Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado West Sub County
ANGLICAN DEVELOPMENT SERVICES-MT.KENYA
Tender No. HELI 101
TENDER FOR THE DRILLING OF ONE
BOREHOLE AT NKARUSA, KISERIAN,
KAJIADO WEST SUB - COUNTY
Anglican Development Services-Mount Kenya (ADS - MK)
P.O. Box 2376-10140 Nyeri
Tel +254 61 2034813
Website: www.ads-mtkenya.or.ke
Email: [email protected]
Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado Sub County
2
April 2015
S ECTIO N P AGE
Section A: Invitation for Tenders ................................................................................................. 3
Section B: Instructions to Tenderers ............................................................................................ 4
Section C: General Conditions of Contract .............................................................................. 14
Section D: Special Conditions of Contract ................................................................................. 25
Section E: Technical Specifications, Schedule of Requirements and Prices ........................... 33
Section F: Appendix to Conditions of Contract ....................................................................... 34
Section G: Specifications, Drawings and Bills of Quantities .................................................... 36
Section H: Borehole Technical Specifications ........................................................................... 42
Section I: Bill of Quantities (BOQ) ............................................................................................. 50
Section J: Standard Forms .......................................................................................................... 51
Appendix A: Location of proposed area for drilling borehole ................................................ 62
Appendix B: Borehole Design .................................................................................................... 63
3
Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado Sub County
Section A: Invitation for Tenders
DRILLING OF ONE BOREHOLEAT NKARUSA, OLOIRIEN, KAJIADO WEST SUB-
COUNTY
Anglican Development Services-Mt. Kenya (ADS-MK) invites you to submit a sealed tender for
drilling and construction of ONE BOREHOLE at Nkarusa village, Oloirien Location, Kajiado West
Sub- County.
Interested eligible candidates may obtain further information from, and inspect the Tender Document
at the office of:
Regional Development Coordinator,
ADS-MK,
P.O. Box 2376-10140 Nyeri
Tel. +254 61 2034813
Interested candidates can download the tender document from the website www.ads-mtkenya.or.ke
A payment of a non-refundable fee of Kshs 3,000.00 (Three Thousand Kenya shillings) to ADS
Mt Kenya Administration A/c No. 0102822135600 Standard Chartered Bank Nyeri Branch. (Attach
the original deposit slip to the tender document as proof of payment)
Tenders must be accompanied by a security in the form and amount specified in the tender
documents, and must be delivered to:
Zonal Development Coordinator,
Anglican Development Service-Mt Kenya,
Wangige Zone,
Bishop Karuiki Integrated Training Centre, Wangige
P.O. Box 3899 – 0623
Nairobi
Tenders will be opened at 2.00 PM on 10th
June, 2015in the presence of the candidates‟
representatives who choose to attend on the above-mentioned date and time at ADS Mt Kenya
Wangige Zone, Bishop Kariuki Integrated Training Centre, Wangige.
Yours Faithfully,
For: Anglican Development Services-Mt. Kenya (ADS-MK)
Kennedy Gichira (Mr.)
REGIONAL DEVELOPMENT COORDINATOR,
4
Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado Sub County
Section B: Instructions to Tenderers
Introduction
1. Eligible Tenderers
1.1 This Invitation for Tenders is open to all tenderers eligible as described in the tender
documents. Successful tenderers shall complete the supply of services by the
intended completion date specified in the tender documents.
1.2 Tenderers shall not be under a declaration of ineligibility for corrupt and fraudulent
practices.
2. Eligible Goods
Not applicable
3. Cost of Tendering
3.1 The Tenderer shall bear all costs associated with the preparation and submission of
the tender, and ADS-MK, will in no case be responsible or liable for those costs,
regardless of the conduct or outcome of the tendering process.
The Tender Document 4
Contents
4.1 The tender document comprises the documents listed below and addenda issued in
accordance with Clause 6 of the Instructions to Tenders .
a) Invitation for Tenders
b) Instructions to Tenders
c) General conditions of Contract
d) Special Conditions of Contract
e) Bill of Quantities, Schedule of Requirements and Price Schedule Specifications and
Drawings
f) Tender Form
g) Tender Security Form
h) Agreement
i) Performance Security Form
j) Bank Guarantee for Advance Payment Form
k) Acceptance Letter
4.2 The Tenderer is expected to examine all instructions, forms, terms, and specifications
in the tender documents. Failure to furnish all information required by the tender
documents or to submit a tender not substantially responsive to the tender documents
in every respect will be at the tenderer‟s risk and may result in the rejection of its
tender.
5. Clarification of Documents
5
Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado Sub County
5.1 A prospective tenderer requiring any clarification of the tender document may notify
ADS-MK in writing at the address indicated in the Invitation for Tenders. ADS-MK
will respond in writing to any request for clarification of the tender documents,
which it receives prior to the deadline for the submission of tenders. Written copies
of ADS-MK's response (including an explanation of the query but without
identifying the source of inquiry) will be sent to all prospective tenderers that have
received the tender document.
6. Amendment of Documents
6.1 At any time prior to the deadline for submission of tenders, ADS-MK, for any
reason, whether at its own initiative or in response to a clarification requested by a
prospective tenderer, may modify the tender documents by amendment.
6.2 All prospective tenderers that have received the tender documents will be notified of
the amendment in writing or facsimile, and will be binding on them.
6.3 In order to allow prospective tenderers reasonable time in which to take the
amendment into account in preparing their tenders, ADS-MK, at its discretion, may
extend the deadline for the submission of tenders.
Preparation of Tenders
7. Language of Tender
7.1 The tender prepared by the tenderer, as well as all correspondence and
documents relating to the tender exchanged by the tenderer and ADS-MK,
shall be written in English. Supporting documents and printed literature
furnished by the tenderer may be written in another language provided they are
accompanied by an accurate English translation of the relevant passages in which
case, for purposes of interpretation of the tender, the English translation shall
govern.
8. Documents Comprising the Tender
8.1 The tender prepared by the tenderer shall comprise the following components:
(a) a Tender Form and a Price Schedule completed in accordance with Clauses
9,10 and 11 below.
(b) documentary evidence established in accordance with Clause 12 that the
tenderer is eligible to tender and is qualified to perform the contract if its
tender is accepted;
6
Drilling and Construction of a water borehole at Nkarusa, Oloirien ,Kajiado West Sub County.
(c) documentary evidence established in accordance with Clause 13 that the
services to be supplied by the tenderer are eligible and conform to the tender
documents; and
(d) tender security furnished in accordance with Clause 14
9. Tender Form
9.1 The tenderer shall complete the Tender Form and the appropriate Bill of Quantities
and Price Schedule furnished in the tender documents, indicating the services to be
supplied, a brief description of the services, quantity and prices.
10. Tender Prices
10.1 The tenderer shall indicate on the appropriate Bill of Quantities and Price Schedule
the unit prices and total tender price of the services it proposes to supply under the
contract.
10.2 Prices indicated on the Price Schedule shall be quoted inclusive of all other cost to
be incurred by the successful tendered in offering the drilling services.
10.3 Prices quoted by the tenderer shall be fixed during the tenderer‟s performance of
the contract and not subject to variation on any account. A tender submitted with
an adjustable price quotation will be treated as non-responsive and will be
rejected, pursuant to Clause 22.
11. Tender Currencies
11.1 Prices shall be quoted in Kenya Shillings.
12. Tenderer’s Eligibility and Qualifications
12.1 The tenderer shall furnish, as part of its tender, documents establishing the
tenderer's eligibility to tender and its qualifications to perform the contract if its
tender is accepted.
12.2 The documentary evidence of the tenderer‟s eligibility to tender shall establish to
ADS-MK‟s satisfaction that the tenderer, at the time of submission of its tender, is
from an eligible source country.
12.3 The documentary evidence of the tenderer‟s qualifications to perform the contract if
its tender is accepted shall establish to ADS-MK‟s satisfaction that the tenderer has
the financial, technical, and production capability necessary to perform the contract.
13. Goods’ Eligibility and Conformity to Tender Document
13.1 Pursuant to Clause 2 of this section, the tenderer shall furnish, as part of its tender,
documents establishing the conformity to the tender documents of all service
7
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
which the tenderer proposes to supply under the contract.
13.2 The documentary evidence of the eligibility of the services shall consist of a
statement in the Price Schedule of the country of origin of the services offered.
13.3 The documentary evidence of conformity of the services to the tend er documents
may be in the form of literature, drawings, and data, and shall consist of:
(a) a detailed description of the essential technical and performance characteristics
of the services; and
(b) a Clause-by-Clause commentary on ADS-MK‟s Technical Specifications
demonstrating substantial responsiveness of the services to those specifications,
or a statement of deviations and exceptions to the provisions of the Technical
Specifications and bill of quantities (BQ).
13.4 For purposes of the commentary to be furnished pursuant to Clause 13.3(b) above,
the tenderer shall note that standards for workmanship, material, and equipment, as
well as references to brand names or catalogue numbers designated by ADS-MK in
its Technical Specifications, are intended to be descriptive only and not restrictive.
The tenderer may substitute alternative standards, brand names, and/or catalogue
numbers in its tender, provided that it demonstrates to ADS-MK‟s satisfaction that
the substitutions ensure substantial equivalence to those designated in the Technical
Specifications.
14. Tender Security
14.1 The tenderer shall furnish, as part of its tender, a tender security in the amount of
2% of the total tender price.
14.2 The tender security is required to protect ADS-MK against the risk of tenderer‟s
conduct, which would warrant the security‟s forfeiture, pursuant to Clause 14.7.
14.3 The tender security shall be denominated in Kenya Shillings, and shall be in the
form of a bank guarantee or a bank draft issued by a reputable bank located in
Kenya, in the form provided in the tender documents or another form acceptable to
ADS-MK and valid for thirty (30) days beyond the validity of the tender.
14.4 Any tender not secured in accordance with Clause 14.1 and 14.3 will be rejected by
ADS-MK as non-responsive, pursuant to Clause 22.
14.5 Unsuccessful tenderers‟ tender security will be discharged or returned as promptly as
possible as but not later than thirty (30) days after the expiration of the period of
tender validity prescribed by ADS-MK.
14.6 The successful tenderer‟s tender security will be discharged upon the tenderer
signing the contract, pursuant to Clause 30, and furnishing the performance
security, pursuant to Clause 31.
Drilling and Construction of a water borehole at Nkarusa, Oloirien ,Kajiado West Sub County.
8
.
14.7 The tender security may be forfeited:
(a) if a tenderer withdraws its tender during the period of tender validity specified
by ADS-MK on the Tender Form; or
(b) in the case of a successful tenderer, if the tenderer fails:
(i) to sign the contract in accordance with Clause 30
Or
(ii) to furnish performance security in accordance with Clause 31.
15. Validity of Tenders
15.1 Tenders shall remain valid for 90 days or as specified in the tender documents after
date of tender opening prescribed by ADS-MK, pursuant to Clause 18. A tender
valid for a shorter period shall be considered as non-responsive and shall be rejected
by ADS-MK.
15.2 In exceptional circumstances, ADS-MK may solicit the tenderer‟s consent to an
extension of the period of validity. The request and the responses thereto shall be
made in writing. The tender security provided under Clause 14 shall also be suitably
extended. A tenderer may refuse the request without forfeiting its tender security. A
tenderer granting the request will not be required nor permitted to modify its tender.
16. Format and Signing of Tender
16.1 The tenderer shall prepare an original and three copies of the tender, clearly
marking each “ORIGINAL TENDER” and “COPY OF TENDER,” as appropriate.
In the event of any discrepancy between them, the original shall govern.
16.2 The original and copies of the tender shall be typed or written in indelible ink and
shall be signed by the tenderer or a person or persons duly authorized to bind the
tenderer to the contract. The latter authorization shall be indicated by written
power-of-attorney accompanying the tender. All pages of the tender, except for un-
amended printed literature, shall be initialed by the person or persons signing the
tender.
16.3 The tender shall have no interlineations, erasures, or overwriting except as necessary
to correct errors made by the tenderer, in which case such corrections shall be
initialed by the person or persons signing the tender.
