Upload
sandyarajagopalan321
View
222
Download
0
Embed Size (px)
Citation preview
7/29/2019 T&I Periodic
1/20
Electrical Inspection and Testing
C & G 2391
MODULE 6
Periodic Inspection & Testing
7/29/2019 T&I Periodic
2/20
Purpose
To determine that the installation is in a satisfactory
condition for continued service i.e. it meets thegeneral objective of the LAW, this is verified by
assuring the requirements of BS7671 are complied
with.
Legislation requires that certain installations are
maintained in a safe condition and therefore must be
periodically inspected and tested
7/29/2019 T&I Periodic
3/20
7/29/2019 T&I Periodic
4/20
Public bodies
Insurance companies
Mortgagors
Additionally
Periodic Inspection and Testing should be considered:-
Changes of ownership or tenancy Changes of use of the premises
After alterations or additions Significant changes in loading
Possible Damage e.g Fire, Flood etc
Inspection and testing may be required by:-
Licensing Authorities
7/29/2019 T&I Periodic
5/20
731-01-03
Careful Scrutiny backed up by Testing
711-01-02 and 712-01-03(xvii) requires information in
the form of diagrams, charts etc to be made available
to the person carrying out the tests
Inspection is the Vital initial operation,
Testing supports the inspection.
The work must be carried out safely.
Where information is not available some exploratory
work will be required.
7/29/2019 T&I Periodic
6/20
Periodic Test Sequence
Continuity of protective conductors
PolarityEarth fault loop impedance
Insulation Resistance
Operation of devices for Isolation and SwitchingOperation of Residual Current Devices
In addition where appropriate: Continuity of Ring final circuits,Earth electrode resistance, Manual operation of circuit breakers etc,
Electrical separation of circuits, Protection by non-conducting locations
7/29/2019 T&I Periodic
7/20
How Much Testing ?
All socket outlets should be checked for polarity
To check bonding conductor continuity the bonds must be
disconnected
The mains must be off for this test
All heavy current equipment e.g. bus-bars, main
switches etc should be tested.
Random selection of points equal to 10% of the installation, if
faults are found this is expanded to 25% and then 100% iffurther faults are found.
As agreed with the client under extent and limitation
7/29/2019 T&I Periodic
8/20
Extent and Limitations
Agree with the client (before starting a detailed inspection and
test) the Extent of the installation to be inspected and anylimitation put on the process by the client
Record the details of this agreement on the Report form
Parts of the installation,
certain floors, sampling
a number of distribution boards
limited to certain types of equipment e.g lighting
Failure to identify these items may result in contractual
liabilities
7/29/2019 T&I Periodic
9/20
Periodic Inspection and Testing Report
744-01-01 On completion of the inspection and testing, a
Report form together with a schedule of test results and a
schedule of inspection should be given to the person ordering
the work.
744-01-02 Any damage, deterioration, defects, dangerousconditions and non-compliance with the requirements which
may give rise to danger, together with any limitations of the
inspection and testing must be recorded.
