1
0.00 -18.30 Tie in Compression Tie in Tension Bending moments without ties Bending moments with ties Mt Wind loads Rx Mw 20.90m 18.90m Why prestressed concrete cable? As protection for fire To decrease shrinkage stresses 42 cm 42 cm 5,9 m Slab Slab Steel plate 5 mm Cables Paseo de la Castellana Paseo de Recoletos Plaza de &ROyQ The principal vertical load of the structure is the slab self-weight. These loads are collected by the prestressed cables and travel to the head. The head transfers the load to the core and the core to the foundation. The cables are precompressed and the slab self-weight generates a decompression in the cables. The head behavior seem a cantilever. Upper head The upper head is an element strongly stressed. For this reason the structure is very rigid but not slender. It has two different parts: - Four cantilevers as a prolongation of the core walls. The cantilevers are 60 cm thick and their depth varies from 5m to 3m. -Four edge beams that are supported by the cantilevers with a constant depth of 3 m and a thickness of 50 cm. All these beams are prestressed in three stages. The hollow of the upper head is reserved for the engine room. - Basement excavation. - Beginning execution basement storeys. - Core elevation - Building slurry wall. - Driving piles. - Core foundation. - Transversal prestress. - Spread footing in piles. - End core elevation. - Head execution. - End basement. - Odd slab execution - Construction of even slabs while supporting on the odd ones. - End slabs execution - Intermediate floors execution - Constructional finishings Continuous waffle slab - 25 cm thick - Due to the slab continuity some embedment effects appears. The efficiency of the ties is reduced on the lower storeyes - Bending moments increase in the lower beams. At that location, more reinforcement need to be located Reinforcement Top face reinforcement concentration area Bottom and top face reinforcement concentration area In addition, a compression slab will be constituted over the waffle slab. It will have a two way reinforcement. Metallic cantilever where the slab supports Central core Dimensions: 7m x 6,8 m; Wall thickness: 0,6 m Place where the stiffness is concentrated. Used for vertical communications and halls. It has 7 gaps to go in every storey Emergency stairs hollow Spandrel beam Torre de Colon ties are aproximately square (42 cm x 42 cm). Inside they have a core (27 cm x 10 cm) where prestressed cables are located. They were prefabricated before. By lengths of 5,9 m (corresponding to the heigth of two storeys). Except for the first one, which lengths is 6,15 m. Underground parking Four of the six buried storeys are used as car parking, while the rest two holds the building hall and the mechanicall facility room. They have around 1700 m 2 . Their structures are formed by reinforced concrete slabs 40 cm thick, which were lighted with plastic coffers. Pile distribution is not regular, to avoid affecting the traffic requirements. Spans are around 11 m. Towers cores are used too to support of the storeys. Building Foundations First of all, a perimetral slurry wall is constructed using bentonite. Piles (60 cm in diameter) are used to support buried floors are embedded. Over these piles, columns will be constructed. Cores are supported by a spread foundations. They are square and 13 m side and reinforced with usual passive steel and eight prestressed cables. These foundations were joint to the core through transversal prestressed. Diggings had be done without the help of soil anchorages. This is due to Metro closeness. Prestressed concrete ties Standard storie and core Edge beams Cantilevers Prestressed reinforcement Figure 4. 3D view Prestressed concrete ties Core Storey Upper head The joint with the upper head is a neoprene support in order to allow elastic shortments produced by creep or shrinkage. On the other hand, joints between prefabricated pieces of ties are made of epoxi. Tower Intermediate floors Basement Slurry wall Against wind loads, the tower presents two coupled mechanisms. The first one of these mechanism is formed by the bending stiffness of the central core, working as a cantilever. The second one is produced by the external ties. The axial stiffness of the straps is quite bigger than the bending stiffness of the core. The axial force of the straps determines at that point a bending moment, and therefore a deflection in the opposite direction of the generated by wind pressures. The point of hanging buildings, related to the wind effect, is that the core is extremely compressed which is optimal to resist bending moments. Self-weight axial diagram Prestress axial diagram Total axial diagram Tie axial diagram Structural Elements Located in Plaza de &ROyQ in the meeting of Paseo de la Castellana and Paseo de Recoletos. This place is Madrid's downtown, where the most important buildings and streets are. Figure 1. &ROyQ 6TXDUH Structural Behavior to Horizontal Loads Structural Behavior to Vertical Loads Construction Process Structural Behavior of Slabs Vertical loads Horizontal loads Upper head bending moments Prestress reinforcement Architectural design is determined from the following ideas: x Need to a better traffic organization in the parking area. x Structural independence between the building and the basement. x Interior flexibility. Is all built in concrete because: x Similar construction time. x Fire protection. x Better behavior in temperature expansions. Slabs are continuous along all the surface. 7KDW iV the reason why they work as an embeddeb beam, even though they are simply supported at the core. In suspension buildings the bigger the ratio h1/a (where h1 referst to suspended heigth; a refer to building side) is, the less effective the ties are. 7KDW iV why number of stories is limited. Therefore, lower beams work almost as embedded beams. "To begin building a house from the roof" Architectural Conception General Data Colon Towers were presented at the World Congress on Prestressed Concrete in Architecture and Public Works held in New York in 1975 as the building erected as the most advanced tecnology available in Spain at the time. In 1989 the building was reformed, adding a new colored grass IDoDGH a external fire scape between the towers and an upper closing with the form of a plug. Shear Bending moments x )HUQiQGH] Casado, C., Manterola, J. y )HUQiQGH] Troyano, L. 1977. Estructura de las Torres &ROyQ Instituto Eduardo Torroja. 0DGULG Informes de la &RQVWUXFFLyQ 1977. SiJV Q DJRVWRVHSWLHPEUH x *XWLpUUH] 5RGUtJXH] E. Edificio colgante: las 7RUUHV GH &ROyQ >3UHVHQWDFLyQ@ x Las Torres &ROyQ y la iglesia de Torre Ciudad. )HUQiQGH] Casado, C. 1973. [ed.] $VRFLDFLyQ 7pFQLFD (VSDxROD del Pretensado. 107, 0DGULG s.n., 1973, +RUPLJyQ y Acero, SiJV 343-347. x 3pUH] *XWLpUUH] M.C. 2009. (YROXFLyQ del tipo estructural "torre" en (VSDxD [ed.] Escuela 7pFQLFD Superior de Arquitectura (UPM). 0DGULG VQ x Torres &ROyQ Lamela, A. y )HUQiQGH] Casado, C. 1974. [ed.] $VRFLDFLyQ 7pFQLFD (VSDxROD del Pretensado. 112, 0DGULG s.n., +RUPLJyQ \ $FHUR SiJV References Authors *RQ]DOR GH OD &UX] $OFDOi 5LFDUGR *RQ]iOH] 3DODFLRV November 2014 A TOUR GUIDE OF HIGH-RISE BUILDINGS: TORRES CMain advantages: x Simultaneous construction of the upper and lower structure, accelerating the path of construction, reduces the execution time and overhead. x This technique allowed to reduce from -24.75 m to -17.95 m, which reduced economic and technical costs of time. x It allowed to save 9% steel, 10% concrete and 19% in workdays Figure 2. 7RUUHV &ROyQ 'UDZLQJ Figure 3. 6LJKW 7RUUHV &ROyQ Figure 5. 7RUUHV &ROyQ FRUH Figure 6. 7RUUHV &ROyQ 7LHV

