Upload
arthur-ward
View
214
Download
0
Embed Size (px)
Citation preview
TIME MANAGEMENT
Definition: Time management is a set of principles, practices, skills, tools, and systems that work together to help you get more value out of your time with the aim of improving the quality of your project.
1
PROJECT MANAGEMENT GROUPS AND KNOWLEDGE AREAS MAPPING
Knowledge Area
Initiating Process Group
Planning Process Group
Executing Process Group
M& CProcess Group
Closing Process Group
6.Project Time Management
6.1 Define activities.
6.2 Sequence activities.
6.3 Estimate activities resources.
6.4 Estimate activity duration.
6.5 Develop schedule
6.6 Control schedule.
2
DEFINE ACTIVITIES
INPUTS OUTPUTS
1. Scope Baseline.2. Enterprise Environmental
Factors.3. Organizational Process
Assets
1. Activity List2. Activity attributes3. Milestone List
3
SEQUENCE ACTIVITIES
INPUTS OUTPUTS
1. Activity List2. Activity attributes3. Milestone List4. Project Scope Statement5. Organizational Process
Assets
1. Project Schedule Network Diagrams
2. Project Document updates
4
ESTIMATE ACTIVITY RESOURCES
INPUTS OUTPUTS
1. Activity List2. Activity attributes3. Resource Calendars4. Enterprise Environmental
Factors5. Organizational Process
Assets
1. Activity Resource Requirements
2. Resource Breakdown Structure
3. Project Document Updates
5
ESTIMATE ACTIVITY DURATIONS
INPUTS OUTPUTS
1. Activity List2. Activity attributes3. Activity Resource
Requirements4. Resource Calendars5. Project Scope Statement6. Enterprise Environmental
Factors7. Organizational Process
Assets
1. Activity Duration Estimates2. Project Document Updates
6
DEVELOP SCHEDULEINPUTS OUTPUTS
1. Activity List2. Activity attributes3. Project Schedule Network
Diagrams4. Activity Resource
Requirements5. Resource Calendars6. Activity Duration Estimates7. Project Scope Statement8. Enterprise Environmental
Factors9. Organizational Process
Assets
1. Project Schedule2. Schedule Baseline3. Schedule Data4. Project Document Updates
7
PROJECT MANAGEMENT GROUPS AND KNOWLEDGE AREAS MAPPING
Knowledge Area
Initiating Process Group
Planning Process Group
Executing Process Group
M& CProcess Group
Closing Process Group
6.Project Time Management
6.1 Define activities.
6.2 Sequence activities.
6.3 Estimate activities resources.
6.4 Estimate activity duration.
6.5 Develop schedule
6.6 Control schedule.
8
CONTROL SCHEDULE
INPUTS OUTPUTS1. Project Management Plan2. Project Schedule3. Work Performance
Information4. Organizational Process
Assets
1. Work Performance Measurements
2. Organizational Process Assets Updates
3. Change requests4. Project Management Plan
Updates5. Project Document Updates
9
SCHEDULE MANAGEMENT PLAN
Schedule Management Plan Includes: Schedule Methodology and Software Establishment of a Schedule Baseline for Measuring
against during the Monitoring and Controlling Process Group
Identification of the Performance Measures to Identify Variances early
Planning for how Schedule Variances will be Managed Identification of Schedule Change Control Procedures
10
DEFINE ACTIVITIES
Taking Work packages in WBS and breaking it down to activity level.
Milestones are significant in schedule not work activities.
11
SEQUENCE ACTIVITIES
Activities, Milestones and Starting to Sequence them into the work will be preformed = Network Diagram and not a PERT chart
Start End
12
RELATIONSHIPS BETWEEN ACTIVITIES
Finish to Start (FS)
Dig Hole Plant Tree
Start to Start (SS)
Design
Code
13
NETWORK DIAGRAM
• Network Diagram can be use to:– Justify time estimate for the project– Aid in Effective planning, Organizing and
Controlling the project– Show Interdependencies of all activities– Show Workflow – what activities need to happen
in a specific sequence– Identify opportunities to compress the schedule
in planning and throughout the life of the project– Show project progress when used for controlling
the schedule and reporting
15
TYPES OF DEPENDENCIES
Mandatory Dependency (Hard Logic) Discretionary Dependency (Preferred, Preferential
or Soft Logic) External Dependency
16
ESTIMATE ACTIVITY DURATIONS
How is Estimating done? One point Estimate – One person one estimate
per activity Analogous Estimating – Top down (total project
estimate) Parametric Estimating – History (estimate per
activity) Heuristics Estimating – 80 / 20 Three point estimate – Pert analysis
18
THREE POINT ESTIMATE FORMULAS Important Formulas can be use for both Time and Cost estimates
Expected Activity Duration
(P + 4M +O)6
Activity Variance
(P - O)6
Activity Standard Deviation
(P + O)6
2
LEGEND: P = Pessimistic,M = Most Likely,O = Optimistic
19
DEVELOP SCHEDULE
Schedule Network Analysis Critical Path method Schedule Compression
Fast Track Crashing
What-if Scenario analysis Monte Carlo Analysis
Resource leveling Critical Chain method
20
FLOAT / SLACK
Total Float: Amount of time an activity can be delayed without delaying the project end date or an intermediary milestone
Free Float: Amount of time an activity can be delayed without delaying the early start date of its successor(s)
Project Float: Amount of time a project can be delayed without delaying the externally imposed project completion date
21
IMPORTANT FORMULAS
Formula for establish Float (Slack)
Equation Float = Late Start – Early Start
Or
Equation Float = Late Finish – Early Finish
22
NODE DIAGRAM
ES
LS LF
EF
Activity Name
Amount of Float
LEGEND:ES = Early StartEF = Early FinishLS = Late StartLF = Late Finish
23
PASS DIAGRAM
ES
LS LF
EF
Activity Name
Amount of Float
LEGEND:ES = Early StartEF = Early FinishLS = Late StartLF = Late Finish
Forward Pass
Backward Pass
24
CONTROL SCHEDULE
Control means measuring against the plan. Schedule control means looking for things
causing changes and influencing them to change.
Assist in conducting performance reviewals. Reestimating
25