Submission of Tenders
17. Sealing and Marking of Tenders
17.1 The tenderer shall seal the original and each copy of the tender in separate
envelopes, duly marking the envelopes as “ORIGINAL” and “COPY.”
The envelopes shall then be sealed in an outer envelope. The inner and outer
envelopes shall be addressed to;
Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado Sub County
9
(a) Anglican Development Services-Mt. Kenya at the following address:
Zonal Development Coordinator,
Anglican Development Service,
Wangige Zone,
Bishop Karuiki Integrated Training Centre, Wangige
P.O. Box 3899 – 0623
Nairobi
(b) Bear, "DRILLING OF WATER BOREHOLE AT NKARUSA,
OLOIRIEN, KAJIADO WEST SUB- COUNTY”, and the statement: “DO
NOT OPEN BEFORE 10th
June, 2015AT 2.00 P.M”.
17.2 The inner envelopes shall also indicate the name and address of the tenderer to
enable the tender to be returned unopened in case it is declared “late”.
17.4 If the outer envelope is not sealed and marked as required by Clause 17.1, ADS-MK
will assume no responsibility for the tender‟s misplacement or premature opening.
18. Deadline for Submission of Tenders
18.1 Tenders must be received by ADS-MK at the address specified under Clause 17.1 not
later than 12.00 Noon on 10th
June, 2015.
18.2 ADS-MK may, at its discretion, extend this deadline for the submission of tenders by
amending the tender documents in accordance with Clause 6, in which case all
rights and obligations of ADS-MK and tenderers previously subject to the deadline
will thereafter be subject to the deadline as extended.
19. Modification and Withdrawal of Tenders
19.1 The tenderer may modify or withdraw its tender after the tender‟s submission,
provided that written notice of the modification, including substitution or
withdrawal of the tenders, is received by ADS-MK prior to the deadline prescribed
for submission of tenders.
19.2 The tenderer‟s modification or withdrawal notice shall be prepared, sealed, marked,
and dispatched in accordance with the provisions of Clause 17. A withdrawal notice
may also be sent by facsimile, but followed by a signed confirmation copy,
postmarked no later than the deadline for submission of tenders.
19.3 No tender may be modified after the deadline for submission of tenders.
19.4 No tender may be withdrawn in the interval between the deadline for submission of
tenders and the expiration of the period of tender validity specified by the tenderer
Drilling and Construction of a water borehole at Nkarusa, Oloirien, Kajiado Sub County
10 on the Tender Form. Withdrawal of a tender during this interval may result in the tenderer‟s forfeiture
of its tender security, pursuant to Clause 14.7.
Opening and Evaluation of Tenders
20. Opening of Tenders
20.1 ADS-MK will open all tenders in the presence of tenderers‟ representatives who
choose to attend on 10th
June, 2015at 2.00 P.M at ADS Mt Kenya Wangige Zone,
Bishop Karuiki Integrated Training Centre, Wangige. Tenderers‟ representatives
present shall sign a register evidencing their attendance.
20.2 The tenderers‟ names, tender modifications or withdrawals, tender p rices, discounts,
and the presence or absence of requisite tender security and such other details as
ADS-MK, at its discretion, may consider appropriate, will be announced at the
opening.
20.3 ADS-MK will prepare minutes of the tender opening.
21. Clarification of Tenders
21.1 To assist in the examination, evaluation and comparison of tenders ADS-MK may, at
its discretion, ask the tenderer for a clarification of its tender. The request for
clarification and the response shall be in writing, and no change in the prices or
substance of the tender shall be sought, offered, or permitted.
Any effort by the tenderer to influence ADS-MK in its decisions on tender
evaluation, tender comparison or contract award may result in the rejection of the
tenderers‟ tender.
22. Preliminary Examination
22.1 ADS-MK will examine the tenders to determine whether they are complete, whether
any computational errors have been made, whether required sureties have been
furnished, whether the documents have been properly signed, and whether the
tenders are generally in order.
22.2 Arithmetical errors will be rectified on the following basis. If there is a discrepancy
between the unit price and the total price that is obtained by multiplying the unit
price and quantity, the unit price shall prevail, and the total price shall be corrected.
If the tenderer does not accept the correction of the errors, its tender will be rejected,
and its tender security may be forfeited. If there is a discrepancy between words and
figures, the amount in words will prevail.
22.3 ADS-MK may waive any minor informality or non-conformity or irregularity in a
tender which does not constitute a material deviation, provided such waiver does
not prejudice or affect the relative ranking of any tenderer.
11
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub
County
22.4 Prior to the detailed evaluation, pursuant to paragraph 23, ADS-MK will determine
the substantial responsiveness of each tender to the tender documents. For purposes
of these paragraphs, a substantially responsive tender is one which conforms to all
the terms and conditions of the tender documents without material deviations. ADS-
MK‟s determination of a tender‟s responsiveness is to be based on the contents of
the tender itself without recourse to extrinsic evidence.
22.5 If a tender is not substantially responsive, it will be rejected by ADS-MK and may
not subsequently be made responsive by the tenderer by correction of the
nonconformity.
23. Evaluation and Comparison of Tenders
23.1 ADS-MK will evaluate and compare the tenders, which have been determined to be
substantially responsive, pursuant to paragraph 22.
23.2 ADS-MK‟s evaluation of a tender will exclude and not take into account any
allowance for price adjustment during the per iod of execution of the contract, if
provided in the tender.
23.3 ADS-MK‟s evaluation of the tender will take into account, in addition to the tender
price the actual slotting period offered in the tender. The liners shall be completely
slotted within 4 months after the date making the end of mobilization.
23.4 Deviation in payment schedule
Tenderers shall state their tender price for the payment schedule outlined in the
special conditions of contract. Tenders will be evaluated on the basis of this price.
Tenderers are, however, permitted to state an alternative payment schedule and
indicate the reduction in tender price they wish to offer for such alternative payment
schedule. ADS-MK may consider the alternative payment schedule offered by the
selected tenderer.
24. Contacting ADS-MK
24.1 Subject to Clause 21, no tenderer shall contact ADS-MK on any matter relating to its
tender, from the time of the tender opening to the time the contract is awarded.
24.2 Any effort by a tenderer to influence ADS-MK in its decisions on tender
evaluation, tender comparison, or contract award may result in the rejection of the
tenderer‟s tender.
Award of Contract
25. Post-qualification
25.1 In the absence of pre-qualification, ADS-MK will determine to its satisfaction
whether the tenderer that is selected as having submitted the lowest evaluated
12
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
responsive tender is qualified to perform the contract satisfactorily.
25.2 The determination will take into account the tenderer financial, technical, and
production capabilities. It will be based upon an examination of the documentary
evidence of the tenderers qualifications submitted by the tenderer, pursuant to
Clause 12.3, as well as such other information as ADS-MK deems necessary and
appropriate.
25.2 An affirmative determination will be a prerequisite for award of the contract to the
tenderer. A negative determination will result in rejection of the tenderer‟s tender, in
which event ADS-MK will proceed to the next lowest evaluated tender to make a
similar determination of that tenderer‟s capabilities to perform satisfactorily.
26. Award Criteria
26.1 Subject to Clauses 10, 23 and 28 ADS-MK will award the contract to the successful
tenderer(s) whose tender has been determined to be substantially responsive and has
been determined to be the lowest evaluated tender, provided further that the
tenderer is determined to be qualified to perform the contract satisfactorily.
27. ADS-MK’s Right to Vary Quantities
27.1 ADS-MK reserves the right at the time of contract award to increase or decrease the
quantities originally specified in the Schedule of Requirements without any change in
unit price or other terms and conditions.
28. ADS-MK’s Right to Accept or Reject Any or All Tenders
28.1 ADS-MK reserves the right to accept or reject any tender, and to annul the tendering
process or reject all tenders at any time prior to contract award, without thereby
incurring any liability to the affected tenderer or tenderers or any obligation to
inform the affected tenderer or tenderers of the grounds for it s action.
29. Notification of Award
29.1 Prior to the expiration of the period of tender validity, ADS-MK will notify the
successful tenderer in writing that its tender has been accepted.
29.2 The successful tenderer shall be given a letter of award to sign and return the
acceptance to ADS-MK without reservations.
29.3 Upon the successful tenderer‟s furnishing of the performance security pursuant to
Clause 31, ADS-MK will promptly notify each unsuccessful tenderer and will
discharge its tender security, pursuant to Clause 14.
30. Signing of Contract
30.1 At the same time as ADS-MK notifies the successful tenderer that its tender has been
accepted, ADS-MK will send the tenderer the Contract Form provided in the tender
13
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
documents, incorporating all agreements between the parties.
30.2 Within fifteen (15) days of receipt of the Contract Form, the successful tenderer
shall sign and date the contract and return it to ADS-MK.
31. Performance Security
31.1 Within fifteen (15) days of the receipt of notification of award from ADS-MK, the
successful tenderer shall furnish the performance security in accordance with the
Conditions of Contract, in the Performance Security Form provided in the tender
documents, or in another form acceptable to ADS-MK.
31.2 Failure of the successful tenderer to comply with the requirement of Clause 30 or
Clause 31 shall constitute sufficient grounds for the annulment of the award and
forfeiture of the tender security, in which event ADS-MK may make the award to the
next lowest evaluated tenderer or call for new tenders.
32. Corrupt or Fraudulent Practices
32.1 ADS-MK requires that tenderers observe the highest standard of ethics during the
procurement process and execution of contracts. In pursuance of this policy, ADS-
MK: -
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) “corrupt practice” means the offering, giving, receiving or soliciting of
anything of value to influence the action of a public official in the
procurement process or in contract execution; and
(ii) “fraudulent practice” means a misrepresentation of facts in order to
influence a procurement process or the execution of a contract to the
detriment of ADS-MK, and includes collusive practice among tenderers
(prior to or after tender submission) designed to establish tender prices
at artificial non-competitive levels and to deprive ADS-MK of the
benefits of free and open competition;
(b) will reject a proposal for award if it determines that the tenderer recommended
for award has engaged in corrupt or fraudulent pract ices in competing for the
contract in question;
(c) will declare a firm ineligible, either indefinitely or for a stated period of time, to
be awarded any contract if it at any time determines that the firm has engaged
in corrupt or fraudulent practices in competing for, or in executing, a contract.
32.2 Furthermore, tenderers shall be aware of the provision stated in the General
Conditions of Contract.
14
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
Section C: General Conditions of Contract
1. Definitions
1.1 In this Contract, except where context otherwise requires, the following terms shall be
interpreted as indicated;
“The Contract” means the agreement entered into between ADS-MK and the
tenderer, as recorded in the Contract Form signed by the parties, including all
attachments and appendices thereto and all documents incorporated by reference
therein, as recorded in the Agreement Form and signed by the parties.
“The Contract Price” means the price payable to the tenderer under the Contract for
the full and proper performance of its contractual obligations.
“The Supplier” means the individual or firm supplying the services under this
Contract.
“The Services” means drilling, construction and testing of the borehole as specified
by ADS-MK under this Contract.
“Bills of Quantities” means the priced and completed Bill of Quantities forming part
of the tender.
“Schedule of Rates” means the priced Schedule of Rates forming part of the tender
[where applicable].
“The Completion Date” means the date of completion of the Works as certified by
the Employer‟s Representative.
“The Contractor” refers to the person or corporate body whose tender to carry out
the Works has been accepted by the Employer”
“The Contractor’s Tender” is the completed tendering document submitted by the
Contractor to the Employer.
“The Contract Price” is the price stated in the letter of Acceptance.
“Days” are calendar days; “Months” are calendar months.
“A Defect” is any part of the Works not completed in accordance with the Contract.
“The Defects Liability Certificate” is the certificate issued by ADS-MK‟s
Representative upon correction of defects by the Contractor.
“The Defects Liability Period” is the period named in the Appendix to conditions of
Contract and calculated from the Completion Date.
15
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
“Drawings” include calculations and other information provided or approved by the
Employer‟s Representative for the execution of the Contract.
“Employer” includes Central or Local Government administration, Universities,
Public Institutions and Corporations and is the party who employs the Contractor to
carry out the Works.
“Equipment” is the Contractor‟s machinery and vehicles brought temporarily to the
Site for the execution of the Works.
