Upload
yovinianus
View
236
Download
3
Tags:
Embed Size (px)
Citation preview
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
TAYAN BRIDGE CONSTRUCTION PROJECT
Technical Proposal for Steel Casing
CRBC – WIKA JO.
1
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Teble of Content
1 General...........................................................................................................................................12 Construction Introduction..............................................................................................................2
2.1 The main method for construction......................................................................................22.2 Flow chat for construction..................................................................................................3
3 Construction Method of Steel Casing............................................................................................43.1 The reinforcement design of steel casing............................................................................43.2 Steel Casing Fabrication and Delivery................................................................................43.3 Pilling sequence and coordinate of pile layout....................................................................53.4 Piling...................................................................................................................................6
4 Equipment, Manpower and Schedule of Driving Steel Casing....................................................204.1 Equipment.........................................................................................................................204.2 Manpower.........................................................................................................................204.3 Construction schedule.......................................................................................................21
5 Quality Assurance........................................................................................................................226 Safety Assurance..........................................................................................................................227 SOP and Check Form...................................................................................................................23
7.1 Sop of steel casing driving................................................................................................237.2 Quality checking form......................................................................................................24
8. Attachment..................................................................................................................................278.1 Coordinate of steel casing.................................................................................................27
2
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Construction Method of Driving Steel Casing
1 General
This document describes the construction procedure of driving steel casing in
the Tayan Bridge Construction project.The steel casing will be drived in two area.
The first location is bridge 1 with total 27 pieces of steel casings.And the second
location is bridge 2 with total 163 pieces of steel casings, which include36 pieces of
steel casings for fender. The diameter of 64 pieces of steel casing in main bridge is
170cm. Diameter of others are 120 cm. The thickness of all steel casings is 10mm.
40,075m40,075m40,075m40,067m 40,075m 40,075m 40,067m
STA: 0+164.486ELEV: 35.179
STA: 0+204.553ELEV: 36.382
STA: 0+244.628ELEV: 37.184
STA: 0+284.703ELEV: 37.585
STA: 0+324.778ELEV: 37.585
STA: 0+364.851ELEV: 37.184
STA: 0+404.928ELEV: 36.382
STA: 0+444.995ELEV: 35.180
OVERALL LENGTH OF BRIDGE = 280,509m
ABT.1 P.1 P.2 P.3 P.4 P.5 P.6 ABT.2
Fig. 1-1 Long Section of Bridge 1
Fig. 1-2. Long Section of Bridge 2—North Approach Bridge
Fig. 1-3.Long Section of Bridge 2—Main Bridge and South Approach Bridge
1
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
In the specification, the material of steel casing isspecified as ASTM A252
Grade 2 with Yield Stress (f y ) 246MPa and ultimate Stress 422MPa. The structural
detailed data for steel casing are shown in following Table 1-1:
Table 1-1. Steel Casing Data
Pier NO.
Diamete
r
(mm)
Wall Thickness
(mm)
Length
(m)Quantity
Total Length
(m)
Bottom
Elevation(m)
P3 1200 10 17.5 9 157.5 +13.25
P4 1200 10 23.5 9 211.5 +7.25
P5 1200 10 20.5 9 184.5 +10.25
P7 1200 10 9.5 9 85.5 +21.25
P8 1200 10 15.5 9 139.5 +15.25
P9 1200 10 15.5 9 139.5 +15.25
P10 1200 10 15.5 9 139.5 +15.25
P11 1200 10 15.5 9 139.5 +15.25
P12 1200 10 16.5 9 148.5 +14.25
P13 1200 10 16.5 9 148.5 +14.25
P14 1200 10 16.5 9 148.5 +14.25
P15 1200 10 16.5 9 148.5 +14.25
P16 1700 10 15.5 12 186 +15.25
P17 1700 10 20.5 20 410 +10.25
P18 1700 10 18.5 20 370 +12.25
P19 1200 10 18.5 12 222 +12.25
2 Construction Introduction
2.1 The main method for construction
Every piece of steel casing will be fabricated in the factory as a whole part Spiral
Pipe. So there is no welding connection in the job site. After checked in the factory,
all the steel casings are delivered to the Tayan storage yard by barge.
