Purpose
This Job Aid provides you with a document that describes how to perform the task. You can print this document or save it to your local hard drive.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
2/60
Procedure
1. Follow the steps below to complete the task:
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
2. The Risk Assessment Approvals training.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
3/60
Important Note:The steps demonstrating how to navigate to the Risk Assessment will be provided in the future as the navigation process is finalized.
The Manage Risk Assessment Approvals training provides the steps for:
Submitting a Risk Assessment for Approval, Approving or Denying a Risk Assessment, and Overriding an Approval.
For additional information on completing a Risk Assessment, review theTM Case - Manage Risk Assessment training module.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
3. Click the Actions menu in the General Information section to access the Approval functions.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
4/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
4. Select the Approval menu item.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
5/60
Submit Risk Assessment for Approval
Upon completion of the Risk Assessment, you will be able to submit the Risk Assessment for Approval.
To start, click the Approval list item.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
5. The Risk Assessment Approval pop-up window displays.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
6/60
The Risk Assessment Approval pop-up window displays.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
6. The Request Risk Assessment Approval area is enabled.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
7/60
The Request Risk Assessment Approval area is enabled if there are no Approval History records or the last Approval History record was denied or overridden.
For this example, the Request Risk Assessment Approval is enabled. To start, click in the Send To textbox.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
7. The Send To field.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
8/60
The Send To field will list the supervisor of the County and the supervisors for all Administration Groups and Units of the County.
The Send To field defaults to one of the supervisors if:
the worker’s supervisor (based on primary affiliation) is one of the supervisors, or
the worker only has one supervisor that is available.
The supervisor will be able to select themselves in the Send To field.
To start, click in the Send To field.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
8. Click in the Send To textbox.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
9/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
9. As required, complete/review the following fields: Field DescriptionSend To
Example: Cg
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
10/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
10. Select the Cgi Qa Test1 list item.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
11/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
11. The Submitted By default display.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
12/60
The Submitted By field displays [Signed on User’s First Name ] [Signed on User’s Last Name] on [Current Date] [Current Time]. This field cannot be changed.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
12. Click in the Comments textbox.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
13/60
The Comments field is blank by default and required to submit a request for the Risk Assessment approval.
For this example, click in the Comments textbox to begin.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
13. As required, complete/review the following fields: Field DescriptionComments
Example: C
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
14/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
14. Select the Comments required menu item.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
15/60
The Comments field will list recent comments beginning with the characters entered. You can also enter a unique comment.
For this example, select the Comments required menu item.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
15. Click the Submit button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
16/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
16. Warning! Message when Risk Factor section is incomplete.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
17/60
A Warning! message displays if a Risk Assessment is submitted for approval without completely filling out the Risk Factors section including comments entered for Yes responses.
For this example, click OK and complete the Risk Factors section prior to submitting for approval.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
17. Click the OK button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
18/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
18. Click the X to close the Risk Assessment Approval window.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
19/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
19. Click the Actions menu.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
20/60
After responding to each question in the Risk Factors section including providing comments for each Yes response, you are ready to submit the Risk Assessment for Approval.
To start, click the Actions menu in the General Information section to access the Approval functions.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
20. Select the Approval menu item.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
21/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
21. Click the Submit button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
22/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
22. The Risk Assessment Approval History is updated with the Approval request.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
23/60
When the Request for Approval is successful...
An Approval History record is created with the request information.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
23. Request Risk Assessment Approval displays and is read only.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
24/60
The Request Approval panel is visible but disabled and displays the last request information.
The Submit button in the Request Approval panel changes to Approval Requested.
A Notification is sent to the Send To supervisor.
When the Request for Approval is successful...
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
24. The Approve Risk Assessment panel displays and is enabled.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
25/60
The Approve Risk Assessment panel displays and is enabled for the supervisor to approve or deny the Risk Assessment.
When the Request for Approval is successful...
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
25. Click the Disposition radio button for Yes to Approve the Risk Assessment.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
26/60
Approve Risk Assessment
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
26. The Dispositioned By and Notify Requester? fields.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
27/60
The Dispositioned By field displays [Signed on User’s First Name ] [Signed on User’s Last Name] on [Current Date] [Current Time].
The Notify Requester? field defaults to No when the disposition is set to Approve but can be changed.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
27. Click in the Comments field to add comments regarding the Approval.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
28/60
Comments are optional if the Risk Assessment is Approved.
For this example, click in the Comments field to add comments.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
28. The optional Comments added for you.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
29/60
For this example, the Comments have been added for you.
Next, click the Submit button to Approve this Risk Assessment.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
29. Click the Submit button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
30/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
30. The Risk Assessment Approval window displays again.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
31/60
The Approval History record is refreshed to include the approved information.
