The NCC's presentation of the proposed interprovincial bridge at Kettle Island

Embed Size (px)

Citation preview

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    1/28

    Interprovincial CrossingsEnvironmental Assessment StudyPhase 2B

    Ottawa Transportation Committee

    June 5, 2013Interprovincial CrossingsEnvironmental Assessment Study

    Mr. Andr Leduc, ing., M. ing.Project Manager

    GENIVAR

    Mr. Raynald Ledoux, Ing., M.Sc.A.Project Director

    Roche Limited

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    2/28

    Meeting Purpose

    z Review Evaluation Process, Results, Sensitivity Testing

    z Present Technically Recommended Corridor

    z Present Fairness Auditors Report

    2

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    3/28

    Agenda1. Background and Study Area

    2. Evaluation Methodologies and Results

    3. Technically Recommended Corridor

    4. Fairness Auditors Report5. Round 3 Public Consultation Summary of Results

    6. Next Steps

    3

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    4/28

    1.1 Backgrounder

    4

    The study is a project funded equally and directed by the Ministries of

    Transport of Ontario and Quebec as well as the NCC since it began in 2006.

    The cities of Ottawa and Gatineau are providing technical support.

    The five organizations are part of the Study Team and the Study Steering

    Committee.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    5/28

    1.1 Background (continued)

    5

    Phase 1 and Phase 2A (Completed)

    Phase 1 verified the need and justification for a new interprovincial crossing

    and assessment of several different solutions, technologies, and corridors.

    Phase 2A prepared a Scoping Document to direct a federal environmental

    assessment (EA); and a Study Design Report describing the activities to beundertaken in Phase 2B.

    Phase 2B

    Phase 2B will complete the EA:

    Round 1: Priorities and Values

    Round 2: Corridor-specific Input Round 3: Ranked Corridor Input We are here

    Round 4: Review of EA Study Report and Preliminary Design

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    6/28

    1.1 Backgrounder (continued)

    6

    The Ontario Municipal Board (OMB) made a decision in 1999 for the removal of

    King Edward Avenue and Rideau Street from the regional truck route network

    as soon as a new bridge is built in the East in order to limit the impacts of trucks

    circulating in downtown Ottawa. This decision has been integrated into Ottawas

    Official Plan.

    Following a Ottawa City resolution, several options ranging from status quo (No

    Truck Prohibition, i.e., the current regulation) to full prohibition (a.k.a. truck

    ban) in the downtown area have been incorporated in Phase 2B with the Study

    Design Report Addendum 1 developed in Phase 2A.

    In 2009, the Ville de Gatineau adopted resolution CM-2009-48, which

    expressed the City Councils opposition to transferring all truck traffic from theMacdonald-Cartier Bridge to the new corridor, and asking the City of Ottawa to

    maintain the truck route designation on King Edward Avenue.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    7/28

    1.2Study Area

    7

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    8/28

    2.1 Evaluation Methodologies

    8

    Two evaluation methods were utilized to determine the Technically Recommended

    Corridor (TRC).

    Pair-wise Comparison (primary weighted method):

    Preference relationships with respect to each evaluation factor and sub-factorwere determined. The relative importance of these preferred relationships were

    taken into account through weighting. This methodology used both qualitative

    and quantitative measurements.

    Reasoned Argument (second method for validation )

    Corridors were ranked based upon an examination of the relative differences innet impacts.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    9/28

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    10/28

    Evaluation Committee Corridor Ranking

    10

    2.2 Evaluation Results (continued)

    10

    - Corridor 5: Kettle Island (monte Paiement)

    - Corridor 6 : Lower Duck Island (Lorrain Boul.)

    - Corridor 7 : Gatineau Airport / McLaurin Bay

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    11/28

    2.2 Evaluation Results (continued)

    11

    The stacked bars

    representation adds

    the weight of each

    factor group for

    which a corridor

    scores a better

    performance

    compared to the

    other.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    12/28

    2.2 Evaluation Results (continued)

    12

    The stacked bars

    representation adds

    the weight of each

    factor group for

    which a corridor

    scores a better

    performance

    compared to the

    other.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    13/28

    2.2 Evaluation Results (continued)

    13

    The stacked bars

    representation adds

    the weight of each

    factor group for

    which a corridor

    scores a better

    performance

    compared to the

    other.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    14/28

    Sensitivity Analysis

    14

    To validate the weighting exercise a

    sensitivity testing program was

    undertaken to determine how

    sensitive the evaluation is withrespect to the deviation of the

    assigned weights (i.e. would the result

    have changed if a perspective of

    importance were used from a

    committee member that was higher or

    lower than the group average). Thisensures greater confidence in the

    selection process.

