43
Cc: Subject: Attachments: G.J . E-Malls .2016.Vol . 1.002314 Powell, Allyn <[email protected]> Wednesday, March 2, 2016 10:22 AM James, Anthony Gary Jones; Sault, Gene Final Presentation Presentation to Electric Cooperatives of SC 2016..03-03 FINAL.pdf; Presentation to Electric Cooperatives of SC 2016..03-03 FINAL.pptx Attached is Gary's final presentation with edits from this morning. My only comment is that I would still consider changing the title to include the words "Independent Assessment on Behalf of the South Carolina Office of Regulatory Staff', but that's up to you and Dukes. Please let me know if there is anywhere else I need to send it . Thanks! ELECTRONICALLY FILED - 2018 November 29 3:20 PM - SCPSC - Docket # 2017-370-E - Page 1 of 43 G.J.E-Mslls2016.Vot L002314 From: Sent: To: Powell, Allyn &[email protected]& Wednesday, March 2, 2016 10:22 AM James, Anthony Gary Jones; Sault, Gene Subject: Attachments: Final Presentation Presentation to Electric Cooperatives of SC 2016-03-03 FINAL.pdf; Presentation to Electric Cooperatives of SC 2016-03-03 FINAL pptx Attached is Gary's final presentation with edits from this morning. My only comment is that I would still consider changing the title to include the words "Independent Assessment on Behalf of the South Carolina Office of Regulatory Staff', but that's up to you and Dukes. Please let me know if there is anywhere else I need to send it. Thanks!

the that's

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: the that's

Cc:

Subject:

Attachments:

G.J .E-Malls.2016.Vol.1.002314

Powell, Allyn <[email protected]>

Wednesday, March 2, 2016 10:22 AM

James, Anthony

Gary Jones; Sault, Gene

Final Presentation

Presentation to Electric Cooperatives of SC 2016..03-03 FINAL.pdf; Presentation to Electric Cooperatives of SC 2016..03-03 FINAL.pptx

Attached is Gary's final presentation with edits from this morning. My only comment is that I would still consider changing the title to include the words "Independent Assessment on Behalf of the South Carolina Office of Regulatory Staff', but that's up to you and Dukes.

Please let me know if there is anywhere else I need to send it.

Thanks!

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page1of43

G.J.E-Mslls2016.Vot L002314

From:

Sent:

To:

Powell, Allyn &[email protected]&

Wednesday, March 2, 2016 10:22 AM

James, Anthony

Gary Jones; Sault, Gene

Subject:

Attachments:

Final Presentation

Presentation to Electric Cooperatives of SC 2016-03-03 FINAL.pdf;Presentation to Electric Cooperatives of SC 2016-03-03 FINALpptx

Attached is Gary's final presentation with edits from this morning. My only comment is thatI would still consider changing the title to include the words "Independent Assessment onBehalf of the South Carolina Office of Regulatory Staff', but that's up to you and Dukes.

Please let me know if there is anywhere else I need to send it.

Thanks!

Page 2: the that's

o f t h e V. C. S u m m e r

U n i t s 2 & 3 Nuclear Power Plants Presentation to the Electric Cooperatives of South Carolina

Gary C. Jones, President of Jones Partners, Ltd.

March 3, 2016

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page2of43

Status of the V. C. SummerUnits 2 & 3 Nuclear Power PlantsPresentation to the Electric Cooperatives of South Carolina

Gary C. Jones, President of Jones Partners, Ltd.

March 3, 2016

Page 3: the that's

CV o f G a r y C. J o n e s

- :.~ .. ;-~c ... .....-,.:-..:;~,

G.J.E-MaHs.2016 Vo1.1.002316 rf ::_ »~ . ~· I -~ -...·.1·'' • ·.)

• 45+ years in the nuclear power industry

• 32 years with Sargent & Lundy (S&L) in Chicago, Illinois

• 16 years as an Owner/Senior Vice President of S&L

• 2 1/2 years with the International Atomic Energy Agency (IAEA) in Vienna, Austria

• Led the design and engineering on 3 major nuclear power plants

• LaSalle County (Commonwealth Edison)

• Marble Hill (Public Service Indiana)

• Braidwood (Commonwealth Edison)

• Provided engineering, design and consulting services to over 50 nuclear power plants

in the United States

• Professional project experience in Armenia, Canada/ China, El Salvador, Finland,

Hungary, Mexico, South Korea and Ukraine as well as throughout the United States

• Retained by South Carolina Office of Regulatory Staff (ORS) since August 2011

• Registered Professional Engineer in Missouri and South Carolina

1

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page3of43

Brief CV of Gary C. Jones G.J.E-Mails. 2016. Vol,1.002316

,6 igF.,

) 45+ years in the nuclear power industry

i 32 years with Sargent & Lundy (S&L) in Chicago, Illinois

i 16 years as an Owner/Senior Vice President of S&L

i 2 '/2 years with the International Atomic Energy Agency (IAEA) in Vienna, Austria

i Led the design and engineering on 3 major nuclear power plants

LaSalle County (Commonwealth Edison)

Marble Hill (Public Service Indiana)

Braidwood (Commonwealth Edison)