In the job site, the steel casing will be drived down to designed position and
elevation by using a 80t barge crane with vibrating hammer. The crane is used to erect
the steel casing and lift the vibrating hammer. Vibrating hammer is used to drive the
steel casing. One guide frame will be used to ensure the verticality comply with
2
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
specified allowable tolerance that is not more than 2%.
2.2 Flow chat for construction
3
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
4
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
3 Construction Method of Steel Casing
3.1 The reinforcement design of steel casing
In order to avoid deformation, stiffening rings were welded around the steel
casing. On the top and bottom ends, a 0.5m long stiffening ring is added for dia.
1200mm steel casing, and 0.8m long stiffening ring is added for dia. 1700mm steel
casing. Some 100mm long stiffening rings are added in middle of steel casing, the
detailed design drawing is shown as the attachment document: Shop Drawing of
Steel Casing.
3.2 Steel Casing Fabrication and Delivery
Steel casing will be fabricated in the factory in Jakarta. All steel casing is rolled
and welded by automatic steel pipe rolling machine. A very good guarantee can be
obtained for the quality of steel casing. Every piece of steel casing is processed as a
whole part spiral pipe. It means there will be no welding connection job in the
construction site.
Fig. 3.2-1 Steel Casing Fabrication
After the quality and the quantity of steel casing is checked to complying with
the specification request, the product can be delivered. The steel casing is transport to
port by long truck firstly, and then delivered form Jakarta Port to Tayan inland
5
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
temporary jetty by barge. In steel casing stack progress, the focus is to prevent
deformation. For diameter 1200mm steel casing, the maximum stack layer is 3 layer;
for diameter 1700mm steel casing, it is only allowed in 2 layer. Measures to prevent
rolling during sea shipping, should be adopted. The demand for stack in the Tayan
storage yard is accordance to the standart handling steel casing material.
Fig. 3.2-2 Lay Out Stock Yard OfSteel Casing
3.3 Pilling sequence and coordinate of pile layout
The steel casing installation procedure for every kinds of pier in bridge 1 and 2 is
shown as following:
Fig. 3.3-1Steel Casing Pilling Sequence of Bridge 1
6
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig. 3.3-2 Steel Casing Pilling Sequence of Bridge 2
The coordinate of steel casing will be submited to the Engineer to check as
another special document. Any steel casing is not allowed to drived before the
coordinate data is approved by Engineer.
3.4 Piling
3.4.1 Construction Method Of Driving Steel Casing In Bridge1
1 Driving Steel Casing of Bridge 1
The detail of driving steel casing procedure in bridge 1 is explained as follow :
a. Carry the steel casing to the middle of the river by barge
Fig. 3.4.1-1 Driving Steel Casing
b. Inserting steel casing to the guide frame using crane, check the verticality and
ensure the steel casing already in fixed position.
7
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig. 3.4.1-2 Lifting Steel Casing
c. Put down slowly steel casing until river bed level, check steel casing position
and verticality, make sure the steel casing position not change or displace
extremely because of water stream.
Fig. 3.4.1-3 Placing Steel Casing
d. Drive the steel casing using vibrating hammer. Monitor the driving steel
casing during work to ensure steel casing condition is fullfill the
specification requirement. During the driving execution, the surveyor must
check/survey the position and verticality of steel casing. Then check the top
elevation of steel casing (+30,5 m)
8
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig. 3.4.1-4 Driving Steel Casing
e. After the steel casing driven properly, then install bracing (steel profile) to
make steel casing work together and stable.
Installing bracing (using steel trust) to strengthening the steel casing each other
into 1 group. The bracing also can be use as base of drilling and formwork platform.
