Town of Harvard, Massachusetts
Municipal Building Committee
Cost Estimating Report and Cost Benchmarking ReportJanuary 30, 2011
Daniel Tavares, AIA Senior Project Manager Skanska USA Building Inc.
253 Summer Street Boston, MA 02210
Phone: 617-574-1484 Email: [email protected]
January 30, 2011 Mr. C. Ronald Ostberg, Chair Harvard Municipal Building Committee 13 Ayer Road Harvard, MA 01451 Re: Final Conceptual Cost Estimating and Cost Benchmarking Reports Dear Ron, Thank you for retaining Skanska to provide cost estimating and cost benchmarking services in support of the Municipal Building Committee’s evaluation of the cost and feasibility of constructing improvements to Hildreth House, the Old Hapgood Library, and the Town Hall. We have enjoyed working with you and are pleased to enclose herewith the final cost estimate and benchmarking report that we have developed based upon months of discussions and meetings and based upon drawings and reports prepared by other consultants. We trust that the enclosed information and the services provided meet your expectations. We appreciate the opportunity to serve the Harvard Municipal Building Committee. Although the delivery of these materials signals the conclusion of our services for this phase of your project, we hope that you will not hesitate to contact us for any reason as the Municipal Building Committee continues forward with its work. Thank you once again. Very sincerely,
Daniel Tavares, AIA Senior Project Manager
Table of ContentsSection 1.0 Executive Summary Section 2.0 Cost Benchmarking Report 2.1 Introduction 2.2 Purpose 2.3 Benchmarking Methodology 2.4 Comparative Project Analysis 2.4.1 Needham Town Hall Renovation & Addition 2.4.2 Sandwich Town Hall Renovation 2.4.3 Upton Town Hall, Proposed Renovation 2.4.4 Westford Town Hall Renovation/Addition 2.4.5 Harvard Public Library Renovation/Addition 2.4.6 Congregational Church Annex Addition 2.4.7 Unitarian Universalist Church, New Fellowship Building 2.5 Soft Costs 2.6 Findings
Section 3.0 Cost Estimating Report 3.1 Overview 3.2 General Terms and Conditions 3.3 Narrative Descriptions of Schemes 3.3.1 Town Hall - Scheme One (3-Phase Construction Approach) 3.3.2 Town Hall - Scheme Two (2-Phase Construction Approach) 3.3.3 Town Hall - Scheme Three (1-Phase Construction Approach) 3.3.4 Hildreth House 3.3.5 Old Library 3.4 Estimate Summaries 3.4.1 Grand Summary 3.4.2 Town Hall Summary 3.4.3 Hildreth House Summary 3.4.4 Old Library Summary 3.4.5 Town Hall - Scheme One (3-Phase Construction Approach) 3.4.6 Town Hall - Scheme Two (2-Phase Construction Approach) 3.4.7 Town Hall - Scheme Three (1-Phase Construction Approach) 3.4.8 Hildreth House 3.4.9 Old Library 3.5 Estimate Detail
Town of Harvard - Municipal Building Committee1..0 Executive SummaryPage 1
1.0 Executive Summary
Th e Town of Harvard, Massachusetts, acting through its Municipal Building Committee, retained Skanska USA Building, Inc. (Skanska) to provide consulting services, the primary focus of which was the development of conceptual cost estimates for a series of proposed improvements to three municipal facilities: the Town Hall, Hildreth House, and the Old Hapgood Library. Skanska also evaluated cost benchmarking data from relevant renovation and renovation/addition projects.
Skanska worked closely with C. Ron Ostberg, Chairman of the Harvard Municipal Building Committee; Douglas Alden Coots, Conceptual Studies Architect; and ARUP USA, Inc., structural, mechanical, electrical and plumbing engineering consultants. Skanska’s team of professionals toured the aforementioned facilities and attended several team coordination and Owner meetings.
Each of the three facilities presented unique challenges and opportunities during the evaluation of various renovation, restoration, and expansion options. Cost estimates were individually prepared for each facility and were based on specifi c needs, alternative use options, and potential phasing requirements. Skanska also explored costs related to upgrading energy performance in each facility in order to comply with applicable building codes.
It should be noted that the drawings used as the basis of the cost estimates were conceptual in nature, as were written narratives and reports describing preferred systems and equipment for each building option. Th e level of design documentation needed to determine costs to a high degree of accuracy and specifi city has not yet been developed. As a result, estimates prepared at this early stage of project development are not defi nitive predictors of cost; they are, however, useful in that they enable a reasonable understanding of order of magnitude costs.
Th e benchmarking exercise came with its own challenges, owing to the limited number of recent comparable and relevant projects. As explained in greater detail within the narrative section of the Cost Benchmarking Report, the purpose of conducting a cost benchmark report is primarily to determine the cost range for constructing a specifi c building type and, in doing so, validate cost estimates. However, this purpose of this exercise is somewhat altered and includes challenging the relevance of unit costs, encouraging the development of risk management strategies, and increasing the productivity of discussions and public discourse.
In closing, the information provided in this report was prepared to the best of our ability by professionals with in-depth experience and expertise in the construction industry. We trust that this report will serve the Town of Harvard well during the process of exploring options with these municipal facilities.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 1
2.0 Cost Benchmarking Report
2.1 IntroductionSkanska prepared conceptual estimates for the Town of Harvard as part of the Town’sMunicipal Building Study. Th e Study consists of an evaluation of potential options forrenovating and/or expanding three buildings central to the Town’s life and identity, namelythe Town Hall, the Old Library, and Hildreth House.
Th e Town also requested that Skanska gather and evaluate a) construction cost benchmarking data from current and recent renovation and renovation/addition projects involving buildings similar inscale, vintage, and use to these three facilities and b) information related to soft costs. (Please refer to defi nition of soft costs in Section 3.2). Th is report presents the fi ndings of Skanska’s benchmarking activities.
2.2 PurposeTh e purpose of engaging in cost benchmarking is primarily to determine the cost range forconstructing a given building type and, in so doing, to validate cost estimates. However, for a public-sector renovation of and addition to an historic structure, the purpose of cost benchmarking is somewhat altered. In the case of the Town of Harvard, the purpose of cost benchmarking includes budget validation but also expands to include challenging the relevance of unit costs, encouraging the development of risk management strategies, and increasing the productivity of committee discussions and public meetings.
Challenging the Relevance of Unit CostsWhen a benchmarking analysis focuses on a buildings type with a straightforward program that is repeated with only moderate variation from project to project, e.g., new, speculative, suburban offi ce buildings, cost benchmarking serves as a reasonable means of budget validation. In such cases, assuming that appropriate normalization and adjustment has occurred, unit costs, i.e., dollars per gross square feet or $/GSF, trend in an orderly fashion along a continuum of projects that range from high to low design complexity.
In such instances, unit costs associated with various projects have direct relevance to the budgeting discussion almost without qualifi cation. In the case of renovation or renovation/addition projects involving older structures, project scopes are narrowly tailored to address the code, infrastructure, and functional defi ciencies unique to one specifi c building, and the nature of the renovation and type of addition varies signifi cantly from project to project. Because of this, $/GSF costs gathered from various projects while still generally informative, will not trend in an orderly fashion and can potentially be misleading as to potential cost.
Th us, within a set of new construction projects with straightforward programs, $/GSF cost fi gures are orderly; $/GSF cost fi gures within a set of renovation or renovation/addition projects are not.
For the Town of Harvard, $/GSF fi gures obtained through benchmarking still have substantial value. In terms of broad orders of magnitude, they indicate general cost ranges for similar projects, but the Town is nonetheless advised against relying on these fi gures as absolute predictors of cost.
Bringing this to the attention of the Town is among the primary purposes of this report.
Encouraging the Development of Risk Management StrategiesAnother important purpose of benchmarking in the current context is to provide project stakeholders throughout the Town with an early indication of cost risks and, by extension, political
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 2
risks. Th e scope and, therefore cost, of the Town’s projects may evolve between the present and when drawings are put out to bid; the construction marketplace may change between the present and when bids are awarded; and unforeseen conditions may increase costs even aft er bids are awarded. Benchmarking not only exposes these risks, it alerts project stakeholders to the need to mitigate risks by conducting parallel estimates at various stages of the project, by carrying appropriate contingencies, and by modeling various escalation scenarios. It also points to the importance of being cautious about publicizing cost projections before all possible means of due diligence have been exhausted.
Increasing the Productivity of Committee Discussions and Public MeetingsA common occurrence in multiple-stakeholder projects, such as the Town of Harvard’s, is that project participants enter into the budgeting discussion with a diversity of skills, backgrounds, biases, and interests. Even committee members who possess in-depth experience with capital projects may lack all of the information required to judge the accuracy of cost projections or understand cost drivers and cost risks. By presenting data for various projects in a consistent format, benchmarking creates a framework for discussion and decision making. Th e result is that project stakeholders, regardless of technical background, can arrive at a common understanding as to the relationship of program to cost and of project type to cost risk. Th e purpose of benchmarking in creating this framework is to increase the productivity of committee discussions and public meetings.
2.3 Benchmarking MethodologyTh e methodology for this benchmarking study deviates from the standard approach owing to the singular nature of the projects for which estimates are being developed. As discussed in section 2.1 above, there are no direct comparables to the Town of Harvard’s upcoming projects. Other towns in eastern Massachusetts have renovated or renovated and expanded historic town halls, but no town hall in this region is identical to Harvard’s, no renovation program is identical to what Harvard will carry out, and no addition is identical to what will be constructed by the Town.
Standard ApproachIn a standard benchmarking exercise where the goal is validation of early cost fi gures, cost estimates for a proposed project (the “baseline project”) would be compared with fi nal costs of similar projects (“comparison projects”). Ideally this would occur when a relatively-fi xed set of cost, programmatic, and dimensional parameters had been established for the baseline project during, for example, schematic design.
Final construction costs (versus estimates or bid prices) for each comparison project, which would ideally be built by the contractor undertaking the study in order to ensure data integrity, would be adjusted for time and location using a widely-accepted construction cost index (e.g., R.S. Means Historical Cost Index) to reconcile diff erences between the cost structure in various construction markets (both geographic and temporal).
Adjusting costs for time and location is important when comparison projects have been built in markedly diff erent bidding climates (e.g., 1999 versus 2007) and in markedly diff erent construction markets (e.g., suburban Boston versus suburban Atlanta).
By way of explanation, construction infl ation (escalation) ran rampant in the period from 2003 to 2008 but was not as pronounced in 1999. $/GSF costs for a given building type in the same region would be markedly higher in 2007 than in 1999. As far as location is concerned, the northeastern U.S. has far higher labor costs than the southeast. Th us a project built in Boston would have a noticeably higher cost than a similar project built in Atlanta in the same year. Th e confl uence of
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 3
these factors, if not taken into account, can greatly skew results and compromise the validity of the study process.
Th us, normalization and adjustment are required in order to compensate for marked diff erences in both geography and period of construction.
Normalized construction costs would then be divided by the gross square footage of each comparison project, yielding $/GSF costs. A simple bar chart would then express the cost range for the project type in present dollars at the location of the subject project, and the process would be essentially complete. Project stakeholders could then evaluate the relative cost effi ciency of their proposed project against that of completed projects.
Modifi ed ApproachFor this report, several factors necessitate modifi cation of this time-tested methodology. Th ese include: 1) fundamental and irreconcilable diff erences between Harvard’s proposed town hall renovation/addition (the baseline project) and other renovation and renovation/addition projects (comparison projects) and 2) a shortfall of fi nal (versus estimated or bid) cost data.
Th ese complications notwithstanding, Skanska identifi ed a set of recent, comparison projects -- outside of its own portfolio -- for which reasonably credible cost information is available.
Th ese include the following:
1. Needham Town Hall, Renovation & Addition
2. Sandwich Town Hall, Renovation
3. Upton Town Hall, Renovation
4. Westford Town Hall, Renovation/Addition
Skanska researched several additional town hall renovation and renovation/addition projects, including ones in West Tisbury, Lexington, and Sturbridge, but found that either cost or square footage information was either lacking, inconsistent, or insuffi ciently detailed.
In order to broaden the set of comparison projects, Skanska gathered cost data for three recent and capital projects in the Town of Harvard, including:
1. Harvard Public Library, Renovation/Addition
2. Congregational Church, Annex Addition
3. Unitarian Universalist Church, New Fellowship Building
As for normalization and adjustment, none was required, given that these projects are relatively recent and all are located in eastern Massachusetts.
Evaluation of these seven projects yields valuable cost data and insight into the volatility of the current construction marketplace.
2.4 Comparative Projects AnalysisEach comparison project is profi led on subsequent pages.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 4
2.4.1 Needham Town Hall Renovation & Addition
Project DescriptionTh is project consists of the construction of a 13,093 GSF addition to and the renovation of a 20,870 GSF, 1903 structure. Construction began in March 2010; completion is expected in September 2011. Th e expected construction duration is 18 months.
Construction Cost $14,879,750
Unit Costs (per 2010 Conceptual Estimate)$/GSF Consolidated Renovation and Addition: $438 (Includes Direct & Indirect Costs) (For a defi nition of Direct and Indirect Costs, please refer to Section 3.2)
EscalationEscalation is calculated to the mid point of construction (Q4 2010) at 6% per annum compounded.
ContingenciesDesign: 13% (13% of the sum of Direct Costs, General Requirements, and Escalation. Please refer to ensuing page)
Construction: Please refer to fi gure on ensuring page.
Observations and Qualifi cationsTh is Town Hall diff ers from Harvard’s in that it has a masonry façade and a higher level of ornamentation. As such, the $438/GSF unit cost is likely to exceed in present (i.e., 2010) dollars the amount required to renovate and expand Harvard’s Town Hall. Cost fi gures for this project are based upon a conceptual estimate; fi nal pricing will be available upon project completion. Th e project will not be completed until September 2011, and all costs stated herein are subject to change. It is important to note that the conceptual estimate for this project was not prepared by Skanska. Skanska is in no way responsible for the accuracy of this estimate and makes no representation as to its predictive value for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 5
Town of Needham, MassachusettsNeedham Town Hall Renovation & Addition
Estimate Date 22-Jul-08Estimate Type ConceptualEstimate Title Conceptual Cost Estimate - Alternate #4Source Town of Needham WebsiteOriginally Constructed 1903Original GSF 20,870Addition GSF 33,963Construction Start Mar-10Construction Completion Sep-11Duration (Months) 18
ConsolidatedGross Floor Area (in square feet) 33,963
Cost Unit CostFoundations $218,788 $6.44Superstructure $752,959 $22.17Exterior Enclosure $1,315,573 $38.74Roofing $670,200 $19.73Interior Construction $375,089 $11.04Stairs $222,310 $6.55Interior Finishes $397,747 $11.71Conveying Systems $128,131 $3.77Plumbing $192,760 $5.68Heating, Ventilating and Air Conditioning $967,027 $28.47Fire Protection Systems $169,815 $5.00Electrical Systems $707,593 $20.83Equipment $54,833 $1.61Furnishings $96,573 $2.84Special Construction and Demolition $2,395,012 $70.52
Subtotal: Building Costs $8,664,410 $255.11
Building Sitework $767,324 $22.59
Subtotal: Direct Costs $9,431,734 $277.71
General Requirements $1,131,808 $33.32Escalation to const. mid-point 4Q 2010* $2,017,636 $59.41Design Contingency** $1,635,553 $48.16Construction Contingency $663,019 $19.52
Total Construction Cost $14,879,750 $438.12
**Design Contingency: 13% (of Direct Costs, General Req's, and Escalation)
*Escalation is included to the mid point of construction (4Q 2010) at 6% per annum compounded.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 6
2.4.2 Sandwich Town Hall Renovation
Project DescriptionTh is project consists of the renovation of a 7,075 GSF structure originally constructed in 1834. Construction lasted 15 months, beginning in July 2009 and ending in October 2010.
Construction Cost $2,321,721
Unit Cost (per 2009 Schematic Estimate)$/GSF Renovation: $328 (Includes Direct & Indirect Costs)
EscalationEscalation is calculated to the mid point of construction (Q4 2009) at 3%.
ContingenciesDesign: 15% (15% of the sum of Direct Costs, General Requirements, and Escalation. Please refer to ensuing page.)
Construction: 8% (8% of the sum of the above plus the design contingency.)
Observations and Qualifi cationsTh e Sandwich Town Hall is similar to Harvard’s in certain respects. It is comparable in size, structure (wood-frame), cladding (wood), and level of ornamentation. It is also roughly comparable in age. Th e $328/GSF unit cost shown above is of interest because it was calculated in the current (post 2008) bid climate.
Readers should note that this project consists of a renovation only. It is also noteworthy that the design contingency in this schematic estimate (15%) is roughly comparable to the 13% shown in the Needham Town Hall Renovation and Addition. Th e construction contingency of 8% is higher than the renovation construction contingency in the Needham estimate (4%). Th e escalation assumption (3%) is also markedly lower than that shown in the Needham estimate (6%), presumably refl ecting changes in market conditions.
Cost fi gures for this project are based upon a schematic estimate, not on bid prices or fi nal costs. Th e actual cost of this project will not be available until the project is closed out. All costs stated herein are, therefore, subject to change. It is important to note that the schematic estimate for this project was not prepared by Skanska. Skanska is in no way responsible for the accuracy of this estimate and makes no representation as to its predictive value for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 7
Town of Sandwich, Massachusetts Sandwich Town Hall Renovation
Estimate Date 12-Jan-09Estimate Type SchematicEstimate Title SD Cost Estimate, Update #1 : SummarySource Board of Selectmen Meeting Agenda 2/26/09Originally Constructed 1834Original GSF 7,075Addition GSF 0Construction Start Jul-09Construction Completion Oct-10Duration (Months) 15
RenovationGross Floor Area (in square feet) 7,075
Cost Unit CostDemolition/Alteration $58,538 $8.27Substructure $0 $0.00Superstructure $218,120 $30.83Stairs $16,410 $2.32Roof Finish $37,947 $5.36Exterior Walls $26,911 $3.80Exterior Windows and Doors $24,440 $3.45Interior Walls $54,428 $7.69Interior Windows and Doors $89,876 $12.70Finishes $156,442 $22.11Specialties $11,710 $1.66Equipment $1,200 $0.17Furnishings $6,605 $0.93Special Construction $0 $0.00Conveying Systems $116,259 $16.43Plumbing $61,575 $8.70Fire Protection $102,598 $14.50HVAC $359,922 $50.87Electrical $182,689 $25.82
Subtotal: Building Costs $1,525,670 $215.64
Site Work/Site Utilities $38,894 $5.50
Subtotal: Direct Costs $1,564,564 $221.14
General Requirements $250,330 $35.38Escalation to mid point of construction 4Q 2009* $54,447 $7.70Design Contingency** $280,401 $39.63Construction Contingency*** $171,979 $24.31
Total Construction Cost $2,321,721 $328.16
**Design Contingency: 15%
***Construction Contingency: 8%
*Escalation to midpoint of construction (4Q 2009) at 3%.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 8
2.4.3 Upton Town Hall, Proposed Renovation
Project DescriptionTh is project consists of the proposed renovation of an 18,000 GSF structure originally constructed in 1884. Th e project has yet to be funded, and it is not known when construction will take place.
Costs:
Total Project Cost $6,032,000 Design Services $720,000 Moving $180,000 Loose Furniture, Fittings, & Equipment $150,000
Construction Direct Costs $4,982,000 Indirect Costs Not Available Total Not Available
Unit Cost (per 2009 Budget)$/GSF Renovation: $277 (Direct Costs Only)
Escalation & Contingencies Not Indicated
Observations and Qualifi cationsEven though Upton Town Hall’s proposed renovation is only in the budgeting stage and consists only of a renovation, the budget is of interest as much for what it includes as for what it does not. For instance, estimates of the total project cost are included. At $6,032,000, however, projections of total project costs are 1.21 times direct costs, raising the issue of cost risk. Th is ratio is modest in comparison with a more conservative range of 1.25 to 1.35. Th e $277/GSF unit cost, moreover, includes direct costs only, i.e., costs associated with renovating the structure exclusive of contractor fees, general requirements, escalation, and design and construction contingencies. A potentially-ambitious project cost ratio is, therefore, being applied to an incomplete construction cost fi gure. Th e Town of Harvard should view the $277/GSF fi gure and the $6 million total project budget with these qualifi cations in mind.