& Provided engineering, design and consulting services to over 50 nuclear power plants

in the United States

& Professional project experience in Armenia, Canada, China, El Salvador, Finland,

Hungary, Mexico, South Korea and Ukraine as well as throughout the United States

i Retained by South Carolina Office of Regulatory Staff (ORS) since August 2011

Registered Professional Engineer in Missouri and South Carolina

Page 4: the that's

~ Updated NRC regulatory environment under 10 CFR 52, which allows for a combined license to both construct and operate a plant

., Modular Construction

• Certified Design

., Success in Asia

:~ Base Load Review Act (BLRA) in South Carolina

• ., Source of non-GHG emitting and diverse power

• Engineering, Procurement and Construction (EPC) Contract

2

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page4of43

A Very Good Idea in zoo8 G.J. E-Mails.201 6. Vol.1,00231 7

Q~ iQ,

Why?i Updated NRC regulatory environment under 10 CFR 52, which allows for

a combined license to both construct and operate a plant

& Modular Construction

i Certified Design

i Success in Asia

i Base Load Review Act (BLRA) in South Carolina

i Source of non-GHG emitting and diverse power

& Engineering, Procurement and Construction (EPC) Contract

Page 5: the that's

S i n c e 2 0 0 8

·: ~ !. G.J.E-Mails.2016.Vol.1.002318 : ~: ~

~,.iJ"~~·;

Regulatory environment not as good as hoped

~ Combined Construction and Operating License (COL) was delayed

~ 9 months until March 30, 2012

~ "Build what you license vs. license what you build"

~ Very strict literal compliance via NRC oversight

~ - license Amendment Requests (LARs)

~ First plants through the Inspection, Tests, Analyses and Acceptance Criteria (ITAAC) process

• Not as much credit for previous experience in China as hoped

• Impact of changes from Fukushima accident

>,,,'!'

3

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page5of43

Experience Since zoo8 G.J.E-Mails201 6Vol. E002318

~ 1

Regulatory environment not as good as hopedt Combined Construction and Operating License (COL) was delayed

9 months until March 30, 2012

& "Build what you license vs. license what you build"

t Very strict literal compliance via NRC oversight

i License Amendment Requests (LARs)

& First plants through the Inspection, Tests, Analyses and AcceptanceCriteria (ITAAC) process

& Not as much credit for previous experience in China as hoped

i Impact of changes from Fukushima accident

Page 6: the that's

Since 2008

. ,~~~

i., ...,. ~ .. , ... \

/; _ ,;.~/ .. ~, ~\ . r- . _,~ .. ~ t G.J.E-Marls.2016.Vol.1 .002319 .: ···-

.,: 1 ' ... -~,,_,,,,..'IF

Modular Construction

~ Fabricators unable to reliably meet schedule and quality requirements

~ Continuing design changes

~ Inadequate constructability reviews

~ Reassignment and de-scoping of fabricators

Certified Design ~ Not as complete as anticipated

~ Lessons leamed at Chinese and sister plants

~ Compliance issues with ·codes, standards and commitments

~ SCE&G requested changes

4

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page6of43

Experience Since zoo81

1

G.J.E-Mails.2016Vol.1.002319~=

'~ l

Modular Constructioni Fabricators unable to reliably meet schedule and quality requirements

i Continuing design changes

i Inadequate constructability reviews

& Reassignment and de-scoping of fabricators

Certified Design& Not as complete as anticipated

i Lessons learned at Chinese and sister plants

i Compliance issues with codes, standards and commitments

i SCERG requested changes

Page 7: the that's

Since 2008

G.J. E -Mails.2016. Vol 1.002320

Asian Schedules Could Not Be Duplicated • More rigorous regulatory environment

• Construction productivity rates lower than planned

BLRA Remains an Essential Element to Success

• Stable enVironment ensures project financing

• Independent study shows plant is still a;positive

Still a Source of Non-·GHG Emitting Power

~ More focus on· this issue due·to· E-PA 'llld

~ Diversity in power supply remains important

,~,,

i~...,·: -~-,·~'\ ~-. / ', ~' -St x~, _,-

""" t

5

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page7of43

Experience Since zooS0

G.J. E4Ia ila,201 B. Vol. I . 002320

~B I

0 I i~

Asian Schedules Could Not Be Duplicatedi More rigorous regulatory environment

i Construction productivity rates lower than planned

BLRA Remains an Essential Element to Successi Stable environment ensures project financing

i Independent study shows plant is still a positive

Still a Source of Non-GHG Emitting Poweri More focus on this issue due to EPA 111d

i Diversity in power supply remains important

Page 8: the that's

S i n c e 2 0 0 8

-~"~~:l~ G.JE-Mails.2016 Vo11 .002321 ~f <?;~~

~ t I ~ lil t ,.,,

EPC Contract

• Multiple Changes in Ownership

• Westinghouse/Shaw Stone & Webster

• Westinghouse/CB&I Stone & Webster

• Westinghouse (with Fluor as a sub-contracted construction manager)

