56
Tayan Bridge Construction Project Technique Proposal for Steel Casing (1 st Edi, 1 Rev) TAYAN BRIDGE CONSTRUCTION PROJECT Technical Proposal for Steel Casing CRBC – WIKA JO. 1

Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Embed Size (px)

Citation preview

Page 1: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

TAYAN BRIDGE CONSTRUCTION PROJECT

Technical Proposal for Steel Casing

CRBC – WIKA JO.

1

Page 2: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Teble of Content

1 General...........................................................................................................................................12 Construction Introduction..............................................................................................................2

2.1 The main method for construction......................................................................................22.2 Flow chat for construction..................................................................................................3

3 Construction Method of Steel Casing............................................................................................43.1 The reinforcement design of steel casing............................................................................43.2 Steel Casing Fabrication and Delivery................................................................................43.3 Pilling sequence and coordinate of pile layout....................................................................53.4 Piling...................................................................................................................................6

4 Equipment, Manpower and Schedule of Driving Steel Casing....................................................204.1 Equipment.........................................................................................................................204.2 Manpower.........................................................................................................................204.3 Construction schedule.......................................................................................................21

5 Quality Assurance........................................................................................................................226 Safety Assurance..........................................................................................................................227 SOP and Check Form...................................................................................................................23

7.1 Sop of steel casing driving................................................................................................237.2 Quality checking form......................................................................................................24

8. Attachment..................................................................................................................................278.1 Coordinate of steel casing.................................................................................................27

2

Page 3: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Construction Method of Driving Steel Casing

1 General

This document describes the construction procedure of driving steel casing in

the Tayan Bridge Construction project.The steel casing will be drived in two area.

The first location is bridge 1 with total 27 pieces of steel casings.And the second

location is bridge 2 with total 163 pieces of steel casings, which include36 pieces of

steel casings for fender. The diameter of 64 pieces of steel casing in main bridge is

170cm. Diameter of others are 120 cm. The thickness of all steel casings is 10mm.

40,075m40,075m40,075m40,067m 40,075m 40,075m 40,067m

STA: 0+164.486ELEV: 35.179

STA: 0+204.553ELEV: 36.382

STA: 0+244.628ELEV: 37.184

STA: 0+284.703ELEV: 37.585

STA: 0+324.778ELEV: 37.585

STA: 0+364.851ELEV: 37.184

STA: 0+404.928ELEV: 36.382

STA: 0+444.995ELEV: 35.180

OVERALL LENGTH OF BRIDGE = 280,509m

ABT.1 P.1 P.2 P.3 P.4 P.5 P.6 ABT.2

Fig. 1-1 Long Section of Bridge 1

Fig. 1-2. Long Section of Bridge 2—North Approach Bridge

Fig. 1-3.Long Section of Bridge 2—Main Bridge and South Approach Bridge

1

Page 4: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

In the specification, the material of steel casing isspecified as ASTM A252

Grade 2 with Yield Stress (f y ) 246MPa and ultimate Stress 422MPa. The structural

detailed data for steel casing are shown in following Table 1-1:

Table 1-1. Steel Casing Data

Pier NO.

Diamete

r

(mm)

Wall Thickness

(mm)

Length

(m)Quantity

Total Length

(m)

Bottom

Elevation(m)

P3 1200 10 17.5 9 157.5 +13.25

P4 1200 10 23.5 9 211.5 +7.25

P5 1200 10 20.5 9 184.5 +10.25

P7 1200 10 9.5 9 85.5 +21.25

P8 1200 10 15.5 9 139.5 +15.25

P9 1200 10 15.5 9 139.5 +15.25

P10 1200 10 15.5 9 139.5 +15.25

P11 1200 10 15.5 9 139.5 +15.25

P12 1200 10 16.5 9 148.5 +14.25

P13 1200 10 16.5 9 148.5 +14.25

P14 1200 10 16.5 9 148.5 +14.25

P15 1200 10 16.5 9 148.5 +14.25

P16 1700 10 15.5 12 186 +15.25

P17 1700 10 20.5 20 410 +10.25

P18 1700 10 18.5 20 370 +12.25

P19 1200 10 18.5 12 222 +12.25

2 Construction Introduction

2.1 The main method for construction

Every piece of steel casing will be fabricated in the factory as a whole part Spiral

Pipe. So there is no welding connection in the job site. After checked in the factory,

all the steel casings are delivered to the Tayan storage yard by barge.

