Upload
sandycse2005
View
212
Download
1
Embed Size (px)
DESCRIPTION
Theory of constraints
Citation preview
Theory of Constraints:
A look at the Drum-Buffer-Rope and Critical Chain Project Management approach
EMGT 364 Term PaperJesse Crispino and Ryan Saulsbury
Theory of Constraints
Developed by Eliyahu M. GoldrattA systems management philosophy
developed in the 1980sBoost process performance by looking
at the entire processIdentifying and reducing “bottlenecks”Often applied in conjunction with
TQM, JIT and ABM
Theory of Constraints
Project managers have always analyzed individual components of a process
Maximizing components may not improve the process
Goldratt views the entire process and finds the weakest link--Capacity Constrained Resource (CCR)
All projects contain one, but not many CCRs
Theory of Constraints: Principles
If a system is performing as well as it can, only one of its component parts will be.
If all parts are performing as well as they can, the system as a whole will not be.
Inertial is the worst enemy of a process of ongoing improvement. Solutions develop weight that resists change.
Ideas are not solution.
Theory of Constraints: Steps
Goldratt’s Five Steps Identify the systems constraints Decide how to exploit the constraints Subordinate everything else to the
exploitation of constraints Elevate the systems constraint If any constraints have been violated,
repeat the process
Theory of Constraints: Defined
Constraint: Anything that limits a system’s performance relative to its goal
Inventory: All the money used to purchase things the system intends to sell
Operating expense: The money a system spends to turn inventory into throughput
Throughput accounting: An accounting system used to measure TOC operations
Theory of Constraints: Defined
Throughput: the difference between net revenues and direct material cost limited by internal constraints (plant capacity) limited by external constraints (market demand)
Two critical assumptions: The goal of product or customer mix and
volume should be to maximize throughput Assumes that once a certain capacity exists,
operating expenses are fixed
Theory of Constraints: Applied
Soldier analogy:Gaps appear due to
Dependent events Statistical fluctuation
Drum-Buffer-Rope (DBR) system links first “soldier” with the slowest one
Drum-Buffer-Rope (DBR)
Logistical tool that balances flow of a system
Drum: A schedule for capacity of the constraint
Buffer: Built in time for parts to reach the constraint early (in process inventory)
Rope: A schedule, or information connection, for releasing raw materials
Drum-Buffer-Rope: Implementing
Identify CCRs-Pareto’s Rule may helpSchedule CCRs to capacity (drum)Protect from statistical fluctuations with
time buffers (buffer)Monitor CCRs to ensure the timely
release of materials “upstream” (rope)Monitor Buffer--Buffer Management
(BM)
Drum-Buffer-Rope: Case Study #1
Oregon Freeze Dry: Four step process wash/prepare food freeze food in cold room dry food to remove ice crystals (sublimation) packaging/shipping
Difficulty finding space in cold room--wash/preparation was very quick
Considered buying new cold room
Drum-Buffer-Rope: Case Study #1
Reduced the amount of raw food going into wash phase
Cold room scheduled by using a BTU calculation for max efficiency
Less product in cold room created faster freezing rates.