• Multiple Amendments

• ~~change in Law" provision interpretation ted to disagreements

• Designer vs. Constructor

6

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page8of43

Experience Since 20oS GJ. E-Ma ila 201 6 Vol.1.002321

1P..h

EPC Contracti Multiple Changes in Ownership

Westinghouse/Shaw Stone &. Webster

i Westinghouse/CBM Stone & Webster

i Westinghouse (with Fluor as a sub-contracted construction manager)

& Multiple Amendments

& "Change in Law" provision interpretation led to disagreements

i Designer vs. Constructor

Page 9: the that's

Current Status '

·o) • .'~-:_<+, ·~ _, !.~

G.J. E-Mails.2016. Vo1.1.002322 ~ ~.~1 •

'" '-+.),, f t.t-·'"~~

Most of the following information is taken directly from a December 9, 2015 SCANA presentation at the 2015 Wells Fargo Energy Symposium. Some

information/ including the photograph on the first slide/ was taken from a presentation given by SCANA on its February 18, 2015 Fourth Quarter and Full Year

2015 Earnings Conference Call.

These presentations are available from the SCANA website at

www:scana. coJntinvestots!webcasts ~presentatiorrs

7

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page9of43

Current Status G.J.E-Mails.201 6. Vol. I . 002322

~ I

Most of the following information is taken directly from a December 9, 2015SCANA presentation at the 2015 Wells Fargo Energy Symposium. Some

information, including the photograph on the first slide, was taken from apresentation given by SCANA on its February 18, 2015 Fourth Quarter and Full Year

2015 Earnings Conference Call.

These presentations are available from the SCANA website at

www segno.com investors ebcasts- resentotions

Page 10: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page10

of43'of j

J

PlA8

R

Q

CJ4-(U

CL

Q o~ H

Q E

tll

O.cC(4Ll

C0O

LI

O

O0

COCV

~O

bllCOO

CJ

P~

,I

l

Cl

ill

CV

a j

Ih Q

CJ

l '~

..l:-l- ~,

y1

gJ

'k(I )Il'

'gg i 05

ml OilC

'Zl

IR4l

I

CQ

E

I-

I, ~

s I,

Page 11: the that's

Equipme ft ' to 'svo L1. 00

2324

2 0 0 9 2 0 1 0

2 0 1 6

~ .sc."""'. ,.<»..,..,•• F o• l.Hn-• • December

Current Posttton

9

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page11

of43

Status of Major Equipment -Uk--

2009 2010 2011 2012

2- Generator

UB-Reactor Coolant Loop

2013 2014

Umt S-RCPs

2015 2016

t - curn orsUS-Accumulators

~ U2&ore Makeup T

— U2 Reactor ~ loop

Unit?-RCps . - -- ——

Unit 253 g~VFDs Q

US-Core Makeup Tanks

2pr. erUnit

Unit 2-Steam Generators,,team enerators

2-Reactor Vessel

Unit S-Reactor Vessel

2&onteinment Vessel

Unit S-Containment Vessel

2-Integrated

Unit S-Integrated Head

2-Squib Valves

Unit S-Squib Valves

Generator

Unit 3-CRDMs

Current Position

Page 12: the that's

N ~------"~-~·~· ~<.!: ,. 0

~---· ... .. ~~· cc - U

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page12

of43

C

0

LJ

8

S

i

CJ

~ M

M)

Page 13: the that's

Five" AssembledGJE-Ma;,.20,.V.I1002326

11

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page13

of43

"Bag Five" Assembled- ""--"" ""-

CA03~

Page 14: the that's

Installed

Concrete fi ll to be determined.

17/47 on-site.

6/4 7 on platen.

Ready for hook in November 2016.

Module Status

Assembly Completed

0/5 on-site.

I

17/17 sub-modules on site.

12/17 sub-modules on assembly platen.

3 sub-modules under on-site repair.

Ready for hook June 2016.

0/17 on-sit e.

Installed

I

Installed

G.J.E-Matls.2016 Vol.1 .002327

Installed

Concrete fill to be determined.

Assembly Completed

Ready for hook in December 2016

I I

,I

Installed Concrete fill is scheduled

for April 2016

68/72 on-site

22/72 on platen.

Ready for hook in April 2016.

12

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page14

of43

Module Status G.J. E-Mails.201 B Vot 1.002327

CA 1 C C (No ggncrete CA CA

Installed

Concrete fill to bedetermined.

17/47 on-site.

3 6/47 on platen. 0/s

Ready for hook inNovember 2016.

0/17 on-site.

Assembly 68/72 on-site

InstalledComPleted 22/72 on platen.

Ready for hook in Ready for hook in

December 2016 April 2016.