In the job site, the steel casing will be drived down to designed position and

elevation by using a 80t barge crane with vibrating hammer. The crane is used to erect

the steel casing and lift the vibrating hammer. Vibrating hammer is used to drive the

steel casing. One guide frame will be used to ensure the verticality comply with

2

Page 5: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

specified allowable tolerance that is not more than 2%.

2.2 Flow chat for construction

3

Page 6: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

4

Page 7: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

3 Construction Method of Steel Casing

3.1 The reinforcement design of steel casing

In order to avoid deformation, stiffening rings were welded around the steel

casing. On the top and bottom ends, a 0.5m long stiffening ring is added for dia.

1200mm steel casing, and 0.8m long stiffening ring is added for dia. 1700mm steel

casing. Some 100mm long stiffening rings are added in middle of steel casing, the

detailed design drawing is shown as the attachment document: Shop Drawing of

Steel Casing.

3.2 Steel Casing Fabrication and Delivery

Steel casing will be fabricated in the factory in Jakarta. All steel casing is rolled

and welded by automatic steel pipe rolling machine. A very good guarantee can be

obtained for the quality of steel casing. Every piece of steel casing is processed as a

whole part spiral pipe. It means there will be no welding connection job in the

construction site.

Fig. 3.2-1 Steel Casing Fabrication

After the quality and the quantity of steel casing is checked to complying with

the specification request, the product can be delivered. The steel casing is transport to

port by long truck firstly, and then delivered form Jakarta Port to Tayan inland

5

Page 8: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

temporary jetty by barge. In steel casing stack progress, the focus is to prevent

deformation. For diameter 1200mm steel casing, the maximum stack layer is 3 layer;

for diameter 1700mm steel casing, it is only allowed in 2 layer. Measures to prevent

rolling during sea shipping, should be adopted. The demand for stack in the Tayan

storage yard is accordance to the standart handling steel casing material.

Fig. 3.2-2 Lay Out Stock Yard OfSteel Casing

3.3 Pilling sequence and coordinate of pile layout

The steel casing installation procedure for every kinds of pier in bridge 1 and 2 is

shown as following:

Fig. 3.3-1Steel Casing Pilling Sequence of Bridge 1

6

Page 9: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig. 3.3-2 Steel Casing Pilling Sequence of Bridge 2

The coordinate of steel casing will be submited to the Engineer to check as

another special document. Any steel casing is not allowed to drived before the

coordinate data is approved by Engineer.

3.4 Piling

3.4.1 Construction Method Of Driving Steel Casing In Bridge1

1 Driving Steel Casing of Bridge 1

The detail of driving steel casing procedure in bridge 1 is explained as follow :

a. Carry the steel casing to the middle of the river by barge

Fig. 3.4.1-1 Driving Steel Casing

b. Inserting steel casing to the guide frame using crane, check the verticality and

ensure the steel casing already in fixed position.

7

Page 10: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig. 3.4.1-2 Lifting Steel Casing

c. Put down slowly steel casing until river bed level, check steel casing position

and verticality, make sure the steel casing position not change or displace

extremely because of water stream.

Fig. 3.4.1-3 Placing Steel Casing

d. Drive the steel casing using vibrating hammer. Monitor the driving steel

casing during work to ensure steel casing condition is fullfill the

specification requirement. During the driving execution, the surveyor must

check/survey the position and verticality of steel casing. Then check the top

elevation of steel casing (+30,5 m)

8

Page 11: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig. 3.4.1-4 Driving Steel Casing

e. After the steel casing driven properly, then install bracing (steel profile) to

make steel casing work together and stable.