Torres Colon.pdf

Embed Size (px)

Citation preview

0.00

-18.30

Tie in

Com

pres

sion

Tie in

Ten

sion

Bending momentswithout ties

Bending momentswith ties

Mt Wind loads

RxMw

20.90m

18.90m

Why prestressedconcrete cable? As protection

for fire

To decreaseshrinkage stresses

42 cm

42 cm

5,9 m

Slab

Slab

Steel plate 5 mm

Cables

Pase

o de

la C

aste

llana

Pase

o de

Rec

olet

os

Plaza deColón

The principal vertical load of the structure is the slab self-weight. These loads are collected by the prestressed cables and travel to the head.The head transfers the load to the core and the core to the foundation.

The cables are precompressed and the slab self-weight generates a decompression in the cables.

The head behavior seem acantilever.

Upper headThe upper head is an element strongly stressed. For this reason the structure is very rigid but not slender.It has two different parts:- Four cantilevers as a prolongation of the core

walls. The cantilevers are 60 cm thick and their depth varies from 5m to 3m.

-Four edge beams that are supported by thecantilevers with a constant depth of 3 m anda thickness of 50 cm.

All these beams are prestressed in three stages.The hollow of the upper head is reserved for the engine room.

- Basement excavation.- Beginning execution

basement storeys. - Core elevation

- Building slurry wall.- Driving piles.- Core foundation.

- Transversal prestress.- Spread footing in piles.- End core elevation.

- Head execution.- End basement.

- Odd slab execution - Construction of even slabswhile supporting on the oddones.

- End slabs execution - Intermediate floors execution- Constructional finishings

Continuous waffle slab- 25 cm thick- Due to the slab continuity some

embedment effects appears. The efficiency of the ties is reduced on the lower storeyes

- Bending moments increase in thelower beams. At that location, more reinforcement need to be located

Reinforcement

Top face reinforcement concentration area

Bottom and top face reinforcement concentration area

In addition, a compression slab will be constituted over the waffle slab. It will have a two way reinforcement.

Metallic cantileverwhere the slab supports

Central coreDimensions: 7m x 6,8 m; Wall thickness: 0,6 m Place where the stiffness is concentrated.Used for vertical communications and halls. It has 7 gaps to go in every storey

Emergencystairs hollow

Spandrel beam

Torre de Colon ties are aproximately square (42 cm x 42 cm). Inside they have a core (27 cm x 10 cm) where prestressed cables are located.