Inside of Containment Containment

Page 15: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page15

of43

O

Cll3CVEO

tO

IU

Q

~or(

~

1i)p(

iA',c(

':

))

w

g'J 5

&8&

'I

j„'4

C~ E

I

P-$

(I

p'5CII . I5,'g

4ePf

f./

i,„I

(

'

tI

.~ ~

~ 'Il S,

k

Page 16: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page16

of43

CioCV

vj

Ul

P

I

C)I4

Nleal

CJ

V

l

2Lg

I

I

I

'1 /tI

I

'.J l

,l

I&

I

.=- QV

Ig

h3

P

i

lh

1

f

k

I

I'I

I

'i I

~'-~

Page 17: the that's

Structural Modules

15

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page17

of43

Shield Building/Contai entVessel

Structural Modules Sh eld Building

II

Annular Space Containment Vessel

Page 18: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page18

of43

Page 19: the that's

GJE~•U•2016Vol1002332

Unit 2 ~ 113/167 panels on-site

~ Courses 01 and 02 installed and filled with concrete

~ Course 03 installation underway

~ 16 courses in total

Unit 3 ~ 36/167 panels on-site

~ None yet installed

17

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page19

of43

Shield Building Panel Status - """-""--

Unit 2i 113/167 panels on-site

i Courses 01 and 02 installed and filled with concretei Course 03 installation underwayi 16 courses in total

Unit 3i 36/167 panels on-site

i None yet installed

Page 20: the that's

S e t t l e m e n t w i t h t h e C o n . soroti u m

G u a r a n t e e d S u b s t a n t i a l

C o m p l e t i o n D a t e s

C a p i t a l C o s t

(SCE&G 55% s h a r e )

Order #2015-661 (Prior EPC)

Unit 2- June 2019 Unit 3 -June 2020

$5.247 billion

Amended EPC Fixed Price Option

Unit 2 - August 2019 Unit 3 - August 2020

$5.492 billion $6.757 billion

Future Escalation to Westinghouse as 6/30/2015*:

$794 million $813 million $19 million*

Total Expected Project Cost (SCE&G 55% share)

Liquidated Damages

Bonuses

Change in Law Language

~ SC.IJNII~ f•o w.- .. T O f//t C. tVfN O

$6.821 billion

$155 million @ 100% $86 million - SCE&G

Capacity Performance Related

Generally defined

$7 ~113 billion

$926 million @ 100% $509 million - SCE&G

$7.601 billion

$676 million @ 100% $372 million - SCE&G

Completion - Capacity Performance bonus removed $550 million @ 100% $300 million @ 100% $303 million- SCE&G $165 million- SCE&G

Explicitly defined- Formal written adoption of a new statute, regulation, requirement, or code or new NRC regulatory

requirement that did not exist as of this amendment

*The Fixed Price Option, regardless of date of acceptance, would fix Project Costs and shift the risk of escalation I excluding escalation on owner's and transmission costs) to Westinghouse as of June 30, 2015.

Total Gross Escalation recorded as of 6/30/2015 Is $386 million. Under the Fixed Price Option, Total Gross Escalation remaining on the project is estimated to be approximately $145 million.

18

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page20

of43

SCE8zG's Settlement with the Ceusartium

LOrder ¹2015-661Prior EPC

Amended EPC

Guaranteed SubstantialCompletion Dates

Unit 2- June 2019Unit 3- June 2020

Unit 2 - August 2019Unit 3- August 2020

Capital Cost(SCE&G 55% share) $5.247 billion $5.492 billion $6.757 bllhon

Future Escalation toWestinghouse as 6/30/2015e: $794 million $813 million $ 19 mil lion e

Total Expected Project Cost(SCE&G 55% share) $ 6.827 billion $7.113 billion $7.601 billion

Liquidated Damages $155 million I 100N

$86 million — SCE&G$926 million @ 100%

$509 million — SCE&G$676 million 8 100%

$372 million — SCE&G

Bonuses

Change in Law Language

Capacity PerformanceRelated

Generally defined

Completion — Capacity Performance bonus removed$550 million g 100% $300 million 5 100%

$303 million — SCE&G $165 million — SCEg G

Explicitly defined — Formal written adoption of a new statute,regulation, requirement, or code or new NRC regulatory

requirement that did not exist as of this amendment«The Fixed Price Option, regardless of date of acceptance, would fix Project Costs and shift the risk of

escalation (excluding escalation on owner's and transmission costs) to Westinghouse as of June 30, 2015.Total Gross Escalation recorded as of 6/30/2015 Is $ 386 million. Under the Fixed Price Option, Total Gross

Escalation remaining on the project is estimated to be approximately $ 145 million.

Page 21: the that's

Project Challenges ~~(~ .... ~8;:.•;._. G.J.E-Mails.2016.Vol.1.002334 /; •. , ... · .; .

~ I -

• Transition Between EPC Conbact Holders and Construction Management

• Modules, Modules. Modules!

• Shield Building Air Inlet Tension Ring and Roof Design

~ Pnxluttlvlty.

~ Mechanical, Elecbfcal and lnsbumentatlon a Controls Installation

~ Ragul_,r.y Compliance

~ Ucense Amendment Requests (LARs)

~ rrAAC (873/unlt"requlrecl; 19 on U2 and ~- .on U3 verlfted. by:'NRC)

, Start"!U,p

~ Operations and Support Staff Readiness

.,,,, , . \f<..)~

19

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page21

of43

Project Challenges G.J.E-Mails.201 6. Vol.1,002334

so l.

