Topshop Oxford Circus 020 8253 4588 www.kpsltd.co.uk Airport House, Purley Way, Croydon, CR0 0XZ Works completed: May 2019 Type of Client: Retail Arcadia Group Duration of Works: 6 weeks Value of Works: £150,000.00 (approx) Knightsbridge Property Services were successfully awarded a project to undertake an important job for one of it largest retail customers. The works consistent of fixing and stabilising internal fit out rafts across a number of floors within the Oxford Street flagship store. Collaboratively working with structural engineer drawings Shop floor cleared and reinstated on completion Works completed outside normal working hours Access hatches installed over the rafts Each raft made good and decorated Works carried out in 6 hour shifts Project Overview: Successful Outcomes: The team from Knightsbridge Property Services liaised heavily with the on site Arcadia team to pre-programme the works in. All the client requests were met, with a heavy focus on not affecting the general operations of the store. The structural report was followed to in details, with reporting provided by the team detailing indexed fixing locations and materials used. All works were successfully signed off by the structural engineers and client team. Handovers with shift managers at the beginning and end of each shift

Topshop Oxford Circus - kpsltd.co.uk€¦ · Topshop Oxford Circus 020 8253 4588 Airport House, Purley Way, Croydon, CR0 0XZ Works completed: May 2019 Type of Client: Retail Arcadia

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Topshop Oxford Circus

020 8253 4588 www.kpsltd.co.uk

Airport House, Purley Way, Croydon, CR0 0XZ

Works completed: May 2019Type of Client: Retail Arcadia GroupDuration of Works: 6 weeksValue of Works: £150,000.00 (approx)

Knightsbridge Property Services were successfully awarded a project to undertake animportant job for one of it largest retail customers. The works consistent of fixing andstabilising internal fit out rafts across a number of floors within the Oxford Street flagshipstore.

Collaboratively working with structural engineer drawings

Shop floor cleared and reinstated on completion

Works completed outside normal working hours

Access hatches installed over the rafts

Each raft made good and decorated

Works carried out in 6 hour shifts

Project Overview:

Successful Outcomes:

The team from Knightsbridge Property Services liaised heavily with the on site Arcadia team to pre-programme the worksin. All the client requests were met, with a heavy focus on not affecting the general operations of the store. The structuralreport was followed to in details, with reporting provided by the team detailing indexed fixing locations and materialsused. All works were successfully signed off by the structural engineers and client team.

Handovers with shift managers at the beginning and end of each shift