Th e budget was developed in 2009 in the current bid climate, but it is not known what level of design provides the basis this budget. It is certain that these fi gures are not based upon bid prices or fi nal costs. All costs stated above, both project and direct costs are, as a result, subject to change.
It is important to note that the budget for this project was not prepared by Skanska. Skanska is in no way responsible for the accuracy of this budget and makes no representation as to its predictive value for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 9
Town of Upton, Massachusetts Upton Town Hall Rehabilitation
Estimate Date 24-Sep-08Estimate Type BudgetEstimate Title Budget for Application for CPC*Source Town of Upton WebsiteOriginally Constructed 1884Original GSF 18,000Addition GSF 0Construction Start Awaiting Approval to ProceedConstruction Completion Not ApplicableDuration (Months) Not Available
ExistingGross Floor Area (in square feet) 18,000
Unit CostDIVISION 1 - GENERAL REQUIREMENTS $400,000 $22.22DIVISION 2 - SITEWORK $35,000 $1.94DIVISION 3 - CONCRETE $40,000 $2.22DIVISION 4 - MASONRY $350,000 $19.44DIVISION 5 - METALS $120,000 $6.67DIVISION 6 - WOOD AND P LASTICS $190,000 $10.56DIVISION 7 - THERMAL AND MOISTURE PROTECTION $86,000 $4.78DIVISION 8 - DOORS & WINDOWS $210,000 $11.67DIVISION 9 - FINISHES $1,200,000 $66.67DIVISION 10 - SPECIALTIES $144,000 $8.00DIVISION 11 - EQUIPMENT $0 $0.00DIVISION 12 - FURNISHINGS $82,000 $4.56DIVISION 13 - SPECIAL CONSTRUCTION $0 $0.00DIVISION 14 - CONVEYING SYSTEMS $185,000 $10.28DIVISION 15 - MECHANICAL $960,000 $53.33DIVISION 16 - ELECTRICAL $980,000 $54.44
Subtotal: Building Costs $4,982,000 $276.78
Site Work/Site Utilities Incl. Above $0.00
Subtotal: Direct Costs $4,982,000 $276.78
General Requirements Not Provided Not AvailableEscalation to mid point of construction 1Q2010 Not Provided Not AvailableDesign Contingency Not Provided Not AvailableConstruction Contingency Not Provided Not Available
Total Construction Cost Not Available Not Available
*Community Preservation Funding (CPC Application Town Hall Rev4.doc)
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 10
2.4.4 Westford Town Hall Renovation/Addition
Project DescriptionTh is project consists of the construction of a 4,200 GSF addition to and the renovation of a 7,528 GSF structure built in 1872. Construction began in November 2009 and ended in September 2010. Th e construction duration was 10 months.
Construction Cost Estimated: $3,545,367Actual $2,700,000 (approximate)
Unit Cost (per 2009 Design Development Estimate)$/GSF Consolidated (Renovation and Addition): $302 (Includes Direct & Indirect Costs)$/GSF Renovation: $196 (Direct Costs Only)$/GSF Addition: $253 (Direct Costs Only, Excludes Site Costs )
Escalation (per same)Escalation was calculated to the mid point of construction (Q1 2010). Th e rate of escalation was not indicated in the design development estimate.
Contingencies (per same) Design 6% of Total Direct CostsConstruction: 9.43% of Total Direct Costs
Observations and Qualifi cationsTh is project is one of the most relevant of all of those evaluated. Not only is this building similar in age, size, structure type, cladding, and level of ornamentation, it is the only town hall project referenced in this report for which fi nal pricing is available. To that point, through a discussion with the general contractor for this project, it was learned that the fi nal construction cost was $2.7 million, 24% lower than the $3.5 million that was projected in the May 2009 design development estimate. Actual construction costs were, as a result, $230/GSF. Th is provides evidence of the volatility that characterizes the current construction market, in which bid pricing and fi nal costs are coming in well below estimates. It would be an error, however, to assume that the “discounts” available in today’s construction market will be available when Harvard’s projects go out to bid. Two footnotes regarding this project are 1) that the building was condemned in 2007 due to concerns as to its structural integrity and 2) it has a relatively low site work/site utility cost.
It is important to note that the design development estimate for this project was not prepared by Skanska, and the $2.7 million fi nal construction cost fi gure was obtained through discussions with the general contractor for this project. Skanska makes no representation as to the predictive value for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 11
Town of Westford, MassachusettsWestford Town Hall, Renovations and Addition
Estimate Date 6-May-09Estimate Type Design DevelopmentEstimate Title DD Cost Estimate, Update #1 : SummarySource Town of WestfordOriginally Constructed 1872Original GSF 7,528Addition GSF 4,200Construction Start Nov-09Construction Completion 10-SepDuration (Months) 10
Consolidated Addition RenovationGross Floor Area (in square feet) 11,728 4,200 7,528
Unit Cost Unit Cost Unit CostDemolition/Alteration $145,341 $12.39 8,340 $1.99 137,001 $18.20Excavation, Etc. $32,490 $2.77 26,665 $6.35 5,825 $0.77Concrete $123,970 $10.57 111,932 $26.65 12,039 $1.60Masonry $36,340 $3.10 36,340 $8.65 0 $0.00Metals $32,039 $2.73 11,617 $2.77 20,422 $2.71Wood & Plastic $354,582 $30.23 154,261 $36.73 200,321 $26.61Thermal & Moisture Protection $148,873 $12.69 79,487 $18.93 69,386 $9.22Doors & Windows $204,384 $17.43 58,384 $13.90 146,000 $19.39Finishes $310,424 $26.47 108,260 $25.78 202,164 $26.85Specialties $34,055 $2.90 12,795 $3.05 21,260 $2.82Equipment $0 $0.00 0 $0.00 0 $0.00Furnishings $82,678 $7.05 10,365 $2.47 72,313 $9.61Special Construction $40,370 $3.44 40,370 $9.61 0 $0.00Conveying Systems $98,146 $8.37 98,146 $23.37 0 $0.00Plumbing $65,323 $5.57 18,663 $4.44 46,659 $6.20Fire Protection $139,901 $11.93 40,461 $9.63 99,440 $13.21HVAC $472,811 $40.31 169,322 $40.31 303,489 $40.31Electrical $223,864 $19.09 80,169 $19.09 143,695 $19.09
Subtotal: Building Costs $2,545,591 $217.05 $1,065,577 $253.71 $1,480,014 $196.60
Site Work/Site Utilities $76,200 $6.50
Subtotal: Direct Costs $2,621,791 $223.55
General Requirements $450,060 $38.37Escalation to mid point of construction 1Q20 $69,117 $5.89Design Contingency $157,048 $13.39Construction Contingency $247,351 $21.09
Total Construction Cost $3,545,367 $302.30
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 12
2.4.5 Harvard Public Library Renovation/Addition
Project DescriptionTh is project consists of the construction of a 13,662 SF addition to and renovation of an 8,132 SF, 1877 building that was originally constructed as a school. Th e 17-month construction process began in November 2005 and ended in April 2007. Th e project was put out to bid in September 2005.
Construction Cost $6,400,000 Unit Cost$/GSF Consolidated (Renovation and Addition): $294 (Includes Direct & Indirect Costs)
Escalation Not Indicated
Contingencies Not Indicated
Observations and Qualifi cationsTh is is an aesthetically- and functionally-impressive project that came in on or near budget and on schedule. According to a member of the Library Building Committee, the conceptual estimate for this project was $6.2 million. Th e 75% Construction Documents Cost Estimate provided to Skanska indicates a total construction cost of $5,946,126. Skanska was then provided with a fi nal construction cost fi gure of $6,400,000 by the same member of the Library Building Committee.
Even though it involves the renovation of and addition to a building that is substantially diff erent than Town Hall in terms of materials and massing, this project does provide a useful cost benchmark in that the project was constructed in the local marketplace. Th is project was completed almost four years prior to the preparation of this report, and ordinarily in such circumstance, the R.S. Means Historical Cost Index would be consulted in order to determine the multiplier for adjusting its costs to present dollars. Given the volatility in the marketplace over the past two to three years, it may be advisable to leave the unit cost to remain unadjusted.
Th e estimate for this project was not prepared by Skanska, and Skanska makes no representation as to its predictive value for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 13
2.4.6 Congregational Church Annex Addition
Project DescriptionTh is project involved upgrading and adding onto a 1960’s church annex building. A budget developed in the summer of 2008 projected a construction cost of $1.8 million. Th e project has since been completed with fi nal construction costs coming in at $1.15 million. Architects fees were approximately $115,000. Th e total project was as a result approximately $1.3 million. Square footage fi gures are not available.
Construction Cost Estimated: $1,800,000 (approximate)Actual: $1,150,000 (approximate) Total Project Cost $1,300,000 (approximate)
Unit Cost Not Available
Escalation Not Available
Contingencies Not Available
Observations and Qualifi cationsDespite the lack of unit cost data, a detailed cost breakdown, or back-up documentation, this project provides a useful “benchmark” because of the 36% diff erence between costs estimated in 2008 and fi nal costs.
Beyond providing further evidence of the volatility in the current construction market, this large diff erence between actual and estimated costs underscores the need to develop strategies for managing cost risks in the Town’s upcoming projects.
Cost data for this project were obtained through a member of the congregation who was actively involved in the project. Skanska makes no representation as to the predictive value of these cost fi gures or diff erences between estimated and actual pricing for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 14
2.4.7 Unitarian Universalist Church, New Fellowship Building
Project DescriptionTh is project involved the construction of a new 6,000 SF fellowship building and a modicum of “remodeling” in an existing building. Th e construction cost was $1,353,000 ($225/GSF). Total project costs were approximately $1.8 million. Construction started in late spring/early summer 2009 and ended in the spring of 2010. Th e entire planning, design, and construction process took eight years. Th e Church is pursuing LEED certifi cation for this project.
Construction Cost $1,353,000 (Includes Direct & Indirect Costs)
Total Project Cost $1,800,000 (approximate)
Unit Cost $225
Escalation Not Available
Contingencies Not Available
Observations and Qualifi cationsDespite the lack of a detailed cost breakdown or back-up documentation, this project provides another useful “benchmark” to the Town because it provides an indication of ratio of total project costs to construction costs. In this instance, the ratio is 1.3, which falls in line with industry averages.
Cost data for this project were obtained through a member of the congregation who was actively involved in the project. Skanska makes no representation as to the predictive value of these cost fi gures or ratios of project to construction costs for the Town of Harvard’s proposed projects.
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 15
2.5 Soft Costs
Skanska reviewed a selected number of projects for which it has served as the Owner’s Project Manager in order to validate assumptions carried in estimates in this report related to soft costs. (Please refer to section 3.2 for the defi nition of soft costs.)
Th e assumption is that on average soft costs will be equivalent to approximately 30 per cent of construction costs. Stated another way, during the early budgeting phase of project development, a factor (multiplier) of approximately 1.3 can be applied to construction costs to determine approximate project costs. Validation of these assumptions was carried out by reviewing Master Project Budgets for the six projects referenced below. In the interest of confi dentiality, actual client names in several instances have been withheld.
Client ProjectTotal Proect
CostConstruction
Cost Soft Costs
Soft Costs as % of
ConsructionCosts
ProjectCost
Multiplier
Independent School 1 New Science Building $10,445,436 $8,089,006 $2,356,430 29% 1.29
Country Club Clubhouse Addition $9,000,000 $6,849,676 $2,150,324 31% 1.31
Independent School 2 Library/ClassroomAddition & Renovations $7,075,345 $5,616,690 $1,458,655 26% 1.26
Attleboro Public Schools
Attleboro High School Roof Replacement $4,649,553 $4,025,463 $624,090 16% 1.16
Independent School 2Adaptive Re-Use of Historic Barn as Arts Center
$1,600,000 $1,163,530 $436,470 38% 1.38
LowellTelecommunications
Interior Office Fitout for Non-Profit Organization $850,000 $539,740 $310,260 57% 1.57
Average: 33% 1.33
Independent School 1New Science BuildingProject Cost: $10,445,436Construction Cost: $8,089,006 Soft Costs: $2,356,430
Country Club Clubhouse Renovation/Addition Project Cost: $9,000,000Construction Cost: $6,849,676 Soft Costs: $2,150,324
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 16
Independent School 2Library/Classroom Renovations & Addition Project Cost: $7,075,345Construction Cost: $5,616,690Soft Costs: $1,458,655
Attleboro Public SchoolsAttleboro High School 300,000 SF Roof Replacement Project Cost:$4,649,553Construction Cost: $4,025,463 Soft Costs: $624,090
Independent School 2Adaptive Re-Use of Historic Barn as Arts CenterProject Cost: $1,600,000Construction Cost: $1,163,530 Soft Costs: $436,470
Lowell Telecommunications (Non-Profi t Organization)8500 SF Interior Fitout (Offi ce Space)Project Cost: $850,000Construction Cost: $539,740 Soft Costs: $310,260
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 17
2.6 Findings
Construction CostsA summary of construction costs fi gures stated in this report is as follows:
Soft CostsAs shown in section 2.5, soft costs are on average equivalent to approximately 30 per cent of construction costs. Th us, during the early phases of project development, multiplying estimated construction costs by a factor of 1.3 will yield an acceptable approximation of total project costs.
Cost PatternsNo clear and consistent unit cost pattern emerges from the above numbers for renovations and renovation/addition projects that relevant to the Municipal Building Study. Th e fact that clear patterns that describe the relationship of program to cost do not emerge is in itself a highly-valuable fi nding.
Th e diffi culty in establishing cost benchmarks for these projects owes not only to their singular nature, but also to the volatility of the current construction market and to the limited utility of unit costs in renovation and renovation/addition projects.
Had this assessment been undertaken prior to the current market downturn, it might have concluded that construction costs for comparable projects ranged from $250 - $350/GSF. Th e post-2008 collapse in bid pricing has dismantled what may have been a more orderly pattern of costs.
$/GSF(Construction Cost)
$438
$328
$276
$302
$230
$294
Not Available
$225Unitarian Universalist Church, New Fellowship Building Actual
Harvard Public Library, Renovation/Addition
Congregational Church, Annex Addition
Actual
Actual Cost 36% Below Estimate
Project Comments
Estimate Only
Estimate Only
Needham Town Hall Renovation & Addition
Sandwich Town Hall, Renovation
Upton Town Hall, Renovation
Westford Town Hall, Renovation/Addition
Direct Costs OnlyBudget Figures Only
$302/GSF - Estimated
$230/GSF - Actual(24% Differential)
Town of Harvard - Municipal Building Committee2..0 Cost Benchmarking Report Page 18
Managing RisksIn conclusion, the benchmarking data provided in this section is of substantial value. It reveals the level of volatility that has characterized the construction market over the past several years and, in so doing, points to the importance of managing cost risks in the Town’s upcoming projects. Section 3.2 (Indirect Costs) describes certain risk mitigation tools available to the Town, such as the inclusion of Project Contingencies, Design Contingencies, Construction Contingencies, and Escalation factors in subsequent estimates.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 1
3.0 Cost Estimating Report
3.1 OverviewTh e estimate for the Town of Harvard, Municipal Buildings Committee encompasses three buildings: the Town Hall, the Hildreth House and the Old Library.
Th e Town Hall estimate is segregated into three “Schemes” based on construction phasing. Scheme 1 is a three phase project; Scheme 2 is a two phase project; and Scheme 3 refl ects the cost if the project is done all at once in a single phase. Each scheme has minor diff erences as a result of the project phasing. Also included in each scheme is “enabling” work which includes the North Road and Parking Lot. Th e cost diff erentials for each scheme are a result of the time required to perform each phase. Th e cost increases as the number of phases increase.
Th e Hildreth House is based on a single scheme with two components. Th e fi rst adds a new entry and parking, along with code and deferred maintenance upgrades; the second adds a new stand-alone structure to act as a multi-purpose space, which would be linked to the existing structure and include a kitchen and toilets.
Th e Old Library is also based on a single scheme with two components. Th e fi rst involves upgrading the entry and accessibility, along with a sprinkler system retrofi t and other code and deferred maintenance upgrades to bring the building up to a usable “shell space”. Th e second is to fi t out the shell space with one of two alternate functions; a Cultural Center (Alternate #1) or for the Council on Aging (Alternate #2). Th ere is also a “Pedestrian Access and Parking Upgrade” alternate, which adds parking spaces and improves the intersections and crosswalks for roads in the vicinity of the Old Library. Th is alternate is optional if the library building is fi t out as a Cultural Center, but is necessary is the fi t out is for the Council on Aging.
All estimates were based on available drawings of the existing buildings (mainly architectural and structural information) and preliminary concept drawings of the proposed renovations and/or additions. Additionally, an engineering report entitled “Building Services Review of Town Hall, Old Library, Hildreth House”, as prepared by ARUP USA, Inc. and dated January 2011, was also used as a basis of the estimates. Other documentation provided by the Town also contributed to the project cost estimates.
Th e estimate was developed using an electronic quantity surveying soft ware called On Screen Takeoff , which enables the estimator to quantify, adjust and track quantities for all aspects of the project. Th e Timberline Precision Estimating System is used as the pricing platform for the estimate, which takes into account material, labor and equipment costs for all aspects of the projects. Since this is a public project, the estimate is based on using prevailing wages for the trades. Th is detail is further summarized on standard spreadsheet formats to best allow the reader to follow the somewhat complicated permutations of the project schemes, phasing and alternates. Th e following will act as a guide to these Summary Sheets.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 2
3.2 General Terms and Defi nitionsTh e estimate for the Town of Harvard, Municipal Buildings Committee is composed of three major cost Groups: Direct Costs, Indirect Costs and Soft costs.
Direct CostsDirect Costs are defi ned as the cost of the construction materials, including fabrication and installation costs that become an integral part of the building and its adjoining site. Another way to look at Direct Cost is the foundations, building walls, roof, fi nishes, plants, doors, windows, mechanical and electrical systems that make a building a building. Th e combined Direct and Indirect Costs are considered the Total Construction Cost.
Indirect CostsIndirect Costs are defi ned as the cost of the temporary requirements that allow a builder to construct a project in a safe, effi cient and cost eff ective manner and are not a part of the building when it is completed. Th ese costs include:
Construction Management Services includes: General Conditions - Salaries for the onsite builders’ representatives (i.e. Superintendent, Project Manager, etc.);
General Requirements - costs for trailers, dumpsters, temporary construction fencing, safety barriers, construction and directional signage and the like;
Preconstruction Services and Misc. Consultants – Estimating, scheduling and consultants used during the preconstruction phase of Private Projects. As this project will be a public lump sum bid, these items are not applicable.
Permits – Th e cost of the Building Permit only. Costs for trade permits, such as plumbing and electrical, are included in the Direct Costs. Other permitting costs that may be associated with the project, such as DEP permits, are considered Soft Costs (See below).
Escalation – the estimate does not include escalation at this time, as this value is highly dependent on the actual planned construction time and market stability. Unfortunately, this value is extremely diffi cult to predict, especially in the current economic climate. However, current predictors are indicating fl at (0 to 1 %) escalation through 2nd Q 2011, followed by normal (3% to 4%) escalation for the next 2 years.
Project Contingency - is included by the Owner in Soft Costs to allow for scope growth, additional user requirements, etc. outside of the control of the builder. In budgeting Soft Costs, MBC has designated 5% of the Construction Cost as a Project Contingency.
Construction Contingency - is available to the Construction Manager to provide funds to address items such as, schedule recovery costs associated with weather, costs associated with subcontractor default, cost increases due to unanticipated local labor and material market conditions, selective overtime, or the like. We have used 5% of Direct Costs in the estimate.
Design/Estimating Contingency - Th e intent of this contingency is to provide for the variation in the cost of labor, material and subcontracts as estimated by Skanska and to accommodate the evolution of the design details within the scope of work to which the project estimate has been based. Th is has not been included at this time due to the preliminary nature of the information provided.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 3
LEED Registration and Certifi cation – Cost for certifying the building with the US Green Build Council, if desired.
Builders Risk Insurance - special property insurance which indemnifi es against damage to buildings while they are under construction. Th is cost is sometimes included in Soft Costs.