& 17snsition Between EPC Contract Holders and Construction Management

& Modules, Modules, Modulesl

& Shield Building Air Inlet Tension Ring and Roof Design

& Productivity

& Mechanical, Hectrical and Instrumentation 4 Controls Installation

& Regulatory Compliance

& Ucense Amendment Requests (LARs)

& ITAAC (873/unit required; 19 on U2 and 18 on UB verified by NRC)

& Start-Up

& Operations and Support Staff Readiness

Page 22: the that's

• R e c a n t I n d e p e n d e n t study Indicates BLRA metiiOdology reduces ~

• Still ~• diverse and non-GHG source of oower

• Project,faces significant.~ but not Insurmountable. challenges

~ Unit J will need substantlal'lmprovernent In all areas to meet the date for federal tax cradlts

• Pr-aaress has been made In the aeneral areas of' the site and·the turbine Island

• Consolidation under Westinghouse is viewed positively by SCE&G

• Addition of Fluor should also be positive

20 ·

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page22

of43

Conclusions G.J.E-Mails.201 6. Vol.1.002335

'.,6 ip.',t'

Recent Independent study indicates BLRA methodology reduces costs

i Still a diverse and non-6H6 source of power

i Project faces significant, but not insurmountable, challenges

i Unit 8 will need substantial Improv. - In all areas to meet the date forfederal tax credits

i Progress has been made in the general areas of the site and the turbine Island

i Consolidation under Weelnghouse Is viewed positively by SCKR6

i Addition of Fluor should also be positive

Page 23: the that's

o f t h e V. C. S u m m e r

U n i t s 2 & 3 Nuclear Power Plants Presentation to the Electric Cooperatives of South Carolina

Gary C. Jones, President of Jones Partners, Ltd.

March 3, 2016

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page23

of43

Status of the V. C. SummerUnits 2 & 3 Nuclear Power PlantsPresentation to the Electric Cooperatives of South Carolina

Gary C. Jones, President of Jones Partners, Ltd.

March 3, 2016

Page 24: the that's

CV o f G a r y C. J o n e s

('l .... ~~i-

G.J.E-M•;I,,2016 Vol.1.002337 ' .,

'el l I -~ '

1)/t 1 , .. ,.,,,.

• 45+ years in the nuclear power industry

• 32 years with Sargent & Lundy (S&L) in Chicago, Illinois

• 16 years as an Owner/Senior Vice President of S&L

• 2 1!2 years with the International Atomic Energy Agency (IAEA) in Vienna, Austria

• Led the design and engineering on 3 major nuclear power plants

~ LaSalle County (Commonwealth Edison)

~ Marble Hill (Public Service Indiana)

~ Braidwood (Commonwealth Edison)

• Provided engineering, design and consulting services to over 50 nuclear power plants

in the United States

• Professional project experience in Armenia, Canada, China, El Salvador, Finland,

Hungary, Mexico, South Korea and Ukraine as well as throughout the United States

• Retained by South Carolina Office of Regulatory Staff (ORS) since August 2011

• Registered Professional Engineer in Missouri and South Carolina

1

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page24

of43

Brief CV of Gary C. Jones..0

G.J.E.Mails.2016. Vol.1.002337

1,6 l

i 45+ years in the nuclear power industry

& 32 years with Sargent & Lundy (S&L) in Chicago, Illinois

16 years as an Owner/Senior Vice President of S&L

i 2 '/2 years with the International Atomic Energy Agency (IAEA) in Vienna, Austria

Led the design and engineering on 3 major nuclear power plants

LaSalle County (Commonwealth Edison)

Marble Hill (Public Service Indiana)

Braidwood (Commonwealth Edison)

& Provided engineering, design and consulting services to over 50 nuclear power plants

in the United States

i Professional project experience in Armenia, Canada, China, El Salvador, Finland,

Hungary, Mexico, South Korea and Ukraine as well as throughout the United States

i Retained by South Carolina Office of Regulatory Staff (ORS) since August 2011

) Registered Professional Engineer in Missouri and South Carolina

Page 25: the that's

2008

·~~ .. :~.:.:.·~ , ~ "'";· ~ ~

G.J.E-Mails.2016.Vo1.1.002338 ·~. ~: . .. ,,_

Why? ~ Updated NRC regulatory environment under 10 CFR 52, which allows for

a combined license to both construct and operate a plant

~ Modular Construction

~ Certified Design

~ Success in Asia

~ Base Load Review Act (BLRA) in South Carolina

• Source of non-GHG emitting and diverse power

• Engineering, Procurement and Construction (EPC) Contract

• ., 'J, . ~,· ·'

2

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page25

of43

A Very Good Idea in zoo8 GJ.E-Mails201 8Vol. 0002338

~ l

Why?i Updated NRC regulatory environment under 10 CFR 52, which allows for

a combined license to both construct and operate a plant

& Modular Construction

& Certified Design

i Success in Asia

i Base Load Review Act (BLRA) in South Carolina

i Source of non-GHG emitting and diverse power

i Engineering, Procurement and Construction (EPC) Contract

Page 26: the that's

S i n c e 2 0 0 8

G.J.E-Mails.2016 Vol 1.002339

Regulatory environment not as good as hoped

~ Combined Construction and Operating License (COL) was delayed

~ 9 months until March 30, 2012

~ "Build what you license vs. license what you build"

~ Very strict literal compliance via NRC oversight

~ License Amendment Requests (LARs)