The bracing elevation location must accomply the design drawing.
Fig. 3.4.1-5 Temporary bracing between steel casing pile
2 Survey and Coordinate Control of Bridge 1
Two total stations will be used to suvery the steel casing at the same time. Every
steel casing will be checked and seted out by two total stations. The location of total
station should be choosed in the river bank to survey different pier’s steel casing.
The two surveying sight should be an angle of less than 180 degrees.
Survey the guidence frame and the sign that have been painted in steel casing.
9
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
check and control the position firstly, adjust the barge position in according with the
calculated deviation until complying with the allowable tolerance that is not more
than 7,5 cm. Fix the location by 4 anchors and keep the stability of the barge in the
help of tug boat.
SURVEYOR WITHTOTAL STATION
SURVEYOR WITHTOTAL STATION
0250
0300
0350
0400
P.6P.5P.4P.3P.2
1200
1200351 497 351
497
1500
6500
1500
351 497 351
497
1200
900
5300
900
1200
1200351 497 351
497
1500
6500
1500
351 497 351
497
1200
900
5300
900
Fig.3.4.2-5 total station location for pilling
3.4.2 Construction Method of Driving Steel Casing in Bridge2
⑴Move and anchor the barge crane
For the barge crane, there are 4 pieces of anchor windlass installed in 4 corner
of barge. Every anchor windlass has 100m wire rope at least, and 1 heavy steel anchor
is fixed on the other end of wire rope. The anchor offer anchor force to the barge
crane, the windlass can adjust the position of barge crane without the tug boat, by
pulling and release the wire rope.
In the beginning of every pier, one tug boat move barge crane to the piling
location of first row of steel casing. The other tug boat takes the anchor to the anchor
position and drops it into the river. After 4 pieces of anchor are drop to the designed
point, the 4 windlass pull the wire rope to make all the wire rope is in force state. Now
the barge can be fixed in position by 4 anchors.
10
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-1: Barge anchoring
⑵Install guide frame
In order to ensure the accuracy for coordinate and verticality of steel casing,
aguide frame will be adopted. The inner diameter of guide frame is 3 cm larger than
the outer diameter of steel casing, and the height of guide frame is 3.2 m. Guide frame
structure is designed as follow:
11
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-2.Guiding Frame
Before vibrating the permanent steel casing, in order to offer a stable fixed
platform for installing the guiding frame, a small temporary platform will be
established firstly.This temporary guide frame platform is composed of 4 steel pipes
and 2 main beams as following drawing.
Fig. 3.4.2-3 The design of guiding frame platform
The guide frame will be installed on it. If the guiding frame is checked in correct
coordinate and vertical direction, the guide frame can limit the steel casing in fixed
12
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
point and lead the steel casing to slide along vertical direction.
Fig. 3.4.2-4 Vibrate steel casing by guiding frame platform
After the first row of steel casings completed, demolish the temporary guide
frame platform and establish the corresponding drilling platform on the first row of
steel casing. Then the guide frame will be installed in cantilever method on the top of
drilling platform to vibrate steel casing. Furthermore all the other steel casings will be
vibrated in this method.
Fig.3.4.2-5 vibrate steel casing by cantilever method
⑶ Survey and Coordinate Control of Bridge 2
13
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Two total stations will be used to suvery the steel casing at the same time. Every
steel casing will be setting out by two total stations.The total station lacation should
be choosed in the river bank to survey different pier’s steel casing. The two
surveying sight should be an angle of approximately 90 degrees.
Survey the guide frame control position firstly, adjust the barge position in
according with the calculated deviation until complying with the allowable tolerance
that is not more than 7,5 cm. Fix the location by 4 anchors and keep the stability of
the barge in the help of tug boat.
Fig.3.4.2-5 total station location for pilling
⑷ Erect steel casing
The lengthiest of steel casing is 21.5m, it will be erected by barge crane and put
into guiding frame.