C.G.L. Insurance – the constructors’ Comprehensive and General Liability Insurance as required by the Owner.
Subcontractor Bonds – the cost to bond subcontractors for payment to suppliers and performance of the work.
CM Payment and Performance Bond - the cost to bond the builder for payment to suppliers and performance of the work.
Hazardous Materials Abatement – the cost to remove, contain and legally dispose of hazardous materials, including asbestos containing materials (ACM’s), PCB’s, lead paint, contaminated soils, etc. Th is cost is excluded from the estimate pending a HazMat survey.
Construction Management Fee – the fee the builder charges to perform the work. Th e estimate assumes a 2.5% fee.
Soft CostsSoft Costs are defi ned as any cost other than Construction Costs that are borne by the Owner of the project. Th e estimate assumes 15% Soft Costs for stand-alone site work items not associated with building work, and 30% Soft Costs for all building items and associated site work. Th ese costs include: Architectural and Engineering Fees to prepare documentation and oversee the project during construction. Including reimbursable expenses, these fees are approximately 9% of the Project Cost. Approximately 80% of this fee is attributed to the design and bidding phases, with the remainder allocated to the administration of the construction. Th is cost excludes special energy modeling.
Owner’s contingency, commonly referred to as a Project Contingency, usually 5% to 15% of the total Construction Costs; 5% has been used in the MBC calculation;
OPM (Owner’s Project Manager) Fees, a relatively new mandated requirement for Public work exceeding $1.5M and includes the Clerk of the Works
Furniture, Furnishings and Equipment (FF&E) including Tel/data, Security and A/V equipment, signage, movable furniture, window treatments, etc.;
Relocation, storage, moving and leasing costs
Surveys (Hazardous Materials Abatement, Geotechnical, etc.);
Regulatory Permitting and Fees
Commissioning, Preliminary and Enhanced
Legal fees
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 4
3.3 Narrative Descriptions of Schemes
Ensuing pages within this section contain detailed narrative descriptions of the following schemes:
Town Hall - Scheme One (3-Phase Construction Approach)
Town Hall - Scheme Two (2-Phase Construction Approach)
Town Hall - Scheme Th ree (1-Phase Construction Approach)
Hildreth House (Two Components)
Old Library (Two Components)
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 5
3.3.1 Town Hall – Scheme One (3- Phase Construction Approach)
Enabling Work New North Road Construction Th e North Road enabling work includes the installation of a new road, along with site utilities, from the main road to entrance of the Hildreth parking area. Th is road essentially replaces the long driveway to the Hildreth House. Th e primary purpose of the North Road is to provide safe emergency access from the fi re station to Ayer Road and a safe pedestrian zone. Th e current emergency vehicle access will not be available when Phase 2 of the Town Hall construction is underway. Th e North Road will also provide access to the Hildreth House and a public road to a potential new parcel.
New North Parking Lot Th e North Parking Lot enabling work includes the installation of a new parking area with site lighting adjacent to and accessed by the new North Road. Th e primary purpose of the lot is to provide parking to Town Hall and adjoining uses.
Phase I Existing Town Hall Renovation and Elevator Addition Th e Architectural scope of work for the 1st Phase of the Town Hall addresses the structural, accessibility, mechanical and electrical issues outlined in the ARUP narrative, along with a revised layout for the building. Th is work includes:
Constructing a small addition to the southwest corner of the Town Hall to house a new 2 story hydraulic elevator.
Improving handicapped accessibility to the front entrance.
Insulating the exterior walls and replacing the siding
Miscellaneous Structural upgrades per engineering report.
Replacing the existing windows with insulated windows.
Refurbishing the existing entry doors and grand stair.
Replacing the roof, gutters and downspouts.
Renovating the interior offi ce space on 2 fl oors.
Enlarging the existing toilets and installing new fi xtures.
Constructing a new ramp to access the stage.
Upgrading the Mechanical and Electrical equipment and systems per the engineering report.
Installing a new fi re sprinkler system.
Site, Canopy and Utility Upgrades Th e Site Work scope of work for the 1st Phase of the Town Hall addresses the replacement of building services, as outlined in the ARUP narrative, along with installation of a steel framed, fabric canopy between the renovated Town Hall and the existing Old Fire Station.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 6
Phase 2 Town Hall Addition and Misc Renovations Th e Architectural scope of work for the 2nd Phase of the Town Hall is the construction of a new wood and steel framed, two-story structure of approximately 4,000 gross square feet in total area. Th is addition is west of and separated from the existing Town Hall by a courtyard bounded on the north and south sides by glass enclosed connections to the existing building. Th e exterior of the addition will have a sloped shed roof and will be fi nished to compliment the renovated Town Hall. Th e fi rst fl oor of the addition will be fi tout with offi ce space in accordance with the preliminary drawings. Th e second fl oor, including the toilet rooms, will be left as shell space with only a minimum amount of heat and lighting to maintain safety and building systems. Th e entire addition, including the shell space, will have a fi re sprinkler system. Th e building addition will share the elevator installed in Phase 1.
Town Hall Site Work and Elm Street Revisions Th e Site Work scope of work for the 2nd Phase of the Town Hall includes extending Elm Street to the North Road; providing parking spaces on Elm Street; eliminating the existing road south of Town Hall and providing the required site improvements for the renovated Town Hall and Addition. Th is work also includes the demolition of the Old Fire Station and the removal of the fabric canopy installed in Phase 1.
Phase 3 Upper Town Hall Fit-Out Th e Architectural scope of work for the 3rd and fi nal Phase of the Town Hall is the interior renovation of the second fl oor of the Town Hall (previously fi t-out as offi ce space in Phase 1 renovations) and fi nal fi t-out of the Addition second fl oor shell space as support space for upper town hall. Th e second fl oor toilet rooms in the Addition will also be completed during this phase.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 7
3.3.2 Town Hall – Scheme Two (2- Phase Construction Approach)
Enabling Work Th e Enabling work for Scheme 2 is identical to Scheme 1. It should be noted that the North Road must be installed prior to the construction of Phase 1 in this Scheme to provide emergency vehicle access. (Th is diff ers from Scheme 1, where the North Road was not required until Phase 2.)
Phase I Existing Town Hall Renovation and Building Addition Th e Architectural and Site Work scope of work for Phase 1 of this scheme essentially combines the fi rst two phases of the 3-Phase Scheme previously described above. However, some of the work items will be diff erent, or not required in this scheme, as follows:
In lieu of renovating and enlarging the toilet on the fi rst fl oor of the existing Town Hall, the second fl oor toilet room in the addition will be fi t-out in this phase.
Th e fabric canopy to the existing Old Fire Station is not required.
Phase 2 Upper Town Hall Fit-Out Th e scope of work for Phase 2 of this scheme is the same as Scheme 1, except that the second fl oor toilet rooms were already fi t-out in Phase 1 of this scheme, and are no longer included in this Phase.
3.3.3 Town Hall – Scheme Three (1- Phase Construction Approach)
Enabling Work Th e Enabling work for Scheme 3 is identical to Scheme 2. Th e North Road must be installed prior to the building construction to provide emergency vehicle access, as in Scheme 2.
Main Construction Existing Town Hall Renovation, Building Addition and Upper Town Hall Fit-Out Th e Architectural and Site Work scope of work for this scheme essentially combines both phases of the 2-Phase Scheme previously described above. However, the 3rd Phase renovation of the second fl oor of the existing Town Hall is not required.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 8
3.3.4 Hildreth House (Two Components)
Baseline New Entry and Elevator/Code & Deferred Maintenance Upgrades Th e scope of work for the Baseline work on Hildreth House addresses the structural, accessibility, parking, mechanical and electrical issues outlined in the ARUP narrative, along with a revised layout for the building. Th is work includes:
Constructing a small addition to the northwest corner of the existing structure to house a new 3 story hydraulic elevator and egress stair. Th e fi rst fl oor of this addition will provide handicapped accessibility at the parking lot level, which is one fl oor below the existing fi rst fl oor. Th e elevator will serve the fi rst two fl oors of the existing 3-story structure. Th e third fl oor will not be accessible.
Provide a new drop-off canopy structure and vestibule at the new building entry.
Miscellaneous Structural upgrades per engineering report.
Renovating a portion of the interior space on 2 fl oors for elevator/stair access.
Upgrading the Mechanical and Electrical equipment and systems per the engineering report.
Installing a new fi re sprinkler system.
Th e Site Work scope of work for the Baseline addresses the replacement of building services as outlined in the ARUP narrative, along with a new circular drop-off and parking for 34 vehicles, retaining walls to accommodate grade changes, and site improvements such as walks and landscaping adjacent to new construction.
Addition Multi-Purpose Pavilion Addition Th e scope of work for the addition to Hildreth House is a single story wood and steel framed addition designed to complement the existing architecture. Th is addition will be located to the northeast corner of the existing structure and connected to the existing building. Th is addition includes:
A kitchen, including kitchen equipment.
Two toilet rooms
An open, barrier-free multipurpose space.
Future Work During the course of conceptual design, potential future additions and creating gardens to the southeast of the existing building were discussed. However, these potential future projects have not been included in this study.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 9
3.3.5 Old Library (Two Components)
Shell Code & Deferred Maintenance Upgrades Th e scope of work for this component of the work addresses the accessibility, mechanical and electrical issues outlined in the ARUP narrative, along with a revised layout for the building. Th e result of this phase is an unoccupied shell space ready for fi t-out.. Th is work includes:
Constructing a small addition to the south side of the existing structure to house a new 2 story, 3 stop hydraulic elevator and egress stair to replace the existing entryway. Th e middle stop of this elevator will provide handicapped accessibility at the street level, which is 1/2 fl oor below the existing fi rst fl oor and ½ fl oor above the existing basement level. Th e elevator will serve the fi rst two fl oors of the existing 3-story structure. Th e third fl oor will be mechanical space and will not be accessible.
Removing the library stacks and self-supporting mezzanine.
Renovating a portion of the interior space to provide egress stair access per code. Th is work includes removing an existing central stair and infi lling the fl oor openings. Th is work also includes decommissioning an existing elevator and removing an existing stair at the north side of the building, as these do not meet current code requirements. Th e space vacated by their removal will be used to install a new code compliant egress stair.
Upgrading the Mechanical and Electrical equipment and systems per the engineering report.
Installing new toilet rooms at the basement level.
Installing a new fi re sprinkler system.
Fitout Alternate # 1 - Cultural Center Th e scope of work for this Fit-Out of the Old Library accommodates a Cultural Center per the conceptual drawings. Th is fi t-out includes:
Drywall walls and wood doors to create offi ces and meeting rooms.
A folding partition to separate meeting room space
Air Conditioning
Walks, curbing, landscaping and paving along Old Littleton Road and Fairbanks Street adjacent to the Old Library Building. Th is alternate would have parking spaces on Fairbanks Street.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 10
Alternate # 2 - Council on AgingTh e scope of work for this alternate Fit-Out of the Old Library accommodates the Council on Aging per the conceptual drawings. Th is fi t-out includes:
Drywall walls and wood doors to create offi ces and meeting rooms.
A new kitchen, including equipment
Two additional toilet rooms on the upper level.
Air Conditioning
Walks, curbing, landscaping and paving along Old Littleton Road and Fairbanks Street adjacent to the Old Library Building. Th is alternate would have a drop-off on Fairbanks Street with a permanent covered walkway from the drop-off to the building entry.
Pedestrian Access & Parking UpgradePursuant to the conceptual drawings, additional parking, along with improved crosswalks and sidewalks have been added to Mass Ave Rte. 111, Fairbanks Street and Old Littleton Road. A portion of this work adjacent to the Old Library has been included with the alternates, above. However, the majority of this work is taken as a separate scope of work. If Alternate #1 – Cultural Center is accepted, this work may be deferred or done as a separate project without impact on the building scope. However, if Alternate #2 – Council on Aging is accepted, these parking and road upgrades are necessary to provide adequate parking and pedestrian safety to the public using the facility.
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 11
3.4 Estimate Summaries
Ensuing pages contain summary estimates of the following schemes:
Grand Summary
Town Hall Summary
Hildreth House Summary
Old Library Summary
Town Hall - Scheme One (3-Phase Construction Approach)
Town Hall - Scheme Two (2-Phase Construction Approach)
Town Hall - Scheme Th ree (1-Phase Construction Approach)
Hildreth House
Old Library
Town of HarvardMunicipal Buildings Renovations
Enabling Work - North Road and North Parking
Town Hall Renovation / Addition Hildreth House Old Library
Pedestrian Access & Parking Upgrade
Total of All Projects
Baseline Architectural - 1,660,000 810,000 1,090,000 - 3,560,000
Civil (Site) - 80,000 360,000 - - 440,000
Total Construction - 1,740,000 1,170,000 1,090,000 - 4,000,000
Soft Costs - 520,000 350,000 330,000 - 1,200,000
Total Baseline - 2,260,000 1,520,000 1,420,000 - 5,200,000
Proposed Architectural - 2,320,000 1,440,000 1,460,000 - 5,220,000
Civil (Site) 530,000 270,000 360,000 20,000 170,000 1,350,000
Total Construction 530,000 2,590,000 1,800,000 1,480,000 170,000 6,570,000
Soft Costs 80,000 780,000 540,000 440,000 30,000 1,870,000
Total Proposed 610,000 3,370,000 2,340,000 1,920,000 200,000 8,440,000
Full Buildout Architectural - 2,770,000 1,440,000 1,460,000 - 5,670,000
Civil (Site) 530,000 270,000 360,000 20,000 170,000 1,350,000
Total Construction 530,000 3,040,000 1,800,000 1,480,000 170,000 7,020,000
Soft Costs 80,000 910,000 540,000 440,000 30,000 2,000,000
Total Full Buildout 610,000 3,950,000 2,340,000 1,920,000 200,000 9,020,000
January 24, 2011
Grand Summary
Town of HarvardMunicipal Buildings Renovations
Town Hall
Phase 1 Phase 2 Phase 3 Total 3-Phase Scheme Phase 1 Phase 2 Total 2-Phase Scheme Phase 1 Total 1-Phase Scheme
Gross Building Area (sf) 8,000 4,000 ---- 12,000 12,000 ---- 12,000 12,000 12,000
Construction Duration (mo) 8 6 4 18 10 4 14 12 12
Enabling Work
North Road Construction 299,000 299,000 299,000 299,000 299,000 299,000
North Parking Lot 228,000 228,000 228,000 228,000 228,000 228,000
Subtotal Enabling Work - 527,000 - 527,000 527,000 - 527,000 527,000 527,000
Soft Costs
15% Enabling Work - 79,000 - 79,000 79,000 - 79,000 79,000 79,000
Total Enabling Work - 606,000 - 606,000 606,000 - 606,000 606,000 606,000
Architectural
Existing Town Hall Code & Deferred Maintenance Upgrades
1,658,000 1,658,000 1,404,000 1,404,000 2,693,000 2,693,000
Building Addition / Fit-Out 1st Floor 917,000 917,000 917,000 917,000 Included Included
Upper Town Hall Fit-Out 515,000 515,000 451,000 451,000 Included Included
Total Archtectural 1,658,000 917,000 515,000 3,090,000 2,321,000 451,000 2,772,000 2,693,000 2,693,000
Site Work
Code & Deferred Maintenance Utility Upgrades
82,000 82,000 57,000 57,000 270,000 270,000
Elm St. / Town Hall Site 231,000 231,000 213,000 213,000 Included Included
Total Site Work 82,000 231,000 - 313,000 270,000 - 270,000 270,000 270,000
Total Construction 1,740,000 1,148,000 515,000 3,403,000 2,591,000 451,000 3,042,000 2,963,000 2,963,000
Soft Costs
30% Architectural & Site Work 522,000 344,000 155,000 1,021,000 777,000 135,000 913,000 889,000 889,000
Total Town Hall Project 2,262,000 1,492,000 670,000 4,424,000 3,368,000 586,000 3,955,000 3,852,000 3,852,000
Total Enabling & Town Hall 2,262,000 2,098,000 670,000 5,030,000 3,974,000 586,000 4,561,000 4,458,000 4,458,000
Cost Differential 3-Phases to 2-Phases: ($469,000)
Cost Differential 3-Phases to 1-Phase: ($572,000)
Cost Differential 2-Phases to 1-Phase: ($103,000)
3-Phase Scheme 2-Phase Scheme 1-Phase Scheme
January 24, 2011
Town of HarvardMunicipal Buildings Renovations
Hildreth House
New Entry & ElevatorCode & Deferred
Maintenance UpgradesBaseline Subtotal
Building Addition
Proposed Subtotal
Garden Landscaping
Full Buildout
Gross Building Area (sf) 1,800 1,800 2,500 4,300 4,300
Construction Duration (mo) 6 6 6 6 0
Architectural
New Entry Canopy, Elevator, Stair and Lobby
563,000 563,000 563,000 563,000
Code & Deferred Maintenance Upgrades
250,000 250,000 250,000 250,000
New Multi-Purpose Room, Kitchen, Toilets, Link & MEP Systems
- 626,000 626,000 626,000
Total Architectural 563,000 250,000 813,000 626,000 1,439,000 - 1,439,000
Site Work
Demolish Existing Parking Area 28,000 28,000 28,000 28,000
Roads and Parking at New Entry 332,000 332,000 332,000 332,000
Total Site Work 360,000 - 360,000 - 360,000 - 360,000
Total Construction 923,000 250,000 1,173,000 626,000 1,799,000 N/A 1,799,000
Soft Costs
30% Architectural & Site Work 277,000 75,000 352,000 188,000 540,000 540,000
Total Project 1,200,000 325,000 1,525,000 814,000 2,339,000 N/A 2,339,000
January 24, 2011
Town of HarvardMunicipal Buildings Renovations
Old Library
Code & Deferred Maintenance Upgrades
Cultural Center Fit-Out
Total Cultural Center Cost
Code & Deferred Maintenance Upgrades
Council on Aging Fit-Out
Total Council on Aging Cost
Pedestrian Access & Parking Upgrade (1)
Gross Building Area (sf) 6,000 6,000
Construction Duration (mo) 6 6
Architectural
Accessibility and Building Systems Upgrade
1,090,000 1,090,000 1,090,000 1,090,000
Interior Fit-Out 142,000 142,000 142,000 142,000
HVAC Upgrade 225,000 225,000 225,000 225,000
Kitchen and Additional Toilet Premium - 144,000 144,000
Total Architectural 1,090,000 367,000 1,457,000 1090000 511,000 1,601,000 -
Site Work
Site Walks 16,000 16,000 -
Drop-Off Turn Around, Walks & Canopy
- 149,000 149,000
Pedestrian Access & Parking Upgrade - - - 172,000
Total Site Work - 16,000 16,000 0 149,000 149,000 172,000
Total Construction 1,090,000 383,000 1,473,000 1,090,000 660,000 1,750,000 172,000
Soft Costs
15% Enabling Work - - 26,000
30% Architectural & Site Work 327,000 115,000 442,000 327,000 198,000 525,000 -
Total Project 1,417,000 498,000 1,915,000 1,417,000 858,000 2,275,000 198,000
Cost Add for Council on Aging Fit-Out including Pedestrian Access: 558,000
Notes:(1) Pedestrian Access & Parking Upgrade is required for Alternate #2 - Council on Aging.
