Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
The Lean Enterprise Quick Change Over / Set-Up Reduction
www.freesixsigmasite.com
Lean Foundations
Continuous Improvement Training
• Understand the concepts and principles of Set-up Reduction.
• Share some ideas and understand the benefits of Set-up Reduction.
• Apply the concepts, principles and techniques of SMED to accomplish
Quick Changeovers !!
Objectives
? What is SMED?
SMED stands for:
Single Minute Exchange of Die
Ideally, set-up time should be
anything less than 10 minutes …
Decreased set-up time;
reduces the need for inventory,
provides more flexibility and capacity,
enables us to better serve our customer!
Set-up Time
There are two types of setup time:
Internal Set-up:
Those activities that must be performed while the
machine is shut down. (Work content done in
addition to Machine Time.)
Example: Removing dies and tooling
External Set-up:
Those activities that are performed while the
machine is operating.
Example: Preparing tooling for the next set-up
Set-up Reduction Process
1. Observe and document the current set-up.
2. Separate Internal and External elements.
3. Improve each element.
4. Observe and document the new set-up process.
5. Standardize the new set-up procedure.
6. Celebrate your success!!
Observe and Document the Current Set Up
A. Select a specific set-up for improvement
B. Identify a set-up “kaizen” team.
C. Observe the set-up process:
Video Record the set-up process
Complete the Set-up Operations Analysis
chart (before Kaizen).
D. Prepare a Pareto chart for each time category.
Record and Recommend
During this phase we:
Observe and document the existing set-up procedure
using
Time Observation and Video Recording techniques
- Analyze all work efforts
- Identify short-term solutions that can be
implemented with procedural changes, modifications to
existing fixtures and minor investment in tooling
Video Recording Tips
Collect background data
Select regular production “Parts”
Determine equipment and operation
Prepare/Evaluate site
Where does operator stand?
Where is the best position for the camera?
Is there adequate lighting?
Narrate
Describe what is happening when the
operator blocks the camera or leaves
the area.
Analyze the Time Observation & Video
Review Time Observation and Video
with the team
Identify opportunities
Internal vs. External
Value Added Vs Non-Value Added
Normal vs. Abnormal
Seven Types of Waste
Automatic, Manual, Walking,
and Waiting times
Solicit ideas for countermeasures /
improvements
Mach # 3456 Before Kaizen AnalysisMinutes From To Area / Department Date 3/7/99
146 Part # Model A Model B Machining Cell
Step No. Changeover Element Element Elapsed Internal External Waste Improvement Plan Eliminate
Internal to
External Reduce
1Pick-up tools from tool crib
(search)19 19 19 x Mount hand tools on machine x
2Remove Fixture (Fixture
Change)15 34 15
Air wrench at machine .
Eliminate bolts - install
quick release. Design SMED
cart to load fixture.
x
3 Look for Tools (Search) 5 39 5 x Mount hand tools on machine x
4Remove Fixture (Fixture
Change)7 46 7 See step 2. x
5Clean & prepare subplate
(Fixture Change)10 56 10 Steel plugs for subplate. x
6Prepare nex fixture (Fixture
Change)20 1'16 20 x
Standardize procedures to
externalize this step.x x
7Put on new fixture (Fixture
Change)22 1'38 22
Air wrench at machine .
Eliminate bolts - install
quick release. Design SMED
cart to load fixture.
x
8Remove preset tools (Tools
Change)4 1'42 4
Establish common tooling for
all models.x x
9 Preset tooling (Tool Change) 6 1'48 6Standardize procedures to
externalize this step.x
10Load new tooling (Tool
Change)11 1'59 11
Establish common tooling for
all models.x x
11 Run 1st Piece (1st Piece) 15 2'14 15
12 Qualify 1st Piece (Gage) 12 2'26 12Standardize procedures to
externalize this step.x
Totals2'26 2'26 2'11 15
Operation Time Changeover Categories Goal of Improvement Plan
Set-up Operations Analysis Chart
Observe and Document the Current Set Up
Observe and Document the Current Set-up Searching
- Looking for tools, jigs, fixtures, etc.
Fixture Change
- Replacing one fixture with another
Tool Change
- Replacing existing tooling
Programming
- Making adjustments or changes to a CNC program in order to
accommodate the new set-up
Walk time
- The time an operator must walk to retrieve a fixture, tools etc.
1st Piece
- The time required to produce a good unit after the initial set-up
Gage
- The time required to qualify the 1st piece
Set-up Pareto Analysis
0
10
20
30
40
50
60
70
80
tim
e in
min
Fixture Chg Search Tool Chg 1st Piece check Calibrate Gauge
Pareto Analysis on each Time Category
Separate the Elements Internal:
Those activities that must be performed while
the machine is shut down.