Guidance on the action to be taken is given by numbering each
non-compliance to1 4
7/29/2019 T&I Periodic
10/20
1)a) What types of inspection and tests need to be carried out
Initial Verification for the new work and Periodic Inspectionand test for the existing installation
Section B. A small office block in Stourbridge
b) State the documentation that should be completed and why
An Electrical Installation Certificate for the new work
(additional circuits have been installed) and a Periodic
Inspection Report for the existing installation
Both of these documents must be accompanied with a
schedule of inspection and a schedule of test results
7/29/2019 T&I Periodic
11/20
The Health and Safety at Work Act and the Electricity at Work
Regulations
d) List the test equipment required for this installation
i) Low reading ohm meter (continuity tester)
ii) Insulation resistance meter
iii) Earth loop impedance tester
iv) Prospective fault current tester
e) If no documentation is available for the installation what
action is required
Some exploratory work, to establish the criteria
c) State the Statutory Regulations that need to be adhered to
7/29/2019 T&I Periodic
12/20
i) Wear and Tear, the installation is 20yrs old, theaccessories,switches etc may show signs of deterioration
ii) Excessive loading e.g. connection of conductors (effects of
heat etc over 20 years)
iii) Damage, the installation equipment may be damaged to the
extent it has become dangerous e.g. exposure of live parts
iv) Corrosion, the conduit is being used as a c.p.c, if this iscorroded the shock protection may be affected
v) Compliance with BS7671, there have been considerable
changes in the standard over the installation life
2)a) List five areas of inspection to be considered on the
existing installation. Give one reason for each
7/29/2019 T&I Periodic
13/20
b) Before commencing testing on the existing installation,
what should be agreed with the client
The extent and limitations that are to be imposed by the client
c) List the correct sequence of tests required for the existing
installation
i) Continuity of protective conductors (including bonds)
ii) Polarity
iii) Earth fault loop impedance
iv) Insulation resistance
v) Operation of devices for isolation and switching
If there are ring final circuits in the existing installation these
should also be tested (as item (ii) )
7/29/2019 T&I Periodic
14/20
Note:- There is no indication that the installation contains
RCDs or Circuit Breakers, these tests therefore would not be
required. Also alternative methods may be used provided theresults are no less effective.
d) List five of the inspection check list items for the new work
i) Connection of conductors
ii) Identification of conductors
iii) Conductor current carrying capacity
iv) Correct connection of accessories
v) Erection methods
7/29/2019 T&I Periodic
15/20
e) List the correct sequence of tests required for the new
installation
i) Continuity of protective conductors including bondsii) Continuity of ring final circuits
iii) Insulation resistance
iv) Polarity
v) Earth loop impedance
vi) Prospective fault currentvii)Functional testing
7/29/2019 T&I Periodic
16/20
Test open ends of the ring, phase to phase, neutral to neutral, cpc to cpc
RECORD results
Cross connect phase to neutral, test phase to neutral at each socket
Reading should be of the phase to phase reading of the open ring
Cross connect phase to cpc, test phase to cpc at each socket
Reading should be approximately
of the phase to phase + of the cpc to cpc
Testsequence
3) Describe how to carry out the ring final circuit continuity
test on the new installation
7/29/2019 T&I Periodic
17/20
4) Describe how to carry out the insulation resistance test on
the existing installation
Test preparation:- All current using equipment should be
disconnected or turned off, the supply to the main
distribution board should be isolated, all protective devices
should be in position or on, all local switches on, anyequipment which may be damaged by the test should be
disconnected or by-passed. The test is then conducted
between:-
i) All live conductors and
ii) All live conductors to Earth
7/29/2019 T&I Periodic
18/20
5) Draw a fully labelled diagram of the complete earth fault
path of the new lighting circuit.
a) Supply phase, b) supply phase conductor, c) circuit phase
conductor, d) exposed-conductive-part of the light, e) c.p.c of
the lighting circuit, f) return path (PEN i.e the earthed neutral)
of the supply cable
a
b c
e
d
f
7/29/2019 T&I Periodic
19/20
6) Because the existing wiring system does not contain
separate c.p.cs describe the three stages of verification that
need to be confirmed.
i) Visual inspection along the length of all conduits to check
their condition regarding corrosion etc
ii) If the conduit appears in good condition measure its
resistance with a low reading ohm meter
iii) If there is any doubt as to its suitability e.g. where itsphysical condition cannot be checked, a high current
injection test is required (not exceeding 25A)
f h i fi l i i i l l h
7/29/2019 T&I Periodic
20/20
7)a) If the ring final circuit R1 + R2 is 0.72, calculate the
approximate reading of Zs
Zs = Ze + (R1 + R2) = 0.2 + 0.72 = 0.92
b) If the maximum tabulated Zs for this circuit is 1.2,
calculate if the reading in (a) is acceptable
There are no correction factors stated, use the rule of thumb
1.2 x 0.75 = 0.9 < 0.92 measured (circuit fails)
c) State what factors need to be considered before measured
earth loop impedance values are compared againstmaximum tabulated Zs values
i) Ambient temperature factors (when not measured at 200C)
ii) Cable temperature factors (not at its operating temperature)