Upload
hadien
View
234
Download
5
Embed Size (px)
Citation preview
1
Track Asset Maintenance and Renewal Søren Boysen Director of Technical Operations, Rail Net Denmark
Presentation Cost Optimisation Track Maintenance & Renewals Congress 2012
• Rail Net Denmark (Banedanmark) – Key Figures
• Implementing The Asset Management Process
• Day to Day Maintenance – work smarter, not harder
• Long-term Maintenance and Renewal
– The Track Analysis Model
• Sum up
Agenda
• We are a state-owned enterprise under the
Ministry of Transport
• We own and manage the Danish state railway
network
• 2,200 employees
• We do day-to-day maintenance, renewal, and large
projects – e.g. the Signalling Programme (3 billion
EURO)
• Traffic Operation and passenger information
• Train operation is done by DSB and private train
operators
About Rail Net Denmark – who we are and what we do
Facts Figures
Line length 2,323 km
Tracks 3,240 km
Bridges 2,342
Total area served 5,500 ha
About Rail Net Denmark
Agenda
• Rail Net Denmark (Banedanmark) – Key Figures • Implementing The Asset Management Process • Day to Day Maintenance
– work smarter, not harder • Long-term Maintenance and Renewal
– The Track Analysis Model • Sum up
Banedanmark has developed a comprehensive activity planning process for both maintenance and renewal
Best practice Asset Management Process
Agenda
• Rail Net Denmark (Banedanmark) – Key Figures • Implementing The Asset Management Process • Day to Day Maintenance
– work smarter, not harder • Long-term Maintenance and Renewal
– The Track Analysis Model • Sum up
Day to day maintenance
Daily maintenance
Mobile Data Capture
Yardstick Method
SAP PM • Link between activities
and money spend • System support
• Identical use of process • No paperwork in the track • Minimise potential failures
• Support individual in track
• Reduce variation
Elements in improving the process of day-to-day maintenance.
SAP PM (Plant Maintenance)
Register Masterdata on: >200 construction elements • Through tracks • Sidings • Points • Trackside signals • Rectifier substation • Level crossings
>2,000,000 pieces of single equipment • Sleepers • Rails • Insulated Rail Joints • Masts etc.
Mobile Data Capture
Presenting, capturing and registering data on location in the track. Inspections and control is handled in the track. Work orders are created directly in SAP when the inspection is done in the track.
Liste over billeder vedhæftet til meddelelsen
Tag billede
Kamera søger
Tilbage til tilstands-‐ meddelelsen
Slet billede
Mobile Data Capture
• Eliminating double procedures • Eliminating double registration • Eliminating typing and paperwork • Submitting data directly to SAP • Automatic time registration
More quality time in the track!
Support tool: Yardstick Method Today: Variation in asset evaluation and requests for maintenance activities
Asset evaluation Asset condition reporting
Good
Functional
Poor
Asset Maintenance Requests
No maintenance/renewal needed
Maintenance/renewal needed by date/year
Maintenance / renewal needed now
Asset Condition Scale (1-4)
Asset Condition
2 3 4 1 Poor Functional Good
Average reported condition Variance in asset condition reporting of the same assets by different assessors results in variance in requests for maintenance/ renewal. Ultimately this may result in under-maintaining some sections of the infrastructure while over-maintaining others.
Yardstick Method Minimising variation in asset evaluation and requests for maintenance activities
The implementation of the yardstick method helps to reduce the variance (measured as standard deviation) in asset condition reporting by different assessors. This makes it possible to make better informed prioritization decisions regarding where and how to maintain and renew the asset infrastructure.