The Risk Assessment Approval pop-up window displays again.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
31. The Request Risk Assessment Approval displays and is read-only.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
32/60
The Request Approval panel is visible but disabled and displays the last request information.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
32. The Approve Risk Assessment panel displays and is disabled.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
33/60
The Approve Risk Assessment panel displays but is disabled and displays the last request information.
The Override Approval button will display for Approved Risk Assessments.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
33. Override Approval for Risk Assessment
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
34/60
Override Approval for Risk Assessment
A supervisor will be able to Override an Approval if:
The last Approval History record was approvedAnd
The supervisor is affiliated to the County of the Primary Worker's assignment to the Assessment or Case.
For this example, these conditions are met. To start, select the Override Approval button.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
34. Click the Override Approval button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
35/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
35. The Override Risk Assessment Approval panel displays.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
36/60
The Override Risk Assessment Approval panel displays.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
36. The Overridden By field.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
37/60
The Overridden By field defaults to the [Signed on Users First Name ] [Signed on Users Last Name] on [Current Date] [Current Time].
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
37. Click in the Comments field.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
38/60
Comments are required if the Risk Assessment Approval is overridden.
For this example, click in the Comments field to add comments.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
38. The comments have been added for you.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
39/60
For this example, the Comments have been added for you.
Next, click the Submit button to Override the Risk Assessment approval.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
39. Click the Submit button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
40/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
40. Return to the Risk Assessment Approval window.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
41/60
You return to the Risk Assessment Approval window.
The Risk Assessment Approval History disposition is updated to Overridden.
The Request Risk Assessment Approval panel is enabled to enter another Approval request.
To start, click in the Send To field to enter a supervisor's name to send the Approval Request.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
41. Click in the Send To textbox.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
42/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
42. As required, complete/review the following fields: Field DescriptionSend To
Example: Cg
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
43/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
43. For this example, select the Cgi Qa Test1 menu item.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
44/60
Remember, Supervisors will be able to select themselves as the Send To supervisor for approval.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
44. Comments are required and entered for you on an Approval Request.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
45/60
Comments are required for an Approval Request. They have been added for you.
Next, click the Submit button to Request Approval for the Risk Assessment.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
45. Click the Submit button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
46/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
46. The Risk Assessment Approval window displays the Approve Risk Assessment panel.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
47/60
You return to the Risk Assessment Approval window.
The Risk Assessment Approval History disposition is refreshed with the Request for Approval.
The Request Risk Assessment Approval panel displays the recent request information but is disabled.
The Approve Risk Assessment panel displays and is enabled to Approve or Deny the Risk Assessment.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
47. Click the No radio button for the Disposition to Deny the Approval Request.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
48/60
Deny Risk Assessment
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
48. The Notify Requester? is set to Yes and not editable.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
49/60
If the Risk Assessment Approval is denied, the Notify Requester? field defaults to Yes and cannot be changed.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
49. Comment are required if a Risk Assessment is denied.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
50/60
Comments are required when the approval is denied. They have been added for you.
Next, click the Submit button to deny the Risk Assessment.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
50. Click the Submit button.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
51/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
51. Click the X to close the Risk Assessment Approval pop-up Window.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
52/60
You return to the Risk Assessment Approval window with an updated Approval History and the Request Risk Assessment Approval panel enabled.
After reviewing, close the Risk Assessment Approval panel.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
52. The Risk Assessment displays.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
53/60
The Risk Assessment displays.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
53. Review the Risk Assessment Approval History
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
54/60
The Risk Assessment Approval History is refreshed for each Approval cycle including:
Approval Requests Approvals Overrides Denials
To start, click the Actions menu to access the Approval window.
Review the Risk Assessment Approval History
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
54. Click the Actions menu.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
55/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
55. Select the Approval menu item.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
56/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
56. TheRisk Assessment Approval pop-up window displays.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
57/60
The Risk Assessment Approval pop-up window displays.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
57. The Risk Assessment Approval History panel.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
58/60
The panel is sorted by Dispositioned Date from newest to oldest.
The Risk Assessment Approval History panel displays one row per approval cycle.
The Disposition displays the status of the Approval including Requested, Approved, Denied, and Overridden.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
58. Scroll right to view additional Risk Assessment Approval History information.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
59/60
Scroll right to view additional Risk Assessment Approval History fields.
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
59. After reviewing the information, click the X to close the window.
TM Case - Manage Risk Assessment Approvals
Wednesday, May 16, 2018Copyright 2016 State of Colorado
60/60
https://trails-dev-ete.state.co.us/RiskAssessment/Details/2061241 - Google Chrome
60. Return to the Risk Assessment page.
You return to the Risk Assessment page.