ound Off -3
Alternate #1 - Cultural Center Alternate #2 - Council on Aging
January 24, 2011
Town of HarvardMunicipal Buildings Renovations
Town Hall 3-Phase SchemeConstruction Costs Summary
TotalDescription North Subtotal Existing Town Hall Canopy & Code Subtotal New Addition & Elm St. & Town Subtotal Upper Town Subtotal Construction
North Road Parking Lot Enabling Renovation Utility Upgrade Cost Renovate Existing Hall Site Work Cost Hall Fit-Out Cost CostGross Building Area ---- ---- 7,850 gsf ---- 7,850 gsf 3,850 gsf ---- 3,850 gsf ---- ---- 11,700 gsfConstruction Duration (Months) 8 6 4 18
Direct Costs
Foundation 0 46,623 46,623 33,476 33,476 0 80,099Basement Construction 0 0 19,200 19,200 0 19,200Superstructure 0 37,209 37,209 73,500 73,500 0 110,709Exterior Closure 0 229,125 229,125 228,583 228,583 0 457,708Roofing 0 49,734 49,734 18,635 18,635 0 68,369Interior Construction 0 93,524 93,524 48,798 48,798 12,720 12,720 155,042Stairs 0 15,000 15,000 20,000 20,000 0 35,000Interior Finishes 0 60,472 60,472 28,144 28,144 32,156 32,156 120,772Conveying (Full Size) 0 100,000 100,000 0 0 100,000Plumbing 0 70,005 70,005 17,742 17,742 48,498 48,498 136,245H.V.A.C. 0 172,300 172,300 79,258 79,258 30,008 30,008 281,566Fire Protection 0 55,890 55,890 14,631 14,631 0 70,521Electrical 0 208,013 208,013 85,592 85,592 76,900 76,900 370,505Equipment 0 0 0 177,566 177,566 177,566Furnishings 0 18,625 18,625 0 0 18,625Demolition 0 59,457 59,457 4,800 4,800 0 64,257Site Preparation 89,100 79,750 168,850 10,000 10,000 64,550 64,550 0 74,550Site Improvements 69,942 82,256 152,198 15,200 15,200 80,305 80,305 0 95,505Site Civil/Mechanical Utilities 69,780 10,080 79,860 9,000 9,000 20,510 20,510 0 29,510Site Electrical Utilities 8,500 8,500 17,000 25,987 25,987 4,250 4,250 0 30,237
Total Construction Cost $237,322 $180,586 $417,908 $1,215,977 $60,187 $1,276,164 $672,359 $169,615 $841,974 $377,848 $377,848 $2,495,986
Indirect Costs
12.0% Construction Management Services (Enabling) 28,479 21,670 50,149 0 0 0 021.0% Construction Management Services (Building) 0 255,355 12,639 267,994 141,195 35,619 176,815 79,348 79,348 524,157
0.0% Preconstruction Services 0 0 0 0 0 0 0 0 0 0 0 00.0% Misc Consultants 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 00.0% Escalation (3rd Qtr 2012 Start) Included with Soft Costs 00.0% Project Contingency Included with Soft Costs 05.0% Construction Contingency 13,990 10,645 24,635 77,439 3,833 81,271 42,819 10,802 53,620 24,063 24,063 158,9550.0% Design/Estimating Contingency Included with Soft Costs 0
0 0 0 0 01.0% Building Permits 2,798 2,129 4,927 16,578 821 17,398 9,167 2,312 11,479 5,151 5,151 34,029
0 00 0 0 0 0
0.015% Builders Risk Insurance 588 447 1,035 4,182 207 4,389 2,312 583 2,896 1,299 1,299 8,5841.25% C.G.L. Insuramce 3,497 2,661 6,159 19,360 958 20,318 10,705 2,700 13,405 6,016 6,016 39,7391.25% Subcontractor Bonds 2,967 2,257 5,224 15,200 752 15,952 8,404 2,120 10,525 4,723 4,723 31,2000.80% CM Payment & Performance Bond 2,317 1,763 4,080 13,262 656 13,919 7,333 1,850 9,183 4,121 4,121 27,223
0 0 0 0 0Hazardous Materials Abatement 0 0 0 0 0 0
0 0 0 0 02.5% Construction Management Fees 7,299 5,554 12,853 40,434 2,001 42,435 22,357 5,640 27,997 12,564 12,564 82,997
Total Indirect Costs $61,934 $47,127 $109,061 $441,809 $21,868 $463,677 $244,292 $61,627 $305,920 $137,286 $137,286 $906,883
Total Construction Cost $299,256 $227,713 $526,969 $1,657,786 $82,055 $1,739,841 $916,651 $231,242 $1,147,894 $515,134 $515,134 $3,402,869
x 0.15 Soft Cost Multiplier 44,888 34,157 79,045 - - - -
x 0.30 Soft Cost Multiplier - $497,336 24,617 521,952 274,995 69,373 344,368 154,540 154,540 1,020,861
Total Project Cost Enabling $606,014 Phase 1 $2,261,793 $1,492,262 Phase 3 $669,674 $4,423,729
$288.13 $387.60 $57.24 $378.10
Phase 3
January 24, 2011
Enabling Phase 2Phase 1
Town of HarvardMunicipal Buildings Renovations
Town Hall 2-Phase SchemeConstruction Costs Summary
TotalTotal Total Construction
Description North Total Existing Town Hall Site & Code Subtotal New Addition Elm St. & Town Subtotal Phase 1 Upper Town Phase 2 CostNorth Road Parking Lot Enabling Renovation Utility Upgrade Cost Hall Site Work Cost Construction Cost Hall Fit-Out Construction Cost 2-Phases
Gross Building Area ---- ---- ---- 7,850 gsf ---- ---- 3,850 gsf ---- ---- 11,700 gsf ---- 11,700 gsf 11,700 gsfConstruction Duration (Months) 10 4 14
Direct Costs
Foundation 0 46,623 46,623 33,476 33,476 80,099 0 80,099Basement Construction 0 0 19,200 19,200 19,200 0 19,200Superstructure 0 37,209 37,209 73,500 73,500 110,709 0 110,709Exterior Closure 0 229,125 229,125 228,583 228,583 457,708 0 457,708Roofing 0 49,734 49,734 18,635 18,635 68,369 0 68,369Interior Construction (1) 0 53,524 53,524 48,798 48,798 102,322 12,720 12,720 115,042Stairs 0 15,000 15,000 20,000 20,000 35,000 0 35,000Interior Finishes 0 60,472 60,472 36,144 36,144 96,616 24,156 24,156 120,772Conveying (Full Size Elevator) 0 100,000 100,000 0 100,000 0 100,000Plumbing (1) 0 10,005 10,005 66,240 66,240 76,245 0 76,245H.V.A.C. 0 172,300 172,300 79,258 79,258 251,558 30,008 30,008 281,566Fire Protection 0 55,890 55,890 14,631 14,631 70,521 0 70,521Electrical 0 208,013 208,013 85,592 85,592 293,605 76,900 76,900 370,505Equipment 0 0 0 0 177,566 177,566 177,566Furnishings 0 18,625 18,625 0 18,625 0 18,625Demolition 0 59,457 59,457 4,800 4,800 64,257 0 64,257Site Preparation 89,100 79,750 168,850 10,000 10,000 64,550 64,550 74,550 0 74,550Site Improvements 69,942 82,256 152,198 0 0 80,305 80,305 80,305 0 80,305Site Civil/Mechanical Utilities 69,780 10,080 79,860 9,000 9,000 20,510 20,510 29,510 0 29,510Site Electrical Utilities 8,500 8,500 17,000 25,987 25,987 4,250 4,250 30,237 0 30,237Combined Phase Savings 0 included 0 0 0 0 0
Total Construction Cost $237,322 $180,586 $417,908 $1,115,977 $44,987 $1,160,964 $728,857 $169,615 $898,472 $2,059,436 $321,350 $321,350 $2,380,786
Indirect Costs
12.0% Enabling/Phase 1 & 2 CM Services 28,479 21,670 50,149 133,917 5,398 139,316 87,463 20,354 107,817 247,132 247,13225.0% Phase 3 CM Services 0 0 0 0 80,338 80,338 80,338
0.0% Preconstruction Services 0 0 0 0 0 0 0 0 0 0 0 0 00.0% Misc Consultants 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 00.0% Escalation (3rd Qtr 2012 Start) 0 Included with Soft Costs 0 0 0 00.0% Project Contingency 0 Included with Soft Costs 0 0 0 05.0% Construction Contingency 13,990 10,645 24,635 62,495 2,519 65,014 40,816 9,498 50,314 115,328 20,084 20,084 135,4130.0% Design/Estimating Contingency 0 Included with Soft Costs 0 0 0 0
0 0 0 0 01.0% Building Permits 2,798 2,129 4,927 13,124 529 13,653 8,571 1,995 10,566 24,219 4,218 4,218 28,437
0 0 0 0 0 00 0 0 0 0
0.015% Builders Risk Insurance 588 447 1,035 2,756 111 2,867 1,800 419 2,219 5,086 886 886 5,9721.25% C.G.L. Insuramce 3,497 2,661 6,159 16,405 661 17,066 10,714 2,493 13,208 30,274 5,272 5,272 35,5461.25% Subcontractor Bonds 2,967 2,257 5,224 13,950 562 14,512 9,111 2,120 11,231 25,743 4,017 4,017 29,7600.80% CM Payment & Performance Bond 2,317 1,763 4,080 10,869 438 11,307 7,099 1,652 8,751 20,058 3,489 3,489 23,547
0 0 0 0 0Hazardous Materials Abatement 0 0 0 0 0 0
0 0 0 0 02.5% Construction Management Fees 7,299 5,554 12,853 34,237 1,380 35,617 22,361 5,204 27,564 63,182 10,991 10,991 74,173
Total Indirect Costs $61,934 $47,127 $109,061 $287,753 $11,600 $299,353 $187,935 $43,735 $231,669 $531,022 $129,295 $129,295 $660,317
Total Construction Cost $299,256 $227,713 $526,969 $1,403,730 $56,587 $1,460,317 $916,792 $213,350 $1,130,141 $2,590,458 $450,645 $450,645 $3,041,103
x 0.15 Soft Cost Multiplier 44,888 34,157 79,045 - - - -
x 0.30 Soft Cost Multiplier - $421,119 $16,976 438,095 275,037 64,005 339,042 777,137 135,194 135,194 912,331
Total Project Cost Enabling $606,014 Baseline $1,898,412 Proposed $3,367,595 Full Buildout $585,839 $3,953,434
$241.84 $287.83 $337.90
Notes:(1) Excludes 1st Floor Toilet Room Renovation required in 3-Phase Scheme. First phase includes fitout of 2nd Floor Toilets in Addition.
Phase 2
January 24, 2011
EnablingWork
Phase 1Phase 1BPhase 1A
Town of HarvardMunicipal Buildings Renovations
Town Hall 1-Phase SchemeConstruction Costs Summary
Description North Construction Town Hall Elm St. & Town ConstructionNorth Road Parking Lot Cost Renovation & Addition Hall Site Work Cost
Gross Building Area ---- ---- ---- 11,700 gsf ---- 11,700 gsfConsgtruction Duration (Months) ---- ---- ---- 12
Direct Costs
Foundation 0 80,099 0 80,099Basement Construction 0 19,200 19,200Superstructure 0 110,709 110,709Exterior Closure 0 457,708 457,708Roofing 0 68,369 68,369Interior Construction (1) (2) 0 90,042 90,042Stairs 0 35,000 35,000Interior Finishes 0 120,772 120,772Conveying (Full Size Elevator) 0 100,000 100,000Plumbing (1) 0 76,245 76,245H.V.A.C. 0 281,566 281,566Fire Protection 0 70,521 70,521Electrical 0 370,505 370,505Equipment 0 177,566 177,566Furnishings 0 18,625 18,625Demolition 0 64,257 64,257Site Preparation 89,100 79,750 168,850 0 74,550 74,550Site Improvements 69,942 82,256 152,198 80,305 80,305Site Civil/Mechanical Utilities 69,780 10,080 79,860 29,510 29,510Site Electrical Utilities 8,500 8,500 17,000 30,237 30,237
Total Construction Cost $237,322 $180,586 $417,908 $2,141,184 $214,602 $2,355,786
Indirect Costs
12.0% Construction Management Services 28,479 21,670 50,149 256,942 25,752 282,6940.0% Preconstruction Services 0 0 0 0 0 00.0% Misc Consultants 0 0 0 0 0 0
0 00.0% Escalation 0 0 0 00.0% Project Contingency 0 0 0 05.0% Construction Contingency 13,990 10,645 24,635 119,906 12,018 131,9240.0% Design/Estimating Contingency 0 0 0 0
0 01.0% Building Permits 2,798 2,129 4,927 25,180 2,524 27,704
LEED Registration & Certification 00 0
0.015% Builders Risk Insurance 588 447 1,035 4,532 454 4,9871.25% C.G.L. Insuramce 3,497 2,661 6,159 31,475 3,155 34,6301.25% Subcontractor Bonds 2,967 2,257 5,224 26,765 2,683 29,4470.80% CM Payment & Performance Bond 2,317 1,763 4,080 21,546 2,159 23,705
0 0Hazardous Materials Abatement 0 0 0
0 02.5% Construction Management Fees 7,299 5,554 12,853 65,688 6,584 72,272
Total Indirect Costs $61,934 $47,127 $109,061 $552,035 $55,328 $607,364
Total Construction Cost $299,256 $227,713 $526,969 $2,693,219 $269,930 $2,963,150
x 0.15 Soft Cost Multiplier 44,888 34,157 79,045 -
x 0.30 Soft Cost Multiplier - 888,945
Total Project Cost Enabling $606,014 $3,852,095
$329.24
Notes:(1) Excludes 1st Floor Toilet Room Renovation required in 3-Phase Scheme.(2) Excludes 2nd Floor Renovation of existing Town Hall required in 2-Phase and 3-Phase Schemes.
January 24, 2011
Enabling Phase 1
Town of HarvardMunicipal Buildings Renovations
Hildreth House Renovations and AdditionConstruction Costs Summary
Total Multi-Purpose Total TotalDescription Construction Pavillion Construction Landscape Construction
Building Site Work Cost Addition Cost Package CostGross Building Area 5,100 gsf ---- 5,100 gsf 2,500 gsf 7,600 gsf 7,600 gsfConsgtruction Duration (Months) ---- 6 ---- 6 6
Direct Costs Not Included
Pavilion Cost (2,500 SF) 0 0 500,000 500,000 500,000Elevator (Full Size)/Canopy Core 450,000 450,000 450,000 450,000Minor Interior Reno & Sprinkler 150,000 150,000 150,000 150,000Enclose Porch (Incl MEPS) 0 0 Not Required 0 0Structural Code Upgrades 50,000 50,000 50,000 50,000Site Preparation 107,150 107,150 107,150 107,150Site Improvements 144,745 144,745 144,745 144,745Site Civil/Mechanical Utilities 18,910 18,910 18,910 18,910Site Electrical Utilities 17,000 17,000 17,000 17,000
Total Construction Cost $650,000 $287,805 $937,805 $500,000 $1,437,805 $0 $1,437,805
Indirect Costs
12.0% Construction Management Services 78,000 34,537 112,537 60,000 172,537 0 172,5370.0% Preconstruction Services 0 0 0 0 0 0 00.0% Misc Consultants 0 0 0 0 0 0 0
0 0 00.0% Escalation 0 0 0 0 0 0 00.0% Project Contingency 0 0 0 0 0 0 05.0% Construction Contingency 32,500 14,390 46,890 25,000 71,890 0 71,8900.0% Design/Estimating Contingency 0 0 0 0 0 0 0
0 0 01.0% Building Permits 8,133 3,601 11,734 6,256 17,990 0 17,990
LEED Registration & Certification 0 00 0
0.015% Builders Risk Insurance 684 303 988 527 1,514 0 1,5141.25% C.G.L. Insuramce 9,506 4,209 13,715 7,313 21,028 0 21,0281.25% Subcontractor Bonds 8,125 3,598 11,723 6,250 17,973 0 17,9730.80% CM Payment & Performance Bond 6,506 2,881 9,387 5,005 14,392 0 14,392
0 0 0Hazardous Materials Abatement 0 0 0
0 0 02.5% Construction Management Fees 19,836 8,783 28,619 15,259 43,878 0 43,878
Total Indirect Costs $163,291 $72,302 $235,593 $125,609 $361,202 $0 $361,202
Total Construction Cost $813,291 $360,107 $1,173,398 $625,609 $1,799,007 $0 $1,799,007
x 0.30 Soft Cost Multiplier 352,019 539,702 539,702
Total Project Cost Baseline $1,525,417 Proposed $2,338,709 Full Buildout $2,338,709
$299.10 $307.72 $307.72
New Entry Core, Parking & Code Upgrades
Town of HarvardMunicipal Buildings Renovations
Old Library Renovations and AdditionConstruction Costs Summary
Energy Description Code & Deferred Total Cultural Center Add Insulation Cultural Center Total Cultural Center Council on Aging Add Insulation Council on Aging Total Council on Aging Pedestrian Access Alternate #2
Maint Upgrades Construction Cost Fit-Up & Air Conditioning (1) Site Work Construction Cost Fit-Up & Air Conditioning (1) Site Work Construction Cost & Parking Upgrade Stretch CodeGross Building Area 6,000 gsf 6,000 gsf 6,000 gsf 6,000 gsf ----Consgtruction Duration (Months) 6 0 0 6 0 0 6 0
Direct Costs
Foundation 48,108 48,108 48,108 48,108Basement Construction Included 0 0 0Superstructure 55,750 55,750 55,750 55,750Exterior Closure 135,955 135,955 135,955 135,955Roofing 17,700 17,700 NIC 17,700 100,000 117,700Interior Construction 129,268 129,268 4,820 134,088 14,845 144,113 Insulate Attic Floor and WallsStairs 48,550 48,550 48,550 48,550 A/V BarrierInterior Finishes 64,094 64,094 15,601 79,695 22,863 86,957Conveying (LULA) 77,500 77,500 77,500 77,500Plumbing 52,486 52,486 52,486 19,567 72,053H.V.A.C. 61,770 61,770 Included in Base 180,000 241,770 2,142 180,000 243,912Fire Protection 57,780 57,780 57,780 470 58,250Electrical 71,429 71,429 93,314 164,743 94,443 165,872Equipment 0 0 74,500 74,500Furnishings 2,000 2,000 2,000 2,000Demolition 35,320 35,320 35,320 35,320Site Preparation 0 3,057 3,057 7,793 7,793 48,496Site Improvements 0 9,779 9,779 11,563 11,563 63,898Site Civil/Mechanical Utilities 0 0 0 24,850Site Electrical Utilities 13,746 13,746 13,746 13,746 0
Total Construction Cost $871,456 $871,456 $113,735 $180,000 $12,836 $1,178,027 $228,830 $180,000 $119,356 $1,399,642 $137,244 $0
Indirect Costs
12.0% Construction Management Services 104,575 104,575 13,648 21,600 1,540 141,363 27,460 21,600 14,323 167,957 16,469 00.0% Preconstruction Services 0 0 0 0 0 0 0 0 0 0 0 00.0% Misc Consultants 0 0 0 0 0 0 0 0 0 0 0 0
0.0% Escalation (3rd Qtr 2012 Start) 0 0 0 0 0 0 0 0 0 0 0 00.0% Project Contingency 0 0 0 0 0 0 0 0 0 0 0 05.0% Construction Contingency 43,573 43,573 5,687 9,000 642 58,901 11,442 9,000 5,968 69,982 6,862 00.0% Design/Estimating Contingency 0 0 0 0 0 0 0 0 0 0 0 0
1.0% Building Permits 10,904 10,904 1,423 2,252 161 14,740 2,863 2,252 1,493 17,513 1,717 0
0.015% Builders Risk Insurance 918 918 120 190 14 1,240 241 190 126 1,474 145 01.25% C.G.L. Insuramce 12,745 12,745 1,663 2,633 188 17,229 3,347 2,633 1,746 20,470 2,007 01.25% Subcontractor Bonds 10,893 10,893 1,422 2,250 160 14,725 2,860 2,250 1,492 17,496 1,716 00.80% CM Payment & Performance Bond 8,723 8,723 1,138 1,802 128 11,792 2,291 1,802 1,195 14,010 1,374 0
Hazardous Materials Abatement 0 0 0
2.5% Construction Management Fees 26,595 26,595 3,471 5,493 392 35,950 6,983 5,493 3,642 42,714 4,188 0
Total Indirect Costs $218,925 $218,925 $28,572 $45,219 $3,225 $295,941 $57,486 $45,219 $29,984 $351,614 $34,478 $0
Total Construction Cost $1,090,381 $1,090,381 $142,307 $225,219 $16,061 $1,473,968 $286,316 $225,219 $149,340 $1,751,256 $171,722 $0
x 0.15 Soft Cost Multiplier - - - 25,758
x 0.30 Soft Cost Multiplier 327,114 442,190 525,377
Total Project Cost Baseline $1,417,495 Proposed & Final Buildout $1,916,158 COA Fitout Alternate $2,276,633 $197,480
$236.25 $319.36 $379.44
Notes: Net Add for COA Fitup & Pedestrian Access = $557,956
(1) Cost Includes Attic Floor Insulation, Air Conditioning System Retrofit and Associated Building and Electrical Work
Base - Shell Space Alternate #1 - Cultural Center Alternate #2 - Council on Aging
Energy Alternate #2 is not expected to be cost effective and
is therefore excluded from consideration.