“Site” means the place or places where the permanent Works are to be carried out
including workshops where the same is being prepared .
“Materials” are all supplies, including consumables, used by the Contractor for
incorporation in the Works.
”Employer’s Representative” is the person appointed by ADS-MK and notified to
the Contractor for the purpose of supervision of the Works.
Specification” means the Specification of the Works included in the Contract.
“Start Date” is the date when the Contractor shall commence execution of the
works.
“A Subcontractor” is a person or corporate body who has a Contract with the
Contractor to carry out a part of the Work in the Contract, which includes Work on the
Site.
“Temporary Works” are works designed, constructed, installed and removed by the
Contractor which are needed for construction or installation of the Works.
“A Variation” is an instruction given by the Employer‟s Representative which
varies the Works.
“The Works” are what the Contract requires the Contractor to construct, install and
turnover to the Employer.
2. ADS-MK’s Representative’s Decision
2.1 Except where otherwise specifically stated, ADS-MK‟s Representative will
decide contractual matters between ADS-MK and the Contractor.
3. Application
3.1 These General Conditions shall apply in all Contracts made by ADS-MK for the
procurement of services.
16
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
4. Country of Origin
4.1 For purposes of this Clause, “origin” means the place where the Services originate.
5. Standards
5.1 The Services supplied under this Contract shall conform to the standards mentioned
in the Technical Specifications.
6. Use of Contract Documents and Information
6.1 The Contractor shall not, without ADS-MK‟s prior written consent, disclose the
Contract, or any provision thereof, or any specification, plan, drawing, pattern,
sample, or information furnished by or on behalf of ADS-MK in connection
therewith, to any person other than a person employed by the tenderer in the
performance of the Contract.
6.2 The Contractor shall not, without ADS-MK‟s prior written consent, make use of
any document or information enumerated in Clause 6.1 above.
6.3 Any document, other than the Contract itself, enumerated in Clause 6.1 shall
remain the property of ADS-MK and shall be returned (all copies) to ADS-MK on
completion of the Supplier‟s performance obligations under the Contract if so
required by ADS-MK.
6. Patent Rights
6.1 The Contractor shall indemnify ADS-MK against all third-party claims of
infringement of patent, trademark, or industrial design rights arising from the
supply of Services in Kenya.
7. Performance Security
7.1 Within fifteen (15) days of receipt of the notification of Contract award, the
successful tenderer shall furnish to ADS-MK the performance security in the
amount specified in Special Conditions of Contract.
7.2 The proceeds of the performance security shall be payable to ADS-MK as
compensation for any loss resulting from the Supplier‟s failure to complete its
obligations under the Contract.
7.3 The performance security shall be denominated in the Kenya shilli ngs, and shall
be in the form of a bank guarantee or an irrevocable letter of credit issued by a
reputable bank located in Kenya, acceptable to ADS-MK, in the form provided in
the tender documents.
7.4 The performance security will be discharged by ADS-MK and returned to the
tenderer not later than thirty (30) days following the date of completion of the
tenderer‟s performance obligations under the Contract, including any warranty
17
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
obligations, under the Contract.
8. Inspection and Tests
8.1 ADS-MK or its representative shall have the right to inspect and/or to test the
drilling materials to confirm their conformity to the Contract specifications.
ADS-MK shall notify the tenderer in writing, in a timely manner, of the
identity of any representatives retained for these purposes.
8.2 The inspections and tests will be conducted on the drilling site
8.3 Should any inspected or tested drilling materials fail to conform to the
Specifications, ADS-MK shall reject the materials, and the Contractor sha ll
either replace the rejected materials or make alterations necessary to meet
specification requirements free of cost to ADS-MK.
8.4 Nothing in Clause 8 shall in any way release the Contractor from any warranty
or other obligations under this Contract.
9. Delivery and Documents
9.1 Delivery of the slotted liners shall be made by the Contractor in accordance with
the terms specified by ADS-MK in its Schedule of Requirements and the
Special Conditions of Contract.
10. Safety, Temporary works and Discoveries
10.1 The Contractor shall be responsible for design of temporary works and shall
obtain approval of third parties to the design of the temporary works where
required.
10.2 The Contractor shall be responsible for the safety of all activities on the Site.
10.3 Anything of historical or other interest or significant value unexpectedly
discovered on the Site shall be the property of the Representative of such
discoveries and carry out ADS-MK Representative‟s instructions for dealing
with them.
11. Work Program and Sub-contracting
11.1 Within seven days after Site possession date, the Contractor shall submit to
the ADS-MK for approval a program showing the general methods,
arrangements, order and timing for all the activities in the Works.
11.2 The Contractor may sub-contract the Works (but only to a maximum of 25
percent of the Contract Price) with the approval of ADS-MK. However, he
shall not assign the Contract without the approval of the Employer in
writing. Sub- contracting shall not alter the Contractor‟s obligations.
18
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
12. The Site
12.1 The Employer shall give possession of all parts of the Site to the Contractor.
12.2 The Contractor shall allow ADS-MK and any other person authorized by
ADS- MK Representative, access to the Site and to any place where work in
connection with the Contract is being carried out or is intended to be carried
out.
13. Instructions
13.1 The Contractor shall carry out all instructions of ADS-MK, which are in
accordance with the Contract.
14. Extension of Completion Date
14.1 ADS-MK shall extend the Completion Date if an occurrence arises which
makes it impossible for completion to be achieved by the Intended
Completion Date. ADS-MK shall decide whether and by how much to extend
the Completion Date.
14.2 For the purpose of this clause, the following shall be
(a) force majeure, or
(b) reason of any exceptionally adverse weather conditions or
(c) reason of civil commotion, strike or lockout affecting any of the trades
employed upon the works or any of the trades engaged in the preparation,
manufacture or transportation of any goods or materials required for the
works, or
(d) reason for ADS-MK‟s instructions issued under these Conditions, or
(e) reason of the contractor not having received in due time necessary
instructions, drawings, details or levels form ADS-MK‟s Representative
for which he specifically applied in writing on a date which having regard
to the date of completion stated in the appendix to these Conditions or any
extension of time then fixed under this clause was neither unreasonably
distant from nor unreasonably close to the date on which it was necessary
for him to receive the same, or
(f) delay on the part of artists, tradesmen or others engaged by ADS -MK in
executing work not forming part of this Contract, or
(g) reason of delay by statutory or other services providers or similar bodies
engaged directly by ADS-MK, or
(h) reason of opening up for inspection of any Work covered up or of the
testing of any of the Work , materials or goods in accordance with these
19
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
conditions unless the inspection or test showed that the Work, materials or
goods were not in accordance with this Contract, or
(i) reason of delay in appointing a replacement ADS-MK Representative, or
(j) reason of delay caused by the later supply of goods or materials or in
executing Works for which ADS-MK or his agents are contractually
obliged to supply or to execute as the case may be, or
(k) Delay in receiving possession of or access to the Site.
15. Management Meeting
15.1 A Contract management meeting shall be held regularly and attended by ADS-
MK‟s Representative and the Contractor. Its business shall be to review the plans
for the remaining Work. ADS-MK‟s Representative shall record the business of
management meetings and provide copies of the record to those attending the
meeting. The responsibility of the parties for actions to be taken shall be decided
by ADS-MK‟s Representative either at the management meeting or after the
management meeting and stated in writing to all who attend the meeting.
15.2 Communication between parties shall be effective only when in writing.
16. Defects
16.1 ADS-MK‟s Representative shall inspect the Contractor‟s work and notify
the Contractor of any defects that are found. Such inspection shall not affect the
Contractor‟s responsibilities. ADS-MK‟s Representative may instruct the
Contractor to search for a defect and to uncover and test any Work that ADS-
MK‟s Representative considers may have a defect. Should the defect be found, the
cost of uncovering and making good shall be borne by the Contractor. However, if
there is no defect found, the cost of uncovering and making good shall be treated
as a variation and added to the Contract Price.
16.2 ADS-MK‟s Representative shall give notice to the Contractor of any defects
before the end of the Defects Liability Period, which begins at Completion, and is
defined in the Appendix to Conditions of Contract.
16.3 Every time notice of a defect is given, the Contractor shall correct the notified
defect within the length of time specified by ADS-MK‟s Representative‟s notice.
If the Contractor has not corrected a defect within the time specified in ADS-MK
Representative‟s notice, the ADS-MK‟s Representative will assess the cost of
having the defect corrected by other parties and such cost shall be treated as a
variation and be deducted from the Contract Price.
17. Bills of Quantities/Schedule of Rates
17.1 The Bills of Quantities/Schedule of Rates shall contain items for the construction,
installation, testing and commissioning of the Work to be done by the Contractor.
The contractor will be paid for the quantity of the Work done at the rates in the
Bills of Quantities/Schedule of Rates for each item.
20
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
Items against which no rate is entered by the Tenderer will not be paid for
when executed and shall be deemed covered by the rates for other items in
the bills of Quantities/Schedule of Rates.
17.2 Where Bills of Quantities do not form part of the Contract, the Contract price
shall be a lump sum (which shall be deemed to have been based on the rates in
the Schedule of Rates forming part of the tender) and shall be subject to re-
measurement after each stage.
18. Variation
18.1 The Contractor shall provide the ADS-MK‟s Representative with a quotation
for carrying out the variations when requested to do so. The ADS-MK‟s
Representative shall assess the quotation and shall obtain the necessary
authority from ADS-MK before the variation.
18.2 If the Work in the variation corresponds with an item description in the Bill of
Quantities/Schedule of Rates, the rates in the Bill of Quantities/Schedule of
Rates shall be used to calculate the value of the variation. If the nature of the
Work in the variation does not correspond with items in the Bill of
Quantities/Schedule of Rates, the quotat ion by the Contractor shall be in the
form of new rates for the relevant items of Work.
18.3 If the Contractor‟s quotation is unreasonable, the ADS -MK‟s Representative
may order the variation and make a change to the Contract Price, which shall
be based on the ADS-MK Representative‟s own forecast of the effects of the
variation on the Contractor‟s costs.
19. Payment Certificate and Final Account
19.1 The Contractor shall be paid after each stage of Work (subject to re -measurement by
ADS-MK of the work done in each stage before payment is made). In case of lump-
sum Contracts, the valuation for each stage shall be based on the quantities so
obtained in the re-measurement and the rates in the Schedule of Rates.
19.2 Upon deciding that Works included in a particular stage are complete, the Contractor
shall submit to the ADS-MK‟s Representative his application for payment. The
ADS-MK‟s Representative shall check, adjust if necessary and certify the amount to
be paid to the Contractor within 21 days of receipt of the Contractor‟s application.
ADS-MK shall pay the Contractor the amounts so certified within 30 days of the date
of issue of each Interim Certificate.
19.3 The Contractor shall supply ADS-MK‟s Representative with a detailed final account
of the total amount that the Contractor considers payable under the Contract before
the end of the Defects Liability Period. The ADS-MK‟s Representative shall issue a
Defect Liability Certificate and certify and final payment that is due to the Contractor
within 30 days of receiving the Contractor‟s account if it is correct and complete. If
not, ADS-MK‟s Representative shall issue within 21 days a schedule that states the
scope of the corrections or additions that are necessary. If the final account is still
unsatisfactory after it has been resubmitted, ADS-MK‟s Representative shall decide
on the amount payable to the Contractor and issue a Final Payment Certificate. ADS -
MK shall pay the Contractor the amount so certified within 60 days of the issue of
the Final Payment Certificate.
21
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
19.4 If the period laid down for payment to the Contractor upon each of the ADS-MK‟s
Representative‟s Certificate by ADS-MK has been exceeded, the Contractor shall be
entitled to claim simple interest calculated pro-rata on the basis of the number of days
delayed at the Central Bank of Kenya‟s average base lending rate prevailing on the first
day the payment becomes overdue. The Contractor will be required to notify the Employer
within 15 days of receipt of delayed payments of his intentions to claim interest.
20. Insurance
20.1 The Contractor shall be responsible for and shall take out appropriate cover against,
among other risks, personal injury; loss of or damage to the Works, materials and
plant; and loss of or damage to property.
