TPS Civil Engineering Plan TPS Civil Engineering Plan Item Completed Schedule 1. Select Architect Fi rm 2007 Quarter 4 (Completed) 2. Planning and Design 2009 Quarter 3 (Completed) 3. Tender Notices 2009 Quarter 4 4. Under Construction 2011 Quarter 3 5. Construction for In terior and Utilities 2012 Quarter 2 6. Completed 2012 Quarter 3 TPS Civil Engineering Target in 2009 Item Time Start End 1. Construction License Appli cation 1.5 month May 15 June 30 (It’s completed on June 9.) 2. Detailed Desig n .3 month May 1 Aug. 31 3. Tender Notice f or Civil Construct 1.5 month Sept. 18 Nov. 9 4. Tender Notice f or Utilities 1.5 month Sept. 25 Nov. 16 TPS Total Area Building Area (m 2 ) 1. Storage Ring 35,053 2. Administration and Operation Cent er 2,908 3. Academic Activi ty Center 11,225 (Floor 1 to 3) 4. Utility Buildin g Phase-III 3,572 5. Surrounding Fac ilities 242 Total 53,000 TPS Administration and Operation Center & Academic Activity Center TPS project is one of the major science and technology initiatives in Taiwan as well as a significant project of NSRRC. The project includes both th e civil engineering and the construction of the accelerator. The TPS project anticipates to complete the core buildings of the TPS in 4.5 years, including 2 years of planning and designing and 2.5 years of civ il construction, with NT$2.78 billions. Currently, the plan includes the stora ge ring, the administration and operation center, the academic activity center, the utility building Phase-III, and surrounding facilities. We have overcome the limitations of the current site and came up with a construction plan of a 3 GeV machine of 24 straight sections with circumference of 518 m. At this mom ent, the design of the accelerator has been accomplished and we are moving int o the procurement, installation, and testing of the major systems. Currently, the TPS project is heading into a new era. We envision the ground breaking of the TPS project in the near future and we sincerely invite all of you to join us to witness this great and significant moment. TPS Construction Area

TPS – Civil Engineering Plan

Embed Size (px)

DESCRIPTION

★. TPS – Civil Engineering Plan. TPS project is one of the major science and technology initiatives in Taiwan as well as a significant project of NSRRC. The project includes both the civil engineering and the construction of the accelerator. - PowerPoint PPT Presentation

Citation preview

Page 1: TPS  –  Civil Engineering Plan

TPS – Civil Engineering Plan

TPS Civil Engineering Plan

Item Completed Schedule

1. Select Architect Firm 2007 Quarter 4 (Completed)

2. Planning and Design 2009 Quarter 3 (Completed)

3. Tender Notices 2009 Quarter 4

4. Under Construction 2011 Quarter 3

5. Construction for Interior and Utilities

2012 Quarter 2

6. Completed 2012 Quarter 3TPS Civil Engineering Target in 2009

Item

Time Start End

1. Construction License Application

1.5 month May 15June 30

(It’s completed on June 9.)

2. Detailed Design .3 month May 1 Aug. 31

3. Tender Notice for Civil Construction

1.5 month Sept. 18 Nov. 9

4. Tender Notice for Utilities

1.5 month Sept. 25 Nov. 16

TPS Total Area

Building Area (m2)

1. Storage Ring 35,053

2. Administration and Operation Center

2,908

3. Academic Activity Center

11,225(Floor 1 to 3)

4. Utility Building Phase-III 3,572

5. Surrounding Facilities 242

Total 53,000

TPSAdministration and Operation Center & Academic Activity Center

TPS project is one of the major science and technology initiatives in Taiwan as well as a significant project of NSRRC. The project includes both the civil engineering and the construction of the accelerator.

The TPS project anticipates to complete the core buildings of the TPS in 4.5 years, including 2 years of planning and designing and 2.5 years of civil construction, with NT$2.78 billions. Currently, the plan includes the storage ring, the administration and operation center, the academic activity center, the utility building Phase-III, and surrounding facilities. We have overcome the limitations of the current site and came up with a construction plan of a 3 GeV machine of 24 straight sections with circumference of 518 m. At this moment, the design of the accelerator has been accomplished and we are moving into the procurement, installation, and testing of the major systems.

Currently, the TPS project is heading into a new era. We envision the ground breaking of the TPS project in the near future and we sincerely invite all of you to join us to witness this great and significant moment.

TPS Construction Area