January 24, 2011
Town of Harvard - Municipal Building Committee3..0 Cost Estimating Report Page 12
3.5 Estimate Detail
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1 1 Town Hall
2 0 Enabling
3 0.1 North Road
4 G10 SITE PREPARATION
5 G1010 Site Clearing
6 Site Preparation / Site Demo 16,200 sf 1.50 24,300
7 G1010 Site Clearing - SF - 24,300
8
9 G1030 Site Earthwork
10 Preparation Roadway & Sidewalk Areas 16,200 sf 4.00 64,800
11 G1030 Site Earthwork - SF - 64,800
12
13 G10 SITE PREPARATION - SF - 89,100
14
15 G20 SITE IMPROVEMENTS
16 G2010 Roadways
17 Bituminous Pavement 1,344 sy 30.00 40,320
18 Granite Curb 168 lf 35.00 5,880
19 Cape Cod Berm 974 lf 8.00 7,792
20 G2010 Roadways - SF - 53,992
21
22 G2020 Parking Lots
23 Bituminous Pavement 447 sy 30.00 13,410
24 Stripe Parking Spaces 5 ea 8.00 40
25 G2020 Parking Lots - SF - 13,450
26
27 G2040 Site Development
28 Relocate Stone Monument 1 ea 2,500.00 2,500
29 G2040 Site Development - SF - 2,500
30
31 G20 SITE IMPROVEMENTS - SF - 69,942
32
33 G30 SITE CIVIL/MECHANICAL UTILITIES
34 G3020 Sanitary Sewer
35 Sanitary Sewer Pipe 57 lf 60.00 3,420
36 Sanitary Sewer Pipe 467 lf 60.00 28,020
37 CTE 1 ea 2,500.00 2,500
38 Sanitary Manhole Precast 48" Dia x 5' Deep 4 ea 3,000.00 12,000
39 G3020 Sanitary Sewer - SF - 45,940
40
41 G3030 Storm Sewer
42 Storm Pipe 164 lf 60.00 9,840
43 Drain Manhole 2 ea 2,500.00 5,000
44 Catch Basins 3 ea 3,000.00 9,000
45 G3030 Storm Sewer - SF - 23,840
46
47 G30 SITE CIVIL/MECHANICAL UTILITIES - SF - 69,780
48
49 G40 SITE ELECTRICAL UTILITIES
50 G4010 Electrical Distribution
51 Light Pole Bases 2 ea 350.00 700
52 E & B Lighting Conduit 200 lf 10.00 2,000
53 G4010 Electrical Distribution - SF - 2,700
54
55 G4020 Site Lighting
56 Conduit PVC Sch 40 1 in 300 lf 2.57 770
57 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
58 Wire THHN 8 AWG 1,050 lf 0.86 902
59 Fixture Pole Single 400w MH 25' 2 ea 2,063.95 4,128
60 - Excl Conduit & Wire
● Bldg, PP, UDF1, Uni 2,3 1 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
61 G4020 Site Lighting - SF - 5,800
62
63 G40 SITE ELECTRICAL UTILITIES - SF - 8,500
64
65 0.1 North Road - SF - 237,322
66
67 0.2 North Parking Lot
68 G10 SITE PREPARATION
69 G1010 Site Clearing
70 Site Preparation / Site Demo 14,500 sf 1.50 21,750
71 G1010 Site Clearing - SF - 21,750
72
73 G1030 Site Earthwork
74 Preparation Roadway & Sidewalk Areas 14,500 sf 4.00 58,000
75 G1030 Site Earthwork - SF - 58,000
76
77 G10 SITE PREPARATION - SF - 79,750
78
79 G20 SITE IMPROVEMENTS
80 G2020 Parking Lots
81 Bituminous Pavement 1,274 sy 30.00 38,220
82 Stripe Parking Spaces 32 ea 8.00 256
83 Granite Curb 205 lf 35.00 7,175
84 Cape Cod Berm 374 lf 8.00 2,992
85 G2020 Parking Lots - SF - 48,643
86
87 G2030 Pedestrian Paving
88 4" Concrete Sidewalk 700 sf 8.50 5,950
89 4" Concrete Sidewalk, to Hildreth 2,251 sf 8.50 19,134
90 G2030 Pedestrian Paving - SF - 25,084
91
92 G2050 Landscaping
93 Swale 2,437 sf 3.50 8,530
94 G2050 Landscaping - SF - 8,530
95
96 G20 SITE IMPROVEMENTS - SF - 82,256
97
98 G30 SITE CIVIL/MECHANICAL UTILITIES
99 G3030 Storm Sewer
100 Storm Pipe 118 lf 60.00 7,080
101 Catch Basins 1 ea 3,000.00 3,000
102 G3030 Storm Sewer - SF - 10,080
103
104 G30 SITE CIVIL/MECHANICAL UTILITIES - SF - 10,080
105
106 G40 SITE ELECTRICAL UTILITIES
107 G4010 Electrical Distribution
108 Light Pole Bases 2 ea 350.00 700
109 E & B Lighting Conduit 200 lf 10.00 2,000
110 G4010 Electrical Distribution - SF - 2,700
111
112 G4020 Site Lighting
113 Conduit PVC Sch 40 1 in 300 lf 2.57 770
114 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
115 Wire THHN 8 AWG 1,050 lf 0.86 902
116 Fixture Pole Single 400w MH 25' 2 ea 2,063.95 4,128
117 - Excl Conduit & Wire
118 G4020 Site Lighting - SF - 5,800
119
120 G40 SITE ELECTRICAL UTILITIES - SF - 8,500
121
● Bldg, PP, UDF1, Uni 2,3 2 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
122 0.2 North Parking Lot - SF - 180,586
123
124 0 Enabling - SF - 417,908
125
126 1 Phase 1
127 1.1 Existing Town Hall Renovations
128 A10 FOUNDATIONS
129 A1010 Standard Foundations
130 3'x1' Footing / 3'x1' Frost Wall, Excavation 540 cy 15.00 8,100
131 3'x1' Footing / 3'x1' Frost Wall, Backfill 455 cy 20.00 9,100
132 Elevator Pit 1 ea 15,000.00 15,000
133 3'x1' Continuous Strip Footing 14 lf 40.00 560
134 - Elevator lobby.
135 3'x1' Continuous Strip Footing 90 lf 40.00 3,600
136 - Handicap ramp.
137 3'x1' Foundation Wall 14 lf 80.00 1,120
138 3'x1' Foundation Wall 90 lf 80.00 7,200
139 - Handicap Ramp
140 A1010 Standard Foundations - SF - 44,680
141
142 A1030 Slab on Grade
143 Excavate For SOG 10 cy 15.00 150
144 6" Structural Fill 6 cy 28.00 168
145 5" Slab-On-Grade 60 sf 6.25 375
146 - Elevator lobby.
147 5" Slab-On-Grade 200 sf 6.25 1,250
148 - Handicap Ramp
149 A1030 Slab on Grade - SF - 1,943
150
151 A10 FOUNDATIONS - SF - 46,623
152
153 B10 SUPERSTRUCTURE
154 B1010 Floor Construction
155 5" SOMD 60 sf 40.00 2,400
156 Steel Columns & Beams 1 tn 2,800.00 2,800
157 Steel Floor Deck 69 sf 5.50 380
158 Elevator Pit Ladders 1 ea 750.00 750
159 Elevator Sill Angles 2 ea 250.00 500
160 Add Support Columns, Allowance 6 ea 2,000.00 12,000
161 B1010 Floor Construction - SF - 18,830
162
163 B1020 Roof Construction
164 Steel Roof Deck 69 sf 5.50 380
165 Reinforce Roof Trusses 3 ea 1,500.00 4,500
166 Reinforce Wall / Roof Connections 80 ea 150.00 12,000
167 Stabilize Chimney 1 ea 1,500.00 1,500
168 B1020 Roof Construction - SF - 18,380
169
170 B10 SUPERSTRUCTURE - SF - 37,209
171
172 B20 EXTERIOR CLOSURE
173 B2010 Exterior Walls
174 CMU - Elevator Shaft 660 sf 18.00 11,880
175 Brick Veneer 660 sf 21.00 13,860
176 Wall Sheathing 5/8" 7,265 sf 4.00 29,060
177 Blown-in Fiberglass 7,265 sf 4.00 29,060
178 Min Fiber Cement Siding, Exist. Bldg. 7,265 sf 10.00 72,650
179 Paint Exterior 7,265 sf 2.00 14,530
180 Refurbish Entry Doors, Allowance 1 ea 1,500.00 1,500
181 B2010 Exterior Walls - SF - 172,540
182
● Bldg, PP, UDF1, Uni 2,3 3 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
183 B2020 Exterior Windows
184 Aluminum Storefront 354 sf 65.00 23,010
185 Wood Window - Double Hung 37 ea 875.00 32,375
186 B2020 Exterior Windows - SF - 55,385
187
188 B2030 Exterior Doors
189 Exterior Door, Frame & Hardware 1 ea 1,200.00 1,200
190 B2030 Exterior Doors - SF - 1,200
191
192 B20 EXTERIOR CLOSURE - SF - 229,125
193
194 B30 ROOFING
195 B3010 Roof Coverings
196 Asphalt Shingles 5,152 sf 7.00 36,064
197 TPO Roofing - Elevator Shaft 75 sf 10.00 750
198 TPO Roofing - Exist. Flat Roof 842 sf 10.00 8,420
199 Downspouts - CI 120 lf 20.00 2,400
200 Gutters - Wood 140 lf 15.00 2,100
201 B3010 Roof Coverings - SF - 49,734
202
203 B30 ROOFING - SF - 49,734
204
205 C10 INTERIOR CONSTRUCTION
206 C1010 Partitions
207 Interior Partition, 12' 3,084 sf 8.50 26,214
208 C1010 Partitions - SF - 26,214
209
210 C1020 Interior Doors
211 Interior Door, Frame & Hardware 7 ea 1,200.00 8,400
212 C1020 Interior Doors - SF - 8,400
213
214 C1030 Building Specialties
215 Rough Carpentry, Allowance 120 sf 1.00 120
216 Rough Carpentry, Allowance 3,675 sf 1.00 3,675
217 Sister Floor Joists For 2nd Floor 1,120 lf 12.00 13,440
218 Repair Exterior Soffit 142 sf 15.00 2,130
219 Repair Exterior Columns 4 ea 750.00 3,000
220 Misc Finish Carpentry / Millwork Allowance 3,675 sf 7.00 25,725
221 Interior Handicap Ramp 269 sf 40.00 10,760
222 Sealants and Caulking, Allowance 120 sf 0.50 60
223 C1030 Building Specialties - SF - 58,910
224
225 C10 INTERIOR CONSTRUCTION - SF - 93,524
226
227 C20 STAIRS
228 C2010 Stair Construction
229 Handicap Ramp Rails, Ptd. Steel 80 lf 125.00 10,000
230 Refurbish Existing Stairs, Allowance 1 ea 5,000.00 5,000
231 C2010 Stair Construction - SF - 15,000
232
233 C20 STAIRS - SF - 15,000
234
235 C30 INTERIOR FINISHES
236 C3010 Wall Finishes
237 Paint Interior Space 120 sf 2.50 300
238 Paint Interior Space 5,771 sf 2.50 14,428
239 C3010 Wall Finishes - SF - 14,728
240
241 C3020 Floor Finishes
242 Flooring, VCT 120 sf 4.00 480
243 Flooring, Carpet 337 sy 40.00 13,480
● Bldg, PP, UDF1, Uni 2,3 4 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
244 Flooring, Refinish 2,740 sf 3.00 8,220
245 C3020 Floor Finishes - SF - 22,180
246
247 C3030 Ceiling Finishes
248 Ceilings 120 sf 4.00 480
249 Ceilings 5,771 sf 4.00 23,084
250 C3030 Ceiling Finishes - SF - 23,564
251
252 C30 INTERIOR FINISHES - SF - 60,472
253
254 D10 CONVEYING
255 D1010 Elevators & Lifts
256 Hydraulic LULA Elevator 2 st 30,000.00 60,000
257 D1010 Elevators & Lifts - SF - 60,000
258
259 D10 CONVEYING - SF - 60,000
260
261 D20 PLUMBING
262 D2010 Plumbing Fixtures
263 Fixture 12 ea 3,600.00 43,200
264 D2010 Plumbing Fixtures - SF - 43,200
265
266 D2020 Domestic Water Distribution
267 Domestic Water Piping 7,940 sf 0.75 5,955
268 Insulation Fiberglass All Service Jkt 7,940 sf 0.50 3,970
269 D2020 Domestic Water Distribution - SF - 9,925
270
271 D2030 Sanitary Waste
272 Sanitary and Vent Piping 7,940 sf 0.75 5,955
273 D2030 Sanitary Waste - SF - 5,955
274
275 D2040 Rain Water Drainage
276 Storm Piping - (NIC Gutter and Down Spout System) 7,940 NIC - -
277 D2040 Rain Water Drainage - SF - -
278
279 D2050 Specialty Gas Systems
280 Natural Gas Piping 7,940 sf 0.75 5,955
281 D2050 Specialty Gas Systems - SF - 5,955
282
283 D2070 Plumbing System Equipment
284 Natural Gas Fired Water Heater 1 ea 1,000.00 1,000
285 D2070 Plumbing System Equipment - SF - 1,000
286
287 D2090 Misc Materials & Methods
288 Misc Materials & Methods 7,940 sf 0.50 3,970
289 D2090 Misc Materials & Methods - SF - 3,970
290
291 D20 PLUMBING - SF - 70,005
292
293 D30 HVAC
294 D3020 Heating Systems & Equipment
295 Heating Water Piping 7,940 sf 2.00 15,880
296 Insulation Fiberglass All Service Jkt 7,940 sf 0.50 3,970
297 Gas Fired Hot Water Boilers 1 ea 9,500.00 9,500
298 Heating Water Equipment 7,940 sf 0.39 3,097
299 Hydronic Fintube Baseboard Radiation - (Repair / Replace / New) 7,940 sf 0.20 1,588
300 D3020 Heating Systems & Equipment - SF - 34,035
301
302 D3030 Cooling Systems & Equipment
303 Little Giant Condensate Pump 6 ea 150.00 900
304 D3030 Cooling Systems & Equipment - SF - 900
305
● Bldg, PP, UDF1, Uni 2,3 5 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
306 D3040 Air Distribution Systems & Equipment
307 Gas Fired / Split DX Furnace 6 ea 7,500.00 45,000
308 Galvanized Ductwork 5,400 lbs 9.00 48,600
309 Fire Dampers 7,940 sf 0.20 1,588
310 Duct Insulation Fiberglass Wrap 2,900 sf 2.00 5,800
311 Toilet Room Exhaust Fan 2 ea 125.00 250
312 Supply, Exhaust, and Return Diffuser 7,940 sf 0.75 5,955
313 D3040 Air Distribution Systems & Equipment - SF - 107,193
314
315 D3070 Controls & Instrumentation
316 Direct Digital Controls 7,940 sf 3.00 23,820
317 D3070 Controls & Instrumentation - SF - 23,820
318
319 D3080 System Test & Balance
320 Air Systems Testing, Adjusting, & Balancing 7,940 sf 0.30 2,382
321 D3080 System Test & Balance - SF - 2,382
322
323 D3090 Misc HVAC Systems
324 Misc Materials & Methods 7,940 sf 0.50 3,970
325 D3090 Misc HVAC Systems - SF - 3,970
326
327 D30 HVAC - SF - 172,300
328
329 D40 FIRE PROTECTION
330 D4000 Fire Suppression
331 Fire Protection Piping 7,940 sf 1.50 11,910
332 Fire Suppression Equipment 7,940 sf 1.00 7,940
333 Sprinkler Heads 69 ea 30.00 2,070
334 Electric Fire Pump w/Controller & Jockey Pump 1 ea 30,000.00 30,000
335 D4000 Fire Suppression - SF - 51,920
336
337 D4090 Misc Materials & Methods
338 Misc Materials & Methods 7,940 sf 0.50 3,970
339 D4090 Misc Materials & Methods - SF - 3,970
340
341 D40 FIRE PROTECTION - SF - 55,890
342
343 D50 ELECTRICAL
344 D5000 ELECTRICAL
345 Temporary Construction Lights, Power and FA 7,940 sf 1.04 8,269
346 Electrical Fees & Permits 1 ea 2,578.88 2,579
347 D5000 ELECTRICAL - SF - 10,848
348
349 D5011 LOW-VOLTAGE ELECTRICAL TRANSMISSION
350 Service Panel 800 amp 208/120 volt 1 ea 8,255.81 8,256
351 Distribution System Upgrades 7,940 sf 1.88 14,958
352
- Includes 50% new panels and 100% new feeders for all existing spaces,
100% new panels and feeders for new spaces.
353 D5011 LOW-VOLTAGE ELECTRICAL TRANSMISSION - SF - 23,214
354
355 D5012 FACILITY ELECTRICAL POWER GENERATING & STORING EQUIPMENT
356 Generator - 125kw Diesel 1 ea 31,145.67 31,146
357 Emergency Distribution System 7,940 sf 0.70 5,593
358 D5012 FACILITY ELECTRICAL POWER GENERATING & STORING EQUIPMENT - SF - 36,739
359
360 D5015 EQUIPMENT CONNECTIONS
361 Equipment Connections 7,940 sf 0.64 5,101
362 D5015 EQUIPMENT CONNECTIONS - SF - 5,101
363
364 D5020 LIGHTING
● Bldg, PP, UDF1, Uni 2,3 6 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
365 Interior Light Fixtures and Controls 7,940 sf 6.00 47,659
366 D5020 LIGHTING - SF - 47,659
367
368 D5025 POWER BRANCH WIRING
369 Receptacles 7,940 sf 1.53 12,171
370
- Includes refeeding existing devices as needed from new panels and
installation of new devices in areas that are completely gutted during
renovations.
371 D5025 POWER BRANCH WIRING - SF - 12,171
372
373 D5031 FIRE ALARM AND DETECTION SYSTEM
374 Fire Alarm Replacement System 7,940 sf 1.59 12,635
375 D5031 FIRE ALARM AND DETECTION SYSTEM - SF - 12,635
376
377 D5040 COMMUNICATIONS
378 Security/Access Systems 7,940 sf 1.38 10,945
379 Fit Out MDF Closet 1 ea 7,629.11 7,629
380 Fit Out IDF Closet 2 ea 3,463.55 6,927
381 Communications Circuits 7,940 sf 0.76 6,051
382 Conference Room AV System - Allowance 1 ea 23,729.05 23,729
383 Paging System 7,940 sf 0.55 4,367
384 D5040 COMMUNICATIONS - SF - 59,648
385
386 D50 ELECTRICAL - SF - 208,013
387
388 E20 FURNISHINGS
389 E2010 Fixed Furnishings
390 Transaction Counter 37 lf 125.00 4,625
391 Demountable Work Stations 4 ea 3,500.00 14,000
392 E2010 Fixed Furnishings - SF - 18,625
393
394 E20 FURNISHINGS - SF - 18,625
395
396 F20 SELECTIVE BUILDING DEMOLITION
397 F2010 Building Elements Demolition
398 Gut 2nd Floor Interior 2,740 sf 5.00 13,700
399 Demo 1st Floor Ceiling 3,031 sf 2.00 6,062
400 Gut 1st Floor Interior 3,031 sf 5.00 15,155
401 Strip Existing Siding 7,265 sf 1.00 7,265
402 Strip Existing Sheathing 7,265 sf 1.00 7,265
403 Cut Opening For Elevator Lobby 32 sf 75.00 2,400
404 Roof Surface Removal - Asphalt Shingles 4,480 sf 0.75 3,360
405 Roof Surface Removal - Flat Section 733 sf 0.75 550
406 Demo Existing Windows 37 ea 100.00 3,700
407 F2010 Building Elements Demolition - SF - 59,457
408
409 F20 SELECTIVE BUILDING DEMOLITION - SF - 59,457
410
411 1.1 Existing Town Hall Renovations - SF - 1,175,976
412
413 1.2 Canopy & Code Utility Upgrade
414 G10 SITE PREPARATION
415 G1030 Site Earthwork
416 Underpinning, Allowance 1 ea 10,000.00 10,000
417 G1030 Site Earthwork - SF - 10,000
418
419 G10 SITE PREPARATION - SF - 10,000
420
421 G20 SITE IMPROVEMENTS
422 G2040 Site Development
423 Canopy Along Addition 760 sf 20.00 15,200
● Bldg, PP, UDF1, Uni 2,3 7 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
424 G2040 Site Development - SF - 15,200
425
426 G20 SITE IMPROVEMENTS - SF - 15,200
427
428 G30 SITE CIVIL/MECHANICAL UTILITIES
429 G3010 Water Supply
430 Replace Water Line 50 lf 60.00 3,000
431 G3010 Water Supply - SF - 3,000
432
433 G3020 Sanitary Sewer
434 Replace Sewer Line 50 lf 60.00 3,000
435 G3020 Sanitary Sewer - SF - 3,000
436
437 G3060 Fuel Distribution
438 Replace Gas Service 50 lf 60.00 3,000
439 G3060 Fuel Distribution - SF - 3,000
440
441 G30 SITE CIVIL/MECHANICAL UTILITIES - SF - 9,000
442
443 G40 SITE ELECTRICAL UTILITIES
444 G4010 Electrical Distribution
445 Information-Circuit Rating 800 amp - -
446 Electrical Ductbank 50 lf 75.00 3,750
447 - Includes excavation, backfill, and concrete.
