Techno Economic Assessment

Embed Size (px)

Citation preview

  • 7/28/2019 Techno Economic Assessment

    1/18

    Life Impact | The University of Adelaide

    Delivering innovative technologiesfor a clean energy future

    Centre for Energy Technology

    Techno-economic assessment of novel

    engineering systems for stranded geothermalenergy resources.Ashok A. KaniyalProf. Graham Gus J. Nathan

    Prof. Jonathan J. Pincus

    School of Mechanical Engineering

    Ricoh Clean Energy Scholarship

  • 7/28/2019 Techno Economic Assessment

    2/18

    Life Impact | The University of AdelaideSlide 1

    Centre for Energy Technology

    Australias Energy Network

    Electricity transmission

    network

    Geothermal

    resources in

    Cooper Basin

    Oil and Natural Gas Pipeline

    network (Geoscience Australia, 2009)

    Geothermal

    resources in

    Cooper Basin

  • 7/28/2019 Techno Economic Assessment

    3/18

    Life Impact | The University of AdelaideSlide 2

    Centre for Energy Technology

    The Geothermal-Data Centre Concept

    Geothermal data fibre link Capital: $60 m + $15 m (Op ex).

    DBCDE, 2010.

    Geothermal-data fibre link

    Proposed NBN Co Fibre

    optic linksFibre optic node

    Geothermal-data

    fibre link~ $60m

    National Broadband

    Network (NBN)(NBN Co., 2010)

  • 7/28/2019 Techno Economic Assessment

    4/18

    Life Impact | The University of AdelaideSlide 3

    Centre for Energy Technology

    Presentation outline

    Gap in literature;

    Techno-economic analysis framework;

    Analysis of Geothermal-data centre concept early results;

    Future work;

    Conclusions.

  • 7/28/2019 Techno Economic Assessment

    5/18

    Life Impact | The University of AdelaideSlide 4

    Centre for Energy Technology

    Gap in literature

    Economic assessment of geothermal direct heat and EGS CHPapplications.

    Address limitations of other novel geothermal engineering systems, Dickinson et al. (2010) and Atrens et al. (2009).

    Geothermal-data centre micro-grid follows complementary networkinfrastructure investment. c.f. Siddiqui and Maribu (2009), Fleten (2007).

    Application of dynamic capital investment decision methods, Not considered in this context.

  • 7/28/2019 Techno Economic Assessment

    6/18

    Life Impact | The University of AdelaideSlide 5

    Centre for Energy Technology

    Aims

    Technical feasibility of direct heat and CHP enhanced geothermal system

    applications,

    Economic viability of fibre optic network and geothermal plant under data

    centre client servicing scenarios: Net present value - Deterministic static analysis,

    NPV approach + dynamic demand and geothermal plant cost

    uncertainty.

    Social welfare analysis a case for public involvement in project.

    Application of techno-economic framework to other eng systems.

  • 7/28/2019 Techno Economic Assessment

    7/18

    Life Impact | The University of AdelaideSlide 6

    Centre for Energy Technology

    Framework for techno-economic analysis

    1. Develop a concept for an engineering system.

    2. Steady state thermodynamic analysis of plant concept.

    3. Static NPVanalysis of investment.

    4. Dynamic analysis of investment in geothermal andnetwork resource faculties.

    5. Social benefit analysis of investment in plant and networkresource.

    Increasingd

    etail

  • 7/28/2019 Techno Economic Assessment

    8/18

    Life Impact | The University of AdelaideSlide 7

    Centre for Energy Technology

    Standardised data centre unit

    Modular data centre of total capacity 350 kWe (Barroso, 2007):

    IT load = 270 kWe

    Cooling load = 200 kWr

    Cooling load

    ~200 kWrData Centre Co. NBN

    market

    Geothermal-data

    fibre link

    (1000-1500 km)

    hv

    IT electrical load

    ~270 kWe

  • 7/28/2019 Techno Economic Assessment

    9/18

    Life Impact | The University of AdelaideSlide 8

    Centre for Energy Technology

    EGS CHP Organic Rankine cycle

    steady state analysis

    2s3

    2

    Temperature[K]

    Entropy (s)

    [kJ/kg-K]

    6 1

    5s5

    4

    Geothermal water:

    Tin = 508 K, TH = 490 K, T = 5 K,

    = 50 kg/s.