Installing bracing (using steel trust) to strengthening the steel casing each other

into 1 group. The bracing also can be use as base of drilling and formwork platform.

The bracing elevation location must accomply the design drawing.

Fig. 3.4.1-5 Temporary bracing between steel casing pile

2 Survey and Coordinate Control of Bridge 1

Two total stations will be used to suvery the steel casing at the same time. Every

steel casing will be checked and seted out by two total stations. The location of total

station should be choosed in the river bank to survey different pier’s steel casing.

The two surveying sight should be an angle of less than 180 degrees.

Survey the guidence frame and the sign that have been painted in steel casing.

9

Page 12: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

check and control the position firstly, adjust the barge position in according with the

calculated deviation until complying with the allowable tolerance that is not more

than 7,5 cm. Fix the location by 4 anchors and keep the stability of the barge in the

help of tug boat.

SURVEYOR WITHTOTAL STATION

SURVEYOR WITHTOTAL STATION

0250

0300

0350

0400

P.6P.5P.4P.3P.2

1200

1200351 497 351

497

1500

6500

1500

351 497 351

497

1200

900

5300

900

1200

1200351 497 351

497

1500

6500

1500

351 497 351

497

1200

900

5300

900

Fig.3.4.2-5 total station location for pilling

3.4.2 Construction Method of Driving Steel Casing in Bridge2

⑴Move and anchor the barge crane

For the barge crane, there are 4 pieces of anchor windlass installed in 4 corner

of barge. Every anchor windlass has 100m wire rope at least, and 1 heavy steel anchor

is fixed on the other end of wire rope. The anchor offer anchor force to the barge

crane, the windlass can adjust the position of barge crane without the tug boat, by

pulling and release the wire rope.

In the beginning of every pier, one tug boat move barge crane to the piling

location of first row of steel casing. The other tug boat takes the anchor to the anchor

position and drops it into the river. After 4 pieces of anchor are drop to the designed

point, the 4 windlass pull the wire rope to make all the wire rope is in force state. Now

the barge can be fixed in position by 4 anchors.

10

Page 13: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-1: Barge anchoring

⑵Install guide frame

In order to ensure the accuracy for coordinate and verticality of steel casing,

aguide frame will be adopted. The inner diameter of guide frame is 3 cm larger than

the outer diameter of steel casing, and the height of guide frame is 3.2 m. Guide frame

structure is designed as follow:

11

Page 14: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-2.Guiding Frame

Before vibrating the permanent steel casing, in order to offer a stable fixed

platform for installing the guiding frame, a small temporary platform will be

established firstly.This temporary guide frame platform is composed of 4 steel pipes

and 2 main beams as following drawing.

Fig. 3.4.2-3 The design of guiding frame platform

The guide frame will be installed on it. If the guiding frame is checked in correct

coordinate and vertical direction, the guide frame can limit the steel casing in fixed

12

Page 15: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

point and lead the steel casing to slide along vertical direction.

Fig. 3.4.2-4 Vibrate steel casing by guiding frame platform

After the first row of steel casings completed, demolish the temporary guide

frame platform and establish the corresponding drilling platform on the first row of

steel casing. Then the guide frame will be installed in cantilever method on the top of

drilling platform to vibrate steel casing. Furthermore all the other steel casings will be

vibrated in this method.

Fig.3.4.2-5 vibrate steel casing by cantilever method

⑶ Survey and Coordinate Control of Bridge 2

13

Page 16: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Two total stations will be used to suvery the steel casing at the same time. Every

steel casing will be setting out by two total stations.The total station lacation should

be choosed in the river bank to survey different pier’s steel casing. The two

surveying sight should be an angle of approximately 90 degrees.

Survey the guide frame control position firstly, adjust the barge position in

according with the calculated deviation until complying with the allowable tolerance

that is not more than 7,5 cm. Fix the location by 4 anchors and keep the stability of

the barge in the help of tug boat.

Fig.3.4.2-5 total station location for pilling

⑷ Erect steel casing

The lengthiest of steel casing is 21.5m, it will be erected by barge crane and put

into guiding frame.