448 Electrical Manhole 1 ea 5,000.00 5,000
449 Conduit PVC Sch 40 4 in 200 lf 5.74 1,148
450 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
451 Conduit PVC Sch 40 4 in 400 lf 5.74 2,297
452 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
453 Drag Line 100 lf 0.57 57
454 Drag Line 100 lf 0.57 57
455 Wire XHHW 1/0 AWG 206 lf 4.38 903
456 - TraserSX - COPPER BUILDING WIRE
457 Wire XHHW 500 MCM 824 lf 14.48 11,933
458 - TraserSX - COPPER BUILDING WIRE
459 Exterior Pad Mounted Transformer Pad Electrical 1 ea 842.83 843
460 G4010 Electrical Distribution - SF - 25,987
461
462 G40 SITE ELECTRICAL UTILITIES - SF - 25,987
463
464 1.2 Canopy & Code Utility Upgrade - SF - 60,187
465
466 1 Phase 1 - SF - 1,236,163
467
468 2 Phase 2
469 2.1 Town Hall Addition
470 A10 FOUNDATIONS
471 A1010 Standard Foundations
472 3'x1' Footing / 3'x1' Frost Wall, Excavation 340 cy 15.00 5,100
473 3'x1' Footing / 3'x1' Frost Wall, Backfill 285 cy 20.00 5,700
474 3'x1' Continuous Strip Footing 240 lf 40.00 9,600
475 - Addition.
476 A1010 Standard Foundations - SF - 20,400
477
478 A1030 Slab on Grade
479 Excavate For SOG 66 cy 15.00 990
480 6" Structural Fill 39 cy 28.00 1,092
481 5" Slab-On-Grade 1,759 sf 6.25 10,994
482 - Addition.
483 A1030 Slab on Grade - SF - 13,076
484
● Bldg, PP, UDF1, Uni 2,3 8 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
485 A10 FOUNDATIONS - SF - 33,476
486
487 A20 BASEMENT CONSTRUCTION
488 A2020 Basement Walls
489 3'x1' Foundation Wall 240 lf 80.00 19,200
490 A2020 Basement Walls - SF - 19,200
491
492 A20 BASEMENT CONSTRUCTION - SF - 19,200
493
494 B10 SUPERSTRUCTURE
495 B1010 Floor Construction
496 Wood Framed Structure 1,759 sf 20.00 35,180
497 B1010 Floor Construction - SF - 35,180
498
499 B1020 Roof Construction
500 Wood Framed Structure 1,916 sf 20.00 38,320
501 B1020 Roof Construction - SF - 38,320
502
503 B10 SUPERSTRUCTURE - SF - 73,500
504
505 B20 EXTERIOR CLOSURE
506 B2010 Exterior Walls
507 Wall Sheathing 5/8" 4,251 sf 4.00 17,004
508 Min Fiber Cement Siding, New Bldg. 4,251 sf 10.00 42,510
509 Exterior Siding Backup 4,251 sf 12.00 51,012
510 Paint Exterior 4,251 sf 2.00 8,502
511 B2010 Exterior Walls - SF - 119,028
512
513 B2020 Exterior Windows
514 Aluminum Storefront, 1st Floor 907 sf 65.00 58,955
515 Aluminum Storefront, 2nd Floor 425 sf 65.00 27,625
516 Wood Window - Double Hung 13 ea 675.00 8,775
517 Wood Window - Fixed Window 60 sf 50.00 3,000
518 B2020 Exterior Windows - SF - 98,355
519
520 B2030 Exterior Doors
521 Exterior Door, Frame & Hardware 1 ea 1,200.00 1,200
522 Pr Medium Stile Alum and Glass Door 4 pr 2,500.00 10,000
523 B2030 Exterior Doors - SF - 11,200
524
525 B20 EXTERIOR CLOSURE - SF - 228,583
526
527 B30 ROOFING
528 B3010 Roof Coverings
529 Asphalt Shingles 1,357 sf 7.00 9,499
530 TPO Roofing - Vestibule 144 sf 10.00 1,440
531 TPO Roofing - Flat Roof 688 sf 10.00 6,880
532 Downspouts - Aluminum 50 lf 8.00 400
533 Gutters - Aluminum 52 lf 8.00 416
534 B3010 Roof Coverings - SF - 18,635
535
536 B30 ROOFING - SF - 18,635
537
538 C10 INTERIOR CONSTRUCTION
539 C1010 Partitions
540 Interior Partition, 12' 3,084 lf 8.50 26,214
541 C1010 Partitions - SF - 26,214
542
543 C1020 Interior Doors
544 Interior Door, Frame & Hardware 8 ea 1,200.00 9,600
545 C1020 Interior Doors - SF - 9,600
546
● Bldg, PP, UDF1, Uni 2,3 9 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
547 C1030 Building Specialties
548 Soffit, Vestibule 86 sf 94.73 8,147
549 Sealants and Caulking, Allowance 3,675 sf 0.50 1,838
550 Toilet Accessories 2 ea 1,500.00 3,000
551 C1030 Building Specialties - SF - 12,984
552
553 C10 INTERIOR CONSTRUCTION - SF - 48,798
554
555 C20 STAIRS
556 C2010 Stair Construction
557 Metal Pan Stairs 20 rsr 1,000.00 20,000
558 C2010 Stair Construction - SF - 20,000
559
560 C20 STAIRS - SF - 20,000
561
562 C30 INTERIOR FINISHES
563 C3010 Wall Finishes
564 Paint Interior Space 1,759 sf 4.00 7,036
565 C3010 Wall Finishes - SF - 7,036
566
567 C3020 Floor Finishes
568 Flooring 1,759 sf 8.00 14,072
569 C3020 Floor Finishes - SF - 14,072
570
571 C3030 Ceiling Finishes
572 Ceilings 1,759 sf 4.00 7,036
573 C3030 Ceiling Finishes - SF - 7,036
574
575 C30 INTERIOR FINISHES - SF - 28,144
576
577 D20 PLUMBING
578 D2010 Plumbing Fixtures
579 2 nd Floor Future Fixture Rough Only 3,690 sf 1.63 6,015
580 D2010 Plumbing Fixtures - SF - 6,015
581
582 D2020 Domestic Water Distribution
583 Domestic Water Piping 3,845 sf 0.75 2,884
584 Insulation Fiberglass All Service Jkt 3,845 sf 0.50 1,923
585 D2020 Domestic Water Distribution - SF - 4,806
586
587 D2030 Sanitary Waste
588 Sanitary and Vent Piping 3,845 sf 1.00 3,845
589 D2030 Sanitary Waste - SF - 3,845
590
591 D2040 Rain Water Drainage
592 Storm Piping - (NIC Gutter and Down Spout System) 3,845 NIC - -
593 D2040 Rain Water Drainage - SF - -
594
595 D2050 Specialty Gas Systems
596 Natural Gas Piping 3,845 sf 0.30 1,154
597 D2050 Specialty Gas Systems - SF - 1,154
598
599 D2090 Misc Materials & Methods
600 Misc Materials & Methods 3,845 sf 0.50 1,923
601 D2090 Misc Materials & Methods - SF - 1,923
602
603 D20 PLUMBING - SF - 17,742
604
605 D30 HVAC
606 D3020 Heating Systems & Equipment
607 No Hydronic System Required - NIC - -
608 D3020 Heating Systems & Equipment - SF - -
● Bldg, PP, UDF1, Uni 2,3 10 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
609
610 D3030 Cooling Systems & Equipment
611 Little Giant Condensate Pump 3 ea 125.00 375
612 D3030 Cooling Systems & Equipment - SF - 375
613
614 D3040 Air Distribution Systems & Equipment
615 Gas Fired / Split DX Furnace 3 ea 9,100.00 27,300
616 Galvanized Ductwork 3,300 lbs 9.00 29,700
617 Fire Dampers 3,845 sf 0.14 538
618 Duct Insulation Fiberglass Wrap 1,800 sf 2.00 3,600
619 Exhaust Fan 2 ea 125.00 250
620 Supply, Exhaust, and Return Diffuser 3,845 sf 0.75 2,884
621 D3040 Air Distribution Systems & Equipment - SF - 64,272
622
623 D3070 Controls & Instrumentation
624 Direct Digital Controls 3,845 sf 3.00 11,535
625 D3070 Controls & Instrumentation - SF - 11,535
626
627 D3080 System Test & Balance
628 Air Systems Testing, Adjusting, & Balancing 3,845 sf 0.30 1,154
629 D3080 System Test & Balance - SF - 1,154
630
631 D3090 Misc HVAC Systems
632 Misc Materials & Methods 3,845 sf 0.50 1,923
633 D3090 Misc HVAC Systems - SF - 1,923
634
635 D30 HVAC - SF - 79,258
636
637 D40 FIRE PROTECTION
638 D4000 Fire Suppression
639 Fire Protection Piping 3,845 sf 2.75 10,574
640 Fire Suppression Equipment 3,845 sf 0.29 1,115
641 Sprinkler Heads 34 ea 30.00 1,020
642 D4000 Fire Suppression - SF - 12,709
643
644 D4090 Misc Materials & Methods
645 Misc Materials & Methods 3,845 sf 0.50 1,923
646 D4090 Misc Materials & Methods - SF - 1,923
647
648 D40 FIRE PROTECTION - SF - 14,631
649
650 D50 ELECTRICAL
651 D5000 ELECTRICAL
652 Temporary Construction Lights, Power and FA 3,845 sf 1.04 4,004
653 D5000 ELECTRICAL - SF - 4,004
654
655 D5011 LOW-VOLTAGE ELECTRICAL TRANSMISSION
656 Distribution System Upgrades 3,845 sf 1.88 7,244
657
- Includes 50% new panels and 100% new feeders for all existing spaces,
100% new panels and feeders for new spaces.
658 D5011 LOW-VOLTAGE ELECTRICAL TRANSMISSION - SF - 7,244
659
660 D5012 FACILITY ELECTRICAL POWER GENERATING & STORING EQUIPMENT
661 Emergency Distribution System 3,845 sf 0.70 2,709
662 D5012 FACILITY ELECTRICAL POWER GENERATING & STORING EQUIPMENT - SF - 2,709
663
664 D5015 EQUIPMENT CONNECTIONS
665 Equipment Connections 3,845 sf 0.64 2,470
666 D5015 EQUIPMENT CONNECTIONS - SF - 2,470
667
● Bldg, PP, UDF1, Uni 2,3 11 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
668 D5020 LIGHTING
669 Interior Light Fixtures and Controls 3,845 sf 6.00 23,079
670 D5020 LIGHTING - SF - 23,079
671
672 D5025 POWER BRANCH WIRING
673 Receptacles 3,845 sf 1.53 5,894
674
- Includes refeeding existing devices as needed from new panels and
installation of new devices in areas that are completely gutted during
renovations.
675 D5025 POWER BRANCH WIRING - SF - 5,894
676
677 D5031 FIRE ALARM AND DETECTION SYSTEM
678 Fire Alarm Replacement System 3,845 sf 1.59 6,119
679 D5031 FIRE ALARM AND DETECTION SYSTEM - SF - 6,119
680
681 D5040 COMMUNICATIONS
682 Security/Access Systems 3,845 sf 1.38 5,300
683 Communications Circuits 3,845 sf 0.76 2,930
684 Conference Room AV System - Allowance 1 ea 23,729.05 23,729
685 Paging System 3,845 sf 0.55 2,115
686 D5040 COMMUNICATIONS - SF - 34,074
687
688 D50 ELECTRICAL - SF - 85,592
689
690 F20 SELECTIVE BUILDING DEMOLITION
691 F2010 Building Elements Demolition
692 Cut Opening For 2nd Floor Lobby 64 sf 75.00 4,800
693 F2010 Building Elements Demolition - SF - 4,800
694
695 F20 SELECTIVE BUILDING DEMOLITION - SF - 4,800
696
697 2.1 Town Hall Addition - SF - 672,359
698
699 2.2 Elm St. & Town Hall Site Work
700 G10 SITE PREPARATION
701 G1010 Site Clearing
702 Site Preparation / Site Demo 10,250 sf 1.50 15,375
703 G1010 Site Clearing - SF - 15,375
704
705 G1020 Site Demolition & Relocations
706 Demo Buildings 15,000 cf 0.50 7,500
707 G1020 Site Demolition & Relocations - SF - 7,500
708
709 G1030 Site Earthwork
710 Excavate Elevator Pit 45 cy 15.00 675
711 Preparation Roadway & Sidewalk Areas 10,250 sf 4.00 41,000
712 G1030 Site Earthwork - SF - 41,675
713
714 G10 SITE PREPARATION - SF - 64,550
715
716 G20 SITE IMPROVEMENTS
717 G2020 Parking Lots
718 Bituminous Pavement 891 sy 30.00 26,730
719 Stripe Parking Spaces 12 ea 8.00 96
720 Handicap Symbol 3 ea 75.00 225
721 Granite Curb 514 lf 35.00 17,990
722 Cape Cod Berm 90 lf 8.00 720
723 G2020 Parking Lots - SF - 45,761
724
725 G2030 Pedestrian Paving
726 Entry Concrete Apron 400 sf 9.50 3,800
● Bldg, PP, UDF1, Uni 2,3 12 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
727 4" Concrete Sidewalk 2,198 sf 8.50 18,683
728 G2030 Pedestrian Paving - SF - 22,483
729
730 G2040 Site Development
731 Courtyard Finishes, Allowance 833 sf 8.00 6,664
732 G2040 Site Development - SF - 6,664
733
734 G2050 Landscaping
735 Swale 1,542 sf 3.50 5,397
736 G2050 Landscaping - SF - 5,397
737
738 G20 SITE IMPROVEMENTS - SF - 80,305
739
740 G30 SITE CIVIL/MECHANICAL UTILITIES
741 G3010 Water Supply
742 Relocate Water Line to Hydrant 50 lf 60.00 3,000
743 Relocate Hydrant 1 ea 2,500.00 2,500
744 G3010 Water Supply - SF - 5,500
745
746 G3030 Storm Sewer
747 Storm Pipe 186 lf 60.00 11,160
748 Catch Basins 1 ea 3,000.00 3,000
749 Area Drain 1 ea 850.00 850
750 G3030 Storm Sewer - SF - 15,010
751
752 G30 SITE CIVIL/MECHANICAL UTILITIES - SF - 20,510
753
754 G40 SITE ELECTRICAL UTILITIES
755 G4010 Electrical Distribution
756 Light Pole Bases 1 ea 350.00 350
757 E & B Lighting Conduit 100 lf 10.00 1,000
758 G4010 Electrical Distribution - SF - 1,350
759
760 G4020 Site Lighting
761 Conduit PVC Sch 40 1 in 150 lf 2.57 385
762 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
763 Wire THHN 8 AWG 525 lf 0.86 451
764 Fixture Pole Single 400w MH 25' 1 ea 2,063.96 2,064
765 - Excl Conduit & Wire
766 G4020 Site Lighting - SF - 2,900
767
768 G40 SITE ELECTRICAL UTILITIES - SF - 4,250
769
770 2.2 Elm St. & Town Hall Site Work - SF - 169,615
771
772 2 Phase 2 - SF - 841,974
773
774 3 Phase 3
775 3.1 Upper Town Hall Fitout
776 C10 INTERIOR CONSTRUCTION
777 C1010 Partitions
778 Interior Partition, 12' 60 lf 102.00 6,120
779 C1010 Partitions - SF - 6,120
780
781 C1020 Interior Doors
782 Interior Door, Frame & Hardware 3 ea 1,200.00 3,600
783 C1020 Interior Doors - SF - 3,600
784
785 C1030 Building Specialties
786 Toilet Accessories 2 ea 1,500.00 3,000
787 C1030 Building Specialties - SF - 3,000
● Bldg, PP, UDF1, Uni 2,3 13 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
788
789 C10 INTERIOR CONSTRUCTION - SF - 12,720
790
791 C30 INTERIOR FINISHES
792 C3010 Wall Finishes
793 Acoustical Banners 100 sy 15.00 1,500
794 Paint Interior Space 1,916 sf 4.00 7,664
795 C3010 Wall Finishes - SF - 9,164
796
797 C3020 Floor Finishes
798 Flooring 1,916 sf 8.00 15,328
799 C3020 Floor Finishes - SF - 15,328
800
801 C3030 Ceiling Finishes
802 Ceilings 1,916 sf 4.00 7,664
803 C3030 Ceiling Finishes - SF - 7,664
804
805 C30 INTERIOR FINISHES - SF - 32,156
806
807 D20 PLUMBING
808 D2010 Plumbing Fixtures
809 Set Fixtures in First Floor Toilets 4 ea 1,500.00 6,000
810 Fixtures at Second Floor Addition 10 ea 3,600.00 36,000
811 D2010 Plumbing Fixtures - SF - 42,000
812
813 D2020 Domestic Water Distribution
814 Domestic Water Piping 3,845 sf 0.75 2,884
815 Insulation Fiberglass All Service Jkt 3,845 sf 0.19 731
816 D2020 Domestic Water Distribution - SF - 3,614
817
818 D2030 Sanitary Waste
819 Sanitary and Vent Piping 3,845 sf 0.75 2,884
820 D2030 Sanitary Waste - SF - 2,884
821
822 D2040 Rain Water Drainage
823 Storm Piping - (NIC Gutter and Down Spout System) - NIC - -
824 D2040 Rain Water Drainage - SF - -
825
826 D2050 Specialty Gas Systems
827 Natural Gas Piping - (Included in Phase #1) - sf - -
828 D2050 Specialty Gas Systems - SF - -
829
830 D2090 Misc Materials & Methods
831 Misc Materials & Methods - sf - -
832 D2090 Misc Materials & Methods - SF - -
833
834 D20 PLUMBING - SF - 48,498
835
836 D30 HVAC
837 D3020 Heating Systems & Equipment
838 Hydronic Heating Equipment & Piping Included with Phase #1 - sf - -
839 D3020 Heating Systems & Equipment - SF - -
840
841 D3040 Air Distribution Systems & Equipment
842
Galvanized Ductwork -(Rework Ex Drops to match New Ceiling in Curtural
Center) 1,000 lbs 9.00 9,000
843 Galvanized Ductwork - (New Ductwork in 2nd Flr Wing.) 1,400 lbs 9.00 12,600
844 Duct Insulation Fiberglass Wrap - (Curtural Center) 550 sf 2.00 1,100
845 Duct Insulation Fiberglass Wrap - (New Ductwork in 2nd Flr Wing.) 750 sf 2.00 1,500
846 Supply, Exhaust, and Return Diffuser (Replace Damaged GRD's ) 3,845 sf 0.30 1,154
847 Supply, Exhaust, and Return Diffuser (2nd flr Wing Fit Out ) 1,811 sf 0.30 543
848 D3040 Air Distribution Systems & Equipment - SF - 25,897
● Bldg, PP, UDF1, Uni 2,3 14 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
849
850 D3070 Controls & Instrumentation
851 Direct Digital Controls 1,811 sf 1.47 2,662
852 D3070 Controls & Instrumentation - SF - 2,662
853
854 D3080 System Test & Balance
855 Air Systems Testing, Adjusting, & Balancing 1,811 sf 0.30 543
856 D3080 System Test & Balance - SF - 543
857
858 D3090 Misc HVAC Systems
859 Misc Materials & Methods 1,811 sf 0.50 906
860 D3090 Misc HVAC Systems - SF - 906
861
862 D30 HVAC - SF - 30,008
863
864 D40 FIRE PROTECTION
865 D4000 Fire Suppression
866 Previously Fit out in Phase 1 & 2 - NIC - -
867 D4000 Fire Suppression - SF - -
868
869 D40 FIRE PROTECTION - SF - -
870
871 D50 ELECTRICAL
872 D5025 POWER BRANCH WIRING
873 Receptacles 3,845 sf 1.53 5,894
874 D5025 POWER BRANCH WIRING - SF - 5,894
875
876 D5040 COMMUNICATIONS
877 Performance Space Lighting / Sound System 1 ea 59,487.16 59,487
878 Fire Alarm System 3,845 sf 1.59 6,119
879 Equipment Connections 3,845 sf 0.64 2,470
880 Communications Circuits 3,845 sf 0.76 2,930
881 D5040 COMMUNICATIONS - SF - 71,006
882
883 D50 ELECTRICAL - SF - 76,900
884
885 E10 EQUIPMENT
886 E1020 Institutional Equipment
887 Performance Space, Allowance 2,500 sf 70.00 175,000
888 E1020 Institutional Equipment - SF - 175,000
889
890 F2010 Building Elements Demolition
891 Demo Demountable Work Stations 4 ea 200.00 800
892 Demo Interior Handicap Ramp 269 sf 5.00 1,345
893 Demo Interior Partition, 12' 240 sf 1.76 421
894 F2010 Building Elements Demolition - SF - 2,566
895
896 E10 EQUIPMENT - SF - 177,566
897
898 3.1 Upper Town Hall Fitout - SF - 377,848
899
900 3 Phase 3 - SF - 377,848
901
902 1 Town Hall - SF - 2,873,894
903
904 2 Hildreth House
905 1 Phase 1
906 2.1.1 Elevator / Entry Core
907 F10 SPECIAL CONSTRUCTION
908 F1020 Integrated Construction
● Bldg, PP, UDF1, Uni 2,3 15 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
909 New Elevator and Stairway Core 1,800 sf 250.00 450,000
910 - Allowance partially based on earlier design.
