29
1hT 1hT August 3, 2000 The One The One HectareTelescope HectareTelescope Progress Report for Progress Report for SKA Workshop at SKA Workshop at Jodrell Jodrell Bank Bank John Dreher Project Scientist Acting Project Manager

The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

1hT1hT

August 3, 2000

The One The One HectareTelescopeHectareTelescope

Progress Report forProgress Report for

SKA Workshop atSKA Workshop at

JodrellJodrell Bank BankJohn DreherProject ScientistActing Project Manager

Page 2: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

1hT1hT

August 3, 2000

The One The One HectareTelescopeHectareTelescope

Progress Report forProgress Report for

SKA Workshop atSKA Workshop at

JodrellJodrell Bank BankJohn DreherProject ScientistActing Project Manager

The Allen Telescope ArrayThe Allen Telescope Array

Page 3: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

The Allen Telescope Array (ATA)The Allen Telescope Array (ATA)

Page 4: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

The Allen Telescope Array (ATA)The Allen Telescope Array (ATA)

• Large, massively parallel array of “TV” dishes– 500 elements each 5 m in diameter

– total collecting area larger than 100 m dish

– 0.5 - 11 GHz simultaneously

– multiple beams

Page 5: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

The Allen Telescope Array (ATA)The Allen Telescope Array (ATA)

• Large, massively parallel array of “TV” dishes– 500 elements each 5 m in diameter

– total collecting area larger than 100 m dish

– 0.5 - 11 GHz simultaneously

– multiple beams

• Must be much cheaper than existing arrays

Page 6: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

The Allen Telescope Array (ATA)The Allen Telescope Array (ATA)

• Large, massively parallel array of “TV” dishes– 500 elements each 5 m in diameter

– total collecting area larger than 100 m dish

– 0.5 - 11 GHz simultaneously

– multiple beams

• Must be much cheaper than existing arrays

• Joint project of SETI Institute and UC Berkeley

Page 7: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

The Allen Telescope Array (ATA)The Allen Telescope Array (ATA)

• Large, massively parallel array of “TV” dishes– 500 elements each 5 m in diameter

– total collecting area larger than 100 m dish

– 0.5 - 11 GHz simultaneously

– multiple beams

• Must be much cheaper than existing arrays

• Joint project of SETI Institute and UC Berkeley

• 26+ M$ from Allen, Myhrvold, others

Page 8: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

The ATA at Hat CreekThe ATA at Hat Creek

Page 9: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

MountsMounts

3.6 m Orbitron

4.2 m AndersenXY drive

worm gear az-el

5 m Prototype

Dual Linear Actuators

belt drive az-el

Page 10: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

MountsMounts

3.6 m Orbitron

4.2 m AndersenXY drive

worm gear az-el

5 m Prototype

Dual Linear Actuators

belt drive az-el

undergoing torque tests

Page 11: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

UltrawidebandUltrawideband Log Periodic Feed Log Periodic Feed

15cm

45 cm

Dual polarization

Cryogenicfront endinside shieldFed at and radiates toward tip

Page 12: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Prototype Feed for TestsPrototype Feed for Tests

Page 13: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Preliminary Feed TestsPreliminary Feed Tests

•Excellent (20 dB) match

•Agrees with EM calcs on

Impedance

Gain

Internal Loss

•More tests ongoing

Page 14: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Optical Design in progressOptical Design in progress• Prime focus with spillover control skirt

• 6 m symmetric shaped Cassegrain

• 5 m offset Gregorian

Page 15: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus
Page 16: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus
Page 17: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

PrototypePrototype InP InP MMIC LNA MMIC LNAMMIC

In-P PHEMT0.18 microns

Weinrebmodel Tsys ~ 10 K

Page 18: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

PrototypePrototype InP InP MMIC LNA MMIC LNAMMIC

In-P PHEMT0.18 microns

WeinrebModel Tin ~ 10 KFirst try

works fineTin ~ 20 K

Page 19: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

PrototypePrototype InP InP MMIC LNA MMIC LNAMMIC

In-P PHEMT0.18 microns

WeinrebModel Tsys ~ 10 KFirst try

works fineTsys ~ 20 K

Bias: 1.46V, 0V, 14mA @ 15K; 1.46V, 0.6V, 25mA @ 82KInput tuned for 6 GHz. DSN lab data Nov 30, 1999 corrected

0

5

10

15

20

25

30

1 2 3 4 5 6 7 8 9 10 11 12

Frequency, GHz

AT 82K

AT 15K

AT 20K

Page 20: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

PrototypePrototype InP InP MMIC LNA MMIC LNAMMIC

In-P PHEMT0.18 microns

WeinrebModel Tsys ~ 10 KFirst try

works fineTsys ~ 20 K

Bias: 1.46V, 0V, 14mA @ 15K; 1.46V, 0.6V, 25mA @ 82KInput tuned for 6 GHz. DSN lab data Nov 30, 1999 corrected

0

5

10

15

20

25

30

1 2 3 4 5 6 7 8 9 10 11 12

Frequency, GHz

AT 82K

AT 15K

AT 20K

Third revision (with active balun) in fabrication

Page 21: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

80 K Cryogenics80 K Cryogenics• Must be

– Small (to fit inside shield)

– Reliable (> 10 yr MTBF)

– Cheap (< few K$)

• In-house solution– “vacuum tube” style dewar with getter

– Pulse tube cooler (no moving parts)

– Clearance seal compressor with voice coil motor

• Commercial solution also possible

Page 22: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

0.5-11 0.5-11 GHzGHz Analog F/O Links Analog F/O Links• Off the shelf units too expensive now

• Reduced component costs soon due torecent massive investments by industry

• Laser progress “Real Soon Now”– Cheaper DFB, e.g. Ortel “Daytona”

– 1300 nm VCSEL (Gore, Novalux, Cielo,Agilent, Infineon)

– Cheaper solid-state lasers?

• External modulators with common laser?

Page 23: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Signal ProcessingSignal Processing• Up/down converter

– PsHEMT GaAs MMIC(s)

– Development at NFRA

– 1st mixer block in fab

• DSP architecture TBD– Beamfomers (>3 beams)

– Digital delay and IF

• Cross correlator with BW set by cost

• RFI mitigation and removal designed in

Page 24: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Rapid Prototyping ArrayRapid Prototyping Array

Page 25: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

RPA pictureRPA picture

Page 26: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Timeline for ATATimeline for ATA

• R&D Phase

• Rapid Prototype Array of 7 antennas built– calibration, beam forming, RFI excision, telescope control

• Selected site, began approval processes

• PDRs : most done by year’s end

• Design staffing nearly complete

1999-20001999-2000

Page 27: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Timeline for ATATimeline for ATA

• R&D Phase

• Rapid Prototype Array of 7 antennas built– calibration, beam forming, RFI excision, telescope control

• Selected site, began approval processes

• PDRs : most done by year’s end

• Design staffing nearly complete

1999-20001999-2000

Wanted: DSP Wizard!

Page 28: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Timeline for ATATimeline for ATA

• CDR

• Build Production Test Array

• Operational tests begin

• Develop tools

2001-20022001-2002

Page 29: The One HectareTelescope - Jodrell Bank Observatory · The One HectareTelescope Progress Report for SKA Workshop at Jodrell Bank John Dreher Project Scientist ... • Prime focus

Timeline for ATATimeline for ATA

• Begin construction

• First use of partial array

• Array complete - extensions begin

• Feed into SKA technology decision point

2003-20042003-2004

20052005