~ First plants through the Inspection, Tests, Analyses and Acceptance Criteria (ITAAC) process

~ Not as much credit for previous experience in China as hoped

~ Impact of changes from Fukushima accident

3

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page26

of43

Experience Since zooS G.J.E-Msils.201 6.Vol.1.002339

Regulatory environment not as good as hoped

i Combined Construction and Operating License (COL) was delayed

9 months until March 30, 2012

i "Build what you license vs. license what you build"

9 Very strict literal compliance via NRC oversight

t License Amendment Requests (LARs)

t First plants through the inspection, Tests, Analyses and AcceptanceCriteria (ITAAC) process

i Not as much credit for previous experience in China as hoped

i Impact of changes from Fukushima accident

Page 27: the that's

S i n c e 2 0 0 8

••• ,, :f.,,

"~\:!~~.:;: .. ~ •. 'f ., ' ...

G.J.E-Mails.2016 Vol.1.002340 ;: • •• ,~ :.

I I • ,, ...-. ,,

Modular Construction

._ Fabricators unable to reliably meet schedule and quality requirements

; Continuing design changes

.- Inadequate constructability reviews

.- Reassignment and de-scoping of fabricators

Certifie.d Desig:n

~ Not as complete as anticipated

.. Lessons learned at Chinese and sister plants

.. Compliance issues with codes, standards and commitments

.. SCE&G requested changes

4

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page27

of43

Experience Since zoo8 G.J.E-Mails. 201 6. Vol.1.002340

~ I

Modular Constructioni Fabricators unable to reliably meet schedule and quality requirements

i Continuing design changes

i Inadequate constructability reviews

v Reassignment and de-scoping of fabricators

Certified Designi Not as complete as anticipated

i Lessons learned at Chinese and sister plants

i Compliance issues with codes, standards and commitments

& SCERG requested changes

Page 28: the that's

S i n c e 2 0 0 8

·- ·~ , ~'f-fiJI • J _I~~

~,c·~~.f~'-f.·

G.J.E-Mails.2016.Vol.1.002341 :~ .. ~ :

I --)J,' ,,.._,,"!-

Asian Schedules Could Not Be Duplicated

• More rigorous regulatory environment

~ Construction productivity rates lower than planned

BLRA Re.mains an Essential Element to Success

• Stable environment ensures project financing

• ~ndependent study shows plant fS stiH a positive

Still a Source of Non-GHG Emitting Power

• More focus on this issue due to EPA 111 d

• Diversity in power supply remains important

5

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page28

of43

Experience Since zoo8 G.J.E-Mails.201 6,Vol.1.002341,2(,6(

Asian Schedules Could Not Be Duplicatedi More rigorous regulatory environment

& Construction productivity rates lower than planned

BLRA Remains an Essential Element to Successi Stable environment ensures project financing

i Independent study shows plant is still a positive

Still a Source of Non-GHG Emitting Poweri More focus on this issue due to EPA 111d

i Diversity in power supply remains important

Page 29: the that's

Experience Since 2008 G.J.E-Mails.2016.Vol.1 .002342 t -· ,": ~ t~~~-..~;,p.\

EPC Contract

• Multiple Changes in Ownership

~ Westinghouse/Shaw Stone & Webster

• Westinghouse/CB&I Stone & Webster

~ Westinghouse (with Fluor as a sub-contracted construction manager)

• Multiple Amendments

• ~~change in Law" provision interpretation led to disagreements

• Designer vs. Constructor

' t I T

·~()It 1 ' ' '' '

6

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page29

of43

Experience Since zoo8 G.J,E-Mails.201 6Vou.002342

'w ~

EPC Contracti Multiple Changes in Ownership

i Westinghouse/Shaw Stone 8 Webster

i Westinghouse/CB8II Stone 8. Webster

i Westinghouse (with Fluor as a sub-contracted construction manager)

i Multiple Amendments

& "Change in Law" provision interpretation led to disagreements

& Designer vs. Constructor

Page 30: the that's

Current Status t~---~·, ~\ G.J. E-Maits.2016. Vol.1 .002343 ·a . o , .. ." 1

' t I ~ -:; .. >.,~ . , .... ~ ..... ~-

Most of the following information is taken directly from a December 91 2015 SCANA presentation at the 201 5 Wells Fargo Energy Symposium. Some

information, including the photograph on the first slide, was taken from a presentation given by SCANA on its February 18, 2015 Fourth Quarter and Full Year

2015 Earnings Conference Call.

These presentations are available from the SCANA website at

wvvw.scana.cotn/investors/webcasts-presentations ' '

7

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page30

of43

Current Status G.J. E-Mails.2010. Vol.1.002343

~ lP,

Most of the following information is taken directly from a December 9, 2015SCANA presentation at the 2015 Wells Fargo Energy Symposium. Some

information, including the photograph on the first slide, was taken from a

presentation given by SCANA on its February 18, 2015 Fourth Quarter and Full Year2015 Earnings Conference Call.