911 Minor Interior Renovation and Sprinkler 4,700 ls 32.00 150,400
912 Structural Code Upgrades 1 ls 50,000.00 50,000
913 F1020 Integrated Construction - SF - 650,400
914
915 F10 SPECIAL CONSTRUCTION - SF - 650,400
916
917 2.1.1 Elevator / Entry Core - SF - 650,400
918
919 2.1.2 Entry Core & Parking Site Work
920 G10 SITE PREPARATION
921 G1010 Site Clearing
922 Site Preparation / Site Demo 15,000 sf 1.50 22,500
923 G1010 Site Clearing - SF - 22,500
924
925 G1030 Site Earthwork
926 Underpinning, Allowance 1 ea 10,000.00 10,000
927 Rock Excavation, Lower Level 112 cy 75.00 8,400
928 Rock Excavation, Elevator Pit 35 cy 100.00 3,500
929 Rock Excavation, Trench For Foundation 10 cy 175.00 1,750
930 Backfill Around Anchored Frost Wall 50 cy 20.00 1,000
931 Preparation Roadway & Sidewalk Areas 15,000 sf 4.00 60,000
932 G1030 Site Earthwork - SF - 84,650
933
934 G10 SITE PREPARATION - SF - 107,150
935
936 G20 SITE IMPROVEMENTS
937 A1030 Slab on Grade
938 Crushed Stone Over Rock Under SOG, 4' Avg. 810 tn 23.00 18,630
939 Crushed Stone Over Rock Under SOG, 6" 12 tn 23.00 276
940 A1030 Slab on Grade - SF - 18,906
941
942 G2020 Parking Lots
943 Fill For Parking Lot 1,500 cy 20.00 30,000
944 Bituminous Pavement 1,532 sy 30.00 45,960
945 Stripe Parking Spaces 28 ea 8.00 224
946 Handicap Symbol 4 ea 75.00 300
947 Granite Curb 330 lf 35.00 11,550
948 Cape Cod Berm 408 lf 8.00 3,264
949 G2020 Parking Lots - SF - 91,298
950
951 G2030 Pedestrian Paving
952 4" Concrete Sidewalk 1,100 sf 8.50 9,350
953 G2030 Pedestrian Paving - SF - 9,350
954
955 G2050 Landscaping
956 Landscape Area 890 sf 1.50 1,335
957 Swale 6,816 sf 3.50 23,856
958 G2050 Landscaping - SF - 25,191
959
960 G20 SITE IMPROVEMENTS - SF - 144,745
961
962 G30 SITE CIVIL/MECHANICAL UTILITIES
963 G3020 Sanitary Sewer
964 Sanitary Sewer Pipe 214 lf 60.00 12,840
965 Sanitary Manhole Precast 48" Dia x 5' Deep 1 ea 3,000.00 3,000
966 G3020 Sanitary Sewer - SF - 15,840
967
968 G3030 Storm Sewer
969 Storm Pipe 37 lf 60.00 2,220
● Bldg, PP, UDF1, Uni 2,3 16 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
970 Area Drain 1 ea 850.00 850
971 G3030 Storm Sewer - SF - 3,070
972
973 G30 SITE CIVIL/MECHANICAL UTILITIES - SF - 18,910
974
975 G40 SITE ELECTRICAL UTILITIES
976 G4010 Electrical Distribution
977 Light Pole Bases 4 ea 350.00 1,400
978 E & B Lighting Conduit 400 lf 10.00 4,000
979 G4010 Electrical Distribution - SF - 5,400
980
981 G40 SITE ELECTRICAL UTILITIES - SF - 5,400
982
983 2.1.2 Entry Core & Parking Site Work - SF - 276,205
984
985 1 Phase 1 - SF - 926,605
986
987 2 Phase 2
988 2.2.1 Multi-Purpose Pavilion Addition
989 F10 SPECIAL CONSTRUCTION
990 F1020 Integrated Construction
991 Total Pavilion Construction Cost 2,500 sf 200.00 500,000
992
- Unit SF cost based on 6,000 sf Unitarian Universalist Fellowship Building
benchmark adjusted for size and date of construction. Similar construction
including toilet rooms and kichen.
993 Enclose Existing Hildreth porch for Pavilion Access - ls - -
994 - Not Included.
995 F1020 Integrated Construction - SF - 500,000
996
997 F10 SPECIAL CONSTRUCTION - SF - 500,000
998
999 2.2.1 Multi-Purpose Pavilion Addition - SF - 500,000
1000
1001 2 Phase 2 - SF - 500,000
1002
1003 2 Hildreth House - SF - 1,426,605
1004
1005 3 Old Library
1006 1 Phase 1
1007 1 Code & Deferred Maintenance Upgrades
1008 A10 FOUNDATIONS
1009 A1010 Standard Foundations
1010 Concrete Foundation Walls - 4' Depth 51 lf 200.00 10,200
1011 Concrete Foundation Walls - 12' Depth @ Elev Shaft 33 lf 350.00 11,550
1012 Concrete Mat Foundation @ Elev Shaft (Incl E/B) 4 cy 300.00 1,200
1013 Support of Shaft wall Excav - Vert Wood Sheeting w/Whalers 1,200 sf 20.00 24,000
1014 A1010 Standard Foundations - SF - 46,950
1015
1016 A1030 Slab on Grade
1017 Slab on Grade 5" thick 193 sf 6.00 1,158
1018 A1030 Slab on Grade - SF - 1,158
1019
1020 A10 FOUNDATIONS - SF - 48,108
1021
1022 B10 SUPERSTRUCTURE
1023 B1010 Floor Construction
1024 Reframe 1st and 2nd floors @ Egress Stairs 200 sf 40.00 8,000
1025 Wood Roof Framing @ Entry 385 sf 30.00 11,550
1026 Reframe 1st and 2nd floors @ Old Stair Openings 140 sf 35.00 4,900
● Bldg, PP, UDF1, Uni 2,3 17 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1027 Subfloor 3/4" 340 sf 8.00 2,720
1028 Connect Roof and Floor to Masonry Walls 320 ea 75.00 24,000
1029 Structural Support at roof for rear Stair Wall being Removed 15 lf 100.00 1,500
1030 B1010 Floor Construction - SF - 52,670
1031
1032 B1020 Roof Construction
1033 Roof Sheathing 3/4" 385 sf 8.00 3,080
1034 B1020 Roof Construction - SF - 3,080
1035
1036 B10 SUPERSTRUCTURE - SF - 55,750
1037
1038 B20 EXTERIOR CLOSURE
1039 B2010 Exterior Walls
1040 CMU Back-up @ Exterior Walls 855 sf 16.00 13,680
1041 Standard Brick - Running Bond 855 sf 25.00 21,375
1042 Cut out CMU Wall for Door Opening 1 ea 800.00 800
1043 B2010 Exterior Walls - SF - 35,855
1044
1045 B2020 Exterior Windows
1046 Entrances & Storefronts @ Entry 100 sf 75.00 7,500
1047 Glass/Alum Entry Doors 2 ea 1,000.00 2,000
1048 Windows in New Addition 2 ea 1,750.00 3,500
1049 Replace Existing Windows 39 ea 1,900.00 74,100
1050 Replace Laylight Windows - Allowance 120 sf 100.00 12,000
1051 B2020 Exterior Windows - SF - 99,100
1052
1053 B2030 Exterior Doors
1054 Exterior HM Door 1 ea 1,000.00 1,000
1055 B2030 Exterior Doors - SF - 1,000
1056
1057 B20 EXTERIOR CLOSURE - SF - 135,955
1058
1059 B30 ROOFING
1060 B3010 Roof Coverings
1061 TPO Roofing 385 sf 20.00 7,700
1062 Misc PAtching and Repairs to Existing Slate Roof 1 ls 10,000.00 10,000
1063 - Based on 10% of Roof Area.
1064 B3010 Roof Coverings - SF - 17,700
1065
1066 B30 ROOFING - SF - 17,700
1067
1068 C10 INTERIOR CONSTRUCTION
1069 C1010 Partitions
1070 Int Borrowed Lites - Fire Rated Glass 63 sf 250.00 15,750
1071 Drywall w/ 7/8" Furring @ CMU Walls 3,100 sf 5.00 15,500
1072 Drywall w/ 3-5/8" 25 ga Stud 1,139 sf 8.00 9,112
1073 Drywall Ceilings Incl Framing 840 sf 7.00 5,880
1074 Misc Patching Allowance 6,106 sf 1.00 6,106
1075 Cutting and Patching for MEP Trades Allowance 1 ls 5,000.00 5,000
1076 Drywall 2-HR Walls 935 sf 12.00 11,220
1077 Cutting and Patching for Diaphragm Connections 320 ea 150.00 48,000
1078 C1010 Partitions - SF - 116,568
1079
1080 C1020 Interior Doors
1081 Interior Door Wood SC w/ KD Mtl Frame 11 ea 1,000.00 11,000
1082 Cut out CMU Wall for Door Opening 1 ea 800.00 800
1083 C1020 Interior Doors - SF - 11,800
1084
1085 C1030 Building Specialties
1086 Vanity Top - Plastic Laminate 18 lf 50.00 900
1087 C1030 Building Specialties - SF - 900
1088
● Bldg, PP, UDF1, Uni 2,3 18 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1089 C10 INTERIOR CONSTRUCTION - SF - 129,268
1090
1091 C20 STAIRS
1092 C2010 Stair Construction
1093 Entry Stairs and Handrail 6 rise 850.00 5,100
1094 Egress Stairs and Handrail 44 rise 850.00 37,400
1095 Egress Stair Landings 110 sf 55.00 6,050
1096 C2010 Stair Construction - SF - 48,550
1097
1098 C20 STAIRS - SF - 48,550
1099
1100 C30 INTERIOR FINISHES
1101 C3010 Wall Finishes
1102 Paint - Walls, Latex - Prime + 2 Finish Coats 14,455 sf 0.65 9,396
1103 Paint - Ceilings Latex - Prime + 2 Finish Coats 7,002 sf 1.00 7,002
1104 Ceramic Tile Wainscot on Wet Walls 130 sf 18.00 2,340
1105 C3010 Wall Finishes - SF - 18,738
1106
1107 C3020 Floor Finishes
1108 Patch Wood Flooring 340 sf 30.00 10,200
1109 Refinish Existing Wood Flooring 6,106 sf 2.50 15,265
1110 Ceramic Tile Flooring @ Toilet Rooms 439 sf 16.00 7,024
1111 Sheet Rubber Flooring @ Egress Stairs 240 sf 10.00 2,400
1112 Vinyl/Rubber Base @ All Walls 1,370 lf 2.75 3,768
1113 Carpet @ Entry 15 sy 40.00 600
1114 C3020 Floor Finishes - SF - 39,257
1115
1116 C3030 Ceiling Finishes
1117 Paint - GWB Ceilings and Soffits, Latex - Prime + 2 Finish Coats 6,100 sf 1.00 6,100
1118 C3030 Ceiling Finishes - SF - 6,100
1119
1120 C30 INTERIOR FINISHES - SF - 64,094
1121
1122 D10 CONVEYING
1123 D1010 Elevators & Lifts
1124 Hydraulic LULA Elevator 3 st 25,833.33 77,500
1125 D1010 Elevators & Lifts - SF - 77,500
1126
1127 D10 CONVEYING - SF - 77,500
1128
1129 D20 PLUMBING
1130 D2010 Plumbing Fixtures
1131 Fixture 7 ea 3,600.00 25,200
1132 D2010 Plumbing Fixtures - SF - 25,200
1133
1134 D2020 Domestic Water Distribution
1135 Domestic Water Piping 7,553 sf 0.75 5,665
1136 Insulation Fiberglass All Service Jkt 7,553 sf 0.50 3,777
1137 D2020 Domestic Water Distribution - SF - 9,441
1138
1139 D2030 Sanitary Waste
1140 Sanitary and Vent Piping 7,553 sf 1.00 7,553
1141 D2030 Sanitary Waste - SF - 7,553
1142
1143 D2040 Rain Water Drainage
1144 Storm Piping - (NIC Gutter and Down Spout System) 7,553 NIC - -
1145 D2040 Rain Water Drainage - SF - -
1146
1147 D2050 Specialty Gas Systems
1148 Natural Gas Piping 7,553 sf 0.75 5,665
1149 D2050 Specialty Gas Systems - SF - 5,665
1150
● Bldg, PP, UDF1, Uni 2,3 19 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1151 D2070 Plumbing System Equipment
1152 Electric Water Heater 1 ea 850.00 850
1153 D2070 Plumbing System Equipment - SF - 850
1154
1155 D2090 Misc Materials & Methods
1156 Misc Materials & Methods 7,553 sf 0.50 3,777
1157 D2090 Misc Materials & Methods - SF - 3,777
1158
1159 D20 PLUMBING - SF - 52,486
1160
1161 D30 HVAC
1162 D3020 Heating Systems & Equipment
1163 Heating Water Piping - (Existing and New) 7,553 sf 2.00 15,106
1164 Insulation Fiberglass All Service Jkt - (Repair and / or Replace) 7,553 sf 0.75 5,665
1165 Gas Fired Hot Water Boilers 1 ea 5,500.00 5,500
1166 Heating Water Equipment 7,553 sf 0.20 1,511
1167 Hydronic Fintube Baseboard Radiation - ( Repair and / or Replace) 7,553 sf 0.50 3,777
1168 Cabinet Unit Heaters 7,553 sf 0.20 1,511
1169 D3020 Heating Systems & Equipment - SF - 33,068
1170
1171 D3070 Controls & Instrumentation
1172 Direct Digital Controls 7,553 sf 3.00 22,659
1173 D3070 Controls & Instrumentation - SF - 22,659
1174
1175 D3080 System Test & Balance
1176 Air Systems Testing, Adjusting, & Balancing 7,553 sf 0.30 2,266
1177 D3080 System Test & Balance - SF - 2,266
1178
1179 D3090 Misc HVAC Systems
1180 Misc Materials & Methods 7,553 sf 0.50 3,777
1181 D3090 Misc HVAC Systems - SF - 3,777
1182
1183 D30 HVAC - SF - 61,770
1184
1185 D40 FIRE PROTECTION
1186 D4000 Fire Suppression
1187 Fire Protection Piping 7,553 sf 2.75 20,771
1188 Fire Suppression Equipment 7,553 sf 0.15 1,133
1189 Sprinkler Heads 70 ea 30.00 2,100
1190 Electric Fire Pump w/Controller & Jockey Pump 1 ea 30,000.00 30,000
1191 D4000 Fire Suppression - SF - 54,004
1192
1193 D4090 Misc Materials & Methods
1194 Misc Materials & Methods 7,553 sf 0.50 3,777
1195 D4090 Misc Materials & Methods - SF - 3,777
1196
1197 D40 FIRE PROTECTION - SF - 57,780
1198
1199 D50 ELECTRICAL
1200 D5000 ELECTRICAL
1201 Temporary Construction Lights, Power and FA 7,553 sf 1.04 7,866
1202 Electrical Fees & Permits 1 ea 2,578.88 2,579
1203 D5000 ELECTRICAL - SF - 10,445
1204
1205 D5011 LOW-VOLTAGE ELECTRICAL TRANSMISSION
1206 Service Panel 400 amp 208/120 volt 1 ea 3,748.88 3,749
1207 Distribution System Upgrades 7,553 sf 2.49 18,825
1208 D5011 LOW-VOLTAGE ELECTRICAL TRANSMISSION - SF - 22,574
1209
1210 D5015 EQUIPMENT CONNECTIONS
1211 Equipment Connections 7,553 sf 0.50 3,767
1212 D5015 EQUIPMENT CONNECTIONS - SF - 3,767
● Bldg, PP, UDF1, Uni 2,3 20 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1213
1214 D5020 LIGHTING
1215 Interior Light Fixtures and Controls 7,553 sf 0.73 5,479
1216 D5020 LIGHTING - SF - 5,479
1217
1218 D5025 POWER BRANCH WIRING
1219 Receptacles 7,553 sf 0.27 2,050
1220 D5025 POWER BRANCH WIRING - SF - 2,050
1221
1222 D5031 FIRE ALARM AND DETECTION SYSTEM
1223 Fire Alarm Replacement System 7,553 sf 2.21 16,703
1224 D5031 FIRE ALARM AND DETECTION SYSTEM - SF - 16,703
1225
1226 D5040 COMMUNICATIONS
1227 Security/Access Systems 7,553 sf 1.38 10,411
1228 D5040 COMMUNICATIONS - SF - 10,411
1229
1230 D50 ELECTRICAL - SF - 71,429
1231
1232 E20 FURNISHINGS
1233 E2010 Fixed Furnishings
1234 Recessed Aluminum Wall-Off Mat 80 sf 25.00 2,000
1235 E2010 Fixed Furnishings - SF - 2,000
1236
1237 E20 FURNISHINGS - SF - 2,000
1238
1239 F20 SELECTIVE BUILDING DEMOLITION
1240 F2010 Building Elements Demolition
1241 Demo interior of existing building 6,160 sf 5.00 30,800
1242
- includes library stacking system, central stair, interior non-load bearing
partitions, reception desk, existing plumbing fixtures, misc shelving, etc. to
leave an empty shell. Excludes attic floor mechanical area.