The steel casing is slided in the guide frame slowly until the bottom begin to
insert the riverbed. Move the crane boom to adjusted the steel casing verticality until
the surveyor confirm the verticality is correct, and then continue to sink the steel
casing into the riverbed untill stop. Check the verticality again, if no problem, loose
the lifting wire rope and continre to next procedure, or lifte up the steel casing out of
the river bed again to adjust the viticalrity.
14
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-6 place the steel casing into the guiding frame
⑸Vibrat steel casing
Keep the stability of barge, after the coordinate and verticality is checked. The
crane lifte the vibrating hammer moving to the top of steel casing slowly, which
stands in the riverbed. Insert hammer clamp into the steel casing and fix the
hydraulic clamp firmly. Any impact and force should be avoided applied to steel pipe
to influnce the viticality. Afterward the crane lower down the hammer slowly, to give
hammper’s death weigth to the top of steel casing, making the steel casing sinking
down slowing. During the procedure, the crane boom should adjust and keep the
viticality continously until the steel casing stoping sinking again. If the steel casing
become inclined out of allowable tolerance, the steel casing should be lifted up of
riverbed to sink again.
15
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-7 vibrate the steel casing in guiding frame (1)
Turn on the generator to provide the power to the vibrating hammer. Switch on
the vibrating hammper only two second, check the verticality after every stop and
then continue to switch on in very short time again.
Fig.3.4.2-8 vibrate steel casing in guiding frame (2)
When it is obvious that the steel casing is vibrated into the riverbed deep enough
to keep the verticality without change, remove the guiding frame and then switch on
the hammper with full power continuously until the steel casing can not be vibrated
16
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
down anymore or stop in the design elevation.
Fig.3.4.2-9 vibrate steel casing without guiding frame
After one steel casing was finished, the surveyor check the coordinate and
elevation, if it is low than the allowable tolerance, move the barge and continue to
vibrate the next steel casing.
Fig.3.4.2-10 The installed steel casing of one pier
17
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
⑹ weld the bracing
After every steel casing is vibracted, weld the bracing immediately, in order to
form as a whole. The section steel or steel pipe will be used as the bracing. Any job
will not be allowed before bracing welded. The bracing should be weld as follow.
18
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-11 Bracing of Pier 17and Pier 18 (the dimension is in cm)
19
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
20
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-12 Bracing of Pier 16and Pier 19 (the dimension is in cm
21
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
22
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
Fig.3.4.2-13 Bracing of Pier 7~Pier 15 (the dimension is in cm)
4 Equipment, Manpower and Schedule of Driving Steel Casing
4.1 Equipment
Table 4.1-1 The List of Driving Steel Equipment Casing Of Bridge 1
No.
Description Type Capacity QuantityUni
t1 Tug Boat 600 HP 1 set2 Piling Barge 180ft 1 set3 Crawler crane 80T 1 set
4Vibration pile
Hammer1 set
5 Welding set 2 set6 Generator set 1 set
7Survey
equipmentTopcon 2 set
8 Lifting wire Φ20mmas
requiredTable 4.1-2 The List of Equipment Of Driving Steel Casing Of Bridge 2
No.