Example: Removing dies and tooling
External:
Those activities that are performed while the
machine is operating.
Example: Acquire fixture/tools for next set-up
Both types of actions must be separated. Once the machine is stopped, the associate should never
depart to perform any part of the external set up.
Mach # 3456 Before Kaizen AnalysisMinutes From To Area / Department Date 3/7/99
146 Part # Model A Model B Machining Cell
Step No. Changeover Element Element Elapsed Internal External Waste Improvement Plan Eliminate
Internal to
External Reduce
1Pick-up t ools from t ool crib
(search)19 19 19 x Mount hand t ools on machine x
2Remove Fixt ure (Fixt ure
Change)15 34 15
Air wrench at machine . Eliminat e bolt s -
ins t all quick release. Des ign SMED cart
t o load fixt ure.x
3 Look for Tools (Search) 5 39 5 x Mount hand t ools on machine x4
Remove Fixt ure (Fixt ure
Change)7 46 7 See s t ep 2. x
5Clean & prepare subplat e
(Fixt ure Change)10 56 10 St eel plugs for subplat e. x
6Prepare nex fixt ure (Fixt ure
Change)20 1'16 20 x St andardize procedures t o ext ernalize t his s t ep. x x
7Put on new fixt ure (Fixt ure
Change)22 1'38 22
Air wrench at machine . Eliminat e bolt s -
ins t all quick release. Des ign SMED cart
t o load fixt ure.x
8Remove preset t ools (Tools
Change)4 1'42 4 Est ablish common t ooling for all models . x x
9 Preset t ooling (Tool Change) 6 1'48 6St andardize procedures t o ext ernalize
t his s t ep. x10 Load new t ooling (Tool Change) 11 1'59 11 Est ablish common t ooling for all models . x x11 Run 1s t Piece (1s t Piece) 15 2'14 15
12 Qualify 1s t Piece (Gage) 12 2'26 12St andardize procedures t o ext ernalize
t his s t ep. x
Totals2'26 2'26 2'11 15
Operation Time Changeover Categories Goal of Improvement Plan
Set-up Operations Analysis Chart
Internal or External?
Separate the Elements
Develop Improvement Plan
5S +1 (6S) discipline is the key to quick changeover!
Every minute spent
looking for tools,
fixtures, drawings, dies,
jigs or other materials
adds to the set-up time.
A ‘strong’ 5S foundation, with a ‘point-of-use’ (POU)
methodology, will ensure that all required materials
are in place when needed, are clean, and in working
condition.
Develop Improvement Plan Remember the ‘Wastes’ ? (refer to the 7W’s)
Defects
Over-Production (inventory)
Transportation
Waiting
Inspection (mass)
Motion
Processing, itself
+ “Unused Creativity”
Storage area for Dies
Tool Cart
Punch Press
Tool Room
Develop Improvement Plan
Specifically:
A. Convert as much of the internal set
up to the external set up.
B. Eliminate or reduce the internal and
external set-up.
C. Eliminate the adjustment process.
Ultimate Goal: Eliminate Set-up!
Application Best Practices
1) Make minor modification to the
existing fixtures.
2) Implement Point-of-Use (POU) techniques.
3) Identify additional tooling to remove attachment
from internal to external.
4) Adopt standardized tooling.
5) Document time savings.
Application Best Practices - Continued
For example:
Slots in fixture and T-Bolts reduce
attachment time.
A new part holder reduced the time required to
load and unload parts to fixture. Swing hook
eliminated the need to remove nut from bolt.
Extra set slides allow detach to be completed on
external time.
Other ideas
1. Quick Changeover begins and ends with the 5S’s.
2. Change the Internal set-up into External, then improve
the remaining Internal set-up time.
3. Bolts are our Enemies.
4. If you have to use your hands make sure your feet stay
put.
5. Don’t rely on Special Fine-tuning skills.
6. Standards are standard: they are NOT flexible.
7. Standardize all SMED Operations
Document the New Set-up
A. List each element on the Set-up
Operations Standard Chart (after Kaizen)
B. Video tape the new set-up procedure.
C. Record the set-up time for each element
D. Note areas for future improvement.
Mach # After KaizenMinutes From To Area / Department Date
Part #
Step No. Changeover Element Element Elapsed Internal External Waste Comments / Future Improvement Plans
Operation Time Changeover Categories
Set-up Operations Standard
Standardize the New Procedure
Standardize the New Procedure
The Set-up Operations Standard chart will
become the basis for the new set-up
procedure.
Prepare the appropriate detail and work
instructions that will be included on the Set-
up Operations Standard chart.
Assure that all appropriate personnel are
trained in the new procedure.
The Lean Enterprise Quick Change Over / Set-Up Reduction
www.freeleansite.com
Lean Foundations
Continuous Improvement Training