The steel casing is slided in the guide frame slowly until the bottom begin to

insert the riverbed. Move the crane boom to adjusted the steel casing verticality until

the surveyor confirm the verticality is correct, and then continue to sink the steel

casing into the riverbed untill stop. Check the verticality again, if no problem, loose

the lifting wire rope and continre to next procedure, or lifte up the steel casing out of

the river bed again to adjust the viticalrity.

14

Page 17: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-6 place the steel casing into the guiding frame

⑸Vibrat steel casing

Keep the stability of barge, after the coordinate and verticality is checked. The

crane lifte the vibrating hammer moving to the top of steel casing slowly, which

stands in the riverbed. Insert hammer clamp into the steel casing and fix the

hydraulic clamp firmly. Any impact and force should be avoided applied to steel pipe

to influnce the viticality. Afterward the crane lower down the hammer slowly, to give

hammper’s death weigth to the top of steel casing, making the steel casing sinking

down slowing. During the procedure, the crane boom should adjust and keep the

viticality continously until the steel casing stoping sinking again. If the steel casing

become inclined out of allowable tolerance, the steel casing should be lifted up of

riverbed to sink again.

15

Page 18: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-7 vibrate the steel casing in guiding frame (1)

Turn on the generator to provide the power to the vibrating hammer. Switch on

the vibrating hammper only two second, check the verticality after every stop and

then continue to switch on in very short time again.

Fig.3.4.2-8 vibrate steel casing in guiding frame (2)

When it is obvious that the steel casing is vibrated into the riverbed deep enough

to keep the verticality without change, remove the guiding frame and then switch on

the hammper with full power continuously until the steel casing can not be vibrated

16

Page 19: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

down anymore or stop in the design elevation.

Fig.3.4.2-9 vibrate steel casing without guiding frame

After one steel casing was finished, the surveyor check the coordinate and

elevation, if it is low than the allowable tolerance, move the barge and continue to

vibrate the next steel casing.

Fig.3.4.2-10 The installed steel casing of one pier

17

Page 20: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

⑹ weld the bracing

After every steel casing is vibracted, weld the bracing immediately, in order to

form as a whole. The section steel or steel pipe will be used as the bracing. Any job

will not be allowed before bracing welded. The bracing should be weld as follow.

18

Page 21: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-11 Bracing of Pier 17and Pier 18 (the dimension is in cm)

19

Page 22: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

20

Page 23: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-12 Bracing of Pier 16and Pier 19 (the dimension is in cm

21

Page 24: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

22

Page 25: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

Fig.3.4.2-13 Bracing of Pier 7~Pier 15 (the dimension is in cm)

4 Equipment, Manpower and Schedule of Driving Steel Casing

4.1 Equipment

Table 4.1-1 The List of Driving Steel Equipment Casing Of Bridge 1

No.

Description Type Capacity QuantityUni

t1 Tug Boat 600 HP 1 set2 Piling Barge 180ft 1 set3 Crawler crane 80T 1 set

4Vibration pile

Hammer1 set

5 Welding set 2 set6 Generator set 1 set

7Survey

equipmentTopcon 2 set

8 Lifting wire Φ20mmas

requiredTable 4.1-2 The List of Equipment Of Driving Steel Casing Of Bridge 2

No.

Description Type Capacity QuantityUni

t

1 Tug BoatTB.TAMBORA

/Indonesia600HP

(14.88×5.05×1.94)1 set

2 Flat Top

BargeBG.BB-023/

Indonesia

1500T(43.91×15.22×3.0

2)1 set

3 Crawler crane QUY80A 80T/209kw 1 set

4Vibration pile

Hammer- 5.8T/90kw 1 set

5 Generator SWT SC330S 343kw 2 set6 Total Station - 2 set

7 Lifting wire Φ20mm -as

required

4.2 Manpower

Table 4.2-1 Manpower Schedule Of Driving Steel Casing Of Bridge 1

No. Type of work Quantity Remark1 Sailor 62 Piling team 10

23

Page 26: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

3 Driver of crawler crane 14 Electrician 15 Site engineer 16 Safety engineer 17 Survey engineer 2

Total 22

Table 4.2-2 Manpower Schedule Of Driving Steel Casing Of Bridge 2

No. Type of work Quantity Remark1 Sailor 62 Piling team 103 Driver of crawler crane 14 Electrician 15 Site engineer 16 Safety engineer 17 Survey engineer 2