Description Type Capacity QuantityUni
t
1 Tug BoatTB.TAMBORA
/Indonesia600HP
(14.88×5.05×1.94)1 set
2 Flat Top
BargeBG.BB-023/
Indonesia
1500T(43.91×15.22×3.0
2)1 set
3 Crawler crane QUY80A 80T/209kw 1 set
4Vibration pile
Hammer- 5.8T/90kw 1 set
5 Generator SWT SC330S 343kw 2 set6 Total Station - 2 set
7 Lifting wire Φ20mm -as
required
4.2 Manpower
Table 4.2-1 Manpower Schedule Of Driving Steel Casing Of Bridge 1
No. Type of work Quantity Remark1 Sailor 62 Piling team 10
23
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
3 Driver of crawler crane 14 Electrician 15 Site engineer 16 Safety engineer 17 Survey engineer 2
Total 22
Table 4.2-2 Manpower Schedule Of Driving Steel Casing Of Bridge 2
No. Type of work Quantity Remark1 Sailor 62 Piling team 103 Driver of crawler crane 14 Electrician 15 Site engineer 16 Safety engineer 17 Survey engineer 2
Total 22
4.3 Construction schedule
Table 4.3-1 The construction schedule of driving steel casing of bridge 1
Table 4.3-2 The construction schedule of driving steel casing of bridge 2
24
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 412345
Driving Steel Casing Pier 4Driving Steel Casing Pier 3
Fabrication
NO WORK December January
Driving Steel Casing Pier 5
February March AprilDURATION
Furnish and Shipping
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
5 Quality Assurance
① It need check the guiding frame and equipment, make sure they are in good
condition.
② When steel casing was driving, the surveyer need check the position and
verticality as soon as possible.
③ When the position and vertical is adjust to the design value , the steel casing
will down slowly by crawler crane. When the bottom was on the river bed, the steel
casing is sinking by itself weight, and then the steel casing have enough
stability,move the guiding frame, and then continue to driving by hammer. When it
is driving, make sure the hammer and axis of steel casing on same vertical line.
6 Safety Assurance
① It need check the equipment before start to hoist, and make sure they are in
good condition.
25
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
② The crawler crane need put down the boom onto the brackets when it is
moving; the driver need cooperate with the director, and the director should have
correct directing posture .
③ Before hoisting, the lifting eyes should be checked, make sure it is intact.
④ The workers should wear a helmet and life jackets. When the storm is
happened ,it should strengthen the machinery and equipment, and take personnel and
vessels to the safety area. In case of gale of more than Grade 6 (wind speed is 13.8
m/s) (including Grade6), working of driving steel casing is not allowed.
⑤ The safety engineer should be responsible for safety in the working areas.
26
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
7 SOP and Check Form
7.1 Sop of steel casing driving
Standard Operation Procedure (SOP)Steel Casing Driving
Checking the steel casing driving Page 1 of 1
No
.Check list
Contractor Consultant EmployerRemar
kYE
SNO
YE
S
YE
SNO
YE
S
1 Does the Vibration Pile Hammer meet the
requirement?
2 Does the steel casing meet the requirement?-length
-wall thickness
-diameter
3 Does the guiding frame meet the requirement?-deviation of central plan location
-whether fixed or not
4 Has the survey equipment been set?
-total station
5 Are traffic vessels available?
-crew boat
-transport barge
6 Is lifting machine available?
7 Is enough power-generating equipment
available?