1243 Remove Wood Framing, Beams 340 sf 10.00 3,400
1244 Remove CMU Wall @ Existing Elevator 280 sf 4.00 1,120
1245 F2010 Building Elements Demolition - SF - 35,320
1246
1247 F20 SELECTIVE BUILDING DEMOLITION - SF - 35,320
1248
1249 G40 SITE ELECTRICAL UTILITIES
1250 G4010 Electrical Distribution
1251 Information-Circuit Rating 600 amp - -
1252 Conduit PVC Sch 40 3 in 400 lf 4.65 1,859
1253 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
1254 Conduit PVC Sch 40 4 in 200 lf 5.74 1,148
1255 - TraserSX - PVC CONDUIT&FITTINGS,P&C DUCT&FITTS
1256 Drag Line 100 lf 0.57 57
1257 Drag Line 100 lf 0.57 57
1258 Wire XHHW 1/0 AWG 206 lf 4.38 903
1259 - TraserSX - COPPER BUILDING WIRE
1260 Wire XHHW 350 MCM 824 lf 10.78 8,879
1261 - TraserSX - COPPER BUILDING WIRE
1262 Exterior Pad Mounted Transformer Pad Electrical 1 ea 842.83 843
1263 G4010 Electrical Distribution - SF - 13,746
1264
1265 G40 SITE ELECTRICAL UTILITIES - SF - 13,746
1266
1267 1 Code & Deferred Maintenance Upgrades - SF - 871,456
1268
1269 2 Pedestrian Access & Parking Upgrade
1270 G10 SITE PREPARATION
● Bldg, PP, UDF1, Uni 2,3 21 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1271 G1010 Site Clearing
1272 Topsoil, Strip and Stockpile 99 cy 4.00 396
1273 G1010 Site Clearing - SF - 396
1274
1275 G1020 Site Demolition & Relocations
1276 Demolish Pavement - Bituminous 10,420 sf 3.00 31,260
1277 Demo & Stockpile Curbs 1,329 lf 5.00 6,645
1278 Relocate Existing Catch Basin 1 ea 2,500.00 2,500
1279 G1020 Site Demolition & Relocations - SF - 40,405
1280
1281 G1030 Site Earthwork
1282 Rough Grading, General 15,749 sf 0.15 2,362
1283 Fine Grading 5,329 sf 0.25 1,332
1284 Excavation 200 cy 20.00 4,000
1285 G1030 Site Earthwork - SF - 7,695
1286
1287 G10 SITE PREPARATION - SF - 48,496
1288
1289 G20 SITE IMPROVEMENTS
1290 G2010 Roadways
1291 Asphalt Pavement & Base 562 sy 30.00 16,860
1292 Reinstall Existing Granite Curb 1,250 lf 10.00 12,500
1293 G2010 Roadways - SF - 29,360
1294
1295 G2030 Pedestrian Paving
1296 Concrete Sidewalk - 4" Conc over 4" Stone w/ WWF 3,225 sf 8.50 27,413
1297 G2030 Pedestrian Paving - SF - 27,413
1298
1299 G2050 Landscaping
1300 Replace Topsoil from Stockpile 225 cy 20.00 4,500
1301 Seeding [small area] 10,500 sf 0.25 2,625
1302 G2050 Landscaping - SF - 7,125
1303
1304 G20 SITE IMPROVEMENTS - SF - 63,898
1305
1306 G30 SITE CIVIL/MECHANICAL UTILITIES
1307 G3010 Water Supply
1308 Water Pipe, Ductile Iron 8" dia Incl Trenching 85 lf 70.00 5,950
1309 Wet Tap, 8" to 10" dia 1 ea 1,200.00 1,200
1310 Valve Gate w/Box 8" 1 ea 1,500.00 1,500
1311 G3010 Water Supply - SF - 8,650
1312
1313 G3020 Sanitary Sewer
1314 Abandon Septic Sewage Systems 1 ls 2,000.00 2,000
1315 Sewer Pipe, Ductile Iron 8" dia incl Trench & Backfill 50 lf 70.00 3,500
1316 Sanitary Manhole Precast 48" Dia x 6' Deep 1 ea 3,500.00 3,500
1317 G3020 Sanitary Sewer - SF - 9,000
1318
1319 G3060 Fuel Distribution
1320 Natural Gas Service Incl Trench & Backfill 120 lf 60.00 7,200
1321 G3060 Fuel Distribution - SF - 7,200
1322
1323 G30 SITE CIVIL/MECHANICAL UTILITIES - SF - 24,850
1324
1325 2 Pedestrian Access & Parking Upgrade - SF - 137,243
1326
1327 5 Alternate #1 - Cultural Center Fit-Out
1328 C10 INTERIOR CONSTRUCTION
1329 C1010 Partitions
1330 Drywall w/ 3-5/8" 25 ga Stud (750) sf 8.00 (6,000)
1331 Drywall 2-HR Walls (500) sf 12.00 (6,000)
● Bldg, PP, UDF1, Uni 2,3 22 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1332 Drywall 2-HR Walls 420 sf 12.00 5,040
1333 Drywall w/ 3-5/8" 25 ga Stud 1,260 sf 8.00 10,080
1334 C1010 Partitions - SF - 3,120
1335
1336 C1020 Interior Doors
1337 Interior Door Wood SC w/ KD Mtl Frame (9) ea 1,000.00 (9,000)
1338 Cut out CMU Wall for Door Opening 1 ea 800.00 800
1339 Interior Door Wood SC w/ KD Mtl Frame 10 ea 1,000.00 10,000
1340 C1020 Interior Doors - SF - 1,800
1341
1342 C1030 Building Specialties
1343 Vanity Top - Plastic Laminate (2) lf 50.00 (100)
1344 C1030 Building Specialties - SF - (100)
1345
1346 C10 INTERIOR CONSTRUCTION - SF - 4,820
1347
1348 C30 INTERIOR FINISHES
1349 C3010 Wall Finishes
1350 Paint - Walls, Latex - Prime + 2 Finish Coats 860 sf 0.65 559
1351 C3010 Wall Finishes - SF - 559
1352
1353 C3020 Floor Finishes
1354 Ceramic Tile Flooring @ Toilet Rooms (38) sf 16.00 (608)
1355 Carpet 402 sy 35.00 14,070
1356 Vinyl/Rubber Base @ All Walls 75 lf 2.75 206
1357 C3020 Floor Finishes - SF - 13,668
1358
1359 C3030 Ceiling Finishes
1360 Acoustical Ceiling 458 sf 4.00 1,832
1361 Paint - GWB Ceilings and Soffits, Latex - Prime + 2 Finish Coats (458) sf 1.00 (458)
1362 C3030 Ceiling Finishes - SF - 1,374
1363
1364 C30 INTERIOR FINISHES - SF - 15,601
1365
1366 D20 PLUMBING
1367 D2010 Plumbing Fixtures
1368 No Plumbing Required - sf - -
1369 D2010 Plumbing Fixtures - SF - -
1370
1371 D20 PLUMBING - SF - -
1372
1373 D30 HVAC
1374 D3020 Heating Systems & Equipment
1375 Heating Water Piping - (Repair and / or Replace) - Included in Base Bid - sf - -
1376 D3020 Heating Systems & Equipment - SF - -
1377
1378 D3070 Controls & Instrumentation
1379 Direct Digital Controls - Included in Base Bid - sf - -
1380 D3070 Controls & Instrumentation - SF - -
1381
1382 D3080 System Test & Balance
1383 Air Systems Testing, Adjusting, & Balancing - Included in Base Bid - sf - -
1384 D3080 System Test & Balance - SF - -
1385
1386 D3090 Misc HVAC Systems
1387 Misc Materials & Methods - Included in Base Bid - sf - -
1388 D3090 Misc HVAC Systems - SF - -
1389
1390 D30 HVAC - SF - -
1391
1392 D40 FIRE PROTECTION
1393 D4000 Fire Suppression
● Bldg, PP, UDF1, Uni 2,3 23 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1394 Fire Protection - Included in Base Bid - sf - -
1395 D4000 Fire Suppression - SF - -
1396
1397 D40 FIRE PROTECTION - SF - -
1398
1399 D50 ELECTRICAL
1400 D5015 EQUIPMENT CONNECTIONS
1401 Equipment Connections 7,553 sf 0.50 3,767
1402 D5015 EQUIPMENT CONNECTIONS - SF - 3,767
1403
1404 D5020 LIGHTING
1405 Interior Light Fixtures and Controls 7,553 sf 5.61 42,349
1406 D5020 LIGHTING - SF - 42,349
1407
1408 D5025 POWER BRANCH WIRING
1409 Receptacles 7,553 sf 1.26 9,527
1410 D5025 POWER BRANCH WIRING - SF - 9,527
1411
1412 D5040 COMMUNICATIONS
1413 Security/Access Systems 7,553 sf 1.38 10,411
1414 Fit Out MDF Closet 1 ea 7,629.11 7,629
1415 Fit Out IDF Closet 1 ea 3,463.55 3,464
1416 Communications Circuits 7,553 sf 0.76 5,756
1417 Audio / Visual System 7,553 ea 1.38 10,411
1418 D5040 COMMUNICATIONS - SF - 37,671
1419
1420 D50 ELECTRICAL - SF - 93,314
1421
1422 5 Alternate #1 - Cultural Center Fit-Out - SF - 113,736
1423
1424 6 Alternate #2 - Council on Aging Fit-Out
1425 C10 INTERIOR CONSTRUCTION
1426 C1010 Partitions
1427 Int Borrowed Lites - Fire Rated Glass (63) sf 250.00 (15,750)
1428 Drywall w/ 3-5/8" 25 ga Stud 2,040 sf 8.00 16,320
1429 Drywall 2-HR Walls 575 sf 12.00 6,900
1430 Drywall w/ 3-5/8" 25 ga Stud (750) sf 8.00 (6,000)
1431 Drywall 2-HR Walls (500) sf 12.00 (6,000)
1432 Folding Partition including Overhead Support 255 sf 45.00 11,475
1433 Folding Partition Soffit 17 lf 50.00 850
1434 C1010 Partitions - SF - 7,795
1435
1436 C1020 Interior Doors
1437 Interior Door Wood SC w/ KD Mtl Frame (9) ea 1,000.00 (9,000)
1438 Cut out CMU Wall for Door Opening 1 ea 800.00 800
1439 Interior Door Wood SC w/ KD Mtl Frame 15 ea 1,000.00 15,000
1440 C1020 Interior Doors - SF - 6,800
1441
1442 C1030 Building Specialties
1443 Vanity Top - Plastic Laminate 5 lf 50.00 250
1444 C1030 Building Specialties - SF - 250
1445
1446 C10 INTERIOR CONSTRUCTION - SF - 14,845
1447
1448 C30 INTERIOR FINISHES
1449 C3010 Wall Finishes
1450 Paint - Walls, Latex - Prime + 2 Finish Coats 2,730 sf 0.65 1,775
1451 C3010 Wall Finishes - SF - 1,775
1452
1453 C3020 Floor Finishes
1454 Quarry Tile @ Kitchen 298 sf 25.00 7,450
● Bldg, PP, UDF1, Uni 2,3 24 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1455 Ceramic Tile Flooring @ Toilet Rooms (58) sf 16.00 (928)
1456 Carpet 355 sy 35.00 12,425
1457 Vinyl/Rubber Base @ All Walls 160 lf 2.75 440
1458 C3020 Floor Finishes - SF - 19,387
1459
1460 C3030 Ceiling Finishes
1461 Acoustical Ceiling 567 sf 4.00 2,268
1462 Paint - GWB Ceilings and Soffits, Latex - Prime + 2 Finish Coats (567) sf 1.00 (567)
1463 C3030 Ceiling Finishes - SF - 1,701
1464
1465 C30 INTERIOR FINISHES - SF - 22,863
1466
1467 D20 PLUMBING
1468 D2010 Plumbing Fixtures
1469 Fixture 4 ea 3,600.00 14,400
1470 D2010 Plumbing Fixtures - SF - 14,400
1471
1472 D2020 Domestic Water Distribution
1473 Domestic Water Piping 126 sf 10.00 1,260
1474 Insulation Fiberglass All Service Jkt 126 sf 7.50 945
1475 D2020 Domestic Water Distribution - SF - 2,205
1476
1477 D2030 Sanitary Waste
1478 Sanitary and Vent Piping 126 sf 15.00 1,890
1479 D2030 Sanitary Waste - SF - 1,890
1480
1481 D2040 Rain Water Drainage
1482 Storm Piping - (NIC Gutter and Down Spout System) - NIC - -
1483 D2040 Rain Water Drainage - SF - -
1484
1485 D2070 Plumbing System Equipment
1486 Electric Water Heater 126 sf 8.00 1,008
1487 D2070 Plumbing System Equipment - SF - 1,008
1488
1489 D2090 Misc Materials & Methods
1490 Misc Materials & Methods 126 sf 0.50 63
1491 D2090 Misc Materials & Methods - SF - 63
1492
1493 D20 PLUMBING - SF - 19,566
1494
1495 D30 HVAC
1496 D3020 Heating Systems & Equipment
1497 Heating Water Piping 126 sf 8.00 1,008
1498 Insulation Fiberglass All Service Jkt 126 sf 4.00 504
1499 Cabinet Unit Heaters 126 sf 5.00 630
1500 D3020 Heating Systems & Equipment - SF - 2,142
1501
1502 D3070 Controls & Instrumentation
1503 Direct Digital Controls - Included in Base Bid - sf - -
1504 D3070 Controls & Instrumentation - SF - -
1505
1506 D3080 System Test & Balance
1507 Air Systems Testing, Adjusting, & Balancing - Included in Base Bid - sf - -
1508 D3080 System Test & Balance - SF - -
1509
1510 D3090 Misc HVAC Systems
1511 Misc Materials & Methods - Included in Base Bid - sf - -
1512 D3090 Misc HVAC Systems - SF - -
1513
1514 D30 HVAC - SF - 2,142
1515
1516 D40 FIRE PROTECTION
● Bldg, PP, UDF1, Uni 2,3 25 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1517 D4000 Fire Suppression
1518 Fire Protection Piping 126 sf 2.75 347
1519 Sprinkler Heads 2 ea 30.00 60
1520 D4000 Fire Suppression - SF - 407
1521
1522 D4090 Misc Materials & Methods
1523 Misc Materials & Methods 126 sf 0.50 63
1524 D4090 Misc Materials & Methods - SF - 63
1525
1526 D40 FIRE PROTECTION - SF - 470
1527
1528 D50 ELECTRICAL
1529 D5015 EQUIPMENT CONNECTIONS
1530 Equipment Connections 7,553 sf 0.65 4,896
1531 D5015 EQUIPMENT CONNECTIONS - SF - 4,896
1532
1533 D5020 LIGHTING
1534 Interior Light Fixtures and Controls 7,553 sf 5.61 42,349
1535 D5020 LIGHTING - SF - 42,349
1536
1537 D5025 POWER BRANCH WIRING
1538 Receptacles 7,553 sf 1.26 9,527
1539 D5025 POWER BRANCH WIRING - SF - 9,527
1540
1541 D5040 COMMUNICATIONS
1542 Security/Access Systems 7,553 sf 1.38 10,411
1543 Fit Out MDF Closet 1 ea 7,629.11 7,629
1544 Fit Out IDF Closet 1 ea 3,463.55 3,464
1545 Communications Circuits 7,553 sf 0.76 5,756
1546 Audio / Visual System 7,553 ea 1.38 10,411
1547 D5040 COMMUNICATIONS - SF - 37,671
1548
1549 D50 ELECTRICAL - SF - 94,443
1550
1551 E10 EQUIPMENT
1552 E1010 Commercial Equipment
1553 Food Service Equipment Allowance 298 sf 250.00 74,500
1554 E1010 Commercial Equipment - SF - 74,500
1555
1556 E10 EQUIPMENT - SF - 74,500
1557
1558 6 Alternate #2 - Council on Aging Fit-Out - SF - 228,828
1559
1560 7 Council on Aging Site Work
1561 B30 ROOFING
1562 B3010 Roof Coverings
1563 Sidewalk Awning Incl Pier Footers 800 sf 125.00 100,000
1564 B3010 Roof Coverings - SF - 100,000
1565
1566 B30 ROOFING - SF - 100,000
1567
1568 G10 SITE PREPARATION
1569 G1010 Site Clearing
1570 Topsoil, Strip and Stockpile 14 cy 4.00 56
1571 G1010 Site Clearing - SF - 56
1572
1573 G1020 Site Demolition & Relocations
1574 Demolish Pavement - Bituminous 1,715 sf 3.00 5,145
1575 Demo & Stockpile Curbs 130 lf 5.00 650
1576 G1020 Site Demolition & Relocations - SF - 5,795
1577
1578 G1030 Site Earthwork
● Bldg, PP, UDF1, Uni 2,3 26 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1579 Rough Grading, General 2,947 sf 0.15 442
1580 Fine Grading 1,200 sf 0.25 300
1581 Excavation 60 cy 20.00 1,200
1582 G1030 Site Earthwork - SF - 1,942
1583
1584 G10 SITE PREPARATION - SF - 7,793
1585
1586 G20 SITE IMPROVEMENTS
1587 G2010 Roadways
1588 Asphalt Pavement & Base 49 sy 30.00 1,456
1589 Stripe Parking Spaces 39 ea 8.00 312
1590 Linestriping, Crosswalk 140 lf 10.00 1,400
1591 Handicap Symbol 5 ea 75.00 375
1592 Reinstall Existing Granite Curb 258 lf 10.00 2,580
1593 G2010 Roadways - SF - 6,123
1594
1595 G2030 Pedestrian Paving
1596 Concrete Sidewalk - 4" Conc over 4" Stone w/ WWF 640 sf 8.50 5,440
1597 G2030 Pedestrian Paving - SF - 5,440
1598
1599 G20 SITE IMPROVEMENTS - SF - 11,563
1600
1601 7 Council on Aging Site Work - SF - 119,356
1602
1603 8 Cultural Center Site Work
1604 B30 ROOFING
1605 B3010 Roof Coverings
1606 Sidewalk Awning - sf - -
1607 - Not Included.
1608 B3010 Roof Coverings - SF - -
1609
1610 B30 ROOFING - SF - -
1611
1612 G10 SITE PREPARATION
1613 G1010 Site Clearing
1614 Topsoil, Strip and Stockpile 11 cy 4.00 44
1615 G1010 Site Clearing - SF - 44
1616
1617 G1020 Site Demolition & Relocations
1618 Demolish Pavement - Bituminous 620 sf 3.00 1,860
1619 Demo & Stockpile Curbs 75 lf 5.00 375
1620 G1020 Site Demolition & Relocations - SF - 2,235
1621
1622 G1030 Site Earthwork
1623 Rough Grading, General 1,230 sf 0.15 185
1624 Fine Grading 614 sf 0.25 154
1625 Excavation 22 cy 20.00 440
1626 G1030 Site Earthwork - SF - 778
1627
1628 G10 SITE PREPARATION - SF - 3,057
1629
1630 G20 SITE IMPROVEMENTS
1631 G2010 Roadways
1632 Patch Asphalt Pavement 1 ls 2,500.00 2,500
1633 Stripe Parking Spaces 33 ea 8.00 264
1634 Linestriping, Crosswalk 140 lf 10.00 1,400
1635 Handicap Symbol 2 ea 75.00 150
1636 Reinstall Existing Granite Curb 147 lf 10.00 1,470
1637 G2010 Roadways - SF - 5,784
1638
1639 G2030 Pedestrian Paving
● Bldg, PP, UDF1, Uni 2,3 27 of 28 1/24/2011 3:34 PM
SKANSKA USA BUILDING, INC.
253 Summer Street, Boston, MA 02210
PROJECT - Town of Harvard ESTIMATE REVISION - 3 ; DATED - 1/24/2011
CLIENT - Town of Harvard PROJECT NO. - 1310822-PDS
LOCATION - Harvard, MA BUILDING AREA - 0 SF
ESTIMATE TYPE - Cost Model
Index Description Qty Unit Unit Cost Total
1640 Concrete Sidewalk - 4" Conc over 4" Stone w/ WWF 470 sf 8.50 3,995
1641 G2030 Pedestrian Paving - SF - 3,995
1642
1643 G20 SITE IMPROVEMENTS - SF - 9,779
1644
1645 8 Cultural Center Site Work - SF - 12,836
1646
1647 1 Phase 1 - SF - 1,483,455
1648
1649 3 Old Library - SF - 1,483,455
1650
● Bldg, PP, UDF1, Uni 2,3 28 of 28 1/24/2011 3:34 PM