23
The AHU From A Case Study Presented by David Sellers Portland Energy Conservation Inc. INLAND EMPIRE CHAPTER 1 - 2/27/200 2

The AHU From

  • Upload
    beau

  • View
    88

  • Download
    7

Embed Size (px)

DESCRIPTION

The AHU From. INLAND EMPIRE CHAPTER. Hell. A Case Study Presented by David Sellers Portland Energy Conservation Inc. 1 - 2/27/2002. 2 - 2/27/2002. 3 - 2/27/2002. 4 - 2/27/2002. 5 - 2/27/2002. - PowerPoint PPT Presentation

Citation preview

Page 1: The AHU From

The AHU From

A Case Study Presented by

David Sellers

Portland Energy Conservation Inc.

INLAND EMPIRE CHAPTER

1 - 2/27/2002

Page 2: The AHU From

2 - 2/27/2002

Page 3: The AHU From

3 - 2/27/2002

Page 4: The AHU From

4 - 2/27/2002

Page 5: The AHU From

5 - 2/27/2002

Page 6: The AHU From

At the time this was all going on, the clean room conditions were stable and within specifications; 68°F+1-1/2°F, 45%+3%

relative humidity.

6 - 2/27/2002

Page 7: The AHU From

Space condition

Outdoor condition

Leaving preheat coil

Leaving fans

Leaving reheat coil

Leaving cooling coil, as found

condition

Leaving cooling coil, repaired condition;

leaving humidifier, as found condition

The process as found was using $5,000 - $7,000 of unnecessary energy per month.

7 - 2/27/2002

Page 8: The AHU From

How Could This Be?

• Clean room conditions were at spec• Fast track design build project

Specific clean room requirements Non-specific HVAC process requirements

• Clean room qualification based commissioning focus

• The nature of the semi-conductor industry business cycle

8 - 2/27/2002

Page 9: The AHU From

Preheat Problems

• Shut down steam when its not needed Integral face and bypass

type preheat coil Valve in place, not control

signal

• Calibrate sensor• Add Alarms

9 - 2/27/2002

Page 10: The AHU From

Preheat Problems

• Integrate control cycle Eliminate multimode control approach

• Operating cycles based on OAT rather than clean room

• Inconsistent operation Sequence with chilled water and reheat Lock out when not required Maintain an independent low limit

10 - 2/27/2002

Page 11: The AHU From

Cooling Problems

• Calibrate sensor A little tricky with an averaging element Relative calibration more important than

absolute calibration

Lock out when not required Add alarms

11 - 2/27/2002

Page 12: The AHU From

Humidification and Reheat Problems

• Eliminated by the other fixes• Improved space sensor calibration

routine• Add alarms• Fan heat provided most of the reheat

12 - 2/27/2002

Page 13: The AHU From

The cost of correction is projected to be between $4,700 and $8,000.

• Exact value depends on the hourly rate used.

• Most of the cost was in facilities engineering labor.

• Some modest costs were associated with hardware.

13 - 2/27/2002

Page 14: The AHU From

Educating the Operators Ensured Persistence

• Diligent, talented operators Lacking training in psychrometrics Lacking training in clean room process

Informal training provided empowerment Kept a psych chart by the operators console Nature of engineering support requests changed Acted on their own initiative

14 - 2/27/2002

Page 15: The AHU From

Systems Integration Problems

24 hour per day plant operating spec taken literally

No light switches in the clean rooms No provisions for coordinated start-up and shut

down

Power failures and equipment failures caused severe pressure fluctuations in the fab

Contamination issue Safety issue Restart issue15 -

2/27/2002

Page 16: The AHU From

Systems Integration Problems

Multiple power sources on the same system

Controls on uninterruptible power supply

Drives on emergency power with different auto-restart options selected

Control interlock circuit on normal power

16 - 2/27/2002

Page 17: The AHU From

Power Coordination Coupled with an Assembly Problem for a

DISASTER!!!

17 - 2/27/2002

Page 18: The AHU From

Fab Leakage = Energy Burden + Operational Danger

Two parallel, redundant fans designed so: Only one fan runs Provides 27,000 cfm at 3.5 inches w.c.

Clean room leakage resulted in running both fans to achieve pressurization required

14,000 extra cfm of outside air to move and condition

Static requirement increased to 7 in.w.c. Duct pressure class was 4 in.w.c.!!18 -

2/27/2002

Page 19: The AHU From

Pressure Relief Doors Provide Protection

• Protect from air hammer effects due to sudden damper position changes.

• Protect over-pressurized ducts to the extent possible

19 - 2/27/2002

Page 20: The AHU From

Improved Damper Reinforcement

Simply matched factory instructions

Reinforcing plate between sections

Bracing is an alternative approach

20 - 2/27/2002

Page 21: The AHU From

Permissive Interlocks and Better Quality Limit Switches

• Start command opens dampers

• Limit switches proving starts the fan Wired to work in all

selector switch positions “Local” control mode on the

drive disabled

21 - 2/27/2002

Page 22: The AHU From

HVAC Process/Efficiency Commissioning Benefits

• Reduction in operating cost and improved performance and reliability in retrocommissioning arena.

• Reduction in operating cost and first cost with improved performance and reliability in new construction.

• Reduction in CO2 emissions.

Complements energy savings.

Potential for additional financial leverage.22 - 2/27/2002

Page 23: The AHU From

Barriers to Moving from Qualification Based Approach

• Rapid fluctuations in the semiconductor market cycle.Short paybacks demanded.Design innovations not embraced.Drive to get on line and in production ASAP.

• Production process tolerances.Run on detection limits.Extremely costly to ship bad product.

23 - 2/27/2002