21. Liquidated Damages
21.1 The Contractor shall pay liquidated damages to ADS-MK at the rate 0.001 per cent of
the Contract price per day for each day that the actual Completion Date is later
than the Intended Completion Date except in the case of any of the occurrences
listed under clause 14.2. ADS-MK may deduct liquidated damages from payments
due to the Contractor. Payment of liquidated damages shall not affect the Contractor‟s
liabilities.
22. Completion and Taking Over
22.1 Upon deciding that the Work is complete the Contractor shall request the ADS-MK‟s
Representative to issue a Certificate of Completion of the Works, upon deciding that the Work
is completed.
22.2 ADS-MK shall take over the Site and Works within seven days of the ADS-MK‟s
Representative issuing a Certificate of Completion.
23. Termination
23.1 ADS-MK may terminate the Contract if the other party causes a fundamental breach of
the Contract. These fundamental breaches of Contract shall include, but shall not be
limited to, the following;
a. the Contractor stops Work for 30 days continuously without reasonable
cause or authority from the ADS-MK‟s Representative;
b. the Contractor is declared bankrupt or goes into liquidation other than for
reconstruction or amalgamation;
c. a payment certificate by the ADS-MK‟s Representative is not paid by
ADS-MK to the Contractor within 30 days after the expiry of the payment
periods stated in sub clauses 19.2 and 19.3 hereinabove.
d. ADS-MK‟s Representative gives notice that failure to correct a particular
defect is a fundamental breach of Contract and the Contractor fails to
correct it within a reasonable period of time. if the Contractor, in
the judgment of ADS-MK has engaged in corrupt or fraudulent practices
in competing for or in executing the Contract.
22
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
23.2 In the event ADS-MK terminates the Contract in whole or in part, it may
procure, upon such terms and in such manner as it deems appropriate, Services
similar to those undelivered, and the Supplier shall be liable to ADS -MK for any
excess costs for such Services.
23.3 If the Contract is terminated, the Contractor shall stop Work immediately, and
leave the Site as soon as reasonably possible. The ADS-MK‟s Representative
shall immediately thereafter arrange for a meeting for the purpose of taking record
of the Works executed and materials, goods, equipment and temporary buildings
on Site.
24. Payment upon Termination
24.1 ADS-MK may employ and pay other persons to carry out and complete the
Works and to rectify any defects and may enter upon the Works and use all
materials on Site, plant, equipment and temporary works.
24.2 The Contractor shall, during the execution or after the Completion of the Works
under this clause, remove from the Site as and when required within such
reasonable time as the ADS-MK‟s Representative may in writing specify, any
temporary buildings, plant, machinery, appliances, goods or materials belonging to
him, and in default thereof, ADS-MK may (without being responsible for any
loss or damage) remove and sell any such property of the Contractor, holding the
proceeds less all costs incurred to the credit of the Contractor.
24.3 Until after completion of the Works under this clause, ADS -MK shall not be
bound by any other provision of this Contract to make any payment to the
Contractor, but upon such completion as aforesa id and the verification within a
reasonable time of the accounts therefore the ADS-MK‟s Representative shall
certify the amount of expenses properly incurred by ADS-MK and if such
amount added to the money paid to the Contractor before such determination
exceeds the total amount which would have been payable on due completion in
accordance with this Contract, the difference shall be a debt payable to ADS-MK
by the Contractor; and if the said amount added to the said money be less than
the said total amount, the difference shall be a debt payable by ADS -MK to the
Contractor.
23
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
25. Payment
25.1 The method and conditions of payment to be made to the Contractor under this
Contract shall be specified in Special Conditions of Contract.
25.2 Payments shall be made promptly by ADS-MK as specified in the Contract.
26. Prices
26.1 Prices charged by the Contractor for drilling borehole under the Contract shall not,
with the exception of any price adjustments authorized in Special Conditions of
Contract, vary from the prices by the Contractor in its tender.
27. Assignment
27.1 The Contractor shall not assign, in whole or in part, its obligations to perform
under this Contract, except with ADS-MK‟s prior written consent.
28. Subcontracts
28.1 The Contractor shall notify ADS-MK in writing of all subcontracts awarded under
this Contract if not already specified in the tender. Such notification, in the original
tender or later, shall not relieve the Supplier from any liability or obligation under
the Contract.
29. Resolution of Disputes
29.1 ADS-MK and the Supplier shall make every effort to resolve amicably by direct
informal negotiation any disagreement or dispute arising between them under or in
connection with the Contract.
29.2 If, after thirty (30) days from the commencement of such informal negotiations
both parties have been unable to resolve amicably a Contract dispute, either party
may require that the dispute be referred for resolution to formal mechanisms.
These mechanisms include, but are not rest ricted to, conciliation by a third party,
adjudication in an agreed national or international forum, and/or international
arbitration.
30. Works, Language and Law of Contract
30.1 The Contractor shall Construct and install the Works in accordance with the
Contract documents. The works may commence on the Start Date and shall be
carried out in accordance with the Program submitted by the Contractor, as updated
with the approval of the ADS-MK‟s Representative, and complete them by the
intended Completion Date.
30.2 The language of the Contract and the law governing the Contract shall be English
language and the Laws of Kenya respectively unless otherwise stated.
24
31. Force Majeure
31.1 The tenderer shall not be liable for forfeiture of its performance security, o r
termination for default if and to the extent that the delay in performance or other
failure to perform its obligations under the Contract is the result of an event of Force
Majeure.
25
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub
County
Section D: Special Conditions of Contract
1. Application
The following Special Conditions of Contract shall supplement the General Conditions of
Contract. Whenever there is a conflict, the provisions herein shall prevail over those in the
General Conditions of Contract.
2. Definitions
The Purchaser is Anglican Development Services-Mt.Kenya. Bishop Chipman House,
2nd
floor, opp. Lord Baden Powell cemetery, and P.O. BOX 2376-10140 Nyeri, Kenya
and includes its legal representatives, successors or assigns.
3. Performance Security
The Performance Security shall be in the amount of 10% of the Contract Price.
4. Inspection of Sites and Access thereto
ADS-MK in no way guarantees completeness nor accuracy of the soil, materials,
subsurface and hydrological information made available to the Contract at the time of
tendering or at any other time during the period of the Contract, and the Contractor shall be
responsible for ascertaining for himself all information as aforesaid for the execution of
Works and his tender shall be deemed to have been priced accordingly.
The Contractor shall not enter any part of the Sites until he has requested and received
permission to do so from ADS-MK or ADS-MK‟s representative.
The Contractor shall not use any portion of the Site for any purpose not connected with
Works.
5 Damage of Persons And Property
The Contractors shall (except if and do far as the specification provides otherwise)
indemnify and keep indemnified ADS-MK against losses and claims for injuries or
damages of any person or any property whatsoever (other than surface or other damage to
land being or crop being n the Site suffered by tenants or occupiers) which may arise out
of or on consequence of the construction and maintenance of the works against all claims,
demands, proceedings, damages, costs, charges and expenses whatsoever in respect of or
in relation thereto. Provided always that nothing herein contained shall be deemed to
render against any contained compensation or damages for or with respect to: -
a) The Permanent use or occupation of land by the Works or any part thereof or (save as
hereinafter provided) surface or other damage as aforesaid.
26
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
b) The right of ADS-MK to construct the Works or any part thereof on, over, under, in
or through any land.
c) Interference whether temporary or permanent with any right or light air way or
water or other easement or quasi-easement which is the unavoidable result of the
Works in accordance with the Contract.
d) Injuries or damages to persons or property resulting from any act or neglect done or
committed during the currency of the Contract of ADS-MK, his agents, servants or
other contractors (not being employed by the Contractor) or for in respect of any
claims, demands, proceedings, damages, costs, charges and expenses in respect
thereof in relation thereto.
6 Contractor’s Superintendence
The Contractor shall, within seven (7) days of receipt of the ADS-MK‟s representative
order to commence the Works, inform ADS-MK in writing, the name of the Contractor‟s
representative and the anticipated date of his arrival on Site.
7 Liquidation Damages for Delay in Completion
7.1 If the Contractor hitherto does not complete the works within the completion time
prescribed by the Contractor or extended time, then the Contractor shall pay to ADS-MK
the sum to money as stated in Sub-clause 7.3, herewith as Liquidated Damages for such
default for everyday or part thereof while shall elapse between the time prescribed by
the Contract or extended time as the case may be and the date of completion.
7.2 ADS-MK may without prejudice to any other method or recovery deduct the amount of
such damages from any monies due or which may become due to the Contractor. The
payment or deductions to such damages shall not relieve the Contractor from his
obligations or liabilities under the Contract.
7.3 The amount of liquidated damages to be paid by the Contractor to ADS-MK for each day
or part thereof of delay in the completion of the works as referred to in clause 7.1 hereof,
shall be 0.00 1% of the contract price. The total amount of liquidation damages payable
under this clause shall not exceed 10% (ten per cent) of the Contract price.
8 Accident or Injury to Workmen
8.1 ADS-MK shall not be liable for or in respect of any damages or compensation payable at
the law in respect or in consequence of any accident or injury to any workman or other
person in the employment of the Contractor and any sub-contractor save and except an
accident or injury resulting from any act or default of ADS-MK, his agents or servants
and the Contractor shall indemnify and keep indemnified ADS-MK against all such
damages and compensation (save and except as aforesaid) and against all claims,
27
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub
County
demands, proceedings, costs, charges, and expenses whatsoever in respect thereof or in
relation thereto.
8.2 The Contractor shall insure against liability with an insurer approved by ADS -MK
(which approval shall not be unreasonably withheld) and shall continue such insurance
during the whole time that any person are employed by him on the works and shall
when required produce to the ADS-MK‟s Representative such policy of insurance and
the receipt for payment of the current premium, provided always that in the respect of
any person employed by any sub-clause shall be satisfied if the sub-contractor shall
have insurance against the liability in respect of such persons in such a manner that
ADS-MK is indemnified under the policy of insurance and the receipt for payment of
the current premiums.
9 Payment of Retention Money
One half of the retention money shall become due upon the issue of a Taking – Over
Certificate and shall be paid to the Contractor when the Engineer‟s Representative shall
certify in writing that the last section of the whole of the Works has been substantial
complete and the other half shall be paid to the Contractor after the expiration of the
Defect Liability Period and the issue of a Certificate to the effect. Provided always that is
such Works ordered during such period in accordance with the Contractor, the
Employer shall be entitled to withhold payment (until the completion of such Works) so
remaining to be executed. Provided further that in the event of different Defects
Liability Period having become applicable to different parts of the Works the expression
“expiration of the Defect Liability Period” shall for the purpose of the Clause be
deemed to mean the expiration of the latest of such period.
10 Co-operation With Other Contractors
The Contractor shall in accordance with the requirements of the ADS-MK Representative
afford all reasonable co-operation to any Contractors and their employees engaged by
ADS-MK and to the employees of ADS-MK and of any other duly constituted authorities
who may be employed in the execution on or near the site of any work not included in the
Contract or of any contract which ADS-MK may enter into in connection with or
ancillary to the works. If however, the Contractor shall on the written request of the
ADS-MK‟s Representative make available to any such other Contractor or to ADS-MK or
any such authority any roads or ways for the maintenance of which the Contractor is
responsible or permit the use by any such of the Contractor‟s scaffolding or other
Contractor‟s Equipment on the site or provided any other services of whatsoever nature
for any such, ADS-MK shall pay to the Contractor in respect of such use or services
such sum or sums as shall , in the opinion of the ADS-MK Representative, be
reasonable provided that the Contractor shall incur additional expenses as a result of
such use.
28
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
11 Interference With Traffic and Adjoining Properties
All operations necessary for the execution of the works and for the construction of any
temporary works shall so far as compliance with the requirements of the Contract
permits be carried out so as not to interfere unnecessarily or improperly with the
convenience of the public or the access to use and occupation of the public or private
roads and footpaths or to or of properties whether in the possession of ADS-MK or of any
other person and the Contractor shall save harmless and indemnify ADS -MK in respect
of all the claims, demands, proceedings, damages, costs, charges and expenses
whatsoever arising out of or in relation to any such matters insofar as the Contractor is
responsible thereof.
