26
Spring 2008, King Saud Time and Cost Control Dr. Khalid Al-Gahtani 1 Updating Construction Schedules Procedure: Change the duration of all completed activities to zeros. Identify all activities on which work is currently proceeding as live activities. Put early start time of live activities equals the update time and their durations equal the remaining duration given by the update report. Change durations of future activities as given in the update report.

Time cost-control

Embed Size (px)

Citation preview

Page 1: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

1

Updating Construction Schedules• Procedure:

– Change the duration of all completed activities to zeros.

– Identify all activities on which work is currently proceeding as live activities.

– Put early start time of live activities equals the update time and their durations equal the remaining duration given by the update report.

– Change durations of future activities as given in the update report.

– Carry out network analysis in the normal way and prepare a new activity schedule.

Page 2: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

2

Example

Page 3: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

3

Example• The position of the activities at the end of the fifth

week is as follows:– Activities B, C, D and E have been completed.– Activity F is ready to start at beginning of week 6.– Remaining duration of activity H is 4 weeks.– Remaining duration of activity I is 3 weeks.– Activity G will not start until end of week 7.– Volume of work in activity L has been increased by 33%

approximately.– Activity J has been omitted.– It is decided to shorten activity K by 2 weeks.

• Construct the updated schedule indicating the critical path and showing new activities times.

Page 4: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

4

Page 5: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

5

Work Breakdown Structure • WBS divides the project into recognizable systems (work

packages, WP’s or Bid Packages) that responsible assignable work units, and for which accountability can be expected/assigned.

Project

Work Packages

Activities Sequencing

Page 6: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

6

Traditional A/E PDS

Owner

A/E GC

Sub1 Sub2 Sub3 Sub4

Page 7: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

7

Professional Construction Management

Owner

CM

WP1 WP2 WP3 WP4 WP4

A/E

Page 8: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

8

Developing WPs

• Develop WBS – Identify WPs

• Draw a WPs Network

WP1

WP2

WP3

WP4

WP5

WP6

Page 9: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

9

Developing WPs• Each WP must have

– One Performing Agency (PA) such as Subcontractor

– One Responsible Agency (RA) such owner’s Project Engineers

• Interconnection between Packages should be district and clear to facilitate coordination

WP1 WP2

WP3

Page 10: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

10

Developing WPs• Bid a WP at the most short time so as to

stimulate competition (Keep away uncertainty)

WP1 WP2 WP3 WP4

Page 11: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

11

Cost Coding System

• Cost Central level = Lowest level at which functional responsibility for individual WBS element exit. – XXX XXX XXX XXX

• An example:– 0534.02220.21.A.00.cf34

Page 12: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

12

MASTERFORMAT system TABLE 1 Major Divisions in the Uniform Construction Index

0 Conditions of the contract 1 General requirements 2 Site work 3 Concrete 4 Masonry 5 Metals 6 Wood and plastics 7 Thermal and moisture prevention 8 Doors and windows

9 Finishes 10 Specialties 11 Equipment 12 Furnishings 13 Special construction 14 Conveying system 15 Mechanical 16 Electrical

Page 13: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

13

Cost Coding System• Advantages of coding systems are:

– Provide a numbering system to replace verbal descriptions of items.

– These codes reduce the length or complexity of the information to be recorded.

– aids consistency in definitions and categories between projects and among the various parties involved in a project.

– aid in the retrieval of historical records of cost, productivity and duration on particular activities.

– electronic data storage and retrieval operations are much more efficient with standard coding systems.

Page 14: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

14

Project Cost Control • Budgeted Cost of Work Scheduled (BCWS) is the

budgeted amount of cost of the work scheduled to be accomplished in a given time period (including support and allocated overhead).

• Budgeted Cost of Work Performed (BCWP) is the budgeted amount of cost for the work completed in a given time period, including support effort and allocated overhead. (This is sometimes referred to as “earned value of work accomplished”.)

• Actual Cost of Work Performed (ACWP) is the amount reported as actually expended in completing the particular work accomplished within a given time period.