8 Are supporting devices available?
-bore-recording pen, pencil
-paint / slate pencil
9 Does the quality of piling meet the
requirement?-top elevation of steel casing
-steel casing position
-buried depth of the steel casing
10 Does the bracing of steel casing meet the
requirement?-length
-location
-quantity
-quality of welding
11 Are survey instrument available?
-total station
27
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)
-steel tape
Checked by:Contractor: Consultant: Employer:
28
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
7.2 Quality checking form
Tayan Bridge Construction Project
Quality Checking Report of Fabrication of Steel CasingThe Contractor: No. The Engineer: B-1-2A
Construction Part Number of steel casing Checking time
No. Checking itemDesign value
(mm)allowable deviation
Checking resultChecking method and frequency
1 Length (mm) ±25.4mm(±1 in) Steel ruler: every piece of steel pile casing
2Outside
diameter(mm)±1% Steel ruler: every piece of steel pile casing
3 Wall Thickness(mm) 12.5% ~﹣ + ∞ Vernier caliper: every piece of steel pile casing
4 Appearance Visible inspection
5 Welded joint Visible inspection
29
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
Site representative: ____________________
date:__________________
Contractor’s quality control engineer : Date:
the Engineer/the Employer: Date :
Tayan Bridge Construction Project
Quality Checking Report of Installation of Steel CasingThe Contractor: No. The Engineer: B-1-2B
Construction Part Number of steel casing Checking time
No. Checking itemSpecified value or
allowable deviation
Checking result Checking method and frequency
1 Gradient ≤2%Measure suspension wire by steel ruler: every piece of steel pile casing
2 Pile location ≤75mmTotal station: every piece of steel pile casing
3 Elevation of top of steel pile casing(m) Comply with designTotal station: every piece of steel pile casing
30
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
4Elevation of Bottom of steel pile
casing(m)Comply with design
Counter-calculate according to the elevation of top of steel pile casing
Site representative: ________________date: ________________
Contractor’s quality control engineer : Date:
the Engineer/the Employer: Date :
31
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
8. Attachment
8.1 Coordinate of steel casing
Pier NO. Steel casing NO. X Y
3
1
4982.92
4 4960.808
2
4983.06
9 4957.812
3
4983.21
4 4954.815
4
4986.17
1 4960.965
5
4986.31
5 4957.968
6
4986.46
0 4954.972
7
4989.41
7 4961.122
8
4989.56
2 4958.125
9
4989.70
6 4955.129
Pier
NO.
Steel
casing
NO.
X Y
4
1 4984.858 4920.780
2 4985.003 4917.783
3 4985.147 4914.787
4 4988.104 4920.937
5 4988.249 4917.940
6 4988.394 4914.944
7 4991.350 4921.093
8 4991.495 4918.097
9 4991.640 4915.100
Pier NO. Steel casing NO. X Y
5 1 4986.79 4880.753
1
2
4986.93
6 4877.757
3
4987.08
1 4874.760
4
4990.03
8 4880.910
5
4990.18
2 4877.914
6
4990.32
7 4874.917
7
4993.28
4 4881.067
8
4993.42
9 4878.071
9
4993.57
3 4875.074
Pier NO. Steel casing NO. X Y
7
1
5015.65
4 4443.857
2
5015.79
9 4440.861
3
5015.94
3 4437.864
4
5011.15
9 4443.640
5
5011.30
5 4440.644
6
5011.44
9 4437.647
7
5006.66
5 4443.423
8 5006.80
9
4440.427
32
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
9
5006.95
4 4437.430
Pier NO. Steel casing NO. X Y
8
1
5017.82
6 4398.888
2
5017.97
2 4395.891
3
5018.11
6 4392.895
4
5013.33
1 4398.671
5
5013.47
7 4395.674
6