12 Accommodation and any Information on Contractor’s Employees
a) The contractor shall ensure that any accommodation he provides for these
employees is used only by such of his personnel as are engaged for the
Contractor and for the period of the Contractor only. The Contractor shall be
responsible for ensuring that permanent rights and occupancy are not acquired by
temporary housed personnel on ADS-MK land or any other land and also for
cleaning the camp sites on completion of the works and indemnify ADS -MK
against claims for compensation arising from lack of such clearances.
b) The Contractor shall provide at the request of the ADS-MK Representative such
reasonable information about his employees as may be necessary including (inter
alia) names, identification numbers, residence permit number and work permit
numbers.
13 Publicity
The Contractor shall treat all matters in connection with the contract as strictly
confidential and shall not publish or cause to be publishes any information concerning
the Project without the prior approval of ADS-MK.
14 Bribery and Corruption
It is hereby agreed by the Contractor that the giving or offering of any bonus or
commission whether in the form of money, goods or services by the Contractor or his
employees to officers or employees of ADS-MK or to firms or persons working on his
behalf shall be deemed a breach of the Contract and ADS-MK shall have the right to
terminate the contract for cause in connection with the provision hereof.
15 Safety and Environment Requirements
The Contractor shall at all times execute the works in a safe and secure manner and
actively practice safety through the term of the Contract and shall comply with the
applicable Government fire and safety regulations.
29
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
The formulation and enforcement of an adequate safety program shall be the obligation of
the Contractor with respect to all the Works under this Contract, regardless of whether
performance by the Contractor or his subcontractors. The Contractor shall, within 14
days after commencement of the works, meet the ADS-MK Representative to present
and discuss his plan for the establishment of such safety measures as may be necessary
to provide against accidents, unsafe acts and so forth. Within 28 days after
commencement of the works, the Contractor shall submit a written safety program to the
ADS-MK covering the overall Works and based on the laws and regulations of Kenya.
In addition, he shall prepare special safety programs for working within electricity
generating and geothermal exploration facilities.
Notwithstanding the foregoing, the Contractor shall observe the following measures
with a view to reducing or eliminating adverse environmental effects by the Site Works.
i) All queries and borrow pits shall be filled and landscaped to their original
state after extraction of construction materials
ii) Soil erosion due to surface runoff or water from culverts or other drainage
structures should be avoided by putting in place proper erosion control
measures that shall include, but not limited to grassing, planting of trees,
gabions etc.
iii) Long traffic diversion roads shall be avoided so as to minimize the effect of
dust on the surrounding environment. In any case all diversions shall be kept
damp and dust free at the Contractor‟s expense.
iv) Dumping shall be done only at designated dumping areas and not
haphazardly on surroundings.
16 Performance and Guarantee Insurance
The Contractor shall avail the performance guarantee and insurance covers as required
in the Contract. No separate payment shall be made for complying with this requirement
and the Contractor should allow for this in his rates.
The Performance Security shall be issued by a Bank incorporated in Kenya. The amount
of guarantee shall be as stated in the Appendix to Condition of Contract.
The bank guarantee shall be issued by an established and reputable bank approved by
the ADS-MK and located in Kenya.
The performance guarantee shall be valid until a date 28 days after the date of issue of
the Taking-Over Certificate. The security shall be returned to the Contractor within 28
days of expiration.
30
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
17 Law Governing the Contract
This Contract shall be governed by and construed in accordance with the Laws of
Kenya.
18 Force Majeure
Neither party shall be considered in default in performance of his obligations under the
Contract to the extent that performance of such obligations is delayed by force majeure.
Force majeure shall mean any event reasonably beyond the control of the parties hereto
including, but not limit to, hostilities, restraint of rules or people, revolution, civil
commotion, forces of nature, explosion, embargo, or any law, proclamation, regulations
or ordinance or any Government or Government agency having or claiming to have
jurisdiction at the site of the work.
19 Responsibility for Sub-Contractors
The Contractor shall be responsible for observance by all sub-contractors of all the
provision of Contract. The Contractor shall be responsible for the acts of default of any
sub-contract, his agents or employees, as fully as if they were the acts or defaults of the
Contractor, his agents or employers.
20 Indemnity Against all Claims of Infringement
The Contractor shall indemnify ADS-MK against all claims of infringement of the patent,
registered design, copyright, trademark or trade name, or other intellectual property
right out of the Contractor‟s execution of the works.
21 Failure to Comply With Contract Requirements
a) If the contact: -
i) Fails to comply with a 14 day notice asking it to execute the works in
accordance with the Contract, or
ii) Abandon or repudiates the Contracts or,
iii) Without reasonable excuse fails to commence or complete the works in
accordance with the Contract, or
iv) Becomes bankrupt or insolvent, goes into liquidation, has a receiving or
administration order and against it or compounds with its creditors.
Then ADS-MK may, after having given 14 days notice to the Contractor, terminate the
Contract and expel the Contractor‟s personnel from the site. After such termination
ADS-MK shall not be liable to make any further payment to the Contractor. ADS- MK
shall be entitled to recover from the Contractor the extra costs of completing the works without
prejudice to any other right of ADS-MK.
31
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
.
b) If ADS-MK;
i) Fails to pay the Contactor in accordance with the terms of the Contract,
or
ii) Becomes bankrupt or insolvent, goes into liquidation, has a receiving or
administration order made against it or compound with its creditors.
Then the Contractor may, after having given 42 days notice to ADS-MK terminate the
Contract. After such termination the Contractor shall be entitled to recover from ADS-
MK the unpaid balance for all services performed and completed by the Contractor in
accordance with the Contract and payment for all additional labor performed by the
Contractor and its subcontractors which has not been paid for otherwise in accordance with the
Contract without prejudice to any other right of the Contractor.
22 Resolution of Disputes
ADS-MK and Contractor shall make every effort to resolve amicably by direct informal
negotiations, any disagreement or dispute arising between them under or in connection
with the Contract. If, after 30 days from the commencement of such informal
negotiations, ADS-MK and the Contractor have been unable to resolve such dispute
arising in connection with the Contract by an amicable settlement, either party may
require that the dispute be referred for resolution by arbitration through a single
arbitrator to be appointed in default of agreement by the Chairman of the Chartered
Institute of Arbitrators, Kenya Branch.
Arbitration shall take place in Nairobi, Kenya. The language of all arbitration
proceedings shall be in English. The cost of arbitration shall be apportioned by the
Arbitrator according to his findings. Neither party shall have recourse to a court of law or
other authority for the purpose of appealing against the decision of the Arbitrator, which
will be binding to both ADS-MK and the Contractor.
23. Notices:
For the Purchaser:
Regional Development Co-ordinator,
Anglican Development Services-Mt. Kenya
Bishop Chipman house, Opp. Baden Powell Cemetery,
P.O Box 2376 10140 Nyeri
Tel: +254 61 2034813
24. Prices
Prices shall be fixed during the Tenderer‟s performance of the Contract and not subject to
variation on any account.
32
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
25 Completion Period
Subject to Clause 22, Section C, the drilling of the borehole shall be completed within 4
weeks after the date of contract award. The date the contract is signed shall be the
commencement date for drilling of borehole in Nkarusa.
33
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
SECTION E: Technical Specifications, Schedule of Requirements and Prices
Notes
1. The goods to be supplied must be 100% genuine parts.
2. Installation must be for all items. Partial installation shall not be accepted.
3. The Steel Casings shall be for borehole
TECHNICAL REQUIREMENTS
(a) The Steel Casings shall be genuine, new and unused.
(b) The Steel Casings shall be seamless.
(c) The Steel Casings shall be manufactured from an open-hearth electric
furnace or basic oxygen steel.
(d) Each piece of Steel Casings shall be supplied with power tight but tress
thread coupling on one end.
(e) Approved steel thread protectors shall be provided for both ends for each
piece of casing.
(f) The Steel Casings shall be mill coated with a non-bituminous coating to
prevent rusting during transit and storage.
(g) Mill test certificate from the manufacturer to be provided.
(h) Attach relevant catalogues and descriptive literature.
34
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub
County
SECTION F – Appendix to Condit ions of Contract
THE EMPLOYER IS
Name: Anglican Development Services-Mt. Kenya
Address P.O. B OX 2376-10140 Nyeri
Name of Employer‟s Representative: Loise W. Chege
Title: Project Manager (HELI Project)
Telephone: +254 61 2034813
The name (and identification number) of the Contract is: HELI 101: TENDER FOR
DRILLING AND CONSTRUCTION OF ONE BOREHOLEAT NKARUSA, KAJIADO
WEST SUB- COUNTY
The Works consist of:
Mobilization of drilling equipment to site, drilling and casing of borehole.
Re-development of borehole to include measurement of total depth, borehole
cleaning, chemical development and physical development.
Testing of borehole to include a pre-test, a step drawdown test, constant
discharge test and recovery test.
Borehole equipping that shall entail installation and testing as per
specifications and Ministry of Water requirements.
Construction of drains and channels internal dimensions to be approved by
ADS-MK.
Construction of a water tower with a plastic storage tank of 24000L capacity.
Testing and commissioning of the system as per the specifications.
Construction of a permanent structure to host master meters and c ontrol
panel.
Facilitating the connection of a 3-phase power line by Kenya Power.
Submission of a Borehole Completion Record Certificate that should include
Geological logging data and other records as per the BOQ
The start date shall be: as prescribed
The following documents also form part of the Contract:
Agreement, Letter of Acceptance, Contractor’s Tender, Conditions of Contract and
Special Conditions, Specifications, Drawings and Bills of Quantities
The Site is located at Nkarusa Village, Oloirien Location, Kajiado West Sub- County, near
Kiserian town.
35
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
The Defects Liability Period is 180 days.
Amount of Tender Security is in the amount of 2% of the total tender price.
The amount of Interim Payment Certificate is Kshs Five Hundred Thousand (Kshs 500,000.00.
Please note that the Interim/advance payment is paid upon payment of an advance payment guarantee of
an equivalent amount.
The Retention Money is 10% percent of Interim Payment Certificate.
36
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
SECTION G – Specifications and Bills of Quantities
Specifications
1. Scope
2. Materials and Workmanship
II Bill of Quantities
ITEMDESCRIPTION UOM QTY UNIT COST AMOUNT
1 Hydrogeological survey report - Sum
2 Follow-up and acquisition of drilling permit from the Water Resources Management Authority - Sum
3 National Environmental Management Authority report - Sum
4 Mobilization / Demobilization of all Drilling Equipment, rig, as well as personnel to the site - 1
5 Erecting & Dismantling of Drilling Rig & Equipment - 1
6 Drilling 8" dia borehole using a rotary rig M 220
7 Supply & Installation of 152 mm dia, class B, steel plain casing M 155
8 Supply & Installation of 152mm dia, class B,steel machine cut screen casing M 65
9 Supply and Installation of non-laterite gravel pack in the borehole Ton 7
10 Borehole development by air jetting before testpumping until water is clean Hrs 3
11 Test Pumping for 24 hours, draw-down, yield recovery and data analysis Hrs 24
12 Borehole Completion Data and Water Chemical Analysis report - Sum
13 Supply and installation of a multistage stainless steel centrifugal submersible pump capable of
pumping water to the raised water reservoir at 5M3/hr, including control
panel, electrodes, electrode cable, underground cables float switch, standard control panel
and all other necessary borehole sundries
- Sum
14
Provide all materials and construct concrete top slab 1 x 1 x 0.5M with well cap mild steel
blank flange, which shall incorporate a threaded nipple of 19 mm (3/4”) diameter with cap - Sum
15 Supply of water for drilling operations and camp use. LS sum
16
Design, provide all materials and construct a standard lockable masonry borehole protection
chamber/Control panel room - sum
17 Well disinfection sum
18
Design to BS449, provide all materials, fabricate and assemble a 10M high steel tower
capable of supporting a 24000L PVC water tank - sum
19
Supply and installation a 24000L capacity PVC tank,complete with 2" PVC pipes(Approx
20M) and fittings to complete the assembly to the ground level - sum
20
Fencing off the borehole site(1/8 Acre) with high quality treated wooden poles and 12 gauge
mesh wire and a 5 by 6 feet faricated lockable gate Sum
21
Making arrangements with Kenya Power for a 3-phase power connection to the pump with
the adjacent power line Sum
Total Amount(Inclusive of 16% VAT tax)
DRILLING A BOREHOLE 220 METERS DEEP AT NKARUSA,OLOIRIEN(APPROX 14KM FROM KISERIAN)
37
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
SPECIFICATIONS
1.0 Scope of Works
The works will comprise drilling, construction, and test pumping of ONE BOREHOLEat
Nkarusa Village, Oloirien Location, Kajiado West Sub- County, 14 KM from Kiserian
town.
