PJM©2011 www.pjm.com Transmission Expansion Advisory Committee Meeting 2011 Market Efficiency Analysis Update November 3, 2011 visited on 6/26/2014

Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©2011www.pjm.com

Transmission Expansion Advisory Committee Meeting

2011 Market Efficiency Analysis Update

November 3, 2011

visited on 6/26/2014

Page 2: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20112

Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11)

visited on 6/26/2014

Page 3: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20113

MEP-B-11 Cost/Benefit Analysis

Project Description• Increase Operational Limit of Cloverdale – Lexington 500 kV

Transmission Line• Expected in-service date=2017

Project Costs• Conservative estimate of $100 million• Cumulative Net Present Value of project costs during first 15

years of Project life is $156 Million based on a carrying charge rate of 17.9%

Project Benefits• Cumulative Net Present Value of project benefits during first 15

years of the Project life is $2.3 Billion based on discount rate of 7.7%.

∆Total Energy Market Benefit = 0.7*PC + 0.3*NLP∆Total Energy Market Benefit = 0.7*($1,601) + 0.3*($3,945)∆Total Energy Market Benefit = $2.3 Billion

Benefit/Cost Ratio = $2.3 billion/$156 millionBenefit/Cost Ratio = 14.76

Benefit/Cost Ratio >1.25 PASSED

Study Year

Net Load

Payment

Benefit

Production

Costs Benefit

Energy

Market

Benefit

2017 106.2 153.5 139.3

2018 200.3 147.9 163.6

2019 294.5 142.2 187.9

2020 388.6 136.5 212.2

2021 383.0 165.6 230.8

2022 430.3 175.4 251.9

2023 477.6 185.1 272.9

2024 524.9 194.9 293.9

2025 572.2 204.6 314.9

2026 619.6 214.4 335.9

2027 666.9 224.1 357.0

2028 714.2 233.9 378.0

2029 761.5 243.6 399.0

2030 808.8 253.4 420.0

2031 856.2 263.1 441.0

Total NPV $3,945 $1,601. $2,304

www.pjm.com

Annual Energy Market Benefit ($Millions)

visited on 6/26/2014

Page 4: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20114

$305.2

0.0

50.0

100.0

150.0

200.0

250.0

300.0

350.0

400.0

450.0

500.0

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

$N

om

nia

l Do

llars

(Mill

ion

)A

nnua

l Ene

rgy

Mar

ket B

enef

it ($

Mill

ions

)

Actual Simulation Benefit

MEP-B-11 Annual Energy Market Benefit

www.pjm.com

2025 Simulation Energy Market Benefit

Trended Energy Market Benefit

visited on 6/26/2014

Page 5: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20115

MEP-B-11 Sensitivity Analysis

• Load Sensitivity– Modeled a 10% Increase and Decrease in load

• Gas Commodity Price Sensitivity– Modeled Upper and Lower Range of Ventyx Expected

Commodity Price based on 12 month Distribution of Nymex Futures Henry Hub Traded Prices (2013 –2023)

www.pjm.com

visited on 6/26/2014

Page 6: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20116

MEP-B-11 Load Sensitivity

www.pjm.com

+/- 10% Load at Bus Bar

0

200

400

600

800

1000

1200

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026

En

erg

y D

em

an

d (G

WH

)

RTO Total Annual Energy Demand Before Losses (GWH)

PJM Annual Energy + 10% PJM Annual Energy - Expected PJM Annual Energy - 10%

RTO Total Energy Demand (Thousands GWH’s)

En

erg

y D

eman

d (

Th

ou

san

ds

GW

H’s

)

+/- 10%

visited on 6/26/2014

Page 7: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20117www.pjm.com

MEP-B-11 Gas Sensitivity

0.00

2.00

4.00

6.00

8.00

10.00

12.00

14.00

16.00

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

$ P

er M

MB

TU

Ventyx Gas Commodity Forecast

Ventyx Gas Commodity Forecast Sensitivity High Gas Forecast Sensitivity Low Gas Forecast

visited on 6/26/2014

Page 8: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20118

MEP-B-11 Sensitivity Results

Low Load CaseLower Loading of Transmission System Results in Less congestion and cheaper means of re-dispatch.

High Load CaseBy increasing the limits on Cloverdale - Lexington there are more West to East transfers, thus higher loading and congestion. In a high load case, congestion caused by West to East transfers are exacerbated whereas the benefits of the project do not grow as quickly.

www.pjm.com

Low Gas CaseMore opportunities for gas units in the east to be committed results in less dependence on West to East Transfers.

High Gas CaseMore dependence on generation in PJM West results in more West to East Transfers.

Scenario Benefit/Cost Ratio

Base 14.76

Low Load 10.02High Load 4.96Low Gas 11.5

High Gas 16.1

visited on 6/26/2014

Page 9: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©20119

MEP-B-11 Summary

• Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) summary

Driver for project is for both Reliability and Markets Sensitivity analysis on results of Cloverdale-Lexington upgrade around key input

assumptions show project still beneficial Year 2025 high level results match with trend Zonal summary results - Posted Recommendation to Board in December

visited on 6/26/2014

Page 10: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©201110

Market Efficiency Projects

COMED AREA

visited on 6/26/2014

Page 11: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©201111

2011 Market Efficiency Analysis Results

www.pjm.com

COMED Area Proposed Projects –Update including Reliability Light Load upgrades

* Updated Benefit/cost Ratio includes addition of upgrades associated with Reliability Light Load analysis identified at October 2011 TEAC.

Project Number Description Expected

ISD VoltageEstimated

Costs ($ millions)

Benefit/CostUpdated Benefit/ Cost*

MEP-A-1 Byron-Cherry Valley-Pleasant Valley 345 KV 2016 345 112.5 0.75 N/A

MEP-A-2 Byron-Pleasant Valley 345 KV 2016 345 105 0.96 N/A

MEP-A-3 Cherry Valley - Pleasant Valley 345 KV 2016 345 67.5 2.74 1.1

MEP-A-4 Byron - Charter Grove- Wayne 345 KV, Charter Grove 345/138 KV TX. 2016 345 275 0.24 N/A

MEP-A-5 Byron - Wayne 345 KV 2016 345 175 0.41 N/A

• MEP-A-3 no longer passes 1.25 threshold and might create reliability issues.

• Not necessary to rerun other projects since Benefit/Cost would only get lower.

• No Projects in COMED AREA to be recommended for Market Efficiency

visited on 6/26/2014

Page 12: Transmission Expansion Advisory Committee Meeting 2011 ... · November 3, 2011. visited on 6/26/2014. 2. PJM©2011. Cloverdale-Lexington 500 KV Line Upgrade (MEP-B-11) visited on

PJM©201112www.pjm.com

Market Efficiency Next Steps

• Update Base Results Add Light Load Upgrades Add Reactive Upgrades

Apply new Reactive Interface Ratings

Rerun appropriate cases

• Study new submitted projects