Oregon Freeze uses only 30% of cold room capacity and produces a higher quality product
Drum-Buffer-Rope: Case Study #2
Wendell August Forge: Hand-hammered aluminum commemorative items
Six production cellsExpected hammering to be drumWalk on shop floor showed buffing
backup to be CCRUnion mandated breaks
Drum-Buffer-Rope: Case Study #2
Break schedule staggered--exploitationCapacity immediately increased 12%Implemented a Rope to limit raw materialsWork in progress inventories decreasedManagers educated on TOC attitudesCapacity up 27% by years
Critical Chain Project Management
Traditional project management, Critical Path Method (CPM) used for over 40 years
DoD projects: 100-200% more expensive, and exceeded duration 40-50% of the time
Commercial projects: 70% more expensive, and exceeded duration 40% of the time
Goldratt’s 1997 book Critical Chain--new paradigm for PMs
People plan and execute projects
Critical Chain Project Management
Accounts for human nature factors Individuals always desire a safety buffer Goldratt’s “student syndrome” Parkinson’s law--Work expands to fill the
time allotted PM multi-tasking reduces efficiency and
penalizes the highest priority No early finishes
Critical Chain Project Management
CPM: Tasks scheduled as soon as possible (ASAP)
CCPM: Tasks scheduled as late as possible (ASLP) Reduce work in progress Reduce up-front costs PMs focus on first tasks Increased knowledge as project progresses
Critical Chain Project Management
ALAP drawback: As the project progresses, all tasks become critical to project completion
Goldratt’s solution: Drum-Buffer-Rope logistical scheduling and consolidated safety buffers
CCPM: Re-define Your Paradigm
CCPM requires individual and organizational behavior changes
Locate and remove hidden safety buffersEmbrace uncertainty vs attempting better
estimatesA 50% change of completing a task on-time
is acceptable--Do not measure against baseline
“Tell me how you will measure me and I will tell you how I will behave”
CCPM: Implementing
Assume all material and information for tasks are on-hand
Resolve resource conflictsLocate the Critical Chain--longest
chain of tasks that consider both task and resource dependencies
Critical Path--longest chain of tasks based upon task dependencies
CCPM: Implementing
Individual projects no longer have safety buffer
Two types of safety buffers are inserted into the project as a whole Project Buffer: protects against overruns
on the critical chain Feeding Buffer: protects against
overruns on tasks that feed the critical chain
CPM vs CCPM
CPM: Tasks have scheduled start and finish dates Early finishes on critical path do not
accumulate Project is on time or late
CCPM: Relay race analogy Tasks are scheduled by preceding tasks
completion
CPM vs CCPM
CCPM will finish tasks fasterProject team’s moral and effectiveness
will improveProject teams/project managers can
produce early finishesOverall costs will decline
Critical Chain: Case Study #1
Harris Semi-conductor: $250M new wafer fabrication plant
Typical construction time 54 monthsCPM analysis yielded 6000 tasksCritical chain analysis reduced to 150
tasks40 day delay for weather15 day delay for equipment problems
Critical Chain: Case Study #1
Buffers allowed for project delaysProject completed 3 days ahead of
schedulePlant constructed in 13 monthsOverall cost only 4% above estimateWafer Fabrication plant able to produce
products 40 months faster than the industry standard
Critical Chain:Case Study #2
Habitat for Humanity: World Record attempt for building a house
Old record: 4hrs 39min, Nashville--1998Critical Chain method predicted 4 hoursBathroom finished 1 hour longer than
estimatedOverall finishing time: 3hrs 44min
In Class Example:
You are a new plant manager for LETZ GETZ BLITZED BREWING CO INC.
You need to re-work the production line soon because your boss, CEO Always Hammered is getting thirsty for the profits so to speak.
Your Suppliers Bottle Cap Billy, and Hops McGee are consistently late. Your line supervisor Mr. Schmidt explains that those producers are from Denmark and the delays are due to rotten shipping.
In Class Example: Current Situation:
The Hops & Malt used in the brewing process is suppose to arrive on the 1st of each month but it can arrive 1 day late.
Yeast is purchased in bulk and is delivered on the 4th of the month. The line supervisor claims yeast requires 4 days of preparation before being added to the WORT.
Packaging is delivered on the 11th of the month and requires imprinting and then fix/assembly (2days total)
Your bottles are delivered on the 15th. You can fix the labels and assemble the packaging after your bottles arrive.
Bottle caps are suppose to arrive on the 16th but lately they have been a day late.
You are unable to obtain new suppliers because of existing contracts signed by the CEO.
In Class Example:
The following is a general concept of how to make the beer in your factory: Step 1: You can start by creating the WORT. A process
that includes adding water, hops, malt and then a boiling/cooling process. ( 1 day)
Step 2: Transfer to the fermenter where the yeast is added
Step 3: Fermentation (10 days-Cannot be reduced) Step 4: Final Preparation includes: Siphon beer to
remove yeast sediment, Add Sugar-Bitters added to product to produce, and carbonation (4 days)
Step 5: Bottling/Packaging (2 days)
In Class Example CCPM:
Develop a CCPM for the Beer Making ProcessRemember: Reduce the Critical Path by 50%,
Project Buffer(5 days) Feeder Buffer(2 total)
Critical Chain vs Critical Path for Army/UMR?
Must teach both techniques CCPM CPM
Army constrained by resources Operations difficult to apply Maintenance has potential
Key differences ASAP vs. ASLP Buffer Management