1.1 Location of the Drilling sites and Installation of Pumping Equipment
Equipment will be supplied and installed at the selected site. The ADS -MK
Representative shall visit with the Contractor or his Representative the exact sites for
drilling borehole and carrying out pumping tests. ADS-MK shall provide the Contractor
with any data, information and facilities that are within his responsibility, required for
the drilling and construction of the borehole. It will remain the Contractor‟s
responsibility to inspect the sites and assess the accessibility. The delivered materials
must be suitable to function properly in tropical hot and dusty conditions.
1.2 Stand-by Time
Charges for stand-by time shall only be reimbursed to the Contractor in case of default on
the part of ADS-MK or his Representative, and with prior written notification by the
Contractor to the same.
1.3 Spare parts
Spare parts of the equipment to be supplied and installed shall as much as possible be
available in Kenya. The Contractor shall furnish the ADS-MK Representative and the
ADS-MK of the addresses of the Suppliers of such spare parts.
1.4 Use of Concrete and Cement
All concrete and cement to be used shall be according to standard specifications or as
directed by the ADS-MK representative.
1.5 Pipelines
All pipelines and fittings to be installed will be of galvanized iron and will be supplied
and installed according to the specifications indicated below: -
Underground pipeline and fittings shall be of Class B GI mate rial at a diameter of not
less than 2”
Pipes shall be buried at a depth of not less than 0.6 meters.
38
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
1.6 Supply and Installation of pumping equipment
This part will be carried out by the Contractor.
1.7 Borehole design
The borehole design (Appendix B) has been provided by ADS-MK and any
modifications to the design by the Contractor shall be made in writing and approved by
ADS-MK prior to commencement of works. The borehole will be drilled with a 12 inch
bit and cased with 152mm dia steel casing in the dry rock formation and 8 inch slotted
liner (steel screen) in the water bearing formation. All this shall be done by the
Contractor to the approval of the ADS-MK. The Contactor shall install a bottom plug and
a gravel pack between the casing and the borehole wall.
1.8 General Site Works
The Construction of drains and water channels shall be as approved by ADS -MK. The
proper functioning of the whole systems will be tested by the Contractor or his
Representative in the presence of the Engineer.
2.0 Pipe work & Excavation
2.1 Setting out-Pipeline
Before commencement of any excavation, the route shall be surveyed in conjunction
with the ADS-MK‟s representative to establish existing ground levels and these agreed
levels shall form the basis for the calculation of quantities of any subsequent
excavation and backfilling. These levels shall be taken before any topsoil has been
removed. The contractor shall in the presence of the ADS-MK Representative set out
pipeline centre line in accordance with the drawings making any changes the ADS -MK
representative may deem necessary and confirming the exact position of other surfaces
e.g. Power cables, Communication cables etc.
2.2 Classification of Excavation
The ADS-MK Representative’s decision on the classification of any excavated material
shall be final and shall be based on the following guidelines: -
1. Class I – Soft material
Soft material shall include all materials which in the opinion of the ADS -MK
representative, does not require blasting or metal wedges and sledge hammers of
compressed air drilling or ripping or rooting. It shall include gravel stones and
39
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
boulders less than 0.2 cubic meters in volume, which can be removed without re-course to
these methods.
2. Class II – Compacted Gravel or Decomposed Rock
Compacted Gravel or decomposed rock shall include all material such as consolidated
murram and decomposed or stratified rock, weathered tuff, stone, or boulder less than 0.2
cubic meters in volume which are harder than soft or normal material in that they may be
extracted by ripping as defined in Clause III, or in confined spaces by hand excavation by
using compressor tolls providing all reasonable steps to the satisfaction of the ADS-MK
Representative have been taken to facilitate the removal of the material by other methods
3. Class III – Rock
Rock shall include all material which in the opinion of the ADS-MK Representative
requires blazing or the use of materials wedge harmers or the use of compressed air drilling
for its removal or cannot be extracted by ripping with a tractor of at least 180 hp and rear
noted heavy duty ripper. Individual boulders greater than 0.2 cubic meters in volume shall
be included in this class. It should be noted that blasting shall not be allowed.
4. Sterilizing Water Retaining Structures
The inside of all interior pipe-work and fitting shall be thoroughly cleaned and washed
after water – tightness test has been approved by the ADS-MK Representative to
remove all contamination and the water from these operations shall be removed by
squeegees and drained away.
5. Accommodation
The Contractor shall provide accommodation for his workers. This may include
providing a workers camp on site.
6. Precautions against Contamination of the Works
The contractor shall at all times take every precaution against contamination of Works.
He shall give strict Instructions to all persons employed by him to use sanitary
accommodation provided. Clause 13 of the Conditions of Contract will be rigidly
enforced.
40
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
7. Supply of Water
The Contractor shall make his own arrangements for obtaining, storing,
transporting and pumping of water required for drilling purposes and for use by
the drilling crew at the site.
8. Supply of Electricity
The Contractor shall make his own arrangements for obtaining power for us for
use for the works on site.
9. First Aid Outfits
During the period of erection on Site, the Contractor shall at each place where
work is in progress provide an adequate First Aid Outfit, which shall be easily
accessible at all times, and shall replenish and maintain as use demands, at his
own cost. The provision of these kits shall be considered part of the contractor‟s
obligations and allowed for the rate and price in the schedule of prices.
The first aid kits shall be available for use by the ADS-MK staff as well as the
contractor‟s staff on site.
10. Lighting and Security
Lighting and Security shall be the responsibility of the Contractor
11. Contractor’s Equipment
The contractor shall provide, maintain and remove on completion of works all
temporary installations, equipment and devices necessary for the completion of
the works.
12. Survey Beacons
During the progress of works, the Contractor shall not remove, damage alt er or
destroy in any way whatsoever, any plot or survey beacons. The Contractor shall
notify the ADS-MK Representative of the need to interfere with any beacon.
The ADS-MK Representative shall approve any removal and reinstatement that
he considers necessary. Should any beacon be found to be above or below the
level of the finished work, the Contractor shall immediately report the same to
the ADS-MK representative. Should any beacon be damaged or destroyed by the
Contractor he shall forthwith report the damage to the ADS-MK and the relevant
authorities and shall be held liable for cost of reinstatement thereof.
13. Damage to Lands
Minimum damage shall be done to the land and the reinstatement should be made
to the approval of ADS-MK.
41
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
14. Reinstatement of Roads and Footways
The opening up of roads and footways and reinstatement of the same shall in all
respects be carried out to the approval of ADS-MK.
15. Existing Services and Installations
The Contractor shall take every precaution to ensure that all existing services,
pipes cables, boundary fence, drainage e.t.c within and near the line of
excavation, are located, supported and safeguarded from damage. Any damage
caused to any such facilities attributable to the contractor‟s operations, his
constructional traffic or his negligence shall be made good by the Contractor at
his own expense to the satisfaction of ADS-MK or the responsible authority.
16. Sign Board
The contractor shall provide, sign-write, erect and maintain until the expiry of
the defects liability period sigh boards of sound timber construction and hollow
section steel upright to the dimensions, sign-written and painted in durable
colours, as directed by ADS-MK. Such signboards shall be removed upon expiry
of the defects liability period, and such removals shall be a prerequisite for the
issuance of the defects liability certificate.
The signboards shall each contain no more than 10 m2 of inscribed painted
timber surfaces and have a total height above ground level of not more than 3.8
m. The steel uprights shall be imbedded in class 20 concrete of sufficient
volume to give the whole assembly adequate stability.
17. Provision of facility For Inspection
The Contractor shall provide the necessary tackle, access, equipment, devices,
consumable and labour to enable ADS-MK conveniently to carry out such
inspections as they deem necessary at all times during the period of the
Contract.
42
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
SECTION H: Borehole Technical Specifications
18. Borehole Location
The Contractor shall drill the borehole at the exact location designated by the
ADS-MK. Access to the site shall be the responsibility of ADS-MK. Tracks
required for access of drilling plant, gear, and accessories to the borehole shall
be made by the Contractor and should as little as necessary interfere with
existing fences and farms including those owned by others without their express
permission. Arrangement for access to the site through private land other than
shall be done by the Contractor at his own expense.
19. Environment Protection of the Site
Care must be taken in the handling and storage of drilling fluids, oils greases
and fuel on site, to avoid any environmental degradation. The contractor shall
dispose of any toxic materials, drilling materials and other additives, cuttings and
discharged water in a manner approved by ADS-MK so as not to create damage
to ADS-MK property or any other property in the surrounding area.
The Contractor shall minimize disturbances to the existing facilitie s. This shall
particularly include ensuring that bailed fines and pumped test water are
discharged in a manner that does not create a nuisance either to public, private
or ADS-MK property.
Site reinstatement under the condition of contract shall include the removal of
all hydrocarbons spilled, leaked or otherwise released and associated packaging
and cotton waste. Site reinstatement is deemed as an integral part of
demobilization.
20. Mobilization, demobilization and site restitution
All machinery, equipment and materials to carry out the drilling, test pumping,
headwork‟s construction, etc as specified in BOQ, are to be mobilized to the
site. The drilling rig should be capable of attaining a minimum depth of 200m at
12-inch diameter, by means of direct rotary or air-hammer technique.
Testing pumping equipment should be independent from the drilling rig. At the
start of the Contract, ADS-MK will verify the specifications and state of repair of
all the major items of plant. ADS-MK shall have the right to order the removal
and/replacement of any plant, which in its opinion is insufficient or
unsatisfactory.
21. Borehole Depths and Diameter
The envisaged borehole depth is approximated to range from 150 - 220 m depth,
while the drilling diameter shall be such that it is able to accept a casing of not
less than 8 inch diameter with 2inch gravel pack around the casing. The
contractor shall however drill to the total depth and at such diameter as will be
instructed by ADS-MK.
The borehole will not be acceptable if drilling of such depth and diameter other
than instructed ADS-MK
43
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
22. Drilling Method
The Contractor is obliged to make exclusive use of the rotary drilling or air
hammer technique. Percussion drilling shall not be accepted. The Contractor
shall submit a detailed account of his proposed drilling method, additives etc.
for approval by ADS-MK.
23. Sampling
Representative, continuous samples (min 200 grams) of the strata penetrated
shall be collected for each 2 m intervals and by whatever method is standard for
the drilling techniques in use and approved by ADS-MK. The contractor shall
take every possible precaution to guard against sample contamination. Samples
are not to be washed. The samples shall be put into suitable sample bags,
labeled with the depth interval, and stored in a portion where they will not be
contaminated by site conditions or drilling operations. Geological logging will
be the responsibility of ADS-MK.
24. Temporary casing
Installation and diameter of any temporary casing required for the installation of
the borehole will be left to the Contractor so long as the finished product meets
the specifications. Cost for supply, installations and removal of temporary
casing shall be borne entirely by the Contractor. The Contractor cannot claim for
any casing left in the borehole, which is not retrievable.
25. Borehole Construction
The construction of the borehole shall be made by the Contractor in consultation
with ADS-MK after drilling is completed.
26. Casing and Screens
Aquifer zones shall be completed or partly lined with 8 inch class B mild steel
casings and torch-cut (gas slotted) mild steel screens as decided and approved by
ADS-MK. The screen open area shall not be less than 2% and shall have a
uniform slot size of 1 to 1.5 mm. The casing and screens must be centralized in
the borehole so that a minimum 1” (25mm) annular space exists between the
borehole wall and the casing.
27. Verticality
If required by ADS-MK, the Contractor will conduct a verticality test during
and after drilling by approved methods to demonstrate that the departure from
the vertical does not exceed 3 in 100 between ground level and the base of the
borehole.
