Upload
martin-skinner
View
217
Download
1
Tags:
Embed Size (px)
Citation preview
31/03/2009 M. Alfonsi - CERN 2
Outline
• Schedule
• Installation of gas pipes
• Gas system
• Global setup & mechanics
• Magnet issues
31/03/2009 M. Alfonsi - CERN 4
Goliathmagnet
Gas pipes installed!
To be done:- gas panel in the experimental area- leak test with He
Gas panel must include also retention buckets for flammable gas sensors.
Is ok to use quick connectors? sensor
sensor
31/03/2009 M. Alfonsi - CERN 5
Cost of the five gas lines
• 6mm diam. pipes x 240m• 10mm diam. pipes x 240m• Mechanical supports• Estimated cleaning cost• Estimated manpower cost
• TOTAL
1584.00 CHF
2715.00 CHF
505.38 CHF
2380.00 CHF
3442.54 CHF
10626.92 CHF
Paid by: Saclay (345 CHF) + CERN
Left-over material: 30m pipes per type, some support
31/03/2009 M. Alfonsi - CERN 6
Gas mixing racks• We can connect to the main distribution:
– Ar, CO2, N2, He, ethane, isobutan
– CH4 temporary on “melange” line
– We pay the bill at the end!!!
• Gas mixing racks:– 5 gas system at least 2 gas
mixing rack, maybe 3 (the lastonly for not-flammable mixes)
– To put 2 mixing rack in theretention bucket, we are askingfor a reorganization of the gaszone, i.e. to move out the not-flammable main distributionrack
Main distribution:flammable not-flammable
Roo
f fo
r lig
ht
flam
mab
le g
ases
Retention bucket for heavy flammable gases
31/03/2009 M. Alfonsi - CERN 7
Gas mixing systems• Goal: flexible, upgradable during the several
runs, possibility to mix main distribution as well as premixed bottles
• At the moment, not enough flowmeters and controllers for all the lines .. We start building setups for June
from maindistribution (use left-over 10mm pipes)
Only required gases or premixed bottles(use left-over 6mm-OR- flexible ss pipes)
Mixing cylinder.. Who can provide some of them?
flowmeterConnection to the pipes going towards the experimetal area
Gas system per line
31/03/2009 M. Alfonsi - CERN 8
Lack of flammable gas sensors!!!
In the gas zone, they are provided by the SPS people: put all the gas racks closer in the same bucket
In the experimetal area, only 2 avalaible.. and 1 is for the gas panel: Additional sensors could be charged on us For June seems ok: no flammable gas in MM
tracker, isobutan for Frascati setup For October we want isobutan and methane !!! Sensors could not work in magnetic field!!! In this
case problems also for June!!!
31/03/2009 M. Alfonsi - CERN 9
Cables list (barrack area)
1) Fiber lines x10 (from Saclay?)
2) Ethernet lines x5 (from Frascati?)
Anyway better to have also:
1) Set of BNC lines (24 from GDD)
2) SHV lines (4 from GDD)
HV PS and DAQ is inside the experimental area, so are required:
31/03/2009 M. Alfonsi - CERN 10
Sketch of the installation
Gas panel
Setup A
electr. rack for setup A
Removable cable tray for
setup A
electr. rack for setup B
Removable cable tray for setup B?
Setup B
DAQPC
31/03/2009 M. Alfonsi - CERN 11
Setup “A” outside the magnet
• Placed upstream Goliath
Beam line
Beam height~ 128 cm
Useful space 3.3 m
Beammonitor
Beamelement
Table withmicromegastracker
If Detector Under Test is large, as in June, place it just after the table (together with your support mechanics!!!)
31/03/2009 M. Alfonsi - CERN 12
Table with micromegas tracker
• A grid of holes for fixation• For flammable gas:
– Retention buckets must be added on table and, in case, as a roof
– Holes must be blind Lenght 120cm
Height 70cm from the floor
Can part of the legs be substituted by a concrete block? If yes, how can we fix on it?
Width 80cm
31/03/2009 M. Alfonsi - CERN 13
Setup “B” inside the magnet
railwheel
Beam
Beam height~ 128 cm
~ 8
5 cm
Table with grid of holes, same issues (blind holes, retention buckets..) for flammable gases, see previous slide.
Dimension to be defined
Only 43 cm between beam level and the level of the Goliath coil surface!!!
A specific rail system will be designed to recover some space:
31/03/2009 M. Alfonsi - CERN 14
Additional issues with Setup “B”
• Rails should extend outside Goliath:– Additional dismontable rails with some
mechanical support? Should we dismount also rails every time?
• Gas alarm sensors in magnetic field• How much close to Goliath can the
electronics rack “B” be place?– Usually LVDS should be not longer than 5m– The electronics can be sensitive to magnetic
field
31/03/2009 M. Alfonsi - CERN 15
Additional common issues
• Cables and gas pipes from panels to setups:– additional removable cable trays?– plastic gas pipes for this year, to be upgraded
to flexible stainless steel (setup B requires flexible ones)
• DAQ PC inside the area:– Radiation issue to be checked (especially for
pc removed after the use)
31/03/2009 M. Alfonsi - CERN 16
Magnet
• Goliath under test today
• Frascati is working on the field map file
• Proposed a week, from 4th to 8th of May, for all our tests:– delimitation of the range of the fringe field– PMTs test– AoB