5013.62
2 4392.678
7
5008.83
6 4398.454
8
5008.98
2 4395.457
9
5009.12
7 4392.461
Pier NO. Steel casing NO. X Y
9
1
5020.72
1 4338.958
2
5020.86
6 4335.961
3
5021.01
1 4332.965
4
5016.22
6 4338.741
5
5016.37
1 4335.744
6
5016.51
6 4332.748
7
5011.73
2 4338.524
8
5011.87
6 4335.527
9 5012.02 4332.530
1
Pier NO. Steel casing NO. X Y
10
1
5022.89
3 4293.987
2
5023.03
8 4290.991
3
5023.18
4 4287.994
4
5018.39
8 4293.770
5
5018.54
3 4290.773
6
5018.68
9 4287.777
7
5013.90
4 4293.553
8
5014.04
8 4290.556
9
5014.19
4 4287.560
Pier NO. Steel casing NO. X Y
11
1
5025.06
6 4249.017
2
5025.21
1 4246.021
3
5025.35
5 4243.024
4
5020.57
1 4248.800
5
5020.71
6 4245.804
6
5020.86
1 4242.807
7
5016.07
6 4248.583
8
5016.22
1 4245.587
9 5016.36 4242.590
33
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
6
Pier NO. Steel casing NO. X Y
12
1
5027.96
0 4189.087
2
5028.10
5 4186.091
3
5028.25
0 4183.094
4
5023.46
6 4188.870
5
5023.61
0 4185.874
6
5023.75
5 4182.877
7
5018.97
1 4188.653
8
5019.11
6 4185.657
9
5019.26
0 4182.660
Pier NO. Steel casing NO. X Y
13
1
5030.13
2 4144.117
2
5030.27
8 4141.120
3
5030.42
3 4138.124
4
5025.63
8 4143.900
5
5025.78
3 4140.903
6 5025.92 4137.907
8
7
5021.14
4 4143.683
8
5021.28
8 4140.686
9
5021.43
3 4137.690
Pier NO. Steel casing NO. X Y
14
1
5032.30
5 4099.147
2
5032.45
0 4096.151
3
5032.59
4 4093.154
4
5027.81
0 4098.930
5
5027.95
5 4095.934
6
5028.10
0 4092.937
7
5023.31
6 4098.713
8
5023.46
0 4095.717
9
5023.60
5 4092.720
Pier NO. Steel casing NO. X Y
15
1
5035.19
9 4039.217
2
5035.34
4 4036.221
3
5035.48
9 4033.224
4
5030.70
5 4039.000
5 5030.84
9
4036.003
34
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
6
5030.99
4 4033.007
7
5026.21
0 4038.783
8
5026.35
5 4035.786
9
5026.49
9 4032.790
Pier NO. Steel casing NO. X Y
16
1
5039.59
3 3994.916
2
5039.81
0 3990.422
3
5040.02
7 3985.927
4
5035.09
8 3994.699
5
5035.31
5 3990.204
6
5035.53
2 3985.710
7
5030.60
3 3994.482
8
5030.82
0 3989.987
9
5031.03
7 3985.493
10
5026.10
8 3994.265
11
5026.32
5 3989.770
12
5026.54
2 3985.276
Pier NO. Steel casing NO. X Y
17
1
5045.39
5 3921.436
2
5045.61
2 3916.941
3
5045.82
9 3912.446
4
5046.04
6 3907.951
5
5040.90
0 3921.219
6
5041.11
7 3916.724
7
5041.33
4 3912.229
8
5041.55
1 3907.734
9
5036.40
5 3921.001
10
5036.62
3 3916.507
11
5036.83
9 3912.012
12
5037.05
7 3907.517
13
5031.91
1 3920.784
14
5032.12
8 3916.290
15
5032.34
5 3911.795
16
5032.56
2 3907.300
17
5027.41
6 3920.567
18
5027.63
3 3916.073
19
5027.85
0 3911.578
20
5028.06
7 3907.083
35
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
Pier NO. Steel casing NO. X Y
18
1
5055.04
4 3721.668
2
5055.26
1 3717.174
3
5055.47
8 3712.679
4
5055.69
5 3708.184
5
5050.54
9 3721.451
6
5050.76
6 3716.957
7
5050.98
3 3712.462
8
5051.20
0 3707.967
9
5046.05
4 3721.234
10
5046.27
1 3716.740
11
5046.48
9 3712.245
12
5046.70
6 3707.750
13
5041.56
0 3721.017
14
5041.77
6 3716.522
15
5041.99
4 3712.028
16
5042.21
1 3707.533
17
5037.06
5 3720.800
18 5037.28
2
3716.305
19
5037.49
9 3711.811
20
5037.71
6 3707.316
Pier NO. Steel casing NO. X Y
19
1
5056.56
9 3643.476
2
5056.78
6 3638.981
3
5057.00
3 3634.486
4
5052.07
4 3643.259
5
5052.29
1 3638.764
6
5052.50
8 3634.269
7
5047.57
9 3643.042
8
5047.79
6 3638.547
9
5048.01
3 3634.052
10
5043.08
4 3642.825
11
5043.30
1 3638.330
12
5043.51
9 3633.835
8.2 Guiding frame
36
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)
8.3 Shop drawing of steel casing
37