44
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
If this departure is exceeded, the Contractor shall make the necessary
corrections to the approval of ADS-MK, without additional payment. If the error
cannot be corrected, then drilling shall cease and a new borehole be drilled at a
position nearby, indicated by ADS-MK. The abandoned borehole shall be
backfilled and/or capped by methods approved by ADS-MK. No payment will
be made for the drilling and the sealing of abandoned borehole, or for moving to
the new site.
28. Gravel pack and Clay Seal
Suitable gravel pack shall be supplied by the Contractor. Prior to delivery,
samples of the gravel pack shall be analysed for grain size and approved by the
ADS-MK. Gravel should consist of washed, well-rounded particles of a uniform
grading. The gravel shall contain not less than ninety (90) % siliceous material
and contain no clay, shales, silt, fines and excessive amount of calcareous
materials or crushed rock. In terms of grain size, ninety (90) % shall conform to
the grading specified and the Contractor shall be required to submit samples of
the material prior to installation for approval by ADS-MK. Sufficient gravel pack
shall be installed to cover completely the uppermost screen, plus an additional
length of not less than 15m (to allow for setting).
The gravel pack should be capped with a bentonite clay seal (minimum thickness
three (3) meters) to prevent contamination. The annual space above this seal can
be back-filled with inert drilling cuttings. The top three (3) meters should be
grouted with cement.
29. Sanitary Seal
To provide an effective seal to the entry of contaminants, the upper meters of
the borehole will be grouted using cement slurry 1.85-2.15 kg/litre. Grout is to
be injected into the annulus between the casing and the walls of the hole, by a
method to be approved by ADS-MK.
30. Yield Estimates during Drilling
When rotary drilling method is used, a ninety (90) degree V-notch flow
measurement device or a drain pipe shall be permanently set up in an approved
manner ad level in the drain line so that continuous monitoring of air lift yield
can be obtained. Average yields shall be read and rated every three (3) meters of
penetration and as otherwise directed by ADS-MK, and recorded in the driller‟s
log. Care should be taken to ensure that no floating debris impede the flow of
water over the V-notch or through the drainpipe. Should air Hammer technique
be used, the contractor shall provide details of how he intends to carry out the
yield estimates to the satisfaction of ADS-MK.
31. Development and Cleaning of Borehole
Development and cleaning of the borehole shall be carried out by the Contractor
upon completion of the drilling and installation of casing.
45
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
This will remove the native silts, clays and drilling fluid residues deposited on the
borehole wall and adjacent portions of the aquifer during the drilling process.
If organic drilling fluids are used, they shall be broken down chemically
according to manufacturer‟s recommendation before or during development of
the borehole. Cleaning shall be carried out by airlift pumping, surging,
backwashing or jetting. Clay desegregation by means of Sodium
Hexametaphosphate („Calgon‟) treatment might be necessary.
The method proposed by the Contractor for development of borehole shall be
submitted to ADS-MK in writing for approval. Development of the borehole
shall be effective from the depth at which water is encountered to the bottom of
the borehole. Development shall continue until water is completely free from fine
particles, as to be decided by ADS-MK. Upon completion of development, any
accumulation of materials shall be removed from the bottom of the borehole by
airlifting.
32. Test Pumping
The Contractor shall perform test pumping to establish well performance and
yield of the borehole. Standard test pumping will consist of a 4-hour step-
drawdown test, followed by a constant discharge test for a period of 24 hours,
which might be extended at the discretion of ADS-MK if the water level has not
stabilized after the 24 hours. The Contractor shall provide a suitable means of
achieving the rate of flows specified.
Before testing, the borehole will be subject to a short term test (calibration) to
establish the approximate yield/drawdown properties and to decide upon pumping
rates for step-drawdown or continuous yield tests. Sufficient time shall be
allowed for the recovery of water level in the borehole between each type of test.
This shall be at the discretion of ADS-MK.
Discharge measurements shall be made by using a flow meter or an otherwise
approved calibrated measuring device. During the test pumping, the discharge
water must be handled and disposed off in an appropriate manner to a point of
overland drainage sufficiently far from the well to prevent recharge. The wat er
shall be diverted over a distance of at least 1 00m from the wellhead.
During all testing operations, once the flow rate has been determined and
preliminary adjustments made, the measured discharge rate shall be maintained
within five (5) % of the required rate for the duration of the test. Persistent
fluctuations beyond this tolerance will require abortion of the test, for which
payment shall not be made.
Any test which is aborted due to the reasons above shall be repeated after
recovery of the water level. No payment shall be made for aborted tests or for
standby time during water level recovery after aborted tests.
46
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
33. Step Drawdown Test
At the discretion of ADS-MK, depending on hydro-geological conditions
encountered, the Contractor will conduct a step drawdown test of not less than
four (4) hour duration. The step drawdown test shall comprise pumping the well
at least four (4) separate discharge rates specified by ADS-MK, each step
lasting for at least one (1) hour.
The change from one pumping rate to the next shall be effected without stopping
the pump by means of a gate valve in the discharge pipe, or by any other means
to be approved by ADS-MK. The change from one step to the next shall take
place in the shortest time possible. During the last step pumping phase, water
discharge measurements shall be taken at appropriate time intervals as
instructed by ADS-MK, while at the same time Electrical Conductivity (EC)
readings are to be taken.
34. Constant Discharge Test
At the discretion of ADS-MK, a constant discharge test for a maximum duration
of 24 hours pumping and 24 hours recovery may be implemented. The discharge
rate at which the well is to be pumped shall be specified prior to the test. During
the test, water levels and discharge measurements shall be made at the same
times intervals as for the step drawdown test. Pumping test data shall be
supplied to ADS-MK from all pumping tests conducted at the borehole. These
will show dates, water levels, discharge rates, electrical conductivity values, time
of starting and stopping the pump, change of discharge, weather, and other
conditions that could affect the test data.
35. Water Level Observations
The Contractor shall supply appropriate water level gauges for measuring water
levels in the borehole to the nearest 10 mm at predetermined intervals. The
minimum length of the dipper shall be 220 meters. Wellhead arrangements shall
permit these gauges to be inserted and passed freely. Hereto the Contractor shall
be required to install a dipping tube, minimum ¾ “ inner diameter, lowered to
approximately 1 meter above the pump. Other meads of measuring water levels
are subject to approval by ADS-MK.
36. Electrical Conductivity (EC) Measurements
The Contractor shall have an operational EC-meter on site to take electrical
conductivity readings whenever required during drilling, development and test
pumping.
37. Records
Daily activity records shall be kept by the Contractor for the borehole. The
records shall contain the information as specified below
47
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
Daily Records
Dates of reporting
Names of foreman and drillers
Method of drilling
Diameter of hole, and depth of changes in diameter
Depth of hole at start and end of shift or working day
Depth and size of casing at start and end of shift or working day
Description of rocks drilled with depths of transitions encountered
Depth at which water is struck (WSL)
Depth at which the water rests (WRL)
Yield of air lifted water, when drilling or developing with air
Time log showing rate of penetration in meters per minute, type of bit, standby
time due to breakdown.
Depth intervals at which each formation samples are taken
Records of components and quantities used or added to the drilling fluid
or air
Water level at the start of each working day
Electrical conductivity measurements
Problems encountered during drilling
Details on installation in the borehole (if any)
Depth and description of well casing
Depth and description of well screens
Details of work to be invoiced at hourly rates (e.g. test pumping)
A copy of the daily drilling record shall be made available daily, including any
other pertinent data as may be requested by ADS-MK.
38. Borehole completion record
As per standard borehole completion form.
Detailed driller‟s log
Copy of standard chemical water quality test
Borehole design and installation details (as-built drawing)
A copy of the Borehole Completion Record Certificate shall be made available
and approved by ADS-MK on completion of the borehole. Three copies of these
Records shall be forwarded to the ADS-MK.
48
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
39. Water Sampling
Water samples for testing the chemical and bacteriological water quality will be
taken at the end of the test pumping. The Contractor shall keep on site a
minimum of twelve (12) suitable one-litre capacity water containers and shall
collect and store water samples as directed by ADS-MK.
40. Capping the Borehole
During borehole construction, installation, development and test pumping, the
Contractor shall use all reasonable measures to prevent entrance of foreign matter
into the borehole. The Contractor shall be responsible for any objectionable
materials that may fall into the borehole and any effect it may have on water
quality or quantity until completion of the works and acceptance by ADS-MK.
41. Acceptance of Borehole
The borehole shall only be accepted by ADS-MK upon satisfactory completion
of all drilling operations, installation of casing and screens, development works,
test pumping and wellhead construction. In the unlikely event of a dry hole, the
employer shall only pay for the works of drilling.
42. Loss of Equipment
Any equipment lost down a borehole must be removed or the borehole will be
considered a lost bore. A replacement borehole will have to be constructed and
test pumped at the Contractor‟s expense.
43. Lost Bore
Should any incident to the plant, behaviour of the ground, jamming of the tools,
or casing, or any other cause prevent the satisfactory completion of the works, a
borehole shall be deemed to be lost and no payment shall be made for that bore or
for attempting to overcome any materials not recovered there-from, nor for any
time spent during drilling or while in problems. If the bore is lost, the Contractor
shall permanently seal the bore at his cost.
In the event of a lost bore, the Contractor shall construct a borehole immediately
adjacent to the lost bore or at a site indicated by ADS-MK. The option of
declaring any bore lost shall rest with the Contractor, subject to the approval of
ADS-MK.
The abandoned hole shall be treated as follows:
(a) The Contractor may salvage as much casing and screen from the initial borehole
as possible and use it, in a new borehole if not damaged, with the approval of
ADS-MK Salvaged material shall remain the property of the Contractor.
(b) The borehole shall be sealed by concrete, cement grout, or neat cement and shall
be placed from the bottom upward by methods that will avoid segregation or
dilution of materials
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
(c) The upper 2 meters of borehole shall be backfilled with native top soil. Scaling
of the abandoned borehole shall be done in such a manner as to avoid accidents
and to prevent it from acting as a vertical conduit for transmitting contaminated
surface or subsurface water into the water bearing formations.
44. Construction of Well Head Cover and Apron
The Contractor shall on completion of the borehole cap the top with a mild steel
blank flange, which shall incorporate a threaded nipple of 19 mm (3/4”)
diameter with cap, welded to the flange, to enable dipping access to the
borehole. The blank flange shall be 400 mm above ground level and be bolted to
a mild steel flange welded to a minimum of 2 m length of mild steel casing
coated internally and externally with non-toxic or bitumen or epoxy coating to
the approval of ADS-MK. This casing shall fit neatly over the borehole casing
and be permanently grouted in at the time of completion of the borehole. Prior to,
during and after the construction of head-works, the Contractor must ensure that
no debris whatsoever falls into the borehole.
45. Well Disinfection
Disinfection of the borehole shall be carried out by the Contractor before
demobilization from the site. This shall be done by placing a chlorine solution
into the well so that a concentration of at least 50 mg/1itre of available chlorine
existing in all parts of the borehole at static conditions. All the borehole surfaces
above the static water level shall be completely flushed with the solution. The
solution shall remain in the borehole for a minimum period of 2 hours before
pumping the borehole to waste.
46. Cleaning and Clearing up of site
The Works shall be handed over in a neat, clean, and aesthetically acceptable
condition to the satisfaction of ADS-MK. All excess materials shall have been
removed from site or handed over to ADS-MK and stored away, as appropriate.
Packaging, trimmings, debris and the like shall have been disposed of; covers,
surfaces etc restored, wiring and cables bunched and put out of normal view
where appropriate and the Works generally handed over in a condition which
would be indicative of reasonable workmanship.
On completion of the borehole the site must be left clean and free from all
debris, hydrocarbons and waster, and all pits filled to the satisfactio n of ADS-
MK. A site not delivered clean may render the borehole unacceptable.
50
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
SECTION I: Bill of Quantities (BOQ)
Preamble to Bills of Quantities
(a) The objective of these Bills of Quantities is to provide sufficient information on the quantities of
Works to be performed to enable tenders to be prepared efficiently and accurately; and
(b) When a Contract has been entered into, to provide a priced Bill of Quantities for use in the
periodic valuation of Works executed.
(c) Tenderers should as much as possible ascertain the correctness of the measurements given by
visiting the site. All the rates or tender sum shall cover for all the costs necessary for the
functional execution and completion of the works.