    2.2 Evaluation Results (continued)14

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    15/28

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    16/28

    16

    Reasoned Arguments Results (Overall Factor Group Summary)

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    17/28

    17

    Reasoned Arguments Results (Overall Factor Group Summary)

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    18/28

    18

    Corridor 5 was recommended from the ECs perspective because it

    performs very well for the most valued factor groups:

    Traffic and Transportation;

    Natural Environment;

    Economic Environment; Land Use and Property; and

    Costs.

    Corridor 5 also performs moderately for Social Environment (it could not be

    preferred compared to Corridor 7 - Community Impacts) and for Water Use

    and Resources (risk to the Gatineau plant - considered manageable, spills

    can be captured by the stormwater management system).

    2.2 Evaluation Results - Highlights18

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    19/28

    19

    Corridor 6 was judged the least preferred by the EC: it performed

    moderately for some of the most valued factor groups (Traffic and

    Transportation, Natural Environment) but is least preferred for Land Use

    and Costs but mostly Social which is considered to have high not mitigable

    impacts (high number of buyouts and severe community disruption).

    Corridor 7 was judged also the least preferred by the EC: it performed

    poorly for Traffic and Transportation, Natural Environment, Land Use and

    Property and Costs. Although this corridor was preferred for Social

    Environment (in the absence of any established communities) and Water

    Use and Resources (furthest downstream of Gatineau Water Treatment

    Plant intake) these were not considered to be as significant factors in this

    evaluation.

    2.2 Evaluation Results Highlights (continued)19

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    20/28

    3. Technical Recommendation - Corridor 5

    20

    Bridge design features common to Corridors 5, 6 and 7 at ultimate :

    One reserved lane for transit in each direction;

    Two lanes of traffic (non-commercial vehicles and trucks) in each direction;

    Multi-use pathways (pedestrians and cyclists) on both sides (one in each direction);

    Median separating opposing traffic;

    Left and right turning lanes at intersections where needed on land sections.

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    21/28

    3. TechnicalRecommendation

    Corridor 5

    Conceptual view of the Ottawa River from the Qubec shoreline

    Conceptual view of Monte

    Paiement looking south

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    22/28

    3. Technical RecommendationCorridor 5

    22

    Conceptual view of Aviation Parkway looking

    south, toward Hemlock Road

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    23/28

    4. Fairness Auditor Conclusion

    The NCC retained a Fairness Auditor who has reported on the openness,

    fairness, integrity, transparency and impartiality of the process. The

    Fairness Auditor has reported that:

    It is our opinion that the evaluation process we observed was carried out in

    compliance with the methodology described in the Evaluation Methodology

    Report, and the process was conducted in an equitable, credible, defendable

    and traceable manner that was in the broad public interest.

    In accordance with its mandate, the Fairness Auditor observed the conduct

    of the evaluation process of the Environmental Assessment Study, Phase

    2B, related to the selection of a corridor for a future interprovincial crossing in

    the National Capital Region.

    23

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    24/28

    5. Round 3 Public Consultation Summary of Results

    As of June 3rd, 2013:

    z May 27th Shenkman Arts Centre (Orleans)

    167 people registered (182 people were counted)

    85 comment sheets received at Open House

    1 petition was handed in at the Open House, signed by 15 residents

    z May 30th Maison du Citoyen (Gatineau)

    15 people registered

    3 comment sheets received at Open House

    z 10 comments (all via e-mail) have been received since May 15th, 2013

    z 98 Total Comment Sheets / Emails Receivedz 321 Total Comments

    24

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    25/28

    Types of Concerns:z Technically Related Issues : 123 comments (38%)

    Noise / Vibration: 21 comments

    Impact to Communities: 20 comments

    Montfort Hospital: 13 comments

    Costs: 14 comments

    Air Quality / Emissions: 10 comments

    Urban Sprawl/Land Use: 8 comments

    Social: 7 comments

    Human Health / Safety: 7 comments

    Recreation: 7 comments

    Property: 5 comments

    Cultural & Heritage: 4 comments

    Documentation: 3 comments

    Political: 2 comments

    25

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    26/28

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    27/28

    6. Next Stepsz Study Steering Committee endorsement of TRC (Decision 1) : July 2013

    z EA Study Report and Preliminary Detailed Design of TRC: Summer-Fall

    2013

    z Round 4 Consultation: Fall 2013

    z Present EA Study Report and project to the NCC Board, City of Ottawaand Ville de Gatineau: Fall 2013

    z Study Steering Committee and the NCC Board endorsement (Decision 2)

    of the Recommended Project: Winter 2013

    z Proceed and seek environmental authorities approvals for the project:

    2014

    27

  • 7/28/2019 The NCC's presentation of the proposed interprovincial bridge at Kettle Island

    28/28

    Questions

    28