Total 22

4.3 Construction schedule

Table 4.3-1 The construction schedule of driving steel casing of bridge 1

Table 4.3-2 The construction schedule of driving steel casing of bridge 2

24

1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 412345

Driving Steel Casing Pier 4Driving Steel Casing Pier 3

Fabrication

NO WORK December January

Driving Steel Casing Pier 5

February March AprilDURATION

Furnish and Shipping

Page 27: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

5 Quality Assurance

① It need check the guiding frame and equipment, make sure they are in good

condition.

② When steel casing was driving, the surveyer need check the position and

verticality as soon as possible.

③ When the position and vertical is adjust to the design value , the steel casing

will down slowly by crawler crane. When the bottom was on the river bed, the steel

casing is sinking by itself weight, and then the steel casing have enough

stability,move the guiding frame, and then continue to driving by hammer. When it

is driving, make sure the hammer and axis of steel casing on same vertical line.

6 Safety Assurance

① It need check the equipment before start to hoist, and make sure they are in

good condition.

25

Page 28: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

② The crawler crane need put down the boom onto the brackets when it is

moving; the driver need cooperate with the director, and the director should have

correct directing posture .

③ Before hoisting, the lifting eyes should be checked, make sure it is intact.

④ The workers should wear a helmet and life jackets. When the storm is

happened ,it should strengthen the machinery and equipment, and take personnel and

vessels to the safety area. In case of gale of more than Grade 6 (wind speed is 13.8

m/s) (including Grade6), working of driving steel casing is not allowed.

⑤ The safety engineer should be responsible for safety in the working areas.

26

Page 29: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

7 SOP and Check Form

7.1 Sop of steel casing driving

Standard Operation Procedure (SOP)Steel Casing Driving

Checking the steel casing driving Page 1 of 1

No

.Check list

Contractor Consultant EmployerRemar

kYE

SNO

YE

S

YE

SNO

YE

S

1 Does the Vibration Pile Hammer meet the

requirement?

2 Does the steel casing meet the requirement?-length

-wall thickness

-diameter

3 Does the guiding frame meet the requirement?-deviation of central plan location

-whether fixed or not

4 Has the survey equipment been set?

-total station

5 Are traffic vessels available?

-crew boat

-transport barge

6 Is lifting machine available?

7 Is enough power-generating equipment

available?

8 Are supporting devices available?

-bore-recording pen, pencil

-paint / slate pencil

9 Does the quality of piling meet the

requirement?-top elevation of steel casing

-steel casing position

-buried depth of the steel casing

10 Does the bracing of steel casing meet the

requirement?-length

-location

-quantity

-quality of welding

11 Are survey instrument available?

-total station

27

Page 30: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 1 Rev)

-steel tape

Checked by:Contractor: Consultant: Employer:

28

Page 31: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

7.2 Quality checking form

Tayan Bridge Construction Project

Quality Checking Report of Fabrication of Steel CasingThe Contractor: No. The Engineer: B-1-2A

Construction Part Number of steel casing Checking time

No. Checking itemDesign value

(mm)allowable deviation

Checking resultChecking method and frequency

1 Length (mm) ±25.4mm(±1 in) Steel ruler: every piece of steel pile casing

2Outside

diameter(mm)±1% Steel ruler: every piece of steel pile casing

3 Wall Thickness(mm) 12.5% ~﹣ + ∞ Vernier caliper: every piece of steel pile casing

4 Appearance Visible inspection

5 Welded joint Visible inspection

29

Page 32: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

Site representative: ____________________

date:__________________

Contractor’s quality control engineer : Date:

the Engineer/the Employer: Date :