Page 15: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

15

Type of performance BCWP

BCWS

ACWP

Fast & Low

ACWP

BCWP

BCWS

Fast & High

B CW S

B CW P

A CW P

S low & Low

BCWS

BCWP

S low & High

ACWP

Page 16: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

16

Type of performance BCWP

BCWS

ACWP

Fast & Low

ACWP

BCWP

BCWS

Fast & High

B CW S

B CW P

A CW P

S low & Low

BCWS

BCWP

S low & High

ACWP

Page 17: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

17

Type of performance BCWP

BCWS

ACWP

Fast & Low

ACWP

BCWP

BCWS

Fast & High

B CW S

B CW P

A CW P

S low & Low

BCWS

BCWP

S low & High

ACWP

Page 18: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

18

Type of performance BCWP

BCWS

ACWP

Fast & Low

ACWP

BCWP

BCWS

Fast & High

B CW S

B CW P

A CW P

S low & Low

BCWS

BCWP

S low & High

ACWP

Page 19: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

19

Cost IndexCost Variance = BCWP ACWP +ve Under Budget Cost Variance 0 Within Budget - ve Over Budget Cost Performance Index = BCWP/ACWP > 1 Under Budget CPI = 1 Within Budget < 1 Over Budget % cost overrun/underrun

= BCWP

BCWPACWP ,

Page 20: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

20

Schedule Index

Schedule/Performance Variance=BCWP-BCWS. +ve Ahead Schedule Sch./per. Variance 0 On Schedule -ve Behind Schedule Schedule Performance Index = BCWP/ BCWS. >1 Ahead Schedule SPI =1 On Schedule <1 Behind Schedule

Page 21: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

21

Estimated Cost/Time At CompletionBudgeted Cost At Completion (BAC)

= Total of Quantities Unit price

Planned Time At Completion (TAC)

= Total of Quantities ÷ Planned Productivity

Estimated Cost At Completion (EAC)

= ToDate

ToDate

BCWPACWP BAC =

ToDateCPIBAC

To Date Variance Time

= ToDateToDate

ToDate Time1BCWSBCWP

Budgeted Cost At Completion (BAC)

= Total of Quantities Unit price

Planned Time At Completion (TAC)

= Total of Quantities ÷ Planned Productivity

Estimated Cost At Completion (EAC)

= ToDate

ToDate

BCWPACWP BAC =

ToDateCPIBAC

To Date Variance Time

= ToDateToDate

ToDate Time1BCWSBCWP

More accurate estimate can be reached by using these formulas:

Estimated Cost At Completion (EAC)

= ThisPeriod

DateToToDate CPI

)BCWP-(BACACWP

Estimated Time At Completion (ETAC)

= ThisPeriod

ToDateThisPeriodToDate BCWP

)BCWP-(BACTime Time

Page 22: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

22

Page 23: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

23

Project Example

Page 24: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

24

Project Example

Page 25: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

25

ENGINEERING SUBTASKS STATUS AT END OF MONTH 3 (thousands of dollars)

Task Status BCWS BCWP ACWP System design Completed $131.0 $131.0 $144.0 Subcontract specs Started 132.0 82.0 84.0 Material tests Completed 22.0 22.0 22.5 Specs review Started 22.0 15.0 15.5 Drafting Started 97.0 59.0 59.0 Fabrication/assembly support Completed 29.0 29.0 36.0 Fabrication/assembly process Started 100.0 63.0 67.0 Test support Started 21.0 21.0 21.0 Engineering release and review Not Started

Total $554.0 $422.0 $449.0

Project Example

Page 26: Time cost-control

Spring 2008, King Saud University

Time and Cost ControlDr. Khalid Al-Gahtani

26

Project ExampleFigure 5-9 Status summary of engineering subtasks in progress and estimate to complete.

Task BCWS BCWP ACWP Status Subcontract specs $132 $82 $84 Behind schedule and over cost Specs review 22 15 15.5 Behind schedule and over cost Drafting 97 59 59 Behind schedule but within cost Fabrication/assembly process 100 63 67 Behind schedule and over cost Test support 21 21 21 On schedule and within cost

Estimated to complete: 765442449 =$812 K

Summary: Engineering work is behind schedule and a cost overrun is occurring