basis. At zero
availability, no transmission charges shall be
payable.
PROCEDURE FOR CALCULATION OF
AVAILABILITY
Availability shall be calculated and declared
separately for each voltage level.
The transmission elements shall be grouped
into following categories.
a) AC transmission lines: Each circuit of AC
transmission line shall be considered as one
element.
b) Inter-Connecting Transformers: Each 3ph
transformer or bank of three Sph transformer
shall form one element.
PROCEDURE FOR CALCULATION OF
AVAILABILITY
c) Static VAR Compensator: SVC along with SVC
transformer if any shall form one element.
d) Switched Bus Reactor: Each switched Bus
Reactor shall be considered as one element.
Weightage factor for each category of
transmission elements shall be as under:
a) For each circuit of AC line- Surge Impedance
loading (SIL) multiplied by Circuit Km. ( SIL
rating for various voltage level and conductor
configuration shall be as per the procedure
adopted for power system analysis)
PROCEDURE FOR CALCULATION OF
TRANSMISSION SYSTEM AVAILABILITY (TSA)
b) For each ICT- The rated MVA capacity
c) For SVC- The rated MVAR capacity
d) For switched Bus Reactor: The rated MVAR
capacity.
The availability for each category of transmission
elements shall be calculated based on the
weightage factor, total hours under consideration
and non-available hours for each element of that
category.
The transmission elements under outage due to
following reasons not attributable to KPTCL
shall be deemed to be available:
1) Shut down of transmission elements availed by
other agencies for maintenance or construction of
their transmission system.
2) Manual tripping of the line due to over voltage
and manual tripping of elements as per the
directions of the RLDC/SLDC.
Outage time of elements due to acts of God and
force majeure events beyond control of KPTCL
shall be excluded.
Outage time caused by grid disturbance not
attributable to KPTCL shall also be excluded. Eg.
Faults in substations or bays owned by other
agencies causing outage of KPTCL elements.
However, if the elements are not restored on
receipt of directions from SLDC while
normalizing the system following a grid
disturbance within reasonable time, then the
element will be considered not available for
whole period of outage and outage time shall
be attributable to KPTCL.
The % availability is calculated for each
transmission element as follows:
1st calculate Availability index= Total time under
consideration-Outage hours due to unscheduled
interruptions/Total time under consideration.
Next calculate availability= Availability
index*Weightage factor
% availability= availability/weightage factor
Then, % availability of category of elements=
Sum of availability of all elements/sum of
weightage factor of all elements.
Then, % System Availability is calculated as the
average of all category availabilities.
FORMULA FOR CALCULATION
% TSA = o*AV₀ + p*AVp + q*AVq + r*AVr X 100
o+p+q+r Where ,
AV = Availability
o = No. of AC lines
p = No. of ICTs
q = Capacitor Bank
r = Bus Reactors
Zone: Bangalore
Element: AC lines
Sl.
No.Name of the line
Voltage
kVConductor Ckt.kM SIL
Weightage
factor
Total time of
consideration-
hours
Un-
Scheduled
Interrupti
ons- hours
Availability
Index
Availability
(Avi)
%
Availability
A B C=A*B D E F=(D-E)/D G=C*F H=G/C*100
1 Nelamangala - Peenya I 220 Drake 17 132 2244 8760 4.87 0.999 2242.752 99.944%
2
3
4
5
290
Total 1305556.1 1304626.78
Sl.No. ZoneNo. of AC
linesWf Availability
No. of
ICT'sWf Availability
No. of
SVAR'sWf Availability
%TSA of
Zones
1 Bagalkote 311 697757.44 695026.05 471 9702.5 9684.27 22 462 460.71 99.73
2 Bangalore 290 1305556.08 1304626.78 499 15753.9 15745.99 31 688.28 688.28 99.94
3 Gulbarga 173 738584.22 734879.11 311 6021.5 6005.16 19 456 455.37 99.65
4 Hassan 198 931824.81 928881.66 268 5836.2 5834.83 16 371 356.16 99.72
5 Mysore 134 176175.12 176082.58 233 3842.6 3841.02 27 430 430 99.96
6 Tumkur 98 286133.19 285761.46 342 6079.7 6076.21 0 0 0 99.93
1204 4136030.86 4125257.64 2124 47236.4 47187.48 115 2407.28 2390.52 99.82
AVO 1204 0.997395276
AVP 2124 0.998964358
AVQ 115 0.993037785
%TSA= 99.82177037
KPTCL TOTAL
KPTCL TOTAL
INCENTIVE
KPTCL shall be entitled to incentive on achieving
annual availability beyond the target availability
of 98% as per the following formula.
Incentive= ATC* (TSA achieved-Target
availability)/Target availability
No incentive shall be payable above the
availability of 99.75%.
50% of the incentive shall be shared by the long
time customers in the ratio of their average
allotted transmission capacity for the year.
SURGE IMPEDANCE LOADING
Surge Impedance Loading (SIL) in MW’s of a long
transmission line is defined as ratio of (kVRE)²/SI
where VRE is the receiving end voltage in KV and
SI is surge impedance of the line.
SIL is typically the limit of the maximum power
that can be transmitted through the line at the
voltage level considered.
SIL can be increased by reducing the SI of the
line.
SIL VALUES AS PER KEGC 2005
Typical values of SIL are as follows:
a) 400 kV lines – Quad conductor- 1051 MW
b) 400 kV lines – Twin conductor-515 MW
c) 220kV lines – Single conductor-132 MW
d) 110kV lines – SC – 50 MW
e) 66kV lines – SC – 35 MW
SURGE IMPEDANCE
SI is defined as the √(L/C), where L and C are
Inductance and Capacitance of the line.
SI can be reduced by bundling.
Bundling is the use of two or more conductors per
phase, which reduces L and increases C.
Hence twin/quad conductors are used in
400/765kV lines.
Transmission lines produce reactive power due to their
natural capacitance.
Mvar produced = ½ CV²
Transmission lines also utilize reactive power to
maintain their magnetic fields.
Mvar used = ½ LI²
SIL is the loading of the line when Mvar produced =
Mvar used
i.e., when ½ LI² = ½ CV²
Which gives V/I = sqare root of L/C, which is nothing
but the SI of the line.
THANK YOU