(d) Tenderers should include in the rates all costs necessary for the execution of the works including
but not limited to Insurance, Security, and Statutory Obligations among others.
(e) Tenderers should familiarize themselves with the conditions relating to working in hazardous
areas, the Safety Permit system, and requirement for adherence to existing Safety Regulations of
ADS-MK.
(f) Payment shall be made periodically for works executed and re-measured. There shall be no
Advance Payments for this contract.
51
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
SECTION J: Standard Forms
List of Standard Forms
i. Form of Tender
ii. Letter of Acceptance
iii. Form of Agreement
iv. Performance Bank Guarantee
v. Tender Questionnaire
vi. Confidential Business Questionnaire
vii. Details of Sub-contractors
viii. Letter of Notification of Award
52
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
FORM OF TENDER
To: ________________________________________________ (Name of Employer): ____________
Date: _____________________ Name of Contractor: ____________________________________
Dear Sir,
1. In Accordance with the Conditions of Contract, Specifications, Drawings and Bills
of Quantities for the execution of the above named Works, we, the undersigned
offer to drill, construct and complete such Works and remedy any defects therein for
the sum of Kshs.(amount in figures/Kenya shillings) _____________________
2. We undertake, if our tender is accepted, to commence the Works as soon as is
reasonably possible after the receipt of the Employer‟s Representative‟s notice to
commence, and to complete the whole of the Works comprised in the Contract
within the time stated in the Appendix to Conditions of Contract.
3. We agree to abide by this tender until(insert date), and it shall remain binding upon
us and may be accepted at any time bore that date.
4. Unless and until a formal Agreement is prepared and executed this tender together
with your written acceptance whereof, shall constitute a binding Contract between
us.
5. We understand that you are not bound to accept the lowest or any tender you may
receive.
Dated this day of __________________ 2015
Signature _________________________ in the capacity of duly authorized to sign
tenders for and on behalf of tenderer.
(Name of Tenderer) ___________________________________________________
(Postal Address of Tenderer) _____________________________________________
Witness: Name ________________________________________________________
Postal Address ________________________________________________________
Signature ___________________________ Date ____________________________
53
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
LETTER OF ACCEPTANCE
(DATE) _________________________________
To: ___________________________________________ (Name of the Contractor)
Postal Address of the Contractor __________________________________________
Dear Sir,
This is to notify you that your Tender dated __________________________________________
for the execution of TENDER NUMBER ………………. FOR DRILLING AND
CONSTRUCTION OF ONE BOREHOLEAT NKARUSA, KAJIADO WEST SUB-
COUNTY for
the Contract price of Kshs.-------------------------------------------- (amount in figures/Kenya
shillings)----------------------------------------------------------- (amount in words) in accordance
with the Instruction of Tenderers is hereby accepted.
You are hereby instructed to proceed with the execution of the said Works in accordance
with the Contract documents.
Authorized signature ……………………………………………………………………………
Name and Title of Signatory …………………………………………………………………...
Attachment: Agreement
54
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West District
FORM OF AGREEMENT
This agreement, made the ______ day of ________________2015 between
ANGLICAN DEVELOPMENT SERVICES-MT.KENYA whose registered office is situated
at Bishop Chipman House, Nyeri (hereinafter called “the employer”) of the one part AND
(hereinafter called “the Contractor”) of the other part.
Whereas ADS-MK is desirous that the Contactor executes:
TENDER NUMBER …………….. FOR DRILLING AND CONSTRUCTION OF ONE
BOREHOLEAT NKARUSA, KAJIADO WEST SUB- COUNTY
(hereinafter called “the works”) located at Nkarusa Village, Oloirien Location, Kajiado West
Sub- County and the Employer has accepted the tender submitted by the Contractor for the
execution and completion of such Works and the remedying of any defects therein for the
Contract price of Kshs. (Amount in figures)__________________ , Kenya shillings ( amount in
words)
-----------------------------------------------------------------------------------------------
NOW THIS AGREEMENT WITNESSETH as follows:
1. In this Agreement, works and expressions shall have the same meanings as are
respectively assigned to them in the Conditions of Contract hereinafter referred to.
2. The following documents shall be deemed to form and shall be read and construed as
part of this Agreement i.e.
(i) Letter of Acceptance
(ii) Form of Tender
(iii) Conditions of Contract
(iv) Appendix to Conditions of Contract
(v) Specifications
(vi) Drawings
(vii) Priced Bill of Quantities
55
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
3. In consideration of the payments to be made by the Employer to the Contractor as
hereinafter mentioned, the Contractor hereby covenants with the Employer to
execute and complete the Works and remedy any defects therein in conformity in all
respects with the provisions of the Contract.
4. The Employer hereby covenants to pay the Contractor in consideration the
execution and completion of the Works and remedying of defects therein, the
Contract Price or such other sum as may become payable under the provisions of the
Contract at the times and in manner prescribed by the Contract.
In witness whereof the parties thereto have caused this Agreement to be executed the day and
year first before written.
The common Seal of ________________________________________________________________
Was hereunto affixed in the presence of _______________________________________________
Signed Sealed, and Delivered by the said ______________________________________________
Binding Signature of Employer _______________________________________________________
Binding Signature of Contractor ______________________________________________________
In the presence of (i) Name_______________________________________________
Address_____________________________________________
Signature____________________________________________
(ii) Name _______________________________________________
Address_____________________________________________
Signature____________________________________________
56
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
FORM OF TENDER SECURITY
WHEREAS ………………………………………………. (hereinafter called “the Tenderer) has
submitted his tender dated …………….for the construction of…………………………………
……………………………………………………………………. (name of Contract)
KNOW ALL PEOPLE by these presents that WE ……………………having our registered office
at ………… (hereinafter called „the Bank”), are bound unto …………… ….. hereinafter called
“the Employer”) in the sum of Kshs ……….………….. for which [payment we; and truly to be
made to the presents sealed with the Common Seal of the said Bank this Day …….. of
………… 2015
THE CONDITIONS of this obligation are:
1. If after tender opening the tenderer withdraws his tender during the period of tender
validity specified in the specified in the instructions to tenderers.
2. If the tenderer, having been notified of the acceptance of his tender by the Employer
during the period of tender validity:
(a) fails or refuses to execute the form of agreement in accordance with the
Instructions to Tenderers, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance wit h the
Instructions to Tenderers;
We undertake to pay to the Employer up to the above amount upon receipt of his first written
demand, without the Employer having to substantiate his demand, provided that in his demand
the Employer will note that the amount claimed by him is due to him, owing to the occurrence of
one or both of the two conditions, specifying the occurred condition or conditions.
This guarantee will remain in force up to including thirty (30) days after the period of tender
validity, and any demand in respect thereof should reach the Bank not later than the said date.
[Date]……………………………………
[Witness]………………………………………………………….
[Signature of the Bank]…………………………………………………….
[Seal]
57
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub
County
PERFORMANCE BANK GUARANTEE
To: ________________________________________________________ (Name of Employer)
(Date) _______________________________________
------------------------------- (Postal Address of Employer)
Dear Sir,
WHEREAS __________________ ____ (hereinafter called “the Contractor”) has undertaken, in
pursuance of Contract No.-------------------------dated------------to execute---------------------------
-------------------------------------------------------------------------------- (hereinafter called “the Works”);
AND WHEREAS we have agreed to give the Contractor such a Bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you,
onbehalf of the Contractor, up to a total Kshs--------------------------------amount of Guarantee
infigure) Kenya shillings------------------------------------------------------(amount of guarantee in
words), and we undertake to pay you, upon your first written demand and without your needing to
prove or to show grounds or reasons for your demand for the sum specified therein.We hereby
waive the necessity of your demanding the said debt from the Contractor before presenting us
with the demand.
We further agree that no change, addition or other modification of the terms of the Contract or of
the Works to be performed thereunder or of any of the Contract documents which may be made
between you and the Contractor shall in any way release us from any liability under this
Guarantee, and we hereby waive notice of any change, addition, or modification.
This guarantee shall be valid until the date of issue of the Certificate of Completion.
SIGNATURE AND SEAL OF THE GUARANTOR-----------------------------------------------------
Name of Bank---------------------------------------------------------------------------------
Postal Address-------------------------------------------- Date-----------------------------
58
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
TENDER QUESTIONNAIRE
Please fill in block letters
1. Full name of tenderer:
…………………………………………………………………………………...
2. Full address of tenderer to which tender correspondence is to be sent (unless an Agent
has been appointed below);
…………………………………………………………………………………………
3. Telephone number (s) of tenderer
………………………………………………………………………………………….
4. Telex of tenderer
………………………………………………………………………………………..
5. Name of tender‟s representative to be contacted on matters of the tender during the
tender period:
…………………………………………………………………………………………….
6. Details of tender‟s nominated agent (if any) to receive tender not ices. This is
essential if the tenderer does not have his registered address in Kenya (name, address,
telephone, and telex)]
………………………………………………………………………………………….……
…………………………………………………………………………………………………
Make copy and deliver to: ANGLICAN DEVELOPMENT SERVICES-MT.KENYA
59
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
CONFIDENTIAL BUSINESS QUESTIONNAIRE
You are requested to give the particulars indicated in Part 1 and either Part 2 (a), 2 (b) or whichever
applies to your type of business.
You are advised that it is a serious offence to give false information on this Form.
Part 1 – General Business Name …………………………………………………………….
Location of business premises; Country/Town …………………………………………..
Plot No. …………………………………… Street/Road ………………………………….
Postal Address ……………………………. Tel, No. …………………………………….
Nature of Business …………………………………………………………………………..
Current Trade Licencee No. …………………….. Expiring date ………………………
Maximum value of business which you can handle at any time Ksh in figures
…………………. …………………………………………………………………..
Name of your bankers ……………………………………………………………………….
Branch …………………………………………………………………………………………
Part 2 (a) – Sole Proprietor
Your name in full ………………………………………………………. Age ………………. Nationality
…………………………………………… Country of Origin ……………………………………………
Citizenship details …………………………………………………………………………………………
Part 2 (b) – Partnership
Give details of partners as follows:
Name in Full Nationality Citizenship Details Shares
1) ……………………………………………………………………………………………
2) ……………………………………………………………………………………………
3) ……………………………………………………………………………………………
4) …………………………………………………………………………………………...
60
Drilling and Construction of water a borehole at Nkarusa, Oloirien, Kajiado West Sub County
DETAILS OF SUB-CONTRACTORS
If the Tender wishes to sublet any portions of the Works under any heading, he must give
below details of the sub-contractors he intends to employ for each portion.
Failure to comply with this requirement may invalidate the tender.
1. Portion of Works to be sublet …………………………………………………….
i. Full name of Sub-contractor …………………………………………………….
And address of head office ………………………………………………… ...
ii. Sub-contractor‟s experience of similar works carried out in the last 3 years
with Contract value;
………………………………………………………………………………………
………………………………………………………………………………………
………………………………………………………………………………………
Portion of Works to sublet:
(i) Full name of sub-contractor ................................................................
And address of head office ................................................................
(ii) Sub-contractor‟s experience of similar works carried out in the last 3 years
with contract value;
……………………………………………………………………………………
……………………………………………………………………………………
…………………………………………………………………………………….
.
[Signature of Tenderer] [Date]
61
Drilling and Construction of water boreholes at Nkarusa, Oloirien, Kajiado West Sub County.
LETTER OF NOTIFICATION OF AWARD
ANGLICAN DEVELOPMENT SERVICES-MT. KENYA
TO: ________________________________
RE: _________________________________________________________________
Tender No: ___________________________________________________________
Tender Name: _________________________________________________________
This is to notify that the contract/s stated below under the above -mentioned tender
have been awarded to you. Please acknowledge receipt of this letter of notification
signifying your acceptance. The contract/contracts shall be signed by the parties
within 30 days of the date of this letter but not earlier than 14 days from the date of
the letter.
You may contact the officer(s) whose particulars appear below on the subject matter
of this letter of notification of award.
[PARTICULARS]
62
Drilling and Construction of water boreholes at Nkarusa, Oloirien, Kajiado West Sub
county.
Appendix A: Location of proposed area for drilling borehole