Implementing yardsticks in Asset evaluation Asset condition reporting Asset Maintenance Requests
Good
Good
Functional
No maintenance/renewal needed
No maintenance/renewal needed
Maintenance/renewal needed by date/year
Reduced variance (standard deviation)
Asset Condition Scale (1-4)
Asset Condition Poor Functional Good
3 2 1 4
Average reported condition
Agenda
• Rail Net Denmark (Banedanmark) – Key Figures • Implementing The Asset Management Process • Day to Day Maintenance
– work smarter, not harder • Long-term Maintenance and Renewal
– The Track Analysis Model • Sum up
Introduction – The Track Analysis Model
The Model Rail Net Denmark has developed a LCC model to support decisions and establish a forecast on track renewal
Origin The model is developed by Prognoz (IT platform) and Civity (conceptual input). Consultants selected through European tender process
Model input • Data on asset components (as in SAP PM) • Traffic data • Prices from more than 120 renewal projects • Prices from last years maintenance activities
Model output • Reinvestment plan for up to 60 years • Economic needs for maintenance in the same period • Consequences on traffic performance
Mapping
Models of deterioration
Activities
Optimisation and prioritisation
DATA INPUT
Geographic location
Deterioration
Maintenance and renewal
Economic optimisation and prioritisation
Asset data
Traffic data
Output
Cost levels
Model structure
Mapping
Rail Detail (rail, sleeper and ballast)
Point Detail (switches and crossings)
Rail Wear (measuring wagons)
Geometrical Track Quality (measuring wagons)
Route Section (single equipment location)
Line Section (administrative units)
Traffic data (time table related units)
Cost data (administrative units)
Mapping
Input data for modelling
Information about the tracks (SAP PM)
Other sources
Deterioration
17 variations of rail service life: • Rails (8) • Sleepers (4) • Ballast (1) • Switches (4)
The service life is as recommended by the UIC with minor adjustments to the Danish conditions
-
200
400
600
800
1.000
1.200
1.400
0 5 10 15 20 25 30 35 40 45 50 55 60
Cumulative Equivalent Mill. Gross Tonnes (cemgt)
Equivalent Mill. Gross Tonnes (emgt)
Rail service life for rails of the type UIC60
Line section 10 ("Kystbanen")
Technical rail service life: 62,5 år
19
Maintenance and renewal
In case of postponed renewal: • Increased maintenance costs • Increased renewal costs • Risk of temporary speed reductions (traffic hindrance costs)
Costs
Optimal time of renewal
Costs
LifetimeOptimal time of renewal
Renewal costs
Maintenance costs
Postponed time of renewal
Postponed renewal Costs
LifetimeTime of investment/reinvestment
Optimal time of investment/reinvestment
The Bath tub-model
Maintenance is executed in order to secure the full lifetime of the assets Description of the maintenance - by the ’bath tub-model’
20
Activities modelled
Renewal activities
Renewal of rails
Renewal of sleepers
Renewal of ballast
Renewal of rails and sleepers
Renewal of rails, ballast, drain, and subgrade
Renewal of sleepers, ballast, drain, and subgrade
Renewal of rails, sleepers, ballast, drain, and subgrade
Renewal of switches
Renewal of ballast, drain, and subgrade
Renewal of rails, ballast, and subgrade
Renewal of sleepers, ballast, and subgrade
Renewal of rails, sleepers, ballast, and subgrade
Renewal of ballast, and drain
Renewal of rails, ballast, and drain
Renewal of sleepers, ballast, and drain
Renewal of rails, sleepers, ballast, and drain
Maintenance activities
Rail grinding
Tamping
Condition based maintenance activities
Norm based maintenance activities
21
Economic optimisation and prioritisation
• Bundling of renewal activities
• Increasing condition based maintenance costs
for track components used after exceeded
service life
• Increasing socio-economic costs caused by
temporary speed reduction in the track due to
using components after exceeded service life
• Penalty for renewal of components before
reached end of life
22
Short-term and long-term planning
• The markings with LCC Tracks- and Bridges (gray boxes) indicates the optimal time for renewal
• The marking with Tracks/Bridges (blue box) indicates the suggested renewal
• Markings with Out of time and Signalling Programme are periods where renewal is not possible
Year 2013 2014 2015 2016 2017 2018 2019 2020 202111bHøje Taastrup -‐ Roskilde
RenewalRenewalOut of Time
Tracks / BridgesLCC Bridges
LCC Tracks
Signalling Programme
Example: Line section Høje Taastup – Roskilde.
The Track Analysis Model – use and development
Results used for political decision on funding
for the period 2015-2020, and as input for
the renewal plan (every 3-year).
With the renewal plan on track (and bridges)
we can plan other activities in the same
closures.
Complete overview of all master data on all pieces of equipment
Unified reporting and prioritisation
LCC model on long-term investments
Sum up
Thank you for your attention