Tayan Bridge Construction Project

Quality Checking Report of Installation of Steel CasingThe Contractor: No. The Engineer: B-1-2B

Construction Part Number of steel casing Checking time

No. Checking itemSpecified value or

allowable deviation

Checking result Checking method and frequency

1 Gradient ≤2%Measure suspension wire by steel ruler: every piece of steel pile casing

2 Pile location ≤75mmTotal station: every piece of steel pile casing

3 Elevation of top of steel pile casing(m) Comply with designTotal station: every piece of steel pile casing

30

Page 33: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

4Elevation of Bottom of steel pile

casing(m)Comply with design

Counter-calculate according to the elevation of top of steel pile casing

Site representative: ________________date: ________________

Contractor’s quality control engineer : Date:

the Engineer/the Employer: Date :

31

Page 34: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

8. Attachment

8.1 Coordinate of steel casing

Pier NO. Steel casing NO. X Y

3

1

4982.92

4 4960.808

2

4983.06

9 4957.812

3

4983.21

4 4954.815

4

4986.17

1 4960.965

5

4986.31

5 4957.968

6

4986.46

0 4954.972

7

4989.41

7 4961.122

8

4989.56

2 4958.125

9

4989.70

6 4955.129

Pier

NO.

Steel

casing

NO.

X Y

4

1 4984.858 4920.780

2 4985.003 4917.783

3 4985.147 4914.787

4 4988.104 4920.937

5 4988.249 4917.940

6 4988.394 4914.944

7 4991.350 4921.093

8 4991.495 4918.097

9 4991.640 4915.100

Pier NO. Steel casing NO. X Y

5 1 4986.79 4880.753

1

2

4986.93

6 4877.757

3

4987.08

1 4874.760

4

4990.03

8 4880.910

5

4990.18

2 4877.914

6

4990.32

7 4874.917

7

4993.28

4 4881.067

8

4993.42

9 4878.071

9

4993.57

3 4875.074

Pier NO. Steel casing NO. X Y

7

1

5015.65

4 4443.857

2

5015.79

9 4440.861

3

5015.94

3 4437.864

4

5011.15

9 4443.640

5

5011.30

5 4440.644

6

5011.44

9 4437.647

7

5006.66

5 4443.423

8 5006.80

9

4440.427

32

Page 35: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

9

5006.95

4 4437.430

Pier NO. Steel casing NO. X Y

8

1

5017.82

6 4398.888

2

5017.97

2 4395.891

3

5018.11

6 4392.895

4

5013.33

1 4398.671

5

5013.47

7 4395.674

6

5013.62

2 4392.678

7

5008.83

6 4398.454

8

5008.98

2 4395.457

9

5009.12

7 4392.461

Pier NO. Steel casing NO. X Y

9

1

5020.72

1 4338.958

2

5020.86

6 4335.961

3

5021.01

1 4332.965

4

5016.22

6 4338.741

5

5016.37

1 4335.744

6

5016.51

6 4332.748

7

5011.73

2 4338.524

8

5011.87

6 4335.527

9 5012.02 4332.530

1

Pier NO. Steel casing NO. X Y

10

1

5022.89

3 4293.987

2

5023.03

8 4290.991

3

5023.18

4 4287.994

4

5018.39

8 4293.770

5

5018.54

3 4290.773

6

5018.68

9 4287.777

7

5013.90

4 4293.553

8

5014.04

8 4290.556

9

5014.19

4 4287.560

Pier NO. Steel casing NO. X Y

11

1

5025.06

6 4249.017

2

5025.21

1 4246.021

3

5025.35

5 4243.024

4

5020.57

1 4248.800

5

5020.71

6 4245.804

6

5020.86

1 4242.807

7

5016.07

6 4248.583

8

5016.22

1 4245.587

9 5016.36 4242.590

33