    Wnet = 1.2 MWe

    Injection

    well

    Production

    well

    Feed pump

    EvaporatorPre-heater

    Geo-fluid:

    water

    Radialturbine

    Generator

    Ext. heat exchanger

    Absorption cycle:

    generatorRefrigeration

    load

    Geo-fluid

    NH3-H20

    5

    3 2

    1

    6

    4

    68%

    (Tc = 562 K, Tin = 375 K, TH = 320 K)

    Absorption refrigeration

    cycle (not shown)

    DiPippo (2005)

    Heberle and Bruggemann (2010)

    Liu , Chien and Wang (2004)

    490

    320

  • 7/28/2019 Techno Economic Assessment

    10/18

    Life Impact | The University of AdelaideSlide 9

    Centre for Energy Technology

    Energy consumption pattern

    Geothermal

    Local CHP 14x Modulardata centres NBNmarket

    Geothermal-data fibre link

    (1500 km)

    hv

    Absorption chiller

    cooling

    Direct heat

    cooling

    Organic Rankine Cycle

    1.2 MWe

    Total IT electrical Load

    3.75 MWe

    3.6 MWth (input) > 2.8MWr (average required output)

    Absorption chiller plant: COP = 1.0

    Natural gas electricity

    generation 2.55 MWe

    Broad X Absorption Chiller Design Manual (2008)

  • 7/28/2019 Techno Economic Assessment

    11/18

    Life Impact | The University of AdelaideSlide 10

    Centre for Energy Technology

    EGS wells and ORC plant costing

    Cost component A$ M

    First injection + production well pair $30.5 M

    ORC plant

    + natural gas storage tank + construction + contingency.

    $3.82 M

    Additional production wells $10.2 M

    Ulrich (1984)

    Vasudevan and Agrawal (2000)

  • 7/28/2019 Techno Economic Assessment

    12/18

    Life Impact | The University of AdelaideSlide 11

    Centre for Energy Technology

    ORC plant economies of scale

    4 PU $10.93 m

    4 x 1 plant unit (PU)$15.87 m

    2 PU x 2 = $11.69m

    3 PU + 1 PU =$12.51m

    $-

    $2

    $4

    $6

    $8

    $10

    $12

    $14

    $16

    $18

    0 1 2 3 4 5

    Cos

    tofplantandinstallation(A$M)

    Geothermal ORC plant units (corresp. no. of production wells)

    Grass roots capital (Full Plant) ($AUD)

    Plant size incrementation cost comparison(4 plant units)

  • 7/28/2019 Techno Economic Assessment

    13/18

    Life Impact | The University of AdelaideSlide 12

    Centre for Energy Technology

    Local CHP Net Present Value scenarios

    NPV scenario iteration Description

    Mk 1 - Increasing rate of data centre commitment,

    - Early investment = no construction lag.

    Mk 2

    - Increasing rate of data centre commitment,- Economies of scale investment in plant.

    Rt= Annual revenue received per data centre,

    Ct=

    Capital and ongoing operating expenditure.i= Cost of capital = 6%

  • 7/28/2019 Techno Economic Assessment

    14/18

    Life Impact | The University of AdelaideSlide 13

    Centre for Energy Technology

    Local CHP Net Present Value scenarios

    -25%

    -20%

    -15%

    -10%

    -5%

    0%

    5%

    10%

    15%

    -$160

    -$140

    -$120

    -$100

    -$80

    -$60

    -$40

    -$20

    $-0 1 2 3 4 5

    N

    PV/Totalexpen

    diture

    NPVan

    dTotalexpendi

    ture(A$M)

    Number of capacity increments (production wells + ORC plant)

    Total expenditure Mk 2 Total expenditure Mk 3

    NPV/Total expenditure Mk 2 NPV/Total expenditure Mk 3

    1

    1 2

    2

  • 7/28/2019 Techno Economic Assessment

    15/18

    Life Impact | The University of AdelaideSlide 14

    Centre for Energy Technology

    Fibre optic network investment

    -$80

    -$60

    -$40

    -$20

    $-

    $20

    $40

    $60

    $80

    $100

    0 5 10 15 20 25 30 35 40 45

    Cumulativ

    enetpresentvalue(A$M)

    Years

    Cumulative NPV of investment in Geothermal-Data Fibre link

    28% subscription

    40% subscription

    50% subscription

    60% subscription

    Barroso (2007)

  • 7/28/2019 Techno Economic Assessment

    16/18

    Life Impact | The University of AdelaideSlide 15

    Centre for Energy Technology

    Dynamic investment decision

    Real options approach.

    An optimal path for capacity investments given uncertain:

    Data centre demand for remote co-location and competition b/w sites,

    Method: Aguerrevere (2003);

    Influence of learning on cost of establishing geothermal wells and plant,

    Method: Bolton and Faure-Grimaud (2009).

    Social welfare analysis under uncertain demand

    public subsidy? Method: Danau (2010).

  • 7/28/2019 Techno Economic Assessment

    17/18

    Life Impact | The University of AdelaideSlide 16

    Centre for Energy Technology

    Future work

    Another application: Wind CHP a techno-economicanalysis?

    H2-fuel cells CHP for NEM feed-in and adsorptiondesalination.

    Common use plant c.f. fibre optic networkinvestment.

  • 7/28/2019 Techno Economic Assessment

    18/18

    Life Impact | The University of AdelaideSlide 17

    Centre for Energy Technology

    Conclusions

    Enhanced geothermal system CHP applicationtechnically feasible.

    Geothermal-data centre concept is economicallyviable.

    Techno-economic framework applicable to otherunique engineering systems and geographies.