They were prefabricated before. By lengths of 5,9 m (corresponding to the heigth of two storeys). Except for the first one, which lengths is 6,15 m.

Underground parkingFour of the six buried storeys are used as car parking, while the rest two holds the building hall and the mechanicall facility room. They have around 1700 m2.

Their structures are formed by reinforced concrete slabs 40 cm thick, which were lighted with plastic coffers.

Pile distribution is not regular, to avoid affecting the traffic requirements. Spans are around 11 m. Towers cores are used too to support of the storeys.

Building FoundationsFirst of all, a perimetral slurry wall is constructed using bentonite. Piles (60 cm in diameter) are used to support buried floors are embedded. Over these piles, columns will be constructed.

Cores are supported by a spread foundations. They are square and 13 m side and reinforced with usual passive steel and eight prestressed cables. These foundations were joint to the core through transversal prestressed.

Diggings had be done without the help of soil anchorages. Thisis due to Metro closeness.

Prestressed concrete ties

Standard storie and core

Edge beams

Cantilevers

Prestressed reinforcement

Figure 4. 3D view

Prestressed concrete ties

Core

Storey

Upper head

The joint with the upper head is a neoprene support in order to allow elastic shortments produced by creep or shrinkage. On the other hand, joints between prefabricated pieces of ties are made of epoxi.

Tower

Intermed

iate floorsBasem

ent

Slurry wall

Against wind loads, the tower presents two coupled mechanisms. The first one of these mechanism is formed by the bending stiffness of the central core, working as a cantilever. The second one is produced by the external ties.

The axial stiffness of the straps is quite bigger than the bending stiffness of the core. The axial force of the straps determines at that point a bending moment, and therefore a deflection in the opposite direction of the generated by wind pressures.

The point of hanging buildings, related to the wind effect, is that the core is extremely compressed which is optimal to resist bending moments.

Self-weightaxial diagram

Prestress axialdiagram

Total axialdiagram

Tie axial diagram

Structural Elements

Located in Plaza de Colón,in the meeting of Paseo dela Castellana and Paseode Recoletos. This place isMadrid's downtown, wherethe most importantbuildings and streets are.

Figure 1. Colón Square.

Structural Behavior to Horizontal Loads

Structural Behavior to Vertical Loads

Construction Process

Structural Behavior of SlabsVertical loads Horizontal loads

Upper head bending moments Prestress reinforcement

Architectural design is determined from the following ideas:

Need to a better traffic organization in theparking area.

Structural independence between the building and the basement.

Interior flexibility.

Is all built in concrete because:

Similar construction time.

Fire protection.

Better behavior in temperature expansions.

Slabs are continuous along all the surface. That is the reason why they work as an embeddeb beam, even though they are simply supported at the core.

In suspension buildings the bigger the ratio h1/a (where h1 referst to suspended heigth; a refer to building side) is, the less effective the ties are. That is why number of stories is limited.

Therefore, lower beams work almost as embeddedbeams.

"To begin building a house from the roof"

Architectural Conception

General Data

Colon Towers were presented at theWorld Congress on Prestressed Concretein Architecture and Public Works held inNew York in 1975 as the building erectedas the most advanced tecnologyavailable in Spain at the time.

In 1989 the building was reformed,adding a new colored grass façade, aexternal fire scape between the towersand an upper closing with the form of aplug.

Shear

Bending moments

Fernández Casado, C., Manterola, J. yFernández Troyano, L. 1977. Estructura de lasTorres Colón. Instituto Eduardo Torroja.Madrid : Informes de la Construcción, 1977.págs. 61-94. nº 293 agosto-septiembre.

Gutiérrez Rodríguez, E. Edificio colgante: lasTorres de Colón. [Presentación]

Las Torres Colón y la iglesia de Torre Ciudad.Fernández Casado, C. 1973. [ed.] AsociaciónTécnica Española del Pretensado. 107,Madrid : s.n., 1973, Hormigón y Acero, págs.343-347.

Pérez Gutiérrez, M.C. 2009. Evolución del tipoestructural "torre" en España. [ed.] EscuelaTécnica Superior de Arquitectura (UPM).Madrid : s.n., 2009.

Torres Colón. Lamela, A. y FernándezCasado, C. 1974. [ed.] Asociación TécnicaEspañola del Pretensado. 112, Madrid : s.n.,1974, Hormigón y Acero, págs. 71-88.

References

Authors

Gonzalo de la Cruz AlcaláRicardo González Palacios

November 2014

A TOUR GUIDE OF HIGH-RISE BUILDINGS: TORRES COLÓN.

Main advantages:

Simultaneous construction of the upper and lowerstructure, accelerating the path of construction, reduces the execution time and overhead.

This technique allowed to reduce from -24.75 m to -17.95m, which reduced economic and technical costs of time.

It allowed to save 9% steel, 10% concrete and 19% inworkdays

Figure 2. Torres Colón Drawing

Figure 3. Sight Torres Colón

Figure 5. Torres Colón core.

Figure 6. Torres Colón Ties