Page 36: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

6

Pier NO. Steel casing NO. X Y

12

1

5027.96

0 4189.087

2

5028.10

5 4186.091

3

5028.25

0 4183.094

4

5023.46

6 4188.870

5

5023.61

0 4185.874

6

5023.75

5 4182.877

7

5018.97

1 4188.653

8

5019.11

6 4185.657

9

5019.26

0 4182.660

Pier NO. Steel casing NO. X Y

13

1

5030.13

2 4144.117

2

5030.27

8 4141.120

3

5030.42

3 4138.124

4

5025.63

8 4143.900

5

5025.78

3 4140.903

6 5025.92 4137.907

8

7

5021.14

4 4143.683

8

5021.28

8 4140.686

9

5021.43

3 4137.690

Pier NO. Steel casing NO. X Y

14

1

5032.30

5 4099.147

2

5032.45

0 4096.151

3

5032.59

4 4093.154

4

5027.81

0 4098.930

5

5027.95

5 4095.934

6

5028.10

0 4092.937

7

5023.31

6 4098.713

8

5023.46

0 4095.717

9

5023.60

5 4092.720

Pier NO. Steel casing NO. X Y

15

1

5035.19

9 4039.217

2

5035.34

4 4036.221

3

5035.48

9 4033.224

4

5030.70

5 4039.000

5 5030.84

9

4036.003

34

Page 37: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

6

5030.99

4 4033.007

7

5026.21

0 4038.783

8

5026.35

5 4035.786

9

5026.49

9 4032.790

Pier NO. Steel casing NO. X Y

16

1

5039.59

3 3994.916

2

5039.81

0 3990.422

3

5040.02

7 3985.927

4

5035.09

8 3994.699

5

5035.31

5 3990.204

6

5035.53

2 3985.710

7

5030.60

3 3994.482

8

5030.82

0 3989.987

9

5031.03

7 3985.493

10

5026.10

8 3994.265

11

5026.32

5 3989.770

12

5026.54

2 3985.276

Pier NO. Steel casing NO. X Y

17

1

5045.39

5 3921.436

2

5045.61

2 3916.941

3

5045.82

9 3912.446

4

5046.04

6 3907.951

5

5040.90

0 3921.219

6

5041.11

7 3916.724

7

5041.33

4 3912.229

8

5041.55

1 3907.734

9

5036.40

5 3921.001

10

5036.62

3 3916.507

11

5036.83

9 3912.012

12

5037.05

7 3907.517

13

5031.91

1 3920.784

14

5032.12

8 3916.290

15

5032.34

5 3911.795

16

5032.56

2 3907.300

17

5027.41

6 3920.567

18

5027.63

3 3916.073

19

5027.85

0 3911.578

20

5028.06

7 3907.083

35

Page 38: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

Pier NO. Steel casing NO. X Y

18

1

5055.04

4 3721.668

2

5055.26

1 3717.174

3

5055.47

8 3712.679

4

5055.69

5 3708.184

5

5050.54

9 3721.451

6

5050.76

6 3716.957

7

5050.98

3 3712.462

8

5051.20

0 3707.967

9

5046.05

4 3721.234

10

5046.27

1 3716.740

11

5046.48

9 3712.245

12

5046.70

6 3707.750

13

5041.56

0 3721.017

14

5041.77

6 3716.522

15

5041.99

4 3712.028

16

5042.21

1 3707.533

17

5037.06

5 3720.800

18 5037.28

2

3716.305

19

5037.49

9 3711.811

20

5037.71

6 3707.316

Pier NO. Steel casing NO. X Y

19

1

5056.56

9 3643.476

2

5056.78

6 3638.981

3

5057.00

3 3634.486

4

5052.07

4 3643.259

5

5052.29

1 3638.764

6

5052.50

8 3634.269

7

5047.57

9 3643.042

8

5047.79

6 3638.547

9

5048.01

3 3634.052

10

5043.08

4 3642.825

11

5043.30

1 3638.330

12

5043.51

9 3633.835

8.2 Guiding frame

36

Page 39: Technical Proposal Steel casing (2st Edi,1 Rev) .docx

Tayan Bridge Construction Project Technique Proposal for Steel Casing (1st Edi, 0 Rev)

8.3 Shop drawing of steel casing

37