These presentations are available from the SCANA website at

www.scana.com investors webcasts- resentations

Page 31: the that's

(Picture f r o m S e p t e m b e r 2015)

8

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page31

of43

Site Overview(Picture from September 2015)

G.J. E-Mails.201 6.vol, l.002344

HLD

=Pa W Cooling Tower 2 Alpha

Cooling Tower 2 Bravo

Turbine Building

. Unit

lng 2

Transformer Bays

4 Ring 1 Unit 3

C ~

MAB

are

Q rat'J'

CV Rings & Heads

CV Lower Bowl

r 4

dg . ~~m ~@SANDecember

Page 32: the that's

of Major Equipme - B t •,.v.u . 00234S

2 0 0 9

2 0 1 0

2 0 1 6

~ sc.vw.~~. ,.O w •• 'O• LI YfH O

• .December Current Posttton

9

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page32

of43

Status of Major Equipment-—2009 2010 2011

2-

2012 2013 2014

Unit 3-RCPs

2015 2016

U3-Reactor Coolant Loop Piping

~ Unit 2-RCPsI

U3-Accumulators

2&ore Makeup T

U2 Reactor Coolant Loop

U3-Core Ma p Tan

2-Pr er

Unit

«~ Unit 2-Steam Generators

team

2-Reactor Vassal

Unit 3-Reactor Vessel

Unit 3-T Generator

Unit 2tkSVFDs ~i

Unit 2-Containment Vessel

Unit 3-Containment Vessel

Unit 2-Integrated Head

'nit3-Integrated Head

Unit 3-Squib Valves

2-CRD s

Unit 3-CRDMs

Current Positio'n" "

Page 33: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page33

of43

C

0

Q

8~p

CJ

~ I~+I

M)

Page 34: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page34

of43

/g ~.

\

I

O

C$

LU

i I

j' ~P."if".!'r

i/

rr

Page 35: the that's

Installed

Concrete fill to be determined.

17/47 on-site.

6!47 on platen.

Ready for hook in November 2016.

,,

Module Status

Assembly Completed

0/5 on-site.

17/17 sub-modules on site.

12/17 sub-modules on assembly platen.

3 sub-modules under on-site repair.

Ready for hook June 2016.

0/17 on-sit e.

Installed

Installed

G.J.E-Mails.2016 Vol.1 .002348

Installed

Concrete fi ll to be determined.

Assembly Completed

Ready for hook in December 2016

Installed

Concrete fi ll is scheduled for April 2016

68/72 on-site

22/72 on platen.

Ready for hook in April 2016.

12

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page35

of43

Module Status G.J.E-Mails. 201 6. Vol,1.002348

CA A A (No concrete ~A CA

17/1 7 sub-moduleson site.

Installed

Concrete fill to bedetermined.

AssemblyCompleted

12/1 7 sub-moduleson assembly platen.

3 sub-modules underon-site repair,

Ready for hook June2016.

Installed (Installed

Concrete fill is scheduledfor April 2016

~I

17/47 on-site.

6/47 on platen.

Ready for hook inNovember 2016.

0/1 7 on-site.

AssemblyCompleted

InstalledReady for hook inDecember 2016

68/72 on-site

22/72 on platen.

Ready for hook inApril 2016.

Inside of Containment Containment

Page 36: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page36

of43

lO

R

d

fj/~

, ~,.'.-'u'- .y

'

g NgQ

;,. r 4~S aiI

J j'/

~ I

J @A~'I

i

~.gE

t

flIO

3~')

cC

- ~ "~~

'

Page 37: the that's

8

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page37

of43

~EA~

CI

8O

tO

CVCI

XUJ

!J

D

I

1

I

~ .X

/t/'~L.

4

I

'a~

-VMr

~ HI l

1/

I ,t .Fl

ii

]IAi'''.i

Page 38: the that's

Building/ Containme nt -- V e s s e l

Structural Modules

15

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page38

of43

Shield Building/Containmerrt"Vessel

Structural Modules Sh eld Building

lI

Annular Space Containment Vessel

Page 39: the that's

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page39

of43

. o

r,

'

8LJN 'a'

~Ti

1

I

ill~~ A

jI

1

I

J'

lE ~E'II

I,.I

If

'-I

'I

I

II

II.

Page 40: the that's

B u i l d i n g P a n e l S t a t u s

G.J.E-Mails.2016. Vol.1 .002353

U.n:it 2 ~ 113/167 panels on~site

• Courses 01 and 02 installed and filled with concrete

• Course 03 installation underway

• 16 courses in total

Un:it 3 • 36/167 panels on-site

• None yet installed

17

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page40

of43

Shield Building Panel Status "'"-"""""'""

Unit 2i 1'l3/167 panels on-site

& Courses 01 and 02 installed and filled with concrete

i Course 03 installation underway

& 16 courses in total

Unit 3i 36/167 panels on-site

i None yet installed

Page 41: the that's

Settlement with the Cojn jsorotiuni

Guaranteed Substantial Completion Dates

Capital Cost (SCE&G 55% share)

Future Escalation to Westinghouse as 6/30/2015*:

Total Expected Project Cost (SCE&G 55% share)

Liquidated Damages

Bonuses

Change in law Language

Order #2015-661 (Prior EPC)

Unit 2 - June 2019 Unit 3 -June 2020

$5.247 billion

$794 million

$6.827 billion

$155 million @ 100% $86 million- SCE&G

Capacity Performance Related

Generally defined

Amended EPC Fixed Price Option

Unit 2- August 2019 Unit 3- August 2020

$5.492 billion

$813 million

$7.113 billion

$926 million @ 100% $509 million- SCE&G

$6.757 billion

$19 million*

$7.601 billion

$676 million @ 100% $372 million- SCE&G

Completion - Capacity Performance bonus removed $550 million@ 100% $300 million@ 100% $303 million - SCE&G $165 million- SCE&G

Explicitly defined - Formal written adoption of a new statute, regulation, requirement, or code or new NRC regulatory

requirement that did not exist as of this amendment

*The Fixed Price Option, regardless of date of acceptance, would fix Project Costs and shift the risk of

ft(" 8&--uvll$ P o .. v~e• llo .. " ' V"'""o

escalation (excluding escalation on owner's and transmission costs) to Westinghouse as of June 30, 2015. Total Gross Escalation recorded as of 6/30/2015 is $386 million. Under the Fixed Price Option, Total Gross

Escalation remaining on the project is estimated to be approximately $145 million. 18

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page41

of43

SCE8zG's Settlement with the Coxxsaltium

LOrder ¹2015-661 $Prior EPC

Amended EPC Fixed Price Option

Guaranteed SubstantialCompletion Dates

Unit 2- June 2019Unit 3 — June 2020

Unit 2 - August 2019Unit 3 — August 2020

Capital Cost(SCE&G 55% share) $5.247 billion $5,492 billion $6.757 billion

Future Escalation toWestinghouse as 6/30/2015*: $794 million $813 million $ 19 million*

Total Expected Project Cost(SCE&G 55% share) $6.827 billion $7.113 billion $7.601 billion

Liquidated Damages $ 155 million N 100N

$86 million — SCE&G$926 million 5 100N

$509 million — SCE&G$ 676 million @ 100%

$372 million — SCE&G

Bonuses

Change in Law Language

Capacity PerformanceRelated

Generally defined

Completion — Capacity Performance bonus removed$550 million 8 100% $300 million g 100%

$303 million — SCE&G $ 165 million — SCE&G

Explicitly defined — Formal written adoption of a new statute,regulation, requirement, or code or new NRC regulatory

requirement that did not exist as of this amendment*The Fixed Price Option, regardless of date of acceptance, would fix Project Costs and shift the risk of

escalation (excluding escalation on owner's and transmission costs) to Westinghouse as of June 30, 2015.Total Gross Escalation recorded as of 6/30/2015 Is $386 million. Under the Fixed Price Option, Total Gross

Escalation remaining on the project is estimated to be approximately $145 million.

Page 42: the that's

•.... ,, .,..,.

Project Challenges ~~-c'..~--f~~. G.J.E-Mails.2016 Vol.1 .002355 a . . . · ;"' ; \Ji I -· ~lf t,l-·''~

~ Transition Between EPC Contract Holders and Construction Management

~ Modules, Modules, Modules!

~ Shield Building Air Inlet Tension Ring and Roof Design

• Productivity

• Mechanical, Electrical and lnstrumenta1ion & Controls Installation

• Regulatory Compliance

• License Amendment Requests (LARs)

~ ITAAC (873/unit required; 19 on U2 and 16 on U3 verified by NRC)

• Start-Up

• Operations and Support Staff Readiness

19

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page42

of43

Project Challenges G.J. E-M alla. 201 6. Vo01.002355g

i Transition Between EPC Contract Holders and Construction Management

i Modules, Modules, Modules!

i Shield Building Air Inlet Tension Ring and Roof Design

& Productivity

& Mechanical, Electrical and Instrumentation & Controls Installation

a Regulatory Compliance

i License Amendment Requests (LARs)

i ITAAC (873/unit required; 19 on U2 and 16 on U3 verified by NRC)

i Start-Up

a Operations and Support Staff Readiness

Page 43: the that's

·~~-· ;~.,~~.,~.~--\.

G.J.E-Mails.2016.Vol.1.002356 ~: • •· , ~ : ,

£ 1 I ~ ' '>, t , ._ , .. .,.,.-

• Recent independent study indicates BLRA methodology reduces costs

• Still a diverse and non-GHG source of power

• Project faces significant, but not insurmountable, challenges

• Unit 3 will need substantial improvement in all areas to meet the date for federal tax credits

• Progress has been made in the general areas of the site and the turbine island

• Consolidation under Westinghouse is viewed positively by SCE&G

• Addition of Fluor should also be positive

20

ELECTR

ONICALLY

FILED-2018

Novem

ber293:20

PM-SC

PSC-D

ocket#2017-370-E

-Page43

of43

Conclusions G.J.E-Mails.201 6. Vol.1.002356'„ ~ 1

/'

Recent independent study indicates BLRA methodology reduces costs

i Still a diverse and non-GHG source of power

i Project faces significant, but not insurmountable, challenges

i Unit 3 will need substantial improvement in all areas to meet the date forfederal tax credits

t Progress has been made in the general areas of the site and the turbine island

& Consolidation under Westinghouse is viewed positively by SCE&